199
2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Project Maps 1 Infrastructure Project Phase Map Operations & Training 2 Automatic External Defibrillators (AED) Replacement Program 3 Fire Helmet Replacement 4 Fire Hose Replacement 5 Fire Training Facility Temporary Expansion 6 Heavy Extrication Equipment Replacement 7 Protective Hood Replacement 8 Self Contained Breathing Apparatus - 45 Minute Air Bottle Replacement 9 Thermal Imaging Camera Replacement 10 APLI (Applications, Permits, Licenses and Inspections) Expansion - Phase 3 11 Citizen Relationship Management (CRM) Solution 12 CMMS Improvement Project - Cityworks 13 ERP Sustainment Program Corporate Asset Management 14 Huronia and Big Bay Point Large Diameter Watermain Condition Assesment 15 Pavement Condition Assessment 16 Stormwater Management Asset Management Plan Update Design & Construction 17 Albert Street New Drainage Outlet 18 Anne and Innisfil Railway Crossing Upgrades - BCRY 19 Anne Street - New 3N Booster Pump Station & 2N Booster Pump Station Reconstruction 20 Anne Street North Pavement Rehabilitation - Neelands to Sunnidale 21 Ashford Drive and Madelaine Drive New 750 mm Transmission Watermain - Big Bay Point to Mapleview 22 Baldwin Lane Watermain Replacement - Marshall to Bayview 23 Bayfield Street Pavement Rehabilitation - Cundles to Coulter 24 Bayfield Street Water Tower - Repairs and Interior Lining Replacement 25 Bayview Drive New Transmission Watermain Road Expansion - Little Avenue to Big Bay Point Road 26 Big Bay Point Road ROW Expansion - Bayview to Huronia 27 Biosolids Facility Roof Coating Rehabilitation 28 Biosolids Storage Facility Lagoons 1, 2 & 3 Hydraulic Upgrades and Overflow Protection Upgrades 29 Bryne Drive New Road Construction - Harvie to North of Caplan 30 Bryne Drive New Road Construction - Harvie to South of Essa 31 Bunker's Creek Culvert Expansion - Bradford Street 32 Bunkers Creek Culvert Expansion - Innisfil Street and Watercourse Upgrade - Innisfil to Bradford 33 Duckworth Street New Transmission Watermain and ROW Expansion - Bell Farm to St. Vincent 34 Dunlop Street West ROW Replacement - Eccles to Toronto 36 Dyments Creek Channel Improvements - Sanford to Bradford 37 Dyments Creek Culvert Expansion - Bradford St. 38 End of Life Pavement Replacement Program 39 Essa Road New Transmission Watermain and Road Expansion - Mapleview to Athabaska (City) 40 Ferndale Drive North ROW Expansion - Dunlop to Tiffin 41 Glen Echo Drive and College Crescent Watermain and Pavement Replacement - Lonsdale to Nelson 42 Gunn Street ROW Replacement - Peel to St. Vincent 43 Harvie Road and Big Bay Point Road New Crossing - Highway 400 44 Harvie Road ROW Expansion - Essa to Bryne 45 Henry Street ROW Replacement - Frances to Eccles 46 HNS Allandale A Neighbourhood Renewal Program Engineering Department Centre for Continuous Improvement Barrie Fire and Emergency Services Department

2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

  • Upload
    others

  • View
    7

  • Download
    0

Embed Size (px)

Citation preview

Page 1: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

2018 Capital Budget Project Detail ReportsTable of Contents

Infrastructure Project Maps

1 Infrastructure Project Phase Map

Operations & Training

2 Automatic External Defibrillators (AED) Replacement Program

3 Fire Helmet Replacement

4 Fire Hose Replacement

5 Fire Training Facility Temporary Expansion

6 Heavy Extrication Equipment Replacement

7 Protective Hood Replacement

8 Self Contained Breathing Apparatus - 45 Minute Air Bottle Replacement

9 Thermal Imaging Camera Replacement

10 APLI (Applications, Permits, Licenses and Inspections) Expansion - Phase 3

11 Citizen Relationship Management (CRM) Solution

12 CMMS Improvement Project - Cityworks

13 ERP Sustainment Program

Corporate Asset Management

14 Huronia and Big Bay Point Large Diameter Watermain Condition Assesment

15 Pavement Condition Assessment

16 Stormwater Management Asset Management Plan Update

Design & Construction

17 Albert Street New Drainage Outlet

18 Anne and Innisfil Railway Crossing Upgrades - BCRY

19 Anne Street - New 3N Booster Pump Station & 2N Booster Pump Station Reconstruction

20 Anne Street North Pavement Rehabilitation - Neelands to Sunnidale

21 Ashford Drive and Madelaine Drive New 750 mm Transmission Watermain - Big Bay Point to Mapleview

22 Baldwin Lane Watermain Replacement - Marshall to Bayview

23 Bayfield Street Pavement Rehabilitation - Cundles to Coulter

24 Bayfield Street Water Tower - Repairs and Interior Lining Replacement

25 Bayview Drive New Transmission Watermain Road Expansion - Little Avenue to Big Bay Point Road

26 Big Bay Point Road ROW Expansion - Bayview to Huronia

27 Biosolids Facility Roof Coating Rehabilitation

28 Biosolids Storage Facility Lagoons 1, 2 & 3 Hydraulic Upgrades and Overflow Protection Upgrades

29 Bryne Drive New Road Construction - Harvie to North of Caplan

30 Bryne Drive New Road Construction - Harvie to South of Essa

31 Bunker's Creek Culvert Expansion - Bradford Street

32 Bunkers Creek Culvert Expansion - Innisfil Street and Watercourse Upgrade - Innisfil to Bradford

33 Duckworth Street New Transmission Watermain and ROW Expansion - Bell Farm to St. Vincent

34 Dunlop Street West ROW Replacement - Eccles to Toronto

36 Dyments Creek Channel Improvements - Sanford to Bradford

37 Dyments Creek Culvert Expansion - Bradford St.

38 End of Life Pavement Replacement Program

39 Essa Road New Transmission Watermain and Road Expansion - Mapleview to Athabaska (City)

40 Ferndale Drive North ROW Expansion - Dunlop to Tiffin

41 Glen Echo Drive and College Crescent Watermain and Pavement Replacement - Lonsdale to Nelson

42 Gunn Street ROW Replacement - Peel to St. Vincent

43 Harvie Road and Big Bay Point Road New Crossing - Highway 400

44 Harvie Road ROW Expansion - Essa to Bryne

45 Henry Street ROW Replacement - Frances to Eccles

46 HNS Allandale A Neighbourhood Renewal Program

Engineering Department

Centre for Continuous Improvement

Barrie Fire and Emergency Services Department

Page 2: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

2018 Capital Budget Project Detail ReportsTable of Contents

Design & Construction

47 HNS Allandale B Neighbourhood Renewal Program

48 HNS Queens Park A1 Neighbourhood Renewal Program

49 Huronia Road New Trunk Sanitary Sewer and Road Replacement - Lockhart to McKay

50 Huronia Road Pavement Holding Strategy - Little to Yonge

51 Hurst Drive Pavement Rehabilitation - Cox Mill to Golden Meadow

52 Interim Watermain Replacement Pilot Program

53 Kidds Creek and Sophia Creek Storm Pond Upgrades - Irwin (KD03), Ford (KD06), and Ottaway (SP03)

54 Lampman to Anne New Transmission Watermain and Lampman to Leacock ROW Rehabilitation

55 Lovers Creek Channel Rehabilitation - Adjacent to Brunton Park

56 Mapleview Dr E Road Expansion & New Trunk Watermain - East of Yonge to Prince William (City)

57 Mapleview Drive East Improvements - Country Lane to Yonge

58 Mapleview Drive West Sanitary Forecemain Twinning and Pumping Station 5 Upgrades and Expansion

59 McKay Road New Interchange - Highway 400

60 McKay Road New Trunk Sanitary Sewer and Road Expansion - Hwy 400 to Huronia

61 Minets Point Sewage Pump Station Relocation

62 PRV Chamber Replacement Program

63 Road Resurfacing Program

64 Sandringham Drive New 600mm Transmission Watermain - Big Bay Point to Mapleview

65 Sanitary Servicing - Royal Oak, Bay, Cottage

66 Sewer Rehabilitation Program

67 St. Vincent Street Watermain Replacement - S of Highway 400 to Bell Farm

68 Water Service and Backflow Prevention Upgrades for Parks and Open Spaces

69 Watermain Cathodic Protection Program

70 Watermain CIPP Lining Program

71 Wellington D1 Neighbourhood Renewal Program

72 Wellington D2 Neighbourhood Renewal Program

73 WwTF Biosolids Storage Tank Mixers

74 WwTF Chemical Building Upgrade

75 WwTF Cogeneration Building Ventilation Upgrades

76 WwTF Electrical Substation and Transformer Upgrade

77 WwTF In-plant Peak Attenuation/Equalization Tank Retrofit

78 WwTF MBR Project Concrete Tanks Rehabilitation

79 WwTF Sludge Thickening System Process - Polymer System Replacement

80 WwTF UNOX To Aeration Tanks Conversion (Phase 1)

81 Yonge Street ROW Expansion - Mapleview to Lockhart

Development Services

82 Big Bay Point New Transmission Watermain and Road Expansion - Prince William to Street N (Developer)

83 Essa Road New Transmission Watermain and Road Expansion - Athabaska to TCP (Developer)

84 Hewitt's Creek New Trunk Sanitary Sewer - Mapleview to Lockhart (Developer)

85 Mapleview Dr E New Sanitary Sewer & Road Expansion - Prince William to Phase 1 Boundary (Developer)

86 Mapleview Drive E New Transmisison Watermain - Yonge to Prince William (Developer)

87 McKay Road ROW Expansion - County Road 27 to Highway 400 (Developer)

88 Salem Road New Transmission Watermain and Road Expansion - County Road 27 to Veterans (Developer)

89 Veterans Drive New Trunk Watermain and Road Expansion - Salem to City Limits (Developer)

Infrastructure Planning

90 Annual Parking Lot Improvement Program

91 Bell Farm Road ROW Expansion - St. Vincent to Duckworth

92 City Wide Cycling Network Program

93 Dunlop Interchange (Barrie)

94 Dunlop Street Right of Way Expansion - Cedar Pointe to Anne (outside of CAH limits)

95 Infrastructure Master Plans / DC Technical Studies Update

96 Painswick Park Rehabilitation

97 Park Condition Assessment Study

Engineering Department

Page 3: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

2018 Capital Budget Project Detail ReportsTable of Contents

Infrastructure Planning

98 Playground Replacement Program

99 Ross, Collier, Bayfield Intersection Realignment

100 Stormwater Utility Finance Study

101 Tennis Court Rehabilitation Program

Environmental Operations

102 Barrie Environmental Centre Recycling Depot Expansion and associated need for additional 40 Yard Bins

103 Barrie Environmental Centre Waste and Recycling Depot Repair

104 Barrie Landfill Household Hazardous Waste Depot Upgrades

105 Historic Waste Site Landfill Gas New Preventative/Remedial Action

106 Public Space Bin Upgrade Program

Wastewater Operations

107 WwTF Drum Replacement - Rotary Drum Thickeners

108 WwTF New PeCOD Unit for Determination of COD - Lab

109 WwTF Sand Filter Controls & Instrumentation Replacement

110 WwTF Unox Tank Isolation Gate Replacement

Water Operations

111 Secondary Plan Area New Bulk Water Filling Station

Corporate Facilities

112 Allandale Recreation Centre Condenser Replacement - Blue Arena

113 Allandale Recreation Centre Sprinkler Replacement - Blue Arena

114 Barrie Molson Centre Elevator Replacement

115 Barrie - Simcoe Emergency Services Campus - Phase 1

116 BFES Station 3 Facility Rehabilitation

117 BFES Station 3 Interior Renovations

118 BFES Station 4 Renovation

119 BFES Station 6 New Building Development

120 City Hall Customer Contact Centre Renovation

121 City Hall Expansion

122 City Hall Parking Garage Rehabilitation

123 Fisher Auditorium Redevelopment

124 Holly Community Centre Pool Deck Rehabilitation

125 Main Library HVAC Rehabilitation

126 Marina Boat Launch Floating Finger Dock Replacement

127 Marina Dock Replacement - E, I and J

128 Operations Centre Building Renovation

129 Painswick Library Flat Roof Repair

130 Secondary Plan Area Municipal Campus New Site Development

131 Tiffin Boat Launch Breakwall Repair

132 Year Round Downtown Market New Development

Energy Management

133 Energy Conservation Program

134 Holly Community Centre Building Automation System Replacement

135 2018-2019 DC Background Study Update

136 eTendering Platform New System

Finance Department

Facilities Department

Environmental Services Department

Engineering Department

Page 4: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

2018 Capital Budget Project Detail ReportsTable of Contents

Application Services

137 Server and Desktop Software Program

Technology Services

138 Application Resiliency Program

139 Barrie Fire and Emergency Services Technology Program

140 Corporate Communications Infrastructure Program

141 Corporate PC Infrastructure Program

142 Mobility Technology Program

143 Network Infrastructure Upgrade Program

144 Network Technology Infrastructure Program

145 Public Safety Communication Program

146 Server and Storage Technology Infrastructure Program

147 Corporate Records & Information Management Strategy System Upgrade

148 Official Plan Comprehensive Update

Fleet Operations

149 10 Foot Lawn Mower Replacement (06-2032) - Parks

150 16 Foot Lawn Mower Replacement (06-2033)

151 6 Foot Lawn Mower Replacement (06-2027) - Parks

152 6 Foot Lawn Mower Replacement (06-2028) - Parks

153 6 Foot Lawn Mower Replacement (06-2029) - Parks

154 Asphalt Hot Box New Purchase - Roads Operations

155 Asphalt Roller Replacement - Roads Operations

156 Conventional Transit Bus Replacement 2018 (PTIF)

157 Downtown Sidewalk Sweeper Replacement

158 Downtown Winter Control Intersection Clearing Equipment New Purchase

159 Environmental Investigation Van Replacement (03-1021) - Environmental Services

160 Loader Replacement (06-8001) - Landfill

161 Mechanical Street Sweeper Replacement (03-7002) - Roads

162 Mechanical Street Sweeper Replacement (03-7006)

163 Medium Dump Truck Replacement (04-3003) - Roads

164 Pickup Truck Replacement (04-1028) - Roads and Parks

165 Pickup Truck Replacement (04-1040) - Roads

166 Pickup Truck Replacement (06-1048) - Roads

167 Pickup Truck Replacement (06-1052) - Facilities

168 Pickup Truck Replacement (08-1071) - Roads

169 Rock Truck and Excavator New Purchase - Landfill

170 Roll Off Truck New Purchase - Environmental Services

171 Sander/Salter Replacement (08-5019) - Roads

172 Sander/Salter Replacement (08-5020) - Roads

173 Tractor Replacement (01-201) - Roads

174 Van Replacement (04-1033) - Environmental Services

Road, Storm & Rail Operations

175 21-31 Commerce Park Sidewalk Replacement

176 Downtown Sidewalk Replacement Program

177 Pine Dr. Subdivision Retaining Wall Removal

178 Road Weather Information System (RWIS) Replacement

179 Storm Water Management Pond Repair - KD02

Roads, Parks, and Fleet Department

Planning & Building Services Department

Legislative Services Department

Information Technology Department

Page 5: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

2018 Capital Budget Project Detail ReportsTable of Contents

Traffic & Parking Services

180 Accessible Pedestrian Pushbutton New Installation

181 Alectra Pole Betterment and Capital Upgrade Program - Street Lighting Equipment Relocation

182 Pay & Display Machine Replacement

183 Traffic Signal Cabinet Replacement Cundles and Harding IPS

184 Traffic Signal Cabinet Replacement Grove Street IPS

185 Traffic Signal Cabinet Replacement Program Blake and Parkview

186 Traffic Signal Cabinet Replacement Program Blake and St. Vincent

187 Traffic Signal Cabinet Replacement Program St. Vincent and Rose

188 Traffic Signal Cabinet Replacement Steel Street IPS

Transit & Parking Strategy

189 Multi Modal Transit Hub New Study

190 Transit Fleet New Onboard CCTV Security Cameras

191 County of Simcoe Capital Program - Long Term Care & Senior Services

192 County of Simcoe Capital Program - Paramedic Services

193 County of Simcoe Capital Program - Social Housing & Community Services

194 Georgian College - Advanced Technology, Innovation and Research Centre

Roads, Parks, and Fleet Department

Service Partners

Page 6: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

!(

!(

!(

!(

!(

!(

!(!(

!(

!(

!(!(

!(

!(

!(

!(

!(

!(!(

!(!(

!(

!(!(

!(

!(

!(

!(

!(

!(

!(

!(

!(

!(

!(

!(

!(

!(

!(

!(

!(

!(

!(

!(

!(

!(

!(

£¤11

DUNLOP ST W

VESPRA ST

BAYFIELD ST

HURONIA RD

WELLINGTON ST E

NAPIER ST

SOUTHWOO DS CRE S

CUNDLES RD W

TROTTER CRT

BRADFORD ST

GROVE ST E

PARTRIDGE RD

BERCZY STST VINCENT ST

MCCU

TCHE

ONCR

T

MCDONALD ST

BEDFORD ESTATES CR ES

MARY STPEEL ST

BATTEAUX ST

COUNTY ROAD 27

INNISFIL ST

DODSON RD

FENCHURCH MANOR

BLAKE ST

PUGE

T ST

FERNDALE DR N

CASTLE DR

SOVEREIGN'S GATE

ROSE ST

DOCK RD

STEEL STJONES DR

EMPIRE DR

DUVAL DR

ROSS ST

SYDNEY LANE

WISMER AVE

H AN M

E RST

W

NORTH LANE

GORE DR

BALLISTON RD

CURRIE ST

CUNDLES RD E

GIBBON DR

ANNE ST N

GUNN ST

FREDERICK ST

LIVINGSTONE ST W

POPLAR DR

DAV IDSO NST

LITTLE AVE

MAPLEVIEW DR W

HILL CRT

ECCLES ST N

CODRINGTON ST

NELS

ON S

T

DY MENT RD

SPEARIN CRT

HURST DR

OAK ST

SHIRLEY AVE

EAGLES TONE LANE

MAGNA CARTA RD

MONTSE RRAND ST

RING RD N

KEMPVIEW LANE

MACM

ILLAN

CRES

TIFFIN ST

DUNLOP ST E

PARK ST

KOZLOV ST

HOLGATE ST

BOORMAN CRT

HANMERST E

H AWKIN S

DR

HERRELLAVE

IMPERIAL CROWN LANE

SANDRINGHAM DR

SURREY DR

COLLINGWOOD ST

FOSTER DR

HIGHCROFT RD

S PRINGHOME RD

SUNSET PL

TOWN LINE

PENE

TANG

UISH

ENE

RD

SEDGEWOOD WAY

VANSITTART CRT

REDOAK

DR

ORIOLE CRT

BIRCHSHIRE DR

GRANT'S WAY

SOPHIA ST W

CHELTENHAM RD

BERRY CRT

FARM

STEA

DCRES

STRO

UD PL

MCCU

AIG C

RT

MAXAVE

ROYAL JUBILEE DR

LEACOCK DR

STUNDEN LANE

THRUSHWOOD

DR

TURNER DR

POWELL DR

TORONTO ST

MCCRON CRES

MOIRCRES

PATTERSON RD

ARBOUR TR AIL

WISEMAN CRT

GLORIAST

YONGE ST

BENTLEY CRES

WRIGHT DR

VALLEY VIEW CRT

HARVIE RD

CALLAWAY

CRT

MORTON CRES

FROST

TRAILAUBURN CRT

BOYD

ST

GIRDWOODDR

TOLLENDAL MILL RD

HOOKCRT

DAVIES CRES

DOYLEDR

AMELIA ST

ROBERT ST

HIGGIN CRT

UNICO

RN LA

NE

EMMS

DR

PORRI TTST

VETERAN'S DR

BURTON AVE

CASSANDRA DR

LANCASTER CRT

DICKE NS DR

OWEN ST

SHORT ST

WILDFLOWER CRT

TRUMAN

RD

HAILEY HOLLOW

DEAN AVE

MERGANSER CRT

ASPEN DR

HOGAN CRT

PERRY ST

MAPLETON AVE

HUITE

MA C

RT

LOUNT ST

BOTHW ELL CRES

GRIFF IN GATE

MCCULLOUGH CRT

THE BOULEVARD

GRAND FOREST DR

MUI RD R

CHESTNUT CRT

JEFF

REY

ST

MEYER AVE

INDIAN ARROW RD

SPROULE DR

SHAINA CRT

HEW ITT PL

COLLIER STCARMAN CRT

WOODGROVE CRT

GLENHILL DR

MARGARET DR

PATTERSON PL

EPSO

M RD

ARDAGH RD

LISA JANE CRT

SUTT

ON D

R

CHARLOTTE CRT

TIMOTHY LANE

ATWOOD CRT

WEST GATE

MILNE CRT

BETHUNE PL

LEECE RD

KNUPP RD

ARTHUR AVE

WHISPERING PINE PL

GARDENDR

WHITE CRES

KRAUS RD

COUGHLIN RD

MCVEIGH DR

MAYOR LANE

PHILLIPS ST

HEATHER ST

CORBETT DRGOLDEN

ME ADOWRD

M ICHELLEDR

S HERWOOD

CRT

CELESTE DR

BALMORAL PL

ELM ST

HIGHVIEW RD

CUTHBERT ST

JESSICA DR

COULTER

ST

REDWOOD CRT

FALLING BROOK DR

CORONATION PKY

NICOLE MARIE AVE

SNOWSHOE TRAIL

DYKSTRA DR

LIVINGSTONE ST E

AUSTEN LANE

COLES ST

PRI SC IL L A' SPL

BLOXHAM PL

TARA RD

LOYALIST CRT

MC INT YR EDR

KNICELY RD

NUGENT CRT

BEARCR EEKDR

BROCK ST

LONGMANDR

SILVERCREEK CRES

VANC

OUVE

RS T

MALL ST

BENNET RD

GLENWOOD DR

KELL PL

PATTON RDLIBRA RD

GOODWIN

DR

CHARLES CRT

DUNNETT DR

ROSEDALE PL

LAWRENCE RD

CHARLBROOK AVE

BROADMOOR AVE

ANNE ST S

MANOR GATE

BEACH CRT

LAMPMAN LANE

BELL FARM RD

JAMES ST

SOUTH VILLAGE WAY

GALL

IE C

RT

MAPLEVIEW DR E

YEATES AVEARMSTRONG BLVD

PURBROOK CRT

MINET'S POINT RD

ATHABASKA RD

CRIMSON RIDGE RD

BOULTON CRT

PALMER DR

KEMPENFELT DR

MARION CRES

SHOREVIEWDR

DALTON ST

ELLEN STGABLE'S W

AY

CORR

INHA

LL S

T

BALDWIN LANE

CARTWRIGHT DR

BLUEJAY DR

LAY ST

ISOBE

L ST

CALLAGHAN DR

PURT CRT

BRONTECRE S

SYLV

IA

ST

SHELLEY LANE

JACOB'S TERR

KEATS DR

HARDING AVE

CATHERINE DR

CAROL RD

TAYLOR DR

SPEIRS RD

SUMMERSET DR

DONALD ST

RING RD S

FRANK'S WAY

LION'S

GATE BLVD

CAMPBELL AVE

NORTHPA

RK RD

CLARENCE CRT

ORSI CRT

RIVER RIDGERD

MERRETT DR

BOWMAN AVE

ALBERT ST

ROLSTON DR

JOANNE CRT

PENETANG ST

CARRD R

HIGHLAND AVE

ALDE

RGRO

VE C

IR

EAST GATE

SOPHIA STE

BOAG

CRT

REVELSTOKE CRT

SHAKESPEARECRES

REGINA RD

MULBERRY CRT

JOHN ST

FRANCES ST N

NINA RD

HAZEL AVE

BOYS ST S

BOYS ST N

ROBINSON ST

CREW COURT

ROS E

NFE L

DD R

LOVERS CRT

BROOKDALE DR

WILLOW FERNDR

FRANCES ST S

GLOU

CEST

ER S

T

SEAFORTH ST

MOORE PL

ST VINCENT SQ

POOLTON LANE

TYNDALE RD

IRIS

H LA

NE

LINDSAY CRT

COUPLES CRT

STANLEY ST

PALL

ING

LANE

MAJESTY BLVD

LEGGOTT AVE

FLET

CHER

DR

FITZROY TERR

OAK RIDGE

DR

DEBRA CRES

D'AMBROSIO DR

NORRIS DR

SHANTY BAY RD

BOURBON CIR

NORTH VILLAGE WAY

PINSENT CRT

RIVERWOOD CRT

EDGEHILL DR

PASS CRT

NELS

ON S

Q E

VALLEY

DR

BYRON CRES

MONTGOMERYD R

VARD

EN C

RES

PRINCE EDWARD PL

LAK EVIEW CRES

LAURELWOOD LANE

BUGGS GATE

CHANTAL ST

PRINCE WILLIAM WAY

MACALLISTER

CRT

REID DRTOMLIN CRT

ARMY, NAVY AND

AIR FORCE DR

NELS

ON S

Q W

G ROUSE GLEN

MOUNTBATTEN CRES

REDPATHRD

COUN

SELL

ORTE

RR

CAMPFIRE CRT

EAST ST

SRIG

LEY S

T

MEADOW LANE

GOWAN ST

FLORENCE ST

CAPILANO CRT

HENRY ST

VARD

EN AV

E

COTTAGE LANE

S UNNIDA LE RD

WILSON CRT

BAYSHORE BLVD

RYANCRT

HUNTER RD

NOAM DR

HEMLOCK CRT

JACKSON ST

ALVA ST

BIBBY CRT

CHERRY CRT

MORROW RDALEDA ST

VINE ST

PATRICK DR

HARROGATE CRT

FIRMAN DR

WESLEY ST

CHARLESON DR

WILDE PL

PARK

WAY

PL

BEATRICE LANE

HORSFIELD DR

PRINCESSMARGARET GATE

RUSSELL HILL DR

SINCLAIR CRT

TA MA RA CKTRAI L

CHAMBORO CRT

BIG BAY POINT RD

NICKLAUS DR

SHADOWOOD RD

JANE CRES

BLUE

GRAS

SDR

EVER

GREE

NCR

T

MOLLARD CRT

COLEMAN DR

BRITAN NIC LANE

CUMBERLAND ST

CROSS ST

SEYMOUR CRES

ARCH BROWN CRT

PRIMROSE

CRES

WYNES RD

MARWENDY DRBURBANK PL

ADDI

SON

TRAI

L

CRESTW

OODDR

LAKEW OODS CRT

CRAWFORD ST

RICHLER CRESLISTER DR

MILLER DR

LOWRY COURT

PRINCE

OF WA LES DR

STRABANE AVE

BISHOP DR

RIDWELL ST

PETER ST

ORLEANS AVE

TODD DR

DORIS DR

KENNETH AVE

MELROSE AVE

LOCKHART RD

GOLFDALE RD

VINE CRE S

OTTAWAY AVE

GEORGIAN DR

SPRINGWOODCRT

DRURY LANE

THOMSON ST

CLIFF RD

STRATHMORE PL

LUCAS AVE

TWISS DR

GWENDOLYN ST

HICKORY LANE

PECK ST

ARCHER ST

MADE LA IN EDR

BRYNE DR

QUEEN EL IZABETHPWY

NORTH ST

BALTIMORE RD

400 HWY

NON

BAY F

I ELD

ST

HUNTINGTON DR

GARSON ST

CLAIRE DR

QUARRY RIDGE

BAKER CRES

KENSINGTON TRAIL

KENNYCRE S

HAMB LY CRT

SARJEANT DR

CRAIGCRES

W ELLS CRES

WELDON CR ES

SPENCER DR

HOPKINS RD

GLENRIDGE RD

ARGYLE RD

ST UAR T AV E

OAKSIDE CRT

SOUTHVIEW RD

ASSINIBOINE DR

THACKERAY CRES

CONNAUGHT LANE

BARTOR BLVD

SALEM RD

CENT

RE ST

BASSWO OD

DR

GRAN

VILLE

ST

GLEN

ECHO

DR

VIRGILWOOD CRES

CAPLAN AVE

GIN GERDR

S EREN

ALA

NE

BLACK ASH TRAIL

TYNHEADRD

GLEN OAK CRT

GRASETTCRES

SNELGROVE CRES

ALEXANDER AVE

MCKAY RD W

WARNICA RD

MAYES

CRT

NEWTON ST

ELLIS DR

GROVE ST W

SELKIRK

CRES

WHITEHORNCRES

PRATT RD

DRAKE DR

GARIBALDI DR

HOLLYHOLME FARM RD

MURRAY ST

SHANNON ST

QUEEN ST

JEAN ST

BE LL ST

STAPLETON

PL

MELINDA C RE S

JC

MASSIE WAY

BLAIR CRES

ELLIOTT AVE

BENJAMIN LANE

BLACK WILLOW

DR

BELLEVUE CRES

FORESTWOOD LANE

LENNOX DR

ETHERINGTON CRES

HAMILTON RD

BOOTH LANE

WILLOW DR

LORENA ST

ELIZABETH ST

HEMI

NGW

AYCR

ES

DEBO

RAHW

AY

AGNES ST

CAPPSDR

LAKESHORE DR

MCKAY RD E

FERNDALE INDUSTRIAL DR

IRENE DR

RADENHURSTCRES

STONEYBROOK

CRES

LAKESIDE TERR

20 SIDEROAD

BEACON RD

WATSON DR

400 HWY N ON ESSA RD

PEREGRINE RD

BRUSHWOOD CRE S

PEPLER PL

ALLSOP CRES

HONEY CRES

PIONEER TRAIL

PLUNKETT CRT

400 HWY S OFF BAYF IELD

ST

MILLS RD

GREENWICH ST

400 HWY N OFF DUCKW ORTH ST

400 HWYN

OFFES SA

RD

FERGUSON DR

400 HW YSOFF

ESSA

RD

GAR R

E TTCRES

FAIRVIEWRD

LITTLE LAKE DR

CHURCHILL DR

400 HW

Y N OF

F BAY

FIELD

ST

RAW

SON

A VE

400 HWY SOFF DUCKWORTH ST

GOVE

RNOR

'S DR

KEAR

SEY

CRT

PRE S

IDE N

T'SDR

COOK

ST

ESSA

RD

LOGGERS RUN

SPRINGDALE DR

DUCK

WOR

TH ST

THICKETWOODAVE

LETITIA ST

K IER LANDRD

PRINGLE DR

CLAPPERTON ST

WELLINGTON ST W

FERNDALE DR S

PEACOCK LANE

COX M ILLRD

WHITE OAKS RD

BRENNAN AVE

DIANA

WAY

OSPREY RIDGE RD

BROWNING

TR AIL

ORWELL CRES

BIRD S T

LOUGHEED RD

SIMCOE ST

SELINE CRES

BAYVIEW DR

COUNTRY LANE

CHUR

CHLA

NDDR

DRAPERC RES

ELMBROOK DR

WESSENGER DR

BIRKHALL PL

HICKLING TRAIL

SAXO

N RD

SUCCESSION CRES

COLUMBIA RD

OREN BLVD

WINCHESTER TERR

FOX RUN

LILLIAN CRES

M ARSELLUSDR

M ACLARENAVE

BROW

N

STCUMMING

DR

GRACE CRES

MASTERS DR

CUNNINGHAMDR

WALLWIN'S WAY

BA YL ANE

NATHAN CRES

BARREDR

RODN

EY S

T

MONARCHY ST

JOHN

SON

ST

THEQUE EN SW

A Y

NEELANDS ST

ESTHER DR

WELH

AM R

D

M ARSH ALLST

PINE DR

PENVI L L TRAIL

DUNSMORE LANE

WARD DR

GRAYL ANE

O'SHAUGHNESSY CRES

MAITL

AND

DR

QUINLAN

RD

LARK

IN D

R

FINLAY RDBURKE DR

NORTHVIEW CRES

SILVE R

MAPLE CRE S

MEADOWLARK RD

DYER

BLVD

CARDINAL ST

HOLLYMEADOW RD

S HEILA

WAY

VIOLET ST

L IVIA HERMAN WAY

TRI LLIUM

CRES

ROYALPARKB LV D

RAQUELST

COLLETE CRES

FERRIS LANE

LOON AVE

TUNBRIDGE RD

JAGGES

DR

LESLIE AVE

FORD ST

AIKENS C

RES

EDWARDS DR

MICHAEL CRES

BROWN WOOD DR

CLUTE CRES

GADW ALL AVE

CLOU GH LEYDR

STOLLAR

B LVD

BARR

I EVI

EWDR

SUN KING CRES

CHALMERS DR

WHITE ELM RD

WESTMINSTER

CI R

BL UE MOUN DDR

WILLIAM ST

WARN

ER R

D

RUFFET DR

KINZ IE LANE

JEWEL HOUSE LANE

CARLEY

CRES

CHI EFTAIN

CRES

COURTNEY CRES

NICHOLSON DR

HUMBER ST

HERI

TAGE

CRT

GOLDEN EAGLEWAY

BRIAR RD

W ILDWOOD TRAIL

BRUCKER RD

ADEL

AIDE S

T

GOSNEY

CRES

PA RKPL ACE

BLVD

TEAL

PL

400 HWY S

CUNDL

ES

ST EACCESS RD

DOVE CRES

CLOVER AVE

BERNICK DR

DOW

NSVIE

W D

R

LA IDLAW DR

CARTER RD

MCAVO

YDR

MAYFAIR DRMAPLE CR

OWN TE

RR

CAMELOT SQ

OAKLEY PARKSQ

FAWN CRES

MCCONKEY

PLMOON DR

TA SCON ACRT

SUMAC ST

JANICEDR

BENSON DR

HARWOOD DR

BUTTERNUT DR

REGAL

IAW

AY

W HITE P INE PL

DAPHNE CRES

CUNDLES RD W ACCESS

RD

SHAKESPEARE

CRES

DOUG

LAS

DR

BRISTO

WCRT

FERNDALEDR S ACCESS RD

FLORENCE PARK RD

PEPIN CRT

BUCHANAN ST

LIVEEIGHT

WAY

PORT

ER C

RES

ENGE

LCRES

MAILEY LANE

GRAND PL

SHAW CRES

LYFYTT CRES

DOWNING

CRES

SAUNDERS RD

VICTORIA ST

WICE RD

FRAS

ER

CRT

CURT

ISS C

RT

ROBIN

CRT

FALCON CRES

WEBB ST

AMBL

ER

BAY

CONCERT WAY

MARTA CRES

COMMERCE PARK DR

FRANK'SWAY

REYNOL

DS

LANE

SYDENHAM

WEL

LS

RESID

ENCE

RD

ST PAUL'S CRES

WEYMOUTH RD

FARMINGDALE CRES

BLOOM CRESLAMONT C RES

400 HWY N

GOLDS CRES

TUDOR

CRES

PENTON DR

FORSYTH CRES

HERSEY CRES

DARCEL CRES

KELSEY CRES

GEDDESCRES

LE E

CRES

TEMPL

ETON

CRES

WADDINGTON CRES

LANG DR

BROADFOOT RD

LA KE

CRES

SPERLING DR

RAYM

OND CRES

PAE DR

MONIQUE CRES

LAURIE CRES

EDEN DR

MAPLEHURSTCRES

EILEEN

DR

DELANEY

CRES

LOOKER

DR

WILL

IAM

PADD

ISON

DR

PLAYER DR

SCOTT CRES

HUBB

ERT C

RES

BURNS CIR

KING ST

PINECLIFFCRES

PARISIANCRES

HAWTHORNE

CRES

FELT CRES

LAYTON CRES

RUNDLE CRES

WINDSOR CRES

TREVINO CIR

B ARW

ICK

DR

ROSLYN RD

PEARCE

Y CRES

QUANCE ST

GEORGE ST

CYNTHIACRT

MOW ATCRES

WALNUTC RES

HADDEN CRES

VERSAILLES CRES

CHR IS TIE CRE S

MEGAN CRES

COMMONWEALTH RD

STEPHANIE LANE

REDFERN AVE

SPRUCE CRES

CEDAR CRES

KENW

ELLCRES

GRAIHA WK

DR

PICKETT CRES

IRWIN DR

CITYVIEW CIR

HODGSON DR

BRIGHTON RD

COPEMAN CRES

ALLIANCE BLVD

HOOPER RD

LOGAN

CRT

JOSEPH

CRES

HART DR

PRESID

ENT'SDR

000310

000072

Z1043

000132

Z525

Z465

000314

Z527

000308

EN1151

EN1140

Z131

000635

Z131

FC1075

000478

EN1117

FC1020 000164

EN1151

EN1117

000696

FC1084

EN1182Z250

EN1140

000447

FC1059

000633

EN1168000519

000657

Z462

Z131

Z852

000628

Z299000282

Z462

Z894

000629

Z131

Z462

000138

000583,000548,EN1127000108,000562,000565,000049000560,000101,000012000584,000588

EN1174

000112

EN112

0

EN1163

EN1043000627

000115

000031

EN1005

000468

Z328

EN1137

EN113

5

EN1134

EN1143

EN1097

Z372

000052

Z482

Z73

EN1183

000545

Z82Z84

000071Z350

EN1172EN

1166

EN1071

Z282

EN1164

Z313

Z463

Z201

Z229

Z230

Z483

Z204Z484

(in various phases)

2018 Phase

*Labels are references to Project Numbers,as noted on Capital Project Detail Reports.

