1303
Standard Specifications for Road, Bridge, and Municipal Construction 2020 M 41-10

2020 Standard Specifications · Title: 2020 Standard Specifications Created Date: 8/28/2019 11:36:00 AM

  • Upload
    others

  • View
    0

  • Download
    0

Embed Size (px)

Citation preview

  • 2020 Standard Specifications M 41-10 Page 1

    StandardSpecificationsfor Road, Bridge, and Municipal Construction

    2020M 41-10

  • Page 2 2020 Standard Specifications M 41-10

    Ordering Information

    The 2020 Standard Specifications can be purchased from the Washington State Department of Printing website at myprint.wa.gov.

    Note: This publication is not for resale.

    The 2020 Standard Specifications can be also downloaded, free of charge, from the following web page at www.wsdot.wa.gov/publications/manuals/m41-10.htm.

    Americans with Disabilities Act (ADA) Information

    Title VI Notice to Public It is the Washington State Department of Transportation’s (WSDOT) policy to assure that no person shall, on the grounds of race, color, national origin or sex, as provided by Title VI of the Civil Rights Act of 1964, be excluded from participation in, be denied the benefits of, or be otherwise discriminated against under any of its federally funded programs and activities. Any person who believes his/her Title VI protection has been violated, may file a complaint with WSDOT’s Office of Equal Opportunity (OEO). For additional information regarding Title VI complaint procedures and/or information regarding our non-discrimination obligations, please contact OEO’s Title VI Coordinator at 360-705-7090.

    http://myprint.wa.govwww.wsdot.wa.gov/publications/manuals/m41-10.htm

  • 2020 Standard Specifications M 41-10 Page 3

    Foreword

    These Standard Specifications for Road, Bridge, and Municipal Construction have been developed to serve as a baseline for the work delivered to the public by the Washington State Department of Transportation (WSDOT). The Standard Specifications are incorporated into the written agreement (Contract) between WSDOT as Contracting Agency and the Contractor, except where the Contract indicates that a particular specification has been amended or replaced with a special provision to resolve project-specific issues. The decision to amend or replace any standard specification with a special provision is made during the design process and is based upon the sound engineering judgment of the project designer.

    These Standard Specifications reflect years of refinement through the literally hundreds of projects the Department delivers each year. In addition, the standards are the result of countless hours of development and review by both our internal WSDOT staff as well as our industry partners through the joint WSDOT/Associated General Contractors’ Standing Committees.

    Finally, these standards reflect the contracting philosophy and balance of risk-allocation that the Department has adopted through the years. We believe that this balance of risks provides us the lowest final cost solution to our transportation needs. For example, shifting risk to the Contractor can provide more certainty on final cost, but may result in higher initial cost. On the other hand, accepting more risk by the owner can result in lower initial costs, but less certainty on the final cost. We at the Department of Transportation believe that we have reached the optimum point of balance for risk, and we will continue to consider this balance on all future specification revisions.

    The language above indicates that these specifications are to be used only as a guideline during the design process, and that is true. Once they have been incorporated into a Contract, however, they become the legal and enforceable language of that Contract. The Standard Specifications, and the Project Special Provisions, along with any attachments in the Contract documents, define a Contract and are no longer seen as guidelines. Rather, they are the written agreement, subject to revision only through the change order process.

    This preface is for informational purposes only and is not to be used to interpret or affect the terms.

    Robert E. Christopher, P.E. State Construction Engineer

  • Page 4 2020 Standard Specifications M 41-10

    Contents

    Division 1 General Requirements

    Division 2 Earthwork

    Division 3 Aggregate Production and Acceptance

    Division 4 Bases

    Division 5 Surface Treatments and Pavements

    Division 6 Structures

    Division 7 Drainage Structures, Storm Sewers, Sanitary Sewers, Water Mains, and Conduits

    Division 8 Miscellaneous Construction

    Division 9 Materials

  • 2020 Standard Specifications M 41-10 Page 5

    Contents

    Division 1 General Requirements . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-1

    1-01 Definitions and Terms . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-11-01.1 General . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-1

    1-01.2 Abbreviations . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-11-01.2(1) Associations and Miscellaneous . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-11-01.2(2) Items of Work and Units of Measurement . . . . . . . . . . . . . . . . . . . . . . . 1-3

    1-01.3 Definitions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-4

    1-02 Bid Procedures and Conditions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-101-02.1 Prequalification of Bidders . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-10

    1-02.2 Plans and Specifications . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-11

    1-02.3 Estimated Quantities . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-12

    1-02.4 Examination of Plans, Specifications, and Site of Work . . . . . . . . . . . . . . . . . . . . . . . . 1-121-02.4(1) General . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-121-02.4(2) Subsurface Information . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-14

    1-02.5 Proposal Forms . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-15

    1-02.6 Preparation of Proposal . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-15

    1-02.7 Bid Deposit . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-16

    1-02.8 Noncollusion Declaration and Lobbying Certification . . . . . . . . . . . . . . . . . . . . . . . . . 1-171-02.8(1) Noncollusion Declaration . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-171-02.8(2) Lobbying Certification . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-17

    1-02.9 Delivery of Proposal . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-18

    1-02.10 Withdrawing, Revising, or Supplementing Proposal . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-19

    1-02.11 Combination and Multiple Proposals . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-19

    1-02.12 Public Opening of Proposals . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-20

    1-02.13 Irregular Proposals . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-20

    1-02.14 Disqualification of Bidders . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-21

