13
STATE OF CALIFORNIA PUBLIC UTILITIES COMMISSION Edmund G. Brown Jr., Governor 505 VAN NESS AVENUE SAN FRANCISCO, CA 94102-3298 May 22, 2015 Susan Nelson, Project Manager Regulatory Affairs Department Southern California Edison 8631 Rush Street, General Office 4 – G10Q (Ground Floor) Rosemead, CA 91770 Re: Data Request No. 1 for the Mesa 500-kV Substation Project (CPUC Proceeding A. 15-03-003) Ms. Nelson: Upon further review of Southern California Edison’s Proponent’s Environmental Assessment (PEA) for the Mesa 500-kV Substation Project, the Energy Division requests the information contained in Attachments 1 and 2 to this letter. We request that the responses to this item be provided to us within 14 days. The Energy Division reserves the right to request additional information at any point in the process. Questions relating to the Mesa 500-kV Substation Project should be directed to me at (415) 703-1966 or [email protected]. Sincerely, MJ Orsaba Lisa Orsaba, California Public Utilities Commission Energy Division CC: Mary Jo Borak, CPUC Infrastructure Permitting and CEQA Molly Sterkel, CPUC Infrastructure Planning and Permitting Nicolas Sher, CPUC Legal Division Rachel James, Ecology and Environment, Inc. Attachment 1: Data Request #1 Attachment 2: Mesa Traffic Study Outline

2015-0522 Mesa Data Request #1 Cover Letter · 2015-07-28 · SCE Mesa 500‐kV Substation Project CPUC Data Request #1 Item # Reference/ Page # Title Request 1 PEA, 2.0 Purpose and

  • Upload
    others

  • View
    0

  • Download
    0

Embed Size (px)

Citation preview

Page 1: 2015-0522 Mesa Data Request #1 Cover Letter · 2015-07-28 · SCE Mesa 500‐kV Substation Project CPUC Data Request #1 Item # Reference/ Page # Title Request 1 PEA, 2.0 Purpose and

STATE OF CALIFORNIA

PUBLIC UTILITIES COMMISSION Edmund G. Brown Jr., Governor

505 VAN NESS AVENUE SAN FRANCISCO, CA 94102-3298

May 22, 2015 Susan Nelson, Project Manager Regulatory Affairs Department Southern California Edison 8631 Rush Street, General Office 4 – G10Q (Ground Floor) Rosemead, CA 91770 Re: Data Request No. 1 for the Mesa 500-kV Substation Project (CPUC Proceeding A. 15-03-003) Ms. Nelson: Upon further review of Southern California Edison’s Proponent’s Environmental Assessment (PEA) for the Mesa 500-kV Substation Project, the Energy Division requests the information contained in Attachments 1 and 2 to this letter. We request that the responses to this item be provided to us within 14 days. The Energy Division reserves the right to request additional information at any point in the process. Questions relating to the Mesa 500-kV Substation Project should be directed to me at (415) 703-1966 or [email protected]. Sincerely,

MJ Orsaba

Lisa Orsaba, California Public Utilities Commission Energy Division CC: Mary Jo Borak, CPUC Infrastructure Permitting and CEQA

Molly Sterkel, CPUC Infrastructure Planning and Permitting Nicolas Sher, CPUC Legal Division

Rachel James, Ecology and Environment, Inc. Attachment 1: Data Request #1 Attachment 2: Mesa Traffic Study Outline

Page 2: 2015-0522 Mesa Data Request #1 Cover Letter · 2015-07-28 · SCE Mesa 500‐kV Substation Project CPUC Data Request #1 Item # Reference/ Page # Title Request 1 PEA, 2.0 Purpose and

SCE Mesa 500‐kV Substation Project CPUC Data Request #1

Item # Reference/ Page #

Title Request

1 PEA,2.0PurposeandNeed

PowerFlowData ProvidethePowerFlowData.