Projects at the WwTF(various phases)

EA

Capital Purchase

DesignPropertyUtilitiesConstruction

Pre-Design

2018 Capital BudgetInfrastructure by Project Phase

0 0.9 1.80.45Kilometres

GIS Branch. 11/24/2017

±

1

Page 7: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

Automatic External Defibrillators (AED) Replacement Program

Department:

Barrie Fire & Emergency Services

Project Number:

Z1057

Summary:

Replacement Program for LIFEPAK 15 Monitor/Defibrillator. LIFEPAK 15 is the standard monitor/defibrillator used during the vast majority of medical emergencies.

Rationale:

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Capital Purchase - Request

$100,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $100,000

Capital Purchase - Forecast

$0 $70,000 $70,000 $85,000 $0 $0 $0 $0 $0 $0 $225,000

Total $100,000 $70,000 $70,000 $85,000 $0 $0 $0 $0 $0 $0 $325,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from Tax Capital Reserve

$100,000 $70,000 $70,000 $85,000 $0 $0 $0 $0 $0 $0 $325,000

Total $100,000 $70,000 $70,000 $85,000 $0 $0 $0 $0 $0 $0 $325,000

2

Page 8: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

Fire Helmet Replacement

Department:

Barrie Fire & Emergency Services

Project Number:

Z51

Summary:

Replacement of fire helmets as required by NFPA 1851-2008.

Rationale:

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Capital Purchase - Request

$80,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $80,000

Total $80,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $80,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from Tax Capital Reserve

$80,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $80,000

Total $80,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $80,000

3

Page 9: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

Fire Hose Replacement

Department:

Barrie Fire & Emergency Services

Project Number:

Z52

Summary:

Fire Hose upgrade and replacement program for current fire hose.

Rationale:

Current BFES fire hose does not meet the Section 21 guidance note, or the NFPA 1410 standard establishing the minimum required water flow for a residential fire. Upgrade to current standards, and the establishment of a replacement program will be undertaken. Fire Hose lifecycle is primarily activity dependent. The environment, nature of the exposure and duration limit the lifecycle. Alternate interventions to extend the lifecycle are not available.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Capital Purchase - Request

$40,000 $40,000 $40,000 $0 $0 $0 $0 $0 $0 $0 $120,000

Total $40,000 $40,000 $40,000 $0 $0 $0 $0 $0 $0 $0 $120,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from Tax Capital Reserve

$40,000 $40,000 $40,000 $0 $0 $0 $0 $0 $0 $0 $120,000

Total $40,000 $40,000 $40,000 $0 $0 $0 $0 $0 $0 $0 $120,000

4

Page 10: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

Fire Training Facility Temporary Expansion

Department:

Barrie Fire & Emergency Services

Project Number:

000642

Summary:

Continue construction on the current facility to meet operational needs and eliminate the rental of external or non- City facilities

Rationale:

BFES is obligated to provide all staff with adequate training. Recommendations, after the line of duty death of Barrie Firefighter Bill Wilkins referenced the need to provide more fire training. Increasing legislative requirements and industry standards across our service delivery areas require us to have adequate training facilities and this addition will be an interim solution until a permanent facility is built. BFES has rented facilities outside the City, but this becomes problematic. When attending remote training grounds, it creates extra implications to the training budget, such as travel time, tuition and overtime pay are required to send crews outside the City. On duty personnel are required every day to cover the City, so if training is required outside the City it requires overtime. A normal live fire training session would require a minimum of 8 to 10 firefighters on overtime. The costs of renting an outside facility is another expensive cost and there are limited resources available in the immediate area, therefore compounding the implications of the overtime budget, due to travel times. The use of a training facility in Barrie would permit BFES to meet its requirements under the Occupational Health & Safety Act, the Section 21 Committee and NFPA Standards. Another problem when going outside the City for training is the availability of other sites for our usage. Many departments have their sites already booked for their own personnel, if not other outside clients. This facility could be used as a means of revenue generation by the City by renting it to other local fire services, which would offset some of the operational costs. It has been identified that the acquisition of a permanent site could be another 8 to 10 years away and thus places BFES in a very precarious position, in not realizing its training obligations. And such failure will also fall back on the Corporation, if a serious injury to a firefighter were to happen and it was found that it was due to the lack of training, it could lead to charges against the City under the OH&S Act. Any training props that were acquired for a temporary site could be moved and re-used at the permanent site. BFES is currently using our temp facility to its full potential and require expansion of the facility to meet best practice and industry standards.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Capital Purchase - Request

$100,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $100,000

Total $100,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $100,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from Tax Capital Reserve

$100,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $100,000

Total $100,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $100,000

5

Page 11: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

Heavy Extrication Equipment Replacement

Department:

Barrie Fire & Emergency Services

Project Number:

BF1006

Summary:

Replacement of heavy extrication tools.

Rationale:

The existing heavy extrication tools are at the end of their useful life due to age, level of service (technology and safety), and financial efficiency. The proposed equipment is battery operated which reduces trip hazards, is easier to transport and may be used indoors. The new tools are also more cost-effective, more versatile and safer to operate.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Capital Purchase - Request

$40,000 $40,000 $0 $0 $0 $0 $0 $0 $0 $0 $80,000

Capital Purchase - Forecast

$0 $0 $0 $0 $0 $0 $45,000 $45,000 $45,000 $0 $135,000

Total $40,000 $40,000 $0 $0 $0 $0 $45,000 $45,000 $45,000 $0 $215,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from Tax Capital Reserve

$40,000 $40,000 $0 $0 $0 $0 $45,000 $45,000 $45,000 $0 $215,000

Total $40,000 $40,000 $0 $0 $0 $0 $45,000 $45,000 $45,000 $0 $215,000

6

Page 12: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

Protective Hood Replacement

Department:

Barrie Fire & Emergency Services

Project Number:

000556

Summary:

Both NFPA 1851 and the OH&S Section 21 states that fire helmets shall not be in service after 10 years. With helmets being exposed to high heat, chemicals, and mechanical wear and tear, it degrades the outer and inner shells over time. The fire helmets will need to be replaced for the H&S of firefighters.

Rationale:

Firefighter protective equipment is governed by NFPA standards. Standards that are continually evolving to provide the best protection possible. Standards can take several years to catch up to new technology. This new technology is not yet included in the NFPA standard but it is expected when the current standard is reviewed the standard will change to include the particulate blocking characteristics of the new hoods. Increasing numbers of work related illnesses are being linked to exposures to the products of combustion. Employee health and safety is the highest priority and this proactive approach will reduce exposures and promote a healthy work environment. Reducing work place related exposures and any subsequent illness has a long term cost avoidance impact to the City.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Capital Purchase - Request

$45,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $45,000

Total $45,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $45,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from Tax Capital Reserve

$45,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $45,000

Total $45,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $45,000

7

Page 13: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

Self Contained Breathing Apparatus - 45 Minute Air Bottle Replacement

Department:

Barrie Fire & Emergency Services

Project Number:

Z47

Summary:

Replacement of Self Contained Breathing Apparatus (SCBA) air bottles as required by CSA standard.

Rationale:

Self Contained Breathing Apparatus air bottles have a life cycle of 15 years from manufacture date. No maintenance program, or alternate life cycle is permitted under current standards. To lessen the financial impact of replacement, a phased approach will be undertaken and maximize the lifecycle of the current inventory. These bottles are the primary SCBA bottles used for all firefighting operations.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Capital Purchase - Request

$55,000 $55,000 $55,000 $55,000 $0 $0 $0 $0 $0 $0 $220,000

Total $55,000 $55,000 $55,000 $55,000 $0 $0 $0 $0 $0 $0 $220,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from Tax Capital Reserve

$55,000 $55,000 $55,000 $55,000 $0 $0 $0 $0 $0 $0 $220,000

Total $55,000 $55,000 $55,000 $55,000 $0 $0 $0 $0 $0 $0 $220,000

8

Page 14: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

Thermal Imaging Camera Replacement

Department:

Barrie Fire & Emergency Services

Project Number:

Z48

Summary:

Replacement of thermal imaging cameras over a 3 year period.

Rationale:

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Capital Purchase - Request

$55,000 $55,000 $55,000 $0 $0 $0 $0 $0 $0 $0 $165,000

Total $55,000 $55,000 $55,000 $0 $0 $0 $0 $0 $0 $0 $165,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from Tax Capital Reserve

$55,000 $55,000 $55,000 $0 $0 $0 $0 $0 $0 $0 $165,000

Total $55,000 $55,000 $55,000 $0 $0 $0 $0 $0 $0 $0 $165,000

9

Page 15: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

APLI (Applications, Permits, Licenses and Inspections) Expansion - Phase 3

Department:

Centre for Continuous Improvement

Project Number:

Z1066

Summary:

Implementation of the planned phase III of the existing Applications, Permits, Licensing, Inspections project (APLI), involving a roll out of the Accela system, and process re-engineering for By-Law, Fire, Environmental Services, Real Estate, Culture and Clerks Services.

Rationale:

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Execute - Request $608,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $608,000

Execute - Forecast $0 $395,000 $395,000 $0 $0 $0 $0 $0 $0 $0 $790,000

Total $608,000 $395,000 $395,000 $0 $0 $0 $0 $0 $0 $0 $1,398,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from Tax Capital Reserve

$608,000 $395,000 $395,000 $0 $0 $0 $0 $0 $0 $0 $1,398,000

Total $608,000 $395,000 $395,000 $0 $0 $0 $0 $0 $0 $0 $1,398,000

10

Page 16: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

Citizen Relationship Management (CRM) Solution

Department:

Centre for Continuous Improvement

Project Number:

IT1031

Summary:

This project focuses on the implementation of a technology solution to enable the Corporation to centrally and electronically manage all of its customers. The need for this system is identified and further defined in the City's Corporate Technology Strategy and its Customer Service Plan. This new CRM system will manage customer complaints, requests and interactions as a single point of reference for all customer data.

Rationale:

Phase One of the Customer Contact Centre—now known as Service Barrie—is operational as of November 2016. Additional services will be incorporated through the following 4 phases, which will greatly increase the volume and type of customer interactions. These interactions will have a higher degree of complexity, requiring accurate and reliable tracking. They will also incorporate data and processes from several different departments and database systems. A centralized CRM will track the volume, type and resolution to all inquiries from multiple channels, allowing the City to identify trends and emerging issues both city wide and neighbourhood specific. The ability to implement future phases of Service Barrie will be limited without adequate technology systems to support these multi-channel services. Easy access to comprehensive metrics will improve the ability to plan, enabling the City to increase efficiencies and improve communication in order to promote a consistent customer experience. A CRM will support customer service problem management, issue ticketing and case management; a single view of the customer experience and history (customer data integration); consistent treatment of the customer across channels; real-time decision support (analytics) to understand customer intentions, and customize services and interactions accordingly; real-time feedback and surveys; and future self-service systems.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Execute - Request $250,000 $100,000 $100,000 $0 $0 $0 $0 $0 $0 $0 $450,000

Total $250,000 $100,000 $100,000 $0 $0 $0 $0 $0 $0 $0 $450,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from Tax Capital Reserve

$137,500 $55,000 $55,000 $0 $0 $0 $0 $0 $0 $0 $247,500

Contribution from WW Capital Reserve

$50,000 $20,000 $20,000 $0 $0 $0 $0 $0 $0 $0 $90,000

Contribution from Water Capital Reserve

$50,000 $20,000 $20,000 $0 $0 $0 $0 $0 $0 $0 $90,000

Contribution from Parking Capital Reserve

$12,500 $5,000 $5,000 $0 $0 $0 $0 $0 $0 $0 $22,500

Total $250,000 $100,000 $100,000 $0 $0 $0 $0 $0 $0 $0 $450,000

11

Page 17: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

CMMS Improvement Project - Cityworks

Department:

Centre for Continuous Improvement

Project Number:

IT1016

Summary:

On-going maintenance and expansion of the CityWorks technology system in alignment with the corporate GIS program, mobility strategy, and integration with other enterprise and business applications systems.

Rationale:

Materials maintenance at the City is currently managed manually, and by segregated applications. This program is targeted at rationalizing the existing applications, into the least amount of applications required to support the City. Additionally the program will focus on moving towards more automation. This will create efficiencies for work orders within the City.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Execute - Request $100,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $100,000

Total $100,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $100,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from Tax Capital Reserve

$40,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $40,000

Contribution from WW Capital Reserve

$10,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $10,000

Contribution from Water Capital Reserve

$50,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $50,000

Total $100,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $100,000

12

Page 18: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

ERP Sustainment Program

Department:

Centre for Continuous Improvement

Project Number:

000335

Summary:

The new SAP system is slated to go live in 2017. This system will house the City's, Police, BIA, LSRA and the Library's financial and HR information. It also contains the City's new business intelligence system (reporting system). Internal staff are currently being trained to support the SAP system. Given that SAP is a very complex system, external support will be required to ensure that any problems that cannot be solved by internal staff, will be remedied quickly using external support.

Rationale:

The new SAP system is slated to go live in 2018. This system will house the City's, Police, BIA, LSRA and the Library's financial and HR information. It also contains the City's new business intelligence system (reporting system). Internal staff are currently being trained to support the SAP system. Given that SAP is a very complex system, external support will be required to ensure that any problems that cannot be solved by internal staff, will be remedied quickly using external support.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Execute - Request $350,000 $350,000 $0 $0 $0 $0 $0 $0 $0 $0 $700,000

Execute - Forecast $0 $0 $350,000 $350,000 $350,000 $350,000 $350,000 $350,000 $350,000 $0 $2,450,000

Total $350,000 $350,000 $350,000 $350,000 $350,000 $350,000 $350,000 $350,000 $350,000 $0 $3,150,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from Tax Capital Reserve

$192,500 $192,500 $192,500 $192,500 $192,500 $192,500 $192,500 $192,500 $192,500 $0 $1,732,500

Contribution from WW Capital Reserve

$70,000 $70,000 $70,000 $70,000 $70,000 $70,000 $70,000 $70,000 $70,000 $0 $630,000

Contribution from Water Capital Reserve

$70,000 $70,000 $70,000 $70,000 $70,000 $70,000 $70,000 $70,000 $70,000 $0 $630,000

Contribution from Parking Capital Reserve

$17,500 $17,500 $17,500 $17,500 $17,500 $17,500 $17,500 $17,500 $17,500 $0 $157,500

Total $350,000 $350,000 $350,000 $350,000 $350,000 $350,000 $350,000 $350,000 $350,000 $0 $3,150,000

13

Page 19: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

Huronia and Big Bay Point Large Diameter Watermain Condition Assessment

Department:

Engineering Department

Project Number:

000523

Summary:

Condition assessment of large diameter watermains, on Huronia Road from Webb to Big Bay Point and Big Bay Point from Huronia to Bayview, as well as on Big Bay Point Road from Ashford to approximately 230m east of the Ashford intersection. The project includes non-destructive condition assessment and reports, recommendations for lifecycle intervention activities, and may also include equipment and licensing for ongoing watermain monitoring.

Rationale:

Two Prestressed Concrete Cylinder Pipe (PCCP) transmission mains that act as critical links in the City’s water distribution network were identified at increased risk of failure based on staff knowledge and desktop analysis of unusual construction practices or post-installation alteration. Their Maximum Potential Life (MPL) is anticipated to be reduced by as much as 50%. The consequence of main failure, should it occur, is high: a large split or hole could shut down the Metrolinx track and/or Big Bay Point Road for several days, disrupting important arterial transportation corridors and causing substantial flooding and property damage; with no redundancy to the City’s south end, supply would run out within approximately 3 days while repair time would require weeks. Rather than proposing immediate replacement of the mains, staff recommend conducting non-destructive condition assessment to determine the current baseline condition and to identify the most appropriate lifecycle intervention activities going forward. The project solution supports Council’s strategic goal of responsible spending by taking a cost-effective approach to the immediate project and potential rehabilitation work in future, while also ensuring that key service levels are maintained.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Study - Request $500,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $500,000

Total $500,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $500,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from Water Capital Reserve

$500,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $500,000

Total $500,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $500,000

14

Page 20: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

Pavement Condition Assessment

Department:

Engineering Department

Project Number:

000521

Summary:

A complete network level pavement condition assessment, including roads, public pay-and-display parking lots, and a complete pavement management analysis. The project will deliver a fully inspected road network, a fully inspected parking lot portfolio, a functional database of the inspection results, modeling and reporting, as well as pavement management recommendations based on the inspection results.

Rationale:

City staff use pavement condition data on a daily basis to conduct analysis related to infrastructure maintenance and renewal, levels of service, and forecasting financial needs. The City's Road Resurfacing Program, Crack Sealing Program, and Neighbourhood Renewal Program all rely on accurate and up-to-date pavement condition data in order to make cost effective decisions that maximize the life of pavement assets at the lowest overall life-cycle cost. The data is also used to evaluate options and determine priorities and timing with regards to major right of way renewal and expansion activities. Road condition data is also used for annual reporting under the Municipal Performance Measurement Program (MPMP) and is anticipated to be used by the City as a Key Performance Indicator (KPI) to measure and report to City Council on how effectively the City is maintaining its road network and ensuring adequate service levels. Road condition assessments are typically undertaken every four years. The last assessment was undertaken in 2014.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Study - Request $270,000 $75,000 $0 $0 $0 $0 $0 $0 $0 $0 $345,000

Study - Forecast $0 $0 $0 $0 $340,000 $0 $0 $0 $370,000 $0 $710,000

Total $270,000 $75,000 $0 $0 $340,000 $0 $0 $0 $370,000 $0 $1,055,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from Federal Gas Tax Reserve

$270,000 $75,000 $0 $0 $340,000 $0 $0 $0 $370,000 $0 $1,055,000

Total $270,000 $75,000 $0 $0 $340,000 $0 $0 $0 $370,000 $0 $1,055,000

15

Page 21: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

Stormwater Management Asset Management Plan Update

Department:

Engineering Department

Project Number:

000611

Summary:

Update to the existing stormwater infrastructure Asset Management Plans (AMP). Comprising the storm infrastructure component of the 2011 Environmental Appendix to the City’s AMP and the 2012 Stormwater Management Facility AMP. Project deliverables will include a stand-alone, comprehensive Stormwater Management Systems AMP. This project will be under taken in conjunction with the Stormwater Utility Finance Study

Rationale:

The City faces many infrastructure challenges, including the need to support services and growth by building new infrastructure while maintaining, rehabilitating, and replacing existing assets such as stormwater management systems. While many storm assets are relatively new, some sewers and culverts are approaching the end of their useful lives. Many sewers, culverts, and ponds are anticipated to be under capacity for water quantity control and/or water quality control. The City designed a path to sustainable management of all existing assets in 2009 though the Asset Management Strategy, with five Asset Management Plan (AMP) appendices, including one for Environmental infrastructure (water, wastewater and stormwater, etc.). Provincial initiatives such as the Municipal Infrastructure Strategy also recognize the importance of asset management planning, and require that municipalities seeking capital grants submit detailed AMPs to be eligible for funding. More recently, a provincial municipal asset management planning regulation was proposed under the Infrastructure for Jobs and Prosperity Act, 2015. When enacted, Phase 1 implementation of this future legislation will require completion of an up-to-date stormwater AMP, among others, by January 1st, 2020. Updating the Stormwater Management Systems AMP in 2018-2019 is recommended to help the City better understand investment needs, plan for renewal and growth more effectively, meet future legislative requirements associated with upcoming asset management planning regulations, and support investigation of a stormwater utility to secure predictable funding going forward. The project supports Council’s strategic goals related to responsible spending as it will assist in building a community that respects current and future taxpayers. Other alternatives, including doing nothing, delaying work on the AMP, and reducing its scope were considered. None of these are recommended, as they could result in lost grant opportunities and financial penalties in future, which would have a negative impact on the City’s ability to deliver needed stormwater projects.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Study - Request $245,000 $130,000 $0 $0 $0 $0 $0 $0 $0 $0 $375,000

Total $245,000 $130,000 $0 $0 $0 $0 $0 $0 $0 $0 $375,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from Federal Gas Tax Reserve

$245,000 $130,000 $0 $0 $0 $0 $0 $0 $0 $0 $375,000

Total $245,000 $130,000 $0 $0 $0 $0 $0 $0 $0 $0 $375,000

16

Page 22: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

Albert Street New Drainage Outlet

Department:

Engineering Department

Project Number:

Z852

Summary:

Undertake detailed design to install a storm sewer system on Albert Street at Amelia Street to convey the 100 year storm flows through a storm sewer system to Theresa Street and ultimately to the outlet at Kempenfelt Bay. The storm sewer system will direct major storms flows from Albert Street and Amelia away from the unopened roadway allowance to rectify flooding and erosion issues within the ravine area and the houses fronting Theresa and Berczy Streets.

Rationale:

The Albert and Amelia Street road systems west of Dundonald have limited areas with a storm sewer system, therefore drainage is conveyed along the road surface and then into the unopened right-of-way and a ravine with no formal drainage outlet. The properties that front onto Theresa and Berczy Street downstream of the ravine are receiving the storm runoff resulting in flooding, erosion and safety issues. The erosion issue is in proximity to public spaces. Current City Drainage Policies require that a drainage system be designed to accommodate all upstream drainage areas. The current drainage system within Albert, Amelia and Berczy are all deficient in meeting this policy. The City Wide Stormwater Model will be the basis for the design of the drainage solution.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Design - Request $50,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $50,000

Construction - Forecast $0 $0 $0 $250,000 $0 $0 $0 $0 $0 $0 $250,000

Total $50,000 $0 $0 $250,000 $0 $0 $0 $0 $0 $0 $300,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from Federal Gas Tax Reserve

$50,000 $0 $0 $250,000 $0 $0 $0 $0 $0 $0 $300,000

Total $50,000 $0 $0 $250,000 $0 $0 $0 $0 $0 $0 $300,000

17

Page 23: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

Anne and Innisfil Railway Crossing Upgrades- BCRY

Department:

Engineering Department

Project Number:

EN1151

Summary:

Road & Railway grade crossing warning system upgrades for the BCRY Railway crossings on Anne Street and on Innisfil Street to meet compliance requirements and safety factors at the crossing.

Rationale:

This work was recommended as a safety improvement to the intersections in the Detailed Railway Crossing Safety Assessment.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Construction - Request $200,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $200,000

Total $200,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $200,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from Tax Capital Reserve

$200,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $200,000

Total $200,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $200,000

18

Page 24: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

Anne Street - New 3N Booster Pump Station & 2N Booster Pump Station Reconstruction

Department:

Engineering Department

Project Number:

000629

Summary:

The existing 2N Anne Street Booster Pump Station is to be consolidated with the new 3N Booster Pump Station.

Rationale:

The proposed Zone 3N Pumping Station and 400mm transmission watermain is part of the required water distribution system improvements for pressure Zone 3N as identified in the Water Storage and Distribution Master Plan (2013). Pressure Zone 3N currently only has one pumping station and requires a second pumping station with associated transmission watermains to provide supply redundancy and system reinforcement in the event of a pumping station or discharge watermain failure. The 2N BPS was constructed circa 1960 and has had several minor upgrades to keep current with Regulations however, it is now in need of replacement. For construction and operational efficiencies the Booster Pump Stations will be combined into one. Note, under a separate project (Z350), the associated watermain works are being coordinated with the new 400mm transmission main.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Design - Request $360,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $360,000

Construction - Forecast $0 $0 $2,213,500 $2,213,500 $0 $0 $0 $0 $0 $0 $4,427,000

Total $360,000 $0 $2,213,500 $2,213,500 $0 $0 $0 $0 $0 $0 $4,787,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from Water Capital Reserve

$360,000 $0 $2,213,500 $2,213,500 $0 $0 $0 $0 $0 $0 $4,787,000

Total $360,000 $0 $2,213,500 $2,213,500 $0 $0 $0 $0 $0 $0 $4,787,000

19

Page 25: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

Anne Street North Pavement Rehabilitation - Neelands to Sunnidale

Department:

Engineering Department

Project Number:

000031

Summary:

Rehabilitation of the pavement through full depth resurfacing on Anne Street North between Neelands St. and Sunnidale Rd.

Rationale:

The existing asphalt pavement is in poor to very poor condition. Full depth resurfacing is required to address distresses not adequately corrected through partial depth resurfacing such as severe potholes, medium to high severity cracking, and/or severe rutting. This will defer a full reconstruction for 10-15 years. If this rehabilitation is not undertaken in the optimum timeframe, the condition of the road will deteriorate further at an increasingly rapid rate, resulting in a significantly decreased level of service and the need for more costly full reconstruction.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Construction - Request $598,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $598,000

Total $598,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $598,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from Federal Gas Tax Reserve

$598,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $598,000

Total $598,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $598,000

20

Page 26: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

Ashford Drive and Madelaine Drive New 750 mm Transmission Watermain - Big Bay Point to Mapleview

Department:

Engineering Department

Project Number:

EN1135

Summary:

New 750mm transmission watermain from Big Bay Point Road along Ashford Drive to Madelaine Drive to Mapleview Drive East.

Rationale:

The new transmission watermain was recommended in the Water Distribution Master Plan to provide potable water, fire protection, system security and redundancy to service growth in Phase 1 of the Annexation lands. Currently if the transmission watermain between the SWTP and the Harvie Road Reservoir goes out of service, water supply in Zones 3S and 2S would be compromised. This transmission watermain will connect to another transmission watermain on Mapleview Drive and Royal Jubilee Drive/Sun King Crescent/Consort Drive/Sandringham Drive to complete the system loop back to Big Bay Point Road.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Construction - Request $645,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $645,000

Total $645,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $645,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from DC Reserves Water (Annex)

$645,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $645,000

Total $645,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $645,000

21

Page 27: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

Baldwin Lane Watermain Replacement - Marshall to Bayview

Department:

Engineering Department

Project Number:

EN1163

Summary:

Watermain replacement on Baldwin Lane from Marshall Street to Bayview Drive. The project includes localized sanitary sewer replacement and full road reinstatement. Underground works completed in 2017. 2018 work will be top lift asphalt.

Rationale:

The existing watermain on Baldwin Lane between Marshall Street and Bayview Drive is in poor structural condition, with an extensive history of breaks and service issues for local residents. If the main is not replaced, the risk of repeated failure is high. Replacing the main will restore the required levels of service for drinking water provision to the local community and reduce operating expenses and staff time related to frequent maintenance and emergency repairs.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Construction - Request $110,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $110,000

Total $110,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $110,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from Water Capital Reserve

$110,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $110,000

Total $110,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $110,000

22

Page 28: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

Bayfield Street Pavement Rehabilitation - Cundles to Coulter

Department:

Engineering Department

Project Number:

000115

Summary:

Pavement rehabilitation of Bayfield Street from Cundles Road to Coulter Street.

Rationale:

Bayfield Street, from Heather to Grove, is proposed to undergo road widening and overpass/interchange expansion to address capacity needs. The MTO has been consulted in order to align this project with their future Hwy 400/Bayfield St Interchange work. It is anticipated that this work will happen around the end of the current 10 year planning period, with EAs proposed to begin in 2019. Due to the current condition of the road between Cundles Road and Coulter Street, Engineering and Roads Operations staff have identified the need to perform immediate rehabilitation work in advance of future full reconstruction. Since the capacity improvements cannot occur until the larger Bayfield interchange project reaches construction, an interim pavement rehabilitation strategy is required to improve road surface. Capital expenditures in the near term are anticipated to reduce operational expenses over the lifespan of the road treatment. From a service perspective, this section of Bayfield is failing to meet the expectations of the public where reliable and safe transportation is concerned. Application of a rehabilitation strategy is intended to improve the condition of the road in order to restore the service provided to the community. The City has applied for a Connecting Link grant that would help offset the capital costs to complete this project; the outcome of the grant is still outstanding, however, it has been assumed that the funding will be received.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Construction - Request $850,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $850,000

Total $850,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $850,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from Tax Capital Reserve

$850,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $850,000

Total $850,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $850,000

23

Page 29: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

Bayfield Street Water Tower - Repairs and Interior Lining Replacement

Department:

Engineering Department

Project Number:

000696

Summary:

At the Bayfield Street Water Tower it is proposed to replace the deteriorating interior protective coating and repair the corroding non-structural painters‘ safety rail. The scope of work includes: Technical/ Contractual Specifications preparation; Tendering; Interior coating removal; Coating Application and; Warranty.

Rationale:

The Bayfield Street Water Tower protective coatings were reapplied in 1997. Interior coatings have a typical lifespan of approximately 10-20 years depending on water reactivity. During a recent tank inspection in 2017, it was found that the condition of the interior coating would require it to be fully replaced. In addition to the condition of the coating there are serious issues with safe access due to severe corrosion that need to be addressed. Failure to replace the interior coating may lead to non-compliance with the Safe Drinking Water Act.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Construction - Request $420,000 $20,000 $0 $0 $0 $0 $0 $0 $0 $0 $440,000

Total $420,000 $20,000 $0 $0 $0 $0 $0 $0 $0 $0 $440,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from Water Capital Reserve

$420,000 $20,000 $0 $0 $0 $0 $0 $0 $0 $0 $440,000

Total $420,000 $20,000 $0 $0 $0 $0 $0 $0 $0 $0 $440,000

24

Page 30: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

Bayview Drive New Transmission Watermain Road Expansion - Little Avenue to Big Bay Point Road

Department:

Engineering Department

Project Number:

000314

Summary:

Reconstruction and widening of Bayview Drive to 3-lanes, bike lanes, sidewalk on the west side and replacement of an existing transmission watermain between Little Avenue and Big Bay Point Road .

Rationale:

The Multi-Modal Active Transportation Master Plan identified the need to widen the existing 2-lane rural cross-section to 3-lanes. A Schedule C Environment Assessment has identified the need for 3-lanes, bike lanes and sidewalk as the preferred alternative. Widening of this link will reinforce the transportation network supporting the Harvie Road / Big Bay Point Road Highway Crossing. The existing 300mm trunk watermain has been identified for replacement due to corrosion and upsizing requirements to accommodate intensification and growth in the Secondary Plan Lands. The road widening project is identified in the Council endorsed Multi-Modal Active Transportation Master Plan. The replacement transmission watermain is identified in the Council endorsed Water Storage and Distribution Master Plan.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Design - Request $736,250 $0 $0 $0 $0 $0 $0 $0 $0 $0 $736,250

Utilities - Forecast $0 $0 $0 $0 $1,019,800 $0 $0 $0 $0 $0 $1,019,800

Construction - Forecast $0 $0 $0 $0 $0 $9,647,000 $0 $0 $0 $0 $9,647,000

Total $736,250 $0 $0 $0 $1,019,800 $9,647,000 $0 $0 $0 $0 $11,403,050

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from DC Reserves Tax

$460,523 $0 $0 $0 $679,901 $5,885,628 $0 $0 $0 $0 $7,026,051

Contribution from DC Reserves Water

$43,680 $0 $0 $0 $0 $786,240 $0 $0 $0 $0 $829,920

Contribution from Tax Capital Reserve

$232,047 $0 $0 $0 $339,899 $2,975,132 $0 $0 $0 $0 $3,547,079

Total $736,250 $0 $0 $0 $1,019,800 $9,647,000 $0 $0 $0 $0 $11,403,050

25

Page 31: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

Big Bay Point Road ROW Expansion - Bayview to Huronia

Department:

Engineering Department

Project Number:

000308

Summary:

Reconstruction and widening of Big Bay Point Road to 5-lanes, buffered bike lanes and sidewalk on the south side between Bayview Drive and Huronia Road. This link is a critical component of the Harvie Road / Big Bay Point Road Highway Crossing. The Bayview / Big Bay intersection will be reconstructed as part of the Harvie Hwy 400 Crossing.

Rationale:

The Multi-Modal Active Transportation Master Plan identified the need to construct a highway crossing at Harvie Road / Big Bay Point Road to accommodate existing traffic volumes and planned growth in the Secondary Plan Lands. The construction of this link is needed to be implemented in conjunction with the Harvie Road / Big Bay Point Road Highway Crossing to provide 5-lanes continuously on Big Bay Point Road from Bayview Drive (east terminus of crossing project) to Huronia Road. The existing 2-lane rural cross-section is not sufficient to accommodate traffic volumes associated with the planned highway crossing. The City has completed a Schedule C Environmental Assessment; expansion to 5-lanes, buffered bike lanes and sidewalk is identified as the preferred solution. The project is identified in the Council endorsed Multi-Modal Active Transportation Master Plan Cash flow has been modified to reflect the elements to be constructed as part of the Harvie Crossing in 2019 and 2020.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Design - Request $660,750 $0 $0 $0 $0 $0 $0 $0 $0 $0 $660,750

Construction - Request $0 $633,510 $633,510 $0 $0 $0 $0 $0 $0 $0 $1,267,020

Property - Forecast $0 $1,219,800 $0 $0 $0 $0 $0 $0 $0 $0 $1,219,800

Utilities - Forecast $0 $0 $1,107,700 $0 $0 $0 $0 $0 $0 $0 $1,107,700

Construction - Forecast $0 $0 $0 $2,956,380 $4,223,400 $0 $0 $0 $0 $0 $7,179,780

Total $660,750 $1,853,310 $1,741,210 $2,956,380 $4,223,400 $0 $0 $0 $0 $0 $11,435,050

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from DC Reserves Tax

$440,522 $1,235,601 $1,160,864 $1,971,018 $2,815,741 $0 $0 $0 $0 $0 $7,623,746

Contribution from Tax Capital Reserve

$220,228 $617,709 $580,346 $985,362 $1,407,659 $0 $0 $0 $0 $0 $3,811,304

Total $660,750 $1,853,310 $1,741,210 $2,956,380 $4,223,400 $0 $0 $0 $0 $0 $11,435,050

26

Page 32: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

Biosolids Facility Roof Coating Rehabilitation

Department:

Engineering Department

Project Number:

Z458

Summary:

The purpose of this project is to remove and replace the existing roof slab coatings on the Pump Room, Storage tanks 1 - 4, and Sludge Hopper/Supernatant Tank, and repair the expansion joint of the pump room and new tunnel. The existing building exterior requires repair at certain locations.

Rationale:

A 2013 Condition Assessment concluded that the concrete coatings were functionally sound but were showing increased wear and diminished performance which is negatively impacting operations. The cracks in the roof coating of the pump room are allowing moisture to penetrate through the slab, which is causing the ceiling insulation to fall off and allow mould to grow. Operations is constantly cleaning up the debris that lands on the Pump Room floor. The timing for this work is coordinated with other capital projects and therefore a phased approach will be undertaken to replace the coatings within 3 years. Concern is growing as the roof reinforcement steel will corrode causing a safety concern and increased costs to repair in the future if works aren't completed in the short term.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Design - Request $170,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $170,000

Construction - Forecast $0 $80,000 $1,170,000 $350,000 $0 $0 $0 $0 $0 $0 $1,600,000

Total $170,000 $80,000 $1,170,000 $350,000 $0 $0 $0 $0 $0 $0 $1,770,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from WW Capital Reserve

$170,000 $80,000 $1,170,000 $350,000 $0 $0 $0 $0 $0 $0 $1,770,000

Total $170,000 $80,000 $1,170,000 $350,000 $0 $0 $0 $0 $0 $0 $1,770,000

27

Page 33: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

Biosolids Storage Facility Lagoons 1, 2 & 3 Hydraulic Upgrades and Overflow Protection Upgrades

Department:

Engineering Department

Project Number:

Z154

Summary:

At the Biosolids Storage Facility upgrades are needed to improve hydraulics and to provide Overflow Protection for Lagoons 1, 2 and 3. This project includes interconnection piping between the 3 existing lagoons and catch basin upgrade including automation, electrical and SCADA.