    1-02.15 Pre-Award Information . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-22

    1-03 Award and Execution of Contract . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-231-03.1 Consideration of Bids . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-23

    1-03.1(1) Identical Bid Totals . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-23

    1-03.2 Award of Contract . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-24

    1-03.3 Execution of Contract . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-24

    1-03.4 Contract Bond . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-24

    1-03.5 Failure to Execute Contract . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-25

    1-03.6 Return of Bid Deposit . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-25

    1-03.7 Judicial Review . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-25

  • Page 6 2020 Standard Specifications M 41-10

    Contents

    1-04 Scope of the Work . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-261-04.1 Intent of the Contract . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-26

    1-04.1(1) Bid Items Included in the Proposal . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-261-04.1(2) Bid Items Not Included in the Proposal . . . . . . . . . . . . . . . . . . . . . . . . 1-26

    1-04.2 Coordination of Contract Documents, Plans, Special Provisions, Specifications, and Addenda . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-26

    1-04.3 Reference Information . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-27

    1-04.4 Changes . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-271-04.4(1) Minor Changes . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-291-04.4(2) Value Engineering Change Proposal (VECP) . . . . . . . . . . . . . . . . . . . . 1-29

    1-04.5 Procedure and Protest by the Contractor . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-33

    1-04.6 Variation in Estimated Quantities . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-34

    1-04.7 Differing Site Conditions (Changed Conditions) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-35

    1-04.8 Progress Estimates and Payments . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-36

    1-04.9 Use of Buildings or Structures . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-36

    1-04.10 Use of Materials Found on the Project . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-36

    1-04.11 Final Cleanup . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-37

    1-05 Control of Work . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-381-05.1 Authority of the Engineer . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-38

    1-05.2 Authority of Assistants and Inspectors . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-39

    1-05.3 Working Drawings . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-39

    1-05.4 Conformity With and Deviations From Plans and Stakes . . . . . . . . . . . . . . . . . . . . . . . 1-40

    1-05.5 Tolerances . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-41

    1-05.6 Inspection of Work and Materials . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-42

    1-05.7 Removal of Defective and Unauthorized Work . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-43

    1-05.8 Vacant . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-43

    1-05.9 Equipment . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-43

    1-05.10 Guarantees . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-44

    1-05.11 Final Inspection . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-44

    1-05.12 Final Acceptance . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-44

    1-05.13 Superintendents, Labor, and Equipment of Contractor . . . . . . . . . . . . . . . . . . . . . . . . 1-451-05.13(1) Emergency Contact List . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-46

    1-05.14 Cooperation With Other Contractors . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-46

    1-05.15 Method of Serving Notices . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-46

  • 2020 Standard Specifications M 41-10 Page 7

    Contents

    1-06 Control of Material . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-471-06.1 Approval of Materials Prior to Use . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-47

    1-06.1(1) Qualified Products List (QPL) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-471-06.1(2) Request for Approval of Material (RAM). . . . . . . . . . . . . . . . . . . . . . . . 1-481-06.1(3) Aggregate Source Approval (ASA) Database . . . . . . . . . . . . . . . . . . . . 1-481-06.1(4) Fabrication Inspection Expense . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-49

    1-06.2 Acceptance of Materials . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-501-06.2(1) Samples and Tests for Acceptance . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-501-06.2(2) Statistical Evaluation of Materials for Acceptance . . . . . . . . . . . . . . . 1-51

    1-06.3 Manufacturer’s Certificate of Compliance . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-57

    1-06.4 Handling and Storing Materials . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-58

    1-06.5 Owners Manuals and Operating Instructions. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-58

    1-06.6 Recycled Materials . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-58

    1-07 Legal Relations and Responsibilities to the Public . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-601-07.1 Laws to be Observed . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-60

    1-07.2 State Taxes . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-611-07.2(1) State Sales Tax: WAC 458-20-171 – Use Tax . . . . . . . . . . . . . . . . . . . 1-611-07.2(2) State Sales Tax: WAC 458-20-170 – Retail Sales Tax . . . . . . . . . . . . . 1-621-07.2(3) Services . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-62

    1-07.3 Fire Prevention and Merchantable Timber Requirements . . . . . . . . . . . . . . . . . . . . . . 1-621-07.3(1) Fire Prevention Control and Countermeasures Plan . . . . . . . . . . . . . 1-621-07.3(2) Merchantable Timber Requirements . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-63

    1-07.4 Sanitation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-641-07.4(1) General . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-641-07.4(2) Health Hazards . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-64

    1-07.5 Environmental Regulations . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-641-07.5(1) General . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-641-07.5(2) State Department of Fish and Wildlife . . . . . . . . . . . . . . . . . . . . . . . . . 1-641-07.5(3) State Department of Ecology . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-651-07.5(4) Air Quality . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-661-07.5(5) U.S. Army Corps of Engineers . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-661-07.5(6) U.S. Fish/Wildlife Services and National Marine Fisheries Service . 1-66

    1-07.6 Permits and Licenses . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-66

    1-07.7 Load Limits . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-671-07.7(1) General . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-671-07.7(2) Load-Limit Restrictions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-68

  • Page 8 2020 Standard Specifications M 41-10

    Contents

    1-07.8 High-Visibility Apparel . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-701-07.8(1) Traffic Control Personnel . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-701-07.8(2) Non-Traffic Control Personnel . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-71