2 PEA,3.0ProjectDescription,Section3.4,Page3‐2

ModificationstoExistingSubstations

Provideadetailedexplanationoftheactivitiesthatwouldbeinvolvedduringtheproposed220‐kVterminationequipmentreplacementatLagunaBellandLightpipeSubstations.Clarifyiftheproposedequipmentreplacementactivitieswouldrequireadditionaltruckandvehicletripsandtheiranticipatedduration.Inaddition,describethetypeofdisturbancethatwouldbeassociatedwiththeproposedupgradestoprotectionrelaysand/ortelecommunicationequipmentsatothersatellitesubstations.

3 PEA,3.0ProjectDescription,Section3.4,Page3‐2

ModificationstoExistingSubstations

Providetheestimatedduration,materialexcavationimport/exportquantities,andvehicleandtrucktripsrequiredfortheproposedrerouteofexistingtelecommunicationroutesinsidetheperimeterofVincent,Pardee,andWalnutSubstations.Attachment3‐BofthePEAalsomentionstheinstallationofnewconduitstoadjacenttransmissiontowerstoprovidediversefiberopticroutesintotheGoodrichSubstation.ClarifyifthisadditionalsubstationispartoftheproposedreroutesoftelecommunicationlinesinsideexistingsubstationslistedinPage3‐22ofthePEA.

4 PEA,3.0ProjectDescription,Section3.5,Page3‐2

ConversionofStreetLightSourceLine

ProvidetheestimateddurationandadetaileddescriptionoftheactivitiesandstructuresrequiredintheproposedconversionoftheexistingstreetlightsourcelineintheCityofBellGardens.

5 PEA,3.0ProjectDescription,Section3.7

HelicopterUse Page3‐84indicatesthathelicopters"mayusethepotentialstagingyardlocations,asneeded."IntheeventthestagingyardlocationsdescribedinTable3‐7cannotoptimizeflighttimetostructurelocations,clarifyifadditionalhelicopterstagingyardswouldbeused.Ifadditionalhelicopterstagingareaswouldberequired,provideapproximatesizeofsuchareas.

Submitted May 22, 2015 Page 1 of 8

Page 3: 2015-0522 Mesa Data Request #1 Cover Letter · 2015-07-28 · SCE Mesa 500‐kV Substation Project CPUC Data Request #1 Item # Reference/ Page # Title Request 1 PEA, 2.0 Purpose and

SCE Mesa 500‐kV Substation Project CPUC Data Request #1

Item # Reference/ Page #

Title Request

6 PEA,3.0ProjectDescription,Section3.4,Page3‐6

OperationandMaintenance Section3.4ofthePEAindicatesthattheproposedMesa500‐kVSubstationwouldbestaffed;however,Section3.8onlyrefersto"SwitchingCenterPersonnel,""SubstationOperationsSupervisor,""SystemOperator,"and"MaintenancePersonnel."ProvideaspecificnumberofpermanentstaffthatwouldbeworkingworkingattheproposedMesa500‐kVSubstation.

7 PEA,3.0ProjectDescription,Section3.7

RemovalofExistingStructures

Pages3‐91and3‐92ofthePEAmentionthepotentialuseofimportedfilltobackfilltheholesleftfromremovingtemporaryshoo‐flystructuresandwoodpoles.Providetheestimatedvolumethatwouldbeimportedandpotentialsourceforthismaterial.

8 PEA,3.0ProjectDescription,Section3.7

TrenchlessTechniques Page3‐100ofthePEAindicatesthatalternativetrenchlessmethodswouldbeusedtoinstallundergroundconduitswhereopen‐cuttrenchingmaynotbepermitted,fesible,orpreferred.Providetheanticipatedjack‐and‐boreandHDDlocationsfortheproposedproject.

9 PEA,3.0ProjectDescription,Section3.7,P.3‐102

HorizontalDirectionalDrilling

Provideacopyoftheproposed'frac‐out'contingencyplantobeusedduringHDDoperations.ClarifywhethertheproposedHDDoperationswouldhaveadrillingmudspillpreventionandcontrolplaninplace.

10 PEA,3.0ProjectDescription,Section3.5,P.3‐4

WoodPoleRemoval Provideestimateddateortimeframewhenthewind‐loadtestingandfinalnumberofwoodpolestoberemovedwouldbeavailable.

