2016_City of Dreams Hotel, Macau

  • Upload
    scegts

  • View
    216

  • Download
    0

Embed Size (px)

Citation preview

  • 8/18/2019 2016_City of Dreams Hotel, Macau

    1/12

    56 TheStructuralEngineer

        

    Project focus

    City of DreamsMarch 2016

    Synopsis

    This article describes how cutting-

    edge parametric-based engineering

    techniques have been used to

    achieve the detailed design of 2500

    complex steelwork connections

    for the exoskeleton of the new City

    of Dreams hotel in Macau, China. It

    discusses the tools, methodology and

    strategy employed by the engineering

    team to automate the diffi cult and

    time-consuming process of creating,

     verifying and documenting the

    geometrically challenging, large-scale

    steel connections using finite-

    element methods within an ambitioustimescale of just 12 months.

    City of Dreams, Macau –making the vision viable

    Emidio Piermarini EI, BEng, MEng, Engineer, BuroHappold Hong KongHayden Nuttall MSc, DIC, BEng, CEng, FIStructE, MHKIE, Director, BuroHappold Hong KongRob May CEng, MIStructE, PE, MHKIE, MHKIBIM, Associate Director, BuroHappold BathVictoria M. Janssens PhD, PEng, Senior Structural Engineer, BuroHappold Hong Kong

    IntroductionAn extraordinary building is taking shape

    in the City of Dreams entertainment

    resort in Macau (a Special Administrative

    Region of the People’s Republic of China).

    The 42-floor twin-tower construction

    incorporates an irregular-form, aluminium-

    clad structural exoskeleton with

    connections of such scale and complexity

    that they are possibly the most analytically

    and geometrically challenging large-scale

    steelwork connections ever to be built

    (Figure 1).

    The project for Melco Crown

    Entertainment by Zaha Hadid Architects

    and BuroHappold is under construction

    (Figure 2). When it opens in 2017 it will

    provide the City of Dreams development

    with a dramatic landmark building tocomplement the existing complex of hotels

    Figure 1

    City of Dreamshotel – architect’srendering    Z   A

       H   A   H   A   D   I   D    A

       R   C   H   I   T   E   C   T   S

  • 8/18/2019 2016_City of Dreams Hotel, Macau

    2/12

    57

    www.thestructuralengineer.org

  • 8/18/2019 2016_City of Dreams Hotel, Macau

    3/12

    58 TheStructuralEngineer

        

    Project focus

    and entertainment facilities on the “Cotai

    Strip”. Housed within its 150 000m2 of

    floor space will be a seven-storey atrium,

    780 hotel rooms, suites and villas, various

    restaurants, luxury retail outlets, gaming

    and event facilities, and a sky pool.

    BuroHappold carried out the general

    structural design of the building, together

    with the detailed design and construction

    documentation of all the steelwork

    connections. The structural design work

    faced engineering challenges arising from

    the typhoon wind climate, seismic design

    requirements, complex load paths and

    highly irregular geometry of the building,

    but it is the uniquely complex problem of

    the detailed design and documentation of

    the thousands of dissimilar and irregular

    steelwork connections of the exoskeleton

    – and the innovative methodology used

    to solve it – that are the subject of this

    article.

    StructureThe design concept for the City of Dreams

    hotel is of a striking exoskeleton which

    wraps around the two concrete cores,

    bringing them together with a flowing mid-

    section featuring three irregular-shaped

    curved openings. Inside the building, the

    free-form steel framework continues,

    curving high above a huge atrium space

    that is echoed by that of the sky poolabove.

    Figure 2City of Dreams hotel –current progress (January 2016)

     Figure 3Structural system

    b) Exoskeleton

    c) Total system

    City of DreamsMarch 2016

    a) Concrete cores

    In structural terms, the steel exoskeleton

    and the two internal concrete cores act

    together to provide lateral load resistance,

    sharing wind and seismic loads in

    proportion to stiffness. The gravity system

    comprises composite beams and slabs

    that span between the exoskeleton and the

    cores with minimal internal columns (Figure

    3).

