2012 Cupa Ust Closure Presentation Revised

  • Upload
    lte002

  • View
    218

  • Download
    0

Embed Size (px)

Citation preview

  • 8/13/2019 2012 Cupa Ust Closure Presentation Revised

    1/85

    UNDERGROUNDSTORAGE

    TANKCLOSURE

  • 8/13/2019 2012 Cupa Ust Closure Presentation Revised

    2/85

    Presented by :

    Brenda ten BruggencateSanta Fe Springs Fire-Rescue

    David NorenEBA Group

  • 8/13/2019 2012 Cupa Ust Closure Presentation Revised

    3/85

    INSPECTORS

    PERSPECTIVE

    Permits Inspections

  • 8/13/2019 2012 Cupa Ust Closure Presentation Revised

    4/85

    OTHER TOPICS

    open excavationsclean certifications

  • 8/13/2019 2012 Cupa Ust Closure Presentation Revised

    5/85

    TYPES OF UST CLOSURES

    Permanent removal

    Permanent-in-place

    Temporary

  • 8/13/2019 2012 Cupa Ust Closure Presentation Revised

    6/85

    CLOSURE VS. REMOVAL

    careful with the termlosure when

    rem ov l is meant

  • 8/13/2019 2012 Cupa Ust Closure Presentation Revised

    7/85

  • 8/13/2019 2012 Cupa Ust Closure Presentation Revised

    8/85

  • 8/13/2019 2012 Cupa Ust Closure Presentation Revised

    9/85

    2010 CFC

    105.7.7 - permitrequired to remove,

    close, or place an USTinto temporary closure

    PERMIT REQUIRED

  • 8/13/2019 2012 Cupa Ust Closure Presentation Revised

    10/85

  • 8/13/2019 2012 Cupa Ust Closure Presentation Revised

    11/85

    UST CLOSUREREQUIREMENTS

    23 CCR Art. 7 2670(e) apply for UST closure to LIA within 90 days

    once hazardous substance storage has stopped

    AND

    Submit closure proposal 30 days priorto closure or shorter

    Check with LIAMost want one submittal

    Process varies

  • 8/13/2019 2012 Cupa Ust Closure Presentation Revised

    12/85

    H SC 25298 - general

    23 CCR Art. 723 CCR 2670 - general to all UST closures23 CCR 2671 - temporary closures23 CCR 2672 (b) - removal23 CCR 2672 (c) - closure-in-place23 CCR 2672 (d) - sampling requirements

    2010 CFC 3404.2.13 - temporary & closure-in-place 3404.2.14 removal

    Ordinance

    UST CLOSUREREQUIREMENTS TYPES

  • 8/13/2019 2012 Cupa Ust Closure Presentation Revised

    13/85

    WHAT DOES AN INSPECTORLOOK FOR ON A PERMIT?

    Tracking of UST and RP

    Application that demonstrate compliance withthe law, regs, codes, standards etc.

    Names & addressesState UST ID#Contents, size, install date etc.State UST Operating Permit Application - Facilityand Tank Information forms contain a lot of this info

    Safe removal or closure (inerting UST)Liquids, sludge, and residuals managed legallySampling to demonstrate if release occurred or not

  • 8/13/2019 2012 Cupa Ust Closure Presentation Revised

    14/85

    WHAT DOES AN INSPECTORLOOK FOR ON A PERMIT?

    Agency specific

    Can be written narrativeLevel of detail varies

    May be done on prescriptive formsSome LIAs attach standard conditionsExample: SFS Closure Permit

  • 8/13/2019 2012 Cupa Ust Closure Presentation Revised

    15/85

    Most fieldson this form

    are requiredby title 22

    Attach Forms A & B

    location

    Type &proceduresfor closure

    description

    contractor

    certification

    RP

  • 8/13/2019 2012 Cupa Ust Closure Presentation Revised

    16/85

    PERMANENTUST CLOSURE

    REQUIREMENTSLG 48-5, Contractor Licensing

    A ( all)

    B ( construct building)C-36 ( service stations)C-61/D-40 ( < 20K capacity)

    andHazardous SubstanceCertification issued by CSLB

    B&P 7058.7

  • 8/13/2019 2012 Cupa Ust Closure Presentation Revised

    17/85

  • 8/13/2019 2012 Cupa Ust Closure Presentation Revised

    18/85

    UST CLOSURE

    Permit approved now what?

