67
2019 DC Study External Stakeholder Meeting – Minutes Date / Time: May 10 th , 2018 10:00 – 11:30 Location: Committee Room #3, City Hall 2 nd Floor Attended: George Kotsifas (Chair) Bill Veitch, Jamie Crich, Craig Linton, Sandy Levin, Alasdair Beaton, Mike Carter Anna Lisa Barbon, Paul Yeoman, Matt Feldberg, Adam Langmuir, Kevin Edwards, Jason Senese, Greg LaForge, Kelly Scherr, Doug MacRae, Michelle Morris, Maged Elmadhoon, Andrew Giesen, Gregg Barrett, Jennie Ramsay, Scott Mathers, Peter Kokkoros Purpose: Monthly meetings leading up to adoption of 2019 DC Study & By-law Update Agenda Item Discussion 1. Complete Streets (Maged E. & Michelle M.) Start-up of informative webpage to be available in roughly 2-3 weeks. There are no anticipated material cost increases to the major road projects Predominately used in larger municipalities, some ‘smaller’ sized cities have adopted a similar approach, considered a progressive approach to road classifications & design Targeting August Committee meeting for tabling of Complete Streets policy Important to know cost implications or scope of, along with tabling to Committee for Council adoption of the policy. Width of neighbourhood streets shrunk from 8m to 7.5m Primary & secondary collectors are now called Neighbourhood Connector, as a result of the London Plan Sidewalk & curb changes on neighbourhood connectors could have implications on owner borne costs (local service) also impacts current development plans. Suggestion to have conversation with utilities in order to reduce utility trench requirements. Staff indicated that

2019 DC Study External Stakeholder Meeting – …...legislation will have an impact on the City’s ability to dictate requirements. • Suggestion to have lead time, phase in, transitional

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: 2019 DC Study External Stakeholder Meeting – …...legislation will have an impact on the City’s ability to dictate requirements. • Suggestion to have lead time, phase in, transitional

2019 DC Study External Stakeholder Meeting – Minutes

Date / Time: May 10th, 2018 10:00 – 11:30

Location: Committee Room #3, City Hall 2nd Floor

Attended:

George Kotsifas (Chair) Bill Veitch, Jamie Crich, Craig Linton, Sandy Levin, Alasdair Beaton, Mike Carter Anna Lisa Barbon, Paul Yeoman, Matt Feldberg, Adam Langmuir, Kevin Edwards, Jason Senese, Greg LaForge, Kelly Scherr, Doug MacRae, Michelle Morris, Maged Elmadhoon, Andrew Giesen, Gregg Barrett, Jennie Ramsay, Scott Mathers, Peter Kokkoros

Purpose: • Monthly meetings leading up to adoption of 2019 DC Study & By-law Update

Agenda Item Discussion

1. Complete Streets (Maged E. & Michelle M.)

• Start-up of informative webpage to be available in roughly 2-3 weeks.

• There are no anticipated material cost increases to the major road projects

• Predominately used in larger municipalities, some ‘smaller’ sized cities have adopted a similar approach, considered a progressive approach to road classifications & design

• Targeting August Committee meeting for tabling of Complete Streets policy

• Important to know cost implications or scope of, along with tabling to Committee for Council adoption of the policy.

• Width of neighbourhood streets shrunk from 8m to 7.5m • Primary & secondary collectors are now called Neighbourhood

Connector, as a result of the London Plan • Sidewalk & curb changes on neighbourhood connectors could

have implications on owner borne costs (local service) also impacts current development plans.

• Suggestion to have conversation with utilities in order to reduce utility trench requirements. Staff indicated that

Page 2: 2019 DC Study External Stakeholder Meeting – …...legislation will have an impact on the City’s ability to dictate requirements. • Suggestion to have lead time, phase in, transitional

legislation will have an impact on the City’s ability to dictate requirements.

• Suggestion to have lead time, phase in, transitional language or date for new design standards/manual implementation. Consideration for current business or design plans already underway not to be ‘throw away.’

2. Non-Residential Rate Review Update (Jason S.)

• London is the only municipality surveyed which used an ‘ICI’ (Industrial, Commercial, Institutional) rate

• Implications to existing incentive plans are outlined in the attached Watson memo

• Guelph had a good example of switching from a uniform rate to an industrial/non-industrial rate trying to stimulate industrial development with a lower rate, turned out to not be the case and several years later reverted back to a uniform non-residential rate

• Definition of ‘industrial’ needs to be looked at again if staying with incentive for those type of permits.

• Suggestion to have LEDC included in consultation to broader group, targeting a meeting towards end of May beginning of June

• Conversion credits were outlined as a stumbling block to current rate structure, difficult to determine how many proposals did not go forward due to the higher DC rate of commercial use vs. industrial use.

3. Local Service Policy (Jason S.)

• Please provide feedback on the proposed policy changes to Jason Senese directly ([email protected]).

• Suggestion to coordinate SWM land valuation with Parks land valuation.

• LID draft policy targeted for June meeting, multiple options will be included

4. Master Planning Review Process (Paul Y.)

• Draft DC rate calculations will be provided concurrently with Master Plans, consultation will commence after that time. Unless a major material cost implication is identified prior to release.

Next DC External Stakeholder Meeting – June 14, 2018 10:00-12:00 Location: Committee Room TBD

Page 3: 2019 DC Study External Stakeholder Meeting – …...legislation will have an impact on the City’s ability to dictate requirements. • Suggestion to have lead time, phase in, transitional

london.ca

Review of the Forthcoming

City of London Complete Streets Design Manual

Presentation to DC External Stakeholder Group May 10, 2018

Page 4: 2019 DC Study External Stakeholder Meeting – …...legislation will have an impact on the City’s ability to dictate requirements. • Suggestion to have lead time, phase in, transitional

london.ca 2

Introduction - What are Complete Streets? A complete street is one that is designed to accommodate the mobility needs of all

ages, abilities, and modes of travel. Safe and comfortable access for pedestrians,

bicycles, transit users, and the mobility challenged are not design after-thoughts,

but are integral to the planning of the street from the start.

