2019/2020 Franklin & Perry Township Projects
Stop 11 Rd. & Combs Rd. RAB
Franklin Rd. bridge over Big Run Creek
Southeastern Ave. pavement repair
Stop 11 Rd. & Five Points Rd. RAB
Five Points Rd. & Edgewood Ave. RAB
Sherman Dr. & Thompson Rd. RAB
2
2019/2020 Franklin & Perry Township Projects
Presented By:City of Indianapolis Department of Public Works
and CrossRoad Engineers, PC
Stop 11 Rd. & Combs Rd.
Franklin Rd. bridge over Big Run Creek
Southeastern Ave. Pavement Repair
Stop 11 Rd. & Five Points Rd.
Five Points Rd. & Edgewood Ave.
8
Sherman Dr. & Thompson Rd.
USDOT Federal Highway Administration Statistics
Traditional intersections account for:
– 45% of all crashes - FHWA
– 33% of all traffic fatalities - FHWA
Compared to traditional intersections, roundabouts:– Reduce fatalities and injuries by 82% - FHWA
– Reduce total crashes by 44% - FHWA
– Require vehicles to travel at lower speeds
9
Why a roundabout? Safety
Collisions at traditional intersections are severe because of:
•High Speed
•Angle of Impact
10
Roundabouts are Safer
(32) (8)
Conflict points are dramatically reduced because all vehicles travel in the same direction.
11
Roundabouts are SAFER
Reduced congestion and less traffic delays
– up to 23% reduction! (Insurance Institute for Highway Safety)
– equivalent to 325,000 fewer
hours annually nationwide
12
Roundabouts are EFFICIENT
Project Information & Schedule
• Project let in September 2019• Construction Cost $600,000
80% covered by FHWA funding through INDOT & MPO• Intersection closed for construction in April and May
(60 day closure)
Franklin Township Projects
Stop 11 Rd. & Combs Rd.
Project Information & Schedule
• Project let in November 2019• Construction Cost $850,000
80% covered by FHWA funding through INDOT & MPO• Franklin Road closed at bridge from April to October
(180 day closure)
Franklin Township Projects
Franklin Rd. bridge over Big Run Creek
Project Information & Schedule
• Project let in October 2019• Construction Cost $565,000
Local funded by Indianapolis DPW• Southbound closed from mid-March to early May
Franklin Township Projects
Southeastern Ave. Pavement Repair
Project Information & Schedule
• Project let in September 2019• Construction Cost $1 Million
80% covered by FHWA funding through INDOT & MPO• Intersection closed for construction in June and July
(60 day closure)
Franklin Township Projects
Stop 11 Rd. & Five Points Rd.
Project Information & Schedule
• Project let in September 2019• Construction Cost $1.63 Million
80% covered by FHWA Congestion Mitigation and Air Quality (CMAQ) funding through INDOT & MPO
• Intersection closed for construction from July toSeptember (90 day closure)
Franklin Township Projects
Five Points Rd. & Edgewood Ave.
Project Information & Schedule
• Project let in November 2019• Construction Cost $1.7 Million
80% covered by FHWA Congestion Mitigation and Air Quality (CMAQ) funding through INDOT & MPO
• Intersection closed for construction from mid August toNovember (75 day closure)
Perry Township Projects
Sherman Dr. & Thompson Rd.
Franklin & Perry Township Projects
2020 - Phase 1 Construction
Franklin & Perry Township Projects
2020 - Phase 2 Construction
QUESTIONS?
Projects in Franklin & Perry Township -
2020