Upload
others
View
3
Download
0
Embed Size (px)
Citation preview
2017 ANNUAL VRL
ANALYSIS Subtitle
Published on 8/1/2017
By Ops Market Support/Forensics
Tom Burns
Ricky Finkbeiner
R
Southwest Power Pool, Inc.
CONTENTS
Executive Summary ................................................................................................................................................................ 1
Recommendations .................................................................................................................................... 2
Background ................................................................................................................................................................................ 3
Analysis of Current VRLs ...................................................................................................................................................... 5
Binding in the Integrated Marketplace ................................................................................................. 6
Breaching in Real-Time Balancing Market ............................................................................................ 8
Breaching in the Day Ahead Market ..................................................................................................... 9
Review of VRL changes from the 2016 VRL Analysis .......................................................................... 10
Sensitivity Analysis ............................................................................................................................................................... 13
Methodology ........................................................................................................................................... 13
Sensitivities Analyzed .............................................................................................................................. 13
Sensitivity Analysis Results ..................................................................................................................... 18
Conclusion ................................................................................................................................................................................ 22
Appendix ................................................................................................................................................................................... 23
Explanation of M2M Breached Intervals ................................................................................................ 23
Impact of kV Level to Shadow Prices and Congestion Cost .................................................................... 24
Cost of Congestion .............................................................................................................................. 24
Impact of External/Parallel Flows ....................................................................................................... 26
Determination of kV Method VRL Blocks ............................................................................................... 28
Southwest Power Pool, Inc.
2017 SPP Annual VRL Analysis 1
EXECUTIVE SUMMARY
This report provides the annual analysis on the Integrated Marketplace Violation Relaxation Limits
(VRLs). It includes the effectiveness of the VRLs and their value on reliability and pricing, as well as
a sensitivity analysis with recommendations for changes. The primary focus of the analysis is for
the period July 2016 – June 2017.
VRLs are applied when the Shadow Price to meet a constraint exceeds the defined Violation
Relaxation Limit. The three VRL constraint/categories are
Spinning Reserve Requirement
Operating Constraint – including Manual, Pnode, Watch List, Flowgate, and Real-Time
Contingency Analysis (RTCA) constraints
Operating Constraint subject to Market-to-Market coordination
Table 1 below shows the summary of VRL instances in the Real-Time Balancing Market (RTBM) and
Day-Ahead Market (DAMKT) for the SPP Integrated Marketplace. Note that RTBM instances
account for a 5-minute interval while the DAMKT instances account for a 1-hour interval. Multiple
VRL instances can occur per interval if there are more than one constraint with a VRL application in
that interval. Analysis in this report will primarily focus on Operational Constraint VRLs due to the
large number of instances of that category’s application.
Table 1: Summary of VRL instances in the RTBM and DAMKT.
Day Ahead Real-Time
July 2015 -
June 2016
July 2016 -
June 2017
July 2015 -
June 2016
July 2016 -
June 2017
Spinning Reserve 0 0 237 622
Operating Constraint 245* 1386* 28,173 47,424
Operating Constraint – Lower
external M2M Shadow Price
0 0 12,501 18,608
*Day-Ahead Market constraint breaches are primarily due to phase shifter constraints that
breach when the equipment is out of service. These instances have $0 Shadow Price and no
pricing impact. They account for 220 of the 245 instances of breached DAMKT constraints in
2015-2016 reporting year and 1,296 of the 1,386 instances of breached DAMKT constraints in
the 2016-2017 reporting year.
Southwest Power Pool, Inc.
2017 SPP Annual VRL Analysis 2
RECOMMENDATIONS SPP recommends no changes to the VRLs related to Spinning Reserve Requirements and Operating
Constraints. Based on the sensitivity analysis presented in this report, SPP also does not
recommend making changes to the VRL blocks for Operational Constraints. The sensitivities
analyzed, while showing differing values from each approach, do not indicate a clear need for
changes or a better method at this time.
However, SPP believes further changes to the Operational Constraint VRLs may be warranted and
will continue analysis to identify improvements to reduce the large number of breached instances.
Southwest Power Pool, Inc.
2017 SPP Annual VRL Analysis 3
BACKGROUND
In certain situations, attempting to enforce all constraints may result in a solution that is not
feasible at a Shadow Price less than an appropriately priced VRL. In those cases, SPP will apply the
VRLs in the Market Clearing Engine (MCE) solution. Per the Integrated Marketplace Protocols,
VRLs and their associated values are intended to achieve the following objectives:
1. Mitigate the occurrence of price excursions or other extreme prices
2. Remove the portion of a loading violation attributed to market flow on a flowgate within
30 minutes of the start of a VRL violation
3. Mitigate the regulation burden placed on the Resources providing regulation services
4. Limit contribution to CPS violations
5. Minimize the need for OOMEs
Table 2 contains the current VRL constraints and values currently in place.
Table 2: Current VRL constraints.
Constraint Type Description VRL [$/MW]
Operating Constraint A MW limit that can be imposed
on SPP related to MW flow across
a market node, a manually-
identified transmission
constraint, a Watch List
transmission constraint, a
flowgate constraint, or a
transmission constraint identified
by SPP’s real-time contingency
analysis.
$750 when the loading is greater than
100% and less than or equal to 101%
at each network constraint at each
Operating Constraint.
$750 when >101% and <= 102%
$1,000 when >102% and <= 103%
$1,250 when >103% and <= 104%
$1,500 when >104%
Operating Constraint
subject to Market-to-
Market coordination
A MW limit that can be imposed
on SPP related to MW flow across
a market node, a manually-
identified transmission
constraint, a Watch List
transmission constraint, a
flowgate constraint, or a
transmission constraint identified
by SPP’s real-time contingency
analysis.
MISO’s Shadow Price as further
defined in Section 3.1 of the SPP-MISO
JOA
Spinning Reserve
Constraint
A MW value representing the
Spinning Reserve requirement
$200
Southwest Power Pool, Inc.
