28
Heating and Cooling with Air Source Heat Pump and Air Handling Unit system for Mobile Temporary Tiny House Clusters Where innovation starts Student: M. Lazauskas 1 st advisor: prof.dr.ir. J.L.M. Hensen 2 nd advisor: dr. M.H. Hassan Mohamed Daily advisor: PhD Stud. L. Xu PDEng A. Papadopoulos Final Colloquium 20-04-2016

2016-04-20 Presentation M. Lazauskas Final Colloquium

Embed Size (px)

Citation preview

  • Heating and Cooling with Air Source Heat Pump and Air Handling Unit system for Mobile Temporary Tiny House Clusters

    Where innovation starts

    Student: M. Lazauskas1st advisor: prof.dr.ir. J.L.M. Hensen2nd advisor: dr. M.H. Hassan MohamedDaily advisor: PhD Stud. L. Xu

    PDEng A. Papadopoulos

    Final Colloquium 20-04-2016

  • HVAC with ASHP and AHU system forMobile Temporary Tiny House Clusters

    Final Colloquium 20-04-2016 M.Lazauskas 2/28

    Combined GraduationOverviewArchitecture Graduation Recap

    IntroductionProject AimResearch QuestionsMethodologyCasesPerformance IndicatorsScenariosModel Validation

    Existing CaseInvestigated CaseLoad Duration Curve and Coincidence FactorASHP Load Duration CurveAHU Load Duration CurvePhotovoltaic system

    ResultsThermal comfort levelsLife-cycle costs

    ConclusionsFurther ResearchRemarks and Questions

    Contents

  • HVAC with ASHP and AHU system forMobile Temporary Tiny House Clusters

    Final Colloquium 20-04-2016 M.Lazauskas 3/28

    Combined Graduation

    Overview

    Investigated CaseExisting Case

    Validation of the Existing Case

    Analysis of the Investigated Case

    Split Graduation

    EnergyCarrier

    EnergySource

    1 Year

    3 Months

    HVAC

    Space Conditioning

    EnergyCarrier

    EnergySource

    HVAC

    July 2015 April 2016Space Conditioning

    Reference data

    Simulated data

  • HVAC with ASHP and AHU system forMobile Temporary Tiny House Clusters

    Final Colloquium 20-04-2016 M.Lazauskas 4/28

    Combined Graduation

    Architecture Graduation Recap

    Concrete Canvas

  • HVAC with ASHP and AHU system forMobile Temporary Tiny House Clusters

    Final Colloquium 20-04-2016 M.Lazauskas 5/28

    Combined Graduation

    Architecture Graduation Recap

    Tiny Houses

  • HVAC with ASHP and AHU system forMobile Temporary Tiny House Clusters

    Final Colloquium 20-04-2016 M.Lazauskas 6/28

    Combined Graduation

    Architecture Graduation Recap

    Concrete Canvas Tiny Houses

  • HVAC with ASHP and AHU system forMobile Temporary Tiny House Clusters

    Final Colloquium 20-04-2016 M.Lazauskas 7/28

    Combined Graduation

    Architecture Graduation Recap

    Scale Models

  • HVAC with ASHP and AHU system forMobile Temporary Tiny House Clusters

    Final Colloquium 20-04-2016 M.Lazauskas 8/28

    Introduction

    Growing interest in Tiny Houses*; EnergyPerformanceofBuildingsDirectiveIncreaseenergyefficiencyinBuiltEnvironment;

    ExploreenergyefficientHVACsystemsforuseinTinyHouseClusters.

    * https://www.google.com/trends/

    Google Trends of the term Tiny House

  • HVAC with ASHP and AHU system forMobile Temporary Tiny House Clusters

    Final Colloquium 20-04-2016 M.Lazauskas 9/28

    Project Aim

    Heijmans ONE Cluster

    InvestigatethefeasibilityandpotentialbenefitsofDistrictHeatingandCoolingforTinyHouse clusters.