”“

- London Transportation Master Plan

Page 5: 2019 DC Study External Stakeholder Meeting – …...legislation will have an impact on the City’s ability to dictate requirements. • Suggestion to have lead time, phase in, transitional

london.ca 3

Introduction – Complete Streets Manuals Complete Streets Guides & Manuals have been developed by many cities

around the world to help direct and coordinate street planning/design towards

more balanced mobility options

Page 6: 2019 DC Study External Stakeholder Meeting – …...legislation will have an impact on the City’s ability to dictate requirements. • Suggestion to have lead time, phase in, transitional

london.ca 4

BackgroundThe 2016 City of London Official Plan introduced a group of Street

Classifications, which set the stage for more context sensitive city building

policies and redefining mobility for Londoners

Classifications Include:

• Rapid Transit Boulevards

• Urban Thoroughfares

• Civic Boulevards

• Main Streets

• Neighbourhood Connectors

• Neighbourhood Streets

• Rural Thoroughfares

• Rural Connectors

Page 7: 2019 DC Study External Stakeholder Meeting – …...legislation will have an impact on the City’s ability to dictate requirements. • Suggestion to have lead time, phase in, transitional

london.ca 5

Background

Each Street Classifications was

accompanied with policies to

guide future planning and design

towards a an intended character

and function, while progressing

towards overall mobility goals

Page 8: 2019 DC Study External Stakeholder Meeting – …...legislation will have an impact on the City’s ability to dictate requirements. • Suggestion to have lead time, phase in, transitional

london.ca 6

Many stakeholders were included in consultation efforts for the development

of the Complete Streets Design Manual and attended a Stakeholder Workshop,

held on June 2nd, 2017. These groups included:

• Downtown London BIA

• London Hydro

• London Transit

• Union Gas

• Tree and Forests Advisory

Committee

• Argyle BIA

• City of London Water

• London Environmental Network

• City of London Development

Services

• Accessibility Advisory Committee

• Can-Bike

• Hyde Park Business Association

• Bell

• London Middlesex Road Safety

Committee

• Middlesex Health Unit

• Start Communications

• Cycling Advisory Committee

• London Fire

• London Development Institute (LDI)

Background

Page 9: 2019 DC Study External Stakeholder Meeting – …...legislation will have an impact on the City’s ability to dictate requirements. • Suggestion to have lead time, phase in, transitional

london.ca 7

GoalsThe City of London Official Plan suggested the preparation of a Complete

Streets Manual to establish:

• Overall cross-sections for the street classifications

• Design parameters for the public realm

Page 10: 2019 DC Study External Stakeholder Meeting – …...legislation will have an impact on the City’s ability to dictate requirements. • Suggestion to have lead time, phase in, transitional

london.ca 8

The Vision!

Streets in London will meet the needs of a wide range of users as

defined by the place type, feature high-quality pedestrian

environments, and integrate seamlessly with transit services,

cycling networks, and automobile users. London’s streets will be

designed for connectivity and support the use of active and

sustainable modes of transportation, and also strongly consider the

needs of utility and maintenance providers within the right-of-way.

With this balance of modes, users, and places in mind, all future

construction, reconstruction, and rehabilitation projects for streets –

both large and small – in London will be influenced by principles of

“completeness” in both planning and design.

Page 11: 2019 DC Study External Stakeholder Meeting – …...legislation will have an impact on the City’s ability to dictate requirements. • Suggestion to have lead time, phase in, transitional

london.ca 9

The vision for the City of London Complete

Streets Design Manual grew to include . . .

Page 12: 2019 DC Study External Stakeholder Meeting – …...legislation will have an impact on the City’s ability to dictate requirements. • Suggestion to have lead time, phase in, transitional

london.ca 10

London Complete Street Manual - Content Chapter 1: Complete Streets: Vision and Principles

• Complete Streets concepts and policy support

Chapter 2: Elements of Complete Streets

• Complete Streets features

Chapter 3: Undertaking Complete Streets Design

• Processes for balancing the needs of current and future users

Chapter 4: Street Design for Roadways

• Street characteristics/priorities and conceptual cross sections, by street

classification

Chapter 5: Street Design for Intersections

• Intersection treatments that provide Complete Streets elements for

specific combinations of street classifications

Chapter 6: Moving Forward with Complete Streets

• Progress indicators for Complete Streets outcomes

Page 13: 2019 DC Study External Stakeholder Meeting – …...legislation will have an impact on the City’s ability to dictate requirements. • Suggestion to have lead time, phase in, transitional

london.ca

Contents:

1. What are Complete Streets?

2. Who is This Guide For?

3. Review of Complete Streets Policies in London

4. Core Principles for Complete Streets

11

Page 14: 2019 DC Study External Stakeholder Meeting – …...legislation will have an impact on the City’s ability to dictate requirements. • Suggestion to have lead time, phase in, transitional

london.ca

Local Policy Support

12

At the local level, policy support for complete streets is

found in a number of documents, including the:

• Strategic Plan

• The London Plan

• Downtown Plan

• Design Specifications and Requirements Manual

• Cycling Master Plan

• London Rapid Transit

• London Road Safety Strategy

• London 2030 Transportation Master Plan

Page 15: 2019 DC Study External Stakeholder Meeting – …...legislation will have an impact on the City’s ability to dictate requirements. • Suggestion to have lead time, phase in, transitional

london.ca

Municipal Council adopted the following Vision Zero Principles:

• No loss of life is acceptable

• Traffic fatalities and serious injuries are preventable

• We all make mistakes

• We are all physically vulnerable when involved in motor vehicle collisions

• Eliminating fatalities and serious injuries is a shared responsibility between

road users and those who design and maintain our roadways

Local Policy Support

13

Page 16: 2019 DC Study External Stakeholder Meeting – …...legislation will have an impact on the City’s ability to dictate requirements. • Suggestion to have lead time, phase in, transitional

london.ca

Prioritize Safe and Accessible Options for People

Embed Sustainability

Ensure Context Sensitivity

Prioritize Connectivity

Emphasize Vitality

14

Core Principles

Page 17: 2019 DC Study External Stakeholder Meeting – …...legislation will have an impact on the City’s ability to dictate requirements. • Suggestion to have lead time, phase in, transitional

london.ca

Streets that attract pedestrians

enhance urban vitality in London.

“”

“ ”15

The safety and mobility needs of all

users is a priority in any street design

exercise.

Prioritize Safe and Accessible Options for People

Emphasize Vitality

Core Principles

Page 18: 2019 DC Study External Stakeholder Meeting – …...legislation will have an impact on the City’s ability to dictate requirements. • Suggestion to have lead time, phase in, transitional

london.ca 16

• Tactile walking surface indicators

• Separation of pedestrians and cyclists where practical

• Consideration of user needs and land uses in prioritizing

street elements such as sidewalk width

• Design processes that emphasize consultation with

stakeholder groups

• Pedestrian crossing refuge islands

• Accessible transit stop design

Key considerations:

Accessibility

The Manual defines what a pedestrian is, describes the central role of walking

and mobility device travel within London and outlines how the City will support

pedestrians through Complete Streets.

Page 19: 2019 DC Study External Stakeholder Meeting – …...legislation will have an impact on the City’s ability to dictate requirements. • Suggestion to have lead time, phase in, transitional

london.ca

Contents:

General Considerations and Tools for:

1. Pedestrian Facility Design

2. Cycling Facility Design

3. Transit Facility Design

4. Motor Vehicles

5. Green Infrastructure

6. Utilities and Municipal Services

17

Page 20: 2019 DC Study External Stakeholder Meeting – …...legislation will have an impact on the City’s ability to dictate requirements. • Suggestion to have lead time, phase in, transitional

london.ca

Cycling Facilities

Considerations

Pedestrian

Facility

Considerations

18

Page 21: 2019 DC Study External Stakeholder Meeting – …...legislation will have an impact on the City’s ability to dictate requirements. • Suggestion to have lead time, phase in, transitional

london.ca

Provide connectivity:

As the slowest

mode of transportation,

pedestrians have

the greatest sensitivity

to route directness.

