2014 Private Sector Initiated Power Projects Luzon Committed September 30[1]

Embed Size (px)

DESCRIPTION

DOE

Citation preview

  • PRIVATESECTORINITIATEDPOWERPROJECTS(LUZON)COMMITTEDAsof30September2014

    Committed/Indicative NameoftheProject

    ProjectProponent Location

    RatedCapacity(MW)

    ProjectStatus TargetTesting&Commissioning

    TargetCommercialOperation

    COAL 1,372.00

    Committed135MWPutingBatoCoalFiredPowerPlantPhaseI

    SouthLuzonThermalEnergyCorp.(SLTEC)

    Brgy.PutingBatoWest,Calaca,Batangas

    135

    FinancialArrangementSecuredon28October2014;GISapprovedbyNGCPon17May2013;StartedConstructiononDecember2011;ConstructionDuration32Months;230kVSalongSwitchingStationownedbyNGCPistiedupwithSLTEC;230kVSalongSwitchingStationenergizedBay1;Alltestaremadeforthe230kVswitchyard;Generatorisforfinalalignment;Allmaterialsfortheprojectisforinstallation;Hydrotestandthermalinsulationinboilercompleted;OngoingairductingandinsulationforESP;EPCworksasof31August201498.88%completed;ConstructionProgress:Commissioingofinstalledequipments;Ongoingcommissioningofsteamblowing,watertreatmentandsaltwaterintake;Allmaterialsneedareinstalled;OngoingairductingandinsulationforESP;AshManagementFacilityCompletion30April2014;GroundbreakingFebruary2012;ProjectcostisPhp12.9B

    May2014 October2014

    Committed2X150MWSLPGCCoalFiredPowerPlantPhaseI

    SouthwestLuzonPowerGenerationCorporation(ProjectCompany)

    Brgy.SanRafael,Calaca,

    Batangas300

    FinancialArrangementSecuredon24February2012(60%Loan/40%Equity);GISapprovedbyNGCPon8November2011;AwaitingfortheapprovalofNGCPfortheDasmariasCalacaReinforcementandrightofwayforthetransmissionlines;Hydrotestingfortheboiler25April2014;Embeddedplateforturbine,readyforinstallationUnit1;CompleteSeawaterIntakeJune2014;OngoinginstallationforpanelsUnitII;ExpectedtocompleteCoalyardoperationbyMidMay2014;230kVSwitchyardsteelsuperstructureissubstantiallycompleted;Ongoingnegotiationswithprospectiveofftakes(DUsandthosecurrentlywithPSAsandcontestablemarketunderOpenAccessRegime;SiteMobilization/CommencementofConstructiononMay2012;ProjectProgressasof31August201486.7%;CompletedSteamTurbineBedPlateLocatingUnitII;CompletedBoilerTestHydroTestUnitII;OngoinginstallatonofCWPiping;OngoingCentralControlRoomCivilWorks;AssemblyandalignmentofturbneonSeptember2014;Ongoingerection/assemblyofgantrysteelstructure(beamandcolumns)andequipmentpedestalsteelstructure;DCSCabinetUnit1tobeenergizedbytheendofAugust2014;GroundbreakingMay2012;ProjectcostforPhaseIisPhp20.4B

    UnitI&IIDecember2014

    Unit1March2015Unit2June2015;

    Committed135MWPutingBatoCoalFiredPowerPlantPhaseII

    SouthLuzonThermalEnergyCorp.(SLTEC)

    Brgy.PutingBatoWest,Calaca,Batangas

    135

    y ;GISapprovedbyNGCPon17May2013;StartedConstructiononAugust2013;ConstructionDuration28Months;DeliveredBoilerStreamDrum22April2014;DeliveryofTurbine2ndweekofSeptember2014;EPCworksasof31August2014:64.05%completed;TurbineGenerationHouseOngoingconstruction;BoilerStructure:OngoingConstruction;Coalyard98%completed(asofAugust2014);OngoingConstruction;Downcomerpipesinstalled;AwaitingforESPstructure;ChimneyFoundtion3.7m;MaterialReceivingFacility99.59%completed;GroundbreakingTargetDateAugust2013;ProjectcostisPhp9.6B

