2012 Planned Facilities Reconstruction Project

2012 Planned Facilities Reconstruction Project. Planned Facilities Reconstruction Health & Life Safety Energy Conservation & Management Security Upgrades

Embed Size (px)

Citation preview

Page 1: 2012 Planned Facilities Reconstruction Project. Planned Facilities Reconstruction Health & Life Safety Energy Conservation & Management Security Upgrades

2012 Planned Facilities Reconstruction Project

Page 2: 2012 Planned Facilities Reconstruction Project. Planned Facilities Reconstruction Health & Life Safety Energy Conservation & Management Security Upgrades

Planned Facilities Reconstruction

• Health & Life Safety• Energy Conservation & Management• Security Upgrades• Reconstruction• Sitework

Page 3: 2012 Planned Facilities Reconstruction Project. Planned Facilities Reconstruction Health & Life Safety Energy Conservation & Management Security Upgrades

Why Do We Need A Capital Project?• State Education Department Requirements• Manual Of Planning Standards• NYS Building Codes• Fire Inspections (Annual)• Visual Inspections (Annual)• Building Condition Survey (5 Year)• 5 Year Capital Plan• NYCRR Part 155 Regulations of CommissionerThe School District is Required to Maintain the Buildings and Grounds to Certain

Standards to Provide a Healthy & Safe Learning Environment

Page 4: 2012 Planned Facilities Reconstruction Project. Planned Facilities Reconstruction Health & Life Safety Energy Conservation & Management Security Upgrades

The “Value” of Planned Facilities Construction Projects

A PLANNED CONSTRUCTION PROJECT PREVENTS THE IMPACT ON OUR DAY TO DAY OPERATIONAL BUDGET

PLANNED FACILITIES RECONSTRUCTION PROJECT

GENERAL IN-HOUSE PROJECT (LOCAL TAX BASE)

COST

FUNDING REIMBURSED BY SED (83% +/- BUILDING AID)

FUNDING FROM DESIGNATED CAPITAL/REPAIR RESERVE

NECESSARY GENERAL FUNDS (LOCAL TAX)

$2,700,000

$2,241,000

$459,000

$0

$2,700,000

$0

$1,000,000

$1,700,000

Page 5: 2012 Planned Facilities Reconstruction Project. Planned Facilities Reconstruction Health & Life Safety Energy Conservation & Management Security Upgrades

All District Buildings

• Public Address/Clock System-Systems are currently serviced by different vendors

-MHS is currently functioning on two separate schedules

• Stone Joint Replacement• Parking Lot Repair

Page 6: 2012 Planned Facilities Reconstruction Project. Planned Facilities Reconstruction Health & Life Safety Energy Conservation & Management Security Upgrades

Middle/High School & Fenner Elementary

PARKING LOT REPAIRBold = Areas of Work

Page 7: 2012 Planned Facilities Reconstruction Project. Planned Facilities Reconstruction Health & Life Safety Energy Conservation & Management Security Upgrades

Temple Elementary

PARKING LOT REPAIRBold = Areas of Work

Page 8: 2012 Planned Facilities Reconstruction Project. Planned Facilities Reconstruction Health & Life Safety Energy Conservation & Management Security Upgrades

Middle/High School

• Terrazzo Reconstruction (1935)• Asbestos Floor Tile Removal (1967)• Ceramic Tile Replacement (1967)• Stair Tread Replacement• Exhaust Fan Replacement (1967)• Upgrade Security Entrance Access

Page 9: 2012 Planned Facilities Reconstruction Project. Planned Facilities Reconstruction Health & Life Safety Energy Conservation & Management Security Upgrades

Fenner Elementary

• Replace Roof (1989)• Replace Interior Gym Doors• Replace Interior Door Hardware (1989)• Replace Boiler & Water Heater• Upgrade HVAC Controls• Upgrade Security System• Repair Sidewalks

Page 10: 2012 Planned Facilities Reconstruction Project. Planned Facilities Reconstruction Health & Life Safety Energy Conservation & Management Security Upgrades

Temple Elementary

• Upgrade Security System• Replace Exhaust Fans• Repair Sidewalk

Page 11: 2012 Planned Facilities Reconstruction Project. Planned Facilities Reconstruction Health & Life Safety Energy Conservation & Management Security Upgrades

Bus Garage

• Add Heat Detection• Upgrade Fire Alarm System• Masonry Repair

Page 12: 2012 Planned Facilities Reconstruction Project. Planned Facilities Reconstruction Health & Life Safety Energy Conservation & Management Security Upgrades

Project Budget

MIDDLE/ HIGH SCHOOL $1,513,000

FENNER ELEMENTARY $ 907,000

TEMPLE ELEMENTARY $ 221,000

BUS GARAGE $ 59,000

Total Budget $2,700,000

(THE ABOVE FIGURE INCLUDES CONTINGENCIES AND INCIDENTAL COSTS)