Rationale:

The Biosolids Storage Facility Lagoons were obtained in 1998. Since then, minimal upgrades to the lagoons have been completed and upgrades are now required to improve hydraulics and provide overflow protection. This project includes the necessary infrastructure and controls to provide operational flexibility and mitigate the risk of an overflow to the adjacent wetlands. Failure to capture the overflows could result in charges under the Environmental Protection Act.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Design - Request $40,000 $40,000 $0 $0 $0 $0 $0 $0 $0 $0 $80,000

Construction - Forecast $0 $0 $214,200 $23,800 $0 $0 $0 $0 $0 $0 $238,000

Total $40,000 $40,000 $214,200 $23,800 $0 $0 $0 $0 $0 $0 $318,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from WW Capital Reserve

$40,000 $40,000 $214,200 $23,800 $0 $0 $0 $0 $0 $0 $318,000

Total $40,000 $40,000 $214,200 $23,800 $0 $0 $0 $0 $0 $0 $318,000

28

Page 34: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

Bryne Drive New Road Construction - Harvie to North of Caplan

Department:

Engineering Department

Project Number:

Z525

Summary:

Construction of the unopened portion of Bryne Drive to 5-lanes, bike lanes and sidewalks between Harvie Road and north of Caplan Avenue. This link is required to support the Harvie Road / Big Bay Point Road Highway Crossing.

Rationale:

The Multi-Modal Active Transportation Master Plan identified the need to construct a highway crossing at Harvie Road / Big Bay Point Road to reduce congestion in the south end of Barrie and to accommodate planned growth. The completion of Bryne Drive from Caplan to Harvie is needed to reduce traffic congestion at the Mapleview Drive interchange by redirecting east / west traffic to the Harvie Road / Big Bay Point Road Highway Crossing. The City has completed a Schedule C Environmental Assessment to determine the preferred alternative for implementation. The project is identified in the Council endorsed Multi-Modal Active Transportation Master Plan Cash flow has been modified to reflect a segment of Bryne immediately south of Harvie being constructed as part of the Harvie Crossing in 2019 and 2020.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Design - Request $522,650 $0 $0 $0 $0 $0 $0 $0 $0 $0 $522,650

Construction - Request $0 $333,650 $333,650 $0 $0 $0 $0 $0 $0 $0 $667,300

Utilities - Forecast $0 $356,800 $0 $0 $0 $0 $0 $0 $0 $0 $356,800

Construction - Forecast $0 $0 $0 $2,669,200 $3,336,500 $0 $0 $0 $0 $0 $6,005,700

Total $522,650 $690,450 $333,650 $2,669,200 $3,336,500 $0 $0 $0 $0 $0 $7,552,450

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from DC Reserves Tax

$245,646 $231,920 $216,873 $570,083 $786,955 $0 $0 $0 $0 $0 $2,051,477

Contribution from Tax Capital Reserve

$277,005 $458,530 $116,777 $2,099,117 $2,549,545 $0 $0 $0 $0 $0 $5,500,974

Total $522,650 $690,450 $333,650 $2,669,200 $3,336,500 $0 $0 $0 $0 $0 $7,552,450

29

Page 35: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

Bryne Drive New Road Construction - Harvie to South of Essa

Department:

Engineering Department

Project Number:

Z527

Summary:

Construction of the unopened portion of Bryne Drive to 5-lanes, bike lanes and sidewalks between Harvie Road and south of Essa Road. This link is required to support the Harvie Road / Big Bay Point Road Highway Crossing.

Rationale:

The Multi-Modal Active Transportation Master Plan identified the need to construct a highway crossing at Harvie Road / Big Bay Point Road to reduce congestion in the south end of Barrie and to accommodate planned growth. The completion of Bryne Drive from Essa to Harvie is needed to reduce traffic congestion at the Essa interchange by redirecting east / west traffic to the Harvie Road / Big Bay Point Road Highway Crossing. The City has completed a Schedule C Environmental Assessment to determine the preferred alternative for implementation. The project is identified in the Council endorsed Multi-Modal Active Transportation Master Plan. Cash flow has been modified to reflect a segment of Bryne immediately north of Harvie being constructed as part of the Harvie Crossing in 2019 and 2020.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Design - Request $570,550 $0 $0 $0 $0 $0 $0 $0 $0 $0 $570,550

Construction - Request $0 $364,360 $364,360 $0 $0 $0 $0 $0 $0 $0 $728,720

Utilities - Forecast $0 $0 $591,400 $0 $0 $0 $0 $0 $0 $0 $591,400

Construction - Forecast $0 $0 $0 $2,914,880 $3,643,600 $0 $0 $0 $0 $0 $6,558,480

Total $570,550 $364,360 $955,760 $2,914,880 $3,643,600 $0 $0 $0 $0 $0 $8,449,150

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from DC Reserves Tax

$211,218 $236,834 $384,410 $1,113,476 $1,350,310 $0 $0 $0 $0 $0 $3,296,248

Contribution from Federal Gas Tax Reserve

$0 $0 $364,360 $1,201,840 $1,566,200 $0 $0 $0 $0 $0 $3,132,400

Contribution from Tax Capital Reserve

$359,333 $127,526 $206,990 $599,564 $727,090 $0 $0 $0 $0 $0 $2,020,503

Total $570,550 $364,360 $955,760 $2,914,880 $3,643,600 $0 $0 $0 $0 $0 $8,449,150

30

Page 36: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

Bunker's Creek Culvert Expansion - Bradford Street

Department:

Engineering Department

Project Number:

Z299

Summary:

Replacement and expansion of the Bunker's Creek culvert on Bradford Street to alleviate flooding.

Rationale:

The current creek infrastructure capacity is limited to minor storm events does not account for climate change. The Bunkers Creek Master Drainage Plan study identified conveyance and structural deficiencies throughout the watershed. The current infrastructure recommendations indicate major conveyance and stream water quality upgrades will be required to support the present and future drainage servicing needs of the City.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Design - Request $215,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $215,000

Utilities - Forecast $0 $50,000 $0 $0 $0 $0 $0 $0 $0 $0 $50,000

Construction - Forecast $0 $0 $2,527,500 $250,000 $0 $0 $0 $0 $0 $0 $2,777,500

Total $215,000 $50,000 $2,527,500 $250,000 $0 $0 $0 $0 $0 $0 $3,042,500

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from DC Reserves Tax

$51,250 $12,500 $619,375 $62,500 $0 $0 $0 $0 $0 $0 $745,625

Contribution from Tax Capital Reserve

$153,750 $37,500 $1,858,125 $187,500 $0 $0 $0 $0 $0 $0 $2,236,875

Contribution from Water Capital Reserve

$10,000 $0 $50,000 $0 $0 $0 $0 $0 $0 $0 $60,000

Total $215,000 $50,000 $2,527,500 $250,000 $0 $0 $0 $0 $0 $0 $3,042,500

31

Page 37: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

Bunkers Creek Culvert Expansion - Innisfil Street and Watercourse Upgrade - Innisfil to Bradford

Department:

Engineering Department

Project Number:

Z482

Summary:

Replacement and expansion of the Bunkers Creek culvert crossing of Innisfil Street, construction of a creek channel and floodway across privately owned lands from Bradford to Innisfil Street.

Rationale:

The Drainage Master Plan recommends replacing the existing twin culverts at Innisfil Street to convey the 1:100 year storm event. The City has undertaken stream upgrades on the Bunkers Creek North East Branch, which has increased the flow conveyance from Highway 400 through to the Boys Street outlet, just upstream of the Innisfil Street Crossing. The scope of this project is to design, acquire and construct a creek channel and floodway across privately owned lands from Bradford to Innisfil Street.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Design - Request $460,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $460,000

Utilities - Forecast $0 $509,546 $0 $0 $0 $0 $0 $0 $0 $0 $509,546

Construction - Forecast $0 $0 $2,871,000 $2,871,000 $0 $0 $0 $0 $0 $0 $5,742,000

Total $460,000 $509,546 $2,871,000 $2,871,000 $0 $0 $0 $0 $0 $0 $6,711,546

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from DC Reserves Tax

$115,000 $127,387 $717,750 $717,750 $0 $0 $0 $0 $0 $0 $1,677,887

Contribution from Tax Capital Reserve

$345,000 $382,160 $2,153,250 $2,153,250 $0 $0 $0 $0 $0 $0 $5,033,660

Total $460,000 $509,546 $2,871,000 $2,871,000 $0 $0 $0 $0 $0 $0 $6,711,546

32

Page 38: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

Duckworth Street New Transmission Watermain and ROW Expansion - Bell Farm to St. Vincent

Department:

Engineering Department

Project Number:

EN1166

Summary:

Reconstruction of Duckworth Street from Bell Farm Road to St. Vincent Street including property acquisition for widening of the right-of-way, utility relocations, road & sidewalk reconstruction, buffered bike lanes, installation of new transmission watermain, replacement of distribution watermain and water services, replacement of sanitary sewer and sanitary laterals, replacement of storm sewer system, upgrades to streetlighting system, replacement of the traffic signal systems at Duckworth/Codrington, at Duckworth/Wellington/Steel, at Duckworth/Grove, and at Duckworth/Rose/Bernick.

Rationale:

The existing road surface has failed, and with the increased growth of Georgian College and RVH there will be additional traffic volume on Duckworth Street. Phases 3 & 4 of the Class EA process were completed in 2015, and provided recommendations for road improvements and lane configurations which includes buffered bicycle lanes. The Water Storage and Distribution Master Plan prepared by Amec in 2013 identified the need for a 300mm watermain on Duckworth Street from Bell Farm Road to St Vincent Street for Zone 2N reinforcement. The Water Storage and Distribution Master Plan indicates that this improvement is required to be completed as early as 2017 but no later than 2021. Replacement of all existing municipal infrastructure (e.g., watermain, sanitary & storm sewers) is to be undertaken as part of this project in order to bundle the infrastructure components and thereby reduce capital and operating costs in the long term, minimize disruption to the community, and limit environmental damages from unnecessary construction.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Utilities - Request $750,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $750,000

Construction - Forecast $0 $4,354,100 $4,354,100 $0 $0 $0 $0 $0 $0 $0 $8,708,200

Total $750,000 $4,354,100 $4,354,100 $0 $0 $0 $0 $0 $0 $0 $9,458,200

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from DC Reserves Tax

$0 $1,459,315 $1,459,315 $0 $0 $0 $0 $0 $0 $0 $2,918,630

Contribution from DC Reserves Water

$153,600 $719,360 $719,360 $0 $0 $0 $0 $0 $0 $0 $1,592,320

Contribution from Tax Capital Reserve

$0 $1,423,785 $1,423,785 $0 $0 $0 $0 $0 $0 $0 $2,847,570

Contribution from WW Capital Reserve

$510,000 $347,000 $347,000 $0 $0 $0 $0 $0 $0 $0 $1,204,000

Contribution from Water Capital Reserve

$86,400 $404,640 $404,640 $0 $0 $0 $0 $0 $0 $0 $895,680

Total $750,000 $4,354,100 $4,354,100 $0 $0 $0 $0 $0 $0 $0 $9,458,200

33

Page 39: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

Dunlop Street West ROW Replacement - Eccles to Toronto

Department:

Engineering Department

Project Number:

EN1071

Summary:

Construct an open flow channel north of Dunlop Street, increasing the culvert capacity by installing new culverts across Dunlop Street and Bradford Street and constructing an open flow channel south of Dunlop Street. Reconstruction of the right of way including sidewalk, watermain, local storm sewer and sanitary replacement.

Rationale:

Kidds Creek currently experiences several issues including flooding through many areas of the watershed resulting in both loss of use of property and property damage. Increased sedimentation and erosion problems have led to reduced conveyance capacities, a decline in water quality and the alteration of fish and wildlife habitat. Kidds Creek Master Drainage Plan determined improvements necessary to mitigate these issues. Dunlop Street from Eccles Street to Toronto Street has deficient road surface conditions and the sanitary sewer is in poor structural condition. The existing drainage system can typically only convey minor storm events at road crossings and channels. Many existing storm water management facilities provide peak flow attenuation (in new areas of the watershed) to pre-development levels up to and including the 100 year storm event to meet current design criteria and typically do not have a water quality component to them (therefore unable to reduce phosphorus loads to watercourses and ultimately Lake Simcoe). The New City Fire Station #1 is also located in this flood area and access to Dunlop Street east for emergency responders’ purposes during a flooding event will not be available. To reduce the potential for increased flooding downstream as a result of the loss of storage behind road crossings with undersized storm sewers the MDP recommended that conveyance improvements ideally start at the most downstream portions of the watershed and be implemented in sequential order upstream. The City of Barrie has been approved for a grant under Intake 3 of the National Disaster Mitigation Program (NDMP) in the amount of $1.5 million for the purchase of property required for this project. The City has also submitted an application for Intake 4 under the NDMP for up to 50%/or $1.5 million of the construction costs for future phases.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Property - Request $3,800,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $3,800,000

Construction - Forecast $0 $4,100,000 $1,594,400 $0 $0 $0 $0 $0 $0 $0 $5,694,400

Total $3,800,000 $4,100,000 $1,594,400 $0 $0 $0 $0 $0 $0 $0 $9,494,400

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Government of Canada Grant Revenue

$1,500,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $1,500,000

Contribution from Federal Gas Tax Reserve

$0 $2,000,000 $1,368,000 $0 $0 $0 $0 $0 $0 $0 $3,368,000

Contribution from Tax Capital Reserve

$2,300,000 $1,650,000 $153,700 $0 $0 $0 $0 $0 $0 $0 $4,103,700

Contribution from WW Capital Reserve

$0 $250,000 $40,400 $0 $0 $0 $0 $0 $0 $0 $290,400

34

Page 40: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

Contribution from Water Capital Reserve

$0 $200,000 $32,300 $0 $0 $0 $0 $0 $0 $0 $232,300

Total $3,800,000 $4,100,000 $1,594,400 $0 $0 $0 $0 $0 $0 $0 $9,494,400

35

Page 41: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

Dyments Creek Channel Improvements - Sanford to Bradford

Department:

Engineering Department

Project Number:

000072

Summary:

The project will require the acquisition of lands, reconstruction of a 30 meter wide naturalized floodway including a low flow channel to convey regional storm event flows.

Rationale:

The current creek infrastructure capacity is limited to minor storm events does not account for climate change. The Dyments Creek Master Drainage Plan update identified conveyance and structural deficiencies throughout the watershed. The current infrastructure recommendations indicate major conveyance and stream water quality upgrades will be required to support the present and future drainage servicing needs of the City. This project is associated with the culvert upgrades are proposed both at Bradford and Sanford road crossings. To ensure efficient functioning of the upgraded culverts the watercourse channel needs to be improved to ensure flooding is reduced on adjacent private property and road systems.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Design - Request $75,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $75,000

Property - Forecast $0 $622,900 $0 $0 $0 $0 $0 $0 $0 $0 $622,900

Utilities - Forecast $0 $0 $60,700 $0 $0 $0 $0 $0 $0 $0 $60,700

Construction - Forecast $0 $0 $0 $850,000 $0 $0 $0 $0 $0 $0 $850,000

Total $75,000 $622,900 $60,700 $850,000 $0 $0 $0 $0 $0 $0 $1,608,600

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from DC Reserves Tax

$9,000 $74,748 $7,284 $102,000 $0 $0 $0 $0 $0 $0 $193,032

Contribution from Tax Capital Reserve

$66,000 $548,152 $53,416 $748,000 $0 $0 $0 $0 $0 $0 $1,415,568

Total $75,000 $622,900 $60,700 $850,000 $0 $0 $0 $0 $0 $0 $1,608,600

36

Page 42: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

Dyments Creek Culvert Expansion - Bradford St.

Department:

Engineering Department

Project Number:

EN1168

Summary:

Replacement and expansion of the Dyments Creek culvert on Bradford Street. The project will include channel improvements upstream and downstream of the culvert, localized utility relocations as well as road and boulevard reinstatement.

Rationale:

The existing conveyance capacity of the Dyments Creek at Bradford Street culvert crossing is a 5 year storm event. The Dyments Creek Storm Master Plan identified the need to upgrade the culvert to ensure conveyance of major storm events and to reduce flooding on private property, the City Wastewater Treatment Facility and the Bradford Street corridor.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Property - Request $242,190 $0 $0 $0 $0 $0 $0 $0 $0 $0 $242,190

Utilities - Request $35,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $35,000

Construction - Forecast $0 $3,620,000 $2,650,000 $0 $0 $0 $0 $0 $0 $0 $6,270,000

Total $277,190 $3,620,000 $2,650,000 $0 $0 $0 $0 $0 $0 $0 $6,547,190

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from DC Reserves Tax

$277,190 $1,629,000 $1,192,500 $0 $0 $0 $0 $0 $0 $0 $3,098,690

Contribution from Federal Gas Tax Reserve

$0 $1,991,000 $1,457,500 $0 $0 $0 $0 $0 $0 $0 $3,448,500

Total $277,190 $3,620,000 $2,650,000 $0 $0 $0 $0 $0 $0 $0 $6,547,190

37

Page 43: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

End of Life Pavement Replacement Program

Department:

Engineering Department

Project Number:

000694

Summary:

The End of Life Pavement Replacement Program will focus on roads where ride quality is poor or very poor, physical maintenance is trending high, and reconstruction is several years away or not currently planned. Typical candidates will be roads that are too far deteriorated for the Road Resurfacing Program and are not candidates for reconstruction in the short term. The program may act as a holding strategy. This request is not intended to replace any of the preservation programs that are being requested in the upcoming Capital Plan, but instead, provide another tool for the City to work with to improve the level of service that the residents of Barrie experience on a daily basis.

Rationale:

The program will address Barrie's worst pavement surfaces by replacing the surfaces or managing localized trouble areas to help reduce continuous operational dependencies. There are many streets that require larger scale asphalt replacements but due to budget constraints, these repairs are usually avoided and left until reconstruction. Reconstruction is often years away or there may be no plans for reconstruction as subsurface infrastructure is still in acceptable condition. These road sections are beyond preservation or rehabilitation and require regular pothole patching and provide poor ride quality.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Design - Request $20,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $20,000

Construction - Request $200,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $200,000

Design - Forecast $0 $20,000 $20,000 $20,000 $20,000 $20,000 $20,000 $20,000 $20,000 $20,000 $180,000

Construction - Forecast

$0 $200,000 $200,000 $200,000 $200,000 $200,000 $200,000 $200,000 $200,000 $200,000 $1,800,000

Total $220,000 $220,000 $220,000 $220,000 $220,000 $220,000 $220,000 $220,000 $220,000 $220,000 $2,200,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from Tax Capital Reserve

$220,000 $220,000 $220,000 $220,000 $220,000 $220,000 $220,000 $220,000 $220,000 $220,000 $2,200,000

Total $220,000 $220,000 $220,000 $220,000 $220,000 $220,000 $220,000 $220,000 $220,000 $220,000 $2,200,000

38

Page 44: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

Essa Road New Transmission Watermain and Road Expansion - Mapleview to Athabaska (City)

Department:

Engineering Department

Project Number:

000132

Summary:

Reconstruction and widening of Essa Road to 3-lanes, bike lanes, sidewalks and replacement of an existing transmission watermain between Mapleview Drive and Athabaska Road.

Rationale:

The Multi-Modal Active Transportation Master Plan identified the need to widen the existing 2-lane rural cross-section to a 3-lanes with buffered bike lanes and sidewalks. A Schedule C Environmental Assessment was completed. The transmission watermain is required to support growth in the Secondary Plan Lands. The road widening project is identified in the Council endorsed Multi-Modal Active Transportation Master Plan. The transmission watermain is identified in the Council endorsed Water Storage and Distribution Master Plan.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Design - Request $798,100 $0 $0 $0 $0 $0 $0 $0 $0 $0 $798,100

Property - Forecast $0 $192,200 $0 $0 $0 $0 $0 $0 $0 $0 $192,200

Utilities - Forecast $0 $225,400 $0 $0 $0 $0 $0 $0 $0 $0 $225,400

Construction - Forecast $0 $0 $2,945,500 $2,945,500 $0 $0 $0 $0 $0 $0 $5,891,000

Total $798,100 $417,600 $2,945,500 $2,945,500 $0 $0 $0 $0 $0 $0 $7,106,700

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Debenture Proceeds - Tax

$110,235 $62,640 $0 $411,615 $0 $0 $0 $0 $0 $0 $584,490

Contribution from DC Reserves Tax (Annex)

$624,665 $354,960 $2,332,485 $2,332,485 $0 $0 $0 $0 $0 $0 $5,644,595

Contribution from DC Reserves Water (Annex)

$63,200 $0 $201,400 $201,400 $0 $0 $0 $0 $0 $0 $466,000

Contribution from Tax Capital Reserve

$0 $0 $411,615 $0 $0 $0 $0 $0 $0 $0 $411,615

Total $798,100 $417,600 $2,945,500 $2,945,500 $0 $0 $0 $0 $0 $0 $7,106,700

39

Page 45: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

Ferndale Drive North ROW Expansion - Dunlop to Tiffin

Department:

Engineering Department

Project Number:

EN1005

Summary:

This project is substantially complete. The project included reconstructing and widening Ferndale Drive from Dunlop Street to Tiffin Street as per the Ferndale Drive EA. Services installed include large diameter storm sewer, Dyments Creek culvert crossing, sanitary sewer and street lighting. The previously existing 300mm diameter watermain has been replaced with a 400mm diameter watermain. Sidewalks have been installed on both sides of the road.

Rationale:

The construction costs for this project were approved in the 2016 Capital Plan at which time it was anticipated that the project would have a three year construction phase. The project has been completed, however this budget year's report is only to show the already committed construction costs.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Construction - Request $270,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $270,000

Total $270,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $270,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from DC Reserves Tax

$175,500 $0 $0 $0 $0 $0 $0 $0 $0 $0 $175,500

Contribution from Tax Capital Reserve

$94,500 $0 $0 $0 $0 $0 $0 $0 $0 $0 $94,500

Total $270,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $270,000

40

Page 46: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

Glen Echo Drive and College Crescent Watermain and Pavement Replacement - Lonsdale to Nelson

Department:

Engineering Department

Project Number:

EN1120

Summary:

Road reconstruction including new curb and gutter, asphalt, and sidewalk on Glen Echo Drive from College Crescent to College Crescent and on College Crescent from Lonsdale Drive to Nelson Street. The existing watermain and residential services are also being replaced. Underground works and base course asphalt completed in 2017. Top lift asphalt and sidewalks to be completed in 2018.

Rationale:

The previously existing asphalt pavement had deteriorated to the point where patching and partial depth resurfacing will no longer be effective lifecycle strategies. The existing watermains are exhibiting signs of physical mortality through frequent breaks indicating the end of their useful life. Watermain replacement is recommended in conjunction with the pavement rehabilitation. This project will improve road and watermain condition on these streets and allow future works in the area to be coordinated. It will increase the level of service provided to road users and residents.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Construction - Request $200,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $200,000

Total $200,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $200,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from Federal Gas Tax Reserve

$200,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $200,000

Total $200,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $200,000

41

Page 47: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

Gunn Street ROW Replacement - Peel to St. Vincent

Department:

Engineering Department

Project Number:

EN1172

Summary:

Replacement of the road and infrastructure on Gunn Street from Peel Street to St. Vincent Street, including road reconstruction, watermain replacement, sanitary sewer replacement, sanitary lateral replacement, storm sewer installation, sidewalk installation and replacement, and streetlight replacement.

Rationale:

Gunn Street between Peel Street and St. Vincent Street is in very poor condition. The Right of Way was constructed between 1947 and 1958 and nearly every piece of infrastructure has experienced severe deterioration and no longer provides reliable service. Given the age and deteriorated condition of all infrastructure within this Right of Way, other lifecycle strategies (status quo, do nothing/run to failure, maintain differently, and/or rehabilitate) are not expected to significantly extend the existing remaining life of current assets. The proposed solution will ensure safe drinking water and adequate fire protection, adequate drainage and reduced risk of flooding, reliable wastewater collection, and improved road safety.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Utilities - Request $250,000 $200,000 $0 $0 $0 $0 $0 $0 $0 $0 $450,000

Construction - Forecast $0 $0 $5,385,000 $120,000 $0 $0 $0 $0 $0 $0 $5,505,000

Total $250,000 $200,000 $5,385,000 $120,000 $0 $0 $0 $0 $0 $0 $5,955,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from DC Reserves Tax

$12,500 $10,000 $163,250 $6,000 $0 $0 $0 $0 $0 $0 $191,750

Contribution from Federal Gas Tax Reserve

$0 $0 $1,800,000 $114,000 $0 $0 $0 $0 $0 $0 $1,914,000

Contribution from Tax Capital Reserve

$237,500 $190,000 $1,301,750 $0 $0 $0 $0 $0 $0 $0 $1,729,250

Contribution from WW Capital Reserve

$0 $0 $1,060,000 $0 $0 $0 $0 $0 $0 $0 $1,060,000

Contribution from Water Capital Reserve

$0 $0 $1,060,000 $0 $0 $0 $0 $0 $0 $0 $1,060,000

Total $250,000 $200,000 $5,385,000 $120,000 $0 $0 $0 $0 $0 $0 $5,955,000

42

Page 48: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

Harvie Road and Big Bay Point Road New Crossing - Highway 400

Department:

Engineering Department

Project Number:

000310

Summary:

Construction of a new 5-lane Highway 400 crossing at Harvie Road and Big Bay Point Road between Bryne Drive and Bayview Drive. The crossing will include buffered bike lanes, sidewalks and protection for a future 7-lane crossing and interchange.

Rationale:

The Multi-Modal Active Transportation Master Plan identified the need to construct a highway crossing at Harvie Road / Big Bay Point Road to reduce traffic congestion in the south end of Barrie and to accommodate planned growth. The construction of this crossing coupled with transportation improvements on Bryne, Harvie, Big Bay and Bayview will reduce traffic congestion at Essa Road and Mapleview Drive highway interchanges. A completed Schedule C Environmental Assessment identified the need for a 5-lane crossing structure with buffered bike lanes and sidewalks. The design will allow for potential future expansion to a partial 7-lane interchange. Updated costs included utility relocates and recoverable costs on Highway 400 associated with the construction of the concrete median barrier, drainage and resurfacing. MTO will be paying for their portion of the work, and this cost is assumed to be $10 million. This is a high priority project for the City.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Design - Request $144,000 $244,000 $244,000 $0 $0 $0 $0 $0 $0 $0 $632,000

Utilities - Request $1,939,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $1,939,000

Construction - Request $0 $18,826,000 $21,420,000 $0 $0 $0 $0 $0 $0 $0 $40,246,000

Total $2,083,000 $19,070,000 $21,664,000 $0 $0 $0 $0 $0 $0 $0 $42,817,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Debenture Proceeds - DCs

$1,388,736 $10,413,187 $7,584,380 $0 $0 $0 $0 $0 $0 $0 $19,386,303

Debenture Proceeds - Tax

$694,264 $0 $3,791,620 $0 $0 $0 $0 $0 $0 $0 $4,485,884

Province of Ontario Grant Revenue

$0 $0 $10,000,000 $0 $0 $0 $0 $0 $0 $0 $10,000,000

Contribution from Tax Capital Reserve

$0 $5,205,813 $0 $0 $0 $0 $0 $0 $0 $0 $5,205,813

Contribution from WW Capital Reserve

$0 $555,000 $0 $0 $0 $0 $0 $0 $0 $0 $555,000

Contribution from Water Capital Reserve

$0 $2,896,000 $288,000 $0 $0 $0 $0 $0 $0 $0 $3,184,000

Total $2,083,000 $19,070,000 $21,664,000 $0 $0 $0 $0 $0 $0 $0 $42,817,000

43

Page 49: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

Harvie Road ROW Expansion - Essa to Bryne

Department:

Engineering Department

Project Number:

Z328

Summary:

Urbanize the existing rural cross section of Harvie Road and widen to 3 lanes from Essa to Veterans and five lanes from Veterans Drive to Bryne Drive. This project will include buffered bike lanes and sidewalks. Timing of the construction costs have been adjusted to reflect anticipation of actual spending.

Rationale:

The Multi-Modal Active Transportation Master Plan identified the need to construct a highway crossing at Harvie Road / Big Bay Point Road to reduce traffic congestion in the south end of Barrie and to accommodate planned growth. A Schedule C Environmental Assessment was completed. The construction of these transportation improvements are a critical component of the Harvie Road / Big Bay Point Road Highway Crossing and required to connect the highway crossing to Veteran's Drive and Essa Road.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Design - Request $205,000 $120,000 $120,000 $0 $0 $0 $0 $0 $0 $0 $445,000

Property - Request $206,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $206,000

Utilities - Request $669,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $669,000

Construction - Request $1,083,000 $4,599,000 $6,688,000 $0 $0 $0 $0 $0 $0 $0 $12,370,000

Total $2,163,000 $4,719,000 $6,808,000 $0 $0 $0 $0 $0 $0 $0 $13,690,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Developer Contributions $0 $65,287 $87,360 $0 $0 $0 $0 $0 $0 $0 $152,647

Contribution from DC Reserves Tax

$1,548,080 $2,627,000 $4,669,400 $0 $0 $0 $0 $0 $0 $0 $8,844,480

Contribution from Tax Capital Reserve

$543,920 $857,713 $1,553,240 $0 $0 $0 $0 $0 $0 $0 $2,954,873

Contribution from WW Capital Reserve

$71,000 $671,000 $0 $0 $0 $0 $0 $0 $0 $0 $742,000

Contribution from Water Capital Reserve

$0 $498,000 $498,000 $0 $0 $0 $0 $0 $0 $0 $996,000

Total $2,163,000 $4,719,000 $6,808,000 $0 $0 $0 $0 $0 $0 $0 $13,690,000

44

Page 50: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

Henry Street ROW Replacement - Frances to Eccles

Department:

Engineering Department

Project Number:

EN1174

Summary:

Right of way reconstruction of Henry Street between Frances Street and Eccles Street including road reconstruction, watermain replacement, water service replacement, sanitary sewer replacement, sanitary lateral replacement, storm sewer installation, and sidewalk replacement.

Rationale:

This section of Henry Street was constructed between 1947 and 1950 and nearly every piece of infrastructure has experienced severe deterioration and no longer provides reliable service. Sewer inspections performed in 2015 confirm that the existing sanitary sewers are in very poor condition. There is a strong likelihood that some or all laterals are bituminous fibre connections, which have a high risk of physical failure. Under Council Motion (94-G-339), sewer connections that are bituminous fibre pipe and that are in a state of failure, are the responsibility of the City including all costs associated with the replacement of the sewer connection from the sewer main to the property line. To mitigate the high probability of failure and to effectively control the City's responsibility with these assets, the proposed solution also includes the replacement of all sanitary laterals. The watermain is undersized, and well beyond its expected useful service life. It has begun to severely impact levels of service including water quality and restricted flow rates. There are no local storm sewers within this right of way. This results in a public safety concern with potential for roadway flooding during major storm events. Reconstruction of the entire right of way is anticipated to enable the City to provide the required levels of service in drinking water provision, sanitary servicing, and stormwater management.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Construction - Request $1,440,000 $50,000 $0 $0 $0 $0 $0 $0 $0 $0 $1,490,000

Total $1,440,000 $50,000 $0 $0 $0 $0 $0 $0 $0 $0 $1,490,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from Tax Capital Reserve

$835,000 $50,000 $0 $0 $0 $0 $0 $0 $0 $0 $885,000

Contribution from WW Capital Reserve

$345,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $345,000

Contribution from Water Capital Reserve

$260,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $260,000

Total $1,440,000 $50,000 $0 $0 $0 $0 $0 $0 $0 $0 $1,490,000

45

Page 51: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

HNS Allandale A Neighbourhood Renewal Program

Department:

Engineering Department

Project Number:

Z84

Summary:

Replacement of ROW assets in the HNS Allandale A Neighbourhood, including Jacobs Terrace (Innisfil to Alfred), Marcus Street (Jacobs to Campbell), Alfred Street (Jacobs to Campbell), Campbell Street (Anne to End), Wood Street (Alfred to End), Centre Street (Anne to Caroline), and Caroline Street (Alfred to Innisfil). This incorporates road reconstruction, watermain replacement, sanitary sewer replacement, sanitary lateral replacement, storm sewer replacement and upgrades, local drainage improvement, major creek channel improvements, large diameter culvert replacement and upgrade, sidewalk replacement, traffic signal replacement, and streetlighting upgrades.

Rationale:

Most of the infrastructure in this neighbourhood was constructed in the early to mid-1950s and is at or approaching the end of its maximum potential life. It has experienced age-related deterioration or physical failure (watermain breaks, etc.), and is in need of replacement. The streets in this area were identified as candidates for full Right of Way reconstruction based on aggregated risk associated with surface and subsurface infrastructure. Given the age and deteriorated condition of infrastructure, other lifecycle strategies (status quo, do nothing/run to failure, operate/maintain differently, and/or rehabilitate/refurbish) are not expected to significantly extend the existing remaining life of current assets. Full reconstruction of the Right of Way will improve service levels to the community, allow the City to monitor the performance of the assets over time, and bundle the application of future lifecycle activities together. This will reduce capital and operating costs in the long term, minimize disruption to the community, and limit environmental damages from construction.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Design - Request $470,750 $470,750 $0 $0 $0 $0 $0 $0 $0 $0 $941,500

Utilities - Forecast $0 $0 $605,000 $605,000 $0 $0 $0 $0 $0 $0 $1,210,000

Construction - Forecast $0 $0 $0 $0 $5,935,000 $5,935,000 $5,935,000 $0 $0 $0 $17,805,000

Total $470,750 $470,750 $605,000 $605,000 $5,935,000 $5,935,000 $5,935,000 $0 $0 $0 $19,956,500

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Developer Contributions

$0 $0 $0 $0 $21,844 $3,502 $2,820 $0 $0 $0 $28,166

Contribution from Tax Capital Reserve

$299,000 $299,000 $605,000 $605,000 $4,030,156 $4,048,498 $4,049,180 $0 $0 $0 $13,935,834

Contribution from WW Capital Reserve

$85,250 $85,250 $0 $0 $978,000 $978,000 $978,000 $0 $0 $0 $3,104,500

Contribution from Water Capital Reserve

$86,500 $86,500 $0 $0 $905,000 $905,000 $905,000 $0 $0 $0 $2,888,000

Total $470,750 $470,750 $605,000 $605,000 $5,935,000 $5,935,000 $5,935,000 $0 $0 $0 $19,956,500

46

Page 52: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

HNS Allandale B Neighbourhood Renewal Program

Department:

Engineering Department

Project Number:

Z82

Summary:

Replacement of right of way assets in the HNS Allandale B Neighbourhood which includes Holgate Street (Innisfil St. to Bayview Dr.), William Street (Burton Ave. to Baldwin Lane), and Granville Street (Burton Ave. to Holgate St.). The proposed solution includes road reconstruction, watermain, sanitary sewer, storm sewer, sidewalk, traffic signal and streetlighting replacement/installation.

