79
NAVA BHARAT FERRO ALLOYS LTD POWER DIVISION DHARMAVARAM STANDARD OPERATING PROCEDURES FOR 20 MW STEAM TURBINE MODEL: C9-R16-ER PREPARED BY . 1

20mw Operation Manual

Embed Size (px)

Citation preview

Page 1: 20mw Operation Manual

NAVA BHARAT FERRO ALLOYS LTDPOWER DIVISIONDHARMAVARAM

STANDARD OPERATING PROCEDURES

FOR 20 MW STEAM TURBINE

MODEL: C9-R16-ER

PREPARED BY

.

1

Page 2: 20mw Operation Manual

Standard Operating Procedure

Steam turbine is a machine, which converts the heat energy available from Boiler

main steam into mechanical energy in an economical way. Turbine is associated with

Reduction gearbox and Generator, to convert this mechanical energy into electrical

energy.

One number 0f 32 MW, single cylinder, horizontal, impulse, multistage, multtivalve,

axial flow, condensing, one controlled and one uncontrolled extractions with

reduction gear and down exhaust type turbo generator supplied by SNM Co Ltd.,

Japan is installed in our plant.

The following are the salient features of Turbine:

Machine is having Electro hydraulic governing system assisted with WOOD WARD

– 505 governor control system, one Emergency stop valve and 4 nos of inbuilt control

valves with one mechanical over speed tripping mechanism. Turbine is having two

numbers of steam extractions, 1st steam uncontrolled extraction for HP heater for

feed water heating, 2nd steam controlled extraction for Deareator, for deareation and

heating purpose and for the sugar plant purpose.

Principle of Operation:

The steam with 86 Kg/Sq.cm pressure and 515 Deg.C temperatures will enter into

turbine through one ESV and 4 numbers Governing control valves. The steam entered

into the turbine expands over the moving and fixed blades of turbine releasing the

mechanical energy and rotates the turbine rotor at 6194 rpm. The turbine is coupled

with the generator rotor through reduction gearbox (6194/1500 rpm) and rotates the

generator rotor to convert mechanical energy into Electrical energy.

2

Page 3: 20mw Operation Manual

Steam after doing it’s work in turbine, gets collected into Condenser and forms as

condensate by giving it’s latent heat to CW water flowing in the tubes of condenser.

From condenser the condensate is pumped with Condensate Extraction Pumps (CEP)

through ejectors and gland steam cooler upto Deareator. From Deareator, feed water

is pumped to boiler Economizer using BFPs through HP heater. Deaerator & HP

heaters draw the steam from the turbine to heat the condensate flowing through them.

This is known as “Regenerative feed heating system.”

The TG set is provided with the following systems:

1. Turbine and reduction gear box assembly

2. Turbine lube oil and Governing system

3. Condenser and Air Evacuation system

4. Feed water heating system

5. Turbine gland steam system

OPERATION - PROCEDURES

1. Cold, warm and hot start up of TG

2. Loading of Turbine

3. Planned and Emergency shutdown.

4. Emergency conditions during Turbine Operation.

5. Important DOs and DONTs

6. Operating parameters and alarm trip values as Annexure – I.

7. Possible troubles, causes and remedies

I. Turbine and reduction Gearbox assembly:

3

Page 4: 20mw Operation Manual

The 20 MW steam turbine, type: C9-R16-ER supplied by Shin Nippon Machinery

Co. Ltd., Japan is installed in our plant. Steam turbine is horizontal, impulse,

multistage, multi valve, axial flow, condensing, nozzle governing, extraction and

geared type. The turbine is provided with 16 stages of blades.

Steam flow to the HP part is regulated by 4nos steam control valves constituted as a

single assembly as HP governor valve. Steam Turbine consists of Casing, fixed

blades, moving blades, rotor (on which moving blades are fixed) bearings (journal

and thrust), steam flow control valves.

The casing or cylinder of turbine is a pressure vessel, which is capable of with -

standing the working pressure and temperature. It provides support to the fixed blades

and rotor bearings. The turbine HP part is made up of Cast alloy and LP part is made

up of carbon steel and rotor is made up of Chromium, molybdenum, and vanadium

steels. The moving blades are fixed on rotor and rotate between the stationary (fixed)

blades. The rotor is mounted on two journal bearings. The front side of the rotor is

mounted with thrust bearing to take the axial thrust coming on rotor. Lube oil to the

bearings is provided from lubrication system.

To reduce the speed of the turbine rotor from 6194 to 1500 rpm, which is required for

generator, reduction gearbox was incorporated between turbine and generator rotors.

The turbine shaft is coupled with pinion shaft of gearbox and where as generator shaft

is coupled with wheel shaft of gearbox. Reduction gearbox assembly also consists of

Turning gear motor arrangement and “Main oil Pump” in it.

The full load parameters of turbine are “86 kg/Sq.cm g” main steam pressure, 515

Deg.C MS temperature, 6194 rpm, 0.1 Kg/Sq.cm (abs) exhaust steam pressure and

127.61 TPH steam flow through it. The two extraction steam quantities are 14.114

TPH for HP heater, 7.68 TPH for Deareator, and 12.05 TPH for LP heater. And

remaining 93.37 TPH gets collected in condenser where it is condensed by using

Circulating water. To supply the cooling water for the above condensation process,

TWO numbers of CW pumps each of 6900 Cu.M/Hr capacities are installed here.

4

Page 5: 20mw Operation Manual

The circulating water gets heated by approx 9 Deg.C in the condenser during

condensation process. In order to cool this water by 10 Deg.C, two nos of cooling

towers with induced draught fans are installed.

The following are the Protections (Trip values) of the Turbine:

1. Steam temperature at turbine inlet high high > 543 Deg.C

2. Steam temp. at turbine inlet low low < 460degC, this protection comes in to

service only when MS temperature reaches to 495 deg C and then falls to 460.

3. Steam pressure at turbine inlet low low < 60 kg/sq.cm (may be bypassed initially

for Cold and Warm start ups if required.)

4.Steam pressure at turbine inlet high high >103kg/sq.cm (not incorporated).

5. Control oil pressure low low 8.0+/-0.5 Kg/sq.cm

6. Lube oil pressure low low < 0.62 Kg/Sq.cm

7. Generator heavy fault (Generator trip).

8. Turbine mechanical over speed trip >/= 5632 rpm

9. Turbine electrical over speed trip >/= 5583 rpm

10. Governor heavy fault.

11. Remote trip from turbine governor panel.

12. Turbine trip from desk push button.

13. Exhaust steam pressure high high > 1.3 Kg/Sq.cm (abs)

14. Exhaust steam Temperature high high > 150 degC

15. Lube oil reservoir level (MOT) low low < 350 mm.

16. Hot well level low low < 300mm

17. Hot well high high 1400 mm

18. Turbine Rotor axial shift high high +0.65, -0.65 mm.

19. Turbine front shaft vibration high high 90 microns

20. Turbine rear shaft vibration high high 90 microns

21. Reduction gear pinion front shaft vibration high high 140 microns

5

Page 6: 20mw Operation Manual

22. Reduction gear pinion rear shaft vibration high high 140 microns

23. Reduction gear wheel front shaft vibration high high 180 microns

24. Reduction gear wheel rear shaft vibration high high 180 microns

25. Generator front shaft vibration high high 160 microns

26. Generator rear shaft vibration high high 160 microns

27. Turbine thrust bearing temperature high high (inactive) 120 Deg.C

28. Turbine thrust bearing temperature high high (active) 120 Deg.C

29. Turbine front shaft bearing temperature high high 120 degC

30. Turbine rear shaft bearing temperature high high 120 degC

31. Reduction Gear pinion front bearing temperature high high 120 degC

32. Reduction Gear pinion rear bearing temperature high high 120 degC

33. Reduction Gear wheel front bearing temperature high high 120 degC

34. Reduction Gear wheel rear bearing temperature high high 120 degC

35. Generator front bearing temperature high high 85 degC

36. Generator rear bearing temperature high high 85 degC

37. HP heater level high high 290mm. (Protection should be bypassed during

charging of HP heater.) not incorporated.

II. Turbine lube oil system:

Turbine lube oil system consists of Main oil tank (MOT), Over head emergency oil

tank (OHT), lube oil coolers (2), Main oil pump (MOP), Control oil pumps (2,COP),

AC driven Auxiliary oil pump (AOP), DCdriven Emergency oil pump (EOP), and oil

vapor extraction fans (2, OVEF) to supply the lube oil to the turbine, reduction gear

box and generator bearings during run up, coasting down and for subsequent turning

gear operations.

The MOP is mounted on reduction gearbox wheel assembly and rotated by turbine

rotor and supplies oil to the lubricating system and as well as trip oil to the governing

system. It takes over its duty from the AOP when turbine speed is above 4650 rpm.

6

Page 7: 20mw Operation Manual

To maintain lube oil temp at 45 degC, Lube oil coolers (2 nos) are provided in the

system. Two numbers of vapor fans (one working and one standby) are provided to

extract oil vapors from MOT and vent them out to atmosphere.

CONTROL OIL PUMP:

Control oil pump (COP) supplies oil to the governing system during initial start and

continuous operation of turbine. COP is rated to deliver 60 LPM at a head of 16.0

Kg/Sq.Cm (g) and is driven by 415V, 5.5KW, and 2880-rpm motor. Two numbers of

COPs are installed, out of two, one is working and another is standby. The auto-

change over is incorporated between COP-1 and COP-2.

