2016 Capital Improvement

Program

Geneva City Council Planning Retreat

Session 2

January 29, 2016

Page 2: 2016 Capital Improvement Program - Genevacityofgenevany.com/wp-content/uploads/2016/09/... · 1/29/2016  · Deep Resurfacing— Downtown Streets Project Description Project entails

Start with Why…

• Why should we concern ourselves with capital improvement planning?

• Our WHY suggests that we are seeking to become a community of choice…a premier destination…

• Our HOW suggests that we will invest public resources wisely, and in projects that enhance aesthetics, functionality, and safety of public spaces…

• For operating year 2016, we are proposing $6,180,000 in capital projects to this end

- Uniquely Urban -

Page 3: 2016 Capital Improvement Program - Genevacityofgenevany.com/wp-content/uploads/2016/09/... · 1/29/2016  · Deep Resurfacing— Downtown Streets Project Description Project entails

Public Works

Projects

Page 4: 2016 Capital Improvement Program - Genevacityofgenevany.com/wp-content/uploads/2016/09/... · 1/29/2016  · Deep Resurfacing— Downtown Streets Project Description Project entails

Lochland Road Water Main

Project Description Project entails either replacement or slip-lining of 12” and 20” water main from the main pump station on Route 14 (WTP) to Geneva on the Lake. Where able, mains will be excavated at valves (or every 500’) and injected with liner. In other places, line will be removed and replaced.

Project to Commence: Late Summer/Early Fall

Project Complete: 12/31/2016

Project Funding Mechanism: Bond

Total Project Cost: $3,750,000

Annual Debt Service: $290,000

- Uniquely Urban -

Page 5: 2016 Capital Improvement Program - Genevacityofgenevany.com/wp-content/uploads/2016/09/... · 1/29/2016  · Deep Resurfacing— Downtown Streets Project Description Project entails
Page 6: 2016 Capital Improvement Program - Genevacityofgenevany.com/wp-content/uploads/2016/09/... · 1/29/2016  · Deep Resurfacing— Downtown Streets Project Description Project entails

Deep Resurfacing—Downtown Streets

Project Description Project entails deep mill and pave of South Exchange Street, Elizabeth Blackwell Drive, Scott LaFaro Drive, and Paradise Alley. This includes milling of existing streets and inlay of thermoplastic crosswalks.

Project to Commence: 5/2016

Project Complete: 7/2016

Project Funding Mechanism: Operating Cash (CHIPS)

Total Project Cost: $150,000

Annual Debt Service: $0

- Uniquely Urban -

Page 7: 2016 Capital Improvement Program - Genevacityofgenevany.com/wp-content/uploads/2016/09/... · 1/29/2016  · Deep Resurfacing— Downtown Streets Project Description Project entails

Street Resurfacing—Neighborhood Streets

Project Description Project entails general mill and pave of multiple neighborhood streets, potentially including Sherill Street, Avenues E, F, and G (east of Genesee), Lehigh, Cortland (Monroe to Madison), Monroe, Madison, and Delancey

Project to Commence: 6/2006

Project Complete: 8/2006

Project Funding Mechanism: Operating Cash (CHIPS+)

Total Project Cost: $150,000 ($125,000-CHIPS)

Annual Debt Service: $0

- Uniquely Urban -

Page 8: 2016 Capital Improvement Program - Genevacityofgenevany.com/wp-content/uploads/2016/09/... · 1/29/2016  · Deep Resurfacing— Downtown Streets Project Description Project entails
Page 9: 2016 Capital Improvement Program - Genevacityofgenevany.com/wp-content/uploads/2016/09/... · 1/29/2016  · Deep Resurfacing— Downtown Streets Project Description Project entails

WTP Pump/SCADA Upgrades

Project Description Project entails replacement of two water pumps which will make operations more efficient and improve pressure of supply. Additionally, SCADA upgrades are required for unmanned operation

Project to Commence: Spring (Pumps)/TBD (SCADA)

Project Complete: Fall (Pumps)/TBD (SCADA)

Project Funding Mechanism: Bond

Total Project Cost: $220,000

Annual Debt Service: $17,000

- Uniquely Urban -

Page 10: 2016 Capital Improvement Program - Genevacityofgenevany.com/wp-content/uploads/2016/09/... · 1/29/2016  · Deep Resurfacing— Downtown Streets Project Description Project entails

PSB Plumbing Upgrades

Project Description Project entails replacement of all toilet fixtures in jail cells at the Public Safety Building. Existing fixtures are original and failing, resulting in leaks and back-ups

Project to Commence: Fall

Project Complete: Fall

Project Funding Mechanism: Fund Balance

Total Project Cost: $60,000

Annual Debt Service: $0

- Uniquely Urban -

Page 11: 2016 Capital Improvement Program - Genevacityofgenevany.com/wp-content/uploads/2016/09/... · 1/29/2016  · Deep Resurfacing— Downtown Streets Project Description Project entails

WWTP Facility Improvements

Project Description Project entails replacement of a manually operated lift gate at the Gulvin Plant, which is difficult to operate under hydraulic pressure. It also includes repainting of the Marsh Creek Plant basement and replacement of air conditioning at the plant.