    June2015 November2015

  • PRIVATESECTORINITIATEDPOWERPROJECTS(LUZON)COMMITTEDAsof30September2014

    Committed/Indicative NameoftheProject

    ProjectProponent Location

    RatedCapacity(MW)

    ProjectStatus TargetTesting&Commissioning

    TargetCommercialOperation

    Committed

    AndaPowerCorporation's82MWCiculatingFluidizedBedCoalFiredPowerPlant

    AndaPowerCorporation

    Brgy.Bundagul,Mabalacat,Pampanga

    82

    FinancialArrangementSecured;Ongoingnegotiationswithofftakers;AwaitingforthereviewreportofNGCPoftheSIS(Unit1tobeincludedinthesimulationintheSIS);CommencementofConstruction:March2014;TotalProjectCost$196,246,837.63;

    June2015 October2015

    Committed300MWLimayPowerPlantProjectPhaseI(2x150MW)

    SMCConsolidatedPowerCorporation

    Brgy.Lamao,Limay,Bataan 300

    FinancialArrangementSecured(65%Loan/35%Equity);EnvironmentalImpactAssessmentcompleted;TopographicandHydrographiccompleted;SoilInvestigationcompleted;GIS/SISsubmittedlast12July2013,underreviewofNGCP;Sitedevelopmentintermsofphysicalaccomplishmentasof26September2014is74.14%;ConstructionActivitiesofUnit1&22x150MWPowerPlant2.30%;DesignandConstructionofPierandJettyStructureis67.59%;EngineeringDesign&ManufacturingofParts71.49%;AshDumpDesignandConstruction100%;FacilityStudyalreadysenttoNGCPforreview;EPCwasexecutedinJanuary2013;ECCwasissuedonSeptember2013;ConstructionoftheProjecthasbeenunderwaysinceJanuary2014SECissuedlast19August2011;Landacquisitioncompleted;Ongoingelectricpowersupplycontractnegotiationwithprospectiveofftakers(DUs);ClearancetoUnderatakeGISfromDOEissuedon13February2013;Projectcostis$622.15M/Php25.508B

    Unit1150MWMarch2016Unit2150MWJuly2016

    Unit1150MWMay2016Unit2150MWSeptember2016

    Committed1x420MWPagbilaoCoalFiredThermalPowerPlant

    PagbilaoEnergyCorporation

    PagbilaoPowerStation,Nrgy.IbabangPolo,Pagbilao,

    Quezon

    420

    FinancialArrangementSecuredwithvariouslenderson30July2014;Allconditionsprecedenthavebeenfulfilled/satisfied;Firstandseconddrawdownscompleted;EstimatedNetCapacity:400MW;FeasibilityStudycompleted;MarketingofGeneratingCapacities:Contractwithofftakerscompleted,Suppyagreementexecuted;Permits&OtherRegulatoryRequirements:EnvironmentalComplianceCertificatewasissuedon18June2013;SecuredendorsementfromSangguniangBarangayofIbabangPolo,SangguniangBayanofPagbilao,SangguniangPanlalawiganofQuezon;InfinalnegotiationswithNPC,PSALM,TeaMEnergyCorporationandThermaLuzon,Inc.tocolocatetheplantintheexistingPagbilaoPowerStation;MarketingofGeneratingCapacities:50%oftheplant'scapabilitywillbesoldtoThermaLuzinInc.andother50%willbesoldtoTeaM(Phils.)EnergyCorporation;ConstructionContractsforPlant&Equipment:Completedandexecuted;NoticetoProceedandCommencementNoticeissuedtoEPCContractor;DownPaymentalreadyreleasedtoEPCcontractor;TargetCommencementofEPCandConstruction:30May2014;GroundBreakingDate:23July2014EstimatedProjectCost:US$1,000,000,000.00

    BetweenMaytoNovember2017 November2017

  • PRIVATESECTORINITIATEDPOWERPROJECTS(LUZON)COMMITTEDAsof30September2014

    Committed/Indicative NameoftheProject

    ProjectProponent Location

    RatedCapacity(MW)