Startup Sequence:

01. Ensure the following

COP1&2 are ready from Mechanical, Electrical and Instrumentation sides and NO

Line Clearance is pending on COP- 1&2, governing and lube oil systems.

Power supply and control supply are available.

Pressure switches and interlocks are properly checked and incorporated.

Discharge valves are opened.

Level of oil in MOT is normal (550mm).

Valves in oil system supply mains are properly lined up.

Ensure oil vapor fan is ready to start (at least one).

02. Start the pump by pressing the start button on DCS.

03. Check the discharge pressure of pump and motor current.

04. Keep the stand by pump in auto, in order to come in to service in auto as per

interlock.

05. Observe the control oil filter differential pressure (DP) (not more than 0.8) from

local gauge. If necessary, change the filter.

7

Page 8: 20mw Operation Manual

NOTE:

Before changing the filter, open air vent & Equalizing valve and ensure that both the

filters are equalized with oil. After change over, close the air vent.

Shutdown Sequence:

As these pumps are intended for continuous supply of governing oil to the turbine,

they are to be switched off only when the turbine is not in service. Before switching

off these pumps, ensure that the standby pump is in ‘MAN’ mode (if pump is in

“AUTO” mode, it will come in to service on interlock).

Important Note:

When one COP is in service with the turbine running, the standby COP should be in

AUTO selection. Otherwise, auto-change over will not take place when running COP

trips and this results n trip of Turbine.

Interlocks on COPs:

Auto Start: COP discharge pressure low (PSL 510) or running COP off, and pump

is selected in auto, the AUTO selected pump will come into service in AUTO.

Auto Stop: No Auto Stop incorporated.

Pump can be switched ON and OFF at any time if it is selected in MAN in DCS.

AUXILARY OIL PUMP:

AOP is an AC driven pump which supplies lube oil at 1.5 kg/Sq.cm to Turbine,

Reduction gear box and generator bearings and trip oil at 4.3 Kg/Sq.cm to the

governing system during turbine speed run up and turning gear operations. It has

rated capacity of 1019 LPM at 6.5 Kg/Sq.Cm and driven by 415V, 22 KW and 1475-

8

Page 9: 20mw Operation Manual

rpm motor. At 4650 rpm, MOP takes over the duty of AOP; AOP will be switched off

in auto. This pump comes into service in AUTO if lube oil header pressure is less

than 0.87+/-0.2 Kg/Sq.Cm and pump is selected in AUTO.

In the event of turbine trip due to any reason, AOP comes into service into operation

by interlock when oil header pressure drops to 0.87+/-0.2 Kg/Sq.Cm to supply lube

oil to all bearings for it’s safe coasting down and subsequent Turning gear operation.

This pump also supplies suction to the Jacking oil pumps. The discharge of AOP

passes through the Lube Oil Coolers.

Start up Sequence:

01.Ensure the following

AOP is ready from Mechanical, Electrical and Instrumentation sides and NO Line

Clearance is pending on AOP, governing and oil systems.

Power supply and control supply are available.

Pressure switches and interlocks are properly checked and incorporated.

Discharge valve is opened.

Level of oil in MOT is normal.

Valves in oil system supply mains are properly lined up.

Ensure oil vapor fan is in service (at least one).

02. Start the pump by pressing the start button on DCS.

03. Check the discharge pressure of pump and motor current.

04. Keep the pump in auto, in order to come in to service in auto as per the interlock.

9

Page 10: 20mw Operation Manual

05. Observe the lube oil filter DP (< than 0.8) from local gauge. If necessary change

the filter.

NOTE:

Before changing the filter, open air vent & Equalizing valve and ensure that both the

filters are equalized with oil. After change over, close the air vent.

Shutdown Sequence:

As this pump is intended for initial run up of Turbine, this will be switched off in auto

when turbine speed is above 4650 rpm (>95% of rated speed). Before switching off

AOP manually, keep the pump in MAN selection and ensure that Turbine speed is

>95%( MOP has taken over the job of AOP) and Turning gear motor is not in service.

Interlocks on AOP:

Auto Start: Lube oil header pressure low (PSL504 ) alarm and pump is selected in

AUTO, AOP comes in to service in AUTO.

Auto Stop: When Turbine speed is greater than 95% of rated speed, AOP will be

switched off in AUTO.

Pump can always be switched on and off manually at any time.

10

Page 11: 20mw Operation Manual

EMERGENCY OIL PUMP

The EOP comes into service in the event of an Emergency. A DC motor drives this. It

has rated capacity of 260LPM against a 1.5 Kg/Sq.cm head and is driven by 2.2 KW,

1500-rpm 110V DC motor. In the event of total power failure or if AOP fails to start

on it’s interlock due to any reason, EOP comes into operation when lube oil header

pressure drops to 0.62Kg/Sq.cm to supply the lube oil to the TG bearings for its safe

coasting down. EOP supplies oil only to the bearings. The discharge of this pump will

not go through oil coolers.

Startup sequence:

01.Ensure the following.

EOP is ready from Mechanical, Electrical and Instrumentation sides and NO Line

Clearance is pending on EOP, governing and oil systems.

DC Power supply and control supply are available.

Pressure switches and interlocks are properly checked and incorporated.

Discharge valve is opened.

Level of oil in MOT is normal

Valves in oil system supply mains are properly lined up.

02.When the above are satisfied, the DC EOP will start by inter lock, if lube oil

header pressure drops to 0.62 Kg/Sq.Cm

03. If the interlock does not work, the pump can be started by pressing the start push

button on Turbine governor panel (TGP).

04. After starting the pump check the discharge pressure, motor current.

Shutdown sequence:

The DC EOP can be stopped from TGP when it is no longer required to run, say,

when AC power is restored and AOP has taken into service. To stop the pump, press

11

Page 12: 20mw Operation Manual

stop button on TGP. The pump can only be stopped whenever lube oil header

pressure is > 0.62Kg/Sq.Cm, otherwise EOP will come into service in auto.

Important Note:

During normal running of turbine, EOP should be ready in all respects to come into

service with out fail. Trail run may be taken in every shift to check the availability

of EOP. While TG is in service or in TGM operation, EOP should be in ‘Auto

Standby’ mode on TGP.

Procedure to take trail run on EOP

Check the Healthiness of DC supply.

Change the selector switch from USUAL to TEST mode in Governor Control Panel.

EOP will start automatically.

Observe the lube oil pressure.

Check the current.

Ensure AOP is in auto.

Change the Selector switch from TEST to USUAL mode.

Stop the EOP. If lube oil pressure drops to 0.87+/-0.2 kg/sq.cm, AOP will start in

auto.

EOP should be kept in Standby mode.

Observe the lube oil pressure to bearing.

After ensuring the lube oil pressure to bearings, Stop AOP.

Observe the lube oil pressure.

Inter locks on EOP:

12

Page 13: 20mw Operation Manual

Auto Start: Lube oil header pressure low low (PSLL 504-1) and EOP auto selected

on TGP then EOP come into service in AUTO.

Auto Stop: Auto stop isn’t incorporated.

Manual start and manual stop can be done at any time from TGP.

13

Page 14: 20mw Operation Manual

TURNING GEAR

Before starting of the turbine and as well as after trip, turbine and generator shafts

are to be rotated at certain speed to avoid deflection of rotor due to self weight in high

temperature atmosphere. Turning Gear is incorporated in the system to facilitate this

operation. In our case, turbine rotates at 40 rpm in turning gear operation. 11 kW,

415V, 1450-rpm motor, drives the turning Gear.

Interlocks on TGM:

Auto Start: TGM comes in to service in AUTO 200 seconds, after the start

permissives were satisfied and if it is selected in AUTO. The start permissives for

TGM are

Turbine speed <10%(490 rpm)

Lube oil header pressure is not low (PSL 504).

Auto Stop: If any one of the above conditions is not present the TGM will trip and

turns to MAN selection. Manual start can be possible if all the start permissives are

satisfied. Manual stop can be done at any time.

During turbine rolling, TGM automatically disengages at 100 rpm (approx) of turbine

rotor, and TGM trip at 490rpm of Turbine.

Whenever the unit trips barring gear will engage automatically, during the barring

gear operation if power fails after restoration power barring gear should be

manually engaged before starting. If it is not so which will lead ton damage the

gears of barring gear.

Putting Turbine on Turning gear Operation:

Ensure the following:

MOT oil level is normal.

NO line clearance is pending on Turbo Generator, Lube oil and Jacking oil systems

and Turning gear motor.

Proper functioning of instruments indicating:

14

Page 15: 20mw Operation Manual

Axial displacement

All turbine, reduction gear box, generator bearing vibrations

All bearing metal temperatures

Lube oil temperature and pressure

Jacking oil pressure

Turbine speed

Ensure DC EOP is healthy and in standby mode on the Governor panel.

Start AOP as per the procedure and check the Lube oil pressure and parameters

mentioned in point 1.c.

Throttle the cooling water outlet from oil coolers and maintain oil temperature around

45 Deg.C +/- 5 Deg.C

Engage turning gear pinion by rotating the motor shaft with the lever from local.