Rationale:

Much of the infrastructure in this area is approaching the end of its useful life and needs to be replaced. The streets in this area were identified as candidates for full Right of Way reconstruction based on aggregated risk associated with surface and subsurface infrastructure. Given the age and deteriorated condition of infrastructure, other lifecycle strategies (status quo, do nothing/run to failure, operate/maintain differently, and/or rehabilitate/refurbish) are not expected to significantly extend the existing remaining life of current assets. In addition, numerous assets in the project area are undersized based on current City standards. Full reconstruction of the Right of Way will improve service levels to the community, allow the City to monitor the performance of the assets over time, and allow application of future lifecycle activities to be bundled together. This will reduce capital and operating costs in the long term, minimize disruption to the community, and limit environmental damages from construction.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Design - Request $210,125 $210,125 $0 $0 $0 $0 $0 $0 $0 $0 $420,250

Utilities - Forecast $0 $136,000 $590,000 $0 $0 $0 $0 $0 $0 $0 $726,000

Construction - Forecast $0 $0 $0 $4,882,500 $4,882,500 $0 $0 $0 $0 $0 $9,765,000

Total $210,125 $346,125 $590,000 $4,882,500 $4,882,500 $0 $0 $0 $0 $0 $10,911,250

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Developer Contributions

$0 $0 $0 $5,698 $3,695 $0 $0 $0 $0 $0 $9,393

Contribution from Federal Gas Tax Reserve

$0 $0 $0 $2,941,802 $2,943,805 $0 $0 $0 $0 $0 $5,885,607

Contribution from Tax Capital Reserve

$126,875 $262,875 $590,000 $0 $0 $0 $0 $0 $0 $0 $979,750

Contribution from WW Capital Reserve

$41,000 $41,000 $0 $960,000 $960,000 $0 $0 $0 $0 $0 $2,002,000

Contribution from Water Capital Reserve

$42,250 $42,250 $0 $975,000 $975,000 $0 $0 $0 $0 $0 $2,034,500

Total $210,125 $346,125 $590,000 $4,882,500 $4,882,500 $0 $0 $0 $0 $0 $10,911,250

47

Page 53: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

HNS Queens Park A1 Neighbourhood Renewal Program

Department:

Engineering Department

Project Number:

Z73

Summary:

The project includes pavement, watermain, sanitary sewer, storm sewer, and sidewalk replacements along with relocation of the Sophia Creek culvert to the Sophia Street Right of Way. This project area encompasses approximately half of the HNS Queens Park A1 neighbourhood, which contains some of the oldest infrastructure in the City. This includes Mary Street from Wellington Street West to Sophia Street West, Maple Avenue from Wellington Street West to Sophia Street West, and Sophia Street West from Ross Street to Bayfield Street.

Rationale:

Sophia Creek runs just north of Sophia St. W, and flow is directed southwest toward Toronto Street via two box culverts installed between 1920 and 1950. These culverts run beneath several residential properties and two businesses. Both are in poor to very poor condition, and pose significant flooding and safety risks. Other buried infrastructure in the neighbourhood, including watermains, sanitary sewers, and storm sewers, is in poor to very poor physical condition and much of it is under-sized. This infrastructure has a high probability of failure. The streets in this area were identified as candidates for full Right of Way reconstruction based on aggregated risk associated with surface and subsurface infrastructure. Given the age and deteriorated condition of infrastructure, other life-cycle strategies (status quo, do nothing/run to failure, operate/maintain differently, and/or rehabilitate/refurbish) are not expected to significantly extend the remaining life of current assets. Full reconstruction of the Right of Way will improve service levels to the community, allow the City to monitor the performance of the assets over time, and bundle the application of future life-cycle activities together. This will reduce capital and operating costs in the long term, minimize disruption to the community, and limit environmental damages from construction.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Design - Request $256,000 $29,000 $0 $0 $0 $0 $0 $0 $0 $0 $285,000

Utilities - Forecast $0 $351,250 $500,000 $0 $0 $0 $0 $0 $0 $0 $851,250

Construction - Forecast $0 $0 $0 $2,837,500 $2,837,500 $0 $0 $0 $0 $0 $5,675,000

Total $256,000 $380,250 $500,000 $2,837,500 $2,837,500 $0 $0 $0 $0 $0 $6,811,250

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from Tax Capital Reserve

$188,500 $380,250 $500,000 $2,162,500 $2,162,500 $0 $0 $0 $0 $0 $5,393,750

Contribution from WW Capital Reserve

$34,000 $0 $0 $340,000 $340,000 $0 $0 $0 $0 $0 $714,000

Contribution from Water Capital Reserve

$33,500 $0 $0 $335,000 $335,000 $0 $0 $0 $0 $0 $703,500

Total $256,000 $380,250 $500,000 $2,837,500 $2,837,500 $0 $0 $0 $0 $0 $6,811,250

48

Page 54: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

Huronia Road New Trunk Sanitary Sewer and Road Replacement - Lockhart to McKay

Department:

Engineering Department

Project Number:

Z201

Summary:

Sanitary servicing and transportation improvements to support proposed growth in the Salem Secondary Plan. Install trunk sanitary sewer under Huronia Road from Veteran's to McKay. The detailed design for Huronia Road is currently underway. The design will incorporate the ultimate reconstruction and widening of Huronia Road to 3-lanes, buffered bike lanes, sidewalks and trunk sanitary sewer between Lockhart Road and McKay Road. Interim design to be implemented in short term would maintain a rural cross section.

Rationale:

The Multi-Modal Active Transportation Master Plan identified the need to widen the existing 2-lane rural cross-section to 3-lanes, buffered bike lanes and sidewalks. A Schedule C EA was completed as part of the Annexation Transportation EA Studies. The Wastewater Collection Master Plan identified a trunk sanitary sewer to support growth in the Secondary Plan Lands. The recommendation is to acquire property for the ultimate design at this point rather than approaching property owners in the future.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Design - Request $1,855,500 $0 $0 $0 $0 $0 $0 $0 $0 $0 $1,855,500

Property - Request $2,000,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $2,000,000

Utilities - Forecast $0 $890,330 $0 $0 $0 $0 $0 $0 $0 $0 $890,330

Construction - Forecast $0 $0 $4,937,910 $4,937,910 $0 $0 $0 $0 $0 $0 $9,875,820

Total $3,855,500 $890,330 $4,937,910 $4,937,910 $0 $0 $0 $0 $0 $0 $14,621,650

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Debenture Proceeds - Tax

$419,280 $133,550 $0 $638,687 $0 $0 $0 $0 $0 $0 $1,191,517

Contribution from DC Reserves Tax (Annex)

$2,375,920 $756,780 $3,619,223 $3,619,223 $0 $0 $0 $0 $0 $0 $10,371,146

Contribution from DC Reserves Wastewater (Annex)

$901,255 $0 $285,600 $285,600 $0 $0 $0 $0 $0 $0 $1,472,455

Contribution from Tax Capital Reserve

$0 $0 $638,687 $0 $0 $0 $0 $0 $0 $0 $638,687

Contribution from WW Capital Reserve

$159,045 $0 $394,400 $394,400 $0 $0 $0 $0 $0 $0 $947,845

Total $3,855,500 $890,330 $4,937,910 $4,937,910 $0 $0 $0 $0 $0 $0 $14,621,650

49

Page 55: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

Huronia Road Pavement Holding Strategy - Little to Yonge

Department:

Engineering Department

Project Number:

000627

Summary:

Installation of asphalt pavement overlay to provide short term pavement improvements for Huronia Road from Little Ave to Yonge Street.

Rationale:

The asphalt surface on Huronia Road from Little Ave to Yonge St is in poor condition. Reconstruction/expansion of this right-of-way is included in the capital plan with construction planned for 2025 and 2026. An asphalt overlay will address problems on the surface of the roadway by providing a quality top layer of asphalt pavement. This will improve levels of service until such time as the right-of-way is reconstructed.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Design - Request $10,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $10,000

Construction - Request $145,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $145,000

Total $155,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $155,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from Tax Capital Reserve

$155,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $155,000

Total $155,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $155,000

50

Page 56: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

Hurst Drive Pavement Rehabilitation - Cox Mill to Golden Meadow

Department:

Engineering Department

Project Number:

Z1043

Summary:

The proposed work involves full-depth reclamation with expanded asphalt mix to improve the structural strength of the road, followed by adding a new lift of asphalt pavement to provide a new driving surface.

Rationale:

Hurst Drive from Cox Mill Road to Golden Meadow Road is in poor condition. The pavement in this location has failed. Substantial deterioration in the form of severe rutting and multiple transverse depressions are resulting in poor service level especially in ride comfort. Multiple solutions were considered, varying from techniques which would be less expensive, yet short-lived, to full depth reconstruction. This solution is considered to be a balanced approach that will improve the road condition with an investment that is considered affordable.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Design - Request $60,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $60,000

Construction - Forecast $0 $1,200,000 $0 $0 $0 $0 $0 $0 $0 $0 $1,200,000

Total $60,000 $1,200,000 $0 $0 $0 $0 $0 $0 $0 $0 $1,260,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from Tax Capital Reserve

$60,000 $1,200,000 $0 $0 $0 $0 $0 $0 $0 $0 $1,260,000

Total $60,000 $1,200,000 $0 $0 $0 $0 $0 $0 $0 $0 $1,260,000

51

Page 57: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

Interim Watermain Replacement Pilot Program

Department:

Engineering Department

Project Number:

EN1178

Summary:

Pilot program for the rehabilitation of various old and undersized galvanized watermains using trenchless technologies such as directional drilling and other approaches as appropriate.

Rationale:

Throughout the City there are many small and/or galvanized watermains, many of them dead ends, which are below the 150mm recommended minimum diameter as per City standards. Water Operations staff have identified substantial challenges in achieving adequate drinking water and fire flows at these mains, and are regularly required to perform maintenance activities in attempts to improve service to residents. Many of the mains are old and require upsizing and replacement. Through this program, watermains with deficient flows will be corrected by installing an interim watermain until a full watermain reconstruction can occur. This project will utilize trenchless technologies such as directional drilling to reduce the construction disruptions in the area. This project will reduce overall operational costs by reducing the need for frequent maintenance activities. The use of directional drilling will minimize road restoration costs.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Design - Request $30,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $30,000

Construction - Request $605,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $605,000

Design - Forecast $0 $30,000 $0 $0 $0 $0 $0 $0 $0 $0 $30,000

Construction - Forecast $0 $615,000 $385,000 $0 $0 $0 $0 $0 $0 $0 $1,000,000

Total $635,000 $645,000 $385,000 $0 $0 $0 $0 $0 $0 $0 $1,665,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from Water Capital Reserve

$635,000 $645,000 $385,000 $0 $0 $0 $0 $0 $0 $0 $1,665,000

Total $635,000 $645,000 $385,000 $0 $0 $0 $0 $0 $0 $0 $1,665,000

52

Page 58: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

Kidds Creek and Sophia Creek Storm Pond Upgrades - Irwin (KD03), Ford (KD06), and Ottaway (SP03)

Department:

Engineering Department

Project Number:

Z462

Summary:

Kidds Creek and Sophia Creek Storm Pond expansion and water quality upgrades - Irwin (KD03), Ford (KD06), and Ottaway (SP03)

Rationale:

The Kidds and Sophia Creek Master Drainage Plans as well as the City Growth Stormwater Management study identified several stormwater management facilities that could be expanded and upgraded to achieve a reduction in peak flows as well as phosphorus loading to Lake Simcoe. The Sophia and Kidds Creek watersheds are underserviced for water conveyance and water quality controls. The identified stormwater management facilities are critical in conveyance peak flow controls and can also provide stream water quality enhancements to support the present and future drainage servicing needs of the City.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Design - Request $64,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $64,000

Property - Forecast $0 $650,000 $0 $0 $0 $0 $0 $0 $0 $0 $650,000

Construction - Forecast $0 $0 $550,000 $0 $0 $675,000 $980,000 $0 $0 $0 $2,205,000

Total $64,000 $650,000 $550,000 $0 $0 $675,000 $980,000 $0 $0 $0 $2,919,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from DC Reserves Tax

$64,000 $650,000 $550,000 $0 $0 $675,000 $980,000 $0 $0 $0 $2,919,000

Total $64,000 $650,000 $550,000 $0 $0 $675,000 $980,000 $0 $0 $0 $2,919,000

53

Page 59: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

Lampman to Anne New Transmission Watermain and Lampman to Leacock ROW Rehabilitation

Department:

Engineering Department

Project Number:

Z350

Summary:

Installation of a new watermain from the Zone 3N Pumping Station along Anne, Letitia, Leacock, and Lampman to Browning Trail. A new Zone 3N Pumping Station will be built. The project includes a 400 mm transmission watermain, road resurfacing. Pump station works are to be performed concurrently as part of project 000629.

Rationale:

The proposed 400mm transmission watermain is part of the required water distribution system improvements for pressure Zone 3N as identified in the Water Storage and Distribution Master Plan (2013). Pressure Zone 3N currently only has one pumping station and requires a second pumping station with associated transmission watermains to provide supply redundancy and system reinforcement in the event of a pumping station or discharge watermain failure. Due to this water capacity project occurring within an older Right of Way with deteriorated pavement conditions, the proposed solution includes road rehabilitation. Cathodic protection will also be installed to preserve the condition of the existing ductile iron distribution water mains. This will achieve maximum cost efficiencies while addressing a combination of needs. Note, under a separate project (000629), the associated Anne Street booster pump station construction is being coordinated with the associated watermain work.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Utilities - Request $315,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $315,000

Construction - Forecast $0 $0 $1,050,000 $1,050,000 $0 $0 $0 $0 $0 $0 $2,100,000

Total $315,000 $0 $1,050,000 $1,050,000 $0 $0 $0 $0 $0 $0 $2,415,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from Tax Capital Reserve

$0 $0 $310,000 $310,000 $0 $0 $0 $0 $0 $0 $620,000

Contribution from Water Capital Reserve

$315,000 $0 $740,000 $740,000 $0 $0 $0 $0 $0 $0 $1,795,000

Total $315,000 $0 $1,050,000 $1,050,000 $0 $0 $0 $0 $0 $0 $2,415,000

54

Page 60: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

Lovers Creek Channel Rehabilitation - Adjacent to Brunton Park

Department:

Engineering Department

Project Number:

Z894

Summary:

Lovers Creek - channel realignment with slope stabilization and toe protection to prevent erosion of the existing creek bank and siltation in the creek. The preferred alternative requires a combination of elements; 1. Purchase lands required to accommodate realignment of the creek; 2. Excavation of the valley slope to a stable inclination, including channel realignment and 3. Complete armor protection of the channel toe-of slope.

Rationale:

The Lovers Creek main channel is eroding the toe of the valley slope as it moves through a sharp bend, causing instability of the soils leading to slope failure and loss of table lands. This active process is eroding the toe of the valley slope adjacent to Brunton Park and resulting in slope failures, public safety conditions, stream degradation and loss of park table land. As a safety precaution, the City installed a chain link fence in 2006 along the top of the valley slope to restrict public access to this area. The slope has continued to erode with storm events and has begun to encroach the fence.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Design - Request $80,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $80,000

Property - Forecast $0 $10,000 $0 $0 $0 $0 $0 $0 $0 $0 $10,000

Construction - Forecast $0 $0 $0 $0 $540,000 $0 $0 $0 $0 $0 $540,000

Total $80,000 $10,000 $0 $0 $540,000 $0 $0 $0 $0 $0 $630,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from Tax Capital Reserve

$80,000 $10,000 $0 $0 $540,000 $0 $0 $0 $0 $0 $630,000

Total $80,000 $10,000 $0 $0 $540,000 $0 $0 $0 $0 $0 $630,000

55

Page 61: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

Mapleview Dr E Road Expansion & New Trunk Watermain - East of Yonge to Prince William (City)

Department:

Engineering Department

Project Number:

Z465

Summary:

Widening of Mapleview Drive East from Yonge to Prince William to 5-lanes with buffered bike lanes, sidewalk on the south side, multi-use trail on the north side, local sanitary sewer, trunk watermain and grade separated railway crossing (underpass).

Rationale:

The Multi-Modal Active Transportation Master Plan identified the need to widen Mapleview to 5 lanes between Yonge and Prince William with a grade separated railway crossing. The Water Distribution Master Plan and Waste Collection Master Plan recommends the installation of a trunk watermain and a local sanitary sewer. A Schedule C Environmental Assessment was completed. The transportation improvements and the trunk watermain are included in the Infrastructure Implementation Plan and the Memorandum of Understanding with developers in the Secondary Plan lands. The watermain is required to provide potable water and fire flow in Phase 1 of the Hewitt's Secondary Plan area.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Design - Request $3,366,500 $3,366,500 $0 $0 $0 $0 $0 $0 $0 $0 $6,733,000

Design - Forecast $0 $179,500 $0 $0 $0 $0 $0 $0 $0 $0 $179,500

Property - Forecast $0 $0 $2,762,500 $0 $0 $0 $0 $0 $0 $0 $2,762,500

Utilities - Forecast $0 $0 $0 $4,258,200 $0 $0 $0 $0 $0 $0 $4,258,200

Construction - Forecast

$0 $0 $0 $0 $13,310,700 $14,018,400 $0 $0 $0 $0 $27,329,100

Total $3,366,500 $3,546,000 $2,762,500 $4,258,200 $13,310,700 $14,018,400 $0 $0 $0 $0 $41,262,300

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from DC Reserves Tax (Annex)

$2,861,525 $3,014,100 $2,348,125 $3,619,470 $11,314,095 $11,915,640 $0 $0 $0 $0 $35,072,955

Contribution from Tax Capital Reserve

$504,975 $531,900 $414,375 $638,730 $1,996,605 $2,102,760 $0 $0 $0 $0 $6,189,345

Total $3,366,500 $3,546,000 $2,762,500 $4,258,200 $13,310,700 $14,018,400 $0 $0 $0 $0 $41,262,300

56

Page 62: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

Mapleview Drive East Improvements - Country Lane to Yonge

Department:

Engineering Department

Project Number:

EN1097

Summary:

Widening of Mapleview Dr. E from Country Lane to Yonge to 5 lanes including: road widening and reconstruction; sanitary sewer and service installation; local storm sewer installation; water service installation; new transmission watermain (750 from Country Lane to Madeline, 600 from Madelaine to Yonge); multi-use asphalt trail on the north side; streetlight installation; and new traffic signal installation at Madelaine and at Dean.

Rationale:

Mapleview Drive East between Country Lane and Yonge is deficient with respect to traffic capacity, sidewalks, bicycle transportation, streetlights, domestic watermain and storm sewers. There is a transmission watermain and a sanitary trunk sewer required on this section of Mapleview Drive East. The proposed work will increase traffic capacity and resolve transportation and other servicing deficiencies, thereby allowing the City to provide the expected levels of service to the community while reducing risk associated with physically deteriorated and under-capacity roads and subsurface infrastructure.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Construction - Request $6,750,000 $6,850,000 $1,440,000 $0 $0 $0 $0 $0 $0 $0 $15,040,000

Total $6,750,000 $6,850,000 $1,440,000 $0 $0 $0 $0 $0 $0 $0 $15,040,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Tax Additions $75,000 $100,000 $22,500 $0 $0 $0 $0 $0 $0 $0 $197,500

Debenture Proceeds - Tax

$562,500 $562,500 $0 $0 $0 $0 $0 $0 $0 $0 $1,125,000

Contribution from DC Reserves Tax (Annex)

$3,187,500 $3,187,500 $722,500 $0 $0 $0 $0 $0 $0 $0 $7,097,500

Contribution from DC Reserves Water (Annex)

$2,000,000 $2,000,000 $400,000 $0 $0 $0 $0 $0 $0 $0 $4,400,000

Contribution from Federal Gas Tax Reserve

$700,000 $700,000 $100,000 $0 $0 $0 $0 $0 $0 $0 $1,500,000

Contribution from Tax Capital Reserve

$0 $0 $127,500 $0 $0 $0 $0 $0 $0 $0 $127,500

Contribution from WW Capital Reserve

$225,000 $300,000 $67,500 $0 $0 $0 $0 $0 $0 $0 $592,500

Total $6,750,000 $6,850,000 $1,440,000 $0 $0 $0 $0 $0 $0 $0 $15,040,000

57

Page 63: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

Mapleview Drive West Sanitary Forecemain Twinning and Pumping Station 5 Upgrades & Expansion

Department:

Engineering Department

Project Number:

EN1143

Summary:

Expansion and upgrade of the Holly Pump Station (located on Logan Court) to increase pumping capacity to 207 L/s, provide emergency storage, increase standby power supply and upgrade the building. Construct 1940m of new 400mm forcemain to service growth and provide redundancy to the existing 350mm forcemain.

Rationale:

The City Growth Studies and Waste Water Collection Master Plan identified the need to provide increased Holly Pumping Station and forcemain capacity to service Phase 1 growth within the Salem Secondary Plan. The new 400mm forcemain will provide redundancy and address existing operational and maintenance limitations. The project will increase pumping capacity and emergency storage, upgrade standby power capacity, electrical supply, and control equipment.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Construction - Request $8,145,000 $1,480,000 $0 $0 $0 $0 $0 $0 $0 $0 $9,625,000

Total $8,145,000 $1,480,000 $0 $0 $0 $0 $0 $0 $0 $0 $9,625,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from DC Reserves Wastewater (Annex)

$8,145,000 $1,480,000 $0 $0 $0 $0 $0 $0 $0 $0 $9,625,000

Total $8,145,000 $1,480,000 $0 $0 $0 $0 $0 $0 $0 $0 $9,625,000

58

Page 64: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

McKay Road New Interchange - Highway 400

Department:

Engineering Department

Project Number:

000138

Summary:

Design and construction of a new highway interchange at McKay Road and widening of the structure to a 5-lane cross section.

Rationale:

McKay Road is currently a two lane rural road in poor condition except for the crossing over Highway 400 which was recently reconstructed by MTO with financial contribution from the City so that it will accommodate a future interchange and structure widening. The proposed McKay Interchange is located in the Secondary Plan lands between Mapleview Drive and Innisfil Beach Road, the Multi-Modal Active Transportation Master Plan indicates that McKay is required to support transportation growth in the area and is a critical infrastructure capacity improvement required in Phase 1 development. The Multi-Modal Active Transportation Master Plan recommends that with increased traffic volumes the construction of a McKay Interchange and widening of the crossing from two to five lanes with buffered bike lanes and sidewalks is needed in Phase 1. The existing Mapleview Drive / Highway 400 interchange operates at a poor level of service and without the McKay Interchange in Phase 1, growth cannot be accommodated. The McKay Interchange is included in the Infrastructure Implementation Plan and the Memorandum of Understanding with developers. The McKay Schedule C Class Environmental Assessment is scheduled to be complete early in 2018.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Design - Request $1,736,900 $1,736,900 $0 $0 $0 $0 $0 $0 $0 $0 $3,473,800

Property - Forecast $0 $0 $4,363,900 $0 $0 $0 $0 $0 $0 $0 $4,363,900

Utilities - Forecast $0 $0 $0 $114,100 $0 $0 $0 $0 $0 $0 $114,100

Construction - Forecast $0 $0 $0 $0 $13,838,800 $13,838,800 $0 $0 $0 $0 $27,677,600

Total $1,736,900 $1,736,900 $4,363,900 $114,100 $13,838,800 $13,838,800 $0 $0 $0 $0 $35,629,400

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from DC Reserves Tax (Annex)

$1,440,835 $1,440,835 $3,709,315 $96,985 $11,524,640 $11,524,640 $0 $0 $0 $0 $29,737,250

Contribution from DC Reserves Water (Annex)

$41,800 $41,800 $0 $0 $280,400 $280,400 $0 $0 $0 $0 $644,400

Contribution from Tax Capital Reserve

$254,265 $254,265 $654,585 $17,115 $2,033,760 $2,033,760 $0 $0 $0 $0 $5,247,750

Total $1,736,900 $1,736,900 $4,363,900 $114,100 $13,838,800 $13,838,800 $0 $0 $0 $0 $35,629,400

59

Page 65: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

McKay Road New Trunk Sanitary Sewer and Road Expansion - Hwy 400 to Huronia

Department:

Engineering Department

Project Number:

Z204

Summary:

Construction of a trunk sanitary sewer and the associated road restoration and expansion of the two lane rural road to a 5-lane road from Huronia Road to Highway 400.

Rationale:

The City of Barrie Multi-Modal Active Transportation Master Plan identified McKay Road as a rural road in poor condition, with no current City subsurface infrastructure. The Wastewater Collection Master Plan indicated that the development of the Salem Secondary plan is fully dependent upon the installation of a trunk sanitary sewer from Huronia Road west to Highway 400. The Wastewater Collection Master Plan recommended drainage of the Salem Secondary Plan sewershed to the Lover's Trunk Sewer as it has significant available spare capacity. Road reconstruction as a result of the sewer installation will improve the safety and drivability, with increases in traffic volume necessitating an expansion from two lanes to four. Additional expansion and urbanization of the right of way to support later phases of development will not be required until post 2031, and is recommended to occur with future watermain construction. A Schedule C Environmental Assessment was completed. The two infrastructure elements have been included in both the Infrastructure Implementation Plan and the Memorandum of Understanding with developers. Property costs reflect estimated value to implement interim design. Costs to be further refined through the detailed design. Total property costs required for ultimate design are in the $10 million range. Project timing needs to be maintained as project delivers critical sanitary servicing to the Salem lands.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Design - Request $2,620,800 $0 $0 $0 $0 $0 $0 $0 $0 $0 $2,620,800

Property - Request $4,204,980 $0 $0 $0 $0 $0 $0 $0 $0 $0 $4,204,980

Utilities - Forecast $0 $1,467,492 $0 $0 $0 $0 $0 $0 $0 $0 $1,467,492

Construction - Forecast $0 $0 $8,660,938 $8,933,138 $0 $0 $0 $0 $0 $0 $17,594,076

Total $6,825,780 $1,467,492 $8,660,938 $8,933,138 $0 $0 $0 $0 $0 $0 $25,887,348

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Debenture Proceeds - Tax

$739,212 $220,124 $0 $0 $0 $0 $0 $0 $0 $0 $959,336

Contribution from DC Reserves Tax (Annex)

$4,188,868 $1,247,368 $3,961,798 $4,193,168 $0 $0 $0 $0 $0 $0 $13,591,202

Contribution from DC Reserves Wastewater (Annex)

$1,897,700 $0 $4,000,000 $4,000,000 $0 $0 $0 $0 $0 $0 $9,897,700

Contribution from Tax Capital Reserve

$0 $0 $699,140 $739,970 $0 $0 $0 $0 $0 $0 $1,439,110

Total $6,825,780 $1,467,492 $8,660,938 $8,933,138 $0 $0 $0 $0 $0 $0 $25,887,348

60

Page 66: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

Minets Point Sewage Pump Station Relocation

Department:

Engineering Department

Project Number:

000628

Summary:

Relocate the existing Minets Point Sewage Pump Station Building which is currently located in Minets Point Park away from the Whiskey Creek channel widening. The proposed solution includes, construction of a new control building and public washroom facilities as well as a review for the potential replacement of the existing pumps. The existing wet well is not expected to move, however consideration is being given to retrofits to allow for twinning the forcemain.

Rationale:

The Whiskey Creek channel is being widened as part of larger drainage improvements throughout the watershed. The pump station control building and public washrooms will need to be relocated to avoid the widened channel. This work is to be completed prior to the commencement of the watercourse improvements. Further, the pumps in the wet well are at their end of life and therefore need to be replaced. No change in location is planned for the wet well.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Design - Request $430,000 $430,000 $0 $0 $0 $0 $0 $0 $0 $0 $860,000

Construction - Forecast $0 $0 $2,500,000 $2,000,000 $540,000 $0 $0 $0 $0 $0 $5,040,000

Total $430,000 $430,000 $2,500,000 $2,000,000 $540,000 $0 $0 $0 $0 $0 $5,900,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from WW Capital Reserve

$430,000 $430,000 $2,500,000 $2,000,000 $540,000 $0 $0 $0 $0 $0 $5,900,000

Total $430,000 $430,000 $2,500,000 $2,000,000 $540,000 $0 $0 $0 $0 $0 $5,900,000

61

Page 67: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

PRV Chamber Replacement Program

Department:

Engineering Department

Project Number:

Z131

Summary:

A program to annually upgrade two existing Pressure Reducing Valves (PRVs) in the water distribution system to the new standard.

Rationale:

The City of Barrie has 29 Pressure Reducing Valves (PRVs) and chambers, excluding those installed in the last 1 to 2 years, on the water distribution system supplying water between pressure zones. They reduce pressure spikes and increase fire water supply. They are a critical component of the water supply, with some of the pressure zones having only one PRV. Many PRV chambers throughout the City are deficient and require significant maintenance to keep running, and do not have SCADA capabilities. The City has also adopted a new standard for PRV chambers, which the older assets do not meet. Staff recently completed a condition assessment and strategic plan for its existing PRVs and chambers to determine their current condition, remaining useful life, major maintenance and/or replacement needs. The proposed solution includes immediate (0-2 years), medium (3-5 years), and long term (6-10 years) replacement requirements. The PRVs in need of immediate replacement were replaced in 2015. This program is to replace the PRV chambers where the replacement was noted as medium and long term in the 2014 PRV Condition Assessment Report. This will minimize risk of PRV and chamber failure, and ensure safe and adequate drinking water and fire protection supplies for the community.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Design - Request $50,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $50,000

Construction - Request $500,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $500,000

Design - Forecast $0 $50,000 $50,000 $50,000 $0 $0 $0 $0 $0 $0 $150,000

Construction - Forecast $0 $500,000 $500,000 $500,000 $500,000 $0 $0 $0 $0 $0 $2,000,000

Total $550,000 $550,000 $550,000 $550,000 $500,000 $0 $0 $0 $0 $0 $2,700,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from Water Capital Reserve

$550,000 $550,000 $550,000 $550,000 $500,000 $0 $0 $0 $0 $0 $2,700,000

Total $550,000 $550,000 $550,000 $550,000 $500,000 $0 $0 $0 $0 $0 $2,700,000

62

Page 68: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

Road Resurfacing Program

Department:

Engineering Department

Project Number:

000333

Summary:

Annual program focused on road resurfacing to restore and preserve road pavement condition at various locations selected each year. Road resurfacing preserves the road structure and addresses problems on the surface of the roadway by replacing all or part of the asphalt pavement. Resurfacing roads using well-timed and appropriate preservation strategies is substantially less expensive than the full reconstruction of a road. The goal of the program is to maximize the life of road assets at the lowest overall life-cycle cost.

Rationale:

The City owns and maintains over 1, 500 lane km of roads all of which require renewal activities at various points in their life-cycle to ensure that service levels to the public are met in the most financially efficient way possible. Timely application of road resurfacing activities preserves and protects the road structure, thereby preventing rapid deterioration in pavement condition and the need for costly reconstruction. Risks due to unsafe driving conditions are also reduced. Resurfacing has been demonstrated to be effective in reducing the life-cycle cost of roads when applied at the right time as a part of a comprehensive pavement preservation approach. This program supports City Council's strategic goals of fostering well planned transportation, by improving road safety, and responsible spending, by demonstrating value for money.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Design - Request $150,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $150,000

Construction - Request

$3,000,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $3,000,000

Design - Forecast $0 $175,000 $200,000 $225,000 $275,000 $325,000 $375,000 $400,000 $400,000 $400,000 $2,775,000

Construction - Forecast

$0 $3,500,000 $4,000,000 $4,500,000 $5,500,000 $6,500,000 $7,500,000 $8,000,000 $8,000,000 $8,000,000 $55,500,000

Total $3,150,000 $3,675,000 $4,200,000 $4,725,000 $5,775,000 $6,825,000 $7,875,000 $8,400,000 $8,400,000 $8,400,000 $61,425,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from Federal Gas Tax Reserve

$3,000,000 $3,500,000 $4,000,000 $4,500,000 $5,500,000 $6,500,000 $7,500,000 $8,000,000 $8,000,000 $8,000,000 $58,500,000

Contribution from Tax Capital Reserve

$150,000 $175,000 $200,000 $225,000 $275,000 $325,000 $375,000 $400,000 $400,000 $400,000 $2,925,000

Total $3,150,000 $3,675,000 $4,200,000 $4,725,000 $5,775,000 $6,825,000 $7,875,000 $8,400,000 $8,400,000 $8,400,000 $61,425,000

63

Page 69: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

Sandringham Drive New 600mm Transmission Watermain - Big Bay Point to Mapleview

Department:

Engineering Department

Project Number:

EN1134

Summary:

New 600mm transmission watermain from Big Bay Point Road along Sandringham Drive to Consort Drive to Sun King Crescent to Royal Jubilee Drive to Mapleview Drive East.

Rationale:

The new transmission watermain was recommended in the Water Distribution MP to provide potable water, fire protection, system security and redundancy to service growth in Phase 1 of the Annexation lands. Currently if the transmission watermain between the SWTP and the Harvie Road Reservoir goes out of service, water supply in Zones 3S and 2S would be compromised. This transmission watermain will connect to another transmission watermain on Mapleview Drive and Madelaine Drive to complete the system loop back to Big Bay Point Road.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Construction - Request $640,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $640,000

Total $640,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $640,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from DC Reserves Water (Annex)

$640,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $640,000

Total $640,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $640,000

64

Page 70: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

Sanitary Servicing - Royal Oak, Bay, Cottage

Department:

Engineering Department

Project Number:

EN1043

Summary:

Sanitary and water servicing for the Royal Oak Drive, Forestwood Lane, Lovers Court, Tollendal Mill Road, Bay Lane, and Cottage Lane Area; and, urbanization of Royal Oak Drive, Forestwood Lane and Lovers Court. The project includes: road reconstruction; watermain replacement/new installation; sanitary sewer installation; streetlighting replacement/upgrade; sidewalk installation; storm sewer replacement/upgrade, and some minor shoreline improvements in Gables Park.

Rationale:

Sanitary servicing for the area is intended to reduce the phosphorus loading on Kempenfelt Bay from septic systems. The water servicing for Bay Lane will provide municipal water to an unserviced area, and provide better water circulation to the Royal Oak Drive, Forestwood Lane and Lovers Court properties. The infrastructure within the road rights-of-way of Royal Oak Drive, Forestwood Lane and Lovers Court is at or beyond its life cycle and should be replaced. The storm system within the Royal Oak Drive area is semi-urban and the sanitary servicing provides an opportunity to upgrade it to current city standards.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Construction - Request $2,562,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $2,562,000

Total $2,562,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $2,562,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Tax Additions $219,213 $0 $0 $0 $0 $0 $0 $0 $0 $0 $219,213

Province of Ontario Grant Revenue

$773,120 $0 $0 $0 $0 $0 $0 $0 $0 $0 $773,120

Government of Canada Grant Revenue

$1,569,667 $0 $0 $0 $0 $0 $0 $0 $0 $0 $1,569,667

Total $2,562,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $2,562,000

65

Page 71: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

Sewer Rehabilitation Program

Department:

Engineering Department

Project Number:

EN1184

Summary:

Pilot program for the rehabilitation of sanitary sewers using trenchless technologies such as cured-in-place pipe lining, slip lining, and other approaches as appropriate.

Rationale:

Throughout the City there are many sanitary sewers, both mains and laterals, which require rehabilitation but not necessarily total replacement. A program of sanitary rehabilitation using trenchless technologies, such as lining, will reduce capital costs over replacement by reducing road restoration requirements and will also reduce operational costs and staff time associated with repeated maintenance activities or emergency repairs.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Design - Request $20,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $20,000

Construction - Request $300,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $300,000

Design - Forecast $0 $20,000 $20,000 $20,000 $20,000 $0 $0 $0 $0 $0 $80,000

Construction - Forecast $0 $300,000 $300,000 $300,000 $300,000 $300,000 $0 $0 $0 $0 $1,500,000

Total $320,000 $320,000 $320,000 $320,000 $320,000 $300,000 $0 $0 $0 $0 $1,900,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from WW Capital Reserve

$320,000 $320,000 $320,000 $320,000 $320,000 $300,000 $0 $0 $0 $0 $1,900,000

Total $320,000 $320,000 $320,000 $320,000 $320,000 $300,000 $0 $0 $0 $0 $1,900,000

66

Page 72: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

St. Vincent Street Watermain Replacement - S of Highway 400 to Bell Farm

Department:

Engineering Department

Project Number:

000112

Summary:

Decommissioning of the dead-end watermain, which acts as a service connection, at St. Vincent St. and Bell Farm Rd. and replacing it with a new service connection from Alliance Blvd.

