1094 Castle Park — 1094
20210812 - Site Visit No.04Created: 08-16-2021Creator: Gavin McCormack (@GMC)Status:Dates: 08-11-2021 - 08-13-2021
Recipients
Description
Purpose of Report: Site Walk undertaken Thursday 12/08/2021 @ 9.45am by DOB & GMcC of MDO to review general progress.
Weather: Dry
Location: Site & Basement
General Comments:1) Majority of rock breaking is now complete bar Zone 3.2) Basement slab is cast in Zone 1 & partially in Zone 2 with re-bar for rising elements in place.3) Rising elements in Zone 1 Block A such as the basement ramp flanking walls and basement stair 01 enclosure are cast with RWP ope'svisible. 4) Lean mix and re-bar installation to Zone 2 is on-going.5) It was noted that a safety net will need to be installed to the rock face at Block C to mitigate any risk of rock falls.
20210812 - Site Visit No.04 pg. 1 Created with Fieldwire on 08-16-2021
#57 - Exposed Cliff Face - Safety netting to be installed on rock face tomitigate the risk on rock falls, as discussed at last site visit 29/07.Priority 2 | David O'brien | Rectify & ProgressPlan: 1094-MDO-XX-RF-DR-A-01001 PROPOSED SITE LAYOUT PLANCreated 08-12-2021
Task messages (time in IST)David O'brien Photo 1 12 Aug 10:06 AMDavid O'brien Photo 2 12 Aug 10:06 AMDavid O'brien Protection? 12 Aug 10:06 AM
Photos
1 2
20210812 - Site Visit No.04 pg. 2 Created with Fieldwire on 08-16-2021
#55 - Core C - No starter bars evident for bin store lobby wall orseparating wall between bin store and telecoms room, TWL to advisehow this wall will be constructed.Priority 2 | David O'brien | Rectify & ProgressPlan: 1094-MDO-ZZ-B1-DR-A-02000Created 08-12-2021
Task messages (time in IST)David O'brien Photo 1 12 Aug 10:02 AMDavid O'brien Wall missing? 12 Aug 10:02 AM
Photos
1
20210812 - Site Visit No.04 pg. 3 Created with Fieldwire on 08-16-2021
#56 - Plant Room - No drainage gully visible, discussion held with JKwho confirmed that a gully is in place but may have been covered atthe time of the site visit, MDO to carry out a follow up inspectionduring the next site visit.Priority 2 | David O'brien | Rectify & ProgressPlan: 1094-MDO-ZZ-B1-DR-A-02000Created 08-12-2021
Task messages (time in IST)David O'brien Photo 1 12 Aug 10:05 AMDavid O'brien Photo 2 12 Aug 10:05 AMDavid O'brien Drainage? 12 Aug 10:05 AM
Photos
1 2
20210812 - Site Visit No.04 pg. 4 Created with Fieldwire on 08-16-2021
#44 - Tower Crane 02 has been erected on site.Priority 3 | David O'brien | ObservationPlan: 1094-MDO-XX-RF-DR-A-01001 PROPOSED SITE LAYOUT PLANCreated 08-12-2021
Task messages (time in IST)David O'brien Photo 1 12 Aug 09:51 AMDavid O'brien Photo 2 12 Aug 09:51 AMDavid O'brien TC02 up 12 Aug 09:51 AM
Photos
1 2
20210812 - Site Visit No.04 pg. 5 Created with Fieldwire on 08-16-2021
#49 - Opes for slung drainage to underside of Ground floor slab arevisible in ramp flanking walls.Priority 3 | David O'brien | ObservationPlan: 1094-MDO-ZZ-B1-DR-A-02000Created 08-12-2021