  • HVAC with ASHP and AHU system forMobile Temporary Tiny House Clusters

    Final Colloquium 20-04-2016 M.Lazauskas 10/28

    How does air conditioning affect thermal comfort levels in Tiny Houses?

    IsRadiativeLocalUnderfloorHeatingmoreefficientthanConvectiveCentralAirSourceHeat Pump Air Handling Unit Heating in electricity consumption terms?

    HowdoesUnderfloorHeatinglife-cyclecostscomparetoCentralAirSourceHeatPumpAir Handling Unit life-cycle costs?

    Research Questions

  • HVAC with ASHP and AHU system forMobile Temporary Tiny House Clusters

    Final Colloquium 20-04-2016 M.Lazauskas 11/28

    Investigated CaseExisting Case

    Validation of the Existing Case

    Analysis of the Investigated Case

    Split Graduation

    EnergyCarrier

    EnergySource

    1 Year

    3 Months

    HVAC

    Space Conditioning

    EnergyCarrier

    EnergySource

    HVAC

    July 2015 April 2016Space Conditioning

    Reference data

    Simulated data

    Methodology

  • HVAC with ASHP and AHU system forMobile Temporary Tiny House Clusters

    Final Colloquium 20-04-2016 M.Lazauskas 12/28

    Validation of the Existing Case

    Analysis of the Investigated Case

    1 Year

    3 Months

    Type759

    Type56 Type660

    Type660

    Reference data

    Simulated data

    Methodology

    Type759

    Type56

    Type660

    Type759

    Type56

    Type660

    Type759

    Type56

    Type660

    Multizone

    Simple Zone with internal controls

    Simple Zone with external controls

  • HVAC with ASHP and AHU system forMobile Temporary Tiny House Clusters

    Final Colloquium 20-04-2016 M.Lazauskas 13/28

    Existing Case Electric Under Floor Heating; Investigated Case Central Air Source Heat Pump and Air Handling Unit.

    Investigated CaseExisting Case

    Validation of the Existing Case

    Analysis of the Investigated Case

    Split Graduation

    EnergyCarrier

    EnergySource

    1 Year

    3 Months

    HVAC

    Space Conditioning

    EnergyCarrier

    EnergySource

    HVAC

    July 2015 April 2016Space Conditioning

    Reference data

    Simulated data

    Investigated CaseExisting Case

    Validation of the Existing Case

    Analysis of the Investigated Case

    Split Graduation

    EnergyCarrier

    EnergySource

    1 Year

    3 Months

    HVAC

    Space Conditioning

    EnergyCarrier

    EnergySource

    HVAC

    July 2015 April 2016Space Conditioning

    Reference data

    Simulated data

    Methodology

    Cases

  • HVAC with ASHP and AHU system forMobile Temporary Tiny House Clusters

    Final Colloquium 20-04-2016 M.Lazauskas 14/28

    Methodology

    Thermal comfort levels occupied overheating and underheating hours: Overheating hours indoor temperature >28C; Underheating hours indoor temperature

  • HVAC with ASHP and AHU system forMobile Temporary Tiny House Clusters

    Final Colloquium 20-04-2016 M.Lazauskas 15/28

    n/a in Existing Case

    n/a in Existing Case

    No Underheating in Investigated Case

    Methodology

    Scenariosn/a in

    Existing Case n/a in

    Existing CaseNo Underheating in

    Investigated Case

    Occupied heating and cooling properties

    Unoccupied heating and cooling propertiesVentilation properties

  • HVAC with ASHP and AHU system forMobile Temporary Tiny House Clusters

    Final Colloquium 20-04-2016 M.Lazauskas 16/28

    Measurements 27th of April 2015 until 15th of September 2015; Simulations2856huntil6264hwithNL-Amsterdam-Schiphol-62400.tm2weatherfile.