    ProjectStatus TargetTesting&Commissioning

    TargetCommercialOperation

    NATURALGAS 1,150.00

    Committed

    Pagbilao600MWCombinedCycleGasFiredPowerPlant

    Proposed3x200MWCCGTPowerPlant

    EnergyWorldCorporation

    Brgy.IbabangPolo,Grande

    Island,Pagbilao,Quezon

    600

    FinancialArrangementSecured:Financingequitywillbe100%sourcedfromEWC;GISfor300MWissuedbyNGCPon8August2013andrevisedon3July2013for600MW;IssuedDOEEndorsementforRevisedCapacityon3July2013;RevisedDOEclearanceforGISsubmittedtoNGCPonJanuary2014;GISfromNGCPforthe600MWwasreleasedonAugust2014;Landisalreadysecuredwithalongleaseenteredintosince2007;CommencementofConstruction:December2013;Offtaker:NospecificofftakeryetbutalreadyhaveadiscussionwithFederationofPhilippineIndustries,intendedtosupplypowerintotheWholesaleElectricitySpotMarketbutisalsoopentodiscussingpotentialofftakearrangementsaswell;PerrmitsandRegulatoryRequirements:SeveralResolutionshasbeenissuedonMay2014(SangguniangBarangayResolution,SangguniangBayanResolutionandSangguniangPanlalawiganResolution)interposingnoobjectionfortheconstructionofa600MWLiquifiedNaturalGas(LNG)PowerPlant;OngoingprocessingofECCforpowerplant;OngoingprocessingEnteredintoaSaleandPurchaseAgreementlastOctober2012withSiemensEnergyfortwo200MWgasturbinesandthefirst200MWturbineisexpectedtoarrivebySeptember2014;LNGTankiscurrentlyat50%constructioncompletedasofAugust2014;ProjectCost:$300M

    January2015:1stUnit200MW,'Dec2015:2ndUnit200MW'Dec2016:3rdUnit200MW

    FebruaryMarch:1stUnit200MW,'Dec2015:2ndUnit200MW'Dec2016:3rdUnit200MW

    Committed 100MWSanGabrielAvionProject

    PrimeMeridianPowerGenCorporation(ProjectCompany)FirstGen

    Corporation

    BarangayBolbok,Batangas

    100

    FinancialArrangementSecured:SecuredClearancefromDOEfortheconductofGISon21June2011;SystemImpactStudy(SIS)wascompleted;AmendmentofPhilippinePortsAuthority(PPA)chartertoaccomodatefortherightofwayfortheprojectsiteisstillforapprovalbytheOfficeofthePresident;EngineeringanddesignbytheContractorsisongoingfinalizationwithparallelreviewsbeingperformedbyPMPCanditsTechnicalConsultants;ExcavationandgroundpreparationworksbytheEPCcontractorareongoing;Procurementofplantequipmentiscontinuing,withmostofthemajorpowerplantcomponentseitherbeingmanufacturedorarescheduledfordeliverytothesite;Deliveryofthefirstoftwo(2)GasTurbineandsomeanicillaryeuipmenthavearrivedatthePortofBatangason5October2014andareexpectedtobedeliveredtothesiteby24October2014;Shipmentofthe2ndGasTurbineandancillaryequipmentisexpectedtoarriveattheprotofBatangasbytheendofOctober2014;AlltestareconductedsuchasSeismic,GeologicalandHydrotests;Seven(7)polesaretobesetupforthetransmissionlines;SigningofContractwithMeiscorfortheconstructionoftransmissionlineApril22,2014;CommittedArrivaloftheTurbineSeptember2014;Offtaker:Discussionwithtargetofftakersongoing;CommencementofConstructionwillbeonOctober2013;ProjectcostisPhp10B

    April2015(TargetCommercialOperation)

    April2015

    Committed1x450SanGabrielPowerPlant(PhaseII)

    FirstNatGasPowerCorp.

