March 16, 2017 2017 NCDOT Contract Administration Workshop Lamar Sylvester, PE State Construction Engineer

2017 NCDOT Contract Administration Workshop...• Total Number of Projects = 223 • Projects Completed by the Original Completion Date = 98 • Projects Completed by the Revised Completion

  • Upload
    others

  • View
    0

  • Download
    0

Embed Size (px)

Citation preview

Page 1: 2017 NCDOT Contract Administration Workshop...• Total Number of Projects = 223 • Projects Completed by the Original Completion Date = 98 • Projects Completed by the Revised Completion

March 16, 2017

2017 NCDOT Contract Administration Workshop

Lamar Sylvester, PE State Construction Engineer

Page 2: 2017 NCDOT Contract Administration Workshop...• Total Number of Projects = 223 • Projects Completed by the Original Completion Date = 98 • Projects Completed by the Revised Completion

Project Delivery

2

Page 3: 2017 NCDOT Contract Administration Workshop...• Total Number of Projects = 223 • Projects Completed by the Original Completion Date = 98 • Projects Completed by the Revised Completion

3

Project Delivery Expectations

• Safety • On Schedule • Teamwork • Timely Issue Resolution • Budget Conscious

Page 4: 2017 NCDOT Contract Administration Workshop...• Total Number of Projects = 223 • Projects Completed by the Original Completion Date = 98 • Projects Completed by the Revised Completion

Project Delivery – All Projects Calendar Years 2012 – 2016

4

46.9%

31.8%

21.3% % Complete byOriginal CompletionDate% Complete byRevised CompletionDate% Not Complete byOriginal or RevisedCompletion Date

• Total Number of Projects = 2,918 • Projects Completed by the Original Completion Date = 1,369 • Projects Completed by the Revised Completion Date = 928 • Projects Not Completed by the Original or Revised Completion Date = 621

*Based on Final Estimates Paid

Page 5: 2017 NCDOT Contract Administration Workshop...• Total Number of Projects = 223 • Projects Completed by the Original Completion Date = 98 • Projects Completed by the Revised Completion

Project Delivery – All Projects Calendar Year 2016

5

45.8%

36.3%

17.8% % Complete byOriginal CompletionDate% Complete byRevised CompletionDate% Not Complete byOriginal or RevisedCompletion Date

• Total Number of Projects = 622 • Projects Completed by the Original Completion Date = 285 • Projects Completed by the Revised Completion Date = 226 • Projects Not Completed by the Original or Revised Completion Date = 111

*Based on Final Estimates Paid

Page 6: 2017 NCDOT Contract Administration Workshop...• Total Number of Projects = 223 • Projects Completed by the Original Completion Date = 98 • Projects Completed by the Revised Completion

Project Delivery – All Projects 2012 - 2016

Calendar Year

Total No. Projects

Complete by Contract

Completion Date

Complete by Revised

Completion Date

Not Complete by Contract Completion

Date or Revised Completion Date

2012 523 217 (41.5%)

168 (32.1%)

138 (26.4%)

2013 606 302 (49.8%)

177 (29.2%)

127 (21.0%)

2014 590 282 (47.8%)

176 (29.8%)

132 (22.4%)

2015 577 283 (49.0%)

181 (31.4%)

113 (19.6%)

2016 622 285 (45.8%)

226 (36.3%)

111 (17.8%)

6

Page 7: 2017 NCDOT Contract Administration Workshop...• Total Number of Projects = 223 • Projects Completed by the Original Completion Date = 98 • Projects Completed by the Revised Completion

Project Delivery – All Projects Calendar Years 2012 - 2016

7

0%

10%

20%

30%

40%

50%

60%

2012 2013 2014 2015 2016

% Complete by OriginalCompletion Date

% Complete by RevisedCompletion Date

% Not Complete byOriginal or RevisedCompletion Date

Page 8: 2017 NCDOT Contract Administration Workshop...• Total Number of Projects = 223 • Projects Completed by the Original Completion Date = 98 • Projects Completed by the Revised Completion

Project Delivery – Resurfacing Projects Calendar Years 2012 – 2016

8

49.6%

22.8%

27.6%

% Complete by OriginalCompletion Date

% Complete by RevisedCompletion Date

% Not Complete byOriginal or RevisedCompletion Date

• Total Number of Projects = 928 • Projects Completed by the Original Completion Date = 460 • Projects Completed by the Revised Completion Date = 212 • Projects Not Completed by the Original or Revised Completion Date = 256

*Based on Final Estimates Paid

Page 9: 2017 NCDOT Contract Administration Workshop...• Total Number of Projects = 223 • Projects Completed by the Original Completion Date = 98 • Projects Completed by the Revised Completion

Project Delivery – Resurfacing Projects Calendar Year 2016

• Total Number of Projects = 223 • Projects Completed by the Original Completion Date = 98 • Projects Completed by the Revised Completion Date = 62 • Projects Not Completed by the Original or Revised Completion Date = 63

9

43.9%

27.8%

28.3% % Complete byOriginal CompletionDate

% Complete byRevised CompletionDate

% Not Complete byOriginal or RevisedCompletion Date

*Based on Final Estimates Paid

Page 10: 2017 NCDOT Contract Administration Workshop...• Total Number of Projects = 223 • Projects Completed by the Original Completion Date = 98 • Projects Completed by the Revised Completion

Project Delivery – Resurfacing Projects 2012 – 2016

10

Calendar Year

Total No. of

Projects

Complete by Contract

Completion Date

Complete by Revised

Completion Date

Not Complete by Contract or Revised

Completion Date

2012 163 72 (44.2%)

37 (22.7%)

54 (33.1%)

2013 178 90 (50.6%)

39 (21.9%)

49 (27.5%)

2014 172 87 (50.6%)

36 (20.9%)

49 (28.5%)

2015 192 113 (58.9%)

38 (19.8%)

41 (21.4%)

2016 223 98 (43.9%)

62 (27.8%)

63 (28.3%)

Page 11: 2017 NCDOT Contract Administration Workshop...• Total Number of Projects = 223 • Projects Completed by the Original Completion Date = 98 • Projects Completed by the Revised Completion

Project Delivery – Resurfacing Projects 2012 – 2016

11

0%

10%

20%

30%

40%

50%

60%

70%

2012 2013 2014 2015 2016

% Complete byOriginal CompletionDate

% Complete byRevised CompletionDate

% Not Complete byOriginal or RevisedCompletion Date

Page 12: 2017 NCDOT Contract Administration Workshop...• Total Number of Projects = 223 • Projects Completed by the Original Completion Date = 98 • Projects Completed by the Revised Completion

Questions?