Upload
others
View
3
Download
0
Embed Size (px)
Citation preview
Dr. Dipl.-Ing. Thomas Ackermann Energynautics, Germany E-Mail: [email protected]
STATUS OF HYBRID POWER SYSTEMS Summary of Hybrid Power System Workshop
2
4th INTERNATIONAL HYBRID POWER SYSTEMS WORKSHOP
130 Participants
>20 Countries
16 Sessions
60 presentations
HISTORY – HYBRID POWER SYSTEMS WORKSHOP
3
2016 Puerto Rico
2013 Hawaii
2019 Crete
2021 North Europe
2021 Caribbean
2020 Madeira
2018 Tenerife
WHY GREECE?
4
• Kythnos • Ikaria • Tilos • Agios Efstratios • Symi • Megisti • Astypalea
HYBRID POWER SYSTEM
5
A power system is understood as hybrid, if it consists of at least two different energy generation systems feeding an island load. A hybrid power plant is a system that consists of at least two different energy generation systems connected to an existing power system.
ENERGY MANAGEMENT SYSTEM (EMS)
Grid
EES
Smart Meter
CHP units
PV Charging Station
EMS
Inverter
Gateway
Communication Power
Customer 6
• Emissions • Noise • Maintenance Requirement • Diesel Storage/ Delivery? • High OPEX
• Reliable • Flexible to load fluctuations • Maintains System Stability • Lower CAPEX than renewables
DIESEL GEN-SET: A MUST?
7
• 600 GW of diesel existing world-wide • Often a given component of a hybrid system
Kythnos is an island in the Western Cyclades with a population of 1.632 people and its 5-year Average Peak Demand is 3,1 MW. The island has been a pilot site for many innovative projects which have taken place on the island during the last three decades:
• 1998 - Installation of the new Vestas 500kW wind turbine • 2000 - Operation of a fully automated power system with 500kW battery
storage and a 500kW Wind Turbine • 2001 - Operation of a Microgrid electrifying 12 houses with intelligent
autonomous Load Control
• 1982 - Operation of the first Wind Park in Europe (5x20kW) • 1983 - Installation of a 100 kW PV system with Battery storage (400kWh) • 1989 - Replacement of the wind turbines (5x33kW) • 1992 - Inverters in the PV system
KYTHNOS I
8
Source:
9 Kythnos Microgrid in Gaidouromantra, consists of 12 houses with PVs and Batteries (52 kWh), 9 kVA Diesel (only back-up), flexible loads (1-2 kW irrigation pumps) and Intelligent Load Controllers.
KYTHNOS II
9
Source:
Siwa Oasis (Egypt) • Photovoltaic Diesel Hybrid System • Comissioned: March 2015 • PV Plant accounts for 30% of power Demand in Siwa city and surroundings
SUCCESSFUL RE INTEGRATION IN OFF-GRID SYSTEMS LOW SHARE OF VRE (~ 30%)
10
Population 23,000
Load 17500 MWh/year
PV System 10 MWP (SMA Sunny Mini Central 7000HV) 5 systems (1 SMA Fuel Save Controlled and 4 manually controlled)
Diesel Generators 8 x 17.7 MW
11
Population 3,877 (2015)
Load 1.6 MW average demand 2.3 MW peak demand
PV System 1.9 MWP (SMA Sunny TriPower 25000-TL-30; SMA Fuel Save Controller)
Diesel Generators 4 MVA
ESS (batteries) 1 MW/ 580 kWh (SMA Sunny Central Storage SCS 1000)
SUCCESSFUL RE INTEGRATION IN OFF-GRID SYSTEMS HIGH SHARE OF VRE PEAK SHARE 80%
St Eustatius Island (Caribbean) • Hybrid Solar/Diesel System with energy storage • 100% Fossil fueled until 2015: operational cost represented over 75% of electricity supplier‘s
income • Commissioned : March 2016 • 23% fossil fuel consumption
reduction; 89% PV + battery penetration observed
SUCCESSFUL RE INTEGRATION IN OFF-GRID SYSTEMS
12 Source: International Hybrid Power Systems Workshop 2016: Caribbean Largest PV-Diesel-Storage System STt Eustatius (Phase 1). SMA.