”Prioritize vulnerable users:

Cyclists are more vulnerable

than transit riders and

motorists in a collision

because they are not

protected within a vehicle.

”19

Page 22: 2019 DC Study External Stakeholder Meeting – …...legislation will have an impact on the City’s ability to dictate requirements. • Suggestion to have lead time, phase in, transitional

london.ca 20

Design For Accessibility

Pedestrians include those who are using a walker, crutches, a wheelchair or an

electrically powered mobility device as well as individuals with a visual impairment. “

Design features should be used to accommodate all of London’s pedestrians,

such as:

• appropriately wide pedestrian clearways;

• audible pedestrian signals;

• tactile walking surface indicators (TWSIs);

• visually contrasting surface treatments; and

• amenities such as seating

Page 23: 2019 DC Study External Stakeholder Meeting – …...legislation will have an impact on the City’s ability to dictate requirements. • Suggestion to have lead time, phase in, transitional

london.ca

Contents:

(under development with City input)

1. Process Overview

2. Planning

3. Conceptualizing

4. Designing

5. Implementing

21

Page 24: 2019 DC Study External Stakeholder Meeting – …...legislation will have an impact on the City’s ability to dictate requirements. • Suggestion to have lead time, phase in, transitional

london.ca

Street Element

Decision

Making Tool

Complete Street

Audit Tool

22

Page 25: 2019 DC Study External Stakeholder Meeting – …...legislation will have an impact on the City’s ability to dictate requirements. • Suggestion to have lead time, phase in, transitional

london.ca

The tool on the

right outlines

suitable

alternatives that

should be

considered in

cases where

the Right of

Way is not

sufficiently

wide.

”23

The selected

street typology

automatically

loads the priority

rankings from the

Complete Street

Priorities Tool and

the graph below

displays the

difference

between desired

and existing

conditions.

Page 26: 2019 DC Study External Stakeholder Meeting – …...legislation will have an impact on the City’s ability to dictate requirements. • Suggestion to have lead time, phase in, transitional

london.ca

Contents:

1. Street Typologies

2. Design Guidance for: • Rapid Transit Boulevards

• Urban Thoroughfares

• Civic Boulevards

• Main Streets

• Neighbourhood Connectors

• Neighbourhood Streets

• Rural Thoroughfares

• Rural Connectors

24

Page 27: 2019 DC Study External Stakeholder Meeting – …...legislation will have an impact on the City’s ability to dictate requirements. • Suggestion to have lead time, phase in, transitional

london.ca 25

Civic

Boulevard

Example

Page 28: 2019 DC Study External Stakeholder Meeting – …...legislation will have an impact on the City’s ability to dictate requirements. • Suggestion to have lead time, phase in, transitional

london.ca

Civic

Boulevard

”“ ”

“ ”Example

26

Civic Boulevards

provide multi-modal

connections

between different

neighbourhoods

across the City

including

downtown.

The variety of destinations along these corridors can

generate significant volumes of walking trips

Physically separated and continuous cycling facilities are preferred.

Page 29: 2019 DC Study External Stakeholder Meeting – …...legislation will have an impact on the City’s ability to dictate requirements. • Suggestion to have lead time, phase in, transitional

london.ca

Neighbourhood

Street

Example

27

Page 30: 2019 DC Study External Stakeholder Meeting – …...legislation will have an impact on the City’s ability to dictate requirements. • Suggestion to have lead time, phase in, transitional

london.ca

Neighbourhood

Street

” “”

“ ”Example

28

Neighbourhood

Streets are where

most Londoners,

including many

families, live;

enhancing the

livability, sense of

community, and the

ability to age-in-place

are important

considerations. Benches and newspaper boxes are

typically provided at corners with other

major streets.

Motorist speeds may be managed with speed humps.

Page 31: 2019 DC Study External Stakeholder Meeting – …...legislation will have an impact on the City’s ability to dictate requirements. • Suggestion to have lead time, phase in, transitional

london.ca

Neighbourhood

Connector

Example

29

Page 32: 2019 DC Study External Stakeholder Meeting – …...legislation will have an impact on the City’s ability to dictate requirements. • Suggestion to have lead time, phase in, transitional

london.ca

Neighbourhood

Connector

”“ ”

“ ”Example

30

Link residential areas to the City-wide road network.

Connectivity to key neighbourhood destinations can

generate large volumes of pedestrian trips

Travel lanes

may be

reduced to

3.0 m, unless

the street is

part of a

transit route.

Page 33: 2019 DC Study External Stakeholder Meeting – …...legislation will have an impact on the City’s ability to dictate requirements. • Suggestion to have lead time, phase in, transitional

london.ca 31

Contents:

1. Intersection Design Principles

2. Design Guidance for: • Rapid Transit Boulevard Intersecting a Main Street

• Urban Thoroughfare intersecting a Civic Boulevard

(Signalized)

• Urban Thoroughfare Intersecting a Civic Boulevard

(Roundabout)

• Urban Thoroughfare Intersecting a Neighbourhood

Connector

• Civic Boulevard Intersecting a Neighbourhood Street

Page 34: 2019 DC Study External Stakeholder Meeting – …...legislation will have an impact on the City’s ability to dictate requirements. • Suggestion to have lead time, phase in, transitional

london.ca 32

Example

Rapid Transit

Boulevard

Intersecting a

Main Street

Page 35: 2019 DC Study External Stakeholder Meeting – …...legislation will have an impact on the City’s ability to dictate requirements. • Suggestion to have lead time, phase in, transitional

london.ca 33

Example

Rapid Transit

Boulevard

Intersecting a

Main Street

The pedestrian

clearway widens as

the planter boxes

and trees are

discontinued,

providing for greater

ease of pedestrian

movement and

queuing. Centre median design requires dedicated

transit signals which use the same phasing

as the through motor vehicle movement.

” “”

Page 36: 2019 DC Study External Stakeholder Meeting – …...legislation will have an impact on the City’s ability to dictate requirements. • Suggestion to have lead time, phase in, transitional

london.ca

Contents:

(under development with City input)

1. Principles of Performance Metrics

2. Options for Measuring Complete Streets

Performance

34

Page 37: 2019 DC Study External Stakeholder Meeting – …...legislation will have an impact on the City’s ability to dictate requirements. • Suggestion to have lead time, phase in, transitional

london.ca

• Undertake relevant and multi-faceted data collection

• Analyze usage patterns in context

• Develop a feasible monitoring strategy

• Communicate findings and integrate data analysis into

project decision-making

Baltimore Case Study:

Network Completeness

Mapping: Pedestrian

Network

NYC Sustainable Streets Report: Combined Sales:

Improvement Sites vs. Comparison Sites35

Principles of Performance Measurement

Page 38: 2019 DC Study External Stakeholder Meeting – …...legislation will have an impact on the City’s ability to dictate requirements. • Suggestion to have lead time, phase in, transitional

london.ca

“”

“”

36

The spatial distribution of Complete Streets

can be used to visualize the City’s progress

and highlight specific areas that may have

less access to sustainable mode choices.

Sales data collected via electronic payment vendors can be

used to compare changes on streets where improvements

are made with control streets that have a similar character.