Start the turning gear motor (TPBSSBGMT) and check the following:

TGM current

Axial displacement

All bearing vibrations

Turbine speed

Lube oil pressure

It needs approx. 10 hours to cool down the turbine casing and bearings. After turbine

cooling period, the TGM may be stopped. AOP & JOP should be continued in service

for another 2 hours.

15

Page 16: 20mw Operation Manual

III.CONDENSER and AIR EVACUATION SYSTEM:

CONDENSER:

Condenser is a tubular, non-contact type heat exchanger, which receives the

steam from turbine after doing work, and condenses it to form condensate using CW

system. Condensate Extraction pumps are connected to condenser, and they will

pump the main condensate to Deareator through Ejector and Gland Steam Cooler. To

increase the work done by the turbine and to avoid backpressure on Turbine rotor,

pressure inside the condenser is maintained below atmosphere pressure (vacuum). To

obtain vacuum in condenser, air and non-condensable gases are to be removed. For

this purpose, air evacuation system with Main ejector has been provided. The makeup

DM water needed for the system is added in the condenser from UCFT through

Normal and Emergency makeup control valve lines.

Heat transfer area in condenser : 2435 Sq.M

Number of Tubes : 5016

Dia/Thickness of tubes : 22.225/0.71mm

Rated CW flow : 5800 Cu.m/hr

DP across condenser at rated flow: <5300 mmwc

AIR EVACUATION SYSTEM (Ejector system):

One starting Ejector (Hogging ejector), two numbers of “two stage steam jet air

ejectors (as a single unit)” are installed to create and maintain vacuum in the

condenser.

1. Ensure the following:

TG set is on turning gear operation as per the procedure.

At least one CW pump is in service and two CT fans are ready to start.

Condenser is charged from CW side.

Hot well level is normal.

16

Page 17: 20mw Operation Manual

CEP is running on re-circulation through Main Ejector, Gland steam cooler.

PRDS steam is available at rated pressure and temperature.

Ensure water sealing is provided for all valves connected to condenser and vacuum

break valve.

2. Close the following valves:

Hand operated valve in airline connected to hogging ejector and main ejectors.

All drain valves and control valves connected to condenser.

Close the vacuum break valve.

3. Warm up the PRDS header by opening the drain valves.

4. By operating the PRDS pressure control valve and Temperature control Valves

attain the required 5. PRDS pressure and Temperatures.

6. Ensure PRDS steam is available with 8Kg/Sq.cm and 210 Deg.C

7. Start the GSC exhaust fan.

8. Charge the Gland steam cooler.

9. Open the steam valve to the starting ejector gradually.

10. Slowly open the air valve and watch for vacuum. After attaining required Value, -

0.6 Kg/Sq.Cm make ready the main ejector for Keeping in service.

11. Open the steam valves of main ejector slowly and then open-air valve and

discharge valve.

Charge the glands by opening the HOV in gland sealing line. Ensure Turbine gland

sealing steam pneumatic control valve is operating and Gland steam pressure is

normal (0.1 to 0.2Kg/Sq.Cm (g)).

After attaining –0.70Kg/Sq.Cm (g) of vacuum, isolate the startup ejector by Closing

air valve first and steam valve next. With the main ejector in service we can attain –

0.9 to –0.95 Kg/ Sq.Cm (g).

17

Page 18: 20mw Operation Manual

Important Note:

a. Before charging the main ejector, ensure flow of main condensate (CEP

discharge) through ejector.

b. While charging the ejector, open steam valve and air valve next gradually.

c. During cut off of the ejector, close air valve first and steam valve next and

discharge valve next.

d. Ensure tightness of vacuum break valve manually. Provide water sealing.

e. Do not open any drain valve connected to condenser when there is no sufficient

vacuum (>0.5Kg/Sq.Cm (abs)).

f. Ensure that the drain line isolation valves of condensate trap & casing drain of

the running exhaust fan are in open position.

g. While charging the main ejectors, ensure that Rotameter isolation valves drain

line isolation valves of Condensate Trap are in open position.

h. Ensure that the suction valve& casing drain valves of the standby exhaust fan

on Gland steam condenser are in closed position.

IV. Main condensate and Feed water system:

Main condensate system:

After condensing of Exhaust steam in condenser, condensate forms. This condensate

is pumped to Deareator using Condensate Extraction pumps through Main ejectors,

GSC. The discharge of CEP is also used for 1. Flash box attemperation,2. Valve

sealing. From CEP discharge header one line is connected to UCFT with Motor

Operated Valve, to drain the excess condensate from the hot well.

18

Page 19: 20mw Operation Manual

CONSENSATE EXTRACTION PUMPS:

Two numbers of CEPs (one working and one standby) are installed to pump the main

condensate from condenser to Deareator through main Ejectors and gland steam

cooler. It has rated capacity to deliver 125 METER CUBE/HOUR at 111.6 Kg/Sq.cm

and is driven by 415V, 1475 rpm, 75 KW motor. As this pump supplies cooling

medium to Main Ejector and GSC, 100% availability of this pump is essential to run

the plant.

STARTING OF CEP:

1. Check no line clearance is pending on CEP and Condensate system2. Ensure that hot well level is normal >700mm & UCFT level is > 1500mm.3. Ensure that suction valve is opened and DP across suction strainer is <0.3

Kg/Sq.cm4. Ensure that the Pump is primed with condensate by opening air vent. (When there

is no vacuum.)5. Open HOV in line from CEP discharge to mechanical seal.6. Ensure that MC PCV “TLIC430AM“ in MC line to Deaerator is closed and PCV

in re-circulation line is full opened.7. Ensure that the discharge valve (HOV) is closed.8. Ensure MOV “ TPBOCMV350“ in CEP shell UCFT line is in closed condition.9. Ensure that Electrical supply is available.10.Ensure that valve sealing line is through to suction valves.11.Open CEP air removal line valve to condenser.12.Check the lube oil level in the bearing oil cup.13.Start the Pump from DCS.14.Check disch. Pressure, Motor current, Brg. temp and hot well level.15.Open MC PCV gradually and maintain the discharge pressure above 8.0

Kg/Sq.cm.

SHUT DOWN SEQUENCE:When there is no vacuum in Condenser, the pump can be stopped by keeping the Pump in re-circulation.

WHAT NOT TO DO:1. Don’t allow any leakage in suction side.

19

Page 20: 20mw Operation Manual

2. Don’t open any valve, fitting, flange in the suction side.In normal working condition (Condenser is in vacuum), this will cause vacuum to drop the Pump to loose it’s suction.

3. Don’t allow the Pump to start or run with the protection/interlock by pass.4. While cleaning suction strainer of stand by CEP, ensure the closed position of

the respective suction, discharge valves, air removal valve to condenser, all drain valves between pump suction, discharge valves and open position of suction valve sealing line valve.

AUTO CHANGE OVER OF CEP:1. Check no line clearance is pending on standby CEP.1. Standby pump should be selected in “AUTO” mode in DCS.2. Suction and discharge valves should be in open position.3. HOV in line from CEP discharge to mechanical seal is in open

position.

Interlocks on CEP:1. When hot well level Hi switch (TLT300A1) is acted (cond. Level >1000 mm)

auto stand by pump comes into service in Auto. 2. When hot well level Low switch (TLT302A) is acted (cond. Level < 550 mm)

auto stand by pump trips in Auto.3. When hot well level Low Low switch (TLT303A) is acted (cond. Level < 300

mm) both pumps will trip. (Turbine trip)

Feed water Heating System (Regenerative system):

The thermal gain and economics of feed water heating given rise to regenerative feed

heating system. It consists of HP heater and Deareator. Feed water heater is a simple

heat exchanger, which is arranged so that water leaving the condenser is preheated

before it is fed to the Boiler. HP heater is of surface type heat exchangers, where as

deareator is direct type heat exchanger. These feed water heaters extracts the steam

from the turbine at high pressure and temperature and heats the feed water flows

through them. The condensed steam from HP heater are connected to condenser and

deareator respectively.

The presence of certain gases like oxygen, carbon monoxide and ammonia, dissolved

in water is harmful because of their corrosive attack on metals. Hence these gases are

20

Page 21: 20mw Operation Manual

removed in deareator unit. Spraying the water and heating the same by steam achieve

the same. The Deaerator consists of two chambers, the deareating column and feed

storage tank.

HP heater charging procedure:

1. Ensure open position of air removal line to condenser

2. Ensure Feed water is charged through HP heater

3. Ensure extraction line drain valves before and after Check valve are in open

position.

4. Open the extraction check valve of HP Heater

5. Open the HPH extraction motor operated valve

6. Maintain the heater level by operating HPH level control valve to Condenser up

to 5Kg/sq.cm extraction steam pressure, and at above 5 Kg/sq.cm pressure

maintain the HPH level by operating the level control valve to Deareator..

7. After charging of heater close the drains before and after check valve.

Note: 1. Do not charge the heater with out water flowing through them

1. During cut out of heater, close steam valve first.

Charging procedure for Deaerator:

Charge the De aerator. after 10 MW load it can be charged from its extraction line.

Open drains before and after HPH extraction check valve

Open HPH extraction check valve

Open HPH extraction bypass to Deareator MOV

Maintain the Deaerator pressure at 4.9 to 5.0 kg/sq.cm by operating the Deareator

pressure control valve.

