29
sPHENIX Director’s Review 2.03 – Cradle Carriage/Pole Tips/Platforms J. Mills April 9-11, 2019 Brookhaven National Laboratory April 9-11, 2019 sPHENIX Director's Review 1

2.03 Cradle Carriage/Pole Tips/Platforms J. Mills April 9

  • Upload
    others

  • View
    3

  • Download
    0

Embed Size (px)

Citation preview

Page 1: 2.03 Cradle Carriage/Pole Tips/Platforms J. Mills April 9

sPHENIX Director’s Review2.03 – Cradle Carriage/Pole Tips/Platforms

J. Mills

April 9-11, 2019

Brookhaven National Laboratory

April 9-11, 2019 sPHENIX Director's Review 1

Page 2: 2.03 Cradle Carriage/Pole Tips/Platforms J. Mills April 9

April 9-11, 2019 sPHENIX Director's Review 2

2.03.01 Drive, and Alignment

System

2.03.04 End Caps/Pole Tips

2.03.01 Carriage Assembly

2.03.01, .04, .05 CARRIAGE/CRADLE SYSTEM

2.03.05 Access Stairs

2.03.01 Seismic Supports

2.03.05 Top and Mid Platforms

2.03.05 Access Stairs

Page 3: 2.03 Cradle Carriage/Pole Tips/Platforms J. Mills April 9

April 9-11, 2019 sPHENIX Director's Review 3

End Caps/Pole Tips

110 TONS

Magnet and Detector Subsystems565 TONS

Carriage assembly130 TONS

CARRIAGE Support Preliminary Design Loads

Top and Mid Platforms

150 psf

• RACKS= 12 TONS• CRYO = 6 TONS• BALANCE:

• CABLES• UTILITIES• DEAD LOAD• PERSONNEL

50 TONS

(analysis also includes seismic loads)

Page 4: 2.03 Cradle Carriage/Pole Tips/Platforms J. Mills April 9

April 9-11, 2019 sPHENIX Director's Review 4

WORK BREAKDOWN STRUCTURE

2.03 CARRIAGE AND STRUCTURAL COMPONENTS

2.03.01 CARRIAGE

- CARRIAGE BASE ASSEMBLY

-TRANSPORT SYSTEM

-ALIGNMENT SYSTEM

-TRACK SYSTEM

-SEISMIC SUPPORTS

2.03.02 Inner Detector Structural Support

2.03.03 Barrel Steel/OHCal Sectors

2.03.04 CAPS/POLE TIPS

-MAGNETIC CAPS

-MOVABLE TO ALLOW ACCESS TO

DETECTOR

2.03.05 CC BRIDGE, MID PLATFORMS AND

ACCESS

- Platforms supporting electronics racks

- Means of egress (stairs/ladder)

Page 5: 2.03 Cradle Carriage/Pole Tips/Platforms J. Mills April 9

5

Collaborators

April 9-11, 2019 sPHENIX Director's Review

• Level 2 Manager – C. Pontieri (BNL-PH)

• Engineering

– J. Hock (BNL-CAD)

– J. Mills (BNL-CAD)

• Design Engineering

– J. Scheblein (BNL-PH)

– D. Puleo (BNL-CAD)

Page 6: 2.03 Cradle Carriage/Pole Tips/Platforms J. Mills April 9

Scope

• Perform engineering and design needed to assemble full specification and construction document packages necessary for fabrication.

• Develop appropriate interfaces with other subsystems.

• Perform design reviews in accordance with sPHENIX procedures.

• Develop bottom-up cost estimate and schedule for this subsystem.

• Fabricate necessary components needed to deliver subsystem to B1008 for assembly. Provide technical oversight during fabrication and assembly.

