26
2015 Winter School Structures Heidi A. Mertz, P.E. District 8-0 Structure Control Engineer

2015 Winter School Structures Heidi A. Mertz, P.E. District 8-0 Structure Control Engineer

Embed Size (px)

Citation preview

Page 1: 2015 Winter School Structures Heidi A. Mertz, P.E. District 8-0 Structure Control Engineer

2015 Winter School

Structures

Heidi A. Mertz, P.E.District 8-0

Structure Control Engineer

Page 2: 2015 Winter School Structures Heidi A. Mertz, P.E. District 8-0 Structure Control Engineer

District 8-0 Structures Staff

Heidi Mertz, [email protected]

Cell – 717.443.1712

VacantCivil Engineer

VacantAss. Structure

Control Engineer

Justin Enck, [email protected]

Cell – 717.315.4150

VacantAss. Structure

Control EngineerDan Wooddell

[email protected] – 717.443.1840

Page 3: 2015 Winter School Structures Heidi A. Mertz, P.E. District 8-0 Structure Control Engineer

General Protocol

• Emails to Structure Control Unit– Title of the Email should include ECMS #, SR, Section,

and subject pertaining to email– Email submissions to Structures account

[email protected]. All meeting announcement and project emails should go to our personal email accounts.

• Field staff field questions before passing them on to the Structure Control Unit

• If a contractor calls the Structure Control Unit with a question… we will call the field staff… field staff will relay the answer to the contractor

Page 4: 2015 Winter School Structures Heidi A. Mertz, P.E. District 8-0 Structure Control Engineer

Winter School 2015

• Section 1001.3(q)2.b – Backfilling• Mechanical Grooving Pie Shapes• Fall Protection Plan• Construction Loading Letters• New Pile Splicing Detail• 2015 Pilot SSP Program for Improving Deck

Performance• District 8-0 Standard 1001 Special Provision• Overview of Bridge Deck Cracking Survey

Page 5: 2015 Winter School Structures Heidi A. Mertz, P.E. District 8-0 Structure Control Engineer

Section 1001.3(q)2.b Backfilling

• Do not backfill or place material adjoining abutment walls, backwalls, retaining walls, box culverts, and arches until 7 days after placing last concrete, and then only if concrete has attained the 7-day Minimum Mix Design Compressive Strength as specified in Section 704, Table A.

Page 6: 2015 Winter School Structures Heidi A. Mertz, P.E. District 8-0 Structure Control Engineer

Mechanical Grooving

Page 7: 2015 Winter School Structures Heidi A. Mertz, P.E. District 8-0 Structure Control Engineer

Mechanical Grooving

Page 8: 2015 Winter School Structures Heidi A. Mertz, P.E. District 8-0 Structure Control Engineer

Mechanical Grooving

Page 9: 2015 Winter School Structures Heidi A. Mertz, P.E. District 8-0 Structure Control Engineer

Mechanical Grooving

Page 10: 2015 Winter School Structures Heidi A. Mertz, P.E. District 8-0 Structure Control Engineer

Mechanical Grooving

Page 11: 2015 Winter School Structures Heidi A. Mertz, P.E. District 8-0 Structure Control Engineer

Fall Protection Plan

• Fall Protection Plan with designed calculations and Rescue Plan– Before the start of work contractors must provide the

Department a designed Fall Protection Plan in accordance with all OSHA regulations for review. The plan must include the design and calculations for the lifeline for review. In addition, the plan must state who the qualified and competent persons are. The Fall Protection System will need to be certified after installation and before use by the qualified person stating the system is installed as designed. The plan also needs to address a Rescue Plan.

Page 12: 2015 Winter School Structures Heidi A. Mertz, P.E. District 8-0 Structure Control Engineer

Fall Protection Plan

Page 13: 2015 Winter School Structures Heidi A. Mertz, P.E. District 8-0 Structure Control Engineer

Fall Protection Plan

• The Fall Protection Plan needs to show:– How many people the plan is rated for– Total weight the plan is rated for

Page 14: 2015 Winter School Structures Heidi A. Mertz, P.E. District 8-0 Structure Control Engineer

Construction Loading Letters

• PUB 408, Section105.17• Loading Limits

– Limited to one individual stockpile with a maximum weight of 250lbs/square foot and a maximum size of 100 square feet.