2017 SPP Annual VRL Analysis 4
SPP has requirements to provide (by November 1st each year) analysis as well as a set of proposed
Violation Relaxation Limits (“VRLs”) for review by the applicable working groups and committees
as described in the Integrated Marketplace Protocols. The report, analysis, sensitivities, and
recommendations are due to the appropriate working groups by August 1st. Sources for these
requirements are currently found in the following SPP governing documents:
Integrated Marketplace Protocols section 4.1.4
SPP Tariff Attachment AE section 3.4 and Addendum 1
Southwest Power Pool, Inc.
2017 SPP Annual VRL Analysis 5
ANALYSIS OF CURRENT VRLS
The following section provides and overview and analysis of the VRL usage in the SPP Integrated
Marketplace. The analysis focused on Operational Constraint VRLs due to the small usage of the
other VRL types. In the past few years, with the analysis and reporting due on August 1st, the data
has been focused on the previous year of data (July of previous year through June of current year)
to provide the latest data available. For this reason, unless otherwise noted, data referred to by
reporting year follows the convention defined below:
Reporting Year 2015: July 2014 – June 2015
Reporting Year 2016: July 2015 – June 2016
Reporting Year 2017: July 2016 – June 2017
Southwest Power Pool, Inc.
2017 SPP Annual VRL Analysis 6
BINDING IN THE INTEGRATED MARKETPLACE
Charts below show the reporting year-to-year changes in binding instances grouped by Shadow
Price range. Both RTBM and DAMKT saw similar large increases in binding instances, relative to the
previous year, with most of the increase occurring in $0-$100 Shadow Price ranges.
RTBM shows higher instances of congestion, but that is mostly due to having 5-minute intervals vs the 1-hour intervals of DAMKT.
SPP does encounter instances of binding with a Shadow Price greater than the $500 range in RTBM, even in 2015 and 2016 before first VRL block was raised above $500. These occur
on non-SPP M2M flowgates where, due to M2M logic, SPP (as the non-monitoring RTO) is
using the higher VRL blocks of the monitoring RTO and is able to bind to that level.
Figure 1: RTBM Binding instances by reporting year and Shadow Price
Figure 2: Day-Ahead Market binding instances by reporting year and Shadow Price.
104461
2429110466 6273 4118 10 18
159602
24353
9363 6241 4211 54 171
181597
49682
2571614497 9829
2761 2069
0
20000
40000
60000
80000
100000
120000
140000
160000
180000
200000
$0 - $100 $100 - $200 $200 - $300 $300 - $400 $400 - $500 $500 - $600 $600 +
To
tal
Bin
din
g I
nst
an
ce
s
RTBM Binding Instances by Reporting Year
2014-2015 2015-2016 2016-2017
39371
3548 764 202 52
57254
2533 325 85 23
75423
6510 1945 692187
26 90
10000
20000
30000
40000
50000
60000
70000
80000
$0 - $100 $100 - $200 $200 - $300 $300 - $400 $400 - $500 $500 - $600 $600 +
To
tal
Bin
din
g I
nst
an
ce
s
DAMKT Binding Instances by Reporting Year
2014-2015 2015-2016 2016-2017
Southwest Power Pool, Inc.
2017 SPP Annual VRL Analysis 7
Furthermore, when we look at the binding instances by Shadow Price as a percent of all binding
instances, we see a higher concentration of Day-Ahead Market binding instances in the $0 - $100
Shadow Price range. This is somewhat typical, though we do see a higher disparity between RTBM
and DAMKT compared to previous years. Causes for smaller Shadow Prices in the DAMKT are
primarily due to:
Less volatility than RTBM data, and
More options to solve constraints (virtual bids/offers, NDVERs participating as
dispatchable, etc.) so the DAMKT constraints can be solved more easily.
Figure 3: Real-Time Balancing Market OC Binding instance by Shadow Price – July 2016-June 2017
Figure 4: Day-Ahead Market OC Binding instance by Shadow Price – July 2016-June 2017
63.5%
17.4%
9.0% 5.1% 3.4% 1.0% 0.7%0%
20%
40%
60%
80%
100%
0
40,000
80,000
120,000
160,000
200,000
$0 -
$100
$100 -
$200
$200 -
$300
$300 -
$400
$400 -
$500
$500 -
$600
$600 +
% O
C T
ota
l B
ind
ing
In
sta
nc
es
To
tal
Bin
din
g I
nst
an
ce
s
RTBM OC Binding Instances by Shadow Price
July 2016 - June 2017
Binding Instances Percentage
89.0%
7.7%2.3% 0.8% 0.2% 0.0% 0.0%
0%
20%
40%
60%
80%
100%
0
20,000
40,000
60,000
80,000
100,000
$0 -
$100
$100 -
$200
$200 -
$300
$300 -
$400
$400 -
$500
$500 -
$600
$600 +
% O
C T
ota
l B
ind
ing
In
sta
nc
es
To
tal
Bin
din
g I
nst
an
ce
s
DAMKT OC Binding Instances by Shadow Price
July 2016 - June 2017
Binding Instances Percentage
Southwest Power Pool, Inc.
2017 SPP Annual VRL Analysis 8
BREACHING IN REAL-TIME BALANCING MARKET
The number of constraint breach events has continued to rise in RTBM from year to year. This is
partly due to increased congestion, as can be seen with the increased binding instances from the
previous section. Additionally, SPP has seen more wind added to the system and with it comes
more congestion. These situations outlined in the 2016 VRL Analysis, with low shift factors and low
offer prices, require Shadow Prices of larger magnitude to control.
This first chart shows the increase in occurrence of breach events in RTBM.
Figure 5: Real-Time Balancing Market Breach instances and severity by reporting year
While at the same time, when looked at as a percentage of total breaches, there has not been a large
change in the distribution of breach overloads, with most breaches staying in the 1-3% range.
