sPHENIX Director’s Review2.03 – Cradle Carriage/Pole Tips/Platforms
J. Mills
April 9-11, 2019
Brookhaven National Laboratory
April 9-11, 2019 sPHENIX Director's Review 1
April 9-11, 2019 sPHENIX Director's Review 2
2.03.01 Drive, and Alignment
System
2.03.04 End Caps/Pole Tips
2.03.01 Carriage Assembly
2.03.01, .04, .05 CARRIAGE/CRADLE SYSTEM
2.03.05 Access Stairs
2.03.01 Seismic Supports
2.03.05 Top and Mid Platforms
2.03.05 Access Stairs
April 9-11, 2019 sPHENIX Director's Review 3
End Caps/Pole Tips
110 TONS
Magnet and Detector Subsystems565 TONS
Carriage assembly130 TONS
CARRIAGE Support Preliminary Design Loads
Top and Mid Platforms
150 psf
• RACKS= 12 TONS• CRYO = 6 TONS• BALANCE:
• CABLES• UTILITIES• DEAD LOAD• PERSONNEL
50 TONS
(analysis also includes seismic loads)
April 9-11, 2019 sPHENIX Director's Review 4
WORK BREAKDOWN STRUCTURE
2.03 CARRIAGE AND STRUCTURAL COMPONENTS
2.03.01 CARRIAGE
- CARRIAGE BASE ASSEMBLY
-TRANSPORT SYSTEM
-ALIGNMENT SYSTEM
-TRACK SYSTEM
-SEISMIC SUPPORTS
2.03.02 Inner Detector Structural Support
2.03.03 Barrel Steel/OHCal Sectors
2.03.04 CAPS/POLE TIPS
-MAGNETIC CAPS
-MOVABLE TO ALLOW ACCESS TO
DETECTOR
2.03.05 CC BRIDGE, MID PLATFORMS AND
ACCESS
- Platforms supporting electronics racks
- Means of egress (stairs/ladder)
5
Collaborators
April 9-11, 2019 sPHENIX Director's Review
• Level 2 Manager – C. Pontieri (BNL-PH)
• Engineering
– J. Hock (BNL-CAD)
– J. Mills (BNL-CAD)
• Design Engineering
– J. Scheblein (BNL-PH)
– D. Puleo (BNL-CAD)
Scope
• Perform engineering and design needed to assemble full specification and construction document packages necessary for fabrication.
• Develop appropriate interfaces with other subsystems.
• Perform design reviews in accordance with sPHENIX procedures.
• Develop bottom-up cost estimate and schedule for this subsystem.
• Fabricate necessary components needed to deliver subsystem to B1008 for assembly. Provide technical oversight during fabrication and assembly.
6April 9-11, 2019 sPHENIX Director's Review
Carriage Base Assembly
April 9-11, 2019 sPHENIX Director's Review 7
STIFFENER BEAMS WITH DOUBLES
PEDESTAL SIDE SUPPORT
CARRIAGE PEDESTAL (Cradle)
WELDED BASE
TOP PEDESTAL SUPPORT
CARRIAGE WELDED ½ BASE
April 9-11, 2019 sPHENIX Director's Review 8
ACCESS HOLE
HOLES FOR CONNECTING HALVES
1 ½” THICK TOP PLATE
6” THICK PLATE TO SUPPORT LIFTING JACKS
STIFFENERS FOR LONG ROLLER ASSEMBLY
FRAME IS MAINLY W14X193 BEAMS
STIFFENERS FOR SHORT ROLLER ASSEMBLY
CARRIAGE BASE HALVES JOINED
April 9-11, 2019 sPHENIX Director's Review 9
STIFFENER BEAMS WITH DOUBLES
PEDESTAL SIDE SUPPORT
CARRIAGE PEDESTAL
CARRIAGE ASSEMBLY
TOP PEDESTAL SUPPORT
TOP JOINING DOUBLE AND BEAM
BOTTOM JOINING DOUBLE
Production Drawings
April 9-11, 2019 sPHENIX Director's Review 10
• Preparing Detailed Production Drawings
• To be used for Fabrication and Budgetary Quotes
Base Assembly Drawing
Production Drawings
April 9-11, 2019 sPHENIX Director's Review 11
Checking and Preparing for Budgetary Quotes
PLATFORM/ACCESS
April 9-11, 2019 sPHENIX Director's Review 12
CARRIAGE SYSTEM
EASTSIDE ACCESS
ELECTRONIC RACKS
2ND TIER
STAIRS
WESTSIDE ACCESS
SEISMIC SUPPORT
April 9-11, 2019 sPHENIX Director's Review 13
CARRIAGE SYSTEM
REMOVABLE PIN ALLOWS FOR ADJUSTMENT IN THE Z DIRECTION
CARRIAGE BRACKET FLOATS IN THEY DIRECTION
TOP BRACKET ALLOWS FOR ADJUSTMENT IN THE X DIRECTION
BASE BRACKET