After charging of Deaerator close the drains before and after check valve.

21

Page 22: 20mw Operation Manual

Charging of Deaerator from its extraction line

Open drains before and after Deareator extraction check valve

Open Deaerator extraction check valve

Open Deaerator extraction MOV and close the HPH extraction bypass to Deaerator

MOV

Maintain the Deaerator pressure by operating the Deareator pressure control valve.

After charging of Deaerator close the drains before and after check valve.

Check the following during increase of pressure in Deareator:

1. Deareator expands freely.

2. No abnormal hammering is there in the pipe line.

3. Steam and air mixture is being vented through the vent line.

4. No major steam/water leakages are there.

Note: Do Not Delay In Charging Deaerator After Charging Of LP Heater.

V. Turbine Gland Sealing System:

If the pressure at the turbine cylinder (Casing) is higher than the atmosphere

pressure, there will be a leakage of steam (from clearance between rotor and stator of

turbine) into atmosphere causes wastage of steam. The pressure is less than the

atmospheric pressure there will be ingression of air into condenser causing falling of

vacuum. To avoid this problem gland sealing is provided with 2000C temperature and

0.1-to 0.2-kg/sq.cm steam. One 3-way pneumatic control valve is provided for this

purpose.

During turbine rolling and up to 10MW load the aux. Steam with 8Kg/sq.cm; 1800C

is being used for sealing. After 10MW load, the turbine HP gland leak off steam is

being used for turbine LP gland sealing. To collect and condense the gland leak off

steam from turbine front and rear glands, gland steam piping and gland steam cooler

22

Page 23: 20mw Operation Manual

are provided. Turbine glands are to be sealed with gland steam during vacuum pulling

after attaining (–) 0.70Kg/sq.cm (g) vacuum in condenser.

After trip of turbine, to kill the vacuum stop the glands sealing by closing the hand

operated valve before 3 – way pneumatic control valve.

VI. Cold, Warm and Hot start of Turbine :

Cold Start Of Turbine

Turbine start up is termed as cold start up, if it is being started 10 to 12 hours after

shutdown or the metal temperature is < 1700C. The main steam parameters should be

maintained 30 kg/sq.cm and 350 deg C. However, according to the site conditions,

we are able to achieve 40 Kg & 400 deg C.

An average increase rate of metal temperature of MS line, ESV, Turbine chest and

Turbine casing, should not to exceed given values as below.

Metal temperature increase rate of metal temp. Deg.c/min.

100 deg C to 200 deg C 4.0

200 deg C to 300 deg C 3.0

300 deg C to 400 deg C 2.0

400 deg C to 500 deg C 1.0

500 deg C to 515 deg C 0.6

The maximum increase rate of metal temperature of the ms connecting pipe should

not exceed 15deg.c/min.

I. Ensure the following:

No line clearance is pending on TG set.

Boiler is steaming and steam is available.

All TG interlocks and protections are checked and checking of all motor operated

valves, Pneumatic

Operated control valves closing and opening is completed.

23

Page 24: 20mw Operation Manual

TG instrumentation / annunciation system is OK. Root valves to transmitter lines are

in open

Position.

DC supply is healthy for EOP and trail run was taken.

MOT level is normal.

Overhead tank level is normal.

Auto start of EOP, COP - 1&2, AOP, are checked.

II. Carry out related operations and ensure the following

AOP&JOP are running as per the procedure.

COP is running as per the procedure.

EOP is selected in standby mode on the Governor panel.

Oil flow is normal through the bearings (observe from sight glass).

Circulating water is charged in condenser and ACW pump and CW pumps are in

service.

TG is on Turning Gear Operation as per the procedure. During cold start up, Turbine

should be kept

in TGM operation 2 hours prior to turbine rolling.

Oil cooler is charged from cooling waterside to maintain oil temperature 45 +/- 5 deg

C.

Ensure ACW to Generator air coolers line valves are in open position.

Condenser hot well level is normal and CEP is running through Main Ejector and

GSC.

Main steam line is charged up to MSV (T).

Start vacuum pulling as per the procedure.

Check the set pressure of sealing steam (PIC 107) is 0.1 to 0.2Kg/Sq.Cm (g) then

open the sealing

Steam HOV.

24

Page 25: 20mw Operation Manual

After attaining 0.5 Kg/Sq.Cm (a) pressure in condenser, open the drains in extraction

lines to

remove the Condensate in the pipelines.

Ensure the following drains are open

Drain before MSV (T).

Drain valves in extraction before check valves lines.

Isolate the Steam traps of ESV, Turbine Casing and Turbine Chest.

Turbine casing drain (Wheel chamber) through Steam trap bypass.

ESV drain through Steam trap bypass.

HP governor chest drain through Steam trap bypass.

Ensure all extraction check valves and MOVs are in closed position.

Meanwhile, attain condenser vacuum to -0.9 Kg/Sq.cm (g).

Check and record the following Turbovisory readings:

Rotor axial displacement

Thermal expansion (Local measurement)

Turbine, Reduction Gear and Generator rotor vibrations

Turbine speed

MOT level

Lube oil pressure and temperature

All bearing temperatures

Casing metal temperature

MS pressure and temperature

Gland steam pressure and temperature

Condenser vacuum

PRDS pressure and temperature

Ensure main steam line is warmed upto MSV (T), then open MSV (T) bypass valve

(H.O.V) and open the drains in MS line and ESV body slowly. (Ensure ESV is in

closed condition before doing the above).

25

Page 26: 20mw Operation Manual

After warming up ESV body, ensure that no Turbine protection is active (from ‘

Turbine Protection’ graphic) and then give “RESET ON” command from DCS. This

will reset all the protections.

Reset fault signals by pressing “ Governor Clear” button on TGP.

Check lube oil pressure, trip oil pressure, control oil pressure and lube oil

temperatures.

Check the auto-standby position of COP, & EOP.

Open the ESV by pressing the “Turbine Reset” button on TGP. Check the open feed

back on TGP and warm up the chest at least 20 min. This is tentative, ensure the chest

drain temp. is equal to the MS metal temp.

Ensure the Hotness of ESV and Turbine Chest drains.

Check AOP & Turning Gear are in service and selected in auto.

Open the MSV (T) before going to roll the turbine.

Start the Turbine rolling by pressing the “START” button on TGP. The governor will

accelerate the speed of the turbo generator and hold it at idle speed 750 rpm. During

the speed rise, check for Turning gear motor stop at the set rpm (> 10% of rated rpm).

Ensure the Hotness of Turbine Casing drain.

Observe the exhaust hood temperature .

Observe all the Turbovisory readings. (Mentioned earlier).

Feel and listen for any rubbing and abnormal noises during warm up.

Check and record the shaft vibrations and axial displacement monitor on TGP.

Check whether the turbine casing expansion has started and its pointer is moving on

local scale, near turbine front bearing.

After ensuring expansion by 1.0 to 1.5mm, Press the “RATED SPEED” button on

TGP. The governor will accelerate the speed of the turbine generator automatically to

4897 rpm. Observe for the bearing vibrations in the Critical speed range from 1650 –

2050 rpm.

Check AOP are stopped at > 95%(4650 rpm) respectively.

26

Page 27: 20mw Operation Manual

Start the CT fans before synchronizing the generator as for the procedure.

Synchronize the generator with the GRID as per the procedure.

Increase the load on generator to 3 MW.

Close all the MS drains.

Gradually increase the load (not more than 1.0mw/min) by means of “SPEED/LOAD

SETTING” lever on TGP or Generator control panel.

At 6.0 MW load, operator can select for load control when connected with grid.

Steam traps of ESV, Turbine Casing, Turbine Chest drains should be kept in service

and close the bypass valves.

Ensure the Steam traps are working or not. If they are not working open the bypass

valve slightly.

Gradually increase the load as per the “loading procedure”.

After paralleling with both the boilers gradually increase the load to 30MW as per the

procedure.

Warm start up and Hot start up

Turbine start up is termed as “Warm startup” if it is being started 3 to 4 hours after

trip of turbine. Turbine start up is termed as “Hot Startup” if it is being started with

in 2 hours after trip of the turbine. Follow the procedure for the cold startup upto

speed up to idle speed (i.e 750 rpm). After reaching 750 rpm, allow the machine for

soaking at the idle speed. Ensure that casing expansion has started from local scale

during soaking than previous condition. After ensuring that casing expansion has

started, then give command for Rated Speed. MS temperature should be maintained

50 0C more than MS skin / MS temp.at Turbine inlet. (Subjected to operating

temperature – 530 0C at Turbine inlet.)

For warm and hot startup following parameters can be maintained.

27

Page 28: 20mw Operation Manual

If the metal temperatures are inlet steam parameters must be

300deg.c (warm) 40kg/sq cm and 400 deg.c

350deg.c 50kg/sq cm and 450 deg.c

400deg.c 65kg/sq cm and 480 deg.c

450deg.c 75kg/sq cm and 500 deg.c

During any start of turbine, do not forget to open all the Turbine drains.

VII. Loading of Turbine:

After synchronizing the turbo generator with grid the minimum load to be maintained

is 4MW.

Check all Turbovisory instrument readings are normal.

Check rise of turbine casing metal temperature and its casing expansion.

Ensure smooth running of Turbine.