6April 9-11, 2019 sPHENIX Director's Review

Page 7: 2.03 Cradle Carriage/Pole Tips/Platforms J. Mills April 9

Carriage Base Assembly

April 9-11, 2019 sPHENIX Director's Review 7

STIFFENER BEAMS WITH DOUBLES

PEDESTAL SIDE SUPPORT

CARRIAGE PEDESTAL (Cradle)

WELDED BASE

TOP PEDESTAL SUPPORT

Page 8: 2.03 Cradle Carriage/Pole Tips/Platforms J. Mills April 9

CARRIAGE WELDED ½ BASE

April 9-11, 2019 sPHENIX Director's Review 8

ACCESS HOLE

HOLES FOR CONNECTING HALVES

1 ½” THICK TOP PLATE

6” THICK PLATE TO SUPPORT LIFTING JACKS

STIFFENERS FOR LONG ROLLER ASSEMBLY

FRAME IS MAINLY W14X193 BEAMS

STIFFENERS FOR SHORT ROLLER ASSEMBLY

Page 9: 2.03 Cradle Carriage/Pole Tips/Platforms J. Mills April 9

CARRIAGE BASE HALVES JOINED

April 9-11, 2019 sPHENIX Director's Review 9

STIFFENER BEAMS WITH DOUBLES

PEDESTAL SIDE SUPPORT

CARRIAGE PEDESTAL

CARRIAGE ASSEMBLY

TOP PEDESTAL SUPPORT

TOP JOINING DOUBLE AND BEAM

BOTTOM JOINING DOUBLE

Page 10: 2.03 Cradle Carriage/Pole Tips/Platforms J. Mills April 9

Production Drawings

April 9-11, 2019 sPHENIX Director's Review 10

• Preparing Detailed Production Drawings

• To be used for Fabrication and Budgetary Quotes

Base Assembly Drawing

Page 11: 2.03 Cradle Carriage/Pole Tips/Platforms J. Mills April 9

Production Drawings

April 9-11, 2019 sPHENIX Director's Review 11

Checking and Preparing for Budgetary Quotes

Page 12: 2.03 Cradle Carriage/Pole Tips/Platforms J. Mills April 9

PLATFORM/ACCESS

April 9-11, 2019 sPHENIX Director's Review 12

CARRIAGE SYSTEM

EASTSIDE ACCESS

ELECTRONIC RACKS

2ND TIER

STAIRS

WESTSIDE ACCESS

Page 13: 2.03 Cradle Carriage/Pole Tips/Platforms J. Mills April 9

SEISMIC SUPPORT

April 9-11, 2019 sPHENIX Director's Review 13

CARRIAGE SYSTEM

REMOVABLE PIN ALLOWS FOR ADJUSTMENT IN THE Z DIRECTION

CARRIAGE BRACKET FLOATS IN THEY DIRECTION

TOP BRACKET ALLOWS FOR ADJUSTMENT IN THE X DIRECTION

BASE BRACKET

X

Z

Y

Page 14: 2.03 Cradle Carriage/Pole Tips/Platforms J. Mills April 9

CARRIAGE FEA ANALYSIS CASE A1

April 9-11, 2019 sPHENIX Director's Review 14

MAX DEFLECTION = .26MAX VON MISES STRESS

MATERIAL: A36 STEELYIELD STRENGTH= 36.3 ksiULTIMATE STRENGTH=58 ksi

MAX STRESS= 16KSIAVERAGE STRESS= .57 KSI

SF=2.27

CARRIAGE ON JACKS¼ OF THE STRUCTURE WAS MODELED USING SYMMETRYLOADS:• WEIGHT OF STRUCTURE (GRAVITY)• WEIGHT OF DETECTOR (565 TONS)• WEIGHT OF PLATFORMS (150#/F2)

Page 15: 2.03 Cradle Carriage/Pole Tips/Platforms J. Mills April 9

CARRIAGE FEA ANALYSIS CASE A2

April 9-11, 2019 sPHENIX Director's Review 15

MAX VON MISES STRESS

MAX STRESS= 16KSIAVERAGE STRESS= .64 KSI

SF=2.27

MATERIAL: A36 STEELYIELD STRENGTH= 36.3 ksiULTIMATE STRENGTH=58 ksi

CARRIAGE ON LONG ROLLER ASSEMBLY (EAST-WEST TRANSLATION)¼ OF THE STRUCTURE WAS MODELED USING SYMMETRYLOADS:• WEIGHT OF STRUCTURE (GRAVITY)• WEIGHT OF DETECTOR (565 TONS)• WEIGHT OF PLATFORMS (150#/F2)