    1-07.9 Wages . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-711-07.9(1) General . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-711-07.9(2) Posting Notices . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-731-07.9(3) Apprentices . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-741-07.9(4) Disputes . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-741-07.9(5) Required Documents . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-741-07.9(6) Audits . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-75

    1-07.10 Worker’s Benefits . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-75

    1-07.11 Requirements for Nondiscrimination . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-761-07.11(1) General Application . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-761-07.11(2) Contractual Requirements . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-761-07.11(3) Equal Employment Opportunity Officer . . . . . . . . . . . . . . . . . . . . . . . . 1-791-07.11(4) Dissemination of Policy . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-791-07.11(5) Sanctions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-801-07.11(6) Incorporation of Provisions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-801-07.11(7) Vacant. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-811-07.11(8) Vacant. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-811-07.11(9) Subcontracting, Procurement of Materials, and Leasing of

    Equipment . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-811-07.11(10) Records and Reports . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-81

    1-07.12 Federal Agency Inspection. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-82

    1-07.13 Contractor’s Responsibility for Work . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-821-07.13(1) General . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-821-07.13(2) Relief of Responsibility for Completed Work . . . . . . . . . . . . . . . . . . . . 1-831-07.13(3) Relief of Responsibility for Damage by Public Traffic . . . . . . . . . . . . . 1-831-07.13(4) Repair of Damage . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-84

    1-07.14 Responsibility for Damage . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-84

    1-07.15 Temporary Water Pollution Prevention . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-861-07.15(1) Spill Prevention, Control, and Countermeasures Plan . . . . . . . . . . . . 1-86

    1-07.16 Protection and Restoration of Property . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-901-07.16(1) Private/Public Property . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-901-07.16(2) Vegetation Protection and Restoration . . . . . . . . . . . . . . . . . . . . . . . . . 1-911-07.16(3) Fences, Mailboxes, Incidentals . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-921-07.16(4) Archaeological and Historical Objects . . . . . . . . . . . . . . . . . . . . . . . . . 1-921-07.16(5) Payment . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-93

  • 2020 Standard Specifications M 41-10 Page 9

    Contents

    1-07.17 Utilities and Similar Facilities . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-931-07.17(1) Utility Construction, Removal, or Relocation by the Contractor . . . . 1-931-07.17(2) Utility Construction, Removal, or Relocation by Others . . . . . . . . . . 1-94

    1-07.18 Public Liability and Property Damage Insurance . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-94

    1-07.19 Gratuities . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-97

    1-07.20 Patented Devices, Materials, and Processes. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-98

    1-07.21 Rock Drilling Safety Requirements . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-98

    1-07.22 Use of Explosives . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-98

    1-07.23 Public Convenience and Safety. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-981-07.23(1) Construction Under Traffic . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-991-07.23(2) Construction and Maintenance of Detours . . . . . . . . . . . . . . . . . . . .1-101

    1-07.24 Rights of Way . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .1-102

    1-07.25 Opening of Sections to Traffic . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .1-102

    1-07.26 Personal Liability of Public Officers . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .1-102

    1-07.27 No Waiver of State’s Legal Rights . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .1-103

    1-08 Prosecution and Progress . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .1-1041-08.1 Subcontracting . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .1-104

    1-08.1(1) Prompt Payment, Subcontract Completion and Return of Retainage Withheld . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .1-106

    1-08.2 Assignment . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .1-108

    1-08.3 Progress Schedule . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .1-1081-08.3(1) General Requirements . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .1-1081-08.3(2) Progress Schedule Types . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .1-1091-08.3(3) Schedule Updates . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .1-1101-08.3(4) Measurement . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .1-1111-08.3(5) Payment . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .1-111

    1-08.4 Prosecution of Work . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .1-111

    1-08.5 Time for Completion . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .1-112

    1-08.6 Suspension of Work . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .1-113

    1-08.7 Maintenance During Suspension . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .1-115

    1-08.8 Extensions of Time . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .1-115

    1-08.9 Liquidated Damages . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .1-118

    1-08.10 Termination of Contract . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .1-1191-08.10(1) Termination for Default . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .1-1191-08.10(2) Termination for Public Convenience . . . . . . . . . . . . . . . . . . . . . . . . . .1-1211-08.10(3) Termination for Public Convenience Payment Request . . . . . . . . . .1-1211-08.10(4) Payment for Termination for Public Convenience . . . . . . . . . . . . . . .1-1211-08.10(5) Responsibility of the Contractor and Surety . . . . . . . . . . . . . . . . . . .1-121

  • Page 10 2020 Standard Specifications M 41-10

    Contents

    1-09 Measurement and Payment . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .1-1221-09.1 Measurement of Quantities . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .1-122

    1-09.2 Weighing Equipment . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .1-1241-09.2(1) General Requirements for Weighing Equipment . . . . . . . . . . . . . . . .1-1241-09.2(2) Specific Requirements for Batching Scales . . . . . . . . . . . . . . . . . . . .1-1251-09.2(3) Specific Requirements for Platform Scales . . . . . . . . . . . . . . . . . . . . .1-1261-09.2(4) Specific Requirements for Belt Conveyor Scales . . . . . . . . . . . . . . . .1-1261-09.2(5) Measurement . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .1-1261-09.2(6) Payment . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .1-127

    1-09.3 Scope of Payment . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .1-128

    1-09.4 Equitable Adjustment . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .1-129

    1-09.5 Deleted or Terminated Work . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .1-129

    1-09.6 Force Account . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .1-130

    1-09.7 Mobilization . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .1-135

    1-09.8 Payment for Material on Hand . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .1-135

