Solids Management The Perfect Storm January 26, 2018 2018 Wastewater Administrators Conference Majid Khan PhD, Director of Operations, GLWA Dan Alford PE, Director of Engg. & Maint., GLWA Ed Hogan PE, Vice President, Wade-Trim

2018 Wastewater Administrators Conference€¦ · 2018 Wastewater Administrators Conference Majid Khan PhD, Director of Operations, GLWA Dan Alford PE, Director of Engg. & Maint.,

  • Upload
    others

  • View
    0

  • Download
    0

Embed Size (px)

Citation preview

Page 1: 2018 Wastewater Administrators Conference€¦ · 2018 Wastewater Administrators Conference Majid Khan PhD, Director of Operations, GLWA Dan Alford PE, Director of Engg. & Maint.,

Solids Management – The Perfect Storm

January 26, 2018

2018 Wastewater Administrators Conference

Majid Khan PhD, Director of Operations, GLWA

Dan Alford PE, Director of Engg. & Maint., GLWA

Ed Hogan PE, Vice President, Wade-Trim

Page 2: 2018 Wastewater Administrators Conference€¦ · 2018 Wastewater Administrators Conference Majid Khan PhD, Director of Operations, GLWA Dan Alford PE, Director of Engg. & Maint.,

WATER RESOURCE RECOVERY FACILITY

(WRRF) OVERVIEW

FeCl3

SO2

FeCl3

SODIUM BI SULFITE

SODIUM HYPO CHLORITE

PRIMARY CLARIFIERS

AERATION TANKS

SECONDARY CLARIFIERS

PUMP STA 1

PUMP STA 2

BIOSOLIDS DRYER

FACILITY

1° SLUDGE PROCESSING

2° SLUDGE PROCESSING

DEWATERING PRESSES

DEWATERING CENTRIFUGES SLUDGE

INCINERATION

SLUDGE OFFLOADING

JUNCTION CHAMBER

PROCESS WATER

DRO

SLUDGE STORAGE

CHLORINE

Page 3: 2018 Wastewater Administrators Conference€¦ · 2018 Wastewater Administrators Conference Majid Khan PhD, Director of Operations, GLWA Dan Alford PE, Director of Engg. & Maint.,

RRO Disinfection – The Initial Challenge

NPDES Permit requires GLWA to

complete construction of the

Rouge River Outfall (RRO)

Disinfection Project and place

the facilities into full operation

on or before April 1, 2019.

GLWA awards a Progressive

Design-Build contract to deliver

the RRO Disinfection Project

Page 4: 2018 Wastewater Administrators Conference€¦ · 2018 Wastewater Administrators Conference Majid Khan PhD, Director of Operations, GLWA Dan Alford PE, Director of Engg. & Maint.,

RRO Disinfection – The Initial Challenge

Page 5: 2018 Wastewater Administrators Conference€¦ · 2018 Wastewater Administrators Conference Majid Khan PhD, Director of Operations, GLWA Dan Alford PE, Director of Engg. & Maint.,

Conduit Inspections – Sediment Identified

Page 6: 2018 Wastewater Administrators Conference€¦ · 2018 Wastewater Administrators Conference Majid Khan PhD, Director of Operations, GLWA Dan Alford PE, Director of Engg. & Maint.,

Deposited Solids in the Conduits

Page 7: 2018 Wastewater Administrators Conference€¦ · 2018 Wastewater Administrators Conference Majid Khan PhD, Director of Operations, GLWA Dan Alford PE, Director of Engg. & Maint.,

RRO Disinfection – The Initial Challenge

1. Sample Collected from deposited solids (single sample)

2. Analysis of sample lead to a determination that the solids were hazardous, based on Resource Conservation & Recovery Act (RCRA) and Toxicity-Characteristic Leaching Procedure (TCLP)

3. Plan of Action to remove the deposited solids:

• Construct temporary dewatering facility

• Install 2 belt filter press rental units

• Provide for sluicing, pumping, hauling and filtrate routing

• Perform all solids removal operations including landfill disposal in accordance with hazardous waste regulations