    Investigated CaseExisting Case

    Validation of the Existing Case

    Analysis of the Investigated Case

    Split Graduation

    EnergyCarrier

    EnergySource

    1 Year

    3 Months

    HVAC

    Space Conditioning

    EnergyCarrier

    EnergySource

    HVAC

    Space Conditioning

    Reference data

    Simulated data

    Model Validation

    Methodology

    Heating demand April-September 2015

  • HVAC with ASHP and AHU system forMobile Temporary Tiny House Clusters

    Final Colloquium 20-04-2016 M.Lazauskas 17/28

    Existing CaseElectric Under Floor Heating (UFH)

    Electric UFH Power 2.5 kW.

  • HVAC with ASHP and AHU system forMobile Temporary Tiny House Clusters

    Final Colloquium 20-04-2016 M.Lazauskas 18/28

    Investigated CaseCentral Air Source Heat Pump (ASHP) and Air Handling Unit (AHU)

    ASHP Power 15/75 (Cooling/Heating) kW; AHU Power 1.6/6.7 (Cooling/Heating) kW; PV Power 24 kW.

  • HVAC with ASHP and AHU system forMobile Temporary Tiny House Clusters

    Final Colloquium 20-04-2016 M.Lazauskas 19/28

    * **

    * http://www.mpoweruk.com/grid_storage.htm** Prof. Natasa Nord Lecture of District heating at NTNU university

    Investigated Case

    Load Duration Curve and Coincidence Factor

    Central Air Source Heat Pump (ASHP) and Air Handling Unit (AHU)

    7LYM30 - Building performance and energy systems simulation16

    Modern Centralized Energy Systems From Economical Point of ViewCoincidence factor

    + < , + ,

    Definition of coincidence factor

    =,

    ,

    n number of consumers, - the maximum power at each consumer

    Consumer maximum effects do not appear at the same time

    Prof. Natasa Nord. Lecture of District heating at NTNU university

    Load Duration Curve Coincidence Factor

    Particular load occurrence frequency; Load estimation for District Heating systems.

    Maximum consumer demand does not appear at the same time: (P1+P2)max< P1,max+ P2,max

    Load estimation for District Heating systems.

  • HVAC with ASHP and AHU system forMobile Temporary Tiny House Clusters

    Final Colloquium 20-04-2016 M.Lazauskas 20/28

    ASHP Peak Cooling Load (50%) 15 kW; ASHP Peak Heating Load (75%) 75 kW; Capacity reserve in a 2 m3 Buffer Tank.

    Investigated Case

    ASHP Load Duration Curve

    Central Air Source Heat Pump (ASHP) and Air Handling Unit (AHU)

    Heating Load Duration Curve

    Cooling Load Duration Curve

    5 Central Danfoss DHP-AQ 15 kW Air Source Heat Pumps 165 h

    4 h

  • HVAC with ASHP and AHU system forMobile Temporary Tiny House Clusters

    Final Colloquium 20-04-2016 M.Lazauskas 21/28

    AHU Peak Cooling Load (50%) 1.6 kW; AHU Peak Heating Load (75%) 6.7 kW; Constant Air Volume capacity modulationviafluidflowrate.

    Investigated Case

    AHU Load Duration Curve

    Central Air Source Heat Pump (ASHP) and Air Handling Unit (AHU)

    Heating Load Duration Curve

    Cooling Load Duration Curve

    ATREA DUPLEX ECV4 ventilation unit

    with Heat Recovery

    ATREA TPO EC THV Water-to-Air

    Heat Exchanger

    150 h

    4 h

  • HVAC with ASHP and AHU system forMobile Temporary Tiny House Clusters

    Final Colloquium 20-04-2016 M.Lazauskas 22/28

    PV total area 131.2 m2; PV installed power 24 kW; PV annual production 23400 kWh*; Inverters 2*12 kW.

    Peak ASHP heating load 35 kW; Peak ASHP cooling load 4.3 kW; Space conditioning annual electricity; demand 21287 kWh.

    * http://re.jrc.ec.europa.eu/pvgis/

    Investigated Case

    Photovoltaic system

    Central Air Source Heat Pump (ASHP) and Air Handling Unit (AHU)

    LG-300N1K-G4 300W PV panel

  • HVAC with ASHP and AHU system forMobile Temporary Tiny House Clusters

    Final Colloquium 20-04-2016 M.Lazauskas 23/28

    Results

    Thermal comfort levels

    Underheating in Existing Case; Lower summer indoor temperatures in Investigated Case.