11 PEA,3.0ProjectDescription,Section3.7

WasteManagement Providetheestimatedquantityofsolidwastethatwouldbegeneratedbytheproposedprojecttobedisposedofatapprovedlandfills.Clarifyiftheoff‐sitedisposalfacilitieslistedinTable3‐10wouldbeusedforallproposedprojectconstructionactivities.

12 PEA,3.0ProjectDescription,Section3.4

SubstationEquipment/GreenhouseGas

ClarifyifalltheproposedMesaSubstationequipmentwouldbe100%airinsulated.Intheeventthattheproposedsubstationwouldusegas‐insulatedequiment,providetheestimatedvolumeofSF6tobestoredattheMesaSubstationsiteandtheanticipatedleakratefromgas‐insulatedequipmentduringoperations.

Submitted May 22, 2015 Page 2 of 8

Page 4: 2015-0522 Mesa Data Request #1 Cover Letter · 2015-07-28 · SCE Mesa 500‐kV Substation Project CPUC Data Request #1 Item # Reference/ Page # Title Request 1 PEA, 2.0 Purpose and

SCE Mesa 500‐kV Substation Project CPUC Data Request #1

Item # Reference/ Page #

Title Request

13 PEA,3.0ProjectDescriptionand4.16Traffic,3.7.1.1/4.16.1.1

ConstructionRoutesandStagingAreas

Confirmthattheexistingroadwaynetworkdefinedin4.16.1.1includesaccesstothestagingareasdefinedin3.7.1.1.Ifnot,definetheprobableroutesthatwillbeusedforaccesstothestagingareasandmaterialdeliveryfromthestagingareastotheconstructionsites.

14 PEA,3.0ProjectDescription,Table3‐7

StagingYards Table3‐7identifiesfourstagingyardsfortheproposedproject.Confirmthesizeandlocationofanyadditionalstagingorlaydownyardswouldbeneededfortheproposedproject.PleaseprovideGISdataforanyadditionallocationsidentifiedthatwerenotincludedintheoriginalGISdatarequest.

15 PEA,4.1Aesthetics,p.4.1‐24

NewTelecommunicationsLinesandPoles

Thedocumentstates:"Thenewtelecommunicationslineswouldbeinstalledoverheadandinexistingandnewundergroundconduitsandwouldutilizeexistingmanholesandutilitypoles.Wherenecessary,upto46utilitypolesalongtheserouteswouldbereplaced."Explainwhetherthereplacementpoleswouldbethesametypeandheight.Iftheywillbedifferent,describethedesignandheightsofthenewpolescomparedtotheexistingpolestheywouldreplace.

16 PEA,4.1Aesthetics,p.4.1‐24‐4.1‐39

MapofPhotoLocationsforTelecommunicationLines

Provideamapormapsshowingthelocationsanddirectionsofviewsofphotographs15through24.

17 PEA,4.1Aesthetics,p.4.1‐40‐4.1‐41

PotentiallyAffectedViewerGroups

Providesourcesforthedeterminationsofsensitivityforthefivepotentiallyaffectedviewergroups.Inaddition,providetheviewersensitivitylevelforthesixthgroupoffutureviewersfortheplannedretailshoppingcenter.

18 PEA,4.1Aesthetics,p.4.1‐64,footnote2

ColoringofLSTs Thedocumentstatesinfootnote2:"ColoringofLSTelementspriortoassemblywillhamperorimpedethiscontinuouselectricpathbecauseitcreatesaninsulatorbetweentheelements.ColorapplicationtoLSTstructureswouldneedtobeappliedfollowingassemblyoftheindividualpieces."Clarifyifthisstatementappliestothepre‐assemblyapplicationofcommerciallyavailabledarkeningstainsforgalvanizedsteelforLSTs.

Submitted May 22, 2015 Page 3 of 8

Page 5: 2015-0522 Mesa Data Request #1 Cover Letter · 2015-07-28 · SCE Mesa 500‐kV Substation Project CPUC Data Request #1 Item # Reference/ Page # Title Request 1 PEA, 2.0 Purpose and

SCE Mesa 500‐kV Substation Project CPUC Data Request #1

Item # Reference/ Page #

Title Request

19 PEA,4.1Aesthetics,p.4.1‐65

VegetationRemovalandPlantingAreas

Thedocumentstates:"TheProposedProjectwouldrequireremovalofsomematurevegetationandwouldalsoincludeinstallationofnewstreettreesatthesitefrontagealongPotreroGrandeDrive."Provideaplanofthesiteindicatingthelocationsofmaturevegetationtoberemovedandaconceptplanshowingareaswherenewstreettreesandothervegetationwouldbeplanted.Identifytheapproximateheight(s)orheightrangesofareasofmaturetreesthatwillberemoved.