Page 8: 2018 Wastewater Administrators Conference€¦ · 2018 Wastewater Administrators Conference Majid Khan PhD, Director of Operations, GLWA Dan Alford PE, Director of Engg. & Maint.,

RRO Disinfection – The Initial Challenge

1. Financial impacts of dewatering, trucking and landfill as hazardous waste to GLWA Capital budget and to the RRO Project budget

2. Total volume removed and associated cost and time (duration)

3. Schedule implications of this removal process vs permit requirements

Page 9: 2018 Wastewater Administrators Conference€¦ · 2018 Wastewater Administrators Conference Majid Khan PhD, Director of Operations, GLWA Dan Alford PE, Director of Engg. & Maint.,

Setting the Stage – the Storm is Forming

• Complex-II Incineration Fire

• Complex-I Incineration Decommissioning

• Biosolids Dryer Facility Performance Testing

• Regulatory Requirements for Solids Inventory & Disposal

Page 10: 2018 Wastewater Administrators Conference€¦ · 2018 Wastewater Administrators Conference Majid Khan PhD, Director of Operations, GLWA Dan Alford PE, Director of Engg. & Maint.,

Setting the Stage – the Storm is Forming

The Complex II Incineration

Facility undergoing

Clean Air Act-mandated upgrade for Maximum Achievable Control-

Technology (MACT) compliance suffers a

Major fire on March 4, 2016 destroying

sludge conveyance, incinerators, and control equipment.

Page 11: 2018 Wastewater Administrators Conference€¦ · 2018 Wastewater Administrators Conference Majid Khan PhD, Director of Operations, GLWA Dan Alford PE, Director of Engg. & Maint.,

Damaged Conveyors at Complex-II

Incineration

Page 12: 2018 Wastewater Administrators Conference€¦ · 2018 Wastewater Administrators Conference Majid Khan PhD, Director of Operations, GLWA Dan Alford PE, Director of Engg. & Maint.,

Fire Damage at Complex-II Incineration

Page 13: 2018 Wastewater Administrators Conference€¦ · 2018 Wastewater Administrators Conference Majid Khan PhD, Director of Operations, GLWA Dan Alford PE, Director of Engg. & Maint.,

Fire Damage at Complex-II Incineration

Page 14: 2018 Wastewater Administrators Conference€¦ · 2018 Wastewater Administrators Conference Majid Khan PhD, Director of Operations, GLWA Dan Alford PE, Director of Engg. & Maint.,

Fire Damage at Complex-II Incineration

Page 15: 2018 Wastewater Administrators Conference€¦ · 2018 Wastewater Administrators Conference Majid Khan PhD, Director of Operations, GLWA Dan Alford PE, Director of Engg. & Maint.,

Fire Damage at Complex-II Incineration

Page 16: 2018 Wastewater Administrators Conference€¦ · 2018 Wastewater Administrators Conference Majid Khan PhD, Director of Operations, GLWA Dan Alford PE, Director of Engg. & Maint.,

Setting the Stage – the Storm is Forming

Complex I Incineration Facility was in the process of being retired.

Operation of this Facility would be a violation of the Clean Air Act-

mandated upgrade for Maximum Achievable Control Technology

(MACT) pursuant to the Sewer Sludge Incinerations (SSI) rules.

Page 17: 2018 Wastewater Administrators Conference€¦ · 2018 Wastewater Administrators Conference Majid Khan PhD, Director of Operations, GLWA Dan Alford PE, Director of Engg. & Maint.,

Setting the Stage – the Storm is Forming

In addition to the NPDES permit and the CAA requirements, GLWA was operating under an Administrative Consent Order.