Rationale:

This dead-end watermain is at the end of its useful life and has experienced numerous recent breaks. The proposed solution includes decommissioning the main and replacing the affected services by connecting them to the watermain on Alliance Blvd. This project will eliminate the risk of repeated failures of this aging watermain and reduce the associated costs from emergency repairs.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Construction - Request $125,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $125,000

Total $125,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $125,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from Water Capital Reserve

$125,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $125,000

Total $125,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $125,000

67

Page 73: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

Water Service and Backflow Prevention Upgrades for Parks and Open Spaces

Department:

Engineering Department

Project Number:

EN1152

Summary:

Installation of backflow prevention devices and water meters for Parks and Open Spaces to reduce the risk of water distribution system contamination and to improve water consumption/usage data.

Rationale:

Water services for many Parks and Open Spaces pose a potential risk for contamination of the drinking water system due to the lack of backflow prevention devices and/or the improper installation of devices. The City’s Backflow Prevention By-law 2010-102 (as amended) requires the City to upgrade these Parks and Open Spaces water service connections to comply with this municipal standard and ensure the protection of the municipal drinking water system from potential cross connections. Additionally, over 90% of all Parks and Open Spaces water services are un-metered resulting in a large quantity of water that is un-accounted for. This lack of metering significantly impacts the ability to accurately calculate water loss values and subsequently the leakage index for the water distribution system.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Construction - Request $195,000 $195,000 $0 $0 $0 $0 $0 $0 $0 $0 $390,000

Total $195,000 $195,000 $0 $0 $0 $0 $0 $0 $0 $0 $390,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from Water Capital Reserve

$195,000 $195,000 $0 $0 $0 $0 $0 $0 $0 $0 $390,000

Total $195,000 $195,000 $0 $0 $0 $0 $0 $0 $0 $0 $390,000

68

Page 74: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

Watermain Cathodic Protection Program

Department:

Engineering Department

Project Number:

EN1189

Summary:

Installation of watermain cathodic protection on existing ductile iron watermains. The anodes will be connected to ductile iron watermains by insulated copper wires; the anodes will corrode, rather than the watermain to which they are attached, thereby extending the life of the watermain.

Rationale:

Ductile iron watermains are more prone to corrosion than non-ferrous pipes. This results in damage to the pipe surface, including pitting, scaling, and other depressions, which eventually leads to cracks, holes and other physical failures. Such damage substantially reduces the maximum potential life of these mains, resulting in increased operational and emergency repair costs as well as service disruptions. Cast Iron pipes, similarly prone to corrosion-related failure, can also be protected via cathodic protection; however it is not intended that these assets will receive such treatment as it is likely that the City will replace them before a return on investment for cathodic protection would be realized. This program is intended to apply cathodic protection to all ductile iron mains that are not otherwise proposed for replacement in other capital projects, and that fall within the recommended age (40 years or younger) to maximize the benefit of cathodic protection. Installation of cathodic protection is expected to increase the life of ductile iron watermains by up to 15 years.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Design - Request $40,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $40,000

Construction - Request $960,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $960,000

Design - Forecast $0 $40,000 $40,000 $40,000 $40,000 $40,000 $40,000 $0 $0 $0 $240,000

Construction - Forecast

$0 $960,000 $960,000 $960,000 $960,000 $960,000 $960,000 $960,000 $0 $0 $6,720,000

Total $1,000,000 $1,000,000 $1,000,000 $1,000,000 $1,000,000 $1,000,000 $1,000,000 $960,000 $0 $0 $7,960,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from Water Capital Reserve

$1,000,000 $1,000,000 $1,000,000 $1,000,000 $1,000,000 $1,000,000 $1,000,000 $960,000 $0 $0 $7,960,000

Total $1,000,000 $1,000,000 $1,000,000 $1,000,000 $1,000,000 $1,000,000 $1,000,000 $960,000 $0 $0 $7,960,000

69

Page 75: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

Watermain CIPP Lining Program

Department:

Engineering Department

Project Number:

000545

Summary:

Pilot program for the rehabilitation of watermains using trenchless technologies such as cured-in-place pipe lining in existing ductile and cast iron watermains as part of an annual rehabilitation program. 2018 work includes the design for Blake Street, from Puget Street to Penetanguishene Road, with future work proposed to include Nelson Street - Grove Street to Colleen Avenue, Shanty Bay Road - Vancouver Street to Penetanguishene Road, Jills Court, Colleen Avenue - Colleen Avenue, Jeffrey Street - Grove Street to Colleen Avenue, and Curtiss Court - Jeffrey Street to Jeffrey Street.

Rationale:

A third of the City’s water distribution network comprises cast and ductile iron mains, and many are approaching or at the end of their Maximum Potential Life (MPL) of 80 and 60 years. Metallic mains are prone to corrosion, which can result in pipe wall thinning and pitting leading to cracks, fractures, and breaks, further reducing the remaining useful life. This represents a significant challenge in meeting service requirements when numerous breaks occur on the same main. Repeated, reactive repairs to watermains necessitate investment in excavation of and damage to other assets, such as roadways and sidewalks, which shortens these other assets’ remaining useful lives as well. If the City does not invest in rehabilitation for these watermain assets, it will assume the increased risk associated with repeated break failures and public safety concerns with inadequate fire flows as service levels decrease. Cured-in-place pipe creates a fully structural, corrosion-resistant, pipe-within-a-pipe, without the need to remove the old main. This has several advantages when road and other subsurface infrastructure replacement is not required. Construction time is typically shorter and disruption to water service is minimized, with many projects completed in days rather than weeks or months. Traffic disturbances are also minimized since only a handful of excavation pits may be required instead of shutting down an entire lane(s). Reduced use of asphalt and watermain replacement materials carries a smaller CO2 footprint than trenching, and case studies suggest that opting to rehabilitate pipes with CIPP rather than replacing them with more conventional methods can achieve up to 40% savings. The project solution to implement a CIPP lining program supports Council’s strategic goal of responsible spending by taking a cost-effective approach to the immediately recommended work as well as potential rehabilitation work in future, while also ensuring that key service levels are maintained.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Design - Request $32,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $32,000

Design - Forecast $0 $32,000 $6,000 $10,000 $15,000 $0 $0 $0 $0 $0 $63,000

Construction - Forecast $0 $970,000 $970,000 $180,000 $310,000 $445,000 $0 $0 $0 $0 $2,875,000

Total $32,000 $1,002,000 $976,000 $190,000 $325,000 $445,000 $0 $0 $0 $0 $2,970,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from Water Capital Reserve

$32,000 $1,002,000 $976,000 $190,000 $325,000 $445,000 $0 $0 $0 $0 $2,970,000

Total $32,000 $1,002,000 $976,000 $190,000 $325,000 $445,000 $0 $0 $0 $0 $2,970,000

70

Page 76: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

Wellington D1 Neighbourhood Renewal Program

Department:

Engineering Department

Project Number:

000052

Summary:

Reconstruction of four streets (Berczy, Amelia, Theresa, and Worsley) in the Wellington D neighbourhood, including road reconstruction, watermain replacement, sanitary sewer replacement and upgrading to current City standards, sanitary lateral replacement to property line, storm sewer replacement and installation, sidewalk replacement, and streetlight upgrades.

Rationale:

This neighbourhood contains some of the City’s oldest subsurface infrastructure outside of the downtown core. Through the Neighbourhood Renewal Program (NRP), designed to highlight and address the renewal needs of local areas which are often overlooked due to high priority projects on arterial/collector roads, the streets in this area were identified as candidates for full Right of Way reconstruction based on aggregated risk associated with surface and subsurface infrastructure. Given the age and deteriorated condition of infrastructure, other lifecycle strategies (status quo, do nothing/run to failure, operate/maintain differently, and/or rehabilitate/refurbish) are not expected to significantly extend the existing remaining life of current assets. Full reconstruction of the Right of Way will improve service levels to the community and allow the City to monitor the performance of the assets over time and bundle the application of future lifecycle activities together. This will reduce capital and operating costs in the long term, minimize disruption to the community, and limit environmental damages from construction.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Design - Request $86,100 $81,100 $0 $0 $0 $0 $0 $0 $0 $0 $167,200

Utilities - Forecast $0 $240,000 $240,000 $0 $0 $0 $0 $0 $0 $0 $480,000

Construction - Forecast $0 $0 $0 $2,280,000 $2,280,000 $0 $0 $0 $0 $0 $4,560,000

Total $86,100 $321,100 $240,000 $2,280,000 $2,280,000 $0 $0 $0 $0 $0 $5,207,200

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from Tax Capital Reserve

$34,100 $269,100 $240,000 $1,385,000 $1,385,000 $0 $0 $0 $0 $0 $3,313,200

Contribution from WW Capital Reserve

$37,000 $37,000 $0 $475,000 $475,000 $0 $0 $0 $0 $0 $1,024,000

Contribution from Water Capital Reserve

$15,000 $15,000 $0 $420,000 $420,000 $0 $0 $0 $0 $0 $870,000

Total $86,100 $321,100 $240,000 $2,280,000 $2,280,000 $0 $0 $0 $0 $0 $5,207,200

71

Page 77: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

Wellington D2 Neighbourhood Renewal Program

Department:

Engineering Department

Project Number:

000071

Summary:

Reconstruction of Three streets (Amelia, Albert, and Dundonald) in the Wellington D neighbourhood, including road reconstruction, distribution watermain replacement, sanitary sewer replacement and upgrading to current City standards, sanitary lateral replacement to property line, storm sewer replacement and installation, sidewalk replacement and installation, and streetlight upgrades.

Rationale:

Most of the infrastructure in this neighbourhood was constructed in the early to mid-1950s and is at or approaching the end of its maximum potential life. It has experienced age-related deterioration or physical failure (watermain breaks, etc.), and is in need of replacement. The streets in this area were identified as candidates for full Right of Way reconstruction based on aggregated risk associated with surface and subsurface infrastructure. Given the age and deteriorated condition of infrastructure, other lifecycle strategies (status quo, do nothing/run to failure, operate/maintain differently, and/or rehabilitate/refurbish) are not expected to significantly extend the existing remaining life of current assets. Full reconstruction of the Right of Way will improve service levels to the community, allow the City to monitor the performance of the assets over time, and bundle the application of future lifecycle activities together. This will reduce capital and operating costs in the long term, minimize disruption to the community, and limit environmental damages from construction.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Pre-Design - Request $70,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $70,000

Design - Forecast $0 $137,000 $137,000 $0 $0 $0 $0 $0 $0 $0 $274,000

Utilities - Forecast $0 $0 $410,000 $410,000 $0 $0 $0 $0 $0 $0 $820,000

Construction - Forecast $0 $0 $0 $0 $2,590,000 $2,590,000 $2,590,000 $0 $0 $0 $7,770,000

Total $70,000 $137,000 $547,000 $410,000 $2,590,000 $2,590,000 $2,590,000 $0 $0 $0 $8,934,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from Tax Capital Reserve

$70,000 $83,000 $493,000 $410,000 $1,570,000 $1,570,000 $1,570,000 $0 $0 $0 $5,766,000

Contribution from WW Capital Reserve

$0 $29,000 $29,000 $0 $540,000 $540,000 $540,000 $0 $0 $0 $1,678,000

Contribution from Water Capital Reserve

$0 $25,000 $25,000 $0 $480,000 $480,000 $480,000 $0 $0 $0 $1,490,000

Total $70,000 $137,000 $547,000 $410,000 $2,590,000 $2,590,000 $2,590,000 $0 $0 $0 $8,934,000

72

Page 78: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

WwTF Biosolids Storage Tank Mixers

Department:

Engineering Department

Project Number:

EN1127

Summary:

The existing mechanical mixers in the circular storage tanks installed in 1998 do not perform up to standards and provide incomplete mixing in the biosolids tanks. This results in increased operation maintenance costs, downtime when mixers are taken out of service for repairs, and/or replacement of the mixer. To improve operations and provide the desired mixing, a 2012/2013 study investigated different mixing technologies and recommended the mixers be replaced with advanced jet mixing. In 2016, the preliminary design phase identified Hydro One power lines and upgrades to the BSF electrical distribution system were required to support the mixer project.

Rationale:

Replacement of the BSF mixers with an advanced jet mixing system will improve operations at the Biosolids Facility. In 2016, the preliminary design phase identified upgrades to the Hydro One power line and electrical upgrades to the BSF distribution system are recommended in 2018 to support the proposed jet mixing system upgrades. The BSF Mixer Replacement Project will improve mixing efficiency in the circular tanks, reduce operating and maintenance costs, reduce transportation costs, and provide operation flexibility at the BSF to provide a better quality Biosolids for land application and compliance with the Nutrient Management Act.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Construction - Request $800,000 $1,600,000 $348,000 $0 $0 $0 $0 $0 $0 $0 $2,748,000

Total $800,000 $1,600,000 $348,000 $0 $0 $0 $0 $0 $0 $0 $2,748,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Debenture Proceeds - Wastewater

$800,000 $1,600,000 $348,000 $0 $0 $0 $0 $0 $0 $0 $2,748,000

Total $800,000 $1,600,000 $348,000 $0 $0 $0 $0 $0 $0 $0 $2,748,000

73

Page 79: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

WwTF Chemical Building Upgrade

Department:

Engineering Department

Project Number:

000108

Summary:

This project is to upgrade the chemical building at the Wastewater Treatment Facility to meet current chemical storage requirements and to reduce odour when the biosolids truck loading arm is in use. The scope for the upgrades, and potential building expansion, include, structural, electrical, mechanical and life safety systems.

Rationale:

The City of Barrie is obliged to comply with growing number of legislative requirements. Achieving compliance is becoming increasingly difficult given the aging asset portfolio and other pressures on limited financial resources. The obligations include these related to fire and life safety requirements, hazardous substances, and environmental protection. Within the context of managing assets, the existing chemical building currently houses on different levels two incompatible chemicals without a scrubber for the off gases, and there is no odour control. The proposed study will recommend preferred engineered controls to protect the workers and that relevant codes and standards are adhered too.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Pre-Design - Request $50,000 $50,000 $0 $0 $0 $0 $0 $0 $0 $0 $100,000

Total $50,000 $50,000 $0 $0 $0 $0 $0 $0 $0 $0 $100,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from WW Capital Reserve

$50,000 $50,000 $0 $0 $0 $0 $0 $0 $0 $0 $100,000

Total $50,000 $50,000 $0 $0 $0 $0 $0 $0 $0 $0 $100,000

74

Page 80: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

WwTF Cogeneration Building Ventilation Upgrades

Department:

Engineering Department

Project Number:

000101

Summary:

Wastewater Treatment Facility (WwTF) ventilation upgrades at the cogeneration building are needed to improve boiler room and cogen room air ventilation and reduce noise originating from within the building. The scope includes: new outdoor air cooled waste heat exchangers for the two co-gen engines; address separation of combustion air to mitigate short-circulation; automatic control of exhaust gas to the heat exchanger; upsize louvres; and improve temperature control and noise mitigation.

Rationale:

The Cogenerator building ventilation is not meeting current capacity needs. A study was undertaken that identified a preferred solution that would resolve issues associated with poor ventilation, high temperatures, noise mitigation and safety. The proposed upgrades will: extend the useful life of the major equipment (e.g., co-generators, boilers, etc.); ensure compliance with legislation /standards with respect to noise originating from the building and the effects on the waterfront; and improve safety for the public.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Design - Request $50,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $50,000

Construction - Forecast $0 $0 $300,000 $0 $0 $0 $0 $0 $0 $0 $300,000

Total $50,000 $0 $300,000 $0 $0 $0 $0 $0 $0 $0 $350,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from WW Capital Reserve

$50,000 $0 $300,000 $0 $0 $0 $0 $0 $0 $0 $350,000

Total $50,000 $0 $300,000 $0 $0 $0 $0 $0 $0 $0 $350,000

75

Page 81: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

WwTF Electrical Substation and Transformer Upgrade

Department:

Engineering Department

Project Number:

000562

Summary:

At the Wastewater Treatment Facility (WwTF), it is proposed to replace the existing electrical infrastructure, including substation and transformers, in coordination with the new electrical requirements for the Membrane Bio-Reactor (MBR) project. The new MBR electrical infrastructure construction is anticipated to start in 2019, ahead of the main project.

Rationale:

The existing electrical substation and transformers were installed in 1984 and have a typical lifespan of 25 to 30 years. Recent maintenance reports have observed leaking that has resulted in ongoing clean up and monitoring since 2015 to mitigate environmental contamination. Further the proposed MBR will require additional power requirements above what is existing to run the plant resulting in the eventual upgrade of the electrical substation and transformers. To lessen the schedule impacts to the MBR project it is proposed to replace the electrical infrastructure now in coordination with the electrical requirements for the MBR project. The substation and transformer replacements are needed to keep the equipment in a state of good repair. At this time temporary measures have been instituted to ensure the operation of the equipment to cover the duration to design and construct. The WwTF is dependent upon this equipment to remain in compliance with the Environmental Protection Act and in particular, the Environmental Compliance Approval.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Design - Request $150,000 $160,000 $0 $0 $0 $0 $0 $0 $0 $0 $310,000

Construction - Forecast $0 $700,000 $530,000 $200,000 $0 $0 $0 $0 $0 $0 $1,430,000

Total $150,000 $860,000 $530,000 $200,000 $0 $0 $0 $0 $0 $0 $1,740,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from WW Capital Reserve

$150,000 $860,000 $530,000 $200,000 $0 $0 $0 $0 $0 $0 $1,740,000

Total $150,000 $860,000 $530,000 $200,000 $0 $0 $0 $0 $0 $0 $1,740,000

76

Page 82: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

WwTF In-plant Peak Attenuation/Equalization Tank Retrofit

Department:

Engineering Department

Project Number:

000565

Summary:

At the Wastewater Treatment Facility (WwTF) it is proposed to continually optimize the wastewater treatment process by refurbishing an existing secondary clarifier tank to perform as a dual purpose tank for peak attenuation and equalization. The overall project includes Predesign, Design, Construction, Performance Verification and Warranty.

Rationale:

Peak Attenuation is required to protect the treatment processes within the WwTF during increasingly intense storm events and quicker snow melts that have become common with changes in climate. The dual purpose tank will also be used for equalization which assists in providing a more steady flow feeding the biological process. Although this project is not required for the MBR project, installing the flow equalization will improve the performance of the existing treatment trains thus reducing the capital cost. It is proposed to optimize the wastewater treatment by utilizing an existing secondary clarifier for peak attenuation/equalization. This would mitigate the risk of wastewater flooding the streets and possible basements near the WwTF.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Pre-Design - Request $60,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $60,000

Design - Forecast $0 $175,000 $175,000 $0 $0 $0 $0 $0 $0 $0 $350,000

Construction - Forecast $0 $0 $0 $0 $720,000 $1,440,000 $230,000 $0 $0 $0 $2,390,000

Total $60,000 $175,000 $175,000 $0 $720,000 $1,440,000 $230,000 $0 $0 $0 $2,800,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from WW Capital Reserve

$60,000 $175,000 $175,000 $0 $720,000 $1,440,000 $230,000 $0 $0 $0 $2,800,000

Total $60,000 $175,000 $175,000 $0 $720,000 $1,440,000 $230,000 $0 $0 $0 $2,800,000

77

Page 83: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

WwTF MBR Project Concrete Tanks Rehabilitation

Department:

Engineering Department

Project Number:

000548

Summary:

Concrete rehabilitation of Secondary Treatment Tanks dedicated to the MBR Project. The work includes a Condition Assessment of the interior of the tanks, Detailed Design, and Construction Administration for concrete resurfacing, caulking of expansion joints, and crack repair. The timing of this work is to align with the MBR project.

Rationale:

The Secondary Clarifier Tanks 1 and 2 were reconstructed in 1998 when Secondary Clarifier 3 was built. The 2007 Condition Assessment identified notable signs of concrete deterioration. Most notably failure of the caulking sealing expansion joints and degradation to the concrete surfaces caused by chemical attack and mechanical abrasion. These tanks will be dedicated to the proposed MBR project. In the interest of mitigating potential risks to the new MBR and increased asset longevity, concrete surface restoration is required. This work is to be completed prior to the construction of the MBR so as to not delay the installation of the membranes.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Design - Request $110,000 $110,000 $0 $0 $0 $0 $0 $0 $0 $0 $220,000

Construction - Forecast $0 $0 $900,000 $800,000 $0 $0 $0 $0 $0 $0 $1,700,000

Total $110,000 $110,000 $900,000 $800,000 $0 $0 $0 $0 $0 $0 $1,920,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from WW Capital Reserve

$110,000 $110,000 $900,000 $800,000 $0 $0 $0 $0 $0 $0 $1,920,000

Total $110,000 $110,000 $900,000 $800,000 $0 $0 $0 $0 $0 $0 $1,920,000

78

Page 84: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

WwTF Sludge Thickening System Process - Polymer System Replacement

Department:

Engineering Department

Project Number:

000049

Summary:

Replacement of the existing Polymer System at the Wastewater Treatment Facility. The project includes design changes to the Sludge Thickening Room and construction including mechanical, electrical, heating and ventilation upgrades, and ancillary work to make the system functional.

Rationale:

The existing dry polymer batching system poses health and safety concerns to the operators and require them to wear their personal protective equipment when they make a new batch. There is not enough space to safely operate a forklift and heating and ventilation upgrades are required to bring the room up to code. Changing to a liquid polymer system will improve polymer delivery and reduce operating costs. The WWOB will procure the liquid polymer and require Engineering to design the delivery system.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Design - Request $165,000 $165,000 $0 $0 $0 $0 $0 $0 $0 $0 $330,000

Construction - Forecast $0 $0 $1,442,000 $158,000 $0 $0 $0 $0 $0 $0 $1,600,000

Total $165,000 $165,000 $1,442,000 $158,000 $0 $0 $0 $0 $0 $0 $1,930,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from WW Capital Reserve

$165,000 $165,000 $1,442,000 $158,000 $0 $0 $0 $0 $0 $0 $1,930,000

Total $165,000 $165,000 $1,442,000 $158,000 $0 $0 $0 $0 $0 $0 $1,930,000

79

Page 85: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

WwTF UNOX To Aeration Tanks Conversion (Phase 1)

Department:

Engineering Department

Project Number:

000560

Summary:

Upgrade the UNOX reactors 1 and 2 with proposed fine bubble aeration. The project includes the preliminary design to blank off the High Purity Oxygen (HPOX) Supply to these tanks, demolition of the existing HPOX equipment, and installation of fine bubble aeration equipment. Phase 2, Intake 589, will convert the remainder of UNOX tanks from HPOX to proposed fine bubble diffusion aeration and the total removal of the High Purity Oxygen system.

Rationale:

Upgrading the UNOX Reactors with conventional aeration is recommended as it is technically feasible requiring no new tankage, cost effective with a payback estimated to be in the 5 to 10 year range, and has value added benefits that could render the other existing Wastewater Treatment Facility (WwTF) equipment redundant in the future.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Design - Request $370,000 $370,000 $0 $0 $0 $0 $0 $0 $0 $0 $740,000

Construction - Forecast $0 $0 $0 $0 $3,000,000 $3,000,000 $810,000 $0 $0 $0 $6,810,000

Total $370,000 $370,000 $0 $0 $3,000,000 $3,000,000 $810,000 $0 $0 $0 $7,550,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from WW Capital Reserve

$370,000 $370,000 $0 $0 $3,000,000 $3,000,000 $810,000 $0 $0 $0 $7,550,000

Total $370,000 $370,000 $0 $0 $3,000,000 $3,000,000 $810,000 $0 $0 $0 $7,550,000

80

Page 86: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

Yonge Street ROW Expansion - Mapleview to Lockhart

Department:

Engineering Department

Project Number:

Z313

Summary:

Reconstruction and widening of Yonge Street to 5 lanes, buffered bike lanes and sidewalks between Mapleview Drive and Lockhart Road.

Rationale:

The Multi-Modal Active Transportation Master Plan identified the need to widen Yonge Street to accommodate planned growth in the Secondary Plan lands, which will support the proposed mixed-use development that is identified for this corridor in the Hewitt's Secondary Plan. The existing 2 lane rural cross-section is not sufficient to accommodate traffic volumes associated with planned growth. The preferred alternative identified the need to widen Yonge Street to 5 lanes and include buffered bike lanes and sidewalks.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Design - Request $615,700 $0 $0 $0 $0 $0 $0 $0 $0 $0 $615,700

Property - Request $200,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $200,000

Property - Forecast $0 $0 $0 $0 $0 $284,200 $0 $0 $0 $0 $284,200

Utilities - Forecast $0 $183,000 $0 $0 $0 $0 $176,500 $0 $0 $0 $359,500

Construction - Forecast $0 $0 $4,567,800 $0 $0 $0 $0 $3,969,900 $0 $0 $8,537,700

Total $815,700 $183,000 $4,567,800 $0 $0 $284,200 $176,500 $3,969,900 $0 $0 $9,997,100

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Debenture Proceeds - Tax

$122,355 $27,450 $0 $0 $0 $0 $0 $0 $0 $0 $149,805

Contribution from DC Reserves Tax (Annex)

$693,345 $155,550 $3,882,630 $0 $0 $241,570 $150,025 $3,374,415 $0 $0 $8,497,535

Contribution from Tax Capital Reserve

$0 $0 $685,170 $0 $0 $42,630 $26,475 $595,485 $0 $0 $1,349,760

Total $815,700 $183,000 $4,567,800 $0 $0 $284,200 $176,500 $3,969,900 $0 $0 $9,997,100

81

Page 87: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

Big Bay Point New Transmission Watermain and Road Expansion - Prince William to Street N (Developer)

Department:

Engineering Department

Project Number:

Z282

Summary:

Expansion of Big Bay Point Road potentially in phases, including urbanization and widening of the road from two to three or five lanes and installation of a new watermain from the former City limits to Collector 11.

Rationale:

Proposed development south of Big Bay Point Road in the Hewitt's Secondary Plan area justifies urbanizing Big Bay Point Road and increasing to three or five lanes. Trunk watermain is needed to provide potable water and fire protection in phase 1 of the Hewitt's Secondary Plan from Collector 11 to Street N. The Transportation MP recommended that Big Bay Point Road be urbanized and widened to 5 lanes to former Barrie Boundary. Funding for this project is partially front-ended by Developers to provide servicing required for Phase 1 of growth-related development in the secondary plan area.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Property - Request $389,500 $0 $0 $0 $0 $0 $0 $0 $0 $0 $389,500

Utilities - Forecast $0 $90,300 $0 $0 $0 $0 $0 $0 $0 $0 $90,300

Construction - Forecast $0 $572,500 $1,166,900 $0 $0 $0 $0 $0 $0 $788,700 $2,528,100

Total $389,500 $662,800 $1,166,900 $0 $0 $0 $0 $0 $0 $788,700 $3,007,900

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Developer Front Ending (Annex) - Developer Build

$331,075 $563,380 $1,016,165 $0 $0 $0 $0 $0 $0 $670,395 $2,581,015

Debenture Proceeds - Tax

$58,425 $99,420 $0 $0 $0 $0 $0 $0 $0 $0 $157,845

Contribution from Tax Capital Reserve

$0 $0 $150,735 $0 $0 $0 $0 $0 $0 $118,305 $269,040

Total $389,500 $662,800 $1,166,900 $0 $0 $0 $0 $0 $0 $788,700 $3,007,900

82

Page 88: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

Essa Road New Transmission Watermain and Road Expansion - Athabaska to TCP (Developer)

Department:

Engineering Department

Project Number:

Z483

Summary:

Expansion of Essa Road, including urbanization and widening of the road from two to three lanes, with buffered bike lanes, and installation of a trunk watermain.

Rationale:

Increases in traffic volumes resulting from growth in the Annexation area justify increasing the number of lanes and urbanizing Essa Road. The trunk watermain is needed to provide potable water and fire protection in Phase 1 of the Salem Secondary Plan. Funding for this project is partially front-ended by Developers to provide servicing required for Phase 1 of growth-related development in the secondary plan area.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Property - Request $444,200 $0 $0 $0 $0 $0 $0 $0 $0 $0 $444,200

Utilities - Forecast $0 $413,100 $573,000 $573,000 $0 $0 $0 $0 $0 $0 $1,559,100

Construction - Forecast $0 $0 $3,925,700 $3,925,700 $0 $0 $0 $0 $0 $0 $7,851,400

Total $444,200 $413,100 $4,498,700 $4,498,700 $0 $0 $0 $0 $0 $0 $9,854,700

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Developer Front Ending (Annex) - Developer Build

$377,570 $351,135 $3,872,690 $3,872,690 $0 $0 $0 $0 $0 $0 $8,474,085

Debenture Proceeds - Tax

$66,630 $61,965 $0 $626,010 $0 $0 $0 $0 $0 $0 $754,605

Contribution from Tax Capital Reserve

$0 $0 $626,010 $0 $0 $0 $0 $0 $0 $0 $626,010

Total $444,200 $413,100 $4,498,700 $4,498,700 $0 $0 $0 $0 $0 $0 $9,854,700

83

Page 89: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

Hewitt's Creek New Trunk Sanitary Sewer - Mapleview to Lockhart (Developer)

Department:

Engineering Department

Project Number:

EN1137

Summary:

Installation of a new trunk sanitary sewer.

Rationale:

Installation of a new trunk sanitary sewer in the Hewitt's Secondary Plan area is required to service growth. Funding for this project is partially front-ended by Developers to provide servicing required for Phase 1 of growth-related development in the secondary plan area.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Construction - Request $474,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $474,000

Construction - Forecast $0 $1,000,000 $1,000,000 $1,000,000 $0 $1,000,000 $1,000,000 $0 $0 $56,025 $5,056,025

Total $474,000 $1,000,000 $1,000,000 $1,000,000 $0 $1,000,000 $1,000,000 $0 $0 $56,025 $5,530,025

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Developer Front Ending (Annex) - Developer Build

$274,920 $580,000 $580,000 $580,000 $0 $580,000 $580,000 $0 $0 $28,013 $3,202,933

Contribution from WW Capital Reserve

$199,080 $420,000 $420,000 $420,000 $0 $420,000 $420,000 $0 $0 $28,013 $2,327,093

Total $474,000 $1,000,000 $1,000,000 $1,000,000 $0 $1,000,000 $1,000,000 $0 $0 $56,025 $5,530,025

84

Page 90: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

Mapleview Dr E New Sanitary Sewer & Road Expansion - Prince William to Phase 1 Boundary (Developer)

Department:

Engineering Department

Project Number:

Z463

Summary:

Expansion of Mapleview Drive East, including installation of a sanitary sewer, and road widening from two lanes to three lanes with adjacent multi-use trail.

Rationale:

Different sanitary servicing alternatives were examined in the Wastewater Collection MP for the Salem Secondary Plan area. The preferred alternative was to drain this sewer shed to the Hewitt's Trunk Sewer because this sewer has spare capacity. Anticipated increases in traffic volumes and active transportation resulting from growth in the Annexation area justifies urbanizing Mapleview Drive east of Prince William Way. The Transportation MP recommended three lanes plus buffered bike lanes. Within former Barrie the existing road is relatively new but the south side has not been urbanized. In consideration of this the project scope was adjusted to include a multi-use trail to retain as much of the existing road as possible. Funding for this project is partially front-ended by Developers to provide servicing required for Phase 1 of growth-related development in the secondary plan area.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Property - Request $1,000,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $1,000,000

Utilities - Forecast $0 $656,100 $0 $0 $0 $0 $0 $0 $0 $0 $656,100

Construction - Forecast $0 $0 $7,159,600 $0 $0 $0 $0 $0 $0 $0 $7,159,600

Total $1,000,000 $656,100 $7,159,600 $0 $0 $0 $0 $0 $0 $0 $8,815,700

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Developer Front Ending (Annex) - Developer Build

$850,000 $557,685 $6,386,875 $0 $0 $0 $0 $0 $0 $0 $7,794,560

Debenture Proceeds - Tax

$150,000 $98,415 $0 $0 $0 $0 $0 $0 $0 $0 $248,415

Contribution from Tax Capital Reserve

$0 $0 $772,725 $0 $0 $0 $0 $0 $0 $0 $772,725

Total $1,000,000 $656,100 $7,159,600 $0 $0 $0 $0 $0 $0 $0 $8,815,700

85

Page 91: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

Mapleview Drive E New Transmisison Watermain - Yonge to Prince William (Developer)

Department:

Engineering Department

Project Number:

000468

Summary:

Installation of a transmission watermain on Mapleview Drive East, from Yonge to Prince William.

Rationale:

The Water Distribution Master Plan calls for a transmission watermain to service and provide redundancy to development in the secondary plan area, to ensure adequate potable water supply and fire protection flows. Funding for this project is front-ended by Developers to provide servicing required for Phase 1 of growth-related development in the secondary plan area. The transmission watermain is proposed south of Mapleview through the proposed subdivision.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Construction - Request $2,131,900 $0 $0 $0 $0 $0 $0 $0 $0 $0 $2,131,900

Total $2,131,900 $0 $0 $0 $0 $0 $0 $0 $0 $0 $2,131,900

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Developer Front Ending (Annex) - Developer Build

$2,131,900 $0 $0 $0 $0 $0 $0 $0 $0 $0 $2,131,900

Total $2,131,900 $0 $0 $0 $0 $0 $0 $0 $0 $0 $2,131,900

86

Page 92: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

McKay Road ROW Expansion - County Road 27 to Highway 400 (Developer)

Department:

Engineering Department

Project Number:

Z229

Summary:

Construction of a trunk sanitary sewer and watermain from Highway 400 westerly. Expansion of the McKay Road right of way, with the construction of a five lane urban road from Reid Drive to Highway 400 and the south half of a three lane rural road from portions of County Road 27 to Reid Drive.

Rationale:

The City of Barrie Growth Studies and Multi-Modal Active Transportation Master Plan identified McKay Road as a rural road in poor condition, with no current City subsurface infrastructure. Installation of a sanitary sewer, trunk watermain and associated transportation improvements are included in both the Infrastructure Implementation Plan and the MOU with developers in Phase 1 of the secondary plan area. The Wastewater Collection Master Plan recommended drainage of the Salem Secondary Plan sewershed to Lover's Trunk Sewer as it has significant available spare capacity, while the Water Distribution Master Plan identified a need for a trunk watermain to provide potable water and fire protection in Phase 1 development. The Transportation Master Plan noted increases in traffic volume, and with construction of the proposed McKay Interchange necessitates an expansion from two lanes to three (west of Reid) and five (Reid to Highway 400) lanes. Funding for this project is partially front-ended by Developers to provide servicing required for Phase 1 of growth-related development in the secondary plan area.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Design - Request $3,966,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $3,966,000

Property - Request $3,000,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $3,000,000

Design - Forecast $0 $0 $0 $0 $0 $0 $290,600 $0 $0 $0 $290,600

Property - Forecast $0 $0 $0 $0 $0 $0 $0 $542,400 $0 $0 $542,400

Utilities - Forecast $0 $631,800 $0 $0 $0 $0 $0 $0 $89,800 $0 $721,600

Construction - Forecast

$0 $0 $18,867,900 $5,961,900 $1,431,100 $0 $0 $0 $0 $1,855,400 $28,116,300

Total $6,966,000 $631,800 $18,867,900 $5,961,900 $1,431,100 $0 $290,600 $542,400 $89,800 $1,855,400 $36,636,900

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Developer Front Ending (Annex) - Developer Build

$5,921,100 $537,030 $17,093,835 $5,961,900 $1,216,435 $0 $247,010 $461,040 $76,330 $1,577,090 $33,091,770

Debenture Proceeds - Tax

$1,044,900 $94,770 $0 $0 $0 $0 $0 $0 $0 $0 $1,139,670

Contribution from Tax Capital Reserve

$0 $0 $1,774,065 $0 $214,665 $0 $43,590 $81,360 $13,470 $278,310 $2,405,460

Total $6,966,000 $631,800 $18,867,900 $5,961,900 $1,431,100 $0 $290,600 $542,400 $89,800 $1,855,400 $36,636,900

87

Page 93: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

Salem Road New Transmission Watermain and Road Expansion - County Road 27 to Veterans (Developer)

Department:

Engineering Department

Project Number:

Z484

Summary:

Construction of a trunk watermain from County Road 27 to Veterans Drive. Expansion of the Salem Road right of way including widening of the road from two to three lanes from Country Road 27 to Veterans; urbanization of the south half of the road from Essa to Veterans.