St Eustatius Island (Caribbean) • Example of operation window with reduced diesel generation
AGIOS EFSTRATIOS – “GREEN ISLAND” PROJECT
13
Law 4495/2018 authorizes the Ministry of Energy, RAE and HEDNO to take all necessary actions for the
implementation of the project.
Heating facilities
Batteries Wind turbines
PVs
Island’s Thermal
Station
Island’s Network
Source:
• Agios Efstratios is a small island in the North – East part of the Aegean Sea, with only 270 inhabitants (2011) and its 5-year Average Peak Demand 0,32 MW.
• The project of Agios Efstratios includes two subprojects, the development of a Hybrid power plant and the development of a District Heating system (teleheating).
• The Hybrid power plant consists of Wind turbines (900 kW), PVs (150 kW) & Batteries (2,5 MWh), which is combined with a District Heating system (teleheating).
• The target of the project is to accomplish 85% energy of the island to come from RES.
• The project is funded by the EU, it is run by the CRES and it is still under study.
14
EXAMPLE EL HIERRO, SPAIN WIND-HYDRO
1800 km
CANARY ISLANDS
95 km
15
0,042 TWh
El Hierro
Tenerife
Spanish Mainland
ENTSO-E SIZE MATTERS
3,4 TWh ( X 80)
248 TWh ( X 6.000) or ( X 70)
3.278 TWh ( X 78.000) or ( X 1.000)
16
Source:
17
CHE:
• Owned by Gorona del Viento: • Cabildo de El Hierro • ENDESA • Instituto Tecnológico de Canarias
• Dispatched by the TSO
EL HIERRO ISLAND
Technical specs:
• Wind: 11.5 MW • Pumps: 6.4 MW • Turbines: 11.4 MW
• Upper reservoir: 380 dam3 • Lower reservoir: 149 dam3 • Roundtrip efficiency: 50%
Peak demand: 7 - 8 MW
Lowest demand: 3.5 – 4 MW
Source:
Wind Farm; 5 Enercon 2.3 MW turbines. Water reservoirs.
• Lined with high density polyethylene membrane
• Higher reservoir 380.000 m3
• Lower reservoir 149.000 m3 Penstocks.
• Turbine pipe of 2.3 km and 1 m of diameter
• Pump pipe of 3 km and 0.8 m of diameter • Hydro turbine station. 4 Andritz Pelton turbines of 2.83 MW (flow 0.5 m3/s) • Pump Station.
• 2 pump units of 1.6 MW (0.178 m3/s), controlled by frequency converters.
• 6 pump units of 0.54 MW (0.058 m3/s), started by 2 frequency converters
GORONA DEL VIENTO WIND HYDRO POWER PLANT
18 Sources:
• 8 consecutive days covering 100 % of the Island demand in June 2017
• 79 % of renewable integration into power system in July 2017
• 18 consecutive days covering 100 % of the Island demand in January-February 2018.
• Continuous improvement process.
• Stakeholders sharing information
• Gorona --> Plant improvements
• REE –> Operational changes
• ITC, Endesa, Enercon, Andritz.
OVERALL RESULTS
19
Years Saved Diesel (tons) CO₂ reduction
(tons) Integration into
power system (%)
2015 (July to end
of year) 2099 4352.57 19.4
2016 5366 11629.56 40.7
2017 6070 13150.87 46.4
Sources:
STORAGE: CENTRAL HIDROEÓLICA DE EL HIERRO: 100% RENEWABLE
Longest run being 100% renewable:
25 Jan – 12 Feb 2018 (18 consecutive days)
100% RENEWABLES Source:
Wind Resource:
Wind Resource Energy integration into El Hierro power system
Jan. Feb. March April 66 % 57 % 49 % 71 %
OVERALL RESULTS Source:
Speed Governor Logic Wind farm Active Power setting treatment
Matlab library Governor diagram
ACTUATIONS – IMPROVEMENTS Source:
23
CONCLUSIONS
Continuous analysis of the system. Collaboration between REE and Gorona is better for the system, because it is easy for the actors to detect, analyze and solve problems.