Raise the load at 0.5MW increment (1.0mw/min) by observing MS pressure and

temperature at turbine inlet.

At above 6 MW load take Generator ‘Automatic Power control’ in to service.

At 8MW stable load charge the Deareator as per the procedure.

At 12 MW stable load charge the HP heater as per the procedure.

IX. Planned and Emergency Shutdown of Turbine:

Planned shut down:

Reduce the load on TG gradually to 3 MW, by operating the load/ speed switch on

GCP.

When load is at 12 MW cut off HP Heater.

When load is at 8 MW cut off Deaerator.

28

Page 29: 20mw Operation Manual

Open generator breaker as per the procedure.

Manually shut down the turbine (decelerate the turbine speed by pressing the

“Remote Trip” button on TGP). Ensure the actuator, ESVand MSSV closes

automatically.

Ensure all extraction check valves and extraction motor operated valves (MOVs) got

closed on interlock.

Open all the Before QCVs drains.

Close HP heater drip to deaerator & condenser control valves and LP heater drip to

condenser.

Open MS drains to atmosphere.

Ensure COPs, AOP, JOPs, TGM turns to AUTO selection on interlock at 95% speed.

Observe AOP to start in auto when lube oil header pressure drops to 0.87+/-0.2

Kg/Sq.Cm. If it is not started, start the pump manually and observe discharge

pressure.

Ensure TGM starts in auto at <10% speed with time delay of 150 seconds. If it is not

started, engage the turning gear manually at “0” rpm of the turbine and start TGM

from DCS.

When the shut down period is less than 1.0 hour, maintain the vacuum in condenser.

During this period, ensure that gland seal exhaust fans are in continuous service and

the PRDS parameters should be reduced to 7.0kg/sq.cm & 150deg.c gradually i.e

5deg.c/min.

When the shut down period is more than 1.0 hour, kill the vacuum in condenser by

opening the vacuum break valve. Before opening the vacuum break valve, make sure

that hand operated valve in gland sealing steam supply line is closed and isolate the

Main ejector as per procedure.

Before killing the vacuum close all the Before QCVs drains.

1. Stop COP as per the procedure.

29

Page 30: 20mw Operation Manual

2. Run the CW pump 2 hours.

3. Run the CEP in recirculation around 4 hours.

4. Run the GSC Exhaust fan around 4 hours.

5. The coasting down period of the turbine will be approximately 20 minutes.

6. Normal TGM operation period is 10 hours after trip of turbine as per SNM

manual, as per SNM Engineer Instructions it is also a measurement of Casing

Expansion should be <2 mm on local indicator but practically it is taking 14 to

20 hours to cool down the turbine casing, rotor and the bearings.

7. After cooling down period, stop TGM and run the AOP, OVE fans further 2

hours.

8. After ensuring the bearing Babbitt, oil inlet and drain oil temperature becomes

near equal. Stop AOP, When AOP is stopped EOP will start in auto. Stop EOP

from TGP.

9. Stop (OVEF) oil vapour fan.

Emergency Shut Down

01. In case of emergency, the turbine can be stopped by either of the following

methods.

‘Remote trip’ button on TGP and GCP.

‘Manual trip cock’ lever from front bearing (i.e Hand Trip)

Turbine trip from Desk push button.

02. For the Emergency shutdown due to abnormality of M/C or tripping of the TG on

protection following steps are to be taken:

Ensure ESV, MSV (T) are closed, all extraction MOVs, extraction check valves

Ensure COPs, AOP, JOPs, TGM turns to AUTO selection on interlock.

30

Page 31: 20mw Operation Manual

Ensure AOP has started on Lube oil pressure low interlock.

Ensure TGM started in AUTO as per the interlock

If required kill the vacuum as per the procedure.

Continue AOP, TGM, GSC exhaust fan, OVE fan, CEP, CW pumps in service as per

the procedure.

03. Follow the activities mentioned in the above “Planned Shutdown”.

WORK INSTRUCTIONS

X. Emergency conditions during Turbine Operation:

The following emergency conditions may occur during Turbine operation. The

turbine operator should always be ready to take correct decision and act as per the

operating procedures. It is also necessary that he should know about the boilers

loading status, Tie- feeders positions, import and export power details in his shift.

a. Total power failureb. Island mode operationc. Any one boiler tripd. DCS failure

a. Total power failure:During total power failure, there will be no power supply to the AC drives (BFP, CW & ACW pumps, CEPs, COPs, AOP, Turning Gear, Oil Vapor Exhaust Fans & GSC Exhaust Fans). BFP, CW & ACW pumps, CEP, COP, Oil Vapor Exhaust Fan & GSC Exhaust Fan will be tripped. Turbine will trip on heavy fault protection.In this case, the following operations are to be carried out by the Turbine desk

operator:

Inform to Turbine field operator about total power failure and subsequent operations

to be carried out.

Ensure ESV is closed and Extraction check valves are closed on interlock. If not,

close them from DCS.

Check EOP starts on interlock at < 0.62 Kg/Sq.Cm. If not, start EOP from TGP.

Close the following control valves:

31

Page 32: 20mw Operation Manual

Normal & Emer. Make up valves by observing the condenser level

PRDS pressure control valve to isolate the ejectors and glands.

PRDS temperature control valve

LPH drip CV to Condenser.

HPH drip CV to Condenser

HPH drip CV to Deaerator

Deaerator pressure control valve to depressurize the Deaerator.

Close the Isolation valves in PRDS Pressure CV and Temperature CV. Close HOVs

in air and steam lines of Ejector from local.

Close HO isolation valve in Gland sealing line.

Close all drain valves connected to condenser. And open Vacuum break valve.

After restoring the Emergency DG set power, close the following valves:

All three extraction MOVs

Main steam stop valve (Turbine)

Discharge valve of BFP

Start AOP after informing to Switchgear operator.

Start JOP as per the procedure.

After turbine reaches to <10% of rated RPM start TGM as per the procedure.

Field Operator’s duty during total power failure:

Close isolation valves of PRDS Pressure CV and Temperature CV.

Close Main ejector air valves and steam valves.

Ensure EOP is started and Lube oil pressure is normal.

Close HOV in gland sealing line.

Close discharge valves of CW pumps.

Close all drains connected to condenser. Ensure turbine gland sealing steam

pneumatic control valve is operating and gland steam pressure is normal (0.1 to

0.2Kg/Sq.Cm (g)).

32

Page 33: 20mw Operation Manual

b. Island Mode Operation

Unit turns to Island mode in the following cases:

1. Sudden rise / drop in frequency

2. Sudden drop in load

3. Internal disturbance in LT / HT systems

4. Mal operation / mal function.

The following procedure is to be followed:

Load drops / rises as per the FAP demand. The turbine rotor speed and MS pressure

at turbine inlet will change.

Maintain the Generator Frequency at 50HZ by changing the turbine speed from

“load/speed change” lever from TGP.

Ensure the steam being supplied from the Boiler is sufficient to generate the load on

the turbine. If steam flow is less, MS pressure will drop. Ask shift engineer to

decrease the load on FAP to the suitable limits.

Observe the turbovisory readings like axial shift, all bearing vibrations, all bearing

temperature and casing expansion for any change. Do not allow MS temp to fall

sharply.

LP heater levels, HP heater levels and Deareator pressure may disturb due to load

fluctuations. Control the above parameters in manual mode.

. DCS failure condition:

Course of action for turbine desk operator and field operator, when total DCS CRT’s

are not available. Obtain the instructions to run or to trip the unit from GM (PP)/

DGM (O&M)/ Manager (O)

Procedure to be followed to run the unit

All control loops work in auto. We do not have monitoring from CRT. All protections

and interlocks may work.

33

Page 34: 20mw Operation Manual

Ensure turbine load / MS pressure control remains in Auto mode.

MS pressure, Turbine RPM, Governor valve actuator position can be monitored from

“WOOD WARD” system.

Monitor and Control PRDS pressure and temperature from local.

Condenser level should be monitored from local gauge glass.

Deaerator level has to be monitored from local gauge glass.

CEP discharge pressure should be observed form local pressure transmeter and

gauge.

Observe HP, LP, Deareator extraction pressures from local pressure transmitters.

LP, HP heater levels to be monitored from local gauge glass and level transmeter

analog indication.

Observe lube oil pressure, governing oil pressure, trip oil pressure, MOT level,

vacuum and Gland steam pressure local gauges/transmitters.

Maintain the same load.

Observe BFP parameters from local. Inform to Boiler operator to maintain constant

feed water flow

Procedure to be followed to trip the turbine:

If any abnormality is found during this period trip the turbine as per the procedure

given:

Inform the Boiler operator about tripping.

Trip the turbine from local hand trip lever or remote trip from TGP.

Ensure ESV, all extraction check valves and extraction MOVs closed from TGP and

local.

Ensure AOP / JOP / TGM has started in sequence as per the interlock. If not start

them as per procedure from MCC. If AOP has not started in AUTO, Start EOP from

start push button on TGP.

34

Page 35: 20mw Operation Manual

Isolate the PRDS station by closing the PRDS pressure CV and Temperature CV

isolation hand operated valves.

Isolate the Gland sealing line by closing the hand-operated valve in GS supply line.

Close LP heater and HP heater drains to condenser CVs isolation valves.