Project to Commence: Spring

Project Complete: Fall

Project Funding Mechanism: Bond

Total Project Cost: $105,000

Annual Debt Service: $8,400

- Uniquely Urban -

Page 12: 2016 Capital Improvement Program - Genevacityofgenevany.com/wp-content/uploads/2016/09/... · 1/29/2016  · Deep Resurfacing— Downtown Streets Project Description Project entails

WWTP Plant Improvements

Project Description Project entails replacement of an aging and non-functional screen at the Gulvin Park plant, along with V-Notch Weirs at the Marsh Creek Plant. Additionally, the SCADA system requires replacement, as the hardware and software are over 20 years old. Failure would require round-the-clock manning of the plant.

Project to Commence: Summer (Plant)/TBD (SCADA)

Project Complete: Late Fall (Plant)/TBD (SCADA)

Project Funding Mechanism: Bond

Total Project Cost: $480,000

Annual Debt Service: $36,000

- Uniquely Urban -

Page 13: 2016 Capital Improvement Program - Genevacityofgenevany.com/wp-content/uploads/2016/09/... · 1/29/2016  · Deep Resurfacing— Downtown Streets Project Description Project entails
Page 14: 2016 Capital Improvement Program - Genevacityofgenevany.com/wp-content/uploads/2016/09/... · 1/29/2016  · Deep Resurfacing— Downtown Streets Project Description Project entails

Recreation

Projects

Page 15: 2016 Capital Improvement Program - Genevacityofgenevany.com/wp-content/uploads/2016/09/... · 1/29/2016  · Deep Resurfacing— Downtown Streets Project Description Project entails

Recreation Complex

Project Description Project entails replacement of dasher board system, netting, and goal assemblies at the Geneva Recreation Complex. Current installation is at the end of its useful life and no longer meets player safety guidelines.

Project to Commence: Late Spring

Project Complete: Late Summer

Project Funding Mechanism: Bond

Total Project Cost: $200,000

Annual Debt Service: $15,600

- Uniquely Urban -

Page 16: 2016 Capital Improvement Program - Genevacityofgenevany.com/wp-content/uploads/2016/09/... · 1/29/2016  · Deep Resurfacing— Downtown Streets Project Description Project entails
Page 17: 2016 Capital Improvement Program - Genevacityofgenevany.com/wp-content/uploads/2016/09/... · 1/29/2016  · Deep Resurfacing— Downtown Streets Project Description Project entails

Neighborhood Park Upgrades

Project Description Project entails development of new drainage system at Neider Park, along with a surface retention pond. Walking trails will also be installed and the basketball court will be relocated. At Richards Park, a new entrance and parking area will be designed. The Len Defrancesco courts will be repaired and resealed New signage will be designed and installed at multiple parks.

Project to Commence: TBD

Project Complete: TBD

Project Funding Mechanism: Bond

Total Project Cost: $255,000

Annual Debt Service: $19,700

- Uniquely Urban -

Page 18: 2016 Capital Improvement Program - Genevacityofgenevany.com/wp-content/uploads/2016/09/... · 1/29/2016  · Deep Resurfacing— Downtown Streets Project Description Project entails
Page 19: 2016 Capital Improvement Program - Genevacityofgenevany.com/wp-content/uploads/2016/09/... · 1/29/2016  · Deep Resurfacing— Downtown Streets Project Description Project entails
Page 20: 2016 Capital Improvement Program - Genevacityofgenevany.com/wp-content/uploads/2016/09/... · 1/29/2016  · Deep Resurfacing— Downtown Streets Project Description Project entails
Page 21: 2016 Capital Improvement Program - Genevacityofgenevany.com/wp-content/uploads/2016/09/... · 1/29/2016  · Deep Resurfacing— Downtown Streets Project Description Project entails

Wine Trailhead

Project Description Project entails design and installation of a trailhead for the Seneca Wine Trail at Bicentennial Park. The City has been approached by the Seneca Wine Trail Association with an offer of grant funding of $25,000 for a $50,000 project. The Public Art Committee is currently evaluating a design competition concept for the project.