    1-09.9 Payments . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .1-1361-09.9(1) Retainage . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .1-137

    1-09.10 Payment for Surplus Processed Materials . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .1-138

    1-09.11 Disputes and Claims . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .1-1391-09.11(1) Disputes Review Board . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .1-1391-09.11(2) Claims . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .1-1421-09.11(3) Time Limitation and Jurisdiction . . . . . . . . . . . . . . . . . . . . . . . . . . . . .1-145

    1-09.12 Audits . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .1-1451-09.12(1) General . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .1-1451-09.12(2) Claims . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .1-1461-09.12(3) Required Documents for Audits . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .1-146

    1-09.13 Claims Resolution . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .1-1471-09.13(1) General . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .1-1471-09.13(2) Nonbinding Alternative Disputes Resolution (ADR) . . . . . . . . . . . . .1-1471-09.13(3) Claims $250,000 or Less . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .1-1481-09.13(4) Claims in Excess of $250,000 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .1-150

  • 2020 Standard Specifications M 41-10 Page 11

    Contents

    1-10 Temporary Traffic Control . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .1-1511-10.1 General . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .1-151

    1-10.1(1) Materials . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .1-1511-10.1(2) Description . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .1-151

    1-10.2 Traffic Control Management . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .1-1531-10.2(1) General . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .1-1531-10.2(2) Traffic Control Plans . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .1-1551-10.2(3) Conformance to Established Standards . . . . . . . . . . . . . . . . . . . . . . .1-156

    1-10.3 Traffic Control Labor, Procedures, and Devices . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .1-1571-10.3(1) Traffic Control Labor . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .1-1571-10.3(2) Traffic Control Procedures . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .1-1581-10.3(3) Traffic Control Devices . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .1-161

    1-10.4 Measurement . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .1-1651-10.4(1) Lump Sum Bid for Project (No Unit Items) . . . . . . . . . . . . . . . . . . . . .1-1651-10.4(2) Item Bids With Lump Sum for Incidentals . . . . . . . . . . . . . . . . . . . . .1-1651-10.4(3) Reinstating Unit Items With Lump Sum Traffic Control . . . . . . . . . .1-1661-10.4(4) Owner-Provided Resources . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .1-166

    1-10.5 Payment . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .1-1671-10.5(1) Lump Sum Bid for Project (No Unit Items) . . . . . . . . . . . . . . . . . . . . .1-1671-10.5(2) Item Bids With Lump Sum for Incidentals . . . . . . . . . . . . . . . . . . . . .1-1671-10.5(3) Reinstating Unit Items With Lump Sum Traffic Control . . . . . . . . . .1-168

  • Page 12 2020 Standard Specifications M 41-10

    Contents

    Division 2 Earthwork . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-1

    2-01 Clearing, Grubbing, and Roadside Cleanup . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-12-01.1 Description . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-1

    2-01.2 Disposal of Usable Material and Debris . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-12-01.2(1) Disposal Method No. 1 – Open Burning . . . . . . . . . . . . . . . . . . . . . . . . 2-12-01.2(2) Disposal Method No. 2 – Waste Site . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-12-01.2(3) Disposal Method No. 3 – Chipping . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-2

    2-01.3 Construction Requirements. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-22-01.3(1) Clearing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-22-01.3(2) Grubbing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-22-01.3(3) Vacant. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-32-01.3(4) Roadside Cleanup . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-3

    2-01.4 Measurement . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-3

    2-01.5 Payment . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-4

    2-02 Removal of Structures and Obstructions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-52-02.1 Description . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-5

    2-02.2 Vacant . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-5

    2-02.3 Construction Requirements. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-52-02.3(1) Removal of Foundations . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-52-02.3(2) Removal of Bridges, Box Culverts, and Other Drainage Structures . . 2-52-02.3(3) Removal of Pavement, Sidewalks, Curbs, and Gutters . . . . . . . . . . . . . 2-7

    2-02.4 Vacant . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-7

    2-02.5 Payment . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-7

    2-03 Roadway Excavation and Embankment . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-82-03.1 Description . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-8

    2-03.2 Vacant . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-8

    2-03.3 Construction Requirements. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-82-03.3(1) Widening of Cuts . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-82-03.3(2) Rock Cuts . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-92-03.3(3) Excavation Below Subgrade . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-122-03.3(4) Sluicing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-122-03.3(5) Slope Treatment . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-122-03.3(6) Deposit of Rock for the Contracting Agency’s Use . . . . . . . . . . . . . . . 2-132-03.3(7) Disposal of Surplus Material . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-132-03.3(8) Wasting Material . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-142-03.3(9) Roadway Ditches . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-14

  • 2020 Standard Specifications M 41-10 Page 13

    Contents

    2-03.3(10) Selected Material . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-142-03.3(11) Slides . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-152-03.3(12) Overbreak . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-152-03.3(13) Borrow . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-152-03.3(14) Embankment Construction . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-162-03.3(15) Aeration . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-232-03.3(16) End Slopes . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-242-03.3(17) Snow Removal . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-242-03.3(18) Stepped Slope Construction . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-252-03.3(19) Removal of Pavement, Sidewalks, Curbs, and Gutters . . . . . . . . . . . . 2-25

    2-03.4 Measurement . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-25

    2-03.5 Payment . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-26

    2-04 Haul . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-292-04.1 Description . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-29

