March 9, 2012 Mr.Enoch Davies Mr. Kent Bolton Associate Engineer WECC Technical Staff Western Electric Coordinatig Council University of Utah Research Park Suite 200. 615 Arapeen Utah, Suite 210 Salt Lake City, Utah 84103-1114 Salt Lake City, UT 84108- 1288 A new SVC (-75 / 200 MVAr) will connected at Tecnologico (20111 “TEK-230 “) substation for local voltage support and to increase reactive margin in the Valley Area of the CFE Baja California system. This project has a year delayed, CFE hopes this SVC will be on service on June Dynamic model was provided by the vendor in PSS/E, we are waiting for the PSLF shortly, commercial operation is scheduled for late June, 2012. New substation “Valle de Puebla” (20460 “VPA-230 “) between TL 20111 “TEK-230 “ – 20112 “STB-230 “ 230 kV. Commercial date, late March 2012. New substation “Carranza” (204161 CZA-161 ”) between TL 20153 “GOR-16 “ – 20147 “CTY-161 “ 161 kV. Commercial date, May 2012. Comisión Federal de Electricidad

2012 CFE Annual Progress Report - WECC 2012.docx · Web viewComisión Federal de Electricidad March 9, 2012 Mr.Enoch DaviesMr. Kent Bolton Associate Engineer WECC Technical Staff

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: 2012 CFE Annual Progress Report - WECC 2012.docx · Web viewComisión Federal de Electricidad March 9, 2012 Mr.Enoch DaviesMr. Kent Bolton Associate Engineer WECC Technical Staff

March 9, 2012

Mr.Enoch Davies Mr. Kent BoltonAssociate Engineer WECC Technical StaffWestern Electric Coordinatig Council University of Utah Research ParkSuite 200. 615 Arapeen Utah, Suite 210Salt Lake City, Utah 84103-1114 Salt Lake City, UT 84108-1288

A new SVC (-75 / 200 MVAr) will connected at Tecnologico (20111 “TEK-230 “) substation for local voltage support and to increase reactive margin in the Valley Area of the CFE Baja California system. This project has a year delayed, CFE hopes this SVC will be on service on June

Dynamic model was provided by the vendor in PSS/E, we are waiting for the PSLF shortly, commercial operation is scheduled for late June, 2012.

New substation “Valle de Puebla” (20460 “VPA-230 “) between TL 20111 “TEK-230 “ – 20112 “STB-230 “ 230 kV. Commercial date, late March 2012.

New substation “Carranza” (204161 CZA-161 ”) between TL 20153 “GOR-16 “ – 20147 “CTY-161 “ 161 kV. Commercial date, May 2012.

No one of the above new transmission facilities affect to neighbor systems. Last Annual Progress Report was sent on February 19, 2010.

If you have any questions regarding the Annual Progress Report, please contact Jose Santamaria at 011 52 (686) 558-1541 or via e-mail at [email protected] Sincerely,

Jose SantamariaGrid Operation Planning ChiefSRWG member

Comisión Federal de Electricidad