Project to Commence: Spring

Project Complete: Early Fall

Project Funding Mechanism: Grant/Bond

Total Project Cost: $50,000 ($25,000 grant)

Annual Debt Service: $1,970

- Uniquely Urban -

Page 22: 2016 Capital Improvement Program - Genevacityofgenevany.com/wp-content/uploads/2016/09/... · 1/29/2016  · Deep Resurfacing— Downtown Streets Project Description Project entails

Bark Park

Project Description Project entails development of a dog park on the site of the Geneva Recreation Complex. A local not-for-profit residents group has raised funds to support design and site preparations. Remaining funds will be used to install fencing and necessary fixtures at the site

Project to Commence: Spring

Project Complete: Early Summer

Project Funding Mechanism: Fundraising/Bond

Total Project Cost: $30,000 ($20,000 fundraising)

Annual Debt Service: $770

- Uniquely Urban -

Page 23: 2016 Capital Improvement Program - Genevacityofgenevany.com/wp-content/uploads/2016/09/... · 1/29/2016  · Deep Resurfacing— Downtown Streets Project Description Project entails

Other Critical

Projects

Page 24: 2016 Capital Improvement Program - Genevacityofgenevany.com/wp-content/uploads/2016/09/... · 1/29/2016  · Deep Resurfacing— Downtown Streets Project Description Project entails

Rescue Truck Replacement

Project Description Project entails to specification building of a rescue apparatus for the Geneva Fire Department. The rescue truck is utilized for a variety of firefighting support efforts. The current truck was deployed in 1997.

Project to Commence: Spring, 2016

Project Complete: Spring, 2017

Project Funding Mechanism: Bond

Total Project Cost: $650,000

Annual Debt Service: $50,400

- Uniquely Urban -

Page 25: 2016 Capital Improvement Program - Genevacityofgenevany.com/wp-content/uploads/2016/09/... · 1/29/2016  · Deep Resurfacing— Downtown Streets Project Description Project entails

Events Center Noise Dampening

Project Description Project entails installation of noise dampening fixtures on the ceiling of the Geneva Events Center. The City has received multiple inquiries as to our ability to manage noise in the facility.

Project to Commence: ASAP

Project Complete: Early Spring

Project Funding Mechanism: Bond

Total Project Cost: $25,000

Annual Debt Service: $1,970

- Uniquely Urban -

Page 26: 2016 Capital Improvement Program - Genevacityofgenevany.com/wp-content/uploads/2016/09/... · 1/29/2016  · Deep Resurfacing— Downtown Streets Project Description Project entails

Project Financing

Project Total Cost Annual Debt Cost Lochland Road $3,750,000 $ 290,000

Deep Resurfacing $ 150,000 $

Resurfacing $ 150,000 $

WTP Upgrades $ 220,000 $ 17,000

PSB Plumbing $ 60,000 $

WWTP Facilities $ 105,000 $ 8,400

WWTP Plant $ 480,000 $ 36,000

Recreation Complex $ 200,000 $ 15,800

Neighborhood Parks $ 255,000 $ 19,700

Public Art $ 25,000 $ 1,970

Bark Park $ 10,000 $ 770

Rescue Truck Replacement $ 650,000 $ 50,400

Events Center $ 25,000 $ 1,970 Total: $6,180,000 $ 442,010

Page 27: 2016 Capital Improvement Program - Genevacityofgenevany.com/wp-content/uploads/2016/09/... · 1/29/2016  · Deep Resurfacing— Downtown Streets Project Description Project entails

Fund Breakout

General Fund

Project Total Cost Annual Debt Cost Deep Resurfacing $ 150,000 $

Resurfacing $ 150,000 $

Recreation Complex $ 200,000 $ 15,800

Neighborhood Parks $ 255,000 $ 19,700

Public Art $ 25,000 $ 1,970

Bark Park $ 10,000 $ 770 Rescue Truck Replacement $ 650,000 $ 50,400

Events Center $ 25,000 $ 1,970

Total: $1,465,000 $ 90,610

Fund Balance Impact: $0

Net Debt Service Impact (2017): ($282,266)

Page 28: 2016 Capital Improvement Program - Genevacityofgenevany.com/wp-content/uploads/2016/09/... · 1/29/2016  · Deep Resurfacing— Downtown Streets Project Description Project entails

Fund Breakout

Water Fund

Project Total Cost Annual Debt Cost Lochland Road $3,750,000 $ 290,000

WTP Upgrades $ 220,000 $ 17,000

Total: $3,970,000 $ 307,000

Fund Balance Impact: $0

Net Debt Service Impact (2017): $107,494

Page 29: 2016 Capital Improvement Program - Genevacityofgenevany.com/wp-content/uploads/2016/09/... · 1/29/2016  · Deep Resurfacing— Downtown Streets Project Description Project entails

Fund Breakout

Sewer Fund

Project Total Cost Annual Debt Cost PSB Plumbing $ 60,000 $

WWTP Facilities $ 105,000 $ 8,400

WWTP Plant $ 480,000 $ 36,000

Total: $ 645,000 $ 44,400

Fund Balance Impact: $60,000

Net Debt Service Impact (2017): $104,798