    There are approximately 2500

    connections in the exoskeleton. The

    members and connections are fabricated

    from steel plate up to 150mm thick

    using grades up to S460. Many of the

    connections incorporate “offshore-quality”

    plate to BS EN 102251 in order to ensure

    adequate ductility and strength in the

    through-thickness direction. Members are

    generally bolted together at connections

    in the flat regions and site-welded in the

    free-form central zone and the corner fillets

    (Figure 4).

    Methodology With such complex and irregular geometry

    it was clear from the outset that traditional

    code-based methods and standard

    drawing software would not be suffi cient

    to design and document the exoskeleton

    connections. Instead, the BuroHappold

    team decided that the complex stress

    states that exist where members merge

    into the connections meant that finite-element (FE) analysis was the only viable

    option to verify their structural adequacy.

    It was also clear that standard software

    packages would not have the functionality

    required to create the constructiondocumentation, especially for the free-

       V   A   D   I   M    I

       S   M   A   G   I   L   O   V

  • 8/18/2019 2016_City of Dreams Hotel, Macau

    4/12

    59

    www.thestructuralengineer.org

    form central region.

    To complicate matters further, since the

    exoskeleton would be clad in aluminium,

    all connections and associated plates

    and bolts would have to be located

    within the cladding zone defined by the

    architect. This would inevitably constrain

    and limit options for the geometry of the

    connections and necessitate non-planar

    solutions.

    Finally, the timescale for detailed

    design and documentation of all 2500

    exoskeleton connections was just 12

    months. Put another way, the team would

    need to complete an average of 50

    connections per week.

    In response to this seemingly impossible

    task, BuroHappold drew on its expertise

    in parametric engineering and structural

    optimisation developed on previous

    projects, including the Aviva Stadium in

    Dublin, Ireland2, and the Louvre Museum

    in Abu Dhabi, United Arab Emirates3.

    Essentially, the team’s solution was to

    create a unique, bespoke computational

    approach using application programming

    interface (API) techniques to allow

    effi cient processing of the huge number

    of FE models required and, critically,corresponding three-dimensional

    Input Parameters

    (variables)

    Grasshopper

    Definition/Script

    Output Model

    Viewed In Rhino 3D

     Figure 5Parametric definitions using Grasshopper visual programming for Rhino 3D Figure 4Zones of exoskeleton  Figure 6Design process

    (3D) visualisation of every connection

    throughout. The approach allowed the

    engineering team to focus on the quality

    of the engineering solution, rather than on

    cumbersome data handling and repetitive

    number-crunching tasks, resulting in

    significantly faster and reliable output. As

    a result, the entire detailed design and

    documentation process was completed on

    schedule, in a fraction of the time that the

    team estimated would have been required

    using a more conventional methodology.

    Tools

    Parametric design is a process in which

    problem parameters are defined as

    variables and a series of functions applied

    in order to find the solution(s). By varying

    these parameters, many variations of

    the same problem can be solved. In this

    case, the problem was FE analysis of the

    many and various steel connections in the

    exoskeleton.

    The modelling software Rhinoceros

    3D (Rhino 3D)4 and its plug-in module

    Grasshopper5 were chosen as parametric

    design tools for the speed and accuracy

    they would bring to the task.

    The combination allowed the team tocreate the geometry for a large number of

    complex 3D forms quickly and accurately

    using visual programming techniques and,

    crucially, to make changes to the geometry

    by changing the parameters (Figure 5).

    They could literally “see what they were

    doing” in each step of the programming

    logic and in the corresponding geometry

    as it was being created, making the code

    debugging process much easier and

    quicker than it would have been using

    traditional practices.

    Rhino 3D was also used to model

    the outer surface geometry as a clash-

    detection study to show that the

    connections were within the cladding

    zone. Autodesk’s Robot Structural Analysis

    (RSA)6 software was used to create

    the local FE models for each unique

    connection type.