Figure 6: Real-Time Balancing Market Percent Breach instances and severity by reporting year
0
5,000
10,000
15,000
20,000
1% or
less
1-2% 2-3% 3-4% 4-5% 5-6% 6-7% 7-8% 8-9% 9-10% 10+%
RT
BM
Bre
ac
h I
nst
an
ce
s
RTBM Breach Instances and Severity (% over limit) by Reporting Year
Excluding Market Flow Control & External M2M
2014-2015 2015-2016 2016-2017
0%10%20%30%40%50%60%
1% or
less
1-2% 2-3% 3-4% 4-5% 5-6% 6-7% 7-8% 8-9% 9-10% 10+%
% o
f B
rea
ch
es
RTBM Percent Breach Instances and Severity (% over limit) by
Reporting Year
Excluding Market Flow Control & External M2M
2014-2015 2015-2016 2016-2017
Southwest Power Pool, Inc.
2017 SPP Annual VRL Analysis 9
Breach instances are excluded from the above where SPP was controlling the constraint in Market
Flow Control (such as external M2M or congestion from TLR to meet market relief assignment).
BREACHING IN THE DAY AHEAD MARKET
The Day-Ahead Market sees far fewer breaches than RTBM, primarily due to:
Less volatility and unexpected system changes
A longer dispatch period (1 hour vs 5 minutes) to solve the constraint
Virtual bids and offers provide much options to resolve the constraint at lower Shadow Prices
Different Resource offer/dispatch behavior between Real-Time and Day-Ahead.
As noted in the opening of the report, many of the “breached” intervals in the Day-Ahead Market
are due to phase shifter control constraints that are unable to solve when the phase-shifting
transformer becomes temporarily radial due to transmission outages. These instances all resulted
in $0 Shadow Price and did not affect the solution but are still reported as breached.
Table 3: Day-Ahead Market Breach events
DAY AHEAD MARKET BREACH EVENTS
Reporting Year
Standard Constraint
Phase Shifter Outaged
Total
2014-2015 43 26 69
2015-2016 25 220 245
2016-2017 90 1296 1386
The vast majority of breached intervals in the Day-Ahead Market are at or below the 1% overload
mark.
Southwest Power Pool, Inc.
2017 SPP Annual VRL Analysis 10
Figure 7: DAMKT Breach Instances and Severity by Reporting Year
REVIEW OF VRL CHANGES FROM THE 2016 VRL ANALYSIS
After the 2016 VRL analysis, a change was proposed (and approved through the stakeholder
process) to modify the VRL blocks that had been in place for several years in SPP. The change was
minor – bypassing the first $500 block and setting both the first and second (for overloads between
100 and 102% of the limit) blocks to breach at a $750 Shadow Price. This helped reduce the
occurrence of continuously breaching flowgates and “economic breaches” (those instances where
plenty of relief was available to resolve the constraint, but at a Shadow Price magnitude larger than
the first VRL block). This change was proposed and accepted for several reasons, with the primary
intent being the reduction in the number of breaches experienced in the RTBM, which would result
in the following:
Increase the likelihood of maintaining a flowgate’s flow under the required limit
Increase transparency in the transmission congestion and allow for fewer effective limit
offsets (which had been required for continuously breaching flowgates)
Adjust for the changing system fleet in SPP, with more wind participating with very low offer prices and low shift factors that require large Shadow Prices to provide relief on the
transmission constraints.
0%
20%
40%
60%
80%
100%
1% or less 1-2% 2-3% 3-4% 4-5% 5% +
% o
f T
ota
l B
rea
ch
es
DAMKT Breach Instances and Severity by Reporting Year
Excluding Market Flow Control & External M2M
2014-2015 2015-2016 2016-2017
Southwest Power Pool, Inc.
2017 SPP Annual VRL Analysis 11
Figure 8: SPP Operational Constraint VRL Blocks
SPP stakeholders and FERC approved this change with an effective date of March 6, 2017. With less
than four months of actual usage of the new blocks in the Integrated Marketplace, SPP has not had
the opportunity to see the full impact of the change. However, by analyzing the data from March 6,
2017 to June 30, 2017 estimates of the reduction in breach events were made.
$750 set as first
VRL block
starting 3/6/17
$0
$250
$500
$750
$1,000
$1,250
$1,500
$1,750
98% 99% 100% 101% 102% 103% 104% 105% 106% 107% 108%
Sh
ad
ow
Pri
ce
% of Effective Constraint Limit
SPP Operational Constraint VRL Blocks
Original VRL Blocks VRL Blocks as of 3/6/17
Southwest Power Pool, Inc.
2017 SPP Annual VRL Analysis 12
To see the reduction in breach events, SPP has added a new definition for “Breach Avoided”, due to
the raising of the first VRL block to $750. An instance is counted as a Breach Avoided if it was binding
in the solution with a Shadow Price between $500 and $750 – meaning that under the old VRL blocks
it would have been required to breach, but under the new VRL blocks it does not. The RTBM data
shows roughly 25% of breached instances were avoided with the new VRL blocks. This is similar to
the value of reduction realized from the 2016 analysis, which confirms that the methodology and
conclusions from the analysis were realistic.
Table 4: Summary of Binding, Breached, and Breach Avoided instances.
BINDING M2M
BREACHED BREACHED
BREACH AVOIDED
TOTAL CONGESTED
% OF BREACHES AVOIDED
DAMKT 27,709 1,299 34 29,042 2.6%
Mar-17 6,379
57
6,436 0.0%
Apr-17 7,729
1 5 7,735 83.3%
May-17 6,385
713 10 7,108 1.4%
Jun-17 7,216
528 19 7,763 3.5%
RTBM 95,461 7,102 13,615 4,747 120,925 25.9%
Mar-17 22,723 1,623 2,587 1,010 27,943 28.1%
Apr-17 26,760 3,106 3,977 1,519 35,362 27.6%
May-17 23,189 1,192 3,602 1,489 29,472 29.2%
Jun-17 22,789 1,181 3,449 729 28,148 17.4%
Figure 9: RTBM Percentage of Congested Instances by Month
Additionally, more coverage of the impacts and comparisons of this change, relative to others, will
be in the Sensitivity Analysis section.