Baltimore Case Study:

Network Completeness

Mapping: Pedestrian

Network

NYC Sustainable Streets Report: Combined Sales:

Improvement Sites vs. Comparison Sites

Page 39: 2019 DC Study External Stakeholder Meeting – …...legislation will have an impact on the City’s ability to dictate requirements. • Suggestion to have lead time, phase in, transitional

london.ca

Next Steps

• Share Draft with Stakeholders and Finalize late

summer 2018

• Education campaign

• Move towards a network of Complete Streets

37

Page 40: 2019 DC Study External Stakeholder Meeting – …...legislation will have an impact on the City’s ability to dictate requirements. • Suggestion to have lead time, phase in, transitional

london.ca

Questions

Page 41: 2019 DC Study External Stakeholder Meeting – …...legislation will have an impact on the City’s ability to dictate requirements. • Suggestion to have lead time, phase in, transitional

2019 Development Charges

DC External Stakeholder CommitteeMay 10, 2018

Page 42: 2019 DC Study External Stakeholder Meeting – …...legislation will have an impact on the City’s ability to dictate requirements. • Suggestion to have lead time, phase in, transitional

2

Meeting Topic:

Page 43: 2019 DC Study External Stakeholder Meeting – …...legislation will have an impact on the City’s ability to dictate requirements. • Suggestion to have lead time, phase in, transitional

Background

• BackgroundoDC Act provides limited guidance regarding sub-

categorization on uses of land

oSome reference to “residential” and by inference, “non-residential”

oThis leaves discretion for how municipalities choose to define non-residential

oCurrent approach:‒ Institutional / Commercial / Industrial

3

Page 44: 2019 DC Study External Stakeholder Meeting – …...legislation will have an impact on the City’s ability to dictate requirements. • Suggestion to have lead time, phase in, transitional

Scope

• Independent third party review (Watson):oWhat are other municipalities doing?

oA review / analysis of other non-residential approaches:‒ Industrial / Non-Industrial‒ Commercial / Non-Commercial‒ Uniform Non-Residential

oConcluding remarks:‒ Summarizing key findings

4

Page 45: 2019 DC Study External Stakeholder Meeting – …...legislation will have an impact on the City’s ability to dictate requirements. • Suggestion to have lead time, phase in, transitional

What Are Other Municipalities Doing?

5

18

# of Municipalities Surveyed

Uniform Non-Residential

Retail / Non-Retail

Industrial / Non-Industrial

Industrial / Commercial / Institutional

Industrial, Office, Institutional (IOI) /

Retail / Hotel / Mixed Use Retail /

Mixed Use IOI

11 2 4 0 1

Page 46: 2019 DC Study External Stakeholder Meeting – …...legislation will have an impact on the City’s ability to dictate requirements. • Suggestion to have lead time, phase in, transitional

What Are Other Municipalities Doing?

6

Municipality Uniform Non-Residential

Retail / Non-Retail

Industrial / Non-Industrial

Industrial / Commercial / Institutional

Industrial, Office, Institutional (IOI) /

Retail / Hotel / Mixed Use Retail /

Mixed Use IOI

Markham X

Oakville X

Burlington X

Ottawa X

Mississauga X

Milton X

Hamilton X

Kitchener X

Thames Centre X

Page 47: 2019 DC Study External Stakeholder Meeting – …...legislation will have an impact on the City’s ability to dictate requirements. • Suggestion to have lead time, phase in, transitional

What Are Other Municipalities Doing?

7

Municipality Uniform Non-Residential

Retail / Non-Retail

Industrial / Non-Industrial

Industrial / Commercial / Institutional

Industrial, Office, Institutional (IOI) /

Retail / Hotel / Mixed Use Retail /

Mixed Use IOI

Waterloo X

Kingston X

Guelph X

Brantford X

St. Thomas X

Sarnia X

Middlesex Centre X

Windsor X

Woodstock X

Page 48: 2019 DC Study External Stakeholder Meeting – …...legislation will have an impact on the City’s ability to dictate requirements. • Suggestion to have lead time, phase in, transitional

Analysis of Options

8

Category Key Takeaways

Industrial / Commercial / Institutional(Current Structure)

• Highest charge for commercial development with lower charges for both Institutional and Industrial development

• Disincentive for conversions of older industrial buildings to commercial use• Greater administrative effort required to administer by-law versus other

options evaluated

Industrial / Non-Industrial

• Lower industrial charge as opposed to non-industrial charge• Disincentive for conversions of older industrial buildings to commercial use

Commercial / Non-Commercial

• Higher commercial charge as opposed to non-commercial charge• Industrial incentive is the least expensive to fund of all options evaluated• Disincentive for conversions of older industrial buildings to commercial use

Uniform Non-Residential

• Least amount of administrative effort required to administer by-law versus other options evaluated

• Eliminates conversion issue• Industrial incentive is the most expensive to fund of all options evaluated

Page 49: 2019 DC Study External Stakeholder Meeting – …...legislation will have an impact on the City’s ability to dictate requirements. • Suggestion to have lead time, phase in, transitional

Financial Impacts

9

* Based on data from 2014 DC Study

Page 50: 2019 DC Study External Stakeholder Meeting – …...legislation will have an impact on the City’s ability to dictate requirements. • Suggestion to have lead time, phase in, transitional

Concluding Remarks

• Most common type of non-residential rate structure is the Uniform structureoLess administrative effort required to administer by-lawoBuilding conversion can occur without additional DC

charges

• Incentives can continue under the alternative options, but the cost of the incentive program will be impacted

10

Page 51: 2019 DC Study External Stakeholder Meeting – …...legislation will have an impact on the City’s ability to dictate requirements. • Suggestion to have lead time, phase in, transitional

Next Steps

• Presentation to DC Stakeholder’s and release of memo from Watson

• Consultation meeting with broader groupo 2-3 weeks

• Report back to next DC Stakeholder’s meetingo June 14o Recommended approach taking into consideration

consultation feedback• Report to SPPC

o July 23o Seeking Council endorsement on recommended

approach

11

Page 52: 2019 DC Study External Stakeholder Meeting – …...legislation will have an impact on the City’s ability to dictate requirements. • Suggestion to have lead time, phase in, transitional

12

Meeting Topic:

Page 53: 2019 DC Study External Stakeholder Meeting – …...legislation will have an impact on the City’s ability to dictate requirements. • Suggestion to have lead time, phase in, transitional

Local Service PolicyOverview

• Current approved local service policies cover the following sections:o General claimability / eligibilityo Road Workso Sanitary Sewage Workso Stormwater Workso Water Distribution

• There were significant changes to the 2014 local service policies.

• Reviewed opportunities for improved:o Clarityo Consistencyo Completeness 13

OVERALL THESE POLICIES WORKED WELL!