20 PEA,4.1Aesthetics,p.4.1‐65‐4.1‐71

RelativeHeightsofExistingandNewStructures

IntheassessmentofimpactsforviewswithvisualsimulationsforKOPs1through13,anumberofreferencesaremadetoneworreplacementstructuresbeingrelatively(i.e.,"somewhat")shorterortallerthanexistingstructures.Wherethesereferencesoccur,identifytheheightsoftheexistingandnewstructuresortherelativeheightdifferences(e.g.,"threeLSTsandoneTSPreplacefiveexistingtowersthatrangebetween10and20feetshorterthanthereplacementstructures"or"thethreenewLSTswillbeapproximately20feettallerthanthefiveexistingLSTstheyarereplacing").InadditiontoheightsofLSTsandTSPs,provideapproximateorrelativeheightsoftheothermajorelementsdiscussed,includingtheswitchracks,transformerracks,operationsbuilding,testandmaintenancebuilding,andperimeterwall.

21 PEA,4.4Biology AgencyContacts ProvidethenamesandcontactinformationfortherepresenativesthatSCEconsultedwithatvariousgovernmentagencies(e.g.wildlifeagenciesandcountyandcityrepresentatives).

22 PEA,4.4Biology ConsultationwithUSACEandRWQCB

ProvideanupdateonthestatusofconsultationwiththeU.S.ArmyCorpsofEngineersregardinganyrequestforanApprovedJurisdictionalDetermination.Inaddition,provideanupdateonthestatusofconsultationwiththeCaliforniaRegionalWaterQualityControlBoardregardingjurisdictionalWatersoftheState.ThisinformationisneededtoevaluatepotentialimpactstoWatersoftheU.SandWatersoftheState.

Submitted May 22, 2015 Page 4 of 8

Page 6: 2015-0522 Mesa Data Request #1 Cover Letter · 2015-07-28 · SCE Mesa 500‐kV Substation Project CPUC Data Request #1 Item # Reference/ Page # Title Request 1 PEA, 2.0 Purpose and

SCE Mesa 500‐kV Substation Project CPUC Data Request #1

Item # Reference/ Page #

Title Request

23 PEA,4.6Geology Geo/Soils/MinResourcesReferences

ElectroniccopiesofthereferencescitedintheGeology&SoilsandMineralResourcessectionsofthePEAareneededtoverifyinformationprovidedinthePEAanddeterminewhetheradditionaldataareneeded.

24 PEA,4.8HazardsandHazardousMaterials

HazardousSubstancesOnSite

ProvidealistofhazardoussubstancescurrentlybeingstoredorusedattheMesaSubstationsite,whichwouldneedtobehandled,transported,ordisposedofaspartofthedecommissioningoftheexistingsubstation.

25 PEA,4.16Traffic,Sec.4.16.4

RoadwayRepair Describemeasurestoensureanydamagedonetoarearoadways,includingbicyclelanes,resultingfromconstructionworkwouldberepairedfollowingcompletionofprojectconstruction.

26 PEA,4.16Traffic TrafficStudy Duetothehighvolumeoftrafficduringconstruction,aTrafficStudyisrequiredtosupporttheconclusionsintheimpactanalysis.ProvideaTrafficStudybasedonthe"ProposedTrafficStudyOutline"providedasAttachment#2tothisDataRequest(DataRequest#1).TheTrafficStudyshouldbebasedontheproposedoutlinebutisnotlimitedtothedatarequestedintheoutline,shouldadditionalinformationbenecessarytosupporttheconclusionsintheTrafficStudy.TheTrafficStudymustbeoverseenorpreparedapprovedbyaTrafficEngineerpriortosubmittaltotheCPUC.