    Complete closure within a reasonable amountof time as determined by LIA - 23 CCR 2670(e)

    Be aware of Ordinance timelinesSFS 6 months, with possible 6 monthextension

    CFC1 year for permanent closures90 days to safe guard temp closures

  • 8/13/2019 2012 Cupa Ust Closure Presentation Revised

    19/85

  • 8/13/2019 2012 Cupa Ust Closure Presentation Revised

    20/85

    TO INSPECT FOR?

    PermanentClosure removal

    Principalsapply to otherclosure type

  • 8/13/2019 2012 Cupa Ust Closure Presentation Revised

    21/85

    CFC 106.2

    Fire Code Official is authorized to conductinspections to determine compliance with thiscode

    Permanent closure by removalTank inert and remove contents, tank, & pipe

    TO INSPECT FOR?

  • 8/13/2019 2012 Cupa Ust Closure Presentation Revised

    22/85

    H SC 25298 23 CCR Art. 7

    UST owner/operator shalldemonstrate/document to the Local

    Agency

    No unauthorized release has occurred, collectsamplesProper disposal (i.e. tank destruction cert)or reuse info

    TO INSPECT FOR?

  • 8/13/2019 2012 Cupa Ust Closure Presentation Revised

    23/85

  • 8/13/2019 2012 Cupa Ust Closure Presentation Revised

    24/85

    UPON ARRIVAL

    Assess logisticsTraffic hazards

    Access in and outHow many people are in removalarea?

    Overhead hazards - electricalTank path from pit to truckPlan ahead

    Use common sense

  • 8/13/2019 2012 Cupa Ust Closure Presentation Revised

    25/85

  • 8/13/2019 2012 Cupa Ust Closure Presentation Revised

    26/85

  • 8/13/2019 2012 Cupa Ust Closure Presentation Revised

    27/85

    UPON ARRIVAL

    Find out whos who SupervisorLooky-loosGeologistclean certifier Who is the SiteSafety Officer?

    Report safety

    concerns to SSO

  • 8/13/2019 2012 Cupa Ust Closure Presentation Revised

    28/85

    UPON ARRIVAL

    Ask where they are in the removal processWhen does your agency require the inspector

    to be present?For excavation?For cold cutting?For cleaning?During the clean certification?During removal?During sample collection?

  • 8/13/2019 2012 Cupa Ust Closure Presentation Revised

    29/85

    UPON ARRIVAL

    Verify info submitted on permit

    What info is different than site conditions

    Has the contractor or subs changed?

    Where are they taking the UST?confirm with driver

    Where are they taking rinseate?Manifest # or copy

  • 8/13/2019 2012 Cupa Ust Closure Presentation Revised

    30/85

    UPON ARRIVAL

    Ask the contractor their plan and logistics

    Is it consistent with the approved permit?

    Does it appear reasonable?

    Assess and record differences

  • 8/13/2019 2012 Cupa Ust Closure Presentation Revised

    31/85

    UPON ARRIVAL

    Look around the site

    Size of crane appropriate?

    Condition of lifting cablesor straps

  • 8/13/2019 2012 Cupa Ust Closure Presentation Revised

    32/85

    Look around the site (cont.) Are the excavation walls stable or loose?

    Where are people standing?

  • 8/13/2019 2012 Cupa Ust Closure Presentation Revised

    33/85

  • 8/13/2019 2012 Cupa Ust Closure Presentation Revised

    34/85

    TALK TO GEOLOGIST

    Do they know the sampling plan?

    Do they have the right sampling equipment?No glass jars for VOCsEPA Method 5035Ice in their chest?

    Ask early - may to allow time to acquirethese things should they not have them

  • 8/13/2019 2012 Cupa Ust Closure Presentation Revised

    35/85

    NOW WHAT?

    At this point SFSFR arrives on site towitness the clean certification

  • 8/13/2019 2012 Cupa Ust Closure Presentation Revised

    36/85

    Residual liquids, sludges, or solids SHALL beremoved from tank and piping and handledhazardous wastes or recyclable materials

    Inert possible flammables vapor at STP to levelsthat preclude explosion

    22 CCR requires Hazardous Waste Tank ClosureCertification

    clean UST or comply with all applicable HWrequirements

    PRE-REMOVALREQUIREMENTS

  • 8/13/2019 2012 Cupa Ust Closure Presentation Revised

    37/85

  • 8/13/2019 2012 Cupa Ust Closure Presentation Revised

    38/85

    API 2015

    Thisstandarddoes notapply toUSTs

    Many safetankcleaning

    principalsareapplicable

    Also see API2016

  • 8/13/2019 2012 Cupa Ust Closure Presentation Revised

    39/85

  • 8/13/2019 2012 Cupa Ust Closure Presentation Revised

    40/85

    WHAT IS ACLEAN CERTIFICATION

    API Publication 2015Intro says this standard does not apply to USTsSafe cleaning principals applyRefers to API 2016Vapors and degassing