Continue AOP, COP, , TGM, OVEF, GSCEF, CEP, CW Pumps, ACW Pump to run.

Stop the BFP after taking clearance from Boiler operator from local. (After box up of

boiler)

Run the CEP in complete Re-circulation.

Cut off the lube oil coolers if necessary.

XI. Important Dos and DON’Ts during Turbine Operation:

DOs:

1. The turbine has to be shutdown immediately in the following cases.

When the turbine rotor speed increases higher than 5200 rpm.

Whenever oil pipes, steam pipes, main condensate pipes, feed water pipes are

broken or some cracks / leaks are found in them.

Whenever some hydraulic shocks are occurred in the piping or in the turbine

casings.

Some metallic noise is heard clearly in the turbine

When the mechanical over speed lever is defective

2. The turbine is to be tripped emergently with breaking vacuum manually in the

following cases:

When the lube oil header pressure drops to <0.45Kg/Sq.cm

When the oil catches fire and fire could not be extinguished immediately.

When the turbine tripped on “Rotor Axial Displacement” protection

3. DO in every shift:

Check Main oil tank level is normal.

Check oil vapour fan and GSC exhaust fan are in service.

35

Page 36: 20mw Operation Manual

Check the availability of DG set.

Check the availability of AOP, Stand by COP and DC EOP.

Check the open position of Discharge valves of AOP, EOP, standby COP.

Ensure the Steam traps of ESV, Turbine Casing and Turbine Chest drains

are working normal.

Ensure condensate system and feed water systems are running normal

Ensure CW system is running normal

Ensure Glands sealing steam control valve is functioning normally

Ensure the parameters of turbine and its auxiliaries are within the limits

Check the sealing water to Condenser connected valves are given

Check starting ejector air valve and vacuum break valve are tightly closed

Ensure that all instruments functioning properly

Ensure that standby ACW and stand by CEP discharge valves are in open

position.

DON’Ts

1. Do not operate the turbine, any equipment bypassing the interlocks

2. Do not operate the turbine with high vibration values and high bearing

temperatures conditions

3. Do not allow sudden drop or rise in MS temperature and MS pressures.

4. Do not start the vacuum pulling with out turbine on Turning Gear operation

5. Do not start the Glands charging with out turbine on Turning Gear operation

6. Do not continue turbine on TGM operation if unusual sound / vibration comes

from gland seal, bearings etc.

7. Do not operate the turbine with LOW main oil tank levels.

8. Do not start the TGM with out Over head oil tank level normal

9. Do not start the Turbine with out Over head oil tank level normal

10.Do not start the TGM with out running the AOP&JOP.

11.Do not run Lube oil system with out running the oil vapor exhaust fan.

36

Page 37: 20mw Operation Manual

12.Don’t run Oil vapor Exhaust Fan when MOT level is high.

13.Do not allow hot rotor to stand with out rolling (with out TGM operation)

14.Do not overlook abnormality in any important reading

15.Do not forget to check stand by position and healthiness of DC EOP

16.Do not allow any leakage in the suction side of the CEPs.

17.Do not start the CEP with out opening of Air removal and Gland sealing.

18.Do not open any valve, fitting, flange in the suction side of CEPs in normal

working condition. When condenser is in vacuum this will cause vacuum to

drop and pump (CEP) to loose its suction.

19.While cleaning suction strainer of stand by CEP, ensure closure of suction

valve.

20.Do not keep the steam valve of main ejector open for long time if condensate

flow is not there through main ejector.

21.Do not run the turbine with open or un tightened flanges on oil tank, oil piping,

steam piping. etc.

22.Don’t charge the PRDS line without closing the Turbine Glands Isolation

Valve.

23.Do not open the Vacuum break valve with out Isolating the Glands Isolation

valve and Steam lines connected to Condenser.

BOILER FEED PUMP:In thermal power plant cycle the feed pumps are placed in the feed water system and are intended to deliver the feed water to the boiler. 100% availability of these pumps are essential to run the plant.This pump delivers feed water at higher pressure against boiler resistance, through feed control station. The feed control station regulates the feed water flow according to drum level.Two numbers of diffuser type boiler feed pumps supplied by KSP make, are installed here. The BFPs are rated to deliver each 150 cu.m/hr. feed water against a head of 1275 Mlc and is driven by 730 KW, 2980-rpm motor.

37

Page 38: 20mw Operation Manual

*/Technical Data/*Type of pump : DiffuserFeed water temperature : 158 Deg.CFlow rate : 166 TPHDeveloped head : 1285 MlcSpeed : 2980 rpmNet positive suction head : 5.8mlcRecirculation flow : 40 TPHDirection of Rotation : CCW from Motor DE.

STARTING OF BFP:Ensure no line clearance is pending on BFP, its auxiliaries and its connecting piping and valves. Ensure supply to the Motor is available.Ensure Deaerator level is normal and CEP is in service to maintain its level.Check the lube oil levels of pump DE & NDE bearings.Ensure ACW pump is in service.The inlet and outlet valves of ACW water to BFP should be in open position and check the ACW pressure at BFP is 2.5 Kg/ Sq.cm

The following inlet and outlet valves should be in open position: -a. Pump NDE side - Thrust bearing housing

Stuffing box Seal water cooler

b. Pump DE side - Journal bearing housing Stuffing box SSeal water cooler

Ensure the feed water system is through to HP Heater.Ensure open position of suction valve of BFP.Ensure discharge valve is in closed position.Check that hand-operated valves (2 nos) in balancing leak off line (one is at pump and another at Deareator tank) are in open position.Check the HOV in recirculation line (at Deareator tank) is in open position.Ensure all isolation valves in impulse lines are open.

Ensure the local Push Button is released.Close the warm up valves for starting the pump.*Ensure that PRDS Attemperation is isolated from BFP discharge.Close the warm up.

38

Page 39: 20mw Operation Manual

Start the Pump from DCS and keep the pump in recirculation for 2 minutes and observe the following:

a. Suction & discharge pressures.b. Suction & discharge temperatures.c. Bearing temperatures.d. Seal water temperatures.e. Differential pressure across the suction strainer.f. Balancing leak off & re-circulation line pressures.g. Motor currents.h. Any abnormal sounds.i. Lube oil levels in bearing cups.

Open the discharge valve from control room DCS.Ensure balancing leak off pressure is higher than suction pressure.Observe the parameters in point no 16.

Shut down sequence:

1. Close the discharge valve.2. Keep the Pump in re-circulation.3. Stop the Pump from Control room.

NOTE*

1. Observe Motor currents shouldn’t exceed >47 amps.2. When the Motor currents have crossed 47 amps and tending to increase,

inform Shift In charge or Boiler Desk Operator.3. Don’t allow the Pump to start or run with Protection interlock bypass.

WHAT NOT TO DO:

1. Don’t close the valves in re-circulation and balancing leak off lines2. Don’t allow the BFP to run when the bearing temperatures exceeds>80 deg.3. Don’t run the Pump without ACW pump is in service.4. Don’t allow the Pump to run when the seal water temp. Exceeds the limit.

(>80 deg)5. Don’t switch on the pump during discharge valve is in open position.

STARTING PERMISSIVES:

39

Page 40: 20mw Operation Manual

Ensure the following permissive at DCS & Local.1. Discharge valve is in closed position.2. Deaerator level is not low >900mm3. DP across suction strainer is not high.

PROTECTIONS FOR BFP:

a. Deaerator level low : < 400mm.b. BFP suction pressure low (trip not incorporated).c. DP across strainer high : > 0.5 Kg/Sq.cm.d. BFP Brg. temps high : > 80 Deg C.e. DT across pump : 20 Deg C.f. Discharge Pressure low : < 105 kg/sq.cmg. Suction temp. Switch active : 160 Deg C.h. Balancing leak Off pressure is high, : >12.0 kg/sq.cmi. ACW pump discharge pressure : < 2 .0 Kg/Sq.cm

with time Delay of 15 sec.

J. BFP motor winding temp.high high : 140 deg.c. K. BFP motor bearing temp. high high : 95 deg.c

Note: For Point ‘f’, initial bypass of protection for a period of 70 seconds is incorporated.

CW PUMPS2 CW pumps (both working) are installed to supply cooling water to condenser. It is rated to deliver 6900 TPH, at 2.10Kg/Sq.cm and is driven by 415V, 550 KW, 740-rpm motor. The cooling water pump receives its suction from CT Sump and discharge is returned to CT sump through Condenser and riser pipes.

STARTING OF CW PUMPS:1. Check no line clearance is pending on CW system.2. Ensure LT supply to the Motor is available.3. Ensure Sump level is normal. If low, make it normal with CT Sump Make up

Pump. (Sump level is > 2800 mm)4. Ensure CW to Condenser I/L and O/L valves and CT raiser valves are opened. (For

one pump one CT riser valve, and for two pumps in operation two riser valves)5. Open all the 4 air vents of Condenser Water box during initial starting of pump. Close them after air vented out6. Open Air release cocks located above the Pump to ensure that the Pump is full of water.

40

Page 41: 20mw Operation Manual

7. Ensure Gland cooling water valves are open. 8. Ensure suction valve is opened and discharge valve is in closed position.9. Release Local Push Button.10. Start the Pump from DCS.11. After speed pick up and restoration of normal currents, slowly open the discharge valve.12. Observe the discharge pressure should be > 1.5 kg/sq.cm at pump.13. Check the bearing & Glands temperatures Physically.14. Observe the gland leakage water from Pump DE and NDE.