Rationale:

The City of Barrie Growth Studies Multi-Modal Active Transportation Master Plan identified Salem Road as a rural road in poor condition, with no current City subsurface infrastructure. The Water Distribution Master plan recommends the installation of a trunk watermain along with the associated local wastewater collection and transportation improvements be implemented. Salem Road is a rural road in poor condition, and anticipated traffic volume increases associated with Phase 1 development in the secondary plan area have resulted in a need to proactively address capacity issues. Transportation improvements are included in both the Infrastructure Implementation Plan and the MOU with developers in the secondary plan area, as well as the Transportation Master Plan. Road widening will increase traffic capacity, and construction of the sidewalks adjacent to developing areas will allow for safer and accessible movement of pedestrians. The Water Distribution Master Plan calls for additional potable water and fire protection to service growth related to Phase 1 of the Salem Secondary Plan. Funding for this project is partially front-ended by Developers to provide servicing required for Phase 1 of growth-related development in the secondary plan area.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Design - Request $2,688,900 $0 $0 $0 $0 $0 $0 $0 $0 $0 $2,688,900

Property - Request $3,430,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $3,430,000

Property - Forecast $0 $0 $0 $0 $1,647,600 $0 $0 $0 $0 $0 $1,647,600

Utilities - Forecast $0 $517,200 $0 $0 $0 $301,000 $0 $0 $0 $0 $818,200

Construction - Forecast $0 $0 $9,378,000 $0 $2,624,300 $0 $6,117,800 $0 $0 $0 $18,120,100

Total $6,118,900 $517,200 $9,378,000 $0 $4,271,900 $301,000 $6,117,800 $0 $0 $0 $26,704,800

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Developer Front Ending (Annex) - Developer Build

$5,201,065 $439,620 $8,197,080 $0 $3,631,115 $255,850 $5,200,130 $0 $0 $0 $22,924,860

Debenture Proceeds - Tax

$917,835 $77,580 $0 $0 $0 $0 $0 $0 $0 $0 $995,415

Contribution from Tax Capital Reserve

$0 $0 $1,180,920 $0 $640,785 $45,150 $917,670 $0 $0 $0 $2,784,525

Total $6,118,900 $517,200 $9,378,000 $0 $4,271,900 $301,000 $6,117,800 $0 $0 $0 $26,704,800

88

Page 94: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

Veterans Drive New Trunk Watermain and Road Expansion - Salem to City Limits (Developer)

Department:

Engineering Department

Project Number:

Z230

Summary:

Construction of a trunk watermain from Salem Road southerly to the City limits, Expansion of Veterans Drive right of way, urbanization and widening of the road from two to five lanes, with buffered bike lanes (Salem to McKay) and from two to three lanes, with buffered bike lanes (McKay to City Limits).

Rationale:

The City of Barrie Growth Studies and Multi-Modal Active Transportation Master Plan identified Veterans Drive as a rural road in poor condition, with no current City subsurface infrastructure. The Water Distribution Master plan recommends the Installation of a trunk watermain along with the associated local wastewater collection and transportation improvements recommended. These infrastructure elements are included in the Infrastructure Implementation Plan and the MOU with developers in the secondary plan area. The watermain is required to provide potable water and fire flow in Phase 1 of the Salem Secondary Plan area. Road reconstruction will improve safety and drivability, with increases in traffic volume necessitating an expansion from two lanes. Funding for this project is partially front-ended by Developers to provide servicing required for Phase 1 of growth-related development in the secondary plan area.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Property - Request $2,600,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $2,600,000

Utilities - Forecast $0 $556,600 $0 $0 $0 $0 $0 $0 $0 $0 $556,600

Construction - Forecast $0 $0 $6,710,700 $6,710,700 $0 $0 $0 $0 $0 $0 $13,421,400

Total $2,600,000 $556,600 $6,710,700 $6,710,700 $0 $0 $0 $0 $0 $0 $16,578,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Developer Front Ending (Annex) - Developer Build

$2,210,000 $473,110 $5,704,095 $5,704,095 $0 $0 $0 $0 $0 $0 $14,091,300

Debenture Proceeds - Tax

$390,000 $83,490 $0 $0 $0 $0 $0 $0 $0 $0 $473,490

Contribution from Tax Capital Reserve

$0 $0 $1,006,605 $1,006,605 $0 $0 $0 $0 $0 $0 $2,013,210

Total $2,600,000 $556,600 $6,710,700 $6,710,700 $0 $0 $0 $0 $0 $0 $16,578,000

89

Page 95: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

Annual Parking Lot Improvement Program

Department:

Engineering Department

Project Number:

Z411

Summary:

Parkland and open space parking lot design and construction to modify, enlarge or reconstruct existing or new vehicle spaces to accommodate park and recreation programmed activities.

Rationale:

The work planned for 2018 will include design of the renewal and/or upgrades to the existing Tyndale Park, Riverwood Park and Harvie Park parking lots with either granular or asphalt surfacing. Tyndale and Riverwood parking lots require a design to increase capacity to service the needs of public users. Construction funding will apply to the Riverwood Park new granular construction parking lot and granular parking lot expansion at Tyndale Park. Future 2019 construction will be for the asphalt surfacing for Harvie Park parking lot only with minor adjacent grading within park.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Design - Request $50,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $50,000

Construction - Request $100,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $100,000

Design - Forecast $0 $0 $17,500 $60,000 $0 $10,000 $110,000 $85,000 $175,000 $0 $457,500

Construction - Forecast $0 $85,000 $157,500 $50,000 $495,000 $0 $0 $0 $0 $0 $787,500

Total $150,000 $85,000 $175,000 $110,000 $495,000 $10,000 $110,000 $85,000 $175,000 $0 $1,395,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from Tax Capital Reserve

$150,000 $85,000 $175,000 $110,000 $495,000 $10,000 $110,000 $85,000 $175,000 $0 $1,395,000

Total $150,000 $85,000 $175,000 $110,000 $495,000 $10,000 $110,000 $85,000 $175,000 $0 $1,395,000

90

Page 96: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

Bell Farm Road ROW Expansion - St. Vincent to Duckworth

Department:

Engineering Department

Project Number:

EN1164

Summary:

Reconstruction and widening of Bell Farm Road to 3-lanes, bike lanes and sidewalks between St. Vincent Street to Duckworth Street.

Rationale:

The existing 2-lane rural cross-section requires reconstruction to address renewal needs. This corridor has been identified for implementation of sidewalks to enhance pedestrian safety as well as stormwater management to improve drainage and mitigate environmental impacts. The existing watermain is approaching the end of its forecasted service life and is identified for replacement. This corridor is a primary route for both Barrie Fire and Emergency Services and Barrie Police Services. Implementation of cycling lanes and pedestrian facilities will promote the use of Active Transportation by Georgian College students to access student residences and St. Vincent Street. In 2016/17, the City undertook a Schedule 'C' Class EA. The study recommends construction of two vehicular lanes with a two-way left turn lane, sidewalks and bicycle lanes. In June 2017, Council approved recommendations identified in the Class EA study.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Design - Request $617,600 $0 $0 $0 $0 $0 $0 $0 $0 $0 $617,600

Property - Request $108,600 $0 $0 $0 $0 $0 $0 $0 $0 $0 $108,600

Utilities - Forecast $0 $925,400 $0 $0 $0 $0 $0 $0 $0 $0 $925,400

Construction - Forecast $0 $0 $3,573,300 $3,693,700 $0 $0 $0 $0 $0 $0 $7,267,000

Total $726,200 $925,400 $3,573,300 $3,693,700 $0 $0 $0 $0 $0 $0 $8,918,600

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from DC Reserves Tax

$351,780 $601,510 $1,136,655 $1,214,915 $0 $0 $0 $0 $0 $0 $3,304,860

Contribution from Tax Capital Reserve

$189,420 $323,890 $1,591,445 $1,633,585 $0 $0 $0 $0 $0 $0 $3,738,340

Contribution from WW Capital Reserve

$78,600 $0 $506,500 $506,500 $0 $0 $0 $0 $0 $0 $1,091,600

Contribution from Water Capital Reserve

$106,400 $0 $338,700 $338,700 $0 $0 $0 $0 $0 $0 $783,800

Total $726,200 $925,400 $3,573,300 $3,693,700 $0 $0 $0 $0 $0 $0 $8,918,600

91

Page 97: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

City Wide Cycling Network Program

Department:

Engineering Department

Project Number:

Z382

Summary:

Construction of cycling infrastructure, including on-street and buffered bike lanes, or multi-purpose trails in locations identified in the 2013 Multi-Modal Active Transportation Master Plan (MMATMP).

Rationale:

The MMATMP identified proposed locations to advance the cycling network in Barrie. High priority locations have been proposed for the initial implementation. A grant application has been made through the Municipal Commuter Cycling Program.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Capital Purchase - Request

$40,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $40,000

Design - Forecast $0 $110,000 $0 $0 $0 $0 $0 $0 $0 $0 $110,000

Construction - Forecast

$0 $0 $1,200,000 $400,000 $400,000 $400,000 $400,000 $400,000 $400,000 $400,000 $4,000,000

Total $40,000 $110,000 $1,200,000 $400,000 $400,000 $400,000 $400,000 $400,000 $400,000 $400,000 $4,150,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Province of Ontario Grant Revenue

$32,000 $88,000 $960,000 $0 $0 $0 $0 $0 $0 $0 $1,080,000

Contribution from Tax Capital Reserve

$8,000 $22,000 $240,000 $400,000 $400,000 $400,000 $400,000 $400,000 $400,000 $400,000 $3,070,000

Total $40,000 $110,000 $1,200,000 $400,000 $400,000 $400,000 $400,000 $400,000 $400,000 $400,000 $4,150,000

92

Page 98: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

Dunlop Interchange (Barrie)

Department:

Engineering Department

Project Number:

000657

Summary:

This represents the estimated cost of Barrie's contribution toward MTO improvements of the Dunlop Interchange (within Cedar Pointe Drive to Hart Drive limits) including the additional lanes identified, conveyance upgrades and replacement of a sanitary trunk sewer. These costs will be further refined through ongoing discussions and collaboration with MTO on all highway projects.

Rationale:

MTO has identified replacement of the Dunlop Street Interchange as part of the Southern Highways Program 2017-2021. MTO plans to replace the existing 2-lane crossing/interchange with a 4 lane structure. The City's Multi-Modal Active Transportation Master Plan identified the need for a 6 lane crossing with buffered bicycle lanes. This project represents an estimate of the City's contribution to fund additional improvements beyond the 4 lane structure. Associated infrastructure included with this project is the Bunkers and Dyments Creek conveyance upgrades and replacement of the sanitary trunk sewer crossing the highway. It is assumed that the associated infrastructure costs would be cost shared with MTO.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Environmental Assessment - Request

$373,500 $0 $0 $0 $0 $0 $0 $0 $0 $0 $373,500

Construction - Forecast $0 $0 $2,212,700 $11,525,400 $4,425,400 $0 $0 $0 $0 $0 $18,163,500

Total $373,500 $0 $2,212,700 $11,525,400 $4,425,400 $0 $0 $0 $0 $0 $18,537,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from DC Reserves Tax

$242,775 $0 $1,441,505 $7,491,510 $2,876,510 $0 $0 $0 $0 $0 $12,052,300

Contribution from Tax Capital Reserve

$130,725 $0 $771,195 $4,033,890 $1,548,890 $0 $0 $0 $0 $0 $6,484,700

Total $373,500 $0 $2,212,700 $11,525,400 $4,425,400 $0 $0 $0 $0 $0 $18,537,000

93

Page 99: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

Dunlop Street Right of Way Expansion - Cedar Pointe to Anne (outside of CAH limits)

Department:

Engineering Department

Project Number:

Z372

Summary:

Reconstruction and widening of Dunlop Street between Cedar Pointe Drive and Anne Street (excluding Cedar Pointe to Hart Drive limits); this project is required in conjunction with the Dunlop Interchange.

Rationale:

In conjunction with the noted Dunlop crossing/interchange improvements; Dunlop Street must be widened to six lanes to ensure proper function of the interchange. The scope of work includes road reconstruction/widening, storm sewer installation, drainage improvements, sidewalk installation, intersection traffic signal replacements and street lighting replacement

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Environmental Assessment - Request

$266,800 $0 $0 $0 $0 $0 $0 $0 $0 $0 $266,800

Construction - Forecast $0 $1,379,600 $2,759,200 $2,759,200 $0 $0 $0 $0 $0 $0 $6,898,000

Total $266,800 $1,379,600 $2,759,200 $2,759,200 $0 $0 $0 $0 $0 $0 $7,164,800

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from DC Reserves Tax

$173,420 $896,740 $1,793,480 $1,793,480 $0 $0 $0 $0 $0 $0 $4,657,120

Contribution from Tax Capital Reserve

$93,380 $482,860 $965,720 $965,720 $0 $0 $0 $0 $0 $0 $2,507,680

Total $266,800 $1,379,600 $2,759,200 $2,759,200 $0 $0 $0 $0 $0 $0 $7,164,800

94

Page 100: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

Infrastructure Master Plans / DC Technical Studies Update

Department:

Engineering Department

Project Number:

EN1177

Summary:

Completion of the following Infrastructure Planning Studies and Master Plan Updates: 1) Stormwater; 2) Transportation; 3) Wastewater Collection; 4) Wastewater Treatment; 5) Water Storage and Distribution; and 6) Water Supply.

Rationale:

The City's Infrastructure Master Plans require updating approximately every 5 years in order to conform with updates to the Official Plan, provide input to Development Charges updates and confirm that the existing work plans are current and valid. Stormwater will be a priority to address issues identified in the City-wide stormwater model. Transportation will be considered under an affordable and practical lens, looking at transportation as a whole including the cycling network, trails, and multi-use paths as well as road networks. Wastewater Collection modelling will be updated to confirm model status, functionality and accuracy. Wastewater Treatment will be reviewed to consider the timing for the next expansion of the plant and review any possible efficiencies to confirm timing of required upgrades. Water Storage and Distribution will be updated from the previous Master Plan including new provincial growth projections through model development, field program and calibration. Water Supply will be updated from the previous Master Plan to confirm the timing for the expansion of the existing supply from the groundwater wells and surface water treatment plant.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Environmental Assessment - Request

$500,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $500,000

Total $500,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $500,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Province of Ontario Grant Revenue

$79,411 $0 $0 $0 $0 $0 $0 $0 $0 $0 $79,411

Government of Canada Grant Revenue

$158,822 $0 $0 $0 $0 $0 $0 $0 $0 $0 $158,822

Contribution from DC Reserves Tax

$190,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $190,000

Contribution from Tax Rate Stabilization Reserve

$71,767 $0 $0 $0 $0 $0 $0 $0 $0 $0 $71,767

Total $500,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $500,000

95

Page 101: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

Painswick Park Rehabilitation

Department:

Engineering Department

Project Number:

EN1182

Summary:

Rehabilitation and expansion of Painswick Park to become a larger multi-use destination park for inner-city baseball league games and various public and charity tournaments while providing community park programs and activities for existing and future residents.

Rationale:

The City is deficient in baseball facilities and requires additional senior adult slow pitch baseball to meet the current need. The project includes the design and reconstruction of the park including the provision of deficient utility infrastructure such as hydro, water and sanitary connections. The project scope will also include the reconstruction of the existing baseball diamond, construction of a 2nd baseball diamond, rehabilitation of the tennis court facility, parking lot and potential for additional amenities.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Construction - Request $1,935,300 $1,381,500 $0 $0 $0 $0 $0 $0 $0 $0 $3,316,800

Total $1,935,300 $1,381,500 $0 $0 $0 $0 $0 $0 $0 $0 $3,316,800

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from DC Reserves Tax

$1,603,620 $1,381,500 $0 $0 $0 $0 $0 $0 $0 $0 $2,985,120

Contribution from Cash-In-Lieu Parkland Reserve

$331,680 $0 $0 $0 $0 $0 $0 $0 $0 $0 $331,680

Total $1,935,300 $1,381,500 $0 $0 $0 $0 $0 $0 $0 $0 $3,316,800

96

Page 102: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

Park Condition Assessment Study

Department:

Engineering Department

Project Number:

000601

Summary:

A study to create a City wide baseline data and benchmark from which City staff can make effective and efficient decisions on the replacement or rehabilitation of all parkland assets for Capital and Operating Business Plans. The review will be based on a consistent, systematic and evidence-based review and will include asphalt walkways, shade structures, parking lots and various play courts.

Rationale:

Implementation of the assessment study recommendations will form the basis of priority for the various parkland programs being recommended through the capital planning process.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Study - Request $125,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $125,000

Total $125,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $125,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from Cash-In-Lieu Parkland Reserve

$125,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $125,000

Total $125,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $125,000

97

Page 103: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

Playground Replacement Program

Department:

Engineering Department

Project Number:

EN1117

Summary:

Replacement of playground equipment around the City.

Rationale:

Playground equipment has an estimated useful life of 20-25 years, depending on use, condition, location and annual compliance audits conducted by staff under the CAN/CSA Z614-07 Children's Playground Equipment Standard. This is to ensure that all components of a play structure are safe and in good repair and is a proactive approach to playground replacement to help reduce maintenance costs of deteriorated equipment, minimize downtime and emergency repair costs for broken equipment, will mitigate the risk of injury and will help maintain high levels of service for recreation and play within parks. The 2018 playground replacement work will include the installation of a new playground for Sam Cancilla Park (subject to design completion in early 2018), the replacement of a neighbourhood park such as Chalmers Park and the installation of free standing components in other parks within the City.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Construction - Request $270,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $270,000

Construction - Forecast $0 $270,000 $270,000 $270,000 $270,000 $270,000 $270,000 $270,000 $270,000 $0 $2,160,000

Total $270,000 $270,000 $270,000 $270,000 $270,000 $270,000 $270,000 $270,000 $270,000 $0 $2,430,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from Cash-In-Lieu Parkland Reserve

$270,000 $270,000 $270,000 $270,000 $270,000 $270,000 $270,000 $270,000 $270,000 $0 $2,430,000

Total $270,000 $270,000 $270,000 $270,000 $270,000 $270,000 $270,000 $270,000 $270,000 $0 $2,430,000

98

Page 104: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

Ross, Collier, Bayfield Intersection Realignment

Department:

Engineering Department

Project Number:

EN1183

Summary:

Implementation of a roundabout at the intersection of Ross-Collier-Bayfield to improve traffic operations and enhance pedestrian safety. This project includes ancillary improvements for the roundabout approaches (Ross Street - Maple Street to Bayfield Street, Bayfield Street - Worsley Street to Collier Street, Collier Street - Clapperton Street to Bayfield Street).

Rationale:

The existing offset intersection of Ross, Collier and Bayfield Streets operates inefficiently and lacks pedestrian crossing infrastructure. To improve east-west traffic operations and improve pedestrian safety, a roundabout is proposed at the intersection of Ross Street and Bayfield Street. The roundabout will include dedicated pedestrian crossing facilities on all legs and serve as both a gateway and traffic calming feature for motorists entering the downtown. The detailed design is proposed for 2018 to determine the exact property impacts for any potential development applications. Construction is currently planned for the latter part of the 10 year plan.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Design - Request $189,889 $0 $0 $0 $0 $0 $0 $0 $0 $0 $189,889

Property - Forecast $0 $0 $0 $0 $0 $53,424 $0 $0 $0 $0 $53,424

Utilities - Forecast $0 $0 $0 $0 $0 $0 $87,416 $87,416 $0 $0 $174,833

Construction - Forecast $0 $0 $0 $0 $0 $0 $0 $0 $2,615,032 $0 $2,615,032

Total $189,889 $0 $0 $0 $0 $53,424 $87,416 $87,416 $2,615,032 $0 $3,033,178

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from DC Reserves Tax

$109,300 $0 $0 $0 $0 $34,726 $56,821 $56,821 $1,505,449 $0 $1,763,117

Contribution from Tax Capital Reserve

$66,732 $0 $0 $0 $0 $18,698 $30,596 $30,596 $918,992 $0 $1,065,613

Contribution from WW Capital Reserve

$8,888 $0 $0 $0 $0 $0 $0 $0 $122,251 $0 $131,139

Contribution from Water Capital Reserve

$4,968 $0 $0 $0 $0 $0 $0 $0 $68,340 $0 $73,309

Total $189,889 $0 $0 $0 $0 $53,424 $87,416 $87,416 $2,615,032 $0 $3,033,178

99

Page 105: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

Stormwater Utility Finance Study

Department:

Engineering Department

Project Number:

000567

Summary:

Stormwater Utility Finance Rate Study to assess alternative options to fund the operation, maintenance and improvements for the City's stormwater management assets.

Rationale:

In an effort to increase the City's stormwater management infrastructure resiliency to climate change and implement identified capital improvements to protect public safety, private property and improve water quality; a dedicated revenue source would facilitate long term implementation of stormwater infrastructure improvements that have been identified in Drainage Master Plans. The Stormwater Utility Finance Study will assess funding needs and alternative options to fund all aspects of the City's stormwater management infrastructure. This project will be coordinated with the Stormwater Asset Management Plan update.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Study - Request $75,000 $225,000 $0 $0 $0 $0 $0 $0 $0 $0 $300,000

Total $75,000 $225,000 $0 $0 $0 $0 $0 $0 $0 $0 $300,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from Tax Rate Stabilization Reserve

$75,000 $225,000 $0 $0 $0 $0 $0 $0 $0 $0 $300,000

Total $75,000 $225,000 $0 $0 $0 $0 $0 $0 $0 $0 $300,000

100

Page 106: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

Tennis Court Rehabilitation Program

Department:

Engineering Department

Project Number:

EN1140

Summary:

Rehabilitation of tennis court facilities, with a primary focus on full surface asphalt replacement; where necessary, rehabilitation will also include colour coat resurfacing, perimeter fencing repair or replacement, and lighting upgrades or replacement. The work planned for 2018 will include reconstruction of the two tennis courts at both Greenfield and Redpath Parks including new asphalt surface, fencing (where required) and lighting.

Rationale:

The repair or replacement of tennis court facilities is required where the physical deterioration results in a much lower service level or the condition renders the court unusable. This deterioration is based on a surface assessment (uneven, cracked or broken asphalt) or where there is an increased the risk of personal injury. Recreation Services loses approximately $1,000 per court per season from lost bookings revenue when this occurs yet the courts also serve a local recreational need for other activities such as pickleball and winter ice rinks. With an average lifecycle of approximately thirty-five years, if a court has a colour coat surface, this requires resurfacing maintenance every ten years to rehabilitate the surface condition and continue to provide the expected level of service to residents. Work in 2018 will address deficiencies at Ferndale and Greenfield Parks; future work will be determined in upcoming capital planning exercises.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Construction - Request $340,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $340,000

Construction - Forecast

$0 $162,000 $324,000 $400,000 $206,000 $340,000 $162,000 $75,000 $162,000 $60,000 $1,891,000

Total $340,000 $162,000 $324,000 $400,000 $206,000 $340,000 $162,000 $75,000 $162,000 $60,000 $2,231,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from Federal Gas Tax Reserve

$340,000 $162,000 $324,000 $400,000 $206,000 $340,000 $162,000 $75,000 $162,000 $60,000 $2,231,000

Total $340,000 $162,000 $324,000 $400,000 $206,000 $340,000 $162,000 $75,000 $162,000 $60,000 $2,231,000

101

Page 107: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

Barrie Environmental Centre Recycling Depot Expansion and additional 40 Yard Bins

Department:

Environmental Services

Project Number:

000691

Summary:

This request is for the purchase of 20 - 40 yard bins for the collection and disposal of residentially deposited waste and recyclables at the City of Barrie Landfill Site.

Rationale:

Forty yard bins are the method with which waste that is dropped off at the landfill site is collected and transported for disposal. A number of the current bins being used at the Waste and Recycling Depot are past their lifecycle and need replacing. in 2017, a additional Recycling Depot is being constructed to assist with the further collection of recyclables and hazardous waste and will require 40 yard bins. Without the additional 40 yard bins being requested, the new depot cannot be operational and disposal of the waste from the existing depot will be delayed. The result will be increasing line-ups at the landfill site as residents wait for bins to be freed up for more disposal.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Capital Purchase - Request

$100,000 $100,000 $0 $0 $0 $0 $0 $0 $0 $0 $200,000

Total $100,000 $100,000 $0 $0 $0 $0 $0 $0 $0 $0 $200,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from Tax Capital Reserve

$100,000 $100,000 $0 $0 $0 $0 $0 $0 $0 $0 $200,000

Total $100,000 $100,000 $0 $0 $0 $0 $0 $0 $0 $0 $200,000

102

Page 108: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

Barrie Environmental Centre Waste and Recycling Depot Repair

Department:

Environmental Services

Project Number:

000544

Summary:

Reconstruction of the currently deteriorated paved area behind the Waste and Recycling Depot saw tooth wall including surface reinstatement.

Rationale:

Reconstruction of the currently deteriorated paved area behind the Waste and Recycling Depot saw tooth wall. This project would include surface reinstatement to prevent deterioration/undermining of the cement saw tooth wall at the Waste and Recycling Depot.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Construction - Request $100,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $100,000

Total $100,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $100,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from Tax Capital Reserve

$100,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $100,000

Total $100,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $100,000

103

Page 109: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

Barrie Landfill Household Hazardous Waste Depot Upgrades

Department:

Environmental Services

Project Number:

000578

Summary:

The need to review the Hazardous Waste Depot and Program was identified when the Fire Plan for the Environmental Centre was submitted to the Fire Department for approval. In addition, Extended Producer Responsibility legislation will impact the current Hazardous Waste Collection processes. Consultant work completed in 2017 will provide recommendations for improvement to both that will ensure compliance within the framework of the changing legislation.

Rationale:

The need to review the Hazardous Waste Depot and Program was identified when the Fire Plan for the Environmental Centre was submitted to the Fire Department for approval and non-compliances were identified. The non-compliances are in relation to the ability to safely store chemical quantities. In addition, environmental legislation regarding diversion of hazardous waste is changing. In 2017, a consultant will be reviewing the Hazardous Waste Collection Program and Depot and will provide recommendations regarding potential future storage capacity needs of the facility as well as the needs resulting from waste diversion legislation impacts. Once compliance is achieved, a Fire Plan will be submitted for approval.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Execute - Request $100,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $100,000

Total $100,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $100,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from Tax Capital Reserve

$100,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $100,000

Total $100,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $100,000

104

Page 110: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

Historic Waste Site Landfill Gas New Preventative/Remedial Action

Department:

Environmental Services

Project Number:

000519

Summary:

The remediation of landfill gas (LFG) migration from City-owned lands within Historic Waste Site 6 (Frederick St area).

Rationale:

Monitoring of Landfill gas (LFG) within publicly owned lands on Historic Waste Site 6 indicates that elevated (above 5%) methane is present around the Frederick Street Area. A LFG Impact and Action Plan study completed by Golder and Associates has recommended that remediation of LFG migration from City-owned lands within Site 6 be undertaken. This will include the procurement of a consultant for the design and installation of a LFG barrier and venting system. The installation of this system will be limited to public lands around the area of concern and is estimated that a maximum length of 300 meters is necessary. This project is a Corporate Need from a liability aspect.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Capital Purchase - Request

$500,000 $500,000 $0 $0 $0 $0 $0 $0 $0 $0 $1,000,000

Total $500,000 $500,000 $0 $0 $0 $0 $0 $0 $0 $0 $1,000,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from Reserves

$500,000 $500,000 $0 $0 $0 $0 $0 $0 $0 $0 $1,000,000

Total $500,000 $500,000 $0 $0 $0 $0 $0 $0 $0 $0 $1,000,000

105

Page 111: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

Public Space Bin Upgrade Program

Department:

Environmental Services

Project Number:

000598

Summary:

In 2017 a Public Space Bin Rationalization Study was initiated and driven by the need to find efficiencies, develop standardization and respond to impacts changing legislation. Of certainty is the fact that the legislation promotes the expansion of diversion programs which will definitely impact this 'Program'. The study identified changes to the program that will require funding for, at a minimum, a 2 year implementation period.

Rationale:

A comprehensive Public Space Bin Rationalization Study was conducted in response to the need to update the Public Space Bin Program. This update was driven by the need to reduce contamination rates, increase diversion, to find efficiencies and standardization (given that processes are shared between 2 departments), to address changing legislation and its potential impacts as well as to implement a second priority initiative within the Sustainable Waste Management Strategy. Of certainty is the fact that the legislation promotes the expansion of diversion programs which will definitely impact this 'Program'. The study identified changes to the program that will require a 2 year implementation.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Execute - Request $237,500 $237,500 $237,500 $237,500 $0 $0 $0 $0 $0 $0 $950,000

Total $237,500 $237,500 $237,500 $237,500 $0 $0 $0 $0 $0 $0 $950,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from Tax Capital Reserve

$237,500 $237,500 $237,500 $237,500 $0 $0 $0 $0 $0 $0 $950,000

Total $237,500 $237,500 $237,500 $237,500 $0 $0 $0 $0 $0 $0 $950,000

106

Page 112: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

WwTF Drum Replacement - Rotary Drum Thickeners

Department:

Environmental Services

Project Number:

000012

Summary:

Replacement of drum frames on Rotary Drum Thickeners (RDT) at the Wastewater Treatment Facility. Replacement of the drum frame on RDT #1 was approved in the 2017 Business Plan and is underway. This request is related to the replacement of the drum frame on RDT #2 in 2018.

Rationale:

Rotary drum thickeners are essential to pre-condition waste activated sludge for effective and efficient treatment. The structural integrity of the rotary drum frames is deteriorating to a point where spot repairs such as welding are not effective. The three (3) rotary drum thickeners were installed and commissioned in 1996 and some key structural components have reached end of life. The drum frame on RDT #3 was replaced in 2014 due to structural failure and the drum frame on RDT #1 was approved for replacement in 2017. The drum frame on RDT #2 has been identified for replacement in 2018. This equipment is identified in the plant ECA and the municipality has an obligation through the ECA to ensure the equipment is operational.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Capital Purchase - Request

$80,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $80,000

Total $80,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $80,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from WW Capital Reserve

$80,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $80,000

Total $80,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $80,000

107

Page 113: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

WwTF New PeCOD Unit for Determination of COD - Lab

Department:

Environmental Services

Project Number:

000584

Summary:

This project involves the acquisition and implementation of a benchtop unit that automatically determines COD with minor user input and uses safe reagents.

Rationale:

The Implementation of a novel photoelectrochemical method for determination of chemical oxygen demand (COD) at the City of Barrie Wastewater Treatment Facility Laboratory would provide increased operational control, enhance optimization initiatives, and aid in maintaining compliance. Alternative COD methodology requires complex methods, dangerous chemicals, and longer time to perform.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Capital Purchase - Request

$31,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $31,000

Total $31,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $31,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from WW Capital Reserve

$31,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $31,000

Total $31,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $31,000

108

Page 114: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

WwTF Sand Filter Controls & Instrumentation Replacement

Department:

Environmental Services

Project Number:

000583

Summary:

Replacement of control panels and Programmable Logic Controllers (PLC) on sand filters 1 through 4 inclusive, and installation of in-situ turbidity analyzers on all 6 sand filter effluents. All work is required for staff to be able to confirm proper operation of this critical treatment process to ensure regulatory compliance.

Rationale:

Proper operation of the sand filters is essential to ensure that the municipality can continuously meet or exceed provincial effluent quality criteria. Optimum performance of the filters cannot be achieved or confirmed without documented performance feedback from the filter control panels and turbidity analyzers. Without feedback and performance monitoring there exists no means to receive alarms due to equipment or process failure, resulting in non-compliance.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Initiate - Request $165,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $165,000

Total $165,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $165,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from WW Capital Reserve

$165,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $165,000

Total $165,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $165,000

109

Page 115: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

WwTF Unox Tank Isolation Gate Replacement

Department:

Environmental Services

Project Number:

000588

Summary:

Existing isolation gates on the UNOX tanks at the WwTF have reached end of life and the installation of new flow control gates in the Unox effluent channel and secondary clarifier influent channels are required prior to implementing the upcoming Membrane Bioreactor (MBR) project.

Rationale:

Installation of the MBRs is necessary to ensure the WwTF maintains compliance with stringent provincial approvals as wastewater flows and loadings increase due to growth. The MBR project cannot commence as planned until WWOB staff are able to isolate Unox tanks 1-3, and the corresponding secondary clarifiers, individually. Replacing the existing 9 UNOX isolation gates is estimated to cost $250K. Installing these new gates at strategic locations along the effluent channels will provide the required flow control and limit the amount of wastewater treatment capacity that is off line for MBR construction purposes.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Initiate - Request $100,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $100,000

Total $100,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $100,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from WW Capital Reserve

$100,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $100,000

Total $100,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $100,000

110

Page 116: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

Secondary Plan Area New Bulk Water Filling Station

Department:

Environmental Services

Project Number:

000125

Summary:

Bulk water required for the development and growth activities in the secondary plan area will currently require developers/contractors to drive to the north end of the City (Operations Centre location) to obtain water or use the hydrant metered gate valve option which is restricted to seasonal (summer) use and draws operational resources away from other Water Operations programs, including system flushing and water meter maintenance.

Rationale:

Installation of an additional Bulk Water Filling Station (BWFS) in the south end of the City will ensure that 24/7 access to bulk water is available near the area of development through a safe, reliable and efficient means. The addition of a BWFS in close proximity to the secondary plan area prior to significant development will be crucial in ensuring the continued safety and integrity of the drinking water system by aiding in the elimination of illegal operation and use of the distribution system (hydrants, water services, blow-offs) by contractors in need of access to a bulk water supply year round. Without a BWFS in close proximity to growth areas contractors will be forced to travel to the Operations Centre for year round bulk water access, with this situation lending its self to water theft and significant risk exposure to the drinking water distribution system and ultimately Barrie's residents. The location of the BWSF would be selected in coordination with the requisite Departments to ensure long term viability and continued access throughout (and beyond) the completion of secondary plan area build out. While this new station could be included within the plans for a south-end satellite operations yard, it is not recommended as the need for this service (bulk water provision) already exists and will only continue to increase with development anticipated in late 2017.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Capital Purchase - Request

$127,125 $0 $0 $0 $0 $0 $0 $0 $0 $0 $127,125

Total $127,125 $0 $0 $0 $0 $0 $0 $0 $0 $0 $127,125

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from Water Capital Reserve

$127,125 $0 $0 $0 $0 $0 $0 $0 $0 $0 $127,125

Total $127,125 $0 $0 $0 $0 $0 $0 $0 $0 $0 $127,125

111

Page 117: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

Allandale Recreation Centre Condenser Replacement - Blue Arena

Department:

Facilities Department

Project Number:

000212

Summary:

Replacement of the Condenser Unit at Allandale Recreation Centre Blue Arena.

Rationale:

The Condenser is showing signs of deterioration and has had several leaks repaired. The unit is original to the building, 32 years, and at the end of its useful life. The condenser is critical to the blue ice plant function, and would result in a major negative impact to programs and the facility should it cease to operate. The project would be completed during schedule maintenance closure of the facility, to limit disturbance to programs.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Construction - Request $90,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $90,000

Total $90,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $90,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from Tax Capital Reserve

$90,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $90,000

Total $90,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $90,000

112

Page 118: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

Allandale Recreation Centre Sprinkler Replacement - Blue Arena

Department:

Facilities Department

Project Number:

000215

Summary:

The Allandale Recreation Centre Blue Arena Sprinklers are at the end of their useful life. As per NFPA 25, all sprinkler heads over 25 years old shall be inspected and tested. The system will require a complete inspection, and if necessary replacement of all piping or deteriorated sections.