    SanGabriel,Batangas 450

    FinancialArrangementSecuredon10July2014:SecuredClearancefromDOEfortheconductofGISon18February2013;SISwasapprovedbyNGCPon11December2013.;CommencementofConstruction:December2013;Offtaker:Discussionwithtargetofftakerstargetedforthefirsthalfof2014;ConstructionoftheProjecthasbeenprogressingwithistepreparationandfoundationworks;ProjectcostisUS$600Million;

    January2016 March2016

  • PRIVATESECTORINITIATEDPOWERPROJECTS(LUZON)COMMITTEDAsof30September2014

    Committed/Indicative NameoftheProject

    ProjectProponent Location

    RatedCapacity(MW)

    ProjectStatus TargetTesting&Commissioning

    TargetCommercialOperation

    HYDROPOWER 34.30

    Committed Sabangan HedcorSabangan,Inc.Sabangan,

    Mt.Province 13.2

    FinancialArrangementSecured;GroundbreakingheldonJune2013;IssuedConfirmationofCommercialityon28August2013;Ongoingconstruction(Preconstruction100%,Construction23.38%,Interconnection0%)completedasof30September2014;SecuredClearancefromDOEfortheconductofGISon18June2012;

    June2015

    June2015(TargetTestingandCommissioning)

    Committed Inabasan OrminPower,Inc.

    SanTeodoro,OrientalMindoro

    10.0

    FinancialArrangementSecured;Groundbreakingheldon29July2013;IssuedConfirmationofCommercialityon28May2013;AlreadysecuredDENRECC,NCIPCertificate,andNWRBPermit;SubmittedFeasibilityStudy,DetailedEngineeringDesignand5YrWorkPlan.

    December2015

    December2015(TargetTestingandCommissioning)

    Committed Catuiran Sta.ClaraPowerCorp.

    Naujan,OrientalMindoro

    8.0

    FinancialArrangementSecured;GroundbreakingheldinJanuary2013;IssuedConfirmationofCommercialityon07February2013;Submissionlackingrequirementse.g.permitsinprogress.

    March2016

    March2016(TargetTestingandCommissioning)

    Committed LinaoCawayan (UpperCascade)

    OrientalMindoroElectricCooperative,Inc.

    Baco,OrientalMindoro 2.1

    FinancialArrangementSecured;Ongoingconstruction;AlreadysecuredLGUEndorsement,DENRECC,NWRBCWP,NCIPComplianceCertificate;SubmittedFeasibilityStudyand5YrWorkPlan.FinancingfromDBP;ProjectcostPhP293M.

    March2016

    March2016(TargetTestingandCommissioning)

    Committed BulanaoDPJEngineersandConsultants

    Tabuk,Kalinga 1.0

    FinancialArrangementSecured;IssuedConfirmationofCommercialityon11March2014;AlreadysecuredNCIPclearance,DENRPermits,ESAwithKalingaApayaoElectricCooperativeInc.,LandleaseAgreement;Ongoingconstructionofintakestructureandwithpurchaseorderfortheturbinegeneratorsystem;SubmittedFeasibilityStudyand5YrWorkPlan.FinancingfromDBP;ProjectcostPhP293M.

    TBD TBD

  • PRIVATESECTORINITIATEDPOWERPROJECTS(LUZON)COMMITTEDAsof30September2014

    Committed/Indicative NameoftheProject

    ProjectProponent Location

    RatedCapacity(MW)

    ProjectStatus TargetTesting&Commissioning

    TargetCommercialOperation

    SOLAR 50.00

    CommittedCaviteEconomicZone(CEZ)SolarRooftopPowerProject

    MajesticsEnergyCorporation

    CaviteEconomic

    ZonesIandII,RosarioandGen.Trias,Cavite

    40

    FinancialArrangementSecured100%Equity;AwardedwithSolarEnergyServiceContract(SESCNo.201310040)on30October2013;SecuredThirdPartySystemImpactStudy,ECC/CNCfromDENR,CNOfromNCIP,ProvincialResolutionsofSupport,CertificateofRegistrationfromPEZA,andEPCContract;AcquiredDOECertificateofConfirmationofCommercialityon27June2013;Completedtechnicalstudy;Ongoingconstructionasof30September2014(PreConstruction90%complete,Construction88%complete,Interconnection85%complete;)OngoingnegotiationforConnectionAgreementwithNGCP;OngoingconstructionofitsBalanceofSystems(BOS);Ongoingconstruction;

    October2014

    October2014(TargetTestingandCommissioning)

