Paraffin Blockage Remediation In A Flexible Flowline

Robert JamesProduction Engineer

Page 2: 2015 Deepwater Operations_Murphy_FINAL

2

Outline

• Background • Remediation• Execution• Lessons Learned

Page 3: 2015 Deepwater Operations_Murphy_FINAL

3

Background

Page 4: 2015 Deepwater Operations_Murphy_FINAL

4

Medusa SS#5 Infrastructure

Page 5: 2015 Deepwater Operations_Murphy_FINAL

5

Flow Assurance Challenges

• Uninsulated flowline• Pigging operations unavailable• Water injection tree

– Limited chemical injection points• Assumed similar fluid characteristics to offset well

– No down-hole samples obtained

Page 6: 2015 Deepwater Operations_Murphy_FINAL

6

Medusa SS#5 HistoricalInitial Production

Snubbing Clean-out Operation

Paraffin Plug In Flowline

Page 7: 2015 Deepwater Operations_Murphy_FINAL

7

Flowline Deposition

Bottom-hole Pressure

Boarding Pressure

Tubing Pressure

Subsea Flowline Pressure

Time Period Shown: 4 Years

Page 8: 2015 Deepwater Operations_Murphy_FINAL

8

Remediation

Page 9: 2015 Deepwater Operations_Murphy_FINAL

9

Remediation Options

Paraffin Deposition

Bullhead Solvent

Coil Tubing Cleanout

Snubbing Unit Cleanout

Page 10: 2015 Deepwater Operations_Murphy_FINAL

10

Bullhead Operation

• Pumped 1000 gals of Xylene down flowline from platform• Impermeable paraffin blockage formed

Subsea Flowline Pressure

Boarding Pressure

Time Period Shown: 5 Months

Page 11: 2015 Deepwater Operations_Murphy_FINAL

11

Remediation Options

Paraffin Deposition

Bullhead Solvent

Paraffin Blockage Formed

Coil Tubing Cleanout

Snubbing Unit Cleanout

Page 12: 2015 Deepwater Operations_Murphy_FINAL

12

Coil Tubing

• Advantages– Circulation– Direct solvent

application to blockage• Disadvantages

– Potential for stuck work string

• Tractoring technology in horizontal section risky

Page 13: 2015 Deepwater Operations_Murphy_FINAL

13

Remediation Options

Paraffin Deposition

Bullhead Solvent

Paraffin Blockage Formed

Coil Tubing Cleanout

High Potential For Stuck

Work String

Snubbing Unit Cleanout

Page 14: 2015 Deepwater Operations_Murphy_FINAL

14

Snubbing Unit

• Advantages– Rotation capability– Circulation– Direct solvent

application to blockage– Proven industry method

• Risks– Flexible flowline integrity– Maneuverability of

curvature in flowline

Page 15: 2015 Deepwater Operations_Murphy_FINAL

15

Flowline Curvature Risk - Mitigation

• Torque and drag modeling shows snubbing unit capable of operating through bend in flowline.

• Provided parameters while running in hole with work string.

Page 16: 2015 Deepwater Operations_Murphy_FINAL

16

Solvent Selection• Solvent Selection:

– Diesel• HSE • Disposal• Cost Effective

– Effectiveness of diesel circulation in question at lower temperatures

Page 17: 2015 Deepwater Operations_Murphy_FINAL

17

Mechanical Remediation

• Pipe in pipe modeling completed– Significant heat loss

expected • Removal of paraffin

using 3” O.D. brass nozzle

Page 18: 2015 Deepwater Operations_Murphy_FINAL

18

Remediation Options

Paraffin Deposition

Bullhead Solvent

Paraffin Blockage Formed

Coil Tubing Cleanout

High Potential For Stuck Work

String

Snubbing Unit Cleanout

Execution

Page 19: 2015 Deepwater Operations_Murphy_FINAL

19

Execution

Page 20: 2015 Deepwater Operations_Murphy_FINAL

20

Operations SpreadSnubbing Unit

Circulation/Flowback

Heated Tanks

Page 21: 2015 Deepwater Operations_Murphy_FINAL

21

Continuous Monitoring

• Snubbing parameters:– Pick Up and Slack Off Weights– Torque

• Diesel parameters:– Pour Point– Viscosity– Density

Page 22: 2015 Deepwater Operations_Murphy_FINAL

22

Operational Results

Subsea Flowline Pressure

Tubing Pressure

Boarding Pressure

Time Period Shown: 3 Months

Page 23: 2015 Deepwater Operations_Murphy_FINAL

23

Operational Results

• Well Test Recorded After Clean-Out• 1381 BOPD, 1223 MCFD, 213 BWPD

Page 24: 2015 Deepwater Operations_Murphy_FINAL

24

Lessons Learned

• Job Execution – Accurate modeling– Multiple remediation options– Real-time monitoring

• Field Development– Accurate data acquisition– Appropriate infrastructure

• Insulation Requirements• Chemical application

Page 25: 2015 Deepwater Operations_Murphy_FINAL

25

Acknowledgements