Rationale:

The fire sprinkler system is a major component of the life safety system in a building. It is imperative that these systems be maintained and inspection at proper intervals to ensure their function if necessary. The inspection and replacement of the sprinkler system would coincide with closure of the Blue Arena during summer months, and would not have an impact on the operation of the arena.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Construction - Request $90,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $90,000

Total $90,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $90,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from Tax Capital Reserve

$90,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $90,000

Total $90,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $90,000

113

Page 119: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

Barrie Molson Centre Elevator Replacement

Department:

Facilities Department

Project Number:

000501

Summary:

This project is to replace the passenger elevator at the Barrie Molson Centre, as recommended in a 2017 Facility Condition Assessment report. The elevator is nearing the end of its useful life and is in immediate need of significant capital upgrades to maintain its function and safety standards.

Rationale:

Significant immediate repairs are required to bring the unit up to date and to code. Originally installed in 1995, the elevator is 22 years old and obsolete compared to current standards, and replacement parts are becoming scarce. Due to its age, there is also a lack of knowledge and expertise among servicemen when repair is necessary on this elevator. There have been numerous instances of patrons being trapped in the elevator, and it is becoming an increasing health and safety liability. Additionally, without an elevator, the building would not meet AODA requirements. A similar project was completed at the Main Library at a cost of roughly 275K. This also included a separate line item for a one year service contract to insure that all component and operating issues have been worked through.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Construction - Request $300,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $300,000

Total $300,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $300,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from Tax Capital Reserve

$300,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $300,000

Total $300,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $300,000

114

Page 120: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

Barrie - Simcoe Emergency Services Campus - Phase 1

Department:

Facilities Department

Project Number:

FC1020

Summary:

The Barrie-Simcoe Emergency Services Campus Phase 1 has been approved by Council, as per Staff Report FCT006-17.

Rationale:

The Barrie-Simcoe Emergency Services Campus Phase 1 has been approved by Council, as per Staff Report FCT006-17.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Construction - Request $44,889,702 $43,110,583 $3,665,760 $0 $0 $0 $0 $0 $0 $0 $91,666,045

Total $44,889,702 $43,110,583 $3,665,760 $0 $0 $0 $0 $0 $0 $0 $91,666,045

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Debenture Proceeds - DCs

$6,908,197 $6,634,403 $564,134 $0 $0 $0 $0 $0 $0 $0 $14,106,734

Debenture Proceeds - Tax

$17,841,223 $17,134,119 $1,456,941 $0 $0 $0 $0 $0 $0 $0 $36,432,283

Contribution from DC Reserves Tax

$2,199,074 $2,111,917 $179,580 $0 $0 $0 $0 $0 $0 $0 $4,490,570

Contribution from Tax Capital Reserve

$7,487,013 $7,190,279 $611,401 $0 $0 $0 $0 $0 $0 $0 $15,288,693

Intercompany - General $10,454,196 $10,039,864 $853,705 $0 $0 $0 $0 $0 $0 $0 $21,347,765

Total $44,889,702 $43,110,583 $3,665,760 $0 $0 $0 $0 $0 $0 $0 $91,666,045

115

Page 121: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

BFES Station 3 Facility Rehabilitation

Department:

Facilities Department

Project Number:

000164

Summary:

In January of 2017, a Facility Condition Assessment (FCA) report was completed by CCI Group at Fire Station 3. The purpose of the report is to investigate building components and identify areas requiring remediation or replacement. Also included is the estimated lifecycle and replacement cost of each component. In order to maintain the facility in a state a good repair, the City must be diligent and complete the recommended repairs.

Rationale:

The recommended solution is to accept the findings in the FCA report and complete the repairs as identified. If the repairs are not completed as outlined in the FCA repair schedule, there is the potential for building component condition to worsen, causing further damage and costlier repairs. Deferring replacement and repairs are not recommended as this could also result in increased energy costs, maintenance costs, and usability resulting in an increase risk to occupants and users of the building.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Construction - Request $40,400 $158,000 $0 $0 $0 $0 $0 $0 $0 $0 $198,400

Construction - Forecast $0 $0 $0 $547,200 $58,400 $10,320 $195,000 $8,000 $0 $0 $818,920

Total $40,400 $158,000 $0 $547,200 $58,400 $10,320 $195,000 $8,000 $0 $0 $1,017,320

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from Tax Capital Reserve

$40,400 $158,000 $0 $547,200 $58,400 $10,320 $195,000 $8,000 $0 $0 $1,017,320

Total $40,400 $158,000 $0 $547,200 $58,400 $10,320 $195,000 $8,000 $0 $0 $1,017,320

116

Page 122: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

BFES Station 3 Interior Renovations

Department:

Facilities Department

Project Number:

FC1059

Summary:

The Fire Master Plan -Update 2014- 2023 was prepared in response to the ongoing review of the Plan and due to the 2010 Annexation of southerly lands. One of the Short Term Goals (1-3 Years) 2014-2016 identified is to undertake renovations at Fire Station 3 to increase the functionality and increase capacity for multiple crews. As identified in the Fire Master Plan - Update 2014-2023, the following renovations are required: - Increasing the kitchen and lounge area to accommodate 2 crews of up to 10 firefighters - Increasing the sleeping quarters and locker rooms / bunker gear / fitness to accommodate more than 2 crews - Renovating to improve / expand female quarters

Rationale:

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Design - Request $150,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $150,000

Construction - Request $750,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $750,000

Total $900,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $900,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Debenture Proceeds - Tax

$900,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $900,000

Total $900,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $900,000

117

Page 123: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

BFES Station 4 Renovation

Department:

Facilities Department

Project Number:

Z250

Summary:

Interior renovation of BFES Station 4.

Rationale:

Interior renovations at Station 4 are required to meet recommendations from the Fire Master Plan, and provide adequate female quarters space for BFES staff. Work will include reconfiguration of existing male quarters, locker area, and offices, to accommodate space needs and ensure accessibility and current code standards are implemented. This renovation also includes required renewal work that was identified in the Facility Condition Assessment studies completed in 2017, which will include replacement of HVAC units and electrical upgrades.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Construction - Request $1,000,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $1,000,000

Total $1,000,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $1,000,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Debenture Proceeds - Tax

$1,000,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $1,000,000

Total $1,000,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $1,000,000

118

Page 124: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

BFES Station 6 New Building Development

Department:

Facilities Department

Project Number:

FC1084

Summary:

The development of a new Barrie Fire & Emergency Service Station 6 to serve the Hewitt's Secondary Plan area. A staff report will be prepared that will identify further details including schedule, costs, and scope.

Rationale:

The City as per Council direction will strive to develop/provide essential services in advance of build-out of future development areas. Station 6 that is planned to be located in the Mapleview Rd. and Prince William Way area will service the Hewitt's Secondary Plan Area. The Barrie Fire and Emergency Service has to have its services in place prior to the start of building to be able to service the planned developments. The existing stations cannot meet the needs of the annexed land area. A staff report will be prepared that will identify further details including schedule, capital and operating costs, and scope. Capital costs include obtaining property, design, construction, utilities, and fit-out. The Fire Master Plan - Update 2014- 2023 was prepared in response to the ongoing review of the Plan and due to the 2010 Annexation of southerly lands. One of the Intermediate Term Goals (3-5 Years) 2016-2018 identified is to construct Station 6.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Construction - Request $300,000 $2,150,000 $0 $0 $0 $0 $0 $0 $0 $0 $2,450,000

Capital Purchase - Request

$900,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $900,000

Capital Purchase - Forecast

$0 $350,000 $500,000 $0 $0 $0 $0 $0 $0 $0 $850,000

Total $1,200,000 $2,500,000 $500,000 $0 $0 $0 $0 $0 $0 $0 $4,200,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from DC Reserves Tax (Annex)

$1,200,000 $2,500,000 $500,000 $0 $0 $0 $0 $0 $0 $0 $4,200,000

Total $1,200,000 $2,500,000 $500,000 $0 $0 $0 $0 $0 $0 $0 $4,200,000

119

Page 125: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

City Hall Customer Contact Centre Renovation

Department:

Facilities Department

Project Number:

000447

Summary:

Interior renovations to 1st Floor City Hall, in support of the implementation strategy for the Customer Contract Centre.

Rationale:

The phased implementation strategy already endorsed by Council, for the Customer Contact Centre, will support the service model through interior renovations to ensure space is available for dedicated staff that will be specifically trained and supported by technology and resources designed to provide a positive customer experience.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Construction - Request $100,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $100,000

Total $100,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $100,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from Tax Capital Reserve

$60,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $60,000

Contribution from WW Capital Reserve

$20,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $20,000

Contribution from Water Capital Reserve

$20,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $20,000

Total $100,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $100,000

120

Page 126: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

City Hall Expansion

Department:

Facilities Department

Project Number:

000635

Summary:

The existing city hall facility is at capacity and does not have space for future growth. A proactive approach will ensure that the corporation is not restricted to a minimum level of service to the residents of Barrie. A design/validation phase leading to a 2 year construction phase is required to accommodate future growth.

Rationale:

The existing city hall facility is at capacity and does not have space for future growth. A proactive approach will ensure that the corporation is able to optimize service delivery to the residents of Barrie by supporting functionality and growth accommodations for staff and the public.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Construction - Request $350,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $350,000

Design - Forecast $0 $0 $0 $1,200,000 $0 $0 $0 $0 $0 $0 $1,200,000

Construction - Forecast $0 $200,000 $200,000 $0 $22,500,000 $22,500,000 $0 $0 $0 $0 $45,400,000

Total $350,000 $200,000 $200,000 $1,200,000 $22,500,000 $22,500,000 $0 $0 $0 $0 $46,950,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from Tax Capital Reserve

$350,000 $200,000 $200,000 $1,200,000 $22,500,000 $22,500,000 $0 $0 $0 $0 $46,950,000

Total $350,000 $200,000 $200,000 $1,200,000 $22,500,000 $22,500,000 $0 $0 $0 $0 $46,950,000

121

Page 127: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

City Hall Parking Garage Rehabilitation

Department:

Facilities Department

Project Number:

FC1075

Summary:

Full rehabilitation of City Hall parking garage including the full removal and replacement of the podium deck and suspended parking slab waterproofing system, repairs of delaminated concrete surfaces and foundation wall cracks, the replacement of corroded drain pipes, collars, catch basins and covers, replacement of expansion joints, removal of existing heaters and replacement with heaters tied into existing hydronic loop, and replacement of existing ramp heating with hydronic heating cables.

Rationale:

The City Hall Underground Parking Lot was constructed in 1974 and is in need of renewal. The garage comprises two levels, P1 and P2. The parking lot extends from the east side of the tower; south side of the property (including paving stone area at Collier entrance); west side of the property (including vacant paving stone area); and the north side of the tower. The unistone paver areas over the parking garage are known as the Podium. It has a concrete slab to support the waterproofing membrane and paving stone components. The pavers are not conducive for this type of application as the salt that is used to melt the snow and ice migrates directly to the membrane. The parking structure is constructed of concrete containing reinforcing steel. During the winter, vehicles carry in road salt laden snow that melts onto the concrete surface. Moisture and salts then migrate through the concrete to the reinforcing steel. This results in steel corrosion, which expands creating fissures in the concrete allowing more moisture and salt to enter the voids. The deterioration then accelerates. To mitigate this, a waterproof membrane layer has been applied to the top of the concrete. It is a sacrificial layer as it is simpler to replace than concrete. The vehicle tires that turn on the membrane affect the integrity of the waterproof membrane. An investigation undertaken by a structural engineering firm in 2013 recommended that rehabilitation work proceed as quickly as possible, to address current damage and slow the rate of future deterioration. Failure to do so will result in accelerated structural deterioration, greater repair costs, and the risk of damage to vehicles or personal injury due to the garage’s poor condition. Though a specification will need to be developed by a consultant, it is anticipated that the newest type of rubberized surface with the best application and life expectancy will be installed.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Construction - Request $1,500,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $1,500,000

Total $1,500,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $1,500,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from Tax Capital Reserve

$1,500,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $1,500,000

Total $1,500,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $1,500,000

122

Page 128: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

Fisher Auditorium Redevelopment

Department:

Facilities Department

Project Number:

000633

Summary:

Feasibility of redeveloping the Fisher Auditorium at the former Barrie Central Collegiate Institute (BCCI) into a stand-alone city theatre asset

Rationale:

Feasibility study work currently underway as directed by council.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Construction - Request $250,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $250,000

Total $250,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $250,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from Tax Capital Reserve

$250,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $250,000

Total $250,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $250,000

123

Page 129: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

Holly Community Centre Pool Deck Rehabilitation

Department:

Facilities Department

Project Number:

000278

Summary:

Holly Community Centre pool deck rehabilitation project involves the removal and replacement of tile grout on the Pool Deck. Multiple complaints from patrons have been recorded as they have incurred injuries from exposed tiles edges. The grout is eroding leaving exposed edges that create an H&S hazard.

Rationale:

The pool tanks have been re-grouted using epoxy grout which is more durable and sanitary, less likely to come out causing cut exposure. The current grout is in poor shape and should be replaced as the loss of grout is exposing sharp edges of tile. There is 11,000 ft2 of pool deck at roughly $6.25 per ft2 to remove and replace the grout. There are many incidents of cut toes to patrons, one such incident required stitches. Local repairs have been completed but the complete deck should be done to avoid injury and potential water seepage.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Construction - Request $100,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $100,000

Total $100,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $100,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from Tax Capital Reserve

$100,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $100,000

Total $100,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $100,000

124

Page 130: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

Main Library HVAC Rehabilitation

Department:

Facilities Department

Project Number:

Z1115

Summary:

Rehabilitation of the Library's HVAC and Controls.

Rationale:

The Barrie Public Library Downtown Branch building is now 20 years old and many of the associated HVAC systems are either at or beyond their service life. There are a number of control/equipment related issues causing thermal discomfort to the occupants, and high energy use due to outdated technology and lack of control in the system. The scope includes replacing existing roof top units, VAV boxes, boilers, perimeter valves, and controls.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Construction - Request $500,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $500,000

Total $500,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $500,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from Tax Capital Reserve

$500,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $500,000

Total $500,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $500,000

125

Page 131: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

Marina Boat Launch Floating Finger Dock Replacement

Department:

Facilities Department

Project Number:

000602

Summary:

Installation of two floating finger docks to replace the docks presently at the Marina Boat Launch.

Rationale:

These docks are vital to marina operations and service delivery / revenue collection by patrons. The present docks are past life cycle and one of the floats has failed and has been temporarily repaired as an emergency fix.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Capital Purchase - Request

$150,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $150,000

Total $150,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $150,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from Marina Reserve

$150,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $150,000

Total $150,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $150,000

126

Page 132: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

Marina Dock Replacement - E, I and J

Department:

Facilities Department

Project Number:

Z823

Summary:

The docks should be replaced for health and safety of the clients, staff and public using the docks.

Rationale:

Replacement of the docks is required to ensure the safety / security of boaters requiring access to their vessels, and staff who operate the marina.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Capital Purchase - Request

$25,000 $350,000 $0 $0 $0 $0 $0 $0 $0 $0 $375,000

Total $25,000 $350,000 $0 $0 $0 $0 $0 $0 $0 $0 $375,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from Reserves

$25,000 $350,000 $0 $0 $0 $0 $0 $0 $0 $0 $375,000

Total $25,000 $350,000 $0 $0 $0 $0 $0 $0 $0 $0 $375,000

127

Page 133: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

Operations Centre Building Renovation

Department:

Facilities Department

Project Number:

000282

Summary:

Operations Centre renovations required to support growth and the new satellite yard operations.

Rationale:

The Operations Master Plan was endorsed by Council in June 2016. This renovation work at Ferndale Operations is the first step in executing the phased approach from the Master Plan, to decrease operational costs and create an efficient delivery model to serve the existing boundary of the City and future growth in the secondary plan area.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Design - Request $1,100,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $1,100,000

Construction - Forecast $0 $0 $8,500,000 $8,500,000 $0 $0 $0 $0 $0 $0 $17,000,000

Total $1,100,000 $0 $8,500,000 $8,500,000 $0 $0 $0 $0 $0 $0 $18,100,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Debenture Proceeds - Tax

$770,000 $0 $0 $4,398,251 $0 $0 $0 $0 $0 $0 $5,168,251

Contribution from DC Reserves Tax (Annex)

$330,000 $0 $2,550,000 $2,550,000 $0 $0 $0 $0 $0 $0 $5,430,000

Contribution from Tax Capital Reserve

$0 $0 $5,950,000 $1,551,749 $0 $0 $0 $0 $0 $0 $7,501,749

Total $1,100,000 $0 $8,500,000 $8,500,000 $0 $0 $0 $0 $0 $0 $18,100,000

128

Page 134: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

Painswick Library Flat Roof Repair

Department:

Facilities Department

Project Number:

000632

Summary:

Painswick library roof has repeatedly leaked and although the facility is relatively new is no longer under warranty. Repeated leaks have resulted in increased facility operational costs and affected library operations. Replacement of wet insulation only and entire roof membrane with new cold applied Built up Roof System. This repair option is recommended as it removes all wet components and will eliminate concerns with ongoing membrane failure. It also allows much of the roof system to remain in place and represents a cost avoidance opportunity.

Rationale:

Complete replacement of roof membrane and replacement of 15% of wet insulation as identified. The exiting roof in no longer under warranty and would be replaced with a cold applied built up roof system with a full system warranty that would cover all costs due to leaks for 20 years and an expected service life of 30 Years.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Construction - Request $150,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $150,000

Total $150,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $150,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from Tax Capital Reserve

$150,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $150,000

Total $150,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $150,000

129

Page 135: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

Secondary Plan Area Municipal Campus New Site Development

Department:

Facilities Department

Project Number:

000284

Summary:

Property purchase for a co-located site of various municipal facilities, to accommodate for growth and serve the secondary plan area.

Rationale:

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Property - Request $10,000,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $10,000,000

Total $10,000,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $10,000,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from DC Reserves Tax

$939,240 $0 $0 $0 $0 $0 $0 $0 $0 $0 $939,240

Contribution from DC Reserves Tax (Annex)

$5,060,760 $0 $0 $0 $0 $0 $0 $0 $0 $0 $5,060,760

Contribution from Cash-In-Lieu Parkland Reserve

$4,000,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $4,000,000

Total $10,000,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $10,000,000

130

Page 136: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

Tiffin Boat Launch Breakwall Repair

Department:

Facilities Department

Project Number:

Z209

Summary:

Repair of the existing breakwall at the Tiffin Boat Launch.

Rationale:

The bottom of the breakwall has begun to degrade, and investigation work needs to be undertaken to establish extent of repairs required to ensure integrity of wall is maintained.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Construction - Request $260,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $260,000

Total $260,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $260,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from Marina Reserve

$260,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $260,000

Total $260,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $260,000

131

Page 137: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

Year Round Downtown Market New Development

Department:

Facilities Department

Project Number:

000478

Summary:

Completion of a financial and technical study for the proposed Downtown Barrie Permanent Public Market Business Plan, including common programming factors, development components, and interrelated costs consistent with a Market Precinct Concept.

Rationale:

Council approved an amendment to the 2017 budget request for completion of a financial and technical study to validate the Downtown Barrie Permanent Public Market Business Plan. Details were presented to Council in Staff Report FCT001-17 on January 23, 2017. The Business Plan was developed by the Market Steering/Working Group, formed by Council direction in 2015 to consider site selection, construction, operation, and programming of a year-round downtown public market. Investigations included a customer survey to seek input, gauge interest levels, and solicit programming suggestions. The survey results positively identified that 77.5% of respondents were 'very likely' to shop downtown if a public market was located there. The Business Plan identified that the Transit Terminal building was the preferred of two locations. Of five potential options outlined in the Plan, a moderate renovation of the Transit Building site in conjunction with construction of a Farmers' Market structure (Option B) was selected as the move-forward option. Staff has recommended that a financial analysis, as well as a technical study including geotechnical investigations to confirm soil conditions and inform future planning and design, be completed to review the feasibility of Option B.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Design - Request $300,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $300,000

Construction - Request $2,600,000 $3,900,000 $0 $0 $0 $0 $0 $0 $0 $0 $6,500,000

Total $2,900,000 $3,900,000 $0 $0 $0 $0 $0 $0 $0 $0 $6,800,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from Tax Capital Reserve

$2,900,000 $3,900,000 $0 $0 $0 $0 $0 $0 $0 $0 $6,800,000

Total $2,900,000 $3,900,000 $0 $0 $0 $0 $0 $0 $0 $0 $6,800,000

132

Page 138: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

Energy Conservation Program

Department:

Facilities Department

Project Number:

000622

Summary:

Energy conservation projects over the previous three years have demonstrated significant cost avoidance and ROI ranging from 12 to over 20%. This program will fund initiatives identified by the Energy Management Branch that have a calculated ROI of 10% or more. The program will fund a variety of projects but will include; interior/exterior lighting conversions to LED, Variable frequency drives for motors and controls for energy using equipment.

Rationale:

Multiyear program to fund energy conservation capital projects with an ROI over 10% to reduce utility costs within city facilities

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Capital Purchase - Request

$300,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $300,000

Capital Purchase - Forecast

$0 $300,000 $300,000 $0 $0 $0 $0 $0 $0 $0 $600,000

Total $300,000 $300,000 $300,000 $0 $0 $0 $0 $0 $0 $0 $900,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from Federal Gas Tax Reserve

$300,000 $300,000 $300,000 $0 $0 $0 $0 $0 $0 $0 $900,000

Total $300,000 $300,000 $300,000 $0 $0 $0 $0 $0 $0 $0 $900,000

133

Page 139: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

Holly Community Centre Building Automation System Replacement

Department:

Facilities Department

Project Number:

000507

Summary:

Holly Building Automation System renewal is a project that was recommended by consultant MCW through a re-commissioning project at the Holly Community Centre. The BAS study was a stand-alone report which examined the cost benefits of replacement or renewal of the BAS system. The recommendation from the report is to replace the system.

Rationale:

Renewal of obsolete Building Automation System, which will result in energy use reductions and cost avoidance for utility operating costs and maintenance costs.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Capital Purchase - Request

$348,500 $0 $0 $0 $0 $0 $0 $0 $0 $0 $348,500

Total $348,500 $0 $0 $0 $0 $0 $0 $0 $0 $0 $348,500

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from Cash-In-Lieu Parkland Reserve

$348,500 $0 $0 $0 $0 $0 $0 $0 $0 $0 $348,500

Total $348,500 $0 $0 $0 $0 $0 $0 $0 $0 $0 $348,500

134

Page 140: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

2018-2019 DC Background Study Update

Department:

Finance Department

Project Number:

000612

Summary:

Update of City-wide and area specific Development Charge By-laws.

Rationale:

In order to continue to collect development charges, the City is required to complete a background study and pass an updated development charges by-law at least every 5 years. The current City-wide by-law 2014-108 expires in August 2019; therefore a new background study must be completed and a new by-law passed prior to that time. The background study takes several months to complete and will involve several meetings with stakeholders in most departments within the City. It is anticipated that the work will start mid-2018 and finish before August 2019.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Execute - Request $65,000 $65,000 $0 $0 $0 $0 $0 $0 $0 $0 $130,000

Total $65,000 $65,000 $0 $0 $0 $0 $0 $0 $0 $0 $130,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from DC Reserves Tax

$36,000 $36,000 $0 $0 $0 $0 $0 $0 $0 $0 $72,000

Contribution from DC Reserves Tax (Annex)

$22,500 $22,500 $0 $0 $0 $0 $0 $0 $0 $0 $45,000

Contribution from Tax Capital Reserve

$2,167 $2,167 $0 $0 $0 $0 $0 $0 $0 $0 $4,334

Contribution from WW Capital Reserve

$2,167 $2,167 $0 $0 $0 $0 $0 $0 $0 $0 $4,334

Contribution from Water Capital Reserve

$2,166 $2,166 $0 $0 $0 $0 $0 $0 $0 $0 $4,332

Total $65,000 $65,000 $0 $0 $0 $0 $0 $0 $0 $0 $130,000

135

Page 141: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

eTendering Platform New System

Department:

Finance Department

Project Number:

000016

Summary:

eTendering is a web-based tendering platform designed to benefit both buyers and suppliers. eTendering enables an organization-wide, strategic approach to procurement and ensures a compliant, transparent, and fair process.

Rationale:

eTendering drives savings of both time and money through optimizing supplier selection and driving efficient improvements to processes. Securely managed electronic tenders using standardized templates are error free, save drafting time and have a full audit trail. Early awareness of upcoming tenders will increase vender participation. By submitting electronic tenders, vendors benefit as well as they build a database of key information that can be used for additional similar bids. eTendering is a win-win for the City of Barrie and the vendor community.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Capital Purchase - Request

$75,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $75,000

Total $75,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $75,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from Tax Capital Reserve

$52,500 $0 $0 $0 $0 $0 $0 $0 $0 $0 $52,500

Contribution from WW Capital Reserve

$11,250 $0 $0 $0 $0 $0 $0 $0 $0 $0 $11,250

Contribution from Water Capital Reserve

$11,250 $0 $0 $0 $0 $0 $0 $0 $0 $0 $11,250

Total $75,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $75,000

136

Page 142: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

Server and Desktop Software Program

Department:

Information Technology

Project Number:

IT1024

Summary:

Corporate wide program for the annual licensing renewal of the City's server and desktop software. This program includes a range of Enterprise software applications that require yearly renewal.

Rationale:

Annual renewal of server and desktop software licences is required in part through an existing contractual obligation with various vendors including Microsoft which require payments in 2017, 20189 and 2019, based on a new 3 year agreement signed in 2017. These license bundles offer volume pricing discounts, timely upgrades, and access to support.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Capital Purchase - Request

$625,000 $650,000 $0 $0 $0 $0 $0 $0 $0 $0 $1,275,000

Capital Purchase - Forecast

$0 $0 $675,000 $700,000 $725,000 $0 $0 $0 $0 $0 $2,100,000

Total $625,000 $650,000 $675,000 $700,000 $725,000 $0 $0 $0 $0 $0 $3,375,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from Reserves

$3,387 $3,522 $3,658 $3,793 $0 $0 $0 $0 $0 $0 $14,359

Contribution from Tax Capital Reserve

$619,811 $644,603 $669,396 $694,188 $725,000 $0 $0 $0 $0 $0 $3,352,998

Contribution from WW Capital Reserve

$801 $833 $865 $897 $0 $0 $0 $0 $0 $0 $3,397

Contribution from Water Capital Reserve

$801 $833 $865 $897 $0 $0 $0 $0 $0 $0 $3,397

Contribution from Parking Capital Reserve

$200 $208 $216 $224 $0 $0 $0 $0 $0 $0 $849

Total $625,000 $650,000 $675,000 $700,000 $725,000 $0 $0 $0 $0 $0 $3,375,000

137

Page 143: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

Application Resiliency Program

Department:

Information Technology

Project Number:

IT1022

Summary:

This program builds on the data centre foundation that's been started with the opening of the SWTP Data Centre. It's an organized implementation of an Application Resiliency strategy. The program includes: - Operational resiliency; - Alternate site redundancy; - A strategy to ensure current application systems and technical architecture are in sync.

Rationale:

The Always Available Technology Program targets the City's Enterprise Applications to protect them in a way that ensures they're "Always Available" even when one of our data centres is no longer functioning. Ultimately this will ensure that key technologies are available for emergency operations, customer service and all City staff. Some key technologies include ERP, APLI (Land Development), email, CityWorks, the Barrie Website and the Internet.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Plan - Request $100,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $100,000

Plan - Forecast $0 $100,000 $100,000 $100,000 $100,000 $0 $0 $0 $0 $0 $400,000

Total $100,000 $100,000 $100,000 $100,000 $100,000 $0 $0 $0 $0 $0 $500,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from Tax Capital Reserve

$100,000 $100,000 $100,000 $100,000 $100,000 $0 $0 $0 $0 $0 $500,000

Total $100,000 $100,000 $100,000 $100,000 $100,000 $0 $0 $0 $0 $0 $500,000

138

Page 144: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

Barrie Fire and Emergency Services Technology Program

Department:

Information Technology

Project Number:

000105

Summary:

This IT program focuses on the BFES technology infrastructure needs including - Server and Storage upgrade; data management; Backup 9-1-1 dispatch centre at 60 Bell farm Rd. ; Next Generation 9-1-1; Computer Aided Dispatch (Symposium) software upgrade; Network Infrastructure improvements including redundant internet connectivity; and Radio software upgrade (server, PCs and console).

Rationale:

Ongoing requirements for sustaining the operation of our emergency services, including the 911 dispatch system, the City's EOC and all other Fire support technologies.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Plan - Request $100,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $100,000

Total $100,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $100,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from Tax Capital Reserve

$100,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $100,000

Total $100,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $100,000

139

Page 145: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

Corporate Communications Infrastructure Program

Department:

Information Technology

Project Number:

IT1013

Summary:

Renewal and maintenance of the City’s corporate telecommunications infrastructure including hardware upgrades, accessories (handsets, soft phones, headsets), and IP gateways to meet the City's growing voice and data communication needs.

Rationale:

Several components of the existing communication infrastructure are beyond their useful life. Renewal and maintenance of the City’s corporate communications infrastructure is required to sustain level of service. Additionally, the opportunity to replace all digital communication infrastructures with an IP based solution will reduce the risk of failure and satisfy the City's future communication needs.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Capital Purchase - Request

$250,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $250,000

Capital Purchase - Forecast

$0 $250,000 $250,000 $250,000 $250,000 $0 $0 $0 $0 $0 $1,000,000

Total $250,000 $250,000 $250,000 $250,000 $250,000 $0 $0 $0 $0 $0 $1,250,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from Tax Capital Reserve

$250,000 $250,000 $250,000 $250,000 $250,000 $0 $0 $0 $0 $0 $1,250,000

Total $250,000 $250,000 $250,000 $250,000 $250,000 $0 $0 $0 $0 $0 $1,250,000

140

Page 146: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

Corporate PC Infrastructure Program

Department:

Information Technology

Project Number:

IT1015

Summary:

The City's Corporate PC Technology Infrastructure Program is for the workstation computers used by all City Staff. This program refreshes leased desktop and laptop hardware every 3 years.

Rationale:

Corporate PC Technology Infrastructure Program is managed through a corporate lease agreement paid annually on a three year cycle. It ensures the City's PC technology is current and up to date.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Capital Purchase - Request

$420,250 $411,000 $422,000 $0 $0 $0 $0 $0 $0 $0 $1,253,250

Capital Purchase - Forecast

$0 $0 $0 $433,000 $444,000 $0 $0 $0 $0 $0 $877,000

Total $420,250 $411,000 $422,000 $433,000 $444,000 $0 $0 $0 $0 $0 $2,130,250

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from Tax Capital Reserve

$420,250 $411,000 $422,000 $433,000 $444,000 $0 $0 $0 $0 $0 $2,130,250

Total $420,250 $411,000 $422,000 $433,000 $444,000 $0 $0 $0 $0 $0 $2,130,250

141

Page 147: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

Mobility Technology Program

Department:

Information Technology

Project Number:

IT1019

Summary:

Scope of this intake form includes; purchase and replacement of all City deployed cellular phones, smartphones, tablets and licensing of mobile device management software. Also includes protective casing and screen protectors.

Rationale:

Moving forward with mobility is mobilizing the City's workforce by providing mobile technology to aid in the delivery of City services to the community. Mobility technology is limited to cellular phones, smartphones, tablets and laptops (although laptops are not in the funding scope of this intake form covered by PC Replacement Program). Mobile technology enables secure real time access to City business applications and data available to all City staff management deems beneficial. Mobile device governance has been established through corporate policy; mobile device security is managed through mobile device management (MDM) software supported by the City's IT Department. The IT Department has recognized the City's growing need for mobile technology supporting mobile office and field workers in delivering services for the community.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Plan - Request $120,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $120,000

Capital Purchase - Forecast

$0 $120,000 $120,000 $120,000 $120,000 $0 $0 $0 $0 $0 $480,000

Total $120,000 $120,000 $120,000 $120,000 $120,000 $0 $0 $0 $0 $0 $600,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from Tax Capital Reserve

$120,000 $120,000 $120,000 $120,000 $120,000 $0 $0 $0 $0 $0 $600,000

Total $120,000 $120,000 $120,000 $120,000 $120,000 $0 $0 $0 $0 $0 $600,000

142

Page 148: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

Network Infrastructure Upgrade Program

Department:

Information Technology

Project Number:

000324

Summary:

This program will aid in the redesigning of the 15 year old networking model to support the multi data centre locations the City has invested in. Current remote sites are communicating with technology systems that do not follow current industry best practices.

Rationale:

The Network Infrastructure Revitalization is a redesign of our old network environment. The City's IT environment has outgrown the network that's used to access it. The areas of focus needing attention include but are not limited to network layers, security, performance, multiple data centre locations and resiliency. As we upgrade our voice system, 911 dispatch and other key applications we must have a network to support it.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Plan - Request $150,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $150,000

Total $150,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $150,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from Tax Capital Reserve

$150,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $150,000

Total $150,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $150,000

143

Page 149: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

Network Technology Infrastructure Program

Department:

Information Technology

Project Number:

IT1010

Summary:

The network technology infrastructure program includes the renewal and deployment of core devices and services associated with network switches, load balancers, firewalls, Wi-Fi access points and other network hardware across the City's facilities and data centres required for the continued delivery of corporate data and voice communication.

Rationale:

Networking infrastructure renewal and improvements are required to meet performance requirements of the existing and upcoming technology projects. This program is based on a 5 year replacement cycle for all networking infrastructure including switches, routers, load balancers and firewalls to reduce the risk of failure. Should the network infrastructure not be replaced and a hardware failure occurs, extended outages would be experienced by staff due to their inability to access applications, data, and voice communications via the corporate network.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Capital Purchase - Request

$500,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $500,000

Capital Purchase - Forecast

$0 $750,000 $750,000 $750,000 $750,000 $750,000 $0 $0 $0 $0 $3,750,000

Total $500,000 $750,000 $750,000 $750,000 $750,000 $750,000 $0 $0 $0 $0 $4,250,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from Tax Capital Reserve

$500,000 $750,000 $750,000 $750,000 $750,000 $750,000 $0 $0 $0 $0 $4,250,000

Total $500,000 $750,000 $750,000 $750,000 $750,000 $750,000 $0 $0 $0 $0 $4,250,000

144

Page 150: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

Public Safety Communication Program

Department:

Information Technology

Project Number:

IT1043

Summary:

The City's IT Department maintains a public safety radio system used by BFES, Barrie Police and the City's Water Operations. This program supports the ongoing support, maintenance and lifecycling of radio system hardware and software.

Rationale:

This is required to maintain the City's public safety radio system used by BFES, Barrie Police and the City's Water Operations. This program covers the ongoing support, maintenance and lifecycling of radio system hardware and software, ensuring this vital communication environment is always available

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Execute - Request $300,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $300,000

Execute - Forecast $0 $440,000 $440,000 $530,000 $510,000 $240,000 $240,000 $240,000 $240,000 $0 $2,880,000

Total $300,000 $440,000 $440,000 $530,000 $510,000 $240,000 $240,000 $240,000 $240,000 $0 $3,180,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from Tax Capital Reserve

$200,000 $220,000 $220,000 $120,000 $120,000 $120,000 $120,000 $120,000 $120,000 $0 $1,360,000

Intercompany - General $100,000 $220,000 $220,000 $410,000 $390,000 $120,000 $120,000 $120,000 $120,000 $0 $1,820,000

Total $300,000 $440,000 $440,000 $530,000 $510,000 $240,000 $240,000 $240,000 $240,000 $0 $3,180,000

145

Page 151: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

Server and Storage Technology Infrastructure Program

Department:

Information Technology

Project Number:

IT1012

Summary:

The City's computing server and storage technology infrastructure program estimates a 60% growth of electronic files/data annually. Replacing old technology with new increases the City's capacity and ability to manage electronic information.

Rationale:

The City's server and storage infrastructure hardware throughout City sites and data centres is renewed every three years aligning with industry best practices. Replacement and upgrade of server and storage technology infrastructure (including physical and virtual servers) increases capacity and mitigates the risk of failure of the server and storage infrastructure.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Capital Purchase - Request

$200,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $200,000

Capital Purchase - Forecast

$0 $400,000 $400,000 $400,000 $400,000 $400,000 $0 $0 $0 $0 $2,000,000

Total $200,000 $400,000 $400,000 $400,000 $400,000 $400,000 $0 $0 $0 $0 $2,200,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from Tax Capital Reserve

$200,000 $400,000 $400,000 $400,000 $400,000 $400,000 $0 $0 $0 $0 $2,200,000

Total $200,000 $400,000 $400,000 $400,000 $400,000 $400,000 $0 $0 $0 $0 $2,200,000

146

Page 152: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

Corporate Records & Information Management Strategy System Upgrade

Department:

Legislative & Court Services

Project Number:

000336

Summary:

A Corporate Records and Information Management Program Review was completed in early 2017. A number of recommendations were made by the consultants on methods to enhance/improve the current Program Review.