27 PEA,4.18Cumulative

CumulativeProject‐‐2015MesaSubstation66‐kVCapacitor

Provideadditionaldetailsastowhattheprojectentailsandwhenconstructionoftheprojectisanticipated.

28 PEA,4.18Cumulative

CumulativeProject‐‐NewMesaSubstationDistributionSubstationPlanCircuit

Provideadditionaldetailsastowhattheprojectentailsandwhenconstructionoftheprojectisanticipatedtostartandend.

29 PEA,4.18Cumulative

CumulativeProject‐‐HardingSubstationElimination

Provideanupdatedscheduleofwhendemolitionisanticipatedtooccurandwhenitisexpectedtobecomplete.

Submitted May 22, 2015 Page 5 of 8

Page 7: 2015-0522 Mesa Data Request #1 Cover Letter · 2015-07-28 · SCE Mesa 500‐kV Substation Project CPUC Data Request #1 Item # Reference/ Page # Title Request 1 PEA, 2.0 Purpose and

SCE Mesa 500‐kV Substation Project CPUC Data Request #1

Item # Reference/ Page #

Title Request

30 PEA,4.18Cumulative

CumulativeProject‐‐Mesa‐LagunaBellNarrows66‐kVReconductoring

Provideanupdatedscheduleofwhenreconductoringisanticipatedtooccurandwhenitisexpectedtobecomplete.

31 PEA,4.18Cumulative

CumulativeProject‐‐DistributionCircuitatWalnutGroveAvenueandLandisLane

Provideadditionaldetailsastowhattheprojectentailsandwhenconstructionoftheprojectisanticipatedtostartandend.

32 PEA,4.18Cumulative

CumulativeProject‐‐DistributionCircuitatParamountBoulevardandElbaStreet

Provideadditionaldetailsastowhattheprojectentailsandwhenconstructionoftheprojectisanticipatedtostartandend.

33 PEA,4.18Cumulative

CumulativeProject‐‐TehachapiRenewableTransmissionProject

ProvideadditionaldetailsastowhetherportionsofTRTPnearMesaSubstationwillbecompleteand,iftheyarenot,whentheywillbecompleted.ProvidedetailsaboutTRTPactivitiesoccurringnear(i.e.,within1mile)oftheMesaSubstationoranyotherprojectcomponents.

34 PEA,4.18Cumulative

CumulativeProject‐‐Mesa‐RushNo.3LineSubtransmissionReconductoring

Provideadditionaldetailsastowhattheprojectentails,theprojectalignment,andwhenconstructionoftheprojectisanticipatedtostartandend.

35 PEA,5.0Alternatives

NoProjectAlternative IftheMesaSubstationProjectisnotapproved,wouldTRTPbeconnectedtotheMesaSubstation(i.e.,wouldthesubstationbeupgraded)aspartoftheNoProjectAlternative?WhatupgradeswouldberequiredundertheNoProjectAlternativetoconnectthe500‐kVline?

36 PEA,AppendixWaterStudy

WaterStudy Thewaterstudyspecifiesthegeneralwaterusefortheproject.Providedetailsforthewateruseduringbothconstructionandoperationsothattheirseparateimpactscanbedetermined.

Submitted May 22, 2015 Page 6 of 8

Page 8: 2015-0522 Mesa Data Request #1 Cover Letter · 2015-07-28 · SCE Mesa 500‐kV Substation Project CPUC Data Request #1 Item # Reference/ Page # Title Request 1 PEA, 2.0 Purpose and

SCE Mesa 500‐kV Substation Project CPUC Data Request #1

Item # Reference/ Page #

Title Request

37 DeficiencyResponsePD‐01

EquipmentRemoval Phase1wouldinvolvetheremovalof"someequipmentstoredonsite."Clarifythetypeandquantityoftheequipmentthatwouldberemovedandtheintendeduseofthisremovedequipment(i.e.,ifreused,recycled,ordisposedofatanoff‐sitelocation).

38 DeficiencyResponsePD‐01

LandDisturbanceperPhase ProvidetheanticipatedlanddisturbanceperconstructionphasewithintheMesaSubstationsite.