    In this context, it is worth noting that

    the size and complexity of the structure

    meant that the global analysis model for

    the building, which was created using

    MIDAS structural analysis software7, took

    over 12 hours to run. Hence, it was not

    viable to create and insert FE models of

    all the connections into the global model,

    as this would have increased the analysis

    time even further, possibly by three or fourtimes. Similarly, if the models were inserted

  • 8/18/2019 2016_City of Dreams Hotel, Macau

    5/12

    60 TheStructuralEngineer

        

    Project focus

    one at a time, there would be at least a

    12-hour wait each time the team wanted to

    investigate alternative arrangements for a

    connection. The only practical alternativewas to create separate “local” FE models

    of the connections and transfer, or map,

    onto them the corresponding moments and

    forces from the global model results file,

    for all 105 load combinations.

    To maintain the t ight programme, almost

    every aspect of the local model generation

    and analysis was automated using bespoke

    Visual Basic scripts that linked MIDAS,

    RSA and Excel with Grasshopper via their

    APIs.

    In achieving the solution to this

    ambitious project, the BuroHappold

    engineering team found themselves at the

    cutting edge, using the software in ways

    that had not been done before, sometimes

    working at the limits of the products’

    capabilities. The team maintained frequent

    dialogue with all the software companies’

    technical support teams throughout, which

    proved to be highly productive for both

    parties.

    Strategy The engineering team’s strategy was to break

    this immense problem into five key steps

    (Figure 6). The first four months of the project

    were spent developing bespoke Grasshopper

    scripts for every step. This significant time

    investment was justified many times over by

    the huge time saving made in the subsequent

    analyses and generation of documentation.

    It is important to understand that bespoke

    programming, however skilled it might be, does

    not replace engineering expertise. Rather,

    it augments it by handling large amounts of

    data effi ciently and releasing engineers to

    focus on optimising the design. Accordingly,

    visualisation, manual verification and

     Figure 8Visualisation of data for similar connections

     Figure 9Developingconnectionarrangement

    City of DreamsMarch 2016

    a) b) c)

       R   U   P   E   R   T

       I   N   M   A   N

     Figure 7Grasshopper script to identify similar connections

  • 8/18/2019 2016_City of Dreams Hotel, Macau

    6/12

    61

    www.thestructuralengineer.org

    b)

    acceptance were considered essential and

    built into the process throughout.

    The five steps were:

    1. Identify similar connections

    2. Develop the connection arrangement3. Find and map forces from global analysis

    model

    4. Analyse the connection

    5. Generate analysis reports and construction

    documents

    Step 1: Identify similar connections

    The first task was to confirm the number

    of unique connection types required by

    identifying those that were similar, in order to

    reduce fabrication and erection time. With up

    to nine elements connecting at each node,

    and each element potentially having a different

    section shape, section size and/or curvature,

    this was not an easy task.

    To identify unique connection types, a

    Grasshopper script was written to interrogate

    the exoskeleton member geometry Rhino

    3D file created previously to help build the

    global structural analysis model. It contained

    the member centreline geometry and the

    associated section shapes and sizes.

    The script was used to search this file for

    all intersections of centrelines (to locate the

    connections) and to collect and organise the

    relevant geometric data, such as the number

    of intersecting members, whether members

    are straight or curved, the member shapes

    and sizes and the angles between adjacent

    members. Thus organised into a programming

    library, the data could be easily and accurately

    compared to determine similarity of the

    intersections, allowing for cases where the

    geometry is handed (Figure 7).

    Once the unique connection types had

    been identified, the script visualised the

    geometric data from the Rhino 3D file,

    allowing the team to verify the similar

    connection information easily (Figure 8). From

    a total number of over 2500 connections, this

    reduced the number of unique types to about

    400.

    Step 2: Develop the connection arrangement

    Next, the principles of the connection weredeveloped through engineering judgement

    based on the load paths (Figure 9a) and a

    Grasshopper script was created to allow the

    designer to rapidly conceive a connection’s

    geometry to meet architectural and fabrication

    constraints before sending the connection to

    be analysed.

    Mindful of the fabrication and erection

    challenges that such massive connection

    nodes would present, 3D study models of

    each connection were created using Rhino

    3D to ensure that the connections could be

    readily fabricated. The models show the “plate-

    by-plate” fabrication sequence for appropriate

    clearance at every stage, including edge

    distance tolerances and room for site welding,

    testing and bolt tightening (Fig. 9b).