Rationale:

The Strategy has evaluated the Corporation’s current program and provided practical recommendations for enhancing it to ensure compliance with the Municipal Freedom of Information and Protection of Privacy Act and Municipal Act. Through a staged approach to implementing new technology including the RMAIS System, Email Capture and an EDRMS it will assist address the exponential growth in electronic records, ensure consistent record keeping practices across the Corporation reducing exposure related to being unable to access required records and information when needed or releasing records/information in contravention of the legislation. An EDRMS system will also reduce the staff time spent searching for information. A Corporate Records and Information Management Program has a significant impact on employee productivity as it is estimated that in a typical organization, staff spend approximately 20% of their time looking for information. Through implementing these three systems, it is anticipated that a staff time to look for information will be reduced.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Capital Purchase - Request

$100,000 $100,000 $0 $0 $0 $0 $0 $0 $0 $0 $200,000

Total $100,000 $100,000 $0 $0 $0 $0 $0 $0 $0 $0 $200,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from Tax Capital Reserve

$100,000 $100,000 $0 $0 $0 $0 $0 $0 $0 $0 $200,000

Total $100,000 $100,000 $0 $0 $0 $0 $0 $0 $0 $0 $200,000

147

Page 153: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

Official Plan Comprehensive Update

Department:

Planning & Building Services

Project Number:

000552

Summary:

Preparation of a comprehensive new Official Plan and Zoning Bylaw to respond to Barrie’s status as an Urban Growth Centre, new legislative requirements and the City’s Strategic and Capital Plans for the next 20+ years.

Rationale:

Recently released provincial growth expectations for Barrie will continue to urbanize the city to greater extents than what has been seen before. Ensuring alignment between intensification policies and capital investment decisions through the Official Plan is essential to ensuring future growth can be appropriately accommodated across the community. It is also essential for the Zoning By-law to align with the OP in order for the vision to be achieved. With the secondary plan lands opening up for development, increasing expectations to intensify within the built-boundary, and all major infrastructure Master Plans now being updated, it is timely to advance this key land use policy tool that supports managing growth and development recommendations for the City.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Study - Request $125,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $125,000

Study - Forecast $0 $125,000 $75,000 $0 $0 $0 $0 $0 $0 $0 $200,000

Total $125,000 $125,000 $75,000 $0 $0 $0 $0 $0 $0 $0 $325,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from DC Reserves Tax

$112,500 $112,500 $67,500 $0 $0 $0 $0 $0 $0 $0 $292,500

Contribution from Tax Rate Stabilization Reserve

$12,500 $12,500 $7,500 $0 $0 $0 $0 $0 $0 $0 $32,500

Total $125,000 $125,000 $75,000 $0 $0 $0 $0 $0 $0 $0 $325,000

148

Page 154: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

10 Foot Lawn Mower Replacement (06-2032) - Parks

Department:

Roads, Parks, & Fleet

Project Number:

000594

Summary:

Replace existing 10 foot lawn mower/tractor.

Rationale:

This existing 10 foot lawn mower/tractor at the end of its life cycle and is exceeding the recommended cost/repair threshold.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Capital Purchase - Request

$90,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $90,000

Total $90,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $90,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from Tax Capital Reserve

$90,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $90,000

Total $90,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $90,000

149

Page 155: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

16 Foot Lawn Mower Replacement (06-2033)

Department:

Roads, Parks, & Fleet

Project Number:

000593

Summary:

Replace existing 16 foot lawn mower/tractor.

Rationale:

This existing 16 foot lawn mower/tractor at the end of its life cycle and is exceeding the recommended cost/repair threshold.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Capital Purchase - Request

$125,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $125,000

Total $125,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $125,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from Tax Capital Reserve

$125,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $125,000

Total $125,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $125,000

150

Page 156: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

6 Foot Lawn Mower Replacement (06-2027) - Parks

Department:

Roads, Parks, & Fleet

Project Number:

000595

Summary:

Replace existing 6 foot lawn mower/tractor at the end of its life cycle.

Rationale:

Replace existing 10 foot lawn mower/tractor at the end of its life cycle.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Capital Purchase - Request

$40,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $40,000

Total $40,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $40,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from Tax Capital Reserve

$40,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $40,000

Total $40,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $40,000

151

Page 157: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

6 Foot Lawn Mower Replacement (06-2028) - Parks

Department:

Roads, Parks, & Fleet

Project Number:

000596

Summary:

Replace existing 6 foot lawn mower/tractor.

Rationale:

This existing 6 foot lawn mower/tractor at the end of its life cycle and is exceeding the recommended cost/repair threshold.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Capital Purchase - Request

$40,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $40,000

Total $40,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $40,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from Tax Capital Reserve

$40,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $40,000

Total $40,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $40,000

152

Page 158: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

6 Foot Lawn Mower Replacement (06-2029) - Parks

Department:

Roads, Parks, & Fleet

Project Number:

000597

Summary:

Replace existing 6 foot lawn mower/tractor.

Rationale:

This existing 6 foot lawn mower/tractor at the end of its life cycle and is exceeding the recommended cost/repair threshold.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Capital Purchase - Request

$40,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $40,000

Total $40,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $40,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from Tax Capital Reserve

$40,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $40,000

Total $40,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $40,000

153

Page 159: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

Asphalt Hot Box New Purchase - Roads Operations

Department:

Roads, Parks, & Fleet

Project Number:

000037

Summary:

Replace existing asphalt recycler & hot box.

Rationale:

Replace asphalt recycler & hot box which provide access to hot mix when the asphalt plant is closed, for example during cold weather months, weekends, and evenings. Repairs will be more permanent resulting in fewer claims and resources for repeat repairs.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Capital Purchase - Request

$50,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $50,000

Total $50,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $50,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from Tax Capital Reserve

$50,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $50,000

Total $50,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $50,000

154

Page 160: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

Asphalt Roller Replacement - Roads Operations

Department:

Roads, Parks, & Fleet

Project Number:

000120

Summary:

Replace existing asphalt roller.

Rationale:

This existing asphalt roller at the end of its life cycle and is exceeding the recommended cost/repair threshold.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Capital Purchase - Request

$35,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $35,000

Total $35,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $35,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from Tax Capital Reserve

$35,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $35,000

Total $35,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $35,000

155

Page 161: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

Conventional Transit Bus Replacement 2018 (PTIF)

Department:

Roads, Parks, & Fleet

Project Number:

Z860

Summary:

Replacement of Barrie Transit conventional fleet vehicles. This project includes the purchase of four buses.

Rationale:

Barrie Transit's current contract with MVT Barrie Bus Inc. identifies minimum maintenance requirements based on a fleet management strategy of run to failure. Barrie Transit's fleet has a life cycle expectancy of 12 years which results in over 1 million kilometers being traveled on the asset. By the end of its anticipated useful life the probability of failure on this in service asset is high and would cause significant impact on the service level provided to the residents. The City participates in a joint bus procurement initiative with 20 municipal partners administered by Metrolinx in order to leverage discounts achieved through large volume purchases. As such Transit would like to purchase four replacement buses and retire the existing asset which has reached its expected life. Barrie Transit's current average age of its fleet is 7 years of age which is above its mid-life point. The City has received funding through PTIF for this project.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Capital Purchase - Request

$2,100,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $2,100,000

Total $2,100,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $2,100,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Government of Canada Grant Revenue

$1,050,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $1,050,000

Contribution from Tax Capital Reserve

$1,050,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $1,050,000

Total $2,100,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $2,100,000

156

Page 162: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

Downtown Sidewalk Sweeper Replacement

Department:

Roads, Parks, & Fleet

Project Number:

000043

Summary:

Replace Downtown Sidewalk Sweeper.

Rationale:

Roads Operations requires replacement of the Downtown Sidewalk Sweeper due to physical mortality. The downtown area is required to be kept clean as part of the City's expected Level of Service with BIA.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Capital Purchase - Request

$175,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $175,000

Total $175,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $175,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from Tax Capital Reserve

$175,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $175,000

Total $175,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $175,000

157

Page 163: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

Downtown Winter Control Intersection Clearing Equipment New Purchase

Department:

Roads, Parks, & Fleet

Project Number:

000044

Summary:

Downtown winter control equipment

Rationale:

Roads Operations requires new equipment for performing winter control in the downtown area due to updated legislative requirement for winter control of sidewalks and bicycle paths.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Capital Purchase - Request

$50,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $50,000

Total $50,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $50,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from Tax Capital Reserve

$50,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $50,000

Total $50,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $50,000

158

Page 164: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

Environmental Investigation Van Replacement (03-1021) - Environmental Services

Department:

Roads, Parks, & Fleet

Project Number:

000618

Summary:

Replace existing 2003 Environmental Investigation Van.

Rationale:

This existing 2003 Environmental Investigation Van has reached the end of its life cycle and is exceeding the recommended cost/repair threshold.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Capital Purchase - Request

$40,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $40,000

Total $40,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $40,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from Tax Capital Reserve

$40,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $40,000

Total $40,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $40,000

159

Page 165: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

Loader Replacement (06-8001) - Landfill

Department:

Roads, Parks, & Fleet

Project Number:

000620

Summary:

Replace existing 2006 Landfill rubber tire loader.

Rationale:

The existing 2006 Landfill rubber tire loader is at the end of its life cycle and is exceeding the recommended cost/repair threshold.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Capital Purchase - Request

$250,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $250,000

Total $250,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $250,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from Tax Capital Reserve

$250,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $250,000

Total $250,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $250,000

160

Page 166: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

Mechanical Street Sweeper Replacement (03-7002) - Roads

Department:

Roads, Parks, & Fleet

Project Number:

Z534

Summary:

Replacement of Roads street sweeper.

Rationale:

The existing roads street sweeper has $206,000 life to date costs and $41,000 in costs last year. Anticipated 2018 Operational costs $35000 if the unit isn't replaced.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Capital Purchase - Request

$275,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $275,000

Total $275,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $275,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from Tax Capital Reserve

$275,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $275,000

Total $275,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $275,000

161

Page 167: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

Mechanical Street Sweeper Replacement (03-7006)

Department:

Roads, Parks, & Fleet

Project Number:

000697

Summary:

Replacement of Roads street sweeper as it is at the end of its life cycle.

Rationale:

Replacement of Roads street sweeper $209,000 LTD $41,000 LY costs. Anticipated 2018 Operational costs $18000

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Capital Purchase - Request

$275,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $275,000

Total $275,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $275,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from Tax Capital Reserve

$275,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $275,000

Total $275,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $275,000

162

Page 168: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

Medium Dump Truck Replacement (04-3003) - Roads

Department:

Roads, Parks, & Fleet

Project Number:

Z583

Summary:

Replace existing small dump truck.

Rationale:

The existing small dump truck has reached the end of its life cycle and is exceeding the recommended cost/repair threshold.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Capital Purchase - Request

$100,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $100,000

Total $100,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $100,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from Tax Capital Reserve

$100,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $100,000

Total $100,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $100,000

163

Page 169: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

Pickup Truck Replacement (04-1028) - Roads and Parks

Department:

Roads, Parks, & Fleet

Project Number:

Z632

Summary:

Replace existing Roads pickup truck.

Rationale:

The existing Roads pickup truck has reached the end of its life cycle and is exceeding the recommended cost/repair threshold.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Capital Purchase - Request

$40,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $40,000

Total $40,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $40,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from Tax Capital Reserve

$40,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $40,000

Total $40,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $40,000

164

Page 170: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

Pickup Truck Replacement (04-1040) - Roads

Department:

Roads, Parks, & Fleet

Project Number:

Z644

Summary:

Replace existing Roads pickup truck.

Rationale:

The existing Roads pickup truck that has reached the end of its life cycle and is exceeding the recommended cost/repair threshold.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Capital Purchase - Request

$40,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $40,000

Total $40,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $40,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from Tax Capital Reserve

$40,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $40,000

Total $40,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $40,000

165

Page 171: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

Pickup Truck Replacement (06-1048) - Roads

Department:

Roads, Parks, & Fleet

Project Number:

Z654

Summary:

Replace existing Parks pickup truck.

Rationale:

The existing Parks pickup truck that has reached the end of its life cycle and is exceeding the recommended cost/repair threshold.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Capital Purchase - Request

$50,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $50,000

Total $50,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $50,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from Tax Capital Reserve

$50,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $50,000

Total $50,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $50,000

166

Page 172: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

Pickup Truck Replacement (06-1052) - Facilities

Department:

Roads, Parks, & Fleet

Project Number:

Z662

Summary:

Replace existing Facilities pickup truck.

Rationale:

The existing Facilities pickup truck has reached the end of its life cycle and is exceeding the recommended cost/repair threshold.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Capital Purchase - Request

$30,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $30,000

Total $30,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $30,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from Tax Capital Reserve

$30,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $30,000

Total $30,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $30,000

167

Page 173: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

Pickup Truck Replacement (08-1071) - Roads

Department:

Roads, Parks, & Fleet

Project Number:

Z713

Summary:

Replace existing Roads pickup truck.

Rationale:

The existing Roads pickup truck has reached the end of its life cycle and is exceeding the recommended cost/repair threshold.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Capital Purchase - Request

$50,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $50,000

Total $50,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $50,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from Tax Capital Reserve

$50,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $50,000

Total $50,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $50,000

168

Page 174: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

Rock Truck and Excavator New Purchase - Landfill

Department:

Roads, Parks, & Fleet

Project Number:

000637

Summary:

New Landfill Rock Truck and Excavator.

Rationale:

A new Landfill Rock Truck and Excavator are required as City resumes operation of the Landfill from the contractor Tervita.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Capital Purchase - Request

$1,200,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $1,200,000

Total $1,200,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $1,200,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from Tax Capital Reserve

$1,200,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $1,200,000

Total $1,200,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $1,200,000

169

Page 175: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

Roll Off Truck New Purchase - Environmental Services

Department:

Roads, Parks, & Fleet

Project Number:

000689

Summary:

Second Roll Off Truck for Landfill.

Rationale:

Second Roll Off Truck for Landfill to back up current unit.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Capital Purchase - Request

$300,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $300,000

Total $300,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $300,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from Tax Capital Reserve

$300,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $300,000

Total $300,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $300,000

170

Page 176: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

Sander/Salter Replacement (08-5019) - Roads

Department:

Roads, Parks, & Fleet

Project Number:

Z1172

Summary:

Replace existing salter/sander truck.

Rationale:

The existing salter/sander truck has reached the end of its life cycle and is exceeding the recommended cost/repair threshold.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Capital Purchase - Request

$300,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $300,000

Total $300,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $300,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from Tax Capital Reserve

$300,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $300,000

Total $300,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $300,000

171

Page 177: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

Sander/Salter Replacement (08-5020) - Roads

Department:

Roads, Parks, & Fleet

Project Number:

Z1175

Summary:

Replace existing salter/sander truck.

Rationale:

The existing salter/sander truck has reached the end of its life cycle and is exceeding the recommended cost/repair threshold.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Capital Purchase - Request

$300,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $300,000

Total $300,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $300,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from Tax Capital Reserve

$300,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $300,000

Total $300,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $300,000

172

Page 178: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

Tractor Replacement (01-201) - Roads

Department:

Roads, Parks, & Fleet

Project Number:

Z759

Summary:

Replace existing Roads tractor.

Rationale:

The existing Roads Tractor has reached the end of its life cycle and is exceeding the recommended cost/repair threshold.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Capital Purchase - Request

$65,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $65,000

Total $65,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $65,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from Tax Capital Reserve

$65,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $65,000

Total $65,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $65,000

173

Page 179: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

Van Replacement (04-1033) - Environmental Services

Department:

Roads, Parks, & Fleet

Project Number:

000619

Summary:

Replace existing 2004 Environmental Investigation Van.

Rationale:

This existing 2004 Environmental Investigation Van has reached the end of its life cycle and is exceeding the recommended cost/repair threshold.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Capital Purchase - Request

$40,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $40,000

Total $40,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $40,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from Tax Capital Reserve

$40,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $40,000

Total $40,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $40,000

174

Page 180: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

21-31 Commerce Park Sidewalk Replacement

Department:

Roads, Parks, & Fleet

Project Number:

000577

Summary:

Replace 203 linear meters of interlocking stone sidewalk on Commerce Park Drive with standard OPSS concrete sidewalk.

Rationale:

203 linear meters of interlocking brick sidewalk fronting east part of 21 Commerce Park Drive and fronting 31 Commerce Park Drive has completely failed. The sidewalk has sunk under the weight of the sidewalk plow creating deep ruts in the interlocking stone. This sidewalk has been closed since March 2017. It is currently out of service to pedestrians who will now have to walk on the roadway, boulevard or adjacent private property. Repairing the interlocking stone would equal or exceed the total cost to reconstruct and also result in a substandard sidewalk.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Design - Request $5,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $5,000

Construction - Request $50,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $50,000

Total $55,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $55,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from Tax Capital Reserve

$55,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $55,000

Total $55,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $55,000

175

Page 181: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

Downtown Sidewalk Replacement Program

Department:

Roads, Parks, & Fleet

Project Number:

RP1006

Summary:

Existing paver conditions in the downtown area are deteriorating at a high rate resulting in uneven surfaces, trip hazards, increasing maintenance cost and a negative impact on the aesthetics of the downtown area. Downtown sidewalks constructed with pavers have been assessed and it has been determined that the most effective way of replacement and ongoing maintenance is to completely replace sections in a planned and prioritized approach rather than focusing on repairs to isolated areas.

Rationale:

Existing paver conditions in the downtown are deteriorating at a high rate resulting in uneven surfaces, trip hazards, increasing maintenance cost and a negative impact on the aesthetics of the downtown area. Downtown sidewalks constructed with pavers have been assessed and it has been determined that the most effective way of replacement and ongoing maintenance is to completely replace sections in a planned and prioritized approach rather than focusing on repairs to isolated areas.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Construction - Request $60,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $60,000

Construction - Forecast $0 $60,000 $60,000 $65,000 $0 $0 $0 $0 $0 $0 $185,000

Total $60,000 $60,000 $60,000 $65,000 $0 $0 $0 $0 $0 $0 $245,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from Tax Capital Reserve

$60,000 $60,000 $60,000 $65,000 $0 $0 $0 $0 $0 $0 $245,000

Total $60,000 $60,000 $60,000 $65,000 $0 $0 $0 $0 $0 $0 $245,000

176

Page 182: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

Pine Dr. Subdivision Retaining Wall Removal

Department:

Roads, Parks, & Fleet

Project Number:

000041

Summary:

Removal and Re-grading - Retaining Wall Pine Dr. Subdivision. Walls are in a mode of failure and deteriorating rapidly posing a potential safety concern.

Rationale:

City owned retaining walls on Pine Drive are in failure mode with complete failure anticipated within 1-5 years and need to be replaced. They pose a potential safety concern to the public if they collapse and for slip and falls due to inadequate snow clearing operations. It is anticipated that needs will occur annually that will cost more on a piece meal basis than a full scale solution. The operating budget is not adequate to carry out repairs.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Construction - Request $75,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $75,000

Construction - Forecast $0 $0 $75,000 $0 $0 $0 $0 $0 $0 $0 $75,000

Total $75,000 $0 $75,000 $0 $0 $0 $0 $0 $0 $0 $150,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from Tax Capital Reserve

$75,000 $0 $75,000 $0 $0 $0 $0 $0 $0 $0 $150,000

Total $75,000 $0 $75,000 $0 $0 $0 $0 $0 $0 $0 $150,000

177

Page 183: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

Road Weather Information System (RWIS) Replacement

Department:

Roads, Parks, & Fleet

Project Number:

000586

Summary:

Replacement of Road Weather Information System that has become inoperable due to age. Data is key to make accurate decisions regarding winter control deployment, activities and salt reduction. This data is required to fulfill the requirements of Ontario Regulation 239/02 Minimum Maintenance Standards.

Rationale:

Road and weather condition and forecasts are key inputs to decision making to meet legislated service levels for winter maintenance and to reduce the use of salt and associated environmental impacts. The current station is down and not being utilized. With the new construction on Duckworth St. and Highway 400 interchange, the traffic pattern has been changed. The replacement station will help to monitor the traffic pattern at the Georgian College area and the RVH hospital to provide a higher level of customer service for winter weather monitoring and snow removal activities.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Capital Purchase - Request

$125,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $125,000

Total $125,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $125,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from Tax Capital Reserve

$125,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $125,000

Total $125,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $125,000

178

Page 184: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

Storm Water Management Pond Repair - KD02

Department:

Roads, Parks, & Fleet

Project Number:

000113

Summary:

Reconstruct stormwater management pond KD02 that has severe damage from intense storms. Extensive erosion is occurring downstream as the pond no longer functions to provide quantity control.

Rationale:

Storm water management pond KD02 was severely damaged by intense rain falls and the culverts and check dams providing quantity control have been washed out. Over the past 15 years receiving storm water is passing through the facility unchecked, greatly increasing the quantity and velocity with extensive erosion occurring. Storm water management pond KD02 is north of Cundles Road West inside the loop of Lillian Crescent. This pond, in the Kidds Creek watershed, was originally a dry pond, providing only quantity control of storm water. Some washouts are up to 3m deep. Parks Operations is currently maintaining a safety fence behind Victoria Woods Park as the largest washout is encroaching on a trail. This facility then discharges into Sunnidale Park which at one time had a resident population of Brook Trout. Due to the increase in velocity and quantity of stormwater entering Sunnidale Park, some washouts have already occurred here as well but so far have been manageable repairs.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Design - Request $100,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $100,000

Construction - Forecast $0 $900,000 $0 $0 $0 $0 $0 $0 $0 $0 $900,000

Total $100,000 $900,000 $0 $0 $0 $0 $0 $0 $0 $0 $1,000,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from Tax Capital Reserve

$100,000 $900,000 $0 $0 $0 $0 $0 $0 $0 $0 $1,000,000

Total $100,000 $900,000 $0 $0 $0 $0 $0 $0 $0 $0 $1,000,000

179

Page 185: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

Accessible Pedestrian Pushbutton New Installation

Department:

Roads, Parks, & Fleet

Project Number:

000139

Summary:

In 2016 the AAC identified the following locations for Accessible Pedestrian Pushbuttons. • Hurst and Little • Little and Bayview • Collier and Mulcaster • Collier and Clapperton • Kozlov/Bayfield/Coulter • Mapleview and Bayview • Madeline and Dean • Esther and Madeline • Milburn and Burton • Veterans and Essa

Rationale:

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Initiate - Request $65,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $65,000

Initiate - Forecast $0 $65,000 $0 $0 $0 $0 $0 $0 $0 $0 $65,000

Total $65,000 $65,000 $0 $0 $0 $0 $0 $0 $0 $0 $130,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from Tax Capital Reserve

$65,000 $65,000 $0 $0 $0 $0 $0 $0 $0 $0 $130,000

Total $65,000 $65,000 $0 $0 $0 $0 $0 $0 $0 $0 $130,000

180

Page 186: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

Alectra Pole Betterment and Capital Upgrade Program - Street Lighting Equipment Relocation

Department:

Roads, Parks, & Fleet

Project Number:

000526

Summary:

The City of Barrie is required by agreement with Alectra (formerly Powerstream) to relocate our street lighting plant as directed by Alectra due to their capital upgrade program. Along with the cost to physically relocate the plant there is a design and permit cost associated with this. This design and engineering cost is identified in Ontario Regulation 22/04. Alectra has identified (5) 2017 projects that will require approx. 225 street lights to be relocated in 2018.

Rationale:

The city has third party attachment agreement with Alectra (formerly Powerstream) for the attachment of streetlights to Alectra hydro poles. Under the Electricity Act the city is required to bring to code and relocate their equipment as identified by Alectra (formerly Powerstream). Alectra has identified 5 projects that will require upgrading in 2018 that will support the growth and provide redundancy in the city.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Capital Purchase - Request

$300,000 $300,000 $300,000 $300,000 $0 $0 $0 $0 $0 $0 $1,200,000

Total $300,000 $300,000 $300,000 $300,000 $0 $0 $0 $0 $0 $0 $1,200,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from Tax Capital Reserve

$300,000 $300,000 $300,000 $300,000 $0 $0 $0 $0 $0 $0 $1,200,000

Total $300,000 $300,000 $300,000 $300,000 $0 $0 $0 $0 $0 $0 $1,200,000

181

Page 187: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

Pay & Display Machine Replacement

Department:

Roads, Parks, & Fleet

Project Number:

000579

Summary:

Replacement of failing pay and display machines.

Rationale:

The City currently has pay and display machines at the end of their lifecycle and we are unable to fix the parts on the older machines as parts are no longer available. When the machines are out of service the parking lots do not generate revenue as there is no other source of payment. The 4 machines we are replacing generate approximately $50/hr. at each machine when in use. The replacements will upgrade the current machines to provide credit card readers.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Capital Purchase - Request

$40,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $40,000

Capital Purchase - Forecast

$0 $40,000 $0 $0 $0 $0 $0 $0 $0 $0 $40,000

Total $40,000 $40,000 $0 $0 $0 $0 $0 $0 $0 $0 $80,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from Parking Capital Reserve

$40,000 $40,000 $0 $0 $0 $0 $0 $0 $0 $0 $80,000

Total $40,000 $40,000 $0 $0 $0 $0 $0 $0 $0 $0 $80,000

182

Page 188: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

Traffic Signal Cabinet Replacement Cundles and Harding IPS

Department:

Roads, Parks, & Fleet

Project Number:

000117

Summary:

The traffic signal control cabinet and components at the Cundles and Harding pedestrian crossing are close to 30 years old and are from a line of products that have not been supported for several years. The city had surplussed several units similar to this intersection as a backup for replacement parts. These surplus parts have been exhausted and we are unable to replenish them.

Rationale:

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Initiate - Request $16,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $16,000

Total $16,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $16,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from Tax Capital Reserve

$16,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $16,000

Total $16,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $16,000

183

Page 189: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

Traffic Signal Cabinet Replacement Grove Street IPS

Department:

Roads, Parks, & Fleet

Project Number:

000116

Summary:

The traffic signal control cabinet and components at the Grove Street pedestrian crossing are close to 30 years old and are from a line of products that have not been supported for several years. The city had surplussed several units similar to this intersection as a backup for replacement parts. These surplus parts have been exhausted and we are unable to replenish them.

Rationale:

Hurst and Little

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Initiate - Request $16,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $16,000

Total $16,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $16,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from Tax Capital Reserve

$16,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $16,000

Total $16,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $16,000

184

Page 190: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

Traffic Signal Cabinet Replacement Program Blake and Parkview

Department:

Roads, Parks, & Fleet

Project Number:

000624

Summary:

The traffic signal control cabinet and components at the intersection of Blake and Parkview Centre are close to 30 years old and are from a line of products that have not been supported for several years. The city had surplussed several units similar to this intersection as a backup for replacement parts. These surplus parts have been exhausted and we are unable to replenish them.

Rationale:

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Capital Purchase - Request

$16,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $16,000

Total $16,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $16,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from Tax Capital Reserve

$16,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $16,000

Total $16,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $16,000

185

Page 191: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

Traffic Signal Cabinet Replacement Program Blake and St. Vincent

Department:

Roads, Parks, & Fleet

Project Number:

000623

Summary:

The traffic signal control cabinet and components at the intersection of Blake and St. Vincent are close to 30 years old and are from a line of products that have not been supported for several years. The city had surplussed several units similar to this intersection as a backup for replacement parts. These surplus parts have been exhausted and we are unable to replenish them.

Rationale:

Little and Bayview

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Capital Purchase - Request

$16,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $16,000

Total $16,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $16,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from Tax Capital Reserve

$16,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $16,000

Total $16,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $16,000

186

Page 192: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

Traffic Signal Cabinet Replacement Program St. Vincent and Rose

Department:

Roads, Parks, & Fleet

Project Number:

000625

Summary:

The traffic signal control cabinet and components at the intersection of St. Vincent and Rose are close to 30 years old and are from a line of products that have not been supported for several years. The city had surplussed several units similar to this intersection as a backup for replacement parts. These surplus parts have been exhausted and we are unable to replenish them.

Rationale:

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Capital Purchase - Request

$16,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $16,000

Total $16,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $16,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from Tax Capital Reserve

$16,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $16,000

Total $16,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $16,000

187

Page 193: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

Traffic Signal Cabinet Replacement Steel Street IPS

Department:

Roads, Parks, & Fleet

Project Number:

000114

Summary:

The traffic signal control cabinet and components at the Steel Street pedestrian crossing are close to 30 years old and are from a line of products that have not been supported for several years. The city had surplussed several units similar to this intersection as a backup for replacement parts. These surplus parts have been exhausted and we are unable to replenish them.

Rationale:

Collier and Mulcaster

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Initiate - Request $16,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $16,000

Total $16,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $16,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from Tax Capital Reserve

$16,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $16,000

Total $16,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $16,000

188

Page 194: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

Multi Modal Transit Hub New Study

Department:

Transit & Parking Strategy

Project Number:

000527

Summary:

A study to assess the feasibility of a mobility hub at Allandale Station.

Rationale:

Collier and Clapperton

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Plan - Request $150,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $150,000

Total $150,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $150,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from Tax Rate Stabilization Reserve

$150,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $150,000

Total $150,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $150,000

189

Page 195: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

Transit Fleet New Onboard CCTV Security Cameras

Department:

Transit & Parking Strategy

Project Number:

000528

Summary:

Installation of CCTV security camera's on transit vehicles

Rationale:

Enhanced security and deterrence is achieved through the use of an adequate number of overt cameras that provide complete coverage of the bus in sufficient detail for Incident Occurrence Investigations. Transit receives many complaints on an annual basis regarding operator conduct, fare issues with fare boxes, issues with other riders, insurance claims, which can be difficult to address without sufficient tools. However the when these issues have occurred on vehicles with CCTV the resolution has been quick and never disputed. The addition of on-board Transit CCTV cameras will help: •Increase customer and employee confidence in regards to safety and security •Detect and deter criminal activity •Reduction in fare evasion •Reduce vandalism and damage to transit vehicles resulting in decreased repair costs and fewer out-of-service buses

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Capital Purchase - Request

$75,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $75,000

Total $75,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $75,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from Tax Capital Reserve

$75,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $75,000

Total $75,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $75,000

190

Page 196: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

County of Simcoe Capital Program - Long Term Care & Senior Services

Department:

County of Simcoe

Project Number:

000449

Summary:

Capital Plan for Long Term Care & Senior services delivered by the County of Simcoe. The costs included are the City of Barrie's share.

Rationale:

The City of Barrie is party to an agreement with the County of Simcoe that requires the City to contribute funding toward the County's capital plan on a prescribed basis. This project reflects the County's 10 year Capital Plan, as it relates to long term care and senior services needs, at the time of budget preparation. The plan is subject to change.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Service Partner - Request

$91,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $91,000

Service Partner - Forecast

$0 $74,000 $161,000 $118,000 $97,000 $33,000 $118,000 $125,000 $74,000 $100,000 $900,000

Total $91,000 $74,000 $161,000 $118,000 $97,000 $33,000 $118,000 $125,000 $74,000 $100,000 $991,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from Reserves

$91,000 $74,000 $161,000 $118,000 $97,000 $33,000 $118,000 $125,000 $74,000 $100,000 $991,000

Total $91,000 $74,000 $161,000 $118,000 $97,000 $33,000 $118,000 $125,000 $74,000 $100,000 $991,000

191

Page 197: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

County of Simcoe Capital Program - Paramedic Services

Department:

County of Simcoe

Project Number:

000450

Summary:

Capital Plan for Paramedic services delivered by the County of Simcoe. The costs included are the City of Barrie's share.

Rationale:

The City of Barrie is party to an agreement with the County of Simcoe that requires the City to contribute funding toward the County's capital plan on a prescribed basis. This project reflects the County's 10 year Capital Plan, as it relates to paramedic services, at the time of budget preparation. The plan is subject to change.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Service Partner - Request

$689,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $689,000

Service Partner - Forecast

$0 $1,075,000 $1,514,000 $1,698,000 $1,585,000 $1,395,000 $1,475,000 $1,740,000 $1,988,000 $2,094,000 $14,564,000

Total $689,000 $1,075,000 $1,514,000 $1,698,000 $1,585,000 $1,395,000 $1,475,000 $1,740,000 $1,988,000 $2,094,000 $15,253,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from DC Reserves Tax

$189,000 $575,000 $764,000 $727,714 $731,538 $887,727 $860,417 $870,000 $818,588 $814,333 $7,238,318

Contribution from Reserves

$500,000 $500,000 $750,000 $970,286 $853,462 $507,273 $614,583 $870,000 $1,169,412 $1,279,667 $8,014,682

Total $689,000 $1,075,000 $1,514,000 $1,698,000 $1,585,000 $1,395,000 $1,475,000 $1,740,000 $1,988,000 $2,094,000 $15,253,000

192

Page 198: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

County of Simcoe Capital Program - Social Housing & Community Services

Department:

County of Simcoe

Project Number:

000451

Summary:

Capital Plan for Social Housing & Community services delivered by the County of Simcoe. The costs included are the City of Barrie's share.

Rationale:

The City of Barrie is party to an agreement with the County of Simcoe that requires the City to contribute funding toward the County's capital plan on a prescribed basis. This project reflects the County's 10 year Capital Plan, as it relates to social housing and community services, at the time of budget preparation. The plan is subject to change.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Service Partner - Request

$1,271,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $1,271,000

Service Partner - Forecast

$0 $1,938,000 $1,948,000 $1,826,000 $2,252,000 $2,685,000 $2,965,000 $2,873,000 $2,977,000 $2,826,000 $22,290,000

Total $1,271,000 $1,938,000 $1,948,000 $1,826,000 $2,252,000 $2,685,000 $2,965,000 $2,873,000 $2,977,000 $2,826,000 $23,561,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from DC Reserves Tax

$762,600 $1,384,286 $1,391,429 $1,404,615 $1,689,000 $2,013,750 $2,400,238 $2,298,400 $2,165,091 $2,153,143 $17,662,552

Contribution from Reserves

$508,400 $553,714 $556,571 $421,385 $563,000 $671,250 $564,762 $574,600 $811,909 $672,857 $5,898,448

Total $1,271,000 $1,938,000 $1,948,000 $1,826,000 $2,252,000 $2,685,000 $2,965,000 $2,873,000 $2,977,000 $2,826,000 $23,561,000

193

Page 199: 2018 Capital Budget Project Detail Reports Table of … Hall/Budget/Documents/2018/09...2018 Capital Budget Project Detail Reports Table of Contents Infrastructure Planning 98 Playground

Expense amounts in bold text – 2018 Budget Request Expense amounts in shaded text – Previously Committed Funding

2018 Capital Project Detail Report

Project Title:

Georgian College - Advanced Technology, Innovation and Research Centre

Department:

Other Service Partners & Grants

Project Number:

000448

Summary:

Transfer of $5 million, or a maximum of 25% of total project costs, whichever is less, to Georgian College in support of its proposed Advanced Technology, Innovation and Research Centre.

Rationale:

If Georgian College is successful in securing government funding for a proposed Advanced Technology, Innovation and Research Centre, the City is to provide up to $5 million (or a maximum of 25% of the total project, whichever is less) over a four year period.

Expenses:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Service Partner - Request

$1,250,000 $1,250,000 $1,250,000 $0 $0 $0 $0 $0 $0 $0 $3,750,000

Total $1,250,000 $1,250,000 $1,250,000 $0 $0 $0 $0 $0 $0 $0 $3,750,000

Revenues:

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total

Contribution from Tax Capital Reserve

$1,250,000 $1,250,000 $1,250,000 $0 $0 $0 $0 $0 $0 $0 $3,750,000

Total $1,250,000 $1,250,000 $1,250,000 $0 $0 $0 $0 $0 $0 $0 $3,750,000

194