39 DeficiencyResponsePD‐01

Stockpile ProvidethepotentiallocationoftheStockpileforPhase3indicatedinTable1andtheproposedmeasurestocontrolfugitivedustfromthisstockpileduringPhase2ofconstruction.

40 DeficiencyResponsePD‐01

StructurestobeConstructedperPhase

ProvidetheanticipatednumberofoverheadandundergroundstructuresthatwouldbeinstalledwithintheMesaSubstationsiteduringeachphaseofconstruction.

41 DeficiencyResponsePD‐01

RetainingWalls Providelocationsandassociatedtemporarydisturbanceareasfortheretainingwallsthatwouldbeconstructedordemolishedduringtheproposedsubstationconstructionphases.

42 DeficiencyResponseNOI‐01

ConstructionNoiseExposure DeficiencyResponseNOI‐01documentschangesintheanticipatednoiseforspecificactivitiesintheworstcasescenario(Phase1,4thquarterof2016)toevaluateconstructionnoise.ThewesternboundaryoftheproposedPhase1area(asdepictedinResponsetoDeficiencyQuestionPD‐01)wouldbeadjacenttotheBestWesternMarklandHotel(locatedat434PotreroGrandeDrive,MontereyPark,CA).Althoughhotelsarenotcommonlydefinedassensitivereceptors,workersandguestsatthishotelcouldbeexposedtonoiseandairemissionsinexcessofambientlevelsduringdaytimehours.ProvidetheestimateddurationandscopeofactivitiesproposedinthewesternboundaryofthePhase1constructionareaadjacenttotheBestWesternMarklandHotel.Inaddition,providetheanticipateddistancefromthesubstationsiteboundarywheremostoftheproposedPhase1constructionwouldoccur.

Submitted May 22, 2015 Page 7 of 8

Page 9: 2015-0522 Mesa Data Request #1 Cover Letter · 2015-07-28 · SCE Mesa 500‐kV Substation Project CPUC Data Request #1 Item # Reference/ Page # Title Request 1 PEA, 2.0 Purpose and

SCE Mesa 500‐kV Substation Project CPUC Data Request #1

Item # Reference/ Page #

Title Request

43 DeficiencyResponseAIR‐01

SensitiveReceptors TheupdatedLocalizedSignificanceThreshold(LST)analysisresultsassumepresenceofreceptorslocatedatadistanceof280feetfromtheMesaSubstationsiteand100feetfromthetransmissionandsubtransmission.Justifytheseassumptionsandprovidethelocationofthesereceptors.

Submitted May 22, 2015 Page 8 of 8

Page 10: 2015-0522 Mesa Data Request #1 Cover Letter · 2015-07-28 · SCE Mesa 500‐kV Substation Project CPUC Data Request #1 Item # Reference/ Page # Title Request 1 PEA, 2.0 Purpose and

Mesa500‐kVSubstationProjectProposedTrafficStudyOutline

1: ExecutiveSummary Brief Project Overview 

Short Discussion of Project Traffic Generation Potential 

Expected Project Impacts 

Summary of Mitigation Measures 

2: Introduction Detailed Study Methodology 

Regional Map 

General Overview of Project Site and Study Area Boundary 

o Site Layout Map  

o Existing Roadways and Intersections in the Study Area 

o Construction Routes 

3: AreaDevelopment Description of Existing Land Uses Near Project Site 

Description of Proposed Land Uses Near Project Site 

4: ExistingStreetSystem(Baseline/2015)o Roadways Used for Project Activities (Anticipated impacted roadways included below; 

Transportation Engineer to verify) 

Study Area Intersections 

East Markland Drive and Potrero Grande Drive 

Greenwood Avenue and Potrero Grande Drive 

Potrero Grande Drive and Hill Drive 

San Gabriel Boulevard and Paramount Boulevard 

Study Area Links 

Potrero Grande Drive (between East Markland Drive and Greenwood 

Avenue) (to capture impacts from substation driveway use) 

Study Area Ramps 

SR 60 (west) off‐ramp at East Markland Drive 

SR 60 (west and east) off‐ramp at Paramount Boulevard 

o Roadway Classification (per Monterey Park) 