    2-04.2 Vacant . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-29

    2-04.3 Vacant . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-29

    2-04.4 Measurement . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-29

    2-04.5 Payment . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-30

    2-05 Vacant . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-31

    2-06 Subgrade Preparation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-322-06.1 Description . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-32

    2-06.2 Vacant . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-32

    2-06.3 Construction Requirements. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-322-06.3(1) Subgrade for Surfacing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-322-06.3(2) Subgrade for Pavement . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-33

    2-06.4 Vacant . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-33

    2-06.5 Measurement and Payment . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-332-06.5(1) Subgrade Constructed Under Same Contract . . . . . . . . . . . . . . . . . . . 2-332-06.5(2) Subgrade Not Constructed Under Same Contract . . . . . . . . . . . . . . . 2-33

    2-07 Watering. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-352-07.1 Description . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-35

    2-07.2 Vacant . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-35

    2-07.3 Construction Requirements. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-35

    2-07.4 Measurement . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-35

    2-07.5 Payment . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-35

    2-08 Vacant . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-36

  • Page 14 2020 Standard Specifications M 41-10

    Contents

    2-09 Structure Excavation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-372-09.1 Description . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-37

    2-09.2 Materials . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-37

    2-09.3 Construction Requirements. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-372-09.3(1) General Requirements . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-372-09.3(2) Classification of Structure Excavation . . . . . . . . . . . . . . . . . . . . . . . . . . 2-402-09.3(3) Construction Requirements, Structure Excavation, Class A . . . . . . . 2-412-09.3(4) Construction Requirements, Structure Excavation, Class B . . . . . . . 2-47

    2-09.4 Measurement . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-47

    2-09.5 Payment . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-49

    2-10 Vacant . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-51

    2-11 Trimming and Cleanup . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-522-11.1 Description . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-52

    2-11.2 Vacant . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-52

    2-11.3 Construction Requirements. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-52

    2-11.4 Vacant . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-52

    2-11.5 Payment . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-52

    2-12 Construction Geosynthetic . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-532-12.1 Description . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-53

    2-12.2 Materials . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-53

    2-12.3 Construction Requirements. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-532-12.3(1) Underground Drainage . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-542-12.3(2) Separation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-542-12.3(3) Soil Stabilization . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-552-12.3(4) Permanent Erosion Control and Ditch Lining . . . . . . . . . . . . . . . . . . . 2-55

    2-12.4 Measurement . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-56

    2-12.5 Payment . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-56

  • 2020 Standard Specifications M 41-10 Page 15

    Contents

    Division 3 Aggregate Production and Acceptance . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-1

    3-01 Production From Quarry and Pit Sites . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-13-01.1 Description . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-1

    3-01.2 Material Sources, General Requirements . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-13-01.2(1) Approval of Source . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-13-01.2(2) Preparation of Site . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-13-01.2(3) Stripping Quarries and Pits . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-23-01.2(4) Production Requirements . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-23-01.2(5) Final Cleanup . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-3

    3-01.3 State Furnished Material Sources . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-33-01.3(1) Quality and Extent of Material . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-33-01.3(2) When More Than One Site is Provided . . . . . . . . . . . . . . . . . . . . . . . . . 3-33-01.3(3) Reject Materials . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-43-01.3(4) Surplus Screenings . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-43-01.3(5) Moving Plant . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-4

    3-01.4 Contractor Furnished Material Sources . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-53-01.4(1) Acquisition and Development . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-53-01.4(2) Surplus Screenings . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-63-01.4(3) Substitution of Gravel Deposit in Lieu of Ledge Rock or Talus

    Source Provided by the Contracting Agency . . . . . . . . . . . . . . . . . . . . . 3-63-01.4(4) Gravel Base . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-6

    3-01.5 Measurement . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-7

    3-01.6 Payment . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-7

    3-02 Stockpiling Aggregates . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-83-02.1 Description . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-8

    3-02.2 General Requirements . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-83-02.2(1) Stockpile Sites Provided by the Contracting Agency . . . . . . . . . . . . . . 3-83-02.2(2) Stockpile Site Provided by the Contractor . . . . . . . . . . . . . . . . . . . . . . . 3-83-02.2(3) Stockpiling Aggregates for Future Use . . . . . . . . . . . . . . . . . . . . . . . . . . 3-83-02.2(4) Stockpiling Aggregates for Immediate Use . . . . . . . . . . . . . . . . . . . . . . . 3-93-02.2(5) Preparation of Site . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-93-02.2(6) Construction of Stockpiles . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-93-02.2(7) Removing Aggregates From Stockpiles . . . . . . . . . . . . . . . . . . . . . . . . . 3-10

    3-02.3 Additional Requirements for Specific Aggregates . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-103-02.3(1) Washed Aggregates . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-10

    3-02.4 Measurement . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-11

    3-02.5 Payment . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-11

  • Page 16 2020 Standard Specifications M 41-10

    Contents

    3-03 Site Reclamation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-123-03.1 Description . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-12

    3-03.2 General Requirements . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-123-03.2(1) Contracting Agency-Provided Sites . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-123-03.2(2) Contractor-Provided Sites . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-123-03.2(3) Out-of-State Sites . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-13

    3-03.3 Reclamation Plans . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-133-03.3(1) Contracting Agency-Provided Sites . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-133-03.3(2) Contractor-Provided Sites . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-13

    3-03.4 Construction Requirements. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-133-03.4(1) Erosion Control . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-133-03.4(2) Deviations From Approved Reclamation Plans . . . . . . . . . . . . . . . . . . 3-13