    Committed PampangaSolarPowerProjectRaslagCorporation

    Brgy.Suclaban,Mexico,Pampanga

    10

    FinancialArrangementSecured;AwardedwithSolarEnergyServiceContract(SESCNo.201401062)on05February2014;SecuredECCfromDENR,MunicipalandBarangayResolutionofSupport,DARConversionofLandUsefromAgriculturaltoIndustrial,ThirdPartyDistributionImpactStudy,andownershipofland;CompletedtheFullBlownFeasibilityStudy;EPCContractisundernegotiation;Ongoingconstructionasof30September2014(PreConstruction85%complete,Construction8%complete,Interconnection0%complete;FinancialClosingisundernegotiation;DeclarationofCommercialitysubmittedon28February2014;AcquiredDOECertificateofConfirmationofCommercialityunderFITSystemon13June2014;RequestforAmendmentofCoCoCfrom8MWto10MWon13August2014;OngoingacquisitionofrelevantpermitsunderPreConstructionStageasperWorkPlan;Filedarequestforendorsementtoavailthedutyfreeimportation;

    December2014

    December2014(TargetTestingandCommissioning)

    WIND 317.40

    CommittedPhase3:BanguiBayWindPowerProject

    NorthWindPower

    DevelopmentCorporation

    Bangui,IlocosNorte 18.9

    FinancialArrangementSecuredwithaBankdated15July2013;CoveredbyWESCNo.201307058dated26February2013;Conducteddetailedwindresourceassessment;Completeddetailedfeasibilitystudy;AcquiredvariousLGUpermitsandresolutionsofsupport,NCIPCertificateofNonOverlap,DENRAmendedEnvironmentalComplianceCertificateandCAAPHeightClearancepermit;SecuredClearancefromDOEfortheconductofGISon12February2013;AcquiredDOECertificateofConfirmationofCommercialityon03December2013;AmendedtheCoCoCinordertorefecttheimprovedcapacityfrom18Mwto18.9MWon10September2014);Ongoingconstructionasof30September2014(PreConstruction100%complete,Construction98%complete,Interconnection100%complete;OngoingcivilworksforaccessroadsandWTGFoundations;asof30Septmber2014Completed6outof6WTGFoundations;Ongoingcompletion/acceptanceofSCADAwithNGCP;Erected6WTG;OngoinginstallationofBalanceofPlantequipment;AcquiredDOECertificateofConfirmationofCommercialityon03December2013TotalprojectcostisUS$48.5Million.

    September2014

    September2014(TargetTestingandCommissioning)

    CommittedPhase1:BurgosWindPowerProject

    EDCBurgosWindPowerCorporation

    NagsurotSaoit,Burgos,IlocosNorte

    87

    FinancialArrangementSecured:Issuedcertificationdated13March2013thatEDC,itsparentcompany,hasthecapacitytofinancetheproject;100%equityfinanced;:AwardedwithWindEnergyServiceContract(WESCNo.200909004)on14Sept2009;Conducteddetailedwindresourceassessment;AcquiredvariousLGUpermitsandresolutionsofsupport,DENREnvironmentalComplianceCertificate,NCIPCertificateofNonOverlap,LandLeaseAgreementwithprivatelandowners,ForestLanduseAgreementwithDENRforpublicland,DARlanduseconversionandexemptionfromCARPandCAAPHeightClearancepermit;FinalReportofSISandConnectionAgreementwithNGCPsecured;Supply,EPCandServiceEnergyBasedAvailabilityAgreementwiththeconsortiumofVestasandFirstBalfuorsecured;ConductedGroundbreakingCeremonyon17Apr2013;Ongoingconstruction;ConstructionStageasofasof30September2014(PreConstruction100%completed,Construction83%completed,Interconnection83%completed);OngoingacquisitionofTLROW;Completedthe29WTGfoundations;Erectedthe29WTG;OngoingconstructionofsubstationandTL;TotalprojectcostisUS$291Million;AcquiredDOECertificateofConfirmationofCommercialityon16May2013;

    November2014

    November2014(TargetTestingandCommissioning)

  • PRIVATESECTORINITIATEDPOWERPROJECTS(LUZON)COMMITTEDAsof30September2014

    Committed/Indicative NameoftheProject

    ProjectProponent Location

    RatedCapacity(MW)