    Under/Over-Heating Hours

    n/a in Existing Case

    n/a in Existing Case

    No Underheating in Investigated Case

    Simulated Indoor Temperatures; Scenario No 3

    5

    10

    15

    20

    25

    30

    35

    0 2000 4000 6000 8000

    Tem

    pera

    ture

    , [C

    ]

    Time, [h]

    Indoor Temperatures OCC-3

    Existing Case OCC-3 Investigated Case OCC-3

    5

    10

    15

    20

    25

    30

    35

    3600 4100 4600 5100 5600

    Tem

    pera

    ture

    , [C

    ]

    Time, [h]

    Indoor Temperatures OCS-3

    Existing Case OCS-3 Investigated Case OCS-3

    5

    10

    15

    20

    25

    30

    35

    0 500 1000 1500 2000

    Tem

    pera

    ture

    , [C

    ]

    Time, [h]

    Indoor Temperatures OCS-3

    Existing Case OCS-3 Investigated Case OCS-3

  • HVAC with ASHP and AHU system forMobile Temporary Tiny House Clusters

    Final Colloquium 20-04-2016 M.Lazauskas 24/28

    Results

    Life-cycle costs

    9 years are required for Investigated Case to pay itself off.

    Investigated Case payback time

    9.2 yr

  • HVAC with ASHP and AHU system forMobile Temporary Tiny House Clusters

    Final Colloquium 20-04-2016 M.Lazauskas 25/28

    Results

    Heat recovery system and cooling in a form of AHU (Investigated Case) increases indoor comfort levels (Summer indoor temperatures up to 3C lower and no underheating) in a Heijmans ONE.

    In electricity consumption terms Investigated Case (21287.6 kWh) requires 4 times less energy than Existing Case (84403 kWh).

    Investments into more capital intense Investigated Case pays off in 9 years (Running costs difference is 10000 /yr).

  • HVAC with ASHP and AHU system forMobile Temporary Tiny House Clusters

    Final Colloquium 20-04-2016 M.Lazauskas 26/28

    Conclusions

    Increasing average ambient temperatures, Photovoltaic electricity coverage of heating and cooling demand and Heijmans ONE lifespan (30 years) indicates that increased indoor comfort outweighs the 9 year payoff period and Investigated Case is more futureproof design, when compared with Existing Case.

    Investigated Case

  • HVAC with ASHP and AHU system forMobile Temporary Tiny House Clusters

    Final Colloquium 20-04-2016 M.Lazauskas 27/28

    Further Research

    With detail TRNSYS Type56 model Predicted Mean Vote and Predicted Percentage of Dissatisfiedindoorcomfortindicatorscanbecomputed.WithmorepreciseindoorcomfortindicatorsthesignificanceofAirConditioningduringthesummercanbebetterjudged.

    In the Investigated Case its not clear how much of the space conditioning electrical energy demand is directly met by the Photovoltaic system and how much of the energy has to be exported and later re-exported (imported) from the grid. Import/Export information would be useful for designing off-grid Tiny Houses.

    TheincreasingambientaverageairtemperatureinfluenceonTinyHouses.

  • HVAC with ASHP and AHU system forMobile Temporary Tiny House Clusters

    Final Colloquium 20-04-2016 M.Lazauskas 28/28

    Remarks and Questions

    Image Source*

    * http://www.heijmans.nl/nl/heijmans-one/

    Combined GraduationOverviewArchitecture Graduation Recap

    IntroductionProject AimResearch QuestionsMethodologyCasesPerformance IndicatorsScenariosModel Validation

    Existing CaseInvestigated CaseLoad Duration Curve and Coincidence FactorASHP Load Duration CurveAHU Load Duration CurvePhotovoltaic system

    ResultsThermal comfort levelsLife-cycle costs

    ConclusionsFurther ResearchRemarks and Questions