50%
60%
70%
80%
90%
100%
7 8 9 101112 1 2 3 4 5 6 7 8 9 101112 1 2 3 4 5 6 7 8 9 101112 1 2 3 4 5 6
2014 2015 2016 2017% o
f C
on
ge
ste
d I
nst
an
ce
s
Month/Year
RTBM % of Congested Instances by MonthBinding Breach avoided Breached
Southwest Power Pool, Inc.
2017 SPP Annual VRL Analysis 13
SENSITIVITY ANALYSIS
METHODOLOGY Rather than just altering the value of the existing VRL blocks, this year’s sensitivity analysis
changed the method and grouping by which SPP applies VRLs. The VRL changes and their impacts
were assessed by re-running RTBM studies for two one-week spans. The weeks picked are recent
and representative of typical congestion patterns on the SPP system. Intervals included in the
assessment were:
4,025 intervals covering the days 5/20 – 5/26/17 and 6/22 – 6/28/17 o This range was used to cover only periods after the pricing implementation of
RR175 (Ramp Shortage Compliance) in early May 2017
System load ranging from 20.8 to 44.3 GW
System wind forecasts from 0.8 GW to 13.1GW
Net Scheduled Interchange ranging from -1.9 GW to +2.1 GW
There were four major sensitivities covered. The sensitivities defined were Base, Old Curve, kV
Method, and Ratchet Method.
The VRL blocks were the only input changes to the cases and the results were assessed based on the
performance of constraint control (how many breached instances are observed) as well as system
cost and pricing indicators.
SENSITIVITIES ANALYZED 1. Base – This was simply the existing curve as posted in the SPP Tariff and Protocols, effective
since 3/6/2017.
a. $750 when the loading is greater than 100% and less than or equal to 101% at each
network constraint at each Operating Constraint.
b. $750 when >101% and <= 102%
c. $1,000 when >102% and <= 103%
d. $1,250 when >103% and <= 104%
e. $1,500 when >104%
2. Old Curve – The original VRL blocks used for several years and in effect in SPP Integrated
Marketplace until 3/6/2017. This is included to provide some assessment of how the older
VRL blocks would fare against the current “Base” VRL blocks as well as other sensitivities.
a. The blocks are the same as the Base blocks with the exception of the first block
being set to $500 when the loading is greater than 100% and less than or equal to
101% at each network constraint at each Operating Constraint.
b. The comparison of Base and Old VRL blocks is shown below.
Southwest Power Pool, Inc.
2017 SPP Annual VRL Analysis 14
Figure 10: Example of Base and Old VRL blocks
3. kV Method – These VRL blocks are set differently based on the kV level of the monitored
element. This is a follow-up from the 2016 VRL Analysis, which showed many constraints
had similar responses to VRL changes as other constraints with the same kV level of the
monitored element(s). More information is available in the Appendix “Impact of kV Level to
Shadow Prices and Congestion Cost” and “Determination of kV Method VRL Blocks”. The kV
VRL blocks are listed in the Table 5 (and Figure 11).
Table 5: kV Method VRL blocks
69kV 115kV 138kV 161KV 230kV 345kV
If VRL passed,
relax limit to
First Block $1,000 $600 $750 $1,000 $300 $300 101%
$1,250 $800 $938 $1,250 $525 $475 102%
$1,500 $1,000 $1,125 $1,500 $750 $650 103%
$1,750 $1,200 $1,313 $1,750 $975 $825 104%
Last Block $2,000 $1,400 $1,500 $2,000 $1,200 $1,000 105%
$0
$250
$500
$750
$1,000
$1,250
$1,500
$1,750
98% 99% 100% 101% 102% 103% 104% 105% 106% 107% 108%
Sh
ad
ow
Pri
ce
% of Effective Constraint Limit
SPP Operational Constraint VRL Blocks
Old Curve Base
Southwest Power Pool, Inc.
2017 SPP Annual VRL Analysis 15
Figure 11: kV Method VRL blocks
4. Ratchet Method – This sensitivity was another proposed item to investigate from the 2016
VRL Analysis. This method is an attempt to increase the VRL blocks after each breached
interval for a constraint. Every time a constraint was breached in the RTBM, the next
interval would shift the VRL blocks over one step. The intent was to imitate the increasing
urgency of a reliability situation as the breached condition persists and to put more pricing
pressure on resolving the situation.
Table 6: Ratchet Method VRL blocks
Base Ratchet
#1 Ratchet
#2 Ratchet
#3 If VRL passed, relax limit to
First Block $750 $1,000 $1,250 $1,500 101%
$750 $1,250 $1,500 $1,500 102%
$1,000 $1,500 $1,500 $1,500 103%
$1,250 $1,500 $1,500 $1,500 104%
Last Block $1,500 $1,500 $1,500 $1,500 105%
Figure 12 below provides a visual representation of the Ratchet Method VRL blocks.
Essentially, after each interval that a constraint breaches, the curve shifts to the left for that
particular constraint so the SCED will enforce a higher starting penalty for breaching the
flowgate.
115kV
138kV
69kV & 161kV
230kV345kV
$0
$500
$1,000
$1,500
$2,000
$2,500
98% 99% 100% 101% 102% 103% 104% 105% 106% 107% 108%
Sh
ad
ow
Pri
ce
% of Effective Constraint Limit
VRL Blocks used for kV Method
69kV 115kV 138kV 161kV 230kV 345kV
Southwest Power Pool, Inc.
2017 SPP Annual VRL Analysis 16
Figure 12: Ratchet Method VRL blocks and timing
Consideration was also given for when to bring the ratchet back down. For instance, a
temporary event could cause sudden loading and several breached intervals for a flowgate.