    Removing sludge and residuesTank cleaningControl of ignition sources

    Atmospheric monitors

  • 8/13/2019 2012 Cupa Ust Closure Presentation Revised

    41/85

  • 8/13/2019 2012 Cupa Ust Closure Presentation Revised

    42/85

    WHAT IS ACLEAN CERTIFICATION

    NFPA 326 Atmospheric Testing

    Combustible gas indicator reading can be incorrect if taken inoxygen deficient environmentCheck instrument specs

    Cleaning Methods

    Triple rinse (low pressure water)High pressure steamPhysical removal (vacuuming, shovel, absorbing)

    Qualifications of person certifying tank atmosphere

    All work stops if >10% LEL

  • 8/13/2019 2012 Cupa Ust Closure Presentation Revised

    43/85

    WHAT IS ACLEAN CERTIFICATION

    API Publication 1604

    Recommended Practice for the Closure ofPetroleum USTs

  • 8/13/2019 2012 Cupa Ust Closure Presentation Revised

    44/85

    WEB ADDRESSES FORCLEANING PROCEDURES

    API Publication 2015http://publications.api.org/ Register or log in for freeUnder Read -Only Documents select Fire andSafety Protection

    Not all API Publications are accessible withoutan account

    API 1604 is not free

    http://publications.api.org/http://publications.api.org/
  • 8/13/2019 2012 Cupa Ust Closure Presentation Revised

    45/85

    WEB ADDRESSES FORCLEANING PROCEDURES

    NFPA 326, 1999 edition

    Formerly NFPA 327, 1993 edition

    www.nfpacodesonline.org

    Need a subscription

    http://www.nfpacodesonline.org/http://www.nfpacodesonline.org/
  • 8/13/2019 2012 Cupa Ust Closure Presentation Revised

    46/85

  • 8/13/2019 2012 Cupa Ust Closure Presentation Revised

    47/85

    If tank is clean (non-haz)

    submit the Hazardous Waste Tank ClosureCertification

    Piping and appurtenances must be clean so nopourable contents come out when inverted

    UST must be free of product, sludge, debris etc.

    UST must be visually inspected

    NEXT STEPTANK CLEANING

    NON HAZARDOUS

  • 8/13/2019 2012 Cupa Ust Closure Presentation Revised

    48/85

    NON-HAZARDOUSREMOVAL

    Visually inspectThrough manway orCut opening on siteUse non-sparking tools, cold cutting techniques

  • 8/13/2019 2012 Cupa Ust Closure Presentation Revised

    49/85

    NON HAZARDOUS

  • 8/13/2019 2012 Cupa Ust Closure Presentation Revised

    50/85

    If a cleaned tank is NOT cut and haspotential to generate flammable vapor

    Visually inspect byUse Class I, Div. 1 light with mirror to see inside tan

    Other method approved by CUPA

    Inert with CO 2 or other inert gasDry ice

    NON-HAZARDOUSREMOVAL

  • 8/13/2019 2012 Cupa Ust Closure Presentation Revised

    51/85

    50 lb bl k i t l 12" 12" 12"

  • 8/13/2019 2012 Cupa Ust Closure Presentation Revised

    52/85

    50 lb. blocks are approximately 12" x 12" x 12"

    10 lb 50 lb

    10K UST requires 220 lbs dry ice= 4.4 50 lbs blocks of dry iceSublimates at a rate of 5 to 10 pounds every 24hours when stored in a typical cooler

    Much faster on hot days in metal UST

    http://www.continentalcarbonic.com/dryicelocations/map.php
  • 8/13/2019 2012 Cupa Ust Closure Presentation Revised

    53/85

    DRY ICE

    Allow sublimation to generate CO 2

    Use CGI to measure LEL top, center,bottom

    Careful! Whats the oxygen conc.?

    Plug all hole except 1/8 vent

    NON HAZARDOUS

  • 8/13/2019 2012 Cupa Ust Closure Presentation Revised

    54/85

    NON-HAZARDOUSREMOVAL

    Use Hazardous Waste Tank ClosureCertification or acceptable alternativecontaining specific information

  • 8/13/2019 2012 Cupa Ust Closure Presentation Revised

    55/85

    Required by 2267383.3 (g)

    Certify free of product,sludge, etc.