    3-03.5 Payment . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-143-03.5(1) Contracting Agency-Provided Sites . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-143-03.5(2) Contractor-Provided Sites . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-14

    3-04 Acceptance of Aggregate . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-153-04.1 Description . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-15

    3-04.2 Materials . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-15

    3-04.3 Construction Requirements. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-153-04.3(1) General . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-153-04.3(2) Point of Acceptance . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-153-04.3(3) Sampling. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-163-04.3(4) Testing Results . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-163-04.3(5) Nonstatistical Evaluation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-163-04.3(6) Statistical Evaluation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-163-04.3(7) Rejected Work . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-173-04.3(8) Price Adjustments for Quality of Aggregate . . . . . . . . . . . . . . . . . . . . . 3-18

    3-04.4 Vacant . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-18

    3-04.5 Payment . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-19

  • 2020 Standard Specifications M 41-10 Page 17

    Contents

    Division 4 Bases . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4-1

    4-01 Vacant . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4-1

    4-02 Gravel Base . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4-24-02.1 Description . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4-2

    4-02.2 Materials . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4-2

    4-02.3 Construction Requirements. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4-2

    4-02.4 Measurement . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4-2

    4-02.5 Payment . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4-2

    4-03 Vacant . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4-3

    4-04 Ballast and Crushed Surfacing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4-44-04.1 Description . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4-4

    4-04.2 Materials . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4-4

    4-04.3 Construction Requirements. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4-44-04.3(1) Equipment . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4-44-04.3(2) Subgrade . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4-54-04.3(3) Mixing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4-54-04.3(4) Placing and Spreading . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4-54-04.3(5) Shaping and Compaction . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4-64-04.3(6) Keystone . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4-64-04.3(7) Miscellaneous Requirements . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4-64-04.3(8) Weather Limitations . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4-74-04.3(9) Hauling . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4-74-04.3(10) Hours of Work . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4-74-04.3(11) Permeable Ballast . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4-7

    4-04.4 Measurement . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4-8

    4-04.5 Payment . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4-8

  • Page 18 2020 Standard Specifications M 41-10

    Contents

    Division 5 Surface Treatments and Pavements . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5-1

    5-01 Cement Concrete Pavement Rehabilitation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5-15-01.1 Description . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5-1

    5-01.2 Materials . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5-1

    5-01.3 Construction Requirements. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5-25-01.3(1) Vacant. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5-25-01.3(2) Material Acceptance . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5-35-01.3(3) Vacant. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5-45-01.3(4) Replace Cement Concrete Panel . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5-45-01.3(5) Partial Depth Spall Repair . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5-65-01.3(6) Dowel Bar Retrofit . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5-75-01.3(7) Sealing Existing Concrete Random Cracks . . . . . . . . . . . . . . . . . . . . . . . 5-95-01.3(8) Sealing Existing Longitudinal and Transverse Joint . . . . . . . . . . . . . . . . 5-95-01.3(9) Cement Concrete Pavement Grinding . . . . . . . . . . . . . . . . . . . . . . . . . . 5-95-01.3(10) Pavement Smoothness . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5-105-01.3(11) Concrete Slurry and Grinding Residue . . . . . . . . . . . . . . . . . . . . . . . . . 5-12

    5-01.4 Measurement . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5-12

    5-01.5 Payment . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5-13

    5-02 Bituminous Surface Treatment . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5-155-02.1 Description . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5-15

    5-02.1(1) New Construction . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5-155-02.1(2) Seal Coats . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5-155-02.1(3) Pavement Sealers – Fog Seal . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5-15

    5-02.2 Materials . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5-15

    5-02.3 Construction Requirements. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5-155-02.3(1) Equipment . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5-155-02.3(2) Preparation of Roadway Surface . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5-165-02.3(3) Application of Emulsified Asphalt and Aggregate . . . . . . . . . . . . . . . . 5-185-02.3(4) Vacant. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5-195-02.3(5) Application of Aggregates . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5-205-02.3(6) Additional Emulsified Asphalt and Aggregate . . . . . . . . . . . . . . . . . . . 5-215-02.3(7) Patching and Correction of Defects . . . . . . . . . . . . . . . . . . . . . . . . . . . 5-215-02.3(8) Progress of Work . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5-225-02.3(9) Protection of Structures . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5-225-02.3(10) Unfavorable Weather . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5-225-02.3(11) Temporary Pavement Markings . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5-22

    5-02.4 Measurement . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5-23

    5-02.5 Payment . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5-23

  • 2020 Standard Specifications M 41-10 Page 19

    Contents

    5-03 Vacant . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5-25

    5-04 Hot Mix Asphalt . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5-265-04.1 Description . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5-26

    5-04.2 Materials . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5-265-04.2(1) How to Get an HMA Mix Design on the QPL . . . . . . . . . . . . . . . . . . . 5-265-04.2(2) Mix Design – Obtaining Project Approval . . . . . . . . . . . . . . . . . . . . . . 5-31