Task messages (time in IST)David O'brien Photo 1 12 Aug 09:58 AM
Photos
1
20210812 - Site Visit No.04 pg. 6 Created with Fieldwire on 08-16-2021
#45 - Zone 3 earth clearance and rock breaking ongoing.Priority 3 | David O'brien | ObservationPlan: 1094-MDO-XX-RF-DR-A-01001 PROPOSED SITE LAYOUT PLANCreated 08-12-2021
Task messages (time in IST)David O'brien Photo 1 12 Aug 09:52 AMDavid O'brien Zone 3 strip out ongoing 12 Aug 09:52 AMDavid O'brien Photo 2 12 Aug 09:53 AMDavid O'brien Photo 3 12 Aug 09:53 AMDavid O'brien Photo 4 12 Aug 09:53 AMDavid O'brien Photo 5 12 Aug 09:53 AM
Photos
1 2 3
4 5
20210812 - Site Visit No.04 pg. 7 Created with Fieldwire on 08-16-2021
#48 - Basement car park ramp walls cast on site, RWP opes are visible.Priority 3 | David O'brien | ObservationPlan: 1094-MDO-ZZ-B1-DR-A-02000Created 08-12-2021
Task messages (time in IST)David O'brien Photo 1 12 Aug 09:56 AMDavid O'brien Photo 2 12 Aug 09:56 AM
Photos
1 2
20210812 - Site Visit No.04 pg. 8 Created with Fieldwire on 08-16-2021
#59 - Core B - Upstands are cast in place and starter bars are in placefore rising elements.Priority 3 | David O'brien | ObservationPlan: 1094-MDO-ZZ-B1-DR-A-02000Created 08-12-2021
Task messages (time in IST)David O'brien Photo 1 12 Aug 10:08 AMDavid O'brien Photo 2 12 Aug 10:08 AMDavid O'brien Photo 3 12 Aug 10:08 AMDavid O'brien Photo 4 12 Aug 10:08 AMDavid O'brien All looks good 12 Aug 10:08 AM
Photos
1 2 3
4
20210812 - Site Visit No.04 pg. 9 Created with Fieldwire on 08-16-2021
#50 - Rising elements for basement stair 01 are now cast, starter barsare in place for core walls.Priority 3 | David O'brien | ObservationPlan: 1094-MDO-ZZ-B1-DR-A-02000Created 08-12-2021
Task messages (time in IST)David O'brien Photo 1 12 Aug 09:59 AMDavid O'brien Photo 2 12 Aug 09:59 AMDavid O'brien Photo 3 12 Aug 09:59 AMDavid O'brien Progress 12 Aug 09:59 AM
Photos
1 2 3
20210812 - Site Visit No.04 pg. 10 Created with Fieldwire on 08-16-2021
#64 - Residents Club - Rock breaking to residents club, MurphySheanon to review landscaping levels at a later date.Priority 3 | David O'brien | ObservationPlan: 1094-MDO-XX-RF-DR-A-01001 PROPOSED SITE LAYOUT PLANCreated 08-12-2021
Task messages (time in IST)David O'brien Photo 1 12 Aug 10:12 AMDavid O'brien Photo 2 12 Aug 10:12 AMDavid O'brien Photo 3 12 Aug 10:12 AMDavid O'brien Photo 4 12 Aug 10:12 AMDavid O'brien Excavation removed 12 Aug 10:12 AM
Photos
1 2 3
4
20210812 - Site Visit No.04 pg. 11 Created with Fieldwire on 08-16-2021
#54 - Core C wall change captured following DAC update.Priority 3 | David O'brien | ObservationPlan: 1094-MDO-ZZ-B1-DR-A-02000Created 08-12-2021
Task messages (time in IST)David O'brien Photo 1 12 Aug 10:01 AMDavid O'brien Change captured 12 Aug 10:01 AM
Photos
1
20210812 - Site Visit No.04 pg. 12 Created with Fieldwire on 08-16-2021
#52 - Upstands to Core A in place, re-bar in place fore core walls.Priority 3 | David O'brien | ObservationPlan: 1094-MDO-ZZ-B1-DR-A-02000Created 08-12-2021
