21
2019/2020 Franklin & Perry Township Projects

2019/2020 Franklin & Perry Township Projects...Project Information & Schedule • Project let in November 2019 • Construction Cost $850,000 80% covered by FHWA funding through INDOT

  • Upload
    others

  • View
    0

  • Download
    0

Embed Size (px)

Citation preview

Page 1: 2019/2020 Franklin & Perry Township Projects...Project Information & Schedule • Project let in November 2019 • Construction Cost $850,000 80% covered by FHWA funding through INDOT

2019/2020 Franklin & Perry Township Projects

Page 2: 2019/2020 Franklin & Perry Township Projects...Project Information & Schedule • Project let in November 2019 • Construction Cost $850,000 80% covered by FHWA funding through INDOT

Stop 11 Rd. & Combs Rd. RAB

Franklin Rd. bridge over Big Run Creek

Southeastern Ave. pavement repair

Stop 11 Rd. & Five Points Rd. RAB

Five Points Rd. & Edgewood Ave. RAB

Sherman Dr. & Thompson Rd. RAB

2

2019/2020 Franklin & Perry Township Projects

Presented By:City of Indianapolis Department of Public Works

and CrossRoad Engineers, PC

Page 3: 2019/2020 Franklin & Perry Township Projects...Project Information & Schedule • Project let in November 2019 • Construction Cost $850,000 80% covered by FHWA funding through INDOT

Stop 11 Rd. & Combs Rd.

Page 4: 2019/2020 Franklin & Perry Township Projects...Project Information & Schedule • Project let in November 2019 • Construction Cost $850,000 80% covered by FHWA funding through INDOT

Franklin Rd. bridge over Big Run Creek

Page 5: 2019/2020 Franklin & Perry Township Projects...Project Information & Schedule • Project let in November 2019 • Construction Cost $850,000 80% covered by FHWA funding through INDOT

Southeastern Ave. Pavement Repair

Page 6: 2019/2020 Franklin & Perry Township Projects...Project Information & Schedule • Project let in November 2019 • Construction Cost $850,000 80% covered by FHWA funding through INDOT

Stop 11 Rd. & Five Points Rd.

Page 7: 2019/2020 Franklin & Perry Township Projects...Project Information & Schedule • Project let in November 2019 • Construction Cost $850,000 80% covered by FHWA funding through INDOT

Five Points Rd. & Edgewood Ave.

Page 8: 2019/2020 Franklin & Perry Township Projects...Project Information & Schedule • Project let in November 2019 • Construction Cost $850,000 80% covered by FHWA funding through INDOT

8

Sherman Dr. & Thompson Rd.

Page 9: 2019/2020 Franklin & Perry Township Projects...Project Information & Schedule • Project let in November 2019 • Construction Cost $850,000 80% covered by FHWA funding through INDOT

USDOT Federal Highway Administration Statistics

Traditional intersections account for:

– 45% of all crashes - FHWA

– 33% of all traffic fatalities - FHWA

Compared to traditional intersections, roundabouts:– Reduce fatalities and injuries by 82% - FHWA

– Reduce total crashes by 44% - FHWA

– Require vehicles to travel at lower speeds

9

Why a roundabout? Safety

Page 10: 2019/2020 Franklin & Perry Township Projects...Project Information & Schedule • Project let in November 2019 • Construction Cost $850,000 80% covered by FHWA funding through INDOT

Collisions at traditional intersections are severe because of:

•High Speed

•Angle of Impact

10

Roundabouts are Safer

Page 11: 2019/2020 Franklin & Perry Township Projects...Project Information & Schedule • Project let in November 2019 • Construction Cost $850,000 80% covered by FHWA funding through INDOT

(32) (8)

Conflict points are dramatically reduced because all vehicles travel in the same direction.