    Atmosphere at top,center, bottom

    Qualifications of certifier

    Date, time, signature

    Cert good only at time ofmonitoring

  • 8/13/2019 2012 Cupa Ust Closure Presentation Revised

    56/85

    UST

  • 8/13/2019 2012 Cupa Ust Closure Presentation Revised

    57/85

    USTREMOVAL

    Ensure clear path frompit to truck

    Remove loose dirt

    Transport off-site

  • 8/13/2019 2012 Cupa Ust Closure Presentation Revised

    58/85

    UST REMOVAL

    Document to LIA disposition of UST

    If disposedDocumentation i.e. tank destruction cert

    If destined for reuseCheck with LIA for local requirements

    Document to LIA within their requiredtime frame

    Name of new owner and new operator of USTLocation of intended use

    Nature of intended use

    SOIL SAMPLING

  • 8/13/2019 2012 Cupa Ust Closure Presentation Revised

    59/85

    SOIL SAMPLINGREQUIREMENTS

    Must demonstrate no unauthorized release hasoccurred

    Must be performed during or immediately after USTclosure activities

    Based on soil and (if present in excavation) water

    analysis and consistent with approved work plan

    Analyze by State-Certified lab for previously storedsubstance(s) and breakdown products or transformationproducts.

    SOIL SAMPLING

  • 8/13/2019 2012 Cupa Ust Closure Presentation Revised

    60/85

    SOIL SAMPLINGREQUIREMENTS

    Geological logs shall be prepared bya Professional Geologist or Civil

    Engineer

    technician working under the directsupervision of one can do this

    provided the professional reviewsthe logs and assumes responsibilityfor them. 23 CCR 2649 (b)(1)(D)

    SOIL SAMPLING

  • 8/13/2019 2012 Cupa Ust Closure Presentation Revised

    61/85

    SOIL SAMPLINGREQUIREMENTS

    Removal

    Minimum 2 below the UST bottom in native soil ateach end of tank

    Every 20 linear feet of piping

    May include vent and vapor for VPH systems based onchange in piping definitionThis includes sampling under the dispenser

    Stockpile sampling (not specified in 23 CCR 2672)

  • 8/13/2019 2012 Cupa Ust Closure Presentation Revised

    62/85

  • 8/13/2019 2012 Cupa Ust Closure Presentation Revised

    63/85

  • 8/13/2019 2012 Cupa Ust Closure Presentation Revised

    64/85

    2670(f)

    Bus. Prof.

    Code 7835

    2672(b)(2)(c)(2)

    2672(b)(3)(4)

    2649(f)(6)HSC

    25298.5

    2672(c)(1)

    Bus. Prof.Code 7835

    2649(f)(5) (g)

    2649(f)(5) (g)HSC 25298.5

    2649(f)(5) (g)

    2670(f)

    SFSFRrequirement

    Needed to de-termine if furtheraction is needed

    Professional

    Professional

    piping & dispensers

    PERMANENT UST CLOSURE

  • 8/13/2019 2012 Cupa Ust Closure Presentation Revised

    65/85

    2 TYPES

    Closure-in-place23 CCR 2672(c)

    Removal23 CCR 2672(b)

    UST

  • 8/13/2019 2012 Cupa Ust Closure Presentation Revised

    66/85

    USTCLOSURE-IN-PLACE

    What justifies leaving UST in place?

    Check with Building Dept. & LIA policy

    City of SFS requires UST be within a 45

    angle of footing of permanent structure

    Consider requiring Engineering Report if not

    obvious

    UST

  • 8/13/2019 2012 Cupa Ust Closure Presentation Revised

    67/85

    USTCLOSURE-IN-PLACE

    Closure-in-place allowed for UST 2

    UST 2

    BUILDING

    UST 1

    45

    UST

  • 8/13/2019 2012 Cupa Ust Closure Presentation Revised

    68/85

    Process similar to removal

    Clean tank

    Legally manage waste

    Sampling borings required

    Fill with inert solidexception

    USTCLOSURE-IN-PLACE

    UST

  • 8/13/2019 2012 Cupa Ust Closure Presentation Revised

    69/85

    USTCLOSURE-IN-PLACE

    Exception: if owner intends to reuse tank forstorage of a non-haz substance

    Non-haz substance must be compatible withprevious UST use and construction

    Check with LIA and Fire Departments on theirrequirements

  • 8/13/2019 2012 Cupa Ust Closure Presentation Revised

    70/85

    UST CLOSURE-IN-PLACE

    Filling with inert solid

    Provide proper openings to filling tank withinert material

    Use concrete slurry, sand, flowable ash, orfoaming agentEnsure UST buoyancy is offset