This would cause the VRL blocks to ratchet up several times in this Ratchet Method. After
the event was resolved, we would still want some mechanism to ratchet back down to the
normal/pre-breach VRL blocks. For these situations, a time limit of 30 minutes with no
breaches was enforced before the ratchet down could start. The ratchet down was also
based on the largest magnitude Shadow Price from those prior 30 minutes, so SPP would
not ratchet down to a VRL block/curve that started lower than the first block of the selected
penalty curve. Table 7 below illustrates an example of both the ratchet up (occurring
intervals 00:15 – 00:20 based on breaching the prior intervals) and then the eventual
ratchet down (intervals 01:05 and 01:15) as the breaching had stopped and the congested
Shadow Price magnitude fell below that of the next lowest VRL block.
$0
$250
$500
$750
$1,000
$1,250
$1,500
$1,750
98% 99% 100% 101% 102% 103% 104% 105% 106% 107% 108%
Sh
ad
ow
Pri
ce
% of Effective Constraint Limit
VRL Blocks used for Ratchet Method Sensitivity
Base Curve Ratchet #1 Ratchet #2 Ratchet #3
After 1st Breach move from
Base Curve to Ratchet #1
After 2nd Breach move from
Ratchet #1 to Ratchet #2
After 3rd Breach move from
Ratchet #2 to Ratchet #3
Southwest Power Pool, Inc.
2017 SPP Annual VRL Analysis 17
Table 7: Ratchet Method example application
INTERVAL CONSTRAINT
STATE SHADOW
PRICE PENALTY
CURVE USED COMMENT
0:00 Binding -$400 Base Curve
0:05 Binding -$450 Base Curve
0:10 Breached -$1,100 Base Curve No impact to inputs yet because of no previous breach
0:15 Breached -$1,150 Ratchet #1 Ratchet up once based on Breach in previous interval
0:20 Binding -$1,150 Ratchet #2 Ratchet up once based on Breach in previous interval
0:25 Binding -$1,100 Ratchet #2 Keep same curve since breached in previous 6 intervals
0:30 Binding -$1,100 Ratchet #2 Keep same curve since breached in previous 6 intervals
0:35 Binding -$900 Ratchet #2 Keep same curve since breached in previous 6 intervals
0:40 Binding -$900 Ratchet #2 Keep same curve since breached in previous 6 intervals
0:45 Binding -$600 Ratchet #2 Keep same curve since breached in previous 6 intervals
0:50 Binding -$600 Ratchet #2 Keep same curve; no breaches but max |SP| in previous 6 intervals ($1,100) is still > $1,000 (Ratchet #1's first penalty)
0:55 Binding -$600 Ratchet #2 Keep same curve; no breaches but max |SP| in previous 6 intervals ($1,100) is still > $1,000 (Ratchet #1's first penalty)
1:00 Binding -$600 Ratchet #2 Keep same curve; no breaches but max |SP| in previous 6 intervals ($1,100) is still > $1,000 (Ratchet #1's first penalty)
1:05 Binding -$600 Ratchet #1 Ratchet down one curve; no breaches and max |SP| in previous 6 intervals ($900) is still > $750 (Base's first penalty)
1:10 Binding -$600 Ratchet #1 Keep same curve; no breaches but max |SP| in previous 6 intervals ($900) is still > $750 (Base's first penalty)
1:15 Binding -$600 Base Curve Ratchet down one curve; no breaches and max |SP| in previous 6 intervals ($600) is still < $750 (Base's first penalty)
1:20 Binding -$600 Base Curve
Southwest Power Pool, Inc.
2017 SPP Annual VRL Analysis 18
SENSITIVITY ANALYSIS RESULTS Performance of the various VRL block sensitivities and methods was primarily analyzed in terms of
total number of breaching flowgate instances and system-level pricing and cost indicators. These
primary indicators are:
Total number of breach instances in the RTBM solutions
Average Marginal Energy Cost (MEC)
Total Intervals with AS Scarcity
Average Operating Cost (Total fuel/offer cost per interval of energy and ancillary services)
Average Settlement Cost (Total cost to be payed to resources based on DispatchMW * LMP + ReservesClearedMW * MCP)
Table 8: Sensitivity Key Indicators
SENSITIVITY AVERAGE
MEC
AVERAGE OPERATING
COST
AVERAGE SETTLEMENT
COST
TOTAL BREACH
INSTANCES
TOTAL AS SCARCE
INTERVALS
Old Curve $21.89 $19,066 $49,025 3708 23
kV Method $21.94 $19,073 $49,122 3370 23
Base $22.18 $19,076 $49,675 3236 23
Ratchet Method
$22.86 $19,113 $51,032 2667 26
The trends are relatively clear, especially when shown on a scatter plot (Figure 13). The tradeoff
between increased reliability (reduced breach events) and cost (system MEC and Settlement Cost)
are apparent, as the individual points appear to form a curve. An optimum VRL setting would most
likely move to the left on this scatter chart (and down as well), where we could see reduced breach
instances with no increase (potentially even a decrease) to system costs. The kV Method seems to
have taken the largest step in this direction, based on the Old Curve sensitivity.
Figure 13: Key Performance Indicators of VRL Sensitivities
Old
Curve
kV
Method
Base/
Current
Ratchet
Method
$48,500
$49,000
$49,500
$50,000
$50,500
$51,000
$51,500
$21.80
$22.00
$22.20
$22.40
$22.60
$22.80
$23.00
2,500 3,000 3,500 4,000Total Breach Instances
Av
era
ge
Se
ttle
me
nt
Co
st
Av
era
ge
ME
C
VRL Sensitivity Key Performance Indicators
Average MEC Average Settlement Cost
Southwest Power Pool, Inc.
2017 SPP Annual VRL Analysis 19
The first set of values above are only averages and counts for the entire 2-week sensitivity time
span. These can show patterns overall, but there are also times when individual intervals,
constraints, and even days do not exhibit the same behavior among sensitivities as the overall
averages.
