28
ES-401 Site-Specific SRO Written Examination Form ES-401-8 Cover Sheet U.S. Nuclear Regulatory Commission Site-Specific SRO Written Examination Applicant Information Name: Date: 04107/2010 Facility/Unit: Oconee Region: I II III IV Reactor Type: W LICE E1BWGE LI Start Time: Finish Time: Instructions Use the answer sheets provided to document your answers. Staple this cover sheet on top of the answer sheets. To pass the examination you must achieve a final grade of at least 80.00 percent overall, with 70.00 percent or better on the SRO-only items if given in conjunction with the RO exam; SRO-only exams given alone require a final grade of 80.00 percent to pass. You have 8 hours to complete the combined examination, and 3 hours if you are only taking the SRO portion. Applicant Certification All work done on this examination is my own. I have neither given nor received aid. Applicant’s Signature Results RO/SRO-Only/Total Examination Values 75 / 25 / 100 Points Applicant’s Scores / / Points Applicant’s Grade I / Percent ES-401 Site-Specific SRO Written Examination Cover Sheet Form ES-401-8 U.S. Nuclear Regulatory Commission Site-Specific SRO Written Examination Applicant Information Name: Date: 04/07/2010 Facility/Unit: Oconee Region: I D II III D IV D Reactor Type: W DeE D Start Time: Finish Time: Instructions Use the answer sheets provided to document your answers. Staple this cover sheet on top of the answer sheets. To pass the examination you must achieve a final grade of at least 80.00 percent overall, with 70.00 percent or better on the SRO-only items if given in conjunction with the RO exam; SRO-only exams given alone require a final grade of 80.00 percent to pass. You have 8 hours to complete the combined examination, and 3 hours if you are only taking the SRO portion. Applicant Certification All work done on this examination is my own. I have neither given nor received aid. Applicant's Signature Results RO/SRO-OnlylTotal Examination Values 75 / / 100 Points Applicant's Scores / -- / -- Points Applicant's Grade / -- / -- Percent

2010A NRC SENIOR REACTOR OPERATOR EXAMFinish Time: Instructions Use the answer sheets provided to document your answers. Staple this cover sheet on top of the answer ... SCM s = 0°F

  • Upload
    others

  • View
    0

  • Download
    0

Embed Size (px)

Citation preview

  • ES-401 Site-Specific SRO Written Examination Form ES-401-8Cover Sheet

    U.S. Nuclear Regulatory Commission

    Site-Specific SRO Written Examination

    Applicant Information

    Name:

    Date: 04107/2010 Facility/Unit: Oconee

    Region: I II III IV Reactor Type: W LICE E1BWGE LI

    Start Time: Finish Time:

    Instructions

    Use the answer sheets provided to document your answers. Staple this cover sheeton top of the answer sheets. To pass the examination you must achieve a final gradeof at least 80.00 percent overall, with 70.00 percent or better on the SRO-only itemsif given in conjunction with the RO exam; SRO-only exams given alone require a final gradeof 80.00 percent to pass. You have 8 hours to complete the combined examination,and 3 hours if you are only taking the SRO portion.

    Applicant Certification

    All work done on this examination is my own. I have neither given nor received aid.

    Applicant’s Signature

    Results

    RO/SRO-Only/Total Examination Values 75 / 25 / 100 Points

    Applicant’s Scores

    _____

    /

    _____

    /

    _____

    Points

    Applicant’s Grade

    _____

    I

    _____

    /

    _____

    Percent

    ES-401 Site-Specific SRO Written Examination Cover Sheet

    Form ES-401-8

    U.S. Nuclear Regulatory Commission

    Site-Specific SRO Written Examination

    Applicant Information

    Name:

    Date: 04/07/2010 Facility/Unit: Oconee

    Region: I D II ~ III D IV D Reactor Type: W DeE DBw~GE D

    Start Time: Finish Time:

    Instructions

    Use the answer sheets provided to document your answers. Staple this cover sheet on top of the answer sheets. To pass the examination you must achieve a final grade of at least 80.00 percent overall, with 70.00 percent or better on the SRO-only items if given in conjunction with the RO exam; SRO-only exams given alone require a final grade of 80.00 percent to pass. You have 8 hours to complete the combined examination, and 3 hours if you are only taking the SRO portion.

    Applicant Certification

    All work done on this examination is my own. I have neither given nor received aid.

