PMS101 Planning and Controlling By Heru Winarto

2013-06-20 Modul Pengajaran Instruktur-Heru PMS101

  • Upload
    yohanes

  • View
    24

  • Download
    4

Embed Size (px)

DESCRIPTION

Primavera 101;Learn about Project Planning And Controlling;OBS (Organizational Breakdown Structure),EPS (Enterprise Project Structure)OBS, EPS, Project, WBS Interrelationships

Citation preview

  • PMS101 Planning and Controlling

    By Heru Winarto

  • Agenda Hari 1

    08:30 09:00 Pre Test Planning and Controlling

    Registration B0 Profile

    09:00 - 10:15 Training in the Classroom

    10:15 10:30 Break 1

    10:30 12:00 Training in the Classroom

    12:00 13:00 Lunch Break

    13:00 15:00 Training in the Classroom

    15:00 15:15 Break 2

    15:15 17:00 Training in the Classroom

    PMS101 Planning and Controlling

  • Agenda Hari 2

    08:30 - 10:15 Training in the Classroom

    10:15 10:30 Break 1 and Foto Group

    10:30 12:00 Training in the Classroom

    12:00 13:00 Lunch Break

    13:00 15:00 Training in the Classroom

    15:00 15:15 Break 2

    15:15 16:30 Training in the Classroom

    16:30 17:00 Evaluation (Post Test) & Questioner

    PMS101 Planning and Controlling

  • PRIMAVERA Project Planning ( Primavera P6 R8.3 )

    Project Portfolio ManagementPPM : - Client Base (Desktop / Client Server)

    Enterprise Project Portfolio ManagementEPPM : - Client Base (Client Server)

    - Web Base (Intranet / Internet)

    Lain-lain :

    - PRIMAVERA Risk Management v.8.7

    - ABC ( Activity Base Cost Estimate ) API P6 R?- Naviswork (Autodesk) Primavera (Planning)

    Produk PRIMAVERA

  • PRIMAVERA P6 R8.? :

    I. Microsoft Database

    MS SQL SERVER 2008 > (Server)

    II. Oracle Database

    ORACLE 10g Express Edition (Standalone)- PPM (Include Database)- Max Space 2 GByte

    ORACLE 10g Database Server > (Server)- EPPM (Not Include Database)

    Media Penyimpanan Data

  • Flowchart Project Planning

  • Flowchart Project Control

  • OBS (Organizational Breakdown Structure)

  • EPS ( Enterprise Project Structure )

  • Legend

    OBS Elements"Program"Managers

    ProjectA

    ProjectB

    ProjectC

    TeamLeader

    EPS

    WBSA.1

    WBSA.1

    WBSA.2

    WBSA.2

    WBSA.3

    WBSA.3

    OBS Elements"Project"

    Managers

    OBS

    EPSNode

    EPSNode

    EPSNode

    TeamLeader

    TeamLeader

    Enterprise Project Structure (EPS)

    Project

    WBS

    Organization Breakdown Structure (OBS)

    OBS, EPS, Project, WBS Interrelationships

  • Format :

    Setting User Preference

  • Format :

    Setting User Preference

  • Format :

    Setting User Preference

  • Format :

    Setting User Preference

  • Format :

    Setting User Preference

  • Project Definition :

    EPS : RamaProject Id : Rama EastProject Name : Rama Office Building EastPlanned Start : 12 Feb 2013 9:00 AMProject Finish : ?

    Create Project

  • Work Breakdown Structure

  • Calendar Definition :

    Hari kerja dimulai Senin sampai Jumat

    Satu hari kerja 8 jam

    Jam Kerja Dimulai dari Jam 9:00 AM sampai Jam 18:00 PM

    Kalender ini mempunyai hari libur sebagai berikut :

    Calendar

    01 January 2013 12 March 2013 29 March 2013

    09 May 2013 06 June 2013 25 Desember 2013

  • UnIts

    - % Complete Type = Physical

    - Duration Type = Fixed Duration &

    - Activity Calendar = Office 5 Day

    Calendar

    Activity , Steps & Relationships

  • Activity & Relationships - Lag

  • PROJECT

    EPS : RamaProject Id : Rama EastProject Name : Rama Office Building EastPlanned Start : 12 Feb 2013 09:00 AMProject Finish : 14 Nov 2013 06:00 PM