For instance, Figure 14 illustrates the comparison of total settlement cost of each sensitivity,
broken out by day, and scaled as a percentage of the largest settlement cost for that day. An
example would be 6/22/2017, which shows the Ratchet Method with the highest total settlement
cost where it is assigned a value in this chart of 100%. The other sensitivities are assigned values
indicating their daily settlement cost as a percent of the highest peak daily settlement cost (Ratchet
Method’s);“Base” shows up at 97%, “kV Method” shows as 89% and “Old Curve” shows up as 92%.
Even when stepped back one level (from the 2-week look to the daily look), the averages somewhat
break down as the complexity of each set of constraints and the day’s events illicit different relative
standings between the VRL methodologies. The differences are even more varied when looked at
by constraint or interval.
Figure 14: Daily Settlement Cost comparison of VRL Sensitivities
Overall, relative to the Base/Current VRL blocks:
Ratchet Method performed the most reliably, resulting in a 17% reduction in breach instances with an increase in MEC and Settlement cost around +3%
kV Method showed an increase of breach instances by 4% with a -1% change to MEC and settlement cost
Old Curve demonstrated an increase of breach instances by 14%, with a cost savings slightly better than the kV Method (still rounding to -1% changes)
60%
65%
70%
75%
80%
85%
90%
95%
100%
% o
f D
ay
's P
ea
k S
ett
lem
en
t C
ost
Se
nsi
tiv
ity
Daily Total Settlement Cost by Sensitivity
as % of Peak Daily Settlement Cost
Base kV Method Old Curve Ratchet Method
Southwest Power Pool, Inc.
2017 SPP Annual VRL Analysis 20
The individual sensitivities show what drove poor performance in some of the sensitivities.
The Ratchet Method showed quite a high percentage (Figure 15) of breach instances even when
moved all the way up to the Ratchet #3 block ($1,500 shadow price for any breach). This indicates
there may not have been sufficient relief available during these times and ratcheting up the VRL
blocks only served to increase system costs which still breached during 60% of those occurrences.
Figure 15: Daily Settlement Cost comparison of VRL Sensitivities
The kV Method results showed some improvement in the percentage of congested intervals that
breached. When comparing the Base to the kV Method in Figure 16, a slightly smoothing effect and
more consistent performance across all kV levels is illustrated. The 230kV and 345kV constraints
experienced more breaches compared to the Base, despite having historically seen the least
breaches. The reverse was true of 69kV and 161kV constraints, which saw a reduction in breach
instances in the kV Method, yet had been historically some of the most frequently breaching.
Figure 16: Binding and Breaching Percentages by kV Level
10291714 413
770
272 179 132
1088
0%
20%
40%
60%
80%
100%
Base Curve Ratchet #1 Ratchet #2 Ratchet #3
% o
f C
on
ge
ste
d I
nte
rva
ls
Ratchet Method - Binding/Breached share of each ratchet step
Binding Breached
0%10%20%30%40%50%60%70%80%90%
100%
Ba
se
kV
Me
tho
d
Ba
se
kV
Me
tho
d
Ba
se
kV
Me
tho
d
Ba
se
kV
Me
tho
d
Ba
se
kV
Me
tho
d
Ba
se
kV
Me
tho
d
115kV 138kV 161kV 230kV 345kV 69kV
% o
f C
on
ge
ste
d I
nte
rva
ls
kV Method - Binding/Breached share for each kV level
Breached
Binding
Southwest Power Pool, Inc.
2017 SPP Annual VRL Analysis 21
Breaking down the kV Method a bit more in Figure 17, the approximate trade-offs at each kV level
for the average Shadow Price (gold bars) when congested vs the total number of breach instances
(red markers) is shown.
Figure 17: Breakdown of kV Method congestion metrics
-$97 -$99
-$291 -$283-$255 -$261
-$221-$257
-$88 -$80
-$145 -$127
132 107
12001280
381 385 426 405
79 12321
730
200
400
600
800
1000
1200
1400
-$350
-$300
-$250
-$200
-$150
-$100
-$50
$0
Base
kV
Method Base
kV
Method Base
kV
Method Base
kV
Method Base
kV
Method Base
kV
Method
69kV 115kV 138kV 161kV 230kV 345kV
# o
f B
rea
ch
In
sta
nc
es
Av
g C
on
ge
ste
d S
ha
do
w P
ric
e
kV Method - Breach Instances and Avg Congested Shadow Prices
Avg Congested Shadow Price Breach Instances
Southwest Power Pool, Inc.
2017 SPP Annual VRL Analysis 22
CONCLUSION
Based on the sensitivity analysis presented in this report, SPP does not recommend making changes
to the VRL blocks for Operational Constraints. The sensitivities analyzed, while showing differing
values from each approach, do not indicate a clear need to change or a better method at this time.
The Ratchet Method showed promise in its ability to provide a substantial reduction in breach
instances, but it provided those at the highest cost of any of the sensitivities analyzed. It does
appear that some of that additional cost could be avoided if the method could be further tuned to
not have as many breach events in the Ratchet #3 block.
The kV Method did provide more consistent performance across all kV level constraints than the
current Base VRL blocks as well as show the best trade-off between reduced breaching instances
with little additional cost. However, the method tested still allowed more breaches than the Base
VRL blocks, so the VRL blocks set for the kV levels may not be ideal.
The Old Curve ($500, $750, $1000, $1250, $1500 blocks) that was active until 3/6/2017
demonstrated a large increase in breach occurrences without much cost reduction. This analysis
did help further validate the move from using the Old Curve to the new Base Curve (starting at
$750).
SPP still believes further changes to the Operational Constraint VRLs may be warranted and will
continue analysis to identify improvements to reduce the large number of breach instances.
Southwest Power Pool, Inc.