Page 54: 2019 DC Study External Stakeholder Meeting – …...legislation will have an impact on the City’s ability to dictate requirements. • Suggestion to have lead time, phase in, transitional

Local Service PolicyRecommended Changes

1. Clean-up of wording throughout policieso These changes are minor in nature and do not alter the intent of the policy

‒ For example:‒ Owner vs Developer (now Owner throughout polices and consistent with agreement language)‒ References to CSRF updated to reflect official name

2. The terminology under the Roads section has been updated to more closely align with terminology under the London Plan street classificationso Arterial continues to be used, but will be defined as Rapid Transit Boulevard, Urban

Thoroughfare, Civic Boulevard, Main Street and Rural Thoroughfare.o Primary Collector/Secondary Collector now referred to as Neighbourhood

Connectoro Local Street now referred to as Neighbourhood Street

14

Minor Improvements Rather Than Major Policy Overhaul

Page 55: 2019 DC Study External Stakeholder Meeting – …...legislation will have an impact on the City’s ability to dictate requirements. • Suggestion to have lead time, phase in, transitional

Local Service PolicyRecommended Changes

3. Policies recommended to be deleted:o “Use of Contingencies” in the General section. Policy not required because the

authority to make a claim related to a contingency is provided for under the provisions in “Claimability”.

o “Exceptions” in the General section. Policy not required because to the authority to substitute a project is permitted under the DC Act (i.e. does not also need to be in the DC By-law).

4. Policies recommended to be added:o Strategic Needs:

‒ Current policy: Sewers that are identified as a strategic need by the City Engineer are eligible for a claim from the CSRF.

‒ Similar policies are recommended to be added to Roads, Water Distribution and Stormwater.‒ These policies are recommended to be added to provide flexibility to address emerging needs that

will satisfy a regional benefit to growth

o In Roads section a new policy to address cycling facilities lanes‒ Eligible for a claim if cycling facilities lanes are identified through development areas in the Cycling

Master Plan, on Neighbourhood Connectors or Neighbourhood Streets

o A new Parkland Development section has been added‒ Defines Parkland Development local service costs and what is eligible for claim from the CSRF‒ Consistent with current requirements under subdivision agreements 15

Page 56: 2019 DC Study External Stakeholder Meeting – …...legislation will have an impact on the City’s ability to dictate requirements. • Suggestion to have lead time, phase in, transitional

Local Service PolicyOutstanding Issues

• Policy addressing Infill and Intensification to be added o Will be consistent with the principles adopted by Council in January 2018o Update to be provided to the DC External Stakeholder’s at the June meeting

• Policy addressing Low Impact Development (LID) to be addedo Policy currently under development by the Staffo Update to be provided to the DC External Stakeholder’s at the June meeting

• Stormwater Management Facility Land Policies to be updatedo In order to provide greater clarity on developable versus non developable land,

Staff are currently reviewing language (can these be more clearly defined)o Land valuations currently being reviewed. Revised land valuations will not be

known for 8-10 weeks.

16

Page 57: 2019 DC Study External Stakeholder Meeting – …...legislation will have an impact on the City’s ability to dictate requirements. • Suggestion to have lead time, phase in, transitional

Local Service PoliciesNext Steps

• June 1st - DC External Stakeholder’s to provide feedback on draft local service policies

• June 14th – Updated local service policies to be presented at the DC External Stakeholder’s meetingo Infill and Intensification finalized for discussiono Low Impact Development (LID) finalized for discussion

17

Page 58: 2019 DC Study External Stakeholder Meeting – …...legislation will have an impact on the City’s ability to dictate requirements. • Suggestion to have lead time, phase in, transitional

Questions?

18

Page 59: 2019 DC Study External Stakeholder Meeting – …...legislation will have an impact on the City’s ability to dictate requirements. • Suggestion to have lead time, phase in, transitional

GENERAL

Claimability Any item listed as claimable, subsidizable, or eligible for funding from a development charge (DC) reserve fund must also be provided for in the approved DC rate calculations as reflected in the 2014 DC Background Study. To the extent that specific cost sharable works and projects cannot be identified as to location or timing, there should be a contingency provided for in the estimates that is incorporated into the rates.

The ultimate ability to claim for reimbursement, the cost of anyfor work constructed by an Owner shall be subject to authorization to construct the work in the development agreement or subject to execution of a servicing agreement prior to commencement of the work, and to other provisions of this Schedule. Coincident with the inclusion of a provision to construct a claimable work in a development agreement, Administration the City shall generate a Source of Financing Report demonstrating the availability of financing for the work in relation to the approved capital budget for the particular category of works. Where the approved budget is not sufficient to absorb the new funding commitment for the work, the capital budget approval may be deferred until the following year’s budget cycle. The developer Owner shall proceed at their own risk of refusal of the claim, should they proceed with works authorized in the development agreement until a commitment approving the funding of such works from an approved project budget has been obtained.

It is important that the City continue to monitor between DC Background Studies, the accuracy of the estimates and assumptions used to establish the rates. To the extent that substantial variations are identified, Council should be advised and will need to consider whether to increase or decrease the rates in accordance with the monitoring observations. Non-Growth Works that Benefit the Existing Population

Where works funded in part from the CSRF are subject to this policy and also include a non-growth component in the DC Background Study, funding of that portion of the works must wait until the City has approved sufficient funds in its Council approved capital budgets, or Council makes provision for a Reserve Fund designated for use in funding the non-growth share of DC funded works, to pay for that non-growth portion of the works. The non-growth portion of the funding shall be identified in the City’s Capital Works Budget and be subject to approval by Council. Use of Contingencies

Works listed as eligible in the DC Background Study, or with the approval of the City Engineer, in consultation with the Director, Development Finance, drawn from a contingency and/or an alternative to a work listed in the Background Study may be funded from the CSRF. Exceptions

The DC By-law allows for exceptions to projects listed in the DC Background Study for works listed as eligible in the DC Background Study, or with the approval of the City Engineer, in consultation with the Director, Development Finance, drawn from a contingency and/or substituted for a work listed in the Background Study may be claimable. ROAD WORKS

“Arterial” refers to London Plan street classifications of Rapid Transit Boulevard, Urban Thoroughfare, Civic Boulevard, Main Street and Rural Thoroughfare.

Major Road Works (CSRF - Roads Services)

Major Transportation road works typically consist of large-scale arterial road widening expansion projects or two lane road upgrades triggered by increased traffic volumes associated with growth across the City. All Major Transportation Road Works are constructed by the City and the growth related cost is eligible for a claim from the CSRF - Roads Services.

The costs of the following items are incorporated into road projects and are required as a result of growth:

Commented [SJ1]: It is recommended this section be

deleted because the authority to make a claim from a

contingency is covered off in the General section under

claimability.

Commented [SJ2]: It is recommended this section be

deleted because authority via by-law is not required to allow for

project substitutions. Also, this does not really fit with the

intent of the policies which is on claimability / eligibility.

Page 60: 2019 DC Study External Stakeholder Meeting – …...legislation will have an impact on the City’s ability to dictate requirements. • Suggestion to have lead time, phase in, transitional

a) Structures to be widened or replaced b) Noise barrier wall where required c) Land acquisition (raw land cost, appraisals, surveying, legal, etc.) but only where lands

cannot be acquired through dedications under the Planning Act on a timely basis. Minor Road Works (CSRF - Roads Services)

Minor Road Works that would be constructed as part of the major road project are eligible to be claimed from the CSRF - Roads Services. These works include: new traffic signals, channelization, sidewalks, and streetlights. In some cases, these works are done in advance of the road capacity expansion project as a means of addressing a network wide benefit to growth, without completing the entire road expansion.

