Upload
marius-lazauskas
View
85
Download
1
Embed Size (px)
Citation preview
Heating and Cooling with Air Source Heat Pump and Air Handling Unit system for Mobile Temporary Tiny House Clusters
Where innovation starts
Student: M. Lazauskas1st advisor: prof.dr.ir. J.L.M. Hensen2nd advisor: dr. M.H. Hassan MohamedDaily advisor: PhD Stud. L. Xu
PDEng A. Papadopoulos
Final Colloquium 20-04-2016
HVAC with ASHP and AHU system forMobile Temporary Tiny House Clusters
Final Colloquium 20-04-2016 M.Lazauskas 2/28
Combined GraduationOverviewArchitecture Graduation Recap
IntroductionProject AimResearch QuestionsMethodologyCasesPerformance IndicatorsScenariosModel Validation
Existing CaseInvestigated CaseLoad Duration Curve and Coincidence FactorASHP Load Duration CurveAHU Load Duration CurvePhotovoltaic system
ResultsThermal comfort levelsLife-cycle costs
ConclusionsFurther ResearchRemarks and Questions
Contents
HVAC with ASHP and AHU system forMobile Temporary Tiny House Clusters
Final Colloquium 20-04-2016 M.Lazauskas 3/28
Combined Graduation
Overview
Investigated CaseExisting Case
Validation of the Existing Case
Analysis of the Investigated Case
Split Graduation
EnergyCarrier
EnergySource
1 Year
3 Months
HVAC
Space Conditioning
EnergyCarrier
EnergySource
HVAC
July 2015 April 2016Space Conditioning
Reference data
Simulated data
HVAC with ASHP and AHU system forMobile Temporary Tiny House Clusters
Final Colloquium 20-04-2016 M.Lazauskas 4/28
Combined Graduation
Architecture Graduation Recap
Concrete Canvas
HVAC with ASHP and AHU system forMobile Temporary Tiny House Clusters
Final Colloquium 20-04-2016 M.Lazauskas 5/28
Combined Graduation
Architecture Graduation Recap
Tiny Houses
HVAC with ASHP and AHU system forMobile Temporary Tiny House Clusters
Final Colloquium 20-04-2016 M.Lazauskas 6/28
Combined Graduation
Architecture Graduation Recap
Concrete Canvas Tiny Houses
HVAC with ASHP and AHU system forMobile Temporary Tiny House Clusters
Final Colloquium 20-04-2016 M.Lazauskas 7/28
Combined Graduation
Architecture Graduation Recap
Scale Models
HVAC with ASHP and AHU system forMobile Temporary Tiny House Clusters
Final Colloquium 20-04-2016 M.Lazauskas 8/28
Introduction
Growing interest in Tiny Houses*; EnergyPerformanceofBuildingsDirectiveIncreaseenergyefficiencyinBuiltEnvironment;
ExploreenergyefficientHVACsystemsforuseinTinyHouseClusters.
* https://www.google.com/trends/
Google Trends of the term Tiny House
HVAC with ASHP and AHU system forMobile Temporary Tiny House Clusters
Final Colloquium 20-04-2016 M.Lazauskas 9/28
Project Aim
Heijmans ONE Cluster
InvestigatethefeasibilityandpotentialbenefitsofDistrictHeatingandCoolingforTinyHouse clusters.
HVAC with ASHP and AHU system forMobile Temporary Tiny House Clusters
Final Colloquium 20-04-2016 M.Lazauskas 10/28
How does air conditioning affect thermal comfort levels in Tiny Houses?
IsRadiativeLocalUnderfloorHeatingmoreefficientthanConvectiveCentralAirSourceHeat Pump Air Handling Unit Heating in electricity consumption terms?
HowdoesUnderfloorHeatinglife-cyclecostscomparetoCentralAirSourceHeatPumpAir Handling Unit life-cycle costs?
Research Questions
HVAC with ASHP and AHU system forMobile Temporary Tiny House Clusters
Final Colloquium 20-04-2016 M.Lazauskas 11/28
Investigated CaseExisting Case
Validation of the Existing Case
Analysis of the Investigated Case
Split Graduation
EnergyCarrier
EnergySource
1 Year
3 Months
HVAC
Space Conditioning
EnergyCarrier
EnergySource
HVAC
July 2015 April 2016Space Conditioning
Reference data
Simulated data
Methodology
HVAC with ASHP and AHU system forMobile Temporary Tiny House Clusters
Final Colloquium 20-04-2016 M.Lazauskas 12/28
Validation of the Existing Case
Analysis of the Investigated Case
1 Year
3 Months
Type759
Type56 Type660
Type660
Reference data
Simulated data
Methodology
Type759
Type56
Type660
Type759
Type56
Type660
Type759
Type56
Type660
Multizone
Simple Zone with internal controls
Simple Zone with external controls
HVAC with ASHP and AHU system forMobile Temporary Tiny House Clusters
Final Colloquium 20-04-2016 M.Lazauskas 13/28
Existing Case Electric Under Floor Heating; Investigated Case Central Air Source Heat Pump and Air Handling Unit.