More confidence in the plant frequency regulation.
• 80 % of pump shedding reduction (more reduction with more than 2 Pelton Turbines dispatched)
• Performance increases Same system security with less pumps • It seems production increases
Source:
24
NEXT STEPS
Synchronous compensator
• Response improvement (damper)
• Diminish water consumption
Wind farm
• FCU enhance
• Primary regulation
Short term forecasting; Machine learning
Source:
25
EXAMPLE FAROE ISLANDS WIND-HYDRO-BATTERY
FAROE ISLANDS
26
Identification of renewable resources
Average wind speed: > 10m/s Precipitation: > 1300 mm/year Tenerife: < 250 mm/year
Peak tidal velocities: ~ 3.5 m/s Average sun hours: ~ 1000 hrs/year Tenerife: ~3000 hours
FAROE ISLANDS
27
0%
20%
40%
60%
80%
100%
116
933
750
567
384
110
0911
7713
4515
1316
8118
4920
1721
8523
5325
2126
8928
5730
2531
9333
6135
2936
9738
6540
3342
0143
6945
3747
0548
7350
4152
0953
7755
4557
1358
8160
4962
1763
8565
5367
2168
8970
5772
2573
9375
6177
2978
9780
6582
3384
0185
6987
37
Hours with renewables only: 1576 h (66 days)
Hours with renewables
> 80%: 3288 h (137 days)
Hours with renewables
> 60%: 5508 h (230 days) Hours with renewables
> 40%: 6810 h (284 days)
hours
RENEWABLE ENERGY DURATION CURVE 2015
28
∆P = -5.4MW in 60 seconds
EXTREME RAMP RATES (HÚSAHAGI WF)
29
Control Inverter
2 Intensium Max 20P Energy 707 kWh
Continuous discharge power 2 400 kW
Continuous charge power 1 500 kW
Nominal voltage 623 V
Voltage range 525V – 700V
ENERCON E-Storage 2300 Apparent power 2300 kVA
AC Voltage LV: 400V MV: 20 kV
DC Power 2 400 kW
DC Voltage Range 345 – 705 V
DC Current 3325 A
60/20kV
WIND FARM BLOCK DIAGRAM
30
31
BATTERY SYSTEM
-4
-2
0
2
4
6
8
0
2
4
6
8
10
12
MW
MW
Time scale: 18 minutes (data from September 1. 2017)
BESS Wind Farm Stabilized output
Battery discharging
Battery charging
32
BATTERY SYSTEM IN OPERATION
48
48,5
49
49,5
50
50,5
51
51,5
52
-101234567
Freq
uenc
y [H
Z]
Pow
er [M
W]
Sundsverkið M2-P Húsareyn HH-P Húsareyn BATT-P Húsareyn 20kV 2-f
Sudden drop of diesel unit
Drop of second diesel unit due to f<
BESS reacts on frequency drop
33
FAST FREQUENCY SUPPORT FROM THE BESS
Foliennummer 1 History – Hybrid Power Systems WorkshopWhy Greece?Hybrid Power System Energy Management System (EMS) Diesel Gen-set: A Must?Kythnos IKythnos IISUCCESSFUL RE INTEGRATION�IN OFF-GRID SYSTEMS low share of VRE (~ 30%)Foliennummer 11SUCCESSFUL RE INTEGRATION�IN OFF-GRID SYSTEMSAgios Efstratios�– “Green Island” projectFoliennummer 14Canary IslandsFoliennummer 16Foliennummer 17Foliennummer 18Foliennummer 19Foliennummer 20Foliennummer 21Foliennummer 22Foliennummer 23Foliennummer 24Foliennummer 25Foliennummer 26Foliennummer 27Foliennummer 28Foliennummer 29Foliennummer 30Foliennummer 31Foliennummer 32Foliennummer 33