Channelization (CSRF - Minor Road WorksRoads)

Channelization on an primary or arterial road into a new public street is eligible for a claim from the CSRF – Minor Road WorksRoads. The following subsections list the various additional components of the channelization which are considered claimable:

a) Tree Plantings

When replacement trees are planted as part of external road works to compensate for removed trees, other than those removed to facilitate an access, the cost of the removal and replacement is claimable. All other tree plantings are not claimable.

b) Ditching

When ditching and/or the installation of catchbasins is required to facilitate claimable external road work the drainage works may be incorporated in the minor road works claim to the CSRF.

c) Utility Relocations

Utility relocations necessitated by the claimable road works can be claimed upon providing a copy of the invoices from the utility and proof of payment in full. The City shall issue a letter to the utility company stating that this work is required by the City under the Public Service Works on HighwaysHighway Act and will pay for 50% of cost of labour and trucking. This 50% share is claimable from the CSRF; the other 50% is the utility’s share and is not claimable. Should the utility refuse to pay these costs, the 50% “utility share” shall be the responsibility of the proponent Owner. Engineering fees associated with these relocations are not claimable.

Minor Road Works - Road Oversizing (CSRF – Minor Road Works- Roads)

Where a new arterial or primary collector road is to be constructed in whole or in part through or adjacent to a development, the Owner is responsible for the cost of constructing a Neighbourhood Connectorsecondary collector road as defined in the City of London’s Design Specifications & Requirements Manual and Complete Streets Guide. If the required road is wider or at a higher standard, the Owner is responsible for the cost of a standard road, including sidewalks, street lights, etc., and is eligible for a claim to the CSRF – Minor Road WorksRoads for the difference in cost between a standard road and the road actually constructed. The construction responsibilities shall be defined by the conditions of an agreement between the City and the Owner. If the Owner wishes to construct the road at an enhanced standard beyond that acceptable to the City Engineer, then the Owner shall pay for the additional costs of enhancement with no eligibility for a claim from any fund. Arterial Road Extensions (CSRF - Roads Services)

When a development precedes the construction of a new arterial road that is either adjacent to or runs through the developable lands, the Owner is responsible for the construction of a Neighbourhood Connectorprimary collector road along the ultimate road right-of-way. A partial claim for this work may be made as per the primary road oversizing provisions for Minor Works -– CSRF - Roads.

Commented [SJ3]: Channelization moved under Minor

Road works.

Page 61: 2019 DC Study External Stakeholder Meeting – …...legislation will have an impact on the City’s ability to dictate requirements. • Suggestion to have lead time, phase in, transitional

Strategic Links (CSRF – Roads)

Portions of proposed Neighbourhood Connectors or Neighbourhood Streets that are required for transportation network connectivity, are not implementable in a timely manner due to reasons beyond the control of the surrounding Owners and are identified as a strategic need by the City Engineer, may be constructed by the City and the cost is eligible for a claim from the CSRF - Roads. Cycling Lanes (CSRF – Roads)

Where on-road cycling facilities lanes are identified through development areas in the Cycling Master Plan, on Neighbourhood Connectors or Neighbourhood Streets, the Owner shall be responsible to construct the cycling lanes. If the required road is wider or at a higher standard, the Owner is responsible for the cost of a standard road, including sidewalks, street lights, etc., and is eligible for a claim to the CSRF - Roads (Active Transportation) for the difference in cost between a standard road and the road actually constructed. The construction responsibilities shall be defined by the conditions of an agreement between the City and the Owner. Local Service Costs (Owner Cost)

The following subsections list the various road components which are considered a local service cost and are therefore constructed at the expense of the Owner:

a) Connections Connections of all public and private new streets, roads, ramps or entrances (including features and design details such as: round-abouts, culverts, signage, gateway treatments, noise wall alterations, sidewalks, bike lanes, bike pathways, paths, directional traffic islands, decorative features) to the existing road infrastructure;

b) Placing Fill

Re-grading, cutting and placing fill on lands beyond the road allowance along their frontage in accordance with City of London standards. In addition, all grading and restoration of road allowance along the development frontage if no claimable road works are required;

c) Topsoil and Sod

Topsoil and sod to the edge of any existing sidewalk fronting the development;

d) Tree Planting Planting of new trees fronting the development, except as provided in the Minor Road Works - Road Oversizing or Channelization policies.

e) Sidewalk Reinforcement

Any upgrade or reinforcement from a standard 100mm thickness sidewalk across the development’s new access;

f) Retaining Walls

Retaining walls along the development frontage, where acceptable to the City Engineer;

g) Temporary Works 100% of the cost of temporary asphalt sidewalks, roads, paths, swales along the frontage abutting arterials or primary collectors where installation in ultimate location is deemed premature;

h) Traffic Signals at Private Streets

Traffic signal installations at all private entrances and at public entrances which do not meet MTO warrants;

i) Other Works

Any other services, removals, relocations, etc., required including but not limited to, utility relocation, sidewalk alterations, and curb cuts;

j) Restoration and Damage

Restoration of any utility cuts, and or damage created by construction activities and /or construction traffic in and out of the development. including but not limited to daily removal of mud tracking, daily dust suppression, milling and paving of deteriorated

Page 62: 2019 DC Study External Stakeholder Meeting – …...legislation will have an impact on the City’s ability to dictate requirements. • Suggestion to have lead time, phase in, transitional

asphalt caused by construction traffic, grading of gravel shoulders to remove rutting caused by construction traffic;

k) Noise Attenuation Measures

All noise berms, window streets, fences and privately maintained noise walls;

l) Grading and BMPs Grading elements such as: swales, ditches, best management practices, (BMPs) and any other feature to address over land flow routes needs created by the development’s grading;

m) Paths and Walkways

Pedestrian paths, walkways, bridges, tunnels, including the related lighting and signage (Note: Parkways are constructed by the City and are specifically provided in the DC Background Study);

n) Utility Upgrades

The costs related to the upgrading of any utility plant, or the relocation of the same, unless necessitated by the roadwork;

o) Relocation and Replacement Costs

The relocation and/or replacement costs of any encroachment on the City’s road allowance or easement including but not limited to hedges, sprinklers systems and fences;

p) Street Lighting

Street lighting at intersections with existing roads where required by the development agreement.

SANITARY SEWERAGE WASTEWATER WORKS

Regional Trunk Sewers (CSRF - Sanitary Sewerage Wastewater)

All sewers required to service future development with a diameter greater than 450mm are considered to satisfy a regional benefit to growth and are to be identified as separate projects in the DC Background Study and are eligible for a claim from the CSRF - Sanitary SewerageWastewater. All sewers of any diameter required to service future development and that are identified as a strategic need by the City Engineer are considered to satisfy a regional benefit to growth and are to be identified as separate projects in the DC Background Study and are eligible for a claim from the CSRF - Sanitary SewerageWastewater. In order to be eligible for a claim as a Regional Trunk Sewer, the sewer must have no Private Drain Connections to individual residential units otherwise the “Sewer Oversizing” policy applies. Sewer Oversizing (CSRF - Minor Sanitary SewersWastewater)

Sanitary Sewers, which are not Regional Trunk Sewers, with all of the following attributes are eligible for a subsidy from the CSRF - Minor Sanitary SewersWastewater:

a) The sewer services external developable areas, and b) The sewer is greater than 250mm in diameter.