    5-04.3 Construction Requirements. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5-325-04.3(1) Weather Limitations . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5-325-04.3(2) Paving Under Traffic . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5-325-04.3(3) Equipment . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5-325-04.3(4) Preparation of Existing Paved Surfaces . . . . . . . . . . . . . . . . . . . . . . . . 5-365-04.3(5) Producing/Stockpiling Aggregates, RAP, & RAS . . . . . . . . . . . . . . . . . 5-385-04.3(6) Mixing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5-395-04.3(7) Spreading and Finishing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5-405-04.3(8) Aggregate Acceptance Prior to Incorporation in HMA. . . . . . . . . . . . 5-405-04.3(9) HMA Mixture Acceptance. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5-415-04.3(10) HMA Compaction Acceptance . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5-475-04.3(11) Reject Work . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5-535-04.3(12) Joints . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5-555-04.3(13) Surface Smoothness . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5-565-04.3(14) Planing Bituminous Pavement . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5-575-04.3(15) Sealing Pavement Surfaces . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5-575-04.3(16) HMA Road Approaches . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5-57

    5-04.4 Measurement . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5-58

    5-04.5 Payment . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5-58

    5-05 Cement Concrete Pavement. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5-615-05.1 Description . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5-61

    5-05.2 Materials . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5-61

    5-05.3 Construction Requirements. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5-615-05.3(1) Concrete Mix Design for Paving . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5-615-05.3(2) Consistency . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5-635-05.3(3) Equipment . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5-635-05.3(4) Measuring and Batching Materials . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5-655-05.3(5) Mixing Concrete . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5-685-05.3(6) Surface Preparation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5-695-05.3(7) Placing, Spreading, and Compacting Concrete . . . . . . . . . . . . . . . . . . 5-705-05.3(8) Joints . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5-725-05.3(9) Vacant. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5-735-05.3(10) Tie Bars and Corrosion Resistant Dowel Bars . . . . . . . . . . . . . . . . . . . 5-73

  • Page 20 2020 Standard Specifications M 41-10

    Contents

    5-05.3(11) Finishing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5-755-05.3(12) Surface Smoothness . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5-765-05.3(13) Curing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5-785-05.3(14) Cold Weather Work . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5-805-05.3(15) Concrete Pavement Construction in Adjacent Lanes . . . . . . . . . . . . . 5-815-05.3(16) Protection of Pavement . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5-815-05.3(17) Opening to Traffic. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5-815-05.3(18) Vacant. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5-825-05.3(19) Vacant. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5-825-05.3(20) Vacant. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5-825-05.3(21) Vacant. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5-825-05.3(22) Repair of Defective Pavement Slabs . . . . . . . . . . . . . . . . . . . . . . . . . . . 5-82

    5-05.4 Measurement . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5-83

    5-05.5 Payment . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5-845-05.5(1) Pavement Thickness . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5-87

  • 2020 Standard Specifications M 41-10 Page 21

    Contents

    Division 6 Structures . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6-1

    6-01 General Requirements for Structures . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6-16-01.1 Description . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6-1

    6-01.2 Foundation Data . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6-1

    6-01.3 Clearing the Site . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6-1

    6-01.4 Appearance of Structures . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6-1

    6-01.5 Vacant . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6-1

    6-01.6 Load Restrictions on Bridges Under Construction . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6-1

    6-01.7 Navigable Streams . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6-2

    6-01.8 Approaches to Movable Spans . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6-2

    6-01.9 Working Drawings . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6-2

    6-01.10 Utilities Supported by or Attached to Bridges . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6-2

    6-01.11 Name Plates . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6-3

    6-01.12 Final Cleanup . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6-3

    6-01.13 Vacant . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6-4

    6-01.14 Premolded Joint Filler . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6-4

    6-01.15 Normal Temperature . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6-4

    6-01.16 Repair of Defective Work . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6-46-01.16(1) General . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6-46-01.16(2) Pre-Approved Repair Procedures . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6-5

    6-02 Concrete Structures . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6-76-02.1 Description . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6-7

    6-02.2 Materials . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6-7

    6-02.3 Construction Requirements. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6-76-02.3(1) Classification of Structural Concrete . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6-76-02.3(2) Proportioning Materials . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6-86-02.3(3) Admixtures . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6-136-02.3(4) Ready-Mix Concrete . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6-146-02.3(5) Acceptance of Concrete . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6-176-02.3(6) Placing Concrete . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6-246-02.3(7) Tolerances . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6-306-02.3(8) Vacant. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6-306-02.3(9) Vibration of Concrete . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6-316-02.3(10) Bridge Decks and Bridge Approach Slabs . . . . . . . . . . . . . . . . . . . . . . . 6-326-02.3(11) Curing Concrete . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6-376-02.3(12) Construction Joints . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6-416-02.3(13) Expansion Joints . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6-436-02.3(14) Finishing Concrete Surfaces . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6-44

  • Page 22 2020 Standard Specifications M 41-10

    Contents

    6-02.3(15) Date Numerals . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6-516-02.3(16) Plans for Falsework and Formwork . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6-516-02.3(17) Falsework and Formwork . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6-536-02.3(18) Placing Anchor Bolts . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6-846-02.3(19) Bridge Bearings . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6-846-02.3(20) Grout for Anchor Bolts and Bridge Bearings . . . . . . . . . . . . . . . . . . . . 6-856-02.3(21) Drainage of Box Girder Cells . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6-866-02.3(22) Drainage of Substructure . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6-866-02.3(23) Opening to Traffic. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6-866-02.3(24) Reinforcement . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6-876-02.3(25) Prestressed Concrete Girders . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6-966-02.3(26) Cast-In-Place Prestressed Concrete . . . . . . . . . . . . . . . . . . . . . . . . . .6-1126-02.3(27) Concrete for Precast Units . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .6-1286-02.3(28) Precast Concrete Panels . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .6-130