Page 11: 2015-0522 Mesa Data Request #1 Cover Letter · 2015-07-28 · SCE Mesa 500‐kV Substation Project CPUC Data Request #1 Item # Reference/ Page # Title Request 1 PEA, 2.0 Purpose and

o Peak Hour Traffic Count  

Traffic counts can be derived from the Monterey Park Marketplace 2015 Traffic 

Impact Assessment (without project) projections if such projections reflect 

actual conditions (i.e., actual growth since 2010 and projects constructed 

nearby since 2010). If they do not reflect actual conditions, revise 2015 numbers 

to reflect actual conditions and provide the methodology for the revision. 

o Daily Traffic Volumes  

Traffic counts for 2015 can be derived from the Monterey Park Marketplace 

2015 Traffic Impact Assessment (without project) projections if such projections 

reflect actual conditions (i.e., actual growth since 2010 and projects constructed 

nearby since 2010). If they do not reflect actual conditions, revise 2015 numbers 

to reflect actual conditions and provide the methodology for the revision. 

Existing SCE Traffic Volumes to the proposed substation site 

5: TrafficGenerationForecast Projected Trip Generation Based on Construction Activity Data 

o AM peak, by construction phase 

o PM peak, by construction phase 

o Daily, by construction phase 

Mitigation Measures, if proposed 

o Projected reduction in trips at AM peak, PM peak, and daily 

6: TrafficDistributionandAssignment Utilization of Roadways by Project Traffic 

Projected Daily Link Volumes 

o For three phases of project, using worst‐case scenario 

Morning and Afternoon Peak Hour Turning Movement Volumes 

o For three phases of project, using worst‐case scenario 

Projected Freeway Ramp Volumes 

o For three phases of project, using worst‐case scenario 

7: TrafficImpactStudy/ProjectImpacts Study Area 

o Selected intersections , links, on‐ and off‐ramps as listed in section 4  

Intersection Analysis (using ICU procedure) 

o Forecasted LOS for studied intersections during three phases of project, using worst‐

case scenario (project plus baseline) 

Midblock Analysis (Links) (using HCM method) 

Page 12: 2015-0522 Mesa Data Request #1 Cover Letter · 2015-07-28 · SCE Mesa 500‐kV Substation Project CPUC Data Request #1 Item # Reference/ Page # Title Request 1 PEA, 2.0 Purpose and

o Forecasted LOS for links during three phases of project, using worst‐case scenario 

(project plus baseline) 

Ramp Analysis 

o Forecasted impacts to on‐ and off‐ramps for three phases of project, using worst‐case 

scenario (project plus baseline) 

Cumulative Analysis 

o For three phases of project, using worst‐case scenario 

o Cumulative projects may include, but not necessarily be limited to: 

Monterey Park Market Place 

TRTP 

New Mesa Substation Distribution Substation Plan Circuit 

Mesa Substation 66‐kV Capacitor 

200 East Markland Drive Specific Plan 

2015 Potrero Grande Drive Specific Plan 

Potrero Grande Drive Sewer Spot Repairs 

Montebello Hills Specific Plan 

Garfield Village Specific Plan 

8: ParkingImpacts Parking During Construction 

o Location of staging yards and other parking areas for vehicles associated with substation 

construction 

o Parking quantity 

Parking During Operation 

o Location and quantity 

9: OtherConstructionImpacts Unusual Circumstances (e.g., truck turn radius issues, use of oversize/overweight vehicles and 

any resultant safety issues, potential damage to pavement surfaces and measures for repairing 

damage) 

Impacts at non‐substation construction areas (e.g., telecom, other substations) 

o Lane closures 

o Duration of construction activities 

o Number and type of vehicles involved 

Proposed Traffic Control 

o Lane Closures 

o Construction Signage 

o Safety Features 

o Detours 

Page 13: 2015-0522 Mesa Data Request #1 Cover Letter · 2015-07-28 · SCE Mesa 500‐kV Substation Project CPUC Data Request #1 Item # Reference/ Page # Title Request 1 PEA, 2.0 Purpose and

11: MitigationMeasures Mitigation Measures to Reduce Significant Impacts to LOS, per standards in the Monterey Park 

Traffic Impact Study Guidelines 

Appendices Intersection Impacts Analysis Calculations 

HCM Link Analysis Calculations