X
Z
Y
CARRIAGE FEA ANALYSIS CASE A1
April 9-11, 2019 sPHENIX Director's Review 14
MAX DEFLECTION = .26MAX VON MISES STRESS
MATERIAL: A36 STEELYIELD STRENGTH= 36.3 ksiULTIMATE STRENGTH=58 ksi
MAX STRESS= 16KSIAVERAGE STRESS= .57 KSI
SF=2.27
CARRIAGE ON JACKS¼ OF THE STRUCTURE WAS MODELED USING SYMMETRYLOADS:• WEIGHT OF STRUCTURE (GRAVITY)• WEIGHT OF DETECTOR (565 TONS)• WEIGHT OF PLATFORMS (150#/F2)
CARRIAGE FEA ANALYSIS CASE A2
April 9-11, 2019 sPHENIX Director's Review 15
MAX VON MISES STRESS
MAX STRESS= 16KSIAVERAGE STRESS= .64 KSI
SF=2.27
MATERIAL: A36 STEELYIELD STRENGTH= 36.3 ksiULTIMATE STRENGTH=58 ksi
CARRIAGE ON LONG ROLLER ASSEMBLY (EAST-WEST TRANSLATION)¼ OF THE STRUCTURE WAS MODELED USING SYMMETRYLOADS:• WEIGHT OF STRUCTURE (GRAVITY)• WEIGHT OF DETECTOR (565 TONS)• WEIGHT OF PLATFORMS (150#/F2)
April 9-11, 2019 sPHENIX Director's Review 16
MAIN MAGNET END CAPS
UTILITIES INTERFACES
April 9-11, 2019 sPHENIX Director's Review 17
TOP PLATFORM ELECTRONIC INTERFACE:• FLOOR PANELS (26”BY 36”) ARE REMOVABLE TO ACCESS
WIRING• FLOOR PLATES CAN BE REMOVED W/O JEOPARDIZING
THE STABILITY OF THE STRUCTURE• DATA CABLE TRAY LOCATED JUST BELOW FLOOR, UNDER
EACH ENCLOSURE.• POWER CABLE TRAY IS JUST UNDER DATA TRAY, 8” REACH.• WATER COOLING PROVIDED FOR EACH ENCLOSURE.
DATA CABLE TRAY
POWER CABLE TRAY
WATER COOLING SUPPLY AND RETURN
PLATFORM FLOOR PANEL REMOVED
Schedule Drivers
sPHENIX Director's Review 18April 9-11, 2019
2.03 CARRIAGE AND STRUCTURAL COMPONENTS
2.03.01 CARRIAGE
- Complete Engineering and Design
- Resolve issue related to tracks
2.03.04 CAPS/POLE TIPS
- Complete Engineering and Design
2.03.05 CC BRIDGE, MID PLATFORMS AND ACCESS
- Complete Engineering and Design
- Finalize means of egress with BNL Safety and Fire Protection
Schedule Development
• Bottom-Up Approach to task and duration
• Engineers and Designers Participated, Buy-In From All
• Assistance from Project Management Professional
• Vetted by Project Management Professional
• Linking and Flow of Tasks Performed in Real Time with Team
April 9-11, 2019 sPHENIX Director's Review 19
Milestones
April 9-11, 2019 20sPHENIX Director's Review
WBS Path WBS Name Activity ID Activity Name Milestone Level Date2.03.01 Cradle Carriage S310300 Carriage Cradle - Design & Safety Reviews Complete Released for Production L4 17-Oct-19
2.03.01 Cradle Carriage S311000 Carriage Cradle - Contract Award(s) L5 5-May-20
2.03.01 Cradle Carriage S311400 Carriage Cradle - Components Ready for Installation L3 24-Feb-21
2.03.01 Cradle Carriage S312900 CC Drive & Alignment System - Contract Award(s) L5 20-Aug-20
2.03.01 Cradle Carriage S313255 Completed - CC Drive & Alignment System - Delivery Acceptance - M&S L5 31-Dec-20
2.03.01 Cradle Carriage S314300 CC Seismic Restraints - Contract Award(s) L5 31-Oct-19
2.03.01 Cradle Carriage S314655 Completed - CC Seismic Restraints - Delivery Acceptance - M&S L5 7-Feb-20
2.03.01 Cradle Carriage S315800 Track Modifications - Contract Award(s) L5 22-Nov-19
2.03.01 Cradle Carriage S316010 Completed - Track Modifications - Delivery Acceptance L5 24-Feb-20
2.03.04 End Caps/ Pole Tips S324500 End Caps/ Pole Tips - Design & Safety Reviews Complete Released for Production L5 23-Dec-19
2.03.04 End Caps/ Pole Tips S325200 End Caps/ Pole Tips - Contract Award(s) L4 12-May-20
2.03.04 End Caps/ Pole Tips S325410 Completed - End Caps/ Pole Tips - Delivery Acceptance L5 3-Nov-20