The oversized portion (>250mm) is eligible for a subsidy payable based on an average oversizing cost and is stated in terms of a $/m of pipe constructed. The oversizing subsidy amounts are reflected in Appendix 8-A. The oversizing subsidy amounts cover the cost per metre of all associated eligible costs including engineering, manholes, restoration, etc.

Commented [SJ4]: Policy addressing infill and

intensification to be added, but currently under development

Commented [SJ5]: Appendix under review.

Page 63: 2019 DC Study External Stakeholder Meeting – …...legislation will have an impact on the City’s ability to dictate requirements. • Suggestion to have lead time, phase in, transitional

Pumping Stations (CSRF - Sanitary SewerageWastewater)

The upgrading or construction of new regional pumping stations are to be identified as separate projects in the DC Background Study and are eligible for a claim from the CSRF - Sanitary Sewerage Wastewater. These projects must also be identified in the DC Background Study. A figure showing the location of all of these pumping stations is provided in the Sanitary Servicing DC Background Study (March 2014). Temporary Pumping Stations (Owner Cost)

The cost of any temporary pumping stations or forcemains is borne by the Owner. Approval of temporary works is at the discretion of the City Engineer. Where a temporary facility precedes the construction of a permanent facility, the Owner that requires the temporary facility will be required to also assist in making provision for the permanent facility (e.g. provide land for permanent facility) as a condition of approval for the temporary facility. In order for a temporary work to proceed there must first be provisions for the permanent work within the current DC Background Study. Wastewater Treatment Upgrades (CSRF - Sanitary SewerageWastewater)

All wastewater treatment upgrades are considered to satisfy a regional benefit to growth and are to be identified as separate projects in the DC Background Study and are eligible for a claim from the CSRF - Sanitary SewerageWastewater. Temporary Sanitary Sewerage Wastewater Systems (Owner Cost)

Costs of all sanitary sewagewastewater systems that are temporary or are not defined in the DC Background Charge Study shall be borne by the Owner. Approval of temporary works is at the discretion of the City Engineer. Where a temporary facility precedes the construction of a permanent facility, the Owner that requires the temporary facility will be required to also assist in making provision for the permanent facility (e.g. secure land for permanent facility) as a condition of approval for the temporary facility. In order for a temporary work to proceed there must first be provisions for the permanent work within the current DC Background Study. Local Service Costs (Owner Cost)

Any pipe or portion of a larger pipe that is less than or equal to 250mm in diameter are referred to as local works, and undertaken at the Owner’s expense. STORMWATER WORKS

Regional Trunk Sewers (CSRF- Major SWM WorksStormwater)

All sewers to be constructed within existing City owned lands that service multiple new development areas are considered to satisfy a regional benefit to growth and are to be identified as separate projects in the DC Background Study and are eligible for a claim from the CSRF- Major SWM WorksStormwater.

All sewers of any diameter required to service future development and that are identified as a strategic need by the City Engineer are considered to satisfy a regional benefit to growth and are eligible for a claim from the CSRF- Stormwater. Regional Open Channels (CSRF- Major SWM WorksStormwater)

Any open channel works identified through the Environmental Assessment process that are considered to satisfy a regional benefit to growth are to be identified as separate projects in the DC Background Study and are eligible for a claim from the CSRF- Major SWM WorksStormwater. Storm Sewer Oversizing (CSRF- Minor Storm WorksStormwater)

Storm Sewers with all of the following attributes are eligible for a subsidy from the CSRF - Minor Storm WorksStormwater:

Commented [SJ6]: Policy addressing Low Impact

Development (LID) to be added, but currently under

development.

Policy addressing infill and intensification to be added, but

currently under development

Page 64: 2019 DC Study External Stakeholder Meeting – …...legislation will have an impact on the City’s ability to dictate requirements. • Suggestion to have lead time, phase in, transitional

a) The sewer services external developable areas, and b) The sewer is greater than 1050mm in diameter.

The oversized portion (>1050mm) is eligible for a subsidy payable based on an average oversizing cost and is stated in terms of a $/m of pipe constructed. The oversizing subsidy amounts are reflected in Appendix 8-B. The oversizing subsidy amounts cover the cost per metre of all associated eligible costs including engineering, manholes, restoration, etc. Open Channel Oversizing (CSRF- Minor Storm WorksStormwater)

Open Channels with all of the following attributes are eligible for a subsidy from the CSRF - Minor Storm WorksStormwater:

a) An open channel design is required for the reason of inherent site drainage constraints

and the design has been accepted by the City Engineer, b) The open channel services external developable areas, and c) The open channel has a 2-year storm design flow cross-sectional area greater than a

1050mm sewer using the City’s minimum design standards. The oversized portion represents the cross-sectional area required in excess of a 1050mm sewer for a 2-year storm design. The oversizing subsidy will be calculated based on the additional cost of oversizing beyond an area equivalent to a 1050mm pipe size using the City’s minimum design standards for a 2-year storm design flow. The oversizing subsidy is payable based on an average oversizing cost in the form of a $/m of channel constructed as calculated by the Owner’s professionalconsulting engineer and as accepted by the City Engineer (or designate). An allowance of 15% will be added to the calculated oversizing amount to cover applicable engineering costs. Stormwater Management Works (CSRF- Major SWM WorksStormwater)

Environmental Assessment Complete

Any municipally owned or operated stormwater management works designed to provide capacity to facilitate growth that are identified through the Environmental Assessment process and are considered to satisfy a regional benefit to growth are to be identified as separate projects in the DC Background Study and are eligible for a claim from the CSRF- Major SWM WorksStormwater.

Environmental Assessment Not Complete

Stormwater Management Works for which an Environmental Assessment has not been completed that are anticipated to satisfy a regional benefit to growth are to be identified as separate area specific contingencies in the DC Background Study and are eligible for a claim from the CSRF- Major SWM WorksStormwater. Upon completion of the applicable Environmental Assessment (i.e. no outstanding Part 2 orders), a review of the related area specific contingency and the DC rate will be undertaken and, if required, a revision to the DC by-law will be made.

Stormwater Management Facility Land Policies (CSRF- Major SWM WorksStormwater)

With respect to land acquisition for storm water management facilities the value of the land shall be subject to review every five years and is established as follows: Non-Developable lands

Non-Developable lands may include designated flood plains, hazard lands, and natural heritage areas as defined in the City’s Official Plan or any area located outside the limit of development as determined through the development studies and/or draft plan or site plan process: $5,500/acre ($13,590/hectare)

Lands under existing open water are not claimable as defined by the London 2 year design storm high water elevation.

Commented [SJ7]: Appendix under review.