    ProjectStatus TargetTesting&Commissioning

    TargetCommercialOperation

    Committed CaparispisanWindEnergyProject

    NorthernLuzonUPCAsia

    Corporation

    Brgy.Caparispisan,Pagudpud,IlocosNorte

    81

    FinancialArrangementSecured:SubmittedacertificationfromvariousBanksdated12July2011;AwardedwithWindEnergyServiceContract(WESCNo.200909005)on14Sept2009;Conducteddetailedwindresourceassessment;Conducteddetailedwindresourceassessment;Completeddetailedfeasibilityatudy;AcquiredvariousLGUpermitsandresolutionsofsupport,NCIPCertificateofNonOverlapon10Apr2007,ForestLanduseAgreementwithDENRon20May2009,DENREnvironmentalComplianceCertificateon23Jul2009,DPWHRoadRightofWayforT/Lconstruction,andCAAPHeightClearancepermit;FinalReportofSISandConnectionAgreementwithNGCPsecuredon4Jan2011;BOIRegisteredon23Jun2011;AcquiredDOECertificateofConfirmationofCommercialityon2July2013;ConstructionStageoverall80.9%asof30September2014(PreConstruction99%completed,Construction85%,Interconnection59%);OverallAccomplishments:72.92%completedasof31August2014;OngoingacquisitionofTLROW;Ongoingcivilworksforaccessroads;Completed16outof27WTGFoundations;AcquiredDOECertificateofConfirmationofCommercialityon2July2013;Erectedthe27WTG;OngoingconstructionofTLROWasperWorkPlan;TotalprojectcostisUS$255Million..

    November2014

    November2014(TargetTestingandCommissioning)

    CommittedPhase2:BurgosWindPowerProject

    EDCBurgosWindPowerCorporation

    NagsurotSaoit,Burgos,IlocosNorte

    63

    'CoveredbyWESCNo.200909004;FinancingArrangements:100%equityfinancedsubjectavailableinstallationtarget;CoveredbyalllocalpermitsacquiredbythePhase1Project;OtherrelevantstudiesandpermitssuchasSystemImpactStudyandConnectionAgreementwithNGCPandEPCContractswerecoveredbytheApproved5YearWorkPlan;100%equityfinancedsubjecttoavailableinstallationtarget.;AcquiredDOECertificateofConfirmationofCommercialityon03December2013;Ongoingconstruction;ConstructionStageasof30September2014(PreConstruction100%completed,Construction80%completed,Interconnection100%completed);OngoingcivilworksforaccessroadsandWTGfoundations;TotalProjectCostisUS$167.58M;

    December2014

    December2014(TargetTestingandCommissioning)

  • PRIVATESECTORINITIATEDPOWERPROJECTS(LUZON)COMMITTEDAsof30September2014

    Committed/Indicative NameoftheProject

    ProjectProponent Location

    RatedCapacity(MW)

    ProjectStatus TargetTesting&Commissioning

    TargetCommercialOperation

    CommittedPhase1:PilillaWindPowerProject

    AlternergyWindOneCorporation

    67.5

    'FinancialArrangementSecuredAWOCtofinancetheimplementationoftheprojectwith100%equity;AwardedwithWindEnergyServiceContract(WESCNo.200909018)on23Oct2009;AcquiredvariousLGUpermitsandresolutionsofsupport,DENREnvironmentalComplianceCertificate,NCIPCertificateofNonOverlap,ContracttoBuywithprivatelandowners,andclearancesfromDAR,NIA,LRA,HLURB,andLagunaLakeDevelopmentAuthority;InterconnectionAgreementwithMERALCOsecuredon1Mar2012;Regulatoryrequirements,permits,GIS,etc.werecompleted;EPCandO&MContractwithconsortiumofNordexSEandMcConnellDonnellsecuredon11Jul2012;SecuredClearancefromDOEfortheconductofGISon21November2011;NGCPReviewofThirdPartySISsecuredon31Jul2012;AcquiredDOECertificateofConfirmationofCommercialityon16May2013;ConductedGroundbreakingCeremonyon18Jun2013;Ongoingconstructionasof30September2014(PreConstruction100%complete,Construction5%,Interconnection0%);Startedcivilworksonaccessroad;AmendedtheContractAreaandassignedfullytoAWOCWESCNo.200909018AF1on27February2014;TotalprojectcostisUS$177.9Million;