Investigated CaseExisting Case
Validation of the Existing Case
Analysis of the Investigated Case
Split Graduation
EnergyCarrier
EnergySource
1 Year
3 Months
HVAC
Space Conditioning
EnergyCarrier
EnergySource
HVAC
July 2015 April 2016Space Conditioning
Reference data
Simulated data
Investigated CaseExisting Case
Validation of the Existing Case
Analysis of the Investigated Case
Split Graduation
EnergyCarrier
EnergySource
1 Year
3 Months
HVAC
Space Conditioning
EnergyCarrier
EnergySource
HVAC
July 2015 April 2016Space Conditioning
Reference data
Simulated data
Methodology
Cases
HVAC with ASHP and AHU system forMobile Temporary Tiny House Clusters
Final Colloquium 20-04-2016 M.Lazauskas 14/28
Methodology
Thermal comfort levels occupied overheating and underheating hours: Overheating hours indoor temperature >28C; Underheating hours indoor temperature
HVAC with ASHP and AHU system forMobile Temporary Tiny House Clusters
Final Colloquium 20-04-2016 M.Lazauskas 15/28
n/a in Existing Case
n/a in Existing Case
No Underheating in Investigated Case
Methodology
Scenariosn/a in
Existing Case n/a in
Existing CaseNo Underheating in
Investigated Case
Occupied heating and cooling properties
Unoccupied heating and cooling propertiesVentilation properties
HVAC with ASHP and AHU system forMobile Temporary Tiny House Clusters
Final Colloquium 20-04-2016 M.Lazauskas 16/28
Measurements 27th of April 2015 until 15th of September 2015; Simulations2856huntil6264hwithNL-Amsterdam-Schiphol-62400.tm2weatherfile.
Investigated CaseExisting Case
Validation of the Existing Case
Analysis of the Investigated Case
Split Graduation
EnergyCarrier
EnergySource
1 Year
3 Months
HVAC
Space Conditioning
EnergyCarrier
EnergySource
HVAC
Space Conditioning
Reference data
Simulated data
Model Validation
Methodology
Heating demand April-September 2015
HVAC with ASHP and AHU system forMobile Temporary Tiny House Clusters
Final Colloquium 20-04-2016 M.Lazauskas 17/28
Existing CaseElectric Under Floor Heating (UFH)
Electric UFH Power 2.5 kW.
HVAC with ASHP and AHU system forMobile Temporary Tiny House Clusters
Final Colloquium 20-04-2016 M.Lazauskas 18/28
Investigated CaseCentral Air Source Heat Pump (ASHP) and Air Handling Unit (AHU)
ASHP Power 15/75 (Cooling/Heating) kW; AHU Power 1.6/6.7 (Cooling/Heating) kW; PV Power 24 kW.
HVAC with ASHP and AHU system forMobile Temporary Tiny House Clusters
Final Colloquium 20-04-2016 M.Lazauskas 19/28
* **
* http://www.mpoweruk.com/grid_storage.htm** Prof. Natasa Nord Lecture of District heating at NTNU university
Investigated Case
Load Duration Curve and Coincidence Factor
Central Air Source Heat Pump (ASHP) and Air Handling Unit (AHU)
7LYM30 - Building performance and energy systems simulation16
Modern Centralized Energy Systems From Economical Point of ViewCoincidence factor
+ < , + ,
Definition of coincidence factor
=,
,
n number of consumers, - the maximum power at each consumer
Consumer maximum effects do not appear at the same time
Prof. Natasa Nord. Lecture of District heating at NTNU university
Load Duration Curve Coincidence Factor
Particular load occurrence frequency; Load estimation for District Heating systems.
Maximum consumer demand does not appear at the same time: (P1+P2)max< P1,max+ P2,max
Load estimation for District Heating systems.
HVAC with ASHP and AHU system forMobile Temporary Tiny House Clusters
Final Colloquium 20-04-2016 M.Lazauskas 20/28
ASHP Peak Cooling Load (50%) 15 kW; ASHP Peak Heating Load (75%) 75 kW; Capacity reserve in a 2 m3 Buffer Tank.
Investigated Case
ASHP Load Duration Curve
Central Air Source Heat Pump (ASHP) and Air Handling Unit (AHU)
Heating Load Duration Curve
Cooling Load Duration Curve
5 Central Danfoss DHP-AQ 15 kW Air Source Heat Pumps 165 h
4 h
HVAC with ASHP and AHU system forMobile Temporary Tiny House Clusters
Final Colloquium 20-04-2016 M.Lazauskas 21/28
AHU Peak Cooling Load (50%) 1.6 kW; AHU Peak Heating Load (75%) 6.7 kW; Constant Air Volume capacity modulationviafluidflowrate.
