9/18/2011 1 “The Value of CMGC as a Tool for “The Value of CMGC as a Tool for Infrastructure Project Delivery” Infrastructure Project Delivery” Prepared for: Prepared for: International Public Works International Public Works International Public Works International Public Works Congress and Exposition” Congress and Exposition” Prepared by: Prepared by: September 18, 2011 September 18, 2011 1 JMC Consulting 75 Introduction Learning Outcomes APWA Peer Exchange FHWA’s EDC Initiative CMGC/CMAR D fi d Discussion Road Map 2 CMGC/CMAR Defined Osceola County Case Study “Genuine leadership comes from the quality of your vision and your ability to spark others to extraordinary performance.” — Jack Welch – Former GE Chairman and CEO 70 Introduction “Educational Consortium” Partners JMC Consulting 3 69

2011 09 18 APWA Annual Congress and Exposition 2Understand and Describe the distinctions between CMGC and CMAR Learn about the value of having CMGC/CMAR in your “project delivery

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: 2011 09 18 APWA Annual Congress and Exposition 2Understand and Describe the distinctions between CMGC and CMAR Learn about the value of having CMGC/CMAR in your “project delivery

9/18/2011

1

“The Value of CMGC as a Tool for “The Value of CMGC as a Tool for Infrastructure Project Delivery”Infrastructure Project Delivery”

Prepared for:Prepared for:

“International Public Works“International Public WorksInternational Public Works International Public Works Congress and Exposition”Congress and Exposition”

Prepared by:Prepared by:

September 18, 2011September 18, 20111

JMC Consulting

75

Introduction

Learning Outcomes

APWA Peer Exchange

FHWA’s EDC Initiative

CMGC/CMAR D fi d

Discussion Road Map

2

CMGC/CMAR Defined

Osceola County Case Study

“Genuine leadership comes from the quality of your vision and your ability to spark others to extraordinary performance.”

— Jack Welch – Former GE Chairman and CEO70

Introduction

“Educational Consortium” Partners

JMC Consulting

369

Page 2: 2011 09 18 APWA Annual Congress and Exposition 2Understand and Describe the distinctions between CMGC and CMAR Learn about the value of having CMGC/CMAR in your “project delivery

9/18/2011

2

University of Florida Research Program

Accelerated Project Delivery Research

Dr. R. Edward Minchin Jr., P.E.

468

Understand and Describe the distinctions between CMGC and CMAR

Learn about the value of having CMGC/CMAR in your “project delivery tool box”

Learning Outcomes

5

Discover practical “lessons learned” from a successful program

67

What experience do you currently have with CMGC and/or CMAR?

What are you hearing from your peers regarding CMGC and/or CMAR?

APWA Peer Exchange

Wh t i N b 1

6

What is your Number 1 Question or Concern about CMGC and/or CMAR?

62

Page 3: 2011 09 18 APWA Annual Congress and Exposition 2Understand and Describe the distinctions between CMGC and CMAR Learn about the value of having CMGC/CMAR in your “project delivery

9/18/2011

3

EDC Initiative

7

“Good is the enemy of great.”

- Jim Collins61

EDC Initiative Primary Directives:

EDC Initiative

8

1. Accelerating Technology and Innovation Deployment

2. Shortening Project Delivery

Design-Build

Construction Manager/General Contractor (CMGC)

60

Preliminary Goals - By December of 2012…

EDC Initiative

9

100 CMGC contracts executed on Federal-aid or Federal Lands projects (1% of Federal Aid Program)

25 state, local, or Federal Land agencies have used CMGC

Increase the number of DB contracts executed for Federal-aid or Federal Lands projects by 50%

59

Page 4: 2011 09 18 APWA Annual Congress and Exposition 2Understand and Describe the distinctions between CMGC and CMAR Learn about the value of having CMGC/CMAR in your “project delivery

9/18/2011

4

Research done in 2009 (NCHRP Synthesis 402)

• Five states were using CMGC/CMAR – AK, OR, UT, FL, AZ

• Six additional States have legislative authority

Who is Using CMGC/CMAR?