    Project Scheduling

  • Update Schedule

    Please make sure for activity A1110, specify Remaining Duration as 6d

    8027-Jun-13 09:00Form/Pour Basement Slab and FloorsA111010026-Jun-13 18:0007-Jun-13 09:00Floor DeckingA110010004-Jun-13 18:0007-May-13 09:00Erect Structural FrameA1090210006-May-13 18:0003-May-13 09:00Backfill and Compact FillsA108010002-May-13 18:0025-Apr-13 09:00Form/Pour Concrete SlabA107010024-Apr-13 18:0011-Apr-13 09:00Form/Pour Concrete WallsA106010010-Apr-13 18:0027-Mar-13 09:00Form/Pour Concrete FootingsA105010026-Mar-13 18:0013-Mar-13 09:00Install Underground Electrical ConduitA104010026-Mar-13 18:0013-Mar-13 09:00Install Underground Water LinesA103010011-Mar-13 18:0026-Feb-13 09:00ExcavationA1020

    10025-Feb-13 18:0012-Feb-13 09:00Site PreparationA101010012-Feb-13 09:00Begin ConstructionA10001%FinishesStartedActivity NameAct IDWBS

    The Activities Completed and in Progress are as shown

  • Apply Actual

  • Activity Code

  • Assignment Activity Code

  • Tampilkan seluruh data Activity yang terkelompokdalam WBS Structure saja

    I. Latihan Group & Sort

  • Tampilkan seluruh data Activity yang terkelompokdalam WBS Exterior dan Interior saja

    II. Latihan Group & Sort

  • Buatlah Filter untuk menampilkan data Activity yang mempunyai Activity Code Finishing Work (FW) saja

    III. Latihan Filter

  • Buatlah Filter untuk menampilkan data Activity yang mempunyai Activity Code Civil Work (CW) dan

    Finishing Work (FW)

    IV. Latihan Filter

  • Buatlah Filter untuk menampilkan data Activity yang dimulaidengan Kode Depan Activity A10.. saja

    Contoh : A1000A1010A1020

    - - -

    A1090dst

    V. Latihan Filter

  • eMail : [email protected]

    Telp : Hp : 081905002979Telp : 021-5805828 - 29

  • Others :

  • Relationship & Lag Time

    FS ( Finish to Start )

    FF ( Finish to Finish )

    SS ( Start to Start )

    SF ( Start to Finish )

    Lag Time ( Negative ) Lag Time ( Positif )

  • Relationship FS

    FS ( Finish to Start )

    FS (Finish to Start)Suatu kegiatan baru dapat dikerjakan jika kegiatan sebelumnya telahselesai.Misalnya : kegiatan pondasi baru dapat dimulai setelah galian

    selesai

  • Relationship FF

    FF (Finish to Finish)Suatu kegiatan harus selesai bersamaan dengan selesainya kegiatanlain.Misalnya : kegiatan taman selesai bersamaan dengan kegiatan pagar

    FF ( Finish to Finish )

  • Relationship SS

    SS (Start to Start)Suatu kegiatan harus dimulai bersamaan dengan kegiatan lainnya.Misalnya : kegiatan pembersihan lapangan bersamaan dengan

    kegiatan direksikeet

    SS ( Start to Start )

  • Relationship SF

    SF ( Start to Finish )Suatu kegiatan baru dapat diakhiri jika kegiatan lain dumulaiMisalnya : kegiatan start engine

    SF ( Start to Finish )

  • Lag Time

    Lag Time NegatifUntuk menghemat waktu yang dibutuhkan dalam penyelesaianSuatu kegiatan

    Lag Time Negatif

  • Lag Time

    Lag Time PositifTenggang waktu antara penyelesaian kegiatan pertama denganpelaksanaan kegiatan berikutnya

    Lag Time Positif

  • Indikator Perhitungan

    Durasi (D) = waktu yang diperlukan untuk melaksanakan kegiatanEarliest Start (ES) = saat paling cepat kegiatan tersebut dilaksanakanEarliest Finish (EF) = saat paling cepat kegiatan tersebut diselesaikanLatest Start (LS) = saat paling lambat kegiatan tersebut dilaksanakanLatest Finish (LF) = saat paling lambat kegiatan tersebut diselesaikanFree Float (FF) = jumlah waktu tunda atau memperpanjang waktu

    kegiatan tanpa mempengaruhi waktu awal kegiatan berikutnyaTotal Float (TF) = jumlah waktu waktu tunda atau memperpanjang waktu

    kegiatan tanpa mempengaruhi akhir proyek

    Rumus : EF = ES + D FF = ES EFLS = LF D TF = LF - EF