Investigated Case
AHU Load Duration Curve
Central Air Source Heat Pump (ASHP) and Air Handling Unit (AHU)
Heating Load Duration Curve
Cooling Load Duration Curve
ATREA DUPLEX ECV4 ventilation unit
with Heat Recovery
ATREA TPO EC THV Water-to-Air
Heat Exchanger
150 h
4 h
HVAC with ASHP and AHU system forMobile Temporary Tiny House Clusters
Final Colloquium 20-04-2016 M.Lazauskas 22/28
PV total area 131.2 m2; PV installed power 24 kW; PV annual production 23400 kWh*; Inverters 2*12 kW.
Peak ASHP heating load 35 kW; Peak ASHP cooling load 4.3 kW; Space conditioning annual electricity; demand 21287 kWh.
* http://re.jrc.ec.europa.eu/pvgis/
Investigated Case
Photovoltaic system
Central Air Source Heat Pump (ASHP) and Air Handling Unit (AHU)
LG-300N1K-G4 300W PV panel
HVAC with ASHP and AHU system forMobile Temporary Tiny House Clusters
Final Colloquium 20-04-2016 M.Lazauskas 23/28
Results
Thermal comfort levels
Underheating in Existing Case; Lower summer indoor temperatures in Investigated Case.
Under/Over-Heating Hours
n/a in Existing Case
n/a in Existing Case
No Underheating in Investigated Case
Simulated Indoor Temperatures; Scenario No 3
5
10
15
20
25
30
35
0 2000 4000 6000 8000
Tem
pera
ture
, [C
]
Time, [h]
Indoor Temperatures OCC-3
Existing Case OCC-3 Investigated Case OCC-3
5
10
15
20
25
30
35
3600 4100 4600 5100 5600
Tem
pera
ture
, [C
]
Time, [h]
Indoor Temperatures OCS-3
Existing Case OCS-3 Investigated Case OCS-3
5
10
15
20
25
30
35
0 500 1000 1500 2000
Tem
pera
ture
, [C
]
Time, [h]
Indoor Temperatures OCS-3
Existing Case OCS-3 Investigated Case OCS-3
HVAC with ASHP and AHU system forMobile Temporary Tiny House Clusters
Final Colloquium 20-04-2016 M.Lazauskas 24/28
Results
Life-cycle costs
9 years are required for Investigated Case to pay itself off.
Investigated Case payback time
9.2 yr
HVAC with ASHP and AHU system forMobile Temporary Tiny House Clusters
Final Colloquium 20-04-2016 M.Lazauskas 25/28
Results
Heat recovery system and cooling in a form of AHU (Investigated Case) increases indoor comfort levels (Summer indoor temperatures up to 3C lower and no underheating) in a Heijmans ONE.
In electricity consumption terms Investigated Case (21287.6 kWh) requires 4 times less energy than Existing Case (84403 kWh).
Investments into more capital intense Investigated Case pays off in 9 years (Running costs difference is 10000 /yr).
HVAC with ASHP and AHU system forMobile Temporary Tiny House Clusters
Final Colloquium 20-04-2016 M.Lazauskas 26/28
Conclusions
Increasing average ambient temperatures, Photovoltaic electricity coverage of heating and cooling demand and Heijmans ONE lifespan (30 years) indicates that increased indoor comfort outweighs the 9 year payoff period and Investigated Case is more futureproof design, when compared with Existing Case.
Investigated Case
HVAC with ASHP and AHU system forMobile Temporary Tiny House Clusters
Final Colloquium 20-04-2016 M.Lazauskas 27/28
Further Research
With detail TRNSYS Type56 model Predicted Mean Vote and Predicted Percentage of Dissatisfiedindoorcomfortindicatorscanbecomputed.WithmorepreciseindoorcomfortindicatorsthesignificanceofAirConditioningduringthesummercanbebetterjudged.
In the Investigated Case its not clear how much of the space conditioning electrical energy demand is directly met by the Photovoltaic system and how much of the energy has to be exported and later re-exported (imported) from the grid. Import/Export information would be useful for designing off-grid Tiny Houses.
TheincreasingambientaverageairtemperatureinfluenceonTinyHouses.
HVAC with ASHP and AHU system forMobile Temporary Tiny House Clusters
Final Colloquium 20-04-2016 M.Lazauskas 28/28
Remarks and Questions
Image Source*
* http://www.heijmans.nl/nl/heijmans-one/
Combined GraduationOverviewArchitecture Graduation Recap
IntroductionProject AimResearch QuestionsMethodologyCasesPerformance IndicatorsScenariosModel Validation
Existing CaseInvestigated CaseLoad Duration Curve and Coincidence FactorASHP Load Duration CurveAHU Load Duration CurvePhotovoltaic system
ResultsThermal comfort levelsLife-cycle costs
ConclusionsFurther ResearchRemarks and Questions