Quick look at current conditions (2011)

• Now Using CMGC/CMAR: MI, CO, CFL, MTO, ME, and NV

• EDC follow ups to EFL + 9 others

1058

Salt Lake City, Utah – June 27 – 29, 2011

Participants

West Coast Peer Exchange Highlights

• Central Federal Lands Highway Division

11

• Western Federal Lands Highway Division

• Sundt Construction

• Stanton Cost Estimating

JMC Consulting

57

East Coast Peer Exchange – Coming Soon!

December 7 – 8, 2011

Boston, MA

Purpose – to group Owners with experience in CMGC with inexperienced Owners and exchange information and strategies for accomplishing FHWA’s EDC Initiative

12

g p g

Build on success of Salt Lake City, Utah event

56

Page 5: 2011 09 18 APWA Annual Congress and Exposition 2Understand and Describe the distinctions between CMGC and CMAR Learn about the value of having CMGC/CMAR in your “project delivery

9/18/2011

5

Project Delivery Method

• DBB; CMGC; DB

Procurement Procedure

The New Paradigm: The Right Tool for the Right Job

• Low Bid; Best Value; Qualifications-based; Sole Source

Contract Payment Provision

• Lump Sum; Guaranteed Maximum Price; Cost Plus Fee; Cost Reimbursable, Unit price

1354

A Project Team consisting of three components:

An Owner

A Contract with a Designer

What are CMGC & CMAR

Phase one – A “Construction Management” consulting contract to help with design

Phase two – A “General Contracting “ contract to build the project

14

g

A Two Phase Contract with a General contractor

52

Design-Bid-Build CMGC/CMAR Design-Build

Contracting Types:FHWA’s EDC Project Delivery Initiatives

1550

Page 6: 2011 09 18 APWA Annual Congress and Exposition 2Understand and Describe the distinctions between CMGC and CMAR Learn about the value of having CMGC/CMAR in your “project delivery

9/18/2011

6

Key Finding:

CMGC/CMAR project delivery “is a less radical shift in procurement culture than design-build…”

O t i t l f

CMGC Highlights

16

Owner retains control of the design

Designer is true owner’s representative

49

Transportation projects require a unique process – With CMGC:

Self-performance requirements are typical

Subcontractor procurement

CMGC is not CMAR

Subcontractor procurement process is different

CMGC relies on best-value selection

GMP timing

1747

With CMAR:

Negotiated prices vs. “BID”

Very little owner involvement during construction

CMGC is not CMAR

Contractor selection is QBS vs. Best Value

Focus is on Quality vs. Risk and Price

1846

Page 7: 2011 09 18 APWA Annual Congress and Exposition 2Understand and Describe the distinctions between CMGC and CMAR Learn about the value of having CMGC/CMAR in your “project delivery

9/18/2011

7

CMGC/CMAR Contracting

Integrated team approach to the planning, design and construction of highway projects

1944

Risk Theory

2042

Schedule/Timeline Comparison

2140

Page 8: 2011 09 18 APWA Annual Congress and Exposition 2Understand and Describe the distinctions between CMGC and CMAR Learn about the value of having CMGC/CMAR in your “project delivery

9/18/2011

8

Model to Implement Innovation

2239

Understanding the good and bad about Design-Bid-Build – 50 years of history

Generally, an understanding of Design-Build

What Leads Owners to CMGC/CMAR?

Looking for a model that takes advantage of the good in both methods

Not looking for a replacement – looking for an additional tool

“The Right Tool for the Right Job”

2337

CMGC/CMAR Process

2435

Page 9: 2011 09 18 APWA Annual Congress and Exposition 2Understand and Describe the distinctions between CMGC and CMAR Learn about the value of having CMGC/CMAR in your “project delivery

9/18/2011

9

Design Team Selection Phase

2533

Designer – regular consultant selection process –Qualifications Based Selection (QBS)

General Contractor Options:

• QBS

How is the Team Selected?

• Best Value = Technical evaluation + price

FHWA allows any fair and transparent selection method to be evaluated under SEP-14. Most CMGC projects trend to Best Value.