Page 16: 2.03 Cradle Carriage/Pole Tips/Platforms J. Mills April 9

April 9-11, 2019 sPHENIX Director's Review 16

MAIN MAGNET END CAPS

Page 17: 2.03 Cradle Carriage/Pole Tips/Platforms J. Mills April 9

UTILITIES INTERFACES

April 9-11, 2019 sPHENIX Director's Review 17

TOP PLATFORM ELECTRONIC INTERFACE:• FLOOR PANELS (26”BY 36”) ARE REMOVABLE TO ACCESS

WIRING• FLOOR PLATES CAN BE REMOVED W/O JEOPARDIZING

THE STABILITY OF THE STRUCTURE• DATA CABLE TRAY LOCATED JUST BELOW FLOOR, UNDER

EACH ENCLOSURE.• POWER CABLE TRAY IS JUST UNDER DATA TRAY, 8” REACH.• WATER COOLING PROVIDED FOR EACH ENCLOSURE.

DATA CABLE TRAY

POWER CABLE TRAY

WATER COOLING SUPPLY AND RETURN

PLATFORM FLOOR PANEL REMOVED

Page 18: 2.03 Cradle Carriage/Pole Tips/Platforms J. Mills April 9

Schedule Drivers

sPHENIX Director's Review 18April 9-11, 2019

2.03 CARRIAGE AND STRUCTURAL COMPONENTS

2.03.01 CARRIAGE

- Complete Engineering and Design

- Resolve issue related to tracks

2.03.04 CAPS/POLE TIPS

- Complete Engineering and Design

2.03.05 CC BRIDGE, MID PLATFORMS AND ACCESS

- Complete Engineering and Design

- Finalize means of egress with BNL Safety and Fire Protection

Page 19: 2.03 Cradle Carriage/Pole Tips/Platforms J. Mills April 9

Schedule Development

• Bottom-Up Approach to task and duration

• Engineers and Designers Participated, Buy-In From All

• Assistance from Project Management Professional

• Vetted by Project Management Professional

• Linking and Flow of Tasks Performed in Real Time with Team

April 9-11, 2019 sPHENIX Director's Review 19

Page 20: 2.03 Cradle Carriage/Pole Tips/Platforms J. Mills April 9

Milestones

April 9-11, 2019 20sPHENIX Director's Review

WBS Path WBS Name Activity ID Activity Name Milestone Level Date2.03.01 Cradle Carriage S310300 Carriage Cradle - Design & Safety Reviews Complete Released for Production L4 17-Oct-19

2.03.01 Cradle Carriage S311000 Carriage Cradle - Contract Award(s) L5 5-May-20

2.03.01 Cradle Carriage S311400 Carriage Cradle - Components Ready for Installation L3 24-Feb-21

2.03.01 Cradle Carriage S312900 CC Drive & Alignment System - Contract Award(s) L5 20-Aug-20

2.03.01 Cradle Carriage S313255 Completed - CC Drive & Alignment System - Delivery Acceptance - M&S L5 31-Dec-20

2.03.01 Cradle Carriage S314300 CC Seismic Restraints - Contract Award(s) L5 31-Oct-19

2.03.01 Cradle Carriage S314655 Completed - CC Seismic Restraints - Delivery Acceptance - M&S L5 7-Feb-20

2.03.01 Cradle Carriage S315800 Track Modifications - Contract Award(s) L5 22-Nov-19

2.03.01 Cradle Carriage S316010 Completed - Track Modifications - Delivery Acceptance L5 24-Feb-20

2.03.04 End Caps/ Pole Tips S324500 End Caps/ Pole Tips - Design & Safety Reviews Complete Released for Production L5 23-Dec-19

2.03.04 End Caps/ Pole Tips S325200 End Caps/ Pole Tips - Contract Award(s) L4 12-May-20

2.03.04 End Caps/ Pole Tips S325410 Completed - End Caps/ Pole Tips - Delivery Acceptance L5 3-Nov-20

2.03.04 End Caps/ Pole Tips S325600 End Caps/ Pole Tips - Ready for Installation L3 17-Nov-20

2.03.05 CC Bridge, Mid Platforms and Access S326100 CC Bridge, Mid Platforms & Access - Design & Safety Reviews Complete Released for Production L4 14-Jul-20

2.03.05 CC Bridge, Mid Platforms and Access S326800 CC Bridge, Mid Platforms & Access - Contract Award(s) L4 16-Nov-20

2.03.05 CC Bridge, Mid Platforms and Access S327110 Completed - CC Bridge, Mid Platforms & Access - Delivery Acceptance L5 6-Apr-21