    6-02.4 Measurement . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .6-134

    6-02.5 Payment . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .6-136

    6-03 Steel Structures . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .6-1386-03.1 Description . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .6-138

    6-03.2 Materials . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .6-138

    6-03.3 Construction Requirements. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .6-1396-03.3(1) Vacant. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .6-1396-03.3(2) Facilities for Inspection . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .6-1396-03.3(3) Inspector’s Authority . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .6-1396-03.3(4) Rejections . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .6-1396-03.3(5) Mill Orders and Shipping Statements . . . . . . . . . . . . . . . . . . . . . . . . .6-1396-03.3(6) Weighing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .6-1396-03.3(7) Shop Plans . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .6-1406-03.3(8) Substitutions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .6-1416-03.3(9) Handling, Storing, and Shipping of Materials . . . . . . . . . . . . . . . . . . .6-1416-03.3(10) Straightening Bent Material . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .6-1426-03.3(11) Workmanship and Finish . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .6-1426-03.3(12) Falsework . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .6-1426-03.3(13) Fabricating Tension Members . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .6-1426-03.3(14) Edge Finishing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .6-1426-03.3(15) Planing of Bearing Surfaces . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .6-1436-03.3(16) Abutting Joints . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .6-1446-03.3(17) End Connection Angles . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .6-1446-03.3(18) Built Members. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .6-1446-03.3(19) Hand Holes . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .6-1446-03.3(20) Lacing Bars . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .6-144

  • 2020 Standard Specifications M 41-10 Page 23

    Contents

    6-03.3(21) Plate Girders . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .6-1446-03.3(22) Eyebars . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .6-1456-03.3(23) Annealing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .6-1456-03.3(24) Pins and Rollers . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .6-1456-03.3(25) Welding and Repair Welding . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .6-1466-03.3(26) Screw Threads . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .6-1496-03.3(27) High-Strength Bolt Holes . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .6-1496-03.3(28) Shop Assembly . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .6-1516-03.3(29) Welded Shear Connectors . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .6-1536-03.3(30) Painting . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .6-1536-03.3(31) Alignment and Camber . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .6-1536-03.3(32) Assembling and Bolting . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .6-1546-03.3(33) Bolted Connections . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .6-1556-03.3(34) Adjusting Pin Nuts . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .6-1626-03.3(35) Setting Anchor Bolts . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .6-1626-03.3(36) Setting and Grouting Masonry Plates . . . . . . . . . . . . . . . . . . . . . . . . .6-1636-03.3(37) Setting Steel Bridge Bearings . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .6-1636-03.3(38) Placing Superstructure . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .6-1636-03.3(39) Swinging the Span . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .6-1636-03.3(40) Draining Pockets . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .6-1646-03.3(41) Vacant. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .6-1646-03.3(42) Surface Condition . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .6-1646-03.3(43) Castings, Steel Forgings, and Miscellaneous Metals . . . . . . . . . . . . .6-164

    6-03.4 Measurement . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .6-165

    6-03.5 Payment . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .6-165

    6-04 Timber Structures . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .6-1676-04.1 Description . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .6-167

    6-04.2 Materials . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .6-167

    6-04.3 Construction Requirements. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .6-1676-04.3(1) Storing and Handling Material . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .6-1676-04.3(2) Workmanship . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .6-1676-04.3(3) Shop Details . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .6-1686-04.3(4) Field Treatment of Cut Surfaces, Bolt Holes, and Contact

    Surfaces . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .6-1686-04.3(5) Holes for Bolts, Dowels, Rods, and Lag Screws . . . . . . . . . . . . . . . . .6-1686-04.3(6) Bolts, Washers, and Other Hardware . . . . . . . . . . . . . . . . . . . . . . . . .6-1686-04.3(7) Countersinking . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .6-1686-04.3(8) Framing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .6-1696-04.3(9) Framed Bents . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .6-1696-04.3(10) Caps . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .6-169

  • Page 24 2020 Standard Specifications M 41-10

    Contents

    6-04.3(11) Bracing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .6-1696-04.3(12) Stringers . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .6-1696-04.3(13) Wheel Guards and Railings . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .6-1706-04.3(14) Single-Plank Floors . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .6-1706-04.3(15) Laminated Floors . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .6-1706-04.3(16) Plank Subfloors for Concrete Decks . . . . . . . . . . . . . . . . . . . . . . . . . .6-1716-04.3(17) Trusses . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .6-1716-04.3(18) Painting . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .6-171

    6-04.4 Measurement . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .6-171

    6-04.5 Payment . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .6-171

    6-05 Piling . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .6-1726-05.1 Description . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .6-172

    6-05.2 Materials . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .6-172

    6-05.3 Construction Requirements. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .6-1726-05.3(1) Piling Terms . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .6-1726-05.3(2) Ordering Piling . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .6-1746-05.3(3) Manufacture of Precast Concrete Piling . . . . . . . . . . . . . . . . . . . . . . .6-1756-05.3(4) Manufacture of Steel Casings for Cast-In-Place Concrete Piles . . .6-1776-05.3(5) Manufacture of Steel Piles . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .6-1776-05.3(6) Splicing Steel Casings and Steel Piles . . . . . . . . . . . . . . . . . . . . . . . . .6-1786-05.3(7) Storage and Handling. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .6-1786-05.3(8) Pile Tips and Shoes . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .6-1796-05.3(9) Pile Driving Equipment . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .6-1806-05.3(10) Test Piles . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .6-1836-05.3(11) Driving Piles . . . . . . . . . . . . . . . . .