The ACO required the WRRF to maintain average 10 day solids dewatering, conveyance, and disposal capacity of 850 dtpd, and average solids inventory of less than 750 dtpd

Page 18: 2018 Wastewater Administrators Conference€¦ · 2018 Wastewater Administrators Conference Majid Khan PhD, Director of Operations, GLWA Dan Alford PE, Director of Engg. & Maint.,

If that weren’t enough to contend with…

Page 19: 2018 Wastewater Administrators Conference€¦ · 2018 Wastewater Administrators Conference Majid Khan PhD, Director of Operations, GLWA Dan Alford PE, Director of Engg. & Maint.,

If that weren’t enough to contend with…Another project addressing requirements pursuant to the NPDES permit, the ACO, the Renewable Operating Permit, (ROP) and the Clean Air Act (CAA) was the construction of the Biosolids Dryer Facility (BDF)

The BDF receives thickened and blended sludge, provides dewatering and drying, and produces pelletized Class-A exceptional quality material suitable for land application. The BDF is the critical component of the 20-year Long-Term Solids Disposal Plan

Page 20: 2018 Wastewater Administrators Conference€¦ · 2018 Wastewater Administrators Conference Majid Khan PhD, Director of Operations, GLWA Dan Alford PE, Director of Engg. & Maint.,

If that weren’t enough to contend with…

The BDF has a contractual requirement to provide an annual average disposal

capacity of 200 dtpd, with firm capacity of 316 dtpd, and a total capacity of 420

dtpd.

Acceptance of the BDF was, in part, dependent of successfully passing a series of

performance tests, culminating in a demonstration of 5 continuous days (120

continuous hours) with all 4 process trains in operation (420 dtpd).

On a routine dry weather day, influent solids loading at this time of year was about

280 - 300 dtpd, not sufficient to support a 5-day continuous operations

performance acceptance test of the BDF.

Demonstration of contract performance was dependent on the WRRF delivering

not less than 420 dtpd for a minimum of 5 continuous days.

Page 21: 2018 Wastewater Administrators Conference€¦ · 2018 Wastewater Administrators Conference Majid Khan PhD, Director of Operations, GLWA Dan Alford PE, Director of Engg. & Maint.,

Summarizing

• The NPDES Permit-required RRO Disinfection Project encounters 10,000cy of deposited solids in Chlorine Contact Conduit

• Deposited solids are assessed as hazardous – significantly impacting project schedule, budget, scope, and possibly compliance

• Complex II Incineration and Dewatering suffers catastrophic fire

• Complex I Incineration being shut down pursuant to the SSI rules; Operation of the facility will be in direct violation of the CAA and the ROP

• The ACO 10-day average solids dewatering, conveyance and disposal capacity of 850 dtpd

• The ACO also requires average solids inventory less than 750 dtpd

• The BDF is in the process of demonstrating performance and acceptance testing, including a requirement for a 5 day continuous test at 420 dtpd

• Dry weather solids loading at this time of year averages 280 -300 dtpd, not sufficient to conduct the performance testing.

Page 22: 2018 Wastewater Administrators Conference€¦ · 2018 Wastewater Administrators Conference Majid Khan PhD, Director of Operations, GLWA Dan Alford PE, Director of Engg. & Maint.,

Developing an Action Plan

First – reevaluate the sample collection, laboratory analyses and decision process that resulted in the determination that the deposited solids were characteristically hazardous.

• The initial hazardous determination was based on a single sample, collected from the deposited solids and submitted for RCRA TCLP as though it was a contaminated waste

• Concurrent with the pumping, dewatering, hauling and landfill operations as hazardous waste, TCLP sample collection and analyses were performed monthly

• Followup comprehensive sample collection and analyses of the deposited solids supported a confirmation that the solids were non-hazardous

• Domestic exclusion provision

Page 23: 2018 Wastewater Administrators Conference€¦ · 2018 Wastewater Administrators Conference Majid Khan PhD, Director of Operations, GLWA Dan Alford PE, Director of Engg. & Maint.,

Developing an Action Plan

Second – closing down the slurry generation, pumping, dewatering, hauling and landfill hazardous waste disposal operation

• devise an approach to pump the slurry under controlled conditions back to the head of the plant

• use on-line monitoring of solids concentration, flow and loading rates to ensure that pumping would not adversely affect the plant processes