Task messages (time in IST)David O'brien Photo 1 12 Aug 10:00 AMDavid O'brien Photo 2 12 Aug 10:00 AMDavid O'brien Review location of wall 12 Aug 10:00 AM
Photos
1 2
20210812 - Site Visit No.04 pg. 13 Created with Fieldwire on 08-16-2021
#61 - Core A - Upstands are cat in place and re-bar is in place for risingelements.Priority 3 | David O'brien | ObservationPlan: 1094-MDO-ZZ-B1-DR-A-02000Created 08-12-2021
Task messages (time in IST)David O'brien Photo 1 12 Aug 10:09 AMDavid O'brien Photo 2 12 Aug 10:09 AMDavid O'brien All looks good 12 Aug 10:09 AM
Photos
1 2
20210812 - Site Visit No.04 pg. 14 Created with Fieldwire on 08-16-2021
#60 - Basement Stair 02 - Starter bars in place fore core risingelements, drainage gully viable.Priority 3 | Gavin McCormack | ObservationPlan: 1094-MDO-ZZ-B1-DR-A-02000Created 08-12-2021
Task messages (time in IST)Gavin McCormack Photo 1 12 Aug 10:09 AMGavin McCormack Photo 2 12 Aug 10:09 AM
Photos
1 2
20210812 - Site Visit No.04 pg. 15 Created with Fieldwire on 08-16-2021
#47 - East flanking wall to car park ramp cast, opes for RWP's visible.Priority 3 | Gavin McCormack | ObservationPlan: 1094-MDO-ZZ-B1-DR-A-02000Created 08-12-2021
Task messages (time in IST)Gavin McCormack Photo 1 12 Aug 09:56 AMGavin McCormack Photo 2 12 Aug 09:56 AM
Photos
1 2
20210812 - Site Visit No.04 pg. 16 Created with Fieldwire on 08-16-2021
#51 - Concrete rising elements to basement stair 1 cast, RWP opes andgully locations visible.Priority 3 | Gavin McCormack | ObservationPlan: 1094-MDO-ZZ-B1-DR-A-02000Created 08-12-2021
Task messages (time in IST)Gavin McCormack Photo 1 12 Aug 09:59 AMGavin McCormack Photo 2 12 Aug 09:59 AMGavin McCormack Photo 3 12 Aug 09:59 AM
Photos
1 2 3
20210812 - Site Visit No.04 pg. 17 Created with Fieldwire on 08-16-2021
#58 - Core B - Starter bars in place for rising elements to be cast,drainage locations are visible.Priority 3 | Gavin McCormack | ObservationPlan: 1094-MDO-ZZ-B1-DR-A-02000Created 08-12-2021
Task messages (time in IST)Gavin McCormack Photo 1 12 Aug 10:06 AMGavin McCormack Photo 2 12 Aug 10:06 AM
Photos
1 2
20210812 - Site Visit No.04 pg. 18 Created with Fieldwire on 08-16-2021
#53 - Core A rising elements - re-bar in place for core wall to be cast.Priority 3 | Gavin McCormack | ObservationPlan: 1094-MDO-ZZ-B1-DR-A-02000Created 08-12-2021
Task messages (time in IST)Gavin McCormack Photo 1 12 Aug 10:00 AMGavin McCormack Photo 2 12 Aug 10:00 AM
Photos
1 2
20210812 - Site Visit No.04 pg. 19 Created with Fieldwire on 08-16-2021
#63 - Residents Club - Rock breaking to residents club, MurphySheanon to review landscaping levels at a later date.Priority 3 | Gavin McCormack | ObservationPlan: 1094-MDO-ZZ-00-DR-A-02001Created 08-12-2021
Task messages (time in IST)Gavin McCormack Photo 1 12 Aug 10:11 AMGavin McCormack Photo 2 12 Aug 10:11 AMGavin McCormack Photo 3 12 Aug 10:11 AM
Photos
1 2 3
20210812 - Site Visit No.04 pg. 20 Created with Fieldwire on 08-16-2021