2631

Transition to Construction –Negotiation or Bid

2729

Page 10: 2011 09 18 APWA Annual Congress and Exposition 2Understand and Describe the distinctions between CMGC and CMAR Learn about the value of having CMGC/CMAR in your “project delivery

9/18/2011

10

Two possible outcomes of “bid”

Owner gets acceptable price - Proceed with build

Owner doesn’t get acceptable price

k

CMGC/CMAR Bid Process

• Re-Scope, More Design, Risk Apportionment –Rebid

• Convert to Design-Bid-Build

2827

Better Designs –

Challenging to Quantify – Contractor satisfaction with plans

Reduced Change Orders

What Does an Owner Get From CMGC/CMAR

Faster, more accurate schedules –Exceeded expectations

Lower costs

Savings in design

Savings in constructability and innovation

2925

Theory Vs. Reality

3023

Page 11: 2011 09 18 APWA Annual Congress and Exposition 2Understand and Describe the distinctions between CMGC and CMAR Learn about the value of having CMGC/CMAR in your “project delivery

9/18/2011

11

Largest volume of highway projects started at one time using CMGC/CMAR

Most accelerated program in the nation to date

Osceola County, FL Case Study

31

nation to date

11 major roadways started in 1-year

$350 Million

~11 times the previous productionNarcoossee Rd.

Phase I21

Introduction – Success Story

“Top 25 Newsmakers of 2009…. Veteran Engineer Revives Road Program” 3219

CMAR will not work in cases where:

A. All right-of-way has not been obtained

B. Permits are not in place

C. Utilities are not coordinated

Group Question

33

D. Plans are already 100% complete

E. None of the above

F. All of the above

17

Page 12: 2011 09 18 APWA Annual Congress and Exposition 2Understand and Describe the distinctions between CMGC and CMAR Learn about the value of having CMGC/CMAR in your “project delivery

9/18/2011

12

CMAR will not work in cases where:

A. All right-of-way has not been obtained

B. Permits are not in place

C. Utilities are not coordinated

Group Question

34

D. Plans are already 100% complete

E. None of the above

F. All of the above

15

CMAR not a viable method for roadway projects

CMAR adds costs

Local contractor perception of being “left-out”

Industry Misnomers

35

CMAR process is just “brokering out the work” for a fee

CMAR projects have built-in soft costs

13

True Costs

36John Young Parkway Ground Breaking

11

Page 13: 2011 09 18 APWA Annual Congress and Exposition 2Understand and Describe the distinctions between CMGC and CMAR Learn about the value of having CMGC/CMAR in your “project delivery

9/18/2011

13

County Manager was tasked with $700M Program

Aggressive Impact Fee Ordinance

18 projects behind schedule – various stages of design (need for contractor input)

The Challenge….The Opportunity!

37

Required 9 projects under construction in 1st year (need for different procurement process)

Poinciana BoulevardPhase II

8

Lack of key Stakeholder buy-in

Right-of-Way acquisition process

The Challenge….The Opportunity!

38

Designs were over budget

Required Owner to function as “Project Leader”

6

Board had no tolerance for projects taking 5 to 7 years to go to construction

Board had no tolerance for change orders

Board had no tolerance for “out of town” contractors

The Challenge….The Opportunity!

39

Board mandated operating budget reductions

4

Page 14: 2011 09 18 APWA Annual Congress and Exposition 2Understand and Describe the distinctions between CMGC and CMAR Learn about the value of having CMGC/CMAR in your “project delivery

9/18/2011

14

Program SummaryProgram Summary

""A good plan, violently executed now, is better than a A good plan, violently executed now, is better than a perfect plan next week."perfect plan next week."

General George S. Patton

402

Understand and Describe the distinctions between CMGC and CMAR

Learn about the value of having CMGC/CMAR in your “project delivery tool box”

Revisit Learning Outcomes

41

Discover practical “lessons learned” from a successful program

0

International Public Works Congress and Exposition

42

Kenneth E. Atkins, [email protected]

Bringing Innovative Solutions to Government

P.O. Box 423487Kissimmee, FL 34742-3487

863.875.5777 • fax 863.875.5778

Gregg A. Hostetler, [email protected]