    UST PIPING

  • 8/13/2019 2012 Cupa Ust Closure Presentation Revised

    71/85

    UST PIPINGCLOSURE-IN-PLACE

    Remove all piping unless it willdamage structures or other pipes

    Piping to remaining in place must beemptied of contents and capped

    Piping does not have to be filled with an inertsolid, only the UST does

    Remove ventBackfill

    SOIL SAMPLING

  • 8/13/2019 2012 Cupa Ust Closure Presentation Revised

    72/85

    SOIL SAMPLINGREQUIREMENTS

    Closure-in-place

    One or more slant boring as close as possible to themidpoint of the UST OR

    Vertical borings drilled along each long dimensionalside of UST OR

    Other method as approved by LIACheck approve permit/workplan

  • 8/13/2019 2012 Cupa Ust Closure Presentation Revised

    73/85

  • 8/13/2019 2012 Cupa Ust Closure Presentation Revised

    74/85

    TEMPORARY

    USTCLOSURE

  • 8/13/2019 2012 Cupa Ust Closure Presentation Revised

    75/85

    TEMPORARY

    UST CLOSURE

    23 CCR 2010 CFC

    When storage of HS has ceasedbut the UST will be used again

    within 12 months

    When UST is taken out of service

    Submit proposal 30 days prior toclosure

    Safeguard within 90 days

  • 8/13/2019 2012 Cupa Ust Closure Presentation Revised

    76/85

    TEMPORARY

    UST CLOSURE23 CCR 2010 CFCRemove liquid and properly manage it same

    Cap and secure pipe, fill line, gauge openings,vapor recovery

    same

    maintain vents same

    Disconnect power to pumps but not cathodicprotection system

    Inert to levels that preclude explosions OR lower ifrequired by LIA

    UST may be filled with a non-corrosive liquid thatis not a hazardous substance

  • 8/13/2019 2012 Cupa Ust Closure Presentation Revised

    77/85

    TEMPORARY

    UST CLOSURE23 CCR 2010 CFCRemove liquid and properly manage it same

    Cap and secure pipe, fill line, gauge openings,vapor recovery

    same

    maintain vents same

    Disconnect power to pumps but not cathodicprotection system

    Inert to levels that preclude explosions OR lower ifrequired by LIA

    UST may be filled with a non-corrosive liquid thatis not a hazardous substance

    TO FILL OR NOT TO FILL?

  • 8/13/2019 2012 Cupa Ust Closure Presentation Revised

    78/85

    TO FILL OR NOT TO FILL?

    Decidingfactors

    High

    groundwater?Intent andtime frame forreuse?

    Consideramount ofwastegenerated

  • 8/13/2019 2012 Cupa Ust Closure Presentation Revised

    79/85

    TEMPORARY UST

  • 8/13/2019 2012 Cupa Ust Closure Presentation Revised

    80/85

    TEMPORARY USTCLOSURE

    f filled

    Non corrosive liquid

    Not a hazardous substance

    Test liquid and submit results to LIA priorto removing it from UST at end of tempclosure period

    UST TEMPORARY

  • 8/13/2019 2012 Cupa Ust Closure Presentation Revised

    81/85

    CLOSURE

    Monitoringrequirements

    Can be modifiedby LIA based onneed to detectunauthorizedrelease

    Cathodicprotection mustbe maintained

  • 8/13/2019 2012 Cupa Ust Closure Presentation Revised

    82/85

    UST TEMPORARY

  • 8/13/2019 2012 Cupa Ust Closure Presentation Revised

    83/85

    CLOSURE

    Continue compliance with the followingrequirements:

    Repair and record keeping

    Release reporting and investigations

    Release response and corrective actions

    TEMPORARY

  • 8/13/2019 2012 Cupa Ust Closure Presentation Revised

    84/85

    UST CLOSURE

    Options at end of permit term

    23 CCR 2010 CFC

    12 month extension may begranted if site assessmentperformed

    Removal from ground within oneyear for USTs out of service

  • 8/13/2019 2012 Cupa Ust Closure Presentation Revised

    85/85