    The connection designs also had to

    accommodate extraordinary architectural

    constraints. Zaha Hadid Architects had

    provided a Rhino 3D model of the inner

    surface of the cladding zone that all the steel

    elements and connections had to fit inside(Figure 10a). For simpler connections, with

    little or no curvature, the connections and

    associated plates and bolts were similar in size

    to the steel elements; therefore, clashes were

    relatively easy to manage. However, in the free-

    form central zone, multiple members typically

    meet with high curvature, leading to complex

    intersections (Fig. 10b). For this reason, the

    connections are necessarily significantly

    larger than the individual members. Given the

    architectural envelope was not only tight but

    also varied in depth where it was in double

    curvature or warped, clashes were a real

    possibility (Fig. 10c).

    Since the constraints of fabrication

    would often oppose those presented by

    the architecture, the team realised that

     Figure 10Workingwith architecturalenvelope

    a)

    c)

  • 8/18/2019 2016_City of Dreams Hotel, Macau

    7/12

    62 TheStructuralEngineer

        

    Project focus

    applying them to the local connection

    models was significant. Once again,

    Grasshopper’s capability as a tool

    for creating and visualising geometry

    offered a number of benefits in terms of

    speed and reliability.

    With a script similar to that used in

    Step 1 to identify unique connections,

    data including connection geometry,

    bar/node numbering, section sizes and

    member orientations were transferred

    to Grasshopper from the global analysis

    model and mapped for each connection

    under consideration (Figure 13). The

    corresponding forces/moments were

    then also extracted. The volume of

    data this created was so large that it

    was split into 55 separate files, each

    containing up to five million sets of bar

    forces/moments.

    The bespoke scripts allowed

    designers to search for any set of

    forces/moments from the entire data

    set and instantly visualise them on

    screen. In-built vector transformation

    tools could then be used to map the

    forces/moments onto the local model.

    The task would have been much more

    diffi cult and time-consuming without the

    powerful visualisation functionality that

    Grasshopper provides, allowing as it did

    for “visual debugging” of the script.

    Even with Grasshopper’s power

    vector tools, mapping and translation of

    the forces/moments from multiple files

    was susceptible to error, so the team

    used a two-step verification process

    comprising visual and numerical checks

    to ensure the extracted data were

    correct (Figure 14).

    For the visual check, the connectionwas displayed in 3D together with

    multiple connections. These allowed parts

    of the parametric scripts for one unique

    connection to be copied or developed for

    application to others.

    For example, as a general design

    principle, a 25mm edge distance tolerance

    was allowed for members being site-

    welded to the connections, to account for

    erection tolerances. However, increasing

    the thickness of a connection node in

    order to maximise edge distance for

    site welds would make it more likely that

    the connection would clash with the

    architectural envelope. In order to

    explore this, the thickness was

    defined as a parameter within the

    Grasshopper script. The value

    could then be adjusted until the

    edge distance tolerance of 25mm

    was achieved.

    Thanks to Grasshopper’s

    powerful visualisation, all these

    changes occurred graphically and

    in real time as the designer moved

    the slider value up and down

    (Figure 12). If the 25mm tolerance

    could not be achieved because

    of a clash with the architectural

    envelope (as in the example

    shown), the designer could rapidly

    determine what value would

    optimise the edge distance while

    remaining within the architectural

    envelope.

    Step 3. Find and map forces from

    global analysis model

    With 105 load combinations and

    up to nine members in a single

    connection, the process of finding

    the correct forces/moments inthe global model and correctly

    finding an optimal solution meant being

    able to explore the design space for

    each connection rapidly. To address this,

    BuroHappold engineers programmed the

    geometry of each connection using a

    parametric script with variables defined

    for all dimensions that were likely to

    need further study to meet architectural,

    fabrication and construction constraints

    (Figure 11). The more complex the

    geometry of the connection, the more

    complex the parametric script became, but

    some guiding principles were common to

     Figure 11Parametric connection definition and fabrication connection

     Figure 13Global analysis model

    City of DreamsMarch 2016

       R   U   P   E   R   T   I   N   M   A   N

  • 8/18/2019 2016_City of Dreams Hotel, Macau

    8/12

    63

    www.thestructuralengineer.org

    vectors showing the magnitude and

    direction of the applied forces/moments.