SHUT DOWN SEQUENCE:1. Close the discharge valve.2. Switch off the Motor.

STARTING PERMISSIVES:1. CW Sump level is > 2800 mm.

PROTECTIONS:1. Sump level low low. (Value not incorporated.)

IMPORTANT NOTE:1. Don’t start the Pump keeping Discharge valve in open position.2. Maintain sump level between 2800 and 3000 mm.3. When both the pumps are in service, ensure that at least two riser valves must be

in open position.4. Discharge valve of the stand by pump should be in closed position.5. Don’t allow the pump to start or run with protection interlock bypass.

41

Page 42: 20mw Operation Manual

DESK OPERATORS GUIDE:

The following are the Protections (Trip values) of the Turbine:

1. Steam temperature at turbine inlet high high > 543 Deg.C

2. Steam temp. at turbine inlet low low < 460degC, this protection comes in to

service only when MS temperature reaches to 495 deg C and then falls to 460.

3. Steam pressure at turbine inlet low low < 60 kg/sq.cm (may be bypassed initially

for Cold and Warm start ups if required.)

4.Steam pressure at turbine inlet high high >103kg/sq.cm (not incorporated).

5. Control oil pressure low low 8.0+/-0.5 Kg/sq.cm

6. Lube oil pressure low low < 0.62 Kg/Sq.cm

7. Generator heavy fault (Generator trip).

8. Turbine mechanical over speed trip >/= 5632 rpm

9. Turbine electrical over speed trip >/= 5583 rpm

10. Governor heavy fault.

11. Remote trip from turbine governor panel.

12. Turbine trip from desk push button.

13. Exhaust steam pressure high high > 1.3 Kg/Sq.cm (abs)

14. Exhaust steam Temperature high high > 150 degC

15. Lube oil reservoir level (MOT) low low < 350 mm.

16. Hot well level low low < 300mm

17. Hot well high high 1400 mm

42

Page 43: 20mw Operation Manual

18. Turbine Rotor axial shift high high +0.65, -0.65 mm.

19. Turbine front shaft vibration high high 90 microns

20. Turbine rear shaft vibration high high 90 microns

21. Reduction gear pinion front shaft vibration high high 140 microns

22. Reduction gear pinion rear shaft vibration high high 140 microns

23. Reduction gear wheel front shaft vibration high high 180 microns

24. Reduction gear wheel rear shaft vibration high high 180 microns

25. Generator front shaft vibration high high 160 microns

26. Generator rear shaft vibration high high 160 microns

27. Turbine thrust bearing temperature high high (inactive) 120 Deg.C

28. Turbine thrust bearing temperature high high (active) 120 Deg.C

29. Turbine front shaft bearing temperature high high 120 degC

30. Turbine rear shaft bearing temperature high high 120 degC

31. Reduction Gear pinion front bearing temperature high high 120 degC

32. Reduction Gear pinion rear bearing temperature high high 120 degC

33. Reduction Gear wheel front bearing temperature high high 120 degC

34. Reduction Gear wheel rear bearing temperature high high 120 degC

35. Generator front bearing temperature high high 85 degC

36. Generator rear bearing temperature high high 85 degC

37. HP heater level high high 290mm. (Protection should be bypassed during

charging of HP heater.) not incorporated.

ANNEXURE-I, Turbo Generator Set - Alarms and Trip values

S.N Tag No Description of Tag Nor Lo Hi LL HH/Trip Condensate System

01 TPT106 Exhaust steam press. 0.086 0.05 0.3 0.02 0.5/1.3

43

Page 44: 20mw Operation Manual

(Vacuum) Kg/Sq.cm (abs)02 TTI800 CW Temperature at Cond

I/L-1 Deg.c30 26 34 25 36

03 TTI801 CW Temperature at Cond O/L-1 Deg.c

38 34 42 33 44

04 TTI802 CW Temperature at Cond I/L-2 Deg.c

30 26 34 25 36

05 TTI803 CW Temperature at Cond O/L-2 Deg.c

38 34 42 33 44

06 TTI106 Exhaust steam temperature Deg.c

44 120 150/150

07 TLT300ACondenser Level mm 800 600 1000

300/300

1400/1400

08 TLT440 UCFT Level mm 1650190009 TDPT40

0ADP across Cond. Left mmwc

5300 4500 60003500 7000

10 TDPT400B

DP across Cond. Right mmwc

5300 4500 60003500 7000

11 TCV440AFB

Emergency Makeup CV Feed back

12 TCV440BFB

Normal Makeup CV Feed back

13 TCV300AFB

CEP Recirculation CV Feed back

14 TLCV430FB

Deareator level CV Feed back

15 TPT321 CEP Discharge Pressure Kg/Sq.cm

9.0 7.0 11 6.0 14.0

16 Hot well Temperature Deg.c44 40 52 35 55

19 TDPT430A

Main Condensate Flow TPH 106 80 120 50 140

25 CPT480 CW Header pressure Kg/Sq.cm

1.6 1.4 1.8 1.0 2.0

44

Page 45: 20mw Operation Manual

BFP & Feed water system

01 TTI470A FW temperature at BFP-1 Suction Deg.c

158 130 165 100 170/170

02 TTI470B FW temperature at BFP-2 Suction Deg.c

158 130 165 100 170/170

03 TTI471A FW temperature at BFP-1 Disch Deg.c

158 140 160 120 160

04 TTI471B FW temperature at BFP-2 Disch Deg.c

158 140 160 120 160

05 TPT460 BFP-1 Discharge Pressure Kg/Sq.cm

120.5 110 135 105/105

140

06 TPT470 BFP-2 Discharge Pressure Kg/Sq.cm

120.5 110 135 105/105

140

07 TTI468A BFP-1 DE Bearing Temperature Deg.c

60 70 80/80

08 TTI468B BFP-2 DE Bearing Temperature Deg.c

60 70 80/80

09 TTI469A BFP-1 NDE Bearing Temperature Deg.c

60 70 80/80

10 TTI469B BFP-2 NDE Bearing Temperature Deg.c

60 70 80/80

11 TTI466A BFP-1 Motor DE Bearing Temp Deg.c

70 90 80/95

12 TTI466B BFP-2 Motor DE Bearing Temp Deg.c

70 90 80/95

13 TTI467A BFP-1 Motor NDE Bearing Temp Deg.c

70 90 80/95

14 TTI467B BFP-2 Motor NDE Bearing Temp Deg.c

70 90 80/95

15 TPT103 HPH Ext. Steam pressure Kg/Sq.cm

20.5 18 22 15 25

16 TTI103 HPH Ext. Steam temperature Deg.c

337 300 350 280 360

17 TTI702A HPH Drain temperature Deg.c

154 140 165 120 180

S.N Tag No Description of Tag Nor Lo Hi LL HH/Trip

45

Page 46: 20mw Operation Manual

18 TTI704A FW temp at HPH I/L Deg.c 158 135 155 120 16019 TTI703A FW temp at HPH O/L Deg.c 220 190 225 180 23520 TLT420AHPH level –1 mm 180 170 220 160 240/29