Commented [SJ8]: Section under review

Page 65: 2019 DC Study External Stakeholder Meeting – …...legislation will have an impact on the City’s ability to dictate requirements. • Suggestion to have lead time, phase in, transitional

Park Land

Lands set aside as a dedication for parks and not designated for development: $ Nil

Where there is a shared use of a stormwater or sanitary wastewater work such as a maintenance road/ pathway, the use and maintenance of the road/pathway shall be viewed as functioning solely for the sanitary wastewater or stormwater service use not the park use. The costs associated with the maintenance access path shall be borne by the related service’s CSRF.

Developable Lands

Developable lands are inside the urban growth boundary and included inside of the limit of development as established by the draft plan or site plan approval process: $125,000/acre ($308,880/hectare)

Lands Required Outside the Urban Growth Boundary

Where lands are required outside the Urban Growth Boundary for the purposes of stormwater management the value of the required lands will be determined via a property appraisal completed by the City to the satisfaction of the City Treasurer.

Legal Fees

Legal fees directly related to the land transfer may be claimable subject to the review and acceptance of the City Solicitor.

Major SWM Facility Inlet and Outlet Sewers within the SWM Block (CSRF- Major SWM WorksStormwater)

Any storm sewers within a Major SWM Facility block that are either upstream or downstream of a facility are considered to satisfy a regional benefit to growth and are eligible for a claim from the CSRF- Major SWM WorksStormwater. Major SWM Facility Outlet Sewers outside the SWM Block (CSRF- Major SWM Works or CSRF- Minor Storm WorksStormwater)

Any major SWM facility outlet sewer that extends outside the SWM block facility is considered to satisfy a regional benefit to growth and is eligible for a claim from the CSRF- Major SWM WorksStormwater if the outlet sewer is not also used to provide drainage to a development adjacent to the outlet sewer.

In the event that all or a portion of the outlet sewer outside the SWM block is used to provide drainage to a development adjacent to the outlet sewer then the portion of the outlet sewer downstream from the adjacent development is eligible for “Storm Sewer Oversizing” as described above. Local Service Costs (Owner Cost)

Any pipe or portion of a larger pipe that is less than or equal to 1050 mm in diameter are referred to as local works, and undertaken at the Owner’s expense. Temporary Storm Sewers (Owner Cost)

Costs of all storm sewer systems that are temporary or not defined in the DC Background Charge Study shall be borne by the Owner. In order for a temporary work to proceed there must first be provisions for the permanent work within the current DC Background Study. Temporary Stormwater Management Works (Owner Cost)

Any temporary works or works not included in the approved DC Background Study are at the sole expense of the Owner including operation, maintenance and decommissioning. Approval of temporary works is at the discretion of the City Engineer. Where a temporary facility precedes the construction of a permanent facility, the Owner that requires the temporary facility will be required to also assist in making provision for the permanent facility (e.g. secure land for permanent facility) as a condition of approval for the temporary facility. In order for a temporary

Page 66: 2019 DC Study External Stakeholder Meeting – …...legislation will have an impact on the City’s ability to dictate requirements. • Suggestion to have lead time, phase in, transitional

work to proceed there must first be provisions for the permanent work within the current DC Background Study.

Best management practices or private drainage systems are not claimable unless identified through the Environmental Assessment process as being required to meet a regional benefit to growth.

The construction of road side ditches, swales, and overland flow routes are not eligible for claim from the City Services Reserve Fund - Stormwater ManagementCSRF - Stormwater.

WATER DISTRIBUTION

Major Watermains (CSRF-Water Distribution)

All watermains required to service future development greater than or equal to 400mm in diameter are considered to satisfy a network wide benefit to growth and are to be identified separately as projects in the DC Background Study and are eligible for a claim from the CSRF-Water Distribution.

All watermains of any diameter required to service future development and that are identified as a strategic need by the City Engineer are considered to satisfy a regional benefit to growth and are eligible for a claim from the CSRF- Water Distribution.

Watermain Oversizing (CSRF-Water Distribution)

Watermains with the all of the following attributes are eligible for a subsidy from the CSRF-Water Distribution:

a) The watermain services external developable areas, and b) The watermain is greater than 250mm in diameter and less than 400mm in diameter.

The oversized portion (>250mm) is eligible for a subsidy payable based on an average oversizing cost and is stated in terms of a $/m of pipe constructed. The oversizing subsidy amounts are identified in Appendix 8-C and are to be payable from the City Services Reserve Fund. Payment of claims from the City Services Reserve fund is subject to budget approval.The oversizing subsidy amounts cover the cost per metre of all associated eligible costs including engineering, appurtenances, restoration, etc.

Water Facilities (CSRF-Water Distribution)

Where the upgrading or construction of new public water booster pumping stations and reservoir projects are designed to increase capacity or improve service to acceptable standards and as a result of growth, these works are eligible for a claim from the CSRF-Water Distribution. These projects must also be identified in the DC Background Study. Temporary Facilities (Owner Cost)

Where a temporary facility precedes the construction of a permanent facility, the Owner that requires the temporary facility will be required to also assist in making provision for the permanent facility (e.g. secure land for permanent facility) as a condition of approval for the temporary facility. Approval of temporary works is at the discretion of the City Engineer. In order for a temporary work to proceed there must first be provisions for the permanent work within the current DC Background Study.

Local Service Costs (Owner Cost)

Any watermain or portion of a larger watermain that is less than or equal to 250mm in diameter is referred to as “local works”, and undertaken at the Owner’s expense.

Commented [SJ9]: Policy addressing infill and

intensification to be added, but currently under development

Commented [SJ10]: Appendix under review.

Commented [SJ11]: Sentence included so similar to

Wastewater Oversizing

Page 67: 2019 DC Study External Stakeholder Meeting – …...legislation will have an impact on the City’s ability to dictate requirements. • Suggestion to have lead time, phase in, transitional

PARKS Parkland Development (Owner Cost)

Parkland Development costs to bring Neighbourhood Parks, District Parks, Sports Parks, Urban Parks and Civic Spaces to a base condition shall be borne by the Owner. This includes grading, seeding, servicing, fencing and the associated engineering and landscape architect design costs as required by City standards. For Open Space, Woodland Parks and Environmentally Significant Areas (ESAs), costs for fencing as required by City standards, and for the establishment of mitigation measures and development limits as outlined in an approved Environmental Impact Study shall be borne by the Owner. Where the Owner enhances Parkland Development above City standards, these costs shall be borne by the Owner. Cul-de-sac Islands, Roundabout Islands and Window Streets (Owner Cost)

Development costs for landscape features, cul-de-sac islands, roundabout islands and window streets shall be borne by the Owner. This includes grading, seeding, landscaping, fencing, plantings and the associated engineering and landscape architect design costs as required by City standards. Parkland Development (CSRF – Parks & Recreation)

Parkland infrastructure beyond the basic parkland development standard noted above may be eligible for a claim from the CSRF – Parks & Recreation. Approval of Owner constructed pathways and parkland infrastructure shall be at the discretion and approval of the City and outlined in the registered Agreement.

Commented [SJ12]: New Policy