2.03.04 End Caps/ Pole Tips S325600 End Caps/ Pole Tips - Ready for Installation L3 17-Nov-20
2.03.05 CC Bridge, Mid Platforms and Access S326100 CC Bridge, Mid Platforms & Access - Design & Safety Reviews Complete Released for Production L4 14-Jul-20
2.03.05 CC Bridge, Mid Platforms and Access S326800 CC Bridge, Mid Platforms & Access - Contract Award(s) L4 16-Nov-20
2.03.05 CC Bridge, Mid Platforms and Access S327110 Completed - CC Bridge, Mid Platforms & Access - Delivery Acceptance L5 6-Apr-21
2.03.05 CC Bridge, Mid Platforms and Access S327300 CC Bridge, Mid Platforms & Access - Ready for Installation L4 13-Apr-21
Cost Drivers
April 9-11, 2019 sPHENIX Director's Review 21
• Fabrication of the Cradle Base
• Fabrication of Pole Tips
• Fabrication of Platforms
• Potential additional cost of rail modifications/replacement
Cost Development
• Bottom-Up Cost Estimate
• Based on Engineering Experience and Judgement
• Vetted in August 2018 by team of Senior Engineers from CAD and sPHENIX.
• Working on drawing package for Cradle/Carriage in Order to Solicit Budgetary Quotes.
April 9-11, 2019 sPHENIX Director's Review 22
April 9-11, 2019 sPHENIX Director's Review 23
Status
SCOPE OF REVIEW -• CARRIAGE BASE DESIGN• OUTER HCAL INTERFACE• ASSEMBLY/TRANSPORT SEQUENCE• TRANSPORT SYSTEM• ALIGNMENT SYSTEM• PLATFORM/ACCESS• MAGNET END CAPS• SYSTEM INTERFACES• SEISMIC SUPPORTS• STRUCTURAL ANALYSIS
• COMPLETE CARRIAGE ASSEMBLY• BOLTED BASE PLATFORM JOINT• XZ ALIGNMENT SYSTEM• TRACKS
• TRACK SYSTEM MODIFICATIONS
Other ParticipantssPHENIX Project Director and ManagerCAD EngineerssPHENIX Chief DesignersPHENIX EngineersQ/A, Safety, Office of Systems Integration
Engineering Design Review Completed - 2-11-19
Committee Members
J. Bowers – LLNL Senior Mechanical EngineerC. Folz – CAD Head, Facilities and Experimental SupportJ. Haggerty – sPHENIX Project ScientistJ. Mills, Chair – sPHENIX Project EngineerC. Pearson – CAD Senior Mechanical EngineerJ. Tuozzolo – CAD Chief Mechanical Engineer
Issues and Concerns
April 9-11, 2019 24sPHENIX Director's Review
• Potential increase in fabrication cost for cradle base.
• Potential rise in raw steel prices due to market fluctuations.
• May need major modifications or replacement of existing rails.
• Continue to value engineer, obtain budgetary quotes as soon as possible. Carry conservative Estimate Uncertainty until contract award.
• Monitor steel market for changes. Carry conservative Estimate Uncertainty until contract award.
• Fully evaluate existing rails and make determination of scope. Carry conservative Estimate Uncertainty until contract award and carry in Risk Registry.
Issues/Concerns Proposed Action/Resolution
Summary
• Design of cradle carriage is mature. Detail drawings for fabrication have been developed and are being checked. Will solicit budgetary quotes within next month.
• Design of Pole Tips/Platforms proceeding with detail design complete later this year.
• Will resolve rail modification/replacement within next 6 weeks
April 9-11, 2019 sPHENIX Director's Review 25
Back Up
April 9-11, 2019 26sPHENIX Director's Review
April 9-11, 2019 27sPHENIX Director's Review
2.03 Current Layout
April 9-11, 2019 28sPHENIX Director's Review
2.03.01 Cradle Base
April 9-11, 2019 29sPHENIX Director's Review
2.03.04 Pole Tips, 2.03.05 Platforms and Stairs