11

Roundabouts are SAFER

Page 12: 2019/2020 Franklin & Perry Township Projects...Project Information & Schedule • Project let in November 2019 • Construction Cost $850,000 80% covered by FHWA funding through INDOT

Reduced congestion and less traffic delays

– up to 23% reduction! (Insurance Institute for Highway Safety)

– equivalent to 325,000 fewer

hours annually nationwide

12

Roundabouts are EFFICIENT

Page 13: 2019/2020 Franklin & Perry Township Projects...Project Information & Schedule • Project let in November 2019 • Construction Cost $850,000 80% covered by FHWA funding through INDOT

Project Information & Schedule

• Project let in September 2019• Construction Cost $600,000

80% covered by FHWA funding through INDOT & MPO• Intersection closed for construction in April and May

(60 day closure)

Franklin Township Projects

Stop 11 Rd. & Combs Rd.

Page 14: 2019/2020 Franklin & Perry Township Projects...Project Information & Schedule • Project let in November 2019 • Construction Cost $850,000 80% covered by FHWA funding through INDOT

Project Information & Schedule

• Project let in November 2019• Construction Cost $850,000

80% covered by FHWA funding through INDOT & MPO• Franklin Road closed at bridge from April to October

(180 day closure)

Franklin Township Projects

Franklin Rd. bridge over Big Run Creek

Page 15: 2019/2020 Franklin & Perry Township Projects...Project Information & Schedule • Project let in November 2019 • Construction Cost $850,000 80% covered by FHWA funding through INDOT

Project Information & Schedule

• Project let in October 2019• Construction Cost $565,000

Local funded by Indianapolis DPW• Southbound closed from mid-March to early May

Franklin Township Projects

Southeastern Ave. Pavement Repair

Page 16: 2019/2020 Franklin & Perry Township Projects...Project Information & Schedule • Project let in November 2019 • Construction Cost $850,000 80% covered by FHWA funding through INDOT

Project Information & Schedule

• Project let in September 2019• Construction Cost $1 Million

80% covered by FHWA funding through INDOT & MPO• Intersection closed for construction in June and July

(60 day closure)

Franklin Township Projects

Stop 11 Rd. & Five Points Rd.

Page 17: 2019/2020 Franklin & Perry Township Projects...Project Information & Schedule • Project let in November 2019 • Construction Cost $850,000 80% covered by FHWA funding through INDOT

Project Information & Schedule

• Project let in September 2019• Construction Cost $1.63 Million

80% covered by FHWA Congestion Mitigation and Air Quality (CMAQ) funding through INDOT & MPO

• Intersection closed for construction from July toSeptember (90 day closure)

Franklin Township Projects

Five Points Rd. & Edgewood Ave.

Page 18: 2019/2020 Franklin & Perry Township Projects...Project Information & Schedule • Project let in November 2019 • Construction Cost $850,000 80% covered by FHWA funding through INDOT

Project Information & Schedule

• Project let in November 2019• Construction Cost $1.7 Million

80% covered by FHWA Congestion Mitigation and Air Quality (CMAQ) funding through INDOT & MPO

• Intersection closed for construction from mid August toNovember (75 day closure)

Perry Township Projects

Sherman Dr. & Thompson Rd.

Page 19: 2019/2020 Franklin & Perry Township Projects...Project Information & Schedule • Project let in November 2019 • Construction Cost $850,000 80% covered by FHWA funding through INDOT

Franklin & Perry Township Projects

2020 - Phase 1 Construction

Page 20: 2019/2020 Franklin & Perry Township Projects...Project Information & Schedule • Project let in November 2019 • Construction Cost $850,000 80% covered by FHWA funding through INDOT

Franklin & Perry Township Projects

2020 - Phase 2 Construction

Page 21: 2019/2020 Franklin & Perry Township Projects...Project Information & Schedule • Project let in November 2019 • Construction Cost $850,000 80% covered by FHWA funding through INDOT

QUESTIONS?

Projects in Franklin & Perry Township -

2020