    This quickly displayed any missing data

    and verified that the forces were acting in

    the correct direction. Additional analytical

    information from the global model, such

    as bar/node numbers, section properties,

    gamma angles and local axes, could

    be displayed as well to ensure proper

    mapping of bar information.

    For numerical verification, an

    equilibrium check was performed for all

    load combinations to ensure no “out-of-

    balance” forces/moments existed. Any

    questionable load combinations or nodes

    were then displayed graphically and further

    interrogated.

    Step 4: Analyse the connection

    The accurate prediction of the resultant

    stresses where multiple members intersect

    was a major concern. Consideration

    of even a simple cruciform example

    illustrates the importance of accurately

    predicting stresses where members merge

    (Figure 15). At the start of the project, the

    BuroHappold team had determined that

    neither established code-based methods

    nor bespoke first-principles methods

    would readily capture the complex stress

    states that exist in the many and varied

    connections of the exoskeleton where

    individual plates intersect and overlap,

    especially in locations where multiple

    plates up to 750mm wide merged into

    a single plate. Given the geometric

    complexity and sheer size of the

    connection nodes, an FE approach was

    the only viable method for verifying the

    adequacy of the connections.

    Almost every step of the connectionanalysis process was semi-automated

     Figure 12Using parametric definition to meet multiple constraints

     Figure 14Visualisation and numerical check of mapped forces

  • 8/18/2019 2016_City of Dreams Hotel, Macau

    9/12

    64 TheStructuralEngineer

        

    Project focus

    to reduce set-up and processing time,

    using bespoke scripts to link the various

    software programs to Grasshopper though

    their APIs. The scripts were used to

     

    • generate the local FE model

     • add extension bars and apply the forces

     

    • apply analytical links and boundary

    conditions

     • run the analysis and extract results

    At every stage, the engineer could

    employ visual checks to ensure the correct

    data were being used. Once the scripts

    had been created, these local analysis

    models took just a few minutes to run

    (compared to 12 hours for the global

    analysis using MIDAS), allowing the team

    to run them as many times as they needed

    to, in order to match plates’ thicknesses to

    stress levels and optimise the connections.

    The FE models were based on 2D shell

    elements that incorporated all plates in the

    connection together with an appropriate

    portion of the incoming members. Beyond

    this, bar elements were added to match

    those in the global model and the mapped

    forces/moments from the global model

    were applied to these. Since the geometry

    and the forces/moments in the local and

    global models should match, it was easy

    to check these visually and numerically

    against one another.

    The first step was to generate the local

    analytical model in RSA (Figure 16). Thescript first created a Rhino 3D model of 2D

    surfaces at the centre of the plates, which

    could be planar or curved, and converted

    these surfaces into RSA objects. It then

    asked RSA to create the FE mesh of 2D

    shell elements from these objects. Since

    the FE mesh would be generated inside

    RSA, the geometry of the surfaces created

    in Rhino 3D needed to be of suffi cient

    accuracy to avoid meshing problems,

    which can occur when the meshing

    algorithms cannot determine the intended

    common boundary between adjacent

    surfaces. Since the Rhino 3D geometry

    was defined parametrically, the overall

    geometry could be altered as necessary

    until the connection was optimised and

    the various fabrication/architectural

    constraints had been met.

    Once the 2D shell elements were

    generated, the script automatically added

    the bar elements to the model. The bar

    geometry was extracted directly from the

    global analysis model and placed in the

    same virtual position in the local model.

    As the bar forces had been mapped

    inside Grasshopper, and the bar numbers

    generated in the local model matched

    the global model, the load combinations

    and bar forces/moments could beautomatically applied using Grasshopper.

    This again mitigated errors associated

    with manual processes such as copy and

    pasting tabulated data.

    Under a conventional approach, the

    definition of the analytical links between

    the bars and the shell elements in RSA,

    and the definition of boundary conditions

    (analytical supports) would both have

    been time-consuming manual operations.