– Combination of material stockpiles, vehicles, other materials, and equipment are limited to a maximum total weight of 100,000 lbs per span in any work zone width less than 24 feet, and a maximum total weight of 200,000 lbs per span for work zones ≥ 24 ft wide, provided loading limits in Sections 105.17(a)1 and 2 are not exceeded.

Page 15: 2015 Winter School Structures Heidi A. Mertz, P.E. District 8-0 Structure Control Engineer

Construction Loading Letters

• The force effects produced by combinations of material stockpiles, vehicles and other materials and equipment are limited to the force effects produced by vehicles of legal configuration evaluated at operating rating levels as defined in Pub 238.

• If loads are proposed that will exceed the above loading limits or loads are proposed to be placed on an incomplete bridge, submit analytical calculations showing the flexural, shear, and axial stressed due to construction loadings do not exceed the operating stress levels as defined in Pub 238 for the main load carrying members of the structure or the deck slab.

Page 16: 2015 Winter School Structures Heidi A. Mertz, P.E. District 8-0 Structure Control Engineer

Construction Loading Letters

• Once the bridge is closed• Have the Contractor submit a Construction

Loading Letter for:– Deck Removal– Beam removal– Scarification equipment– Hydrodemolition– Latex Trucks– Etc…

• There will be times we will request calculations showing the flexural, shear, and axial stressed due to construction loadings

Page 17: 2015 Winter School Structures Heidi A. Mertz, P.E. District 8-0 Structure Control Engineer

Pile Splicing

Page 18: 2015 Winter School Structures Heidi A. Mertz, P.E. District 8-0 Structure Control Engineer

Pile Splicing

Eliminated

• Splicing Piles – BC 757 Pile Splicing Method #1 “Diamond Plate” no longer permitted– Change #2 Pub 219-BC’s (dated Nov. 26, 2013)– Check your list of Supplemental Drawings!

Page 19: 2015 Winter School Structures Heidi A. Mertz, P.E. District 8-0 Structure Control Engineer

Pile Splicing

Page 20: 2015 Winter School Structures Heidi A. Mertz, P.E. District 8-0 Structure Control Engineer

Pile Splicing

BC-757M Pile Splicing Method #1 “Diamond Plate” no longer is permitted.

• Acceptable methods will be renamed as:– Method 1: CJP (Complete Joint Penetration Weld)

welded splice for both flanges and web– Method 2: Splicer Sleeve method

Method 2: Splicer Sleeve

Page 21: 2015 Winter School Structures Heidi A. Mertz, P.E. District 8-0 Structure Control Engineer

Pile Splicing

What not to do

Page 22: 2015 Winter School Structures Heidi A. Mertz, P.E. District 8-0 Structure Control Engineer

District 8-0 Revised 1001 SP

• Water Cement ratio 0.40 or greater• Slump less than 6 inch (rejected over 6”)• No high range water reducing admixtures

(superplasticizers)• Maintain 22°F differential temperature between

concrete and mean beam temperature• Place decks when air temperature is 35°F and

rising and less than 80°F• Concrete decks with a skew less than 75°, place

and finish concrete on the skew angle

Page 23: 2015 Winter School Structures Heidi A. Mertz, P.E. District 8-0 Structure Control Engineer

2014 Deck Cracking Results

• District 8-0 completed 14 bridge decks during 2014 construction season– Compared to 16 in 2013 construction season

• 4 bridge decks showed cracks at the time of the initial survey– 1 Integral Abutment bridge (new)– 1 4 span P/S concrete PA I-Beam bridge (rehab)– 1 single span P/S concrete I-Beam bridge (new)– 1 18 span closed spandrel concrete arch bridge (rehab)

• Only initial surveys has been complete to date – Post one year surveys to be completed by May 2015

• Looking forward to statewide bridge deck performance metrics in August 2015?– Last years performance metrics showed District 8-0 had above average

deck quality with only two badly cracked decks

Page 24: 2015 Winter School Structures Heidi A. Mertz, P.E. District 8-0 Structure Control Engineer

Overview of Bridge Deck Cracking Survey

Page 25: 2015 Winter School Structures Heidi A. Mertz, P.E. District 8-0 Structure Control Engineer

Overview of Bridge Deck Cracking Survey

Page 26: 2015 Winter School Structures Heidi A. Mertz, P.E. District 8-0 Structure Control Engineer

Questions ???