• suspending pumping operations during wet weather events to avoid excessive solids loading and associated operational and regulatory compliance issues

• Verify that the solids removal process will not adversely affect the scheduled completion of the RRO Disinfection project

Page 24: 2018 Wastewater Administrators Conference€¦ · 2018 Wastewater Administrators Conference Majid Khan PhD, Director of Operations, GLWA Dan Alford PE, Director of Engg. & Maint.,

Developing an Action Plan

Third - using the deposited solids that were pumped to the head of the plant to supplement the normal WRRF solids loading

• thereby ensuring that there would be a continuous source of solids (in excess of 420 dtpd) that would feed the BDF and

• Allowing for scheduling of the 5-day performance test to demonstrate the ability of the process equipment to meet contractual requirements.

• As well as having a reliable continuous source of solids should the test need to be extended or re-run.

Page 25: 2018 Wastewater Administrators Conference€¦ · 2018 Wastewater Administrators Conference Majid Khan PhD, Director of Operations, GLWA Dan Alford PE, Director of Engg. & Maint.,

Solids Removal Set-up in Progress

Page 26: 2018 Wastewater Administrators Conference€¦ · 2018 Wastewater Administrators Conference Majid Khan PhD, Director of Operations, GLWA Dan Alford PE, Director of Engg. & Maint.,

Solids Removed from the Conduits

Page 27: 2018 Wastewater Administrators Conference€¦ · 2018 Wastewater Administrators Conference Majid Khan PhD, Director of Operations, GLWA Dan Alford PE, Director of Engg. & Maint.,

Closing and Summary

The performance test was able to be conducted without any concern whether there would be sufficient solids; the BDF is now operating at the contractual process rates

Page 28: 2018 Wastewater Administrators Conference€¦ · 2018 Wastewater Administrators Conference Majid Khan PhD, Director of Operations, GLWA Dan Alford PE, Director of Engg. & Maint.,

Complex-I Incinerators Permanently

Decommissioned Effective June 01, 2017

Page 29: 2018 Wastewater Administrators Conference€¦ · 2018 Wastewater Administrators Conference Majid Khan PhD, Director of Operations, GLWA Dan Alford PE, Director of Engg. & Maint.,

Closing and Summary continuedThe Complex II Incineration facility has been fully returned to service to comply with MACT emission requirements

Page 30: 2018 Wastewater Administrators Conference€¦ · 2018 Wastewater Administrators Conference Majid Khan PhD, Director of Operations, GLWA Dan Alford PE, Director of Engg. & Maint.,

Closing and Summary continued

The Complex II Incineration facility has been fully returned to service to comply with MACT emission requirements

Page 31: 2018 Wastewater Administrators Conference€¦ · 2018 Wastewater Administrators Conference Majid Khan PhD, Director of Operations, GLWA Dan Alford PE, Director of Engg. & Maint.,

Closing and Summary continued

The Complex II Incineration facility has been fully returned to service to comply with MACT emission requirements

Page 32: 2018 Wastewater Administrators Conference€¦ · 2018 Wastewater Administrators Conference Majid Khan PhD, Director of Operations, GLWA Dan Alford PE, Director of Engg. & Maint.,

Closing and Summary continuedThe Complex II Incineration facility has been fully returned to service to comply with MACT emission requirements

Page 33: 2018 Wastewater Administrators Conference€¦ · 2018 Wastewater Administrators Conference Majid Khan PhD, Director of Operations, GLWA Dan Alford PE, Director of Engg. & Maint.,

Closing and Summary continued

• The RRO Disinfection project is proceeding on schedule

• GLWA has consistently maintained compliance throughout, with both the NPDES permit and ACO solids handling and disposal capacity requirements

• GLWA and the WRRF not only survived the perfect storm….we took advantage of the opportunity and made it work for us!

Page 34: 2018 Wastewater Administrators Conference€¦ · 2018 Wastewater Administrators Conference Majid Khan PhD, Director of Operations, GLWA Dan Alford PE, Director of Engg. & Maint.,

Closing and Summary