    Applicant's Signature

    Results

    RO/SRO-OnlylTotal Examination Values 75 / ~ / 100 Points

    Applicant's Scores / -- / -- Points

    Applicant's Grade / -- / -- Percent

  • 2010A NRC SENIOR REACTOR OPERATOR EXAM

    I POINTQuestion 76

    Unit 2 initial conditions:• Time=1300• Reactor power = 100%

    Current conditions:• Time=1310• RCS pressure = 52 psig slowly decreasing• Reactor Building pressure = 52 psig slowly decreasing• All SCM’s = 0°F• 2RIA-57 = 92 R/hr slowly increasing• 2RIA-58 = 45 R/hr slowly increasing• Average of 5 highest CETC’s = 312°F decreasing• NO RBCU’s can be started• NO RBS Pumps can be started

    Based on the above conditions, which ONE of the following is the Emergency ActionLevel Classification?

    REFERENCE PROVIDED

    A. Alert based on Loss of Fuel Clad Barrier and Potential Loss of Containment Barrier

    B. Alert based on Loss of RCS Barrier and Potential Loss of Containment Barrier

    C. Site Area Emergency based on Loss of RCS Barrier and Loss of ContainmentBarrier

    D. Site Area Emergency based on Loss of Fuel Clad Barrier and Loss of ContainmentBarrier

    2010A NRC SENIOR REACTOR OPERATOR EXAM

    1 POINT Question 76

    Unit 2 initial conditions: • Time = 1300 • Reactor power = 100%

    Current conditions: • Time = 1310 • RCS pressure = 52 psig slowly decreasing • Reactor Building pressure = 52 psig slowly decreasing • All SCM's = OaF • 2RIA-57 = 92 Rlhr slowly increasing • 2RIA-58 = 45 Rlhr slowly increasing • Average of 5 highest CETC's = 312°F decreasing • NO RBCU's can be started • NO RBS Pumps can be started

    Based on the above conditions, which ONE of the following is the Emergency Action Level Classification?

    REFERENCE PROVIDED

    A. Alert based on Loss of Fuel Clad Barrier and Potential Loss of Containment Barrier

    B. Alert based on Loss of RCS Barrier and Potential Loss of Containment Barrier

    C. Site Area Emergency based on Loss of RCS Barrier and Loss of Containment Barrier

    D. Site Area Emergency based on Loss of Fuel Clad Barrier and Loss of Containment Barrier

  • 2010A NRC SENIOR REACTOR OPERATOR EXAM

    I POINTQuestion 77

    Unit 1 plant conditions:• Reactor power = 100%• CC CRD Return Flow = 125 gpm slowly decreasing• CC Return Flow = 563 gpm decreasing• Letdown Temperature = 138°F stable• The following alarms have actuated:

    o 1SA-91B-1 (CC CRD Return Flow Low).o ISA-21C-1 (HP Letdown Temperature High)o 1SA-91C-1 (CC Component Cooling Return Flow Low)

    Based on the above conditions:(1) Which ONE of the following describes a required action from the associated ARG(s)

    to mitigate this event?AND(2) If the ARG directed actions are NOT successful, which Abnormal Procedure is

    required to be entered first?

    A. (1) Decrease letdown flow using I HP-7 (LETDOWN CONTROL)

    (2) AP/32 (Loss of Letdown)

    B. (I) Decrease letdown flow using 1 HP-7 (LETDOWN CONTROL)

    (2) AP/20 (Loss of Component Cooling)

    C. (1) Verify CC Surge Tank level> 12 inches and start the standby CC pump

    (2) AP/32 (Loss of Letdown)

    D. (1) Verify CC Surge Tank level> 12 inches and start the standby CC pump

    (2) AP/20 (Loss of Component Cooling)

    2010A NRC SENIOR REACTOR OPERATOR EXAM

    1 POINT Question 77

    Unit 1 plant conditions: • Reactor power = 100% • CC CRD Return Flow = 125 gpm slowly decreasing • CC Return Flow = 563 gpm decreasing • Letdown Temperature = 138°F stable • The following alarms have actuated:

    o 1SA-9/B-1 (CC CRD Return Flow Low). o 1 SA-2/C-1 (HP Letdown Temperature High) o 1 SA-9/C-1 (CC Component Cooling Return Flow Low)

    Based on the above conditions: (1) Which ONE of the following describes a required action from the associated ARG(s)

    to mitigate this event? AND (2) If the ARG directed actions are NOT successful, which Abnormal Procedure is

    required to be entered first?