2.03.05 CC Bridge, Mid Platforms and Access S327300 CC Bridge, Mid Platforms & Access - Ready for Installation L4 13-Apr-21

Page 21: 2.03 Cradle Carriage/Pole Tips/Platforms J. Mills April 9

Cost Drivers

April 9-11, 2019 sPHENIX Director's Review 21

• Fabrication of the Cradle Base

• Fabrication of Pole Tips

• Fabrication of Platforms

• Potential additional cost of rail modifications/replacement

Page 22: 2.03 Cradle Carriage/Pole Tips/Platforms J. Mills April 9

Cost Development

• Bottom-Up Cost Estimate

• Based on Engineering Experience and Judgement

• Vetted in August 2018 by team of Senior Engineers from CAD and sPHENIX.

• Working on drawing package for Cradle/Carriage in Order to Solicit Budgetary Quotes.

April 9-11, 2019 sPHENIX Director's Review 22

Page 23: 2.03 Cradle Carriage/Pole Tips/Platforms J. Mills April 9

April 9-11, 2019 sPHENIX Director's Review 23

Status

SCOPE OF REVIEW -• CARRIAGE BASE DESIGN• OUTER HCAL INTERFACE• ASSEMBLY/TRANSPORT SEQUENCE• TRANSPORT SYSTEM• ALIGNMENT SYSTEM• PLATFORM/ACCESS• MAGNET END CAPS• SYSTEM INTERFACES• SEISMIC SUPPORTS• STRUCTURAL ANALYSIS

• COMPLETE CARRIAGE ASSEMBLY• BOLTED BASE PLATFORM JOINT• XZ ALIGNMENT SYSTEM• TRACKS

• TRACK SYSTEM MODIFICATIONS

Other ParticipantssPHENIX Project Director and ManagerCAD EngineerssPHENIX Chief DesignersPHENIX EngineersQ/A, Safety, Office of Systems Integration

Engineering Design Review Completed - 2-11-19

Committee Members

J. Bowers – LLNL Senior Mechanical EngineerC. Folz – CAD Head, Facilities and Experimental SupportJ. Haggerty – sPHENIX Project ScientistJ. Mills, Chair – sPHENIX Project EngineerC. Pearson – CAD Senior Mechanical EngineerJ. Tuozzolo – CAD Chief Mechanical Engineer

Page 24: 2.03 Cradle Carriage/Pole Tips/Platforms J. Mills April 9

Issues and Concerns

April 9-11, 2019 24sPHENIX Director's Review

• Potential increase in fabrication cost for cradle base.

• Potential rise in raw steel prices due to market fluctuations.

• May need major modifications or replacement of existing rails.

• Continue to value engineer, obtain budgetary quotes as soon as possible. Carry conservative Estimate Uncertainty until contract award.

• Monitor steel market for changes. Carry conservative Estimate Uncertainty until contract award.

• Fully evaluate existing rails and make determination of scope. Carry conservative Estimate Uncertainty until contract award and carry in Risk Registry.

Issues/Concerns Proposed Action/Resolution

Page 25: 2.03 Cradle Carriage/Pole Tips/Platforms J. Mills April 9

Summary

• Design of cradle carriage is mature. Detail drawings for fabrication have been developed and are being checked. Will solicit budgetary quotes within next month.

• Design of Pole Tips/Platforms proceeding with detail design complete later this year.

• Will resolve rail modification/replacement within next 6 weeks

April 9-11, 2019 sPHENIX Director's Review 25

Page 26: 2.03 Cradle Carriage/Pole Tips/Platforms J. Mills April 9

Back Up

April 9-11, 2019 26sPHENIX Director's Review

Page 27: 2.03 Cradle Carriage/Pole Tips/Platforms J. Mills April 9

April 9-11, 2019 27sPHENIX Director's Review

2.03 Current Layout

Page 28: 2.03 Cradle Carriage/Pole Tips/Platforms J. Mills April 9

April 9-11, 2019 28sPHENIX Director's Review

2.03.01 Cradle Base

Page 29: 2.03 Cradle Carriage/Pole Tips/Platforms J. Mills April 9

April 9-11, 2019 29sPHENIX Director's Review

2.03.04 Pole Tips, 2.03.05 Platforms and Stairs