    Here, they were both scripted to happen

    automatically, saving considerable time

    for the project. The nodes of the FE mesh

    were imported into Grasshopper, which

    applied a script that used geometric

    search algorithms to find the appropriate

    nodes to which the bar elements should

    be connected. This information was then

    sent back to RSA and used to create

    the analytical connections. The script

    also automatically applied the required

    boundary conditions to the local RSA

    model in predetermined locations.

    After the forces/moments for all load

    cases had been applied, the models were

    batch-processed. Finally, the sum of each

    reaction was checked to ensure they all

    equalled zero before the results were

    prepared for extraction.

    To avoid unnecessary handling of largeand cumbersome data files, and to speed

     Figure 15Interaction of in-plane principle stresses and theoreticalvon Mises envelope for simple cruciform connection

     Figure 16Connectionmodel

    a) In Rhino 3D

    b) Connected live to RSA

    City of DreamsMarch 2016

    NB In both cases, the stress levels σ1 and σ2 for the incoming members of the cruciform are set at the yield stress of the material(p

    y). When σ

    1 and σ

    2 are both positive or negative (right-hand case), the maximum stress in the overlapping region does not

    significantly increase. However, when σ1 and σ2 have opposite signs (left-hand case), the maximum stress in the overlappingregion reaches √3 × p

    y. This phenomenon is predicted by inspection of the well-known “von Mises failure envelope”.

  • 8/18/2019 2016_City of Dreams Hotel, Macau

    10/12

    65

    www.thestructuralengineer.org

    up the process, a script was developed to

    extract stresses in batches to determine

    the governing load cases. Stress maps

    of these connections were interrogated

    using a scale based on the maximum plate

    thickness for a given selection of plates

    (Figure 17). The stress maps were then

    visually inspected to establish whether the

    stresses in any areas were unacceptable.

    If necessary, the plates’ thicknesses,

    arrangements or grades were changed andthe whole process re-run until satisfactory

    results were achieved.

    Finally, the results were all individually

    reviewed by BuroHappold engineers as

    part of the verification and acceptance

    process.

    Step 5: Generate analysis reports and

    construction documents

    It was recognised early in the project

    that, given the large number of unique

    nodes, the generation of engineeringdocumentation for each connection

    could be a laborious task. Since all the

    visual data available to the designers

    during the design process were created

    in Grasshopper, the logical solution was

    to transfer this to an Excel template after

    the analysis was complete. By creating a

    tool to automate this task, the team made

    considerable time savings and provided a

    comprehensive visual record of all steps

    of the design process, ensuring that any

    independent party could easily follow the

    assumptions made and data used for the

    design of each connection (Figure 18).

    While documentation was not a primary

    objective of the process, the Grasshopper

    scripts generated rich and coordinated

    data that could be easily extracted to

    provide accurate and relevant information

    for the fabricator.

    After careful consideration of the

    options, it was agreed with the contractor

    that the construction information would

    be issued in the form of 2D drawings for

    the connections in the flat-sided areas

    and curved corners, where the geometry

    could be readily defined using conventional

    drawing software, and as 3D digital models

    for the free-form areas to assist the

    fabricator in understanding the connection

    geometry (Figures 19 and 20).

    This was because the design intent for

    the connections in the free-form area was

    more diffi cult to communicate using 2D

    drawings. Since the 3D information was

    readily available, it seemed illogical to

    convert this to conventional 2D drawings

    that would have required multiple views,

    sections and coordinates to define the

    shape, position and orientation relative to

    the finished structure. Rather, using the

    Rhino 3D surface models that had already

    been created for the clash-detectionstudies, 3D models that were geometrically

     Figure 193D documentation for largestfree-form connection

     Figure 17RSA von Mises stress plot and fabricated connection

     Figure 18Example of calculation output

  • 8/18/2019 2016_City of Dreams Hotel, Macau

    11/12

    66 TheStructuralEngineer

        

    Project focus

     Figure 20Example of complex 3D documentation

    accurate in every sense (plate thickness,

    plate geometry, plate hierarchy at plate

    intersections, actual position/orientation

    in the building) were provided for the

    fabricator, who simply transferred them into

    their own 3D construction model.

    The approach was mutually beneficial

    as it saved time for all parties in what was

    already an aggressive schedule and helped

    to minimise fabrication errors (Figure 21).