2017 SPP Annual VRL Analysis 23
APPENDIX
EXPLANATION OF M2M BREACHED INTERVALS M2M breaches are times when the constraint was reported as breached in the solution, but the
Penalty value it breached at was less than $750 (which is currently SPP’s first VRL block).
These instances are part of the design of Market-to-Market (M2M) flowgate coordination. When
SPP is the Non-Monitoring RTO (NMRTO) on an M2M flowgate, the maximum Shadow Price that
SPP will use in achieving its relief on the constraint is the Shadow Price of the Monitoring RTO
(MRTO) of the constraint. An explanation of this logic is contained in Section 3.1 and Section 7 of
the MISO-SPP Joint Operating Agreement, Attachment 2.
In normal M2M flowgate coordination, when the Monitoring RTO is congested on its flowgate, it will
calculate a relief request to send to the NMRTO in real-time. The NMRTO is to activate this
constraint in its dispatch system to meet the relief request until either of these conditions is met:
The Non-Monitoring RTO has provided the relief requested by the Monitoring RTO
The Non-Monitoring RTO has provided relief at a cost as high as the current Shadow Price
from the Monitoring RTO.
In the case where SPP is the NMRTO and the MRTO has the flowgate under control at a low Shadow
Price (such as $-30), the MRTO will send a relief request amount to SPP and SPP will attempt to
bind to meet the relief request. The Shadow Price of the MRTO will replace the VRL blocks of SPP,
such that $-30 is the largest magnitude Shadow Price SPP can be constrained on before it relaxes
the constraint limit in its solution. If SPP is able to meet the relief request at a Shadow Price
magnitude less than that of the MRTO, then the constraint is reported as binding in SPP’s RTBM
solution. However, when the MRTO has a low Shadow Price (such as the $-30), SPP may not be able
to bind to meet the relief request and the constraint will be reported as breached in SPP’s RTBM
solution. The “breach” events are not the same as a typical interval “breached” constraint for SPP, so
it creates a reporting/consistency issue. In order to help mitigate this, we consider those
constraints where SPP is breaching a flowgate in RTBM at a Penalty Value less than SPP’s first VRL
block ($750), to be “M2M breached” and those instances are excluded from most analysis on
breached intervals in RTBM.
Southwest Power Pool, Inc.
2017 SPP Annual VRL Analysis 24
IMPACT OF KV LEVEL TO SHADOW PRICES AND CONGESTION COST This is additional information from the 2016 VRL Analysis demonstrating the application of the OC
VRLs in the SPP Integrated Marketplace, as well as a further breakdown of congestion by kV level of
the monitored element. The primary focus of the data was be on the period July 2015 – June 2016,
for RTBM data. Due to constraint performance and shift factor behavior, flowgates with
transformers are grouped based on the kV level of the low-side of the transformer.
COST OF CONGESTION
Another indicator for the breach instances is the cost of congestion. Because of data reporting and
storage sizing issues, SPP cannot fully or easily recalculate the total cost of congestion for every
flowgate for every interval, however, approximations can be made with the available shift factor
and Shadow Price data. The cost of congestion as shown below is calculated as:
𝐶𝑜𝑠𝑡 𝐶𝑜𝑛𝑔𝑒𝑠𝑡𝑖𝑜𝑛𝐹𝐺 = ∑(𝐿𝑑𝐿𝐴) ∙ (𝑆𝑃𝐹𝐺) ∙ (𝑆𝐹𝐿𝐴,𝐹𝐺) − (𝐺𝑛𝑅𝐴) ∙ (𝑆𝑃𝐹𝐺) ∙ (𝑆𝐹𝑅𝐴,𝐹𝐺)
Where
LdLA = Estimated MWhr Load at Aggregate Load Location
SPFG = Shadow Price of flowgate FG
SFLA,FG = Shift factor of Load Aggregate LA on flowgate FG
GnRA = Estimated MWhr Generation at Resource Aggregate Location
SFRA,FG = Shift Factor of
This is essentially calculating the MCC for each aggregate Settlement Location and calculating the
cost based on the estimated MWhr of the Settlement Location for that instance. The generation
value has to be subtracted due to the reversal of polarity of generation (injecting) to load
(withdrawing). Because shift factors are gathered from the aggregate locations, there is potential
for the load costs to be less accurate due to reducing the granularity, where the true cost born by a
handful of loads in an aggregate may not necessarily equal the calculated cost of the aggregate itself.
Looking at the chart below showing the calculation for the entire year, SPP sees that it follows
roughly with DAMKT congestion, with a bit higher congestion costs per month.
$0
$10
$20
$30
$40
$50
$M
illio
n
RTBM Estimated Cost of Congestion (July 2015 - June 2016)
Southwest Power Pool, Inc.
2017 SPP Annual VRL Analysis 25
The second chart below shows this average cost, by kV level of the flowgate and Shadow Price for
breached instances (excludes M2M breaches).
While the lack of sample data at the higher kVs + higher Shadow Price makes the far right of the
chart look a bit messy (we very rarely breach 230kV and 345kV flowgates over $1,000), the trend is
clear: within the same Shadow Price levels, the lower the kV level of a flowgate, the lower the total
cost of congestion. The same effect can be observed with binding constraints (below).
$0
$20,000
$40,000
$60,000
$80,000
$100,000
$120,000
$140,000
Co
nge
stio
n C
ost
per
inst
ance
Shadow Price > $Bucket
Estimated Average Congestion Cost by Shadow Price Level and kV Level(Breached Flowgates, July 2015 - June 2016)
69kV 115kV 138kV 161kV 230kV 345kV
$0$2,000$4,000$6,000$8,000
$10,000$12,000$14,000$16,000$18,000
$0 $100 $200 $300 $400
Co
nge
stio
n C
ost
per
inst
ance
Shadow Price > $Bucket
Estimated Average Congestion Cost by Shadow Price Level and kV Level(Binding Flowgates, July 2015 - June 2016)
69kV 115kV 138kV 161kV 230kV 345kV
Southwest Power Pool, Inc.