    July2015

    July2015(TargetTestingandCommissioning)

  • PRIVATESECTORINITIATEDPOWERPROJECTS(LUZON)COMMITTEDAsof30September2014

    Committed/Indicative NameoftheProject

    ProjectProponent Location

    RatedCapacity(MW)

    ProjectStatus TargetTesting&Commissioning

    TargetCommercialOperation

    BIOMASS 59.73

    Committed

    24MWSJCiPowerRiceHuskFiredBiomasspowerPlantProject(Phase112MWPhase212MW)

    SanJoseCityIPower

    Corporation

    Brgy.Tulat,SanJose,

    NuevaEcija20.00

    'FinanciallyClosed;BREOCNo.201101013;Preconstruction(100%completedasof31August2014);PhaseIEstimatedAccomplishmentofConstruction98%completedasof31August2014);Remainingmajorequipmentinprogressistheinstallationoftravellinggate;Ongoinginstallationsofthefeedwaterpipingsystem,chemicaldosingpipeline,threecontrolelementsoftheboilerandotherfieldinstruments;ExpectedarrivalofswitchyardisonMay2014;Interconnection(100%completedasof31August2014);Construction(Ongoingconstructionasof30September2014PreConstruction100%;Construction98%;Interconnection100%);PermitsobtainedECC,LGU,LandUsePermit)EPCw/EngconofSingapore;SecuredClearancefromDOEfortheconductofGISon21July2011;IssuedCertificateConfirmationofCommercialityon2Sept2013;Groundbreakingon12Oct2013;Proj.CostPhp1.234B

    Phase1September2014

    Phase2December2014(SubjecttoFIT)

    Phase1October2014

    Phase2December2014(SubjecttoFIT)

    Committed12.5MWBataan2020RicehullfiredCogenPlant

    Bataan2020Inc. Bataan 7.50

    FinanciallyClosed;BREOCNo.201001008;IssuedCertificateConfirmationofCommercialityon27August2013;100%Constructed&Operational(OperatingforOwnUse);Interconnection80%completedasof30September2014;

    October2014

    December2014(TargetTestingandCommissioning)

    Committed 20MWRuskFiredBiomassPowerPlant

    IsabelaBiomassEnergy

    CorporationAlicia,Isabela 18

    FinanciallyClosed;BREOCNo.201303030;IssuedCertificateConfirmationofCommercialityon6January2014;Ongoingconstructionasof31August201449%completed;Preconstruction95%completed;Interconnection2%completed;SteamTurbineGenerator(STG)forconcreting;FuelStoragewithpartialroofing;AwaitingpermitfromDPWHfortheconstructionofdrainagesystem;Permitsobtained(ECC,LGUEndorsement,LandUsePermit,etc.);SecuredClearancefromDOEfortheconductofGISon22April2013;IssuedDeclarationofCommercialityon6January2014;HasEPC;ProjectStatusasof30September2014:Preconstruction:95%;Construction:49%;Interconnection2%;SubjecttoFIT;ProjectcostisPhp1.9B

    March2015(SubjecttoFIT)

    March2015(SubjecttoFIT)(TargetTestingandCommissioning)

    Committed 12MWBiomassPowerPlantProject

    GreenInnovationsforTomorrowCorporation

    NuevaEcija 10.80

    FinanciallyClosed;BREOCNo.201309037;ProjectStatusasof30September2014:PreConstruction:79%;Construction:18%;Interconnection:0%IssuedDeclarationofCommercialityon16June2014;Ongoingconstruction

    December2015 Jnauary2016

    Committed 3.5MWBicolBiomassEnergyCorporation

    BicolBiomassEnergy

    CorporationCamarinesSur 3.15 FinanciallyClosed;

    Ongoingconstruction December2015

    December2015(TargetTestingandCommissioning)

    Committed0.4MWVMAgbayaniRiceMillRiceHuskFiredPowerPlant

    V.M.AgbayaniRiceMill

    OrientalMindoro 0.28

    FinanciallyClosed;Ongoingconstruction;

    TotalCommittedRatedCapacity 2,983.43