    Conclusion

    To meet the aggressive construction

    programme for the City of Dreams

    hotel project, BuroHappold needed to

    develop a state-of-the-art approach to

    the complex design and documentation

    of the exoskeleton connections. Thisinvolved full FE analysis of more than 2500

    connections and 105 load cases. The

    whole process was run using bespoke

    parametric Grasshopper scripts, which

    successfully integrated MIDAS, RSA,

    Rhino 3D and Excel. Due to the number of

    unique arrangements, their highly irregular

    shapes and the complex stress states

    that exist where the members merge, the

    exoskeleton connections are possibly

    the most analytically and geometrically

    challenging large-scale connections of

    any building constructed to date (Figure

    22).

    The Grasshopper scripts not only

    allowed the engineering team to process

    vast amounts of data quickly; importantly,

    they also incorporated “on-screen” visual

    checks at all stages of the process tohelp eliminate errors. The scripts were

    carefully designed to avoid being a so-

    called “black box” set of tools, but rather

    an extension of the engineer’s hand; cutting

    out mundane tasks and allowing more time

    to focus on problem-solving.

    The initial decision to spend the first

    four months of the 12-month programme

    developing the process and writing/testing

    the parametric scripts was a bold one, but

    one which paid off later when some of the

    connections were being created, analysed

    and documented in less than one hour.

    There was inevitably periodic updating

    of the scripts throughout the project,

    but the majority of the development was

    completed in this early stage. Once set up,

    this innovative design approach achieved

    huge savings in man-hours and allowedBuroHappold to consistently deliver ahead

     Figure 213D documentation via digital model and construction

    City of DreamsMarch 2016

    a) Assembly details b) 3D setting-out

  • 8/18/2019 2016_City of Dreams Hotel, Macau

    12/12

    67

    www.thestructuralengineer.org

     

    1 British Standards Institution (2009) BS EN

    10225:2009 Weldable structural steel for fixed

    offshore structures. Technical delivery conditions, 

    London, UK: BSI

    2 Shepherd P. (2011) ‘Aviva Stadium – the use ofparametric modelling in structural design’, The

    Structural Engineer, 89 (3), pp. 28–34

    3 Shrubshall C. and Fisher A. (2011) ‘The practical

    application of structural optimisation in the design

    of the Louvre Abu Dhabi’, Taller, Longer, Lighter:

    Proc. IABSE–IASS Symposium, London, UK, 20–23

    September

    4 Robert McNeel & Associates (2016) Rhinoceros

    References

      3D [Online] Available at: www.rhino3d.com

    (Accessed: January 2016)

    5 Robert McNeel & Associates (2016) Grasshopper  

    [Online] Available at: www.grasshopper3d.com

    (Accessed: January 2016)

    6 Autodesk (2016) Robot Structural Analysis

    Professional  [Online] Available at: www.autodesk.

      co.uk/products/robot-structural-analysisoverview

    (Accessed: January 2016)

    7 MIDAS Engineering Software (2016) midas Gen 

    [Online] Available at: http://en.midasuser.com/

      product/gen_overview.asp (Accessed: January

    2016)

    of schedule.

    Structural engineering in themodern era is challenged by projects

    of increasing complexity, falling fees

    and faster construction programmes.

    The profession will not meet these

    competing challenges successfully

    without harnessing the best available

    technology. The construction industry

    is now largely a “digital” industry, with

    the leading design teams, contractors

    and manufacturers increasingly

    creating and sharing digital information.

    For structural engineers, parametric

    and computational design are the tools

    that will enable them to embrace this

    complexity, avoid getting bogged down

    in ever-increasing amounts of data and

    devote more valuable time to what they

    do best – engineering.

     Figure 22Node fabrication in Guangzhou, China

    ADVERT

     fact 

    A concrete shieldA serious re can damage business. Concrete’s inherent properties

    mean it doesn’t burn or give off noxious fumes. Its slow rate of

    thermal conductivity also provides an effective re shield, protecting

    lives, livelihoods and the environment.

    Choose concrete for built-in re resistance.

    Visit www.concretecentre.com  to nd out more.