2017 SPP Annual VRL Analysis 26
IMPACT OF EXTERNAL/PARALLEL FLOWS
These trends from the previous section make sense intuitively, as generation and load tend to have
higher per-MW shift factors on higher-kV constraints. It may be noticed that the 161kV constraints
seem to be out-of-order in this regard, sitting between the 115kV and 138kV constraints, rather
than 138kV and 230kV constraints as would be expected. This can be explained primarily by
looking at where the 161kV constraints are located. Most of the 161kV transmission system in SPP
is in Missouri, NW Arkansas, and eastern Nebraska – all areas heavily impacted by external entities.
These constraints have less flow attributed to SPP, and thus have less impacts that can be both
dispatched with (so Shadow Price is higher) and assign congestion cost to (so congestion cost will
be lower). The two charts below help illustrate this. The first chart shows the impacted load (had a
shift factor reported for it on the constraint) by kV level and Shadow Price. You can see the higher
kV flowgates (230kV and 345kV) impact much more load and the 161kV constraints impact far less
SPP load proportionally compared to the other kVs. Part of this is also due to the usage of
aggregates for the load impact estimation, and that can be seen with the 69kV constraints, who
have a larger load impact than would be expected.
0
5,000
10,000
15,000
20,000
25,000
30,000
Avg
Imp
acte
d L
oad
MW
Shadow Price > $Bucket
Average Amount of SPP Load (MW) Impacted by constraintby Shadow Price Level and kV Level (July 2015 - June 2016)
69kV 115kV 138kV 161kV 230kV 345kV
Southwest Power Pool, Inc.
2017 SPP Annual VRL Analysis 27
Finally, the percent of occurrences of each VRL block by kV level are shown below, with the average
percent of external/parallel flow impacts overlaid with a red line. The VRL blocks are shown as the
next level that would be applied, so the $500 VRL block is an indication that the constraint was
binding. Note that the kV levels that have the most proportional occurrences of non-binding
intervals (VRL >$500) are the 69kV and 161kV constraints, which also have the highest average
parallel flow impact. This helps to further explain the complexity of congestion costs and Shadow
Prices for constraints, and to illustrate why, though kV level is a significant indicator of congestion
costs and Shadow Prices, it does not fully encompass the other aspects of a flowgate’s congestion.
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
69kV 115kV 138kV 161kV 230kV 345kV
Flowgate kV Level
SPP Internal Flowgate Occurrence of VRL Block in RTBM, by kV Level
$500 $750 $1,000 $1,250 1500 Avg % External Flows
Southwest Power Pool, Inc.
2017 SPP Annual VRL Analysis 28
DETERMINATION OF KV METHOD VRL BLOCKS The VRL block settings for each kV level in use by the kV Method were determined with the process
below. Historical data was used to help estimate these, pulling all congested (binding or breached)
flowgates in RTBM between 10/1/15 and 4/1/17, internal flowgates only.
69kV 115kV 138kV 161KV 230kV 345kV
If VRL passed,
relax limit to
First Block $1,000 $600 $750 $1,000 $300 $300 101%
$1,250 $800 $938 $1,250 $525 $475 102%
$1,500 $1,000 $1,125 $1,500 $750 $650 103%
$1,750 $1,200 $1,313 $1,750 $975 $825 104%
Last Block $2,000 $1,400 $1,500 $2,000 $1,200 $1,000 105%
Then then data was broken into percentiles of shadow price for each kV level. Though the data was
not a normal distribution, the standard deviation points for that distribution type were used to
provide approximate minimum and maximum percentile bands for the block setting. The first
block for each kV was to be roughly the 2-sigma point (95.45 percentile). The setting of the last
block was determined by taking the higher of 2*first block or the 3-sigma point (99.73
percentile). This higher-of logic was used to ensure we were not just capping to our old VRL blocks
of $1,500 (because for 69kV and 161kV especially, we hit $1,500 shadow more frequently than
others). So a max of $1,500 may not be the ideal last breakpoint for the VRL blocks that we
need. All of this was to provide good starting points for kV-based VRL blocks using some standard
statistical values combined with general experiential knowledge.
The data from the October 2015 – March 2017 period are shown below, with starting points for
high and low blocks highlighted in the bold rows.
69 115 138 161 230 345
50.00% $111 $48 $96 $84 $34 $44
75.00% $375 $141 $324 $372 $93 $117
90.00% $636 $391 $567 $740 $192 $236
95.00% $1,000 $554 $748 $1,000 $277 $301
95.45% $1,057 $589 $750 $1,050 $298 $310
96.00% $1,150 $639 $795 $1,134 $336 $324
97.00% $1,255 $733 $898 $1,236 $427 $360
98.00% $1,401 $860 $998 $1,338 $500 $463
99.00% $1,488 $1,100 $1,237 $1,462 $750 $580
99.50% $1,495 $1,292 $1,401 $1,492 $1,000 $754
99.73% $1,498 $1,415 $1,476 $1,498 $1,245 $1,087
99.90% $1,500 $1,484 $1,498 $1,500 $1,442 $1,427
Southwest Power Pool, Inc.
2017 SPP Annual VRL Analysis 29
Below are two examples of how this initial data was transformed into the VRL blocks used in the kV
Method sensitivity:
69kV o First block was 2-sigma point of $1,057, so it was rounded to $1,000 o 2*first block = 2*1000 = $2,000 o 3-sigma point was $1,498 o Last block was max of $2,000 or $1,498 = $2,000. o For 69kV, the first block is $1,000, last block is $2,000, and the intermediate blocks
are scaled linear in-between 230kV
o First block was 2-sigma point of $298, so it was rounded to $300 o 2*first block = 2*300 = $600 o 3-sigma point was $1,245 o Last block was max of $600 or $1,245 = $1,245. This was rounded to $1,200 o For 230kV, the first block is $300, last block is $1,200, and the intermediate blocks
are scaled linear in-between