021 TLT420BHPH level –2 mm 180 170 220 160 240/29

022 TCV420F

BHPH drain to Deareator CV Feed Back

23 TCV420BFB

HPH drain to Condenser CV Feed Back

24 TPT104 Deareator Extr Steam Pressure Kg/Sq.cm

5.00 5.51 6

25 TTI104 Deareator Extraction Steam Temp Deg.c

219 240 300

26 TPT430 Deareator Pressure Kg/Sq.cm

5.0 5.5 6.0

27 TLT430ADeareator Level – 1 mm 1150 650 1465

500/400

1665

28 TLT430BDeaerator Level – 2 mm 1150 650 1465

500/400

1665

29 TLT430SEL

Deareator Level Selection mm

1350 650 1665

500/400

1865

Main Steam/Aux./Gland steam sys

01 1PT001 M S press at common header Kg/Sq.cm

90 80 95 60/60 105

02 TPT101 Steam pressure at turbine I/L

90 80 95 80 94/102

03 TTI101 Steam temperature at turbine I/L Deg.c

530 485 538 460/460

543/543

04 TPT102 Steam pres aft turbine 1st stage Kg/Sq.cm

65 63 67

05 TTI1021 Steam temp after turbine 1st stage Deg.c

475 480

06 TPT164APRDS Pressure Kg/Sq.cm 24 22 27 20 3007 TTI152A PRDS steam Temperature

Deg.c370 360 380 340 400

46

Page 47: 20mw Operation Manual

08 TPT107 Gland steam Pressure Kg/Sq.cm

0.2 0.08 0.4 0.06 0.45

09 TTI108 Gland steam temperature Deg.c

400 360 410 350 420

10 TTI108 Gland leak steam pressure11 TTI1022 Metal temp at turbine 1st

stage Deg.c465 475 480

12 TTI1023 Metal temp at turbine 1st stage Deg.c

465 475 480

Turbovisory

01 TLT500ALube oil tank level mm 550 400 800 350/350

870

02 TPT531ALube oil pressure to Bearings Kg/Sq.cm

1.5 1.17 1.7 0.62/0.62

2.0

03 TTI510A Lube oil temp at cooler I/L Deg.c

65 40 70 30 75

04 TTI511A Lube oil temp at cooler O/L Deg.c

45 40 50 30 55

05 TPT530 Control oil Pressure Kg/Sq.cm

14 12 10 17

06 TTI804 ACW temp at I/L of oil cooler Deg.c

30 25 34 20 36

07 TTI805 ACW temp at O/L of oil cooler-1 Deg.c

35 27 39 25 42

08 TTI806 ACW temp at O/L of oil cooler-2 Deg.c

35 27 39 25 42

09 TTI807 ACW temp at I/L of Gen cooler Deg.c

30 25 34 20 36

10 TTI807A ACW temp at O/L of Gen cooler-1 Deg.c

35 30 39 25 41

11 TTI807B ACW temp at O/L of Gen cooler-1 Deg.c

35 30 39 25 41

12 TTI807C ACW temp at O/L of Gen cooler-1 Deg.c

35 30 39 25 41

13 TTI807D ACW temp at O/L of Gen cooler-1 Deg.c

35 30 39 25 41

14 TSE2011Turbine Seed rated rpm 4900 4700 5338

4652 5632

47

Page 48: 20mw Operation Manual

Turbine Seed 16% rpm 816Turbine Seed 95% rpm 4650

S.N Tag No Description of Tag Nor Lo Hi LL/Tri HH/Trip15 TZE2011Axial shift mm 0 -0.45 0.45 -0.65 -

0.65/0.65

16 TZE2012Axial shift mm 0 -0.45 0.45 -0.65 -0.65/0.65

17 TTI201 Turbine bearing temperature – 1 Deg.c

60 110 120/120

18 TTI202 Turbine bearing temperature – 2 Deg.c

60 110 120/120

19 TTI203 Turbine bearing temperature – 3 Deg.c

60 110 120/120

20 TTI204 Turbine bearing temperature – 4 Deg.c

60 110 120/120

21 TTI205 R/G pinion front bearing temp-1 Deg.c

100 120/120

22 TTI206 R/G pinion rear bearing temp-2 Deg.c

100 120/120

23 TTI207 R/G wheel front bearing temp-3 Deg.c

100 120/120

24 TTI208 R/G wheel rear bearing temp-4 Deg.c

100 120/120

25 TTI209 Generator front bearing temp-1 Deg.c

75 85/85

26 TTI210 Generator rear bearing temp-2 Deg.c

75 85/85

27 TVXT201Turbine front shaft vib, Horizontal microns

45 90/90

28 TVYT201Turbine front shaft vibr, Vertical microns

45 90/90

29 TVXT202Turbine rear shaft vibr, Hor microns

45 90/90

30 TVYT202Turbine rear shaft vibr, Vertical microns

45 90/90

31 TVXT203RG pinion front shaft vibr, Hor microns

96 140/140

32 TVYT203RG pinion frt shaft vibr, 96 140/14

48

Page 49: 20mw Operation Manual

Vertical microns 033 TVXT204RG pinion rear shaft vibr,

Hor microns96 140/14

034 TVYT204RG pinion rear shaft vibr,

Vert microns96 140/14

035 TVXT205RG wheel front shaft vibr,

Hor microns120 180/18

036 TVYT205RG wheel front shaft vibr,

Vert microns120 180/18

037 TVXT206RG wheel rear shaft vibr,

Hori microns120 180/18

038 TVYT206RG wheel rear shaft vibr,

Vert microns120 180/18

039 TVXT207Generator front shaft vibr

hor microns100 160/16

040 TVYT207Generator front shaft vibr

Vert microns100 160/16

041 TVXT208Generator Rear shaft vibr

hor microns100 160/16

042 TVYT208Generator Rear shaft vibr

vert microns100 160/16

043 TTI254 Gen cold air temp 5044 TTI255 Gen cold air temp 5045 TTI256 Gen hot air temp 7746 TTI251 Gen Winding temp-1 100 80 110 70 12047 TTI252 Gen Winding temp-2 100 80 110 70 12048 TTI253 Gen Winding temp-3 100 80 110 70 120

Currents / Winding Temperatures

01 CCT626A

CW Pump – 1 Motor current, Amp

02 CCT626B

CW Pump – 2 Motor current Amp

03 CCT626C

CW Pump – 3 Motor current Amp

06 CCT625A

CT Fan-1 Motor current Amp

07 CCT625B

CT Fan-2 Motor current Amp

49

Page 50: 20mw Operation Manual

08 CCT625C

CT Fan-3 Motor current Amp

09 CCT670 BFP-1 Motor current Amp10 CCT671 BFP-2 Motor current Amp11 CEP motor current Amp12 AOP motor current Amp13 COP motor current Amp14 JOP motor current Amp15 EOP motor current AmpS.N Tag No Description of Tag Nor Lo Hi LL/Tri HH/Trip16 OVEF motor current, Amp17 GSCEF motor current Amp18 TGM motor current Amp19 TTI460A BFP-1 Winding

temperature-1 Deg.c95 140 110

20 TTI460B BFP-2 Winding temperature-1 Deg.c

95 140 110

21 TTI461A BFP-1 Winding temperature-2 Deg.c

95 140 110

22 TTI461B BFP-2 Winding temperature-2 Deg.c

95 140 110

23 TTI462A BFP-1 Winding temperature-3 Deg.c

95 140 110

24 TTI462B BFP-2 Winding temperature-3 Deg.c

95 140 110

25 TTI463A BFP-1 Winding temperature-4 Deg.c

95 140 110

26 TTI463B BFP-2 Winding temperature-4 Deg.c

95 140 110

27 TTI464A BFP-1 Winding temperature-5 Deg.c

95 140 110

28 TTI464B BFP-2 Winding temperature-5 Deg.c

95 140 110

29 TTI465A BFP-1 Winding temperature-6 Deg.c

95 140 110

30 TTI465B BFP-2 Winding temperature-6 Deg.c

95 140 110

50

Page 51: 20mw Operation Manual

COMMUNICATION

To avoid communication gap among all the power plant staff the following

stationary to be maintained in addition to the walke talkies and phanes.

1. Line Clearance form for safety.

2. complaint register to enter abnormalities.

3. Instructions register.

4. Log sheets for each field.

5. Log books for each field.

6. Running hours log book.

7. Coal & bagasse stock log book.

8. Coal & ash analysis log sheets.

9. Daily Generation & consumption log sheets & log books.

10. Water and steam analysis log sheets.

Line Clearance form for safety:

51

Page 52: 20mw Operation Manual

Before doing any work on running or stanby equipments in running or in shut

down the respective maintenance persons should take the Line Clearence from the

shift in charge/engineer.

The shift in charge/engineer should understand the work to be carried out. If he

feels the work can be caried out with out disturbing the running of the plant then he

should in form the line or equipment to be Isolated to the concerned field operator.

After the isolating the equipment/line the field operator will sign on the line clearence

form. After ensuring the line /equipment isolated the shift in charge/engineer con give

Line Clearence to carryout the work to concerned maintenance department.

Before starting the work the maintenance person should ensure that the

field operator & shift in charge/ engineer signed on the L.C form and the

equipment is isolated.

After completion of the work the maintenance persons has to return the L.C.

The concerned operator should keep the equipment ready for operation. The

same is to be ensured by shift in charge/engineer.

If needed the trail run of the equipment/line to be carried out in presence of

shift in charge/engineer & maintenance person.

complaint register to enter abnormalities:

If any abnormalities observed in the system/equipment concerned operator should

bring to the notice of shift in charge/ engineer. The shift in charge/engineer should

check the equipment/system parameters and the abnormality to be registered in the

complaint register and inform to the concerned department.

If the abnormality is emergency then the maintenance people should be called

immediately and the same is to be informed to C.M.(O&M).

Instructions register:

52

Page 53: 20mw Operation Manual

If any special instructions in operations of any equipment/system the same is to

be entered in the Instruction register by the maintenance depart and the instruction

to be duly signed by the C.M(O&M). The instruction should contain the reasons

for the specialty and the valid period.

Log sheets for each field:

Each field operator and desk operator should enter the parameters

periodically in the log sheet. The log sheet should be duly signed by the shift in

charge in each shift.

Log books for each field:

Each field operator and desk operator should enter all the events in the log

book with time. The log books should be duly signed by the shift inc harge in each

shift.

Running hours log book:

Every day in the C shift the shift in charge should enter the day running hours

of every equipment in the register.

Coal & bagasse stock log book:

All the coal & bagasse receipts and consumptions to be entered in this log book

shift wise by the shift in charge/engineer and available stock to be evaluated daily.

Coal & ash analysis log sheets:

The log sheets to be filled daily wise by quality control department and to be

sent to shift in charge.

Daily Generation & consumption log sheets & log books:

53

Page 54: 20mw Operation Manual

Daily in 1st shift the consumptions of all the equipments to be recorded for the

previous day. The previous day total generation, total auxiliary consumption, PLF,

average frequency and percentage of auxiliary consumption to be recorded. The

reasons for any change in the generation & consumption also to be recorded.

Water and steam analysis log sheets:

The DM plant chemist should enter the periodical water and steam analysis in

the log sheets and the duly signed log sheets to be sent to shift in charge for reference

and recording.

54