    A. (1) Decrease letdown flow using 1 HP-7 (LETDOWN CONTROL)

    (2) AP/32 (Loss of Letdown)

    B. (1) Decrease letdown flow using 1 HP-7 (LETDOWN CONTROL)

    (2) AP/20 (Loss of Component Cooling)

    C. (1) Verify CC Surge Tank level> 12 inches and start the standby CC pump

    (2) AP/32 (Loss of Letdown)

    D. (1) Verify CC Surge Tank level> 12 inches and start the standby CC pump

    (2) AP/20 (Loss of Component Cooling)

  • 2010A NRC SENIOR REACTOR OPERATOR EXAM

    I POINTQuestion 78

    Unit I initial conditions:• Datel2/0I• TimeO800• Reactor Power = 100%• All Pressurizer heater breakers trip open and cannot be reclosed

    Current conditions:• Date 12/04• Time 2200

    Based on the above conditions, which ONE of the following is the HIGHER RCStemperature (degrees F) that is in compliance with the requirements of Tech SpecsAND the bases for the Pzr heater power supply requirements in TS 3.4.9 (Pressurizer)?

    REFERENCE PROVIDED

    A. 320 I ensure ability to perform a subcooled cooldown while on natural circulationduring an extended loss of power

    B. 320 / ensure ability to control pressure and remain subcooled during an extendedloss of power

    C. 375 I ensure ability to perform a natural circulation cooldown during an extendedloss of power

    D. 375 / ensure ability to control pressure and remain subcooled during an extendedloss of power

    2010A NRC SENIOR REACTOR OPERATOR EXAM

    1 POINT Question 78

    Unit 1 initial conditions: • Date = 12/01 • Time = 0800 • Reactor Power = 100% • All Pressurizer heater breakers trip open and cannot be reclosed

    Current conditions: • Date = 12/04 • Time = 2200

    Based on the above conditions, which ONE of the following is the HIGHER RCS temperature (degrees F) that is in compliance with the requirements of Tech Specs AND the bases for the Pzr heater power supply requirements in TS 3.4.9 (Pressurizer)?

    REFERENCE PROVIDED

    A. 320 / ensure ability to perform a subcooled cooldown while on natural circulation during an extended loss of power

    B. 320 / ensure ability to control pressure and remain subcooled during an extended loss of power

    C. 375 / ensure ability to perform a natural circulation cool down during an extended loss of power

    D. 375 / ensure ability to control pressure and remain subcooled during an extended loss of power

  • 2010A NRC SENIOR REACTOR OPERATOR EXAM

    I POINTQuestion 79

    Unit 1 initial conditions:• Reactor power = 75% stable• ICSinMANUAL• lB HPIP tagged out• The following alarms actuate:

    o ISA-I/Al (RPCHANNELATRIP)o 1SA-l/Bl (RPCHANNELBTRIP)

    Current conditions:• Reactor power = 34% slowly decreasing• BOTH Main Feedwater pumps are operating• All SCM’s = 0°F stable

    Based on the above conditions, which ONE of the following describes the EOP tab thatwill be directed first AND the guidance the SRO will provide to the RO?

    A. UNPP I Trip the Main Turbine

    B. UNPP / Throttle Feedwater to control RCS temperature

    C. LOSCM / Fully depressurize BOTH Steam Generators

    D. LOSCM / Throttle Feedwater to control RCS temperature

    2010A NRC SENIOR REACTOR OPERATOR EXAM

    1 POINT Question 79

    Unit 1 initial conditions: • Reactor power = 75% stable • ICS in MANUAL • 1 B HPIP tagged out • The following alarms actuate:

    o 1SA-1/A1 (RP CHANNEL A TRIP) o 1SA-1/B1 (RP CHANNEL B TRIP)

    Current conditions: • Reactor power = 34% slowly decreasing • BOTH Main Feedwater pumps are operating • All SCM's = OaF stable

    Based on the above conditions, which ONE of the following describes the EOP tab that will be directed first AND the guidance the SRO will provide to the RO?

    A. UNPP I Trip the Main Turbine

    B. UNPP I Throttle Feedwater to control RCS temperature

    C. LOSCM I Fully depressurize BOTH Steam Generators

    D. LOSCM I Throttle Feedwater to control RCS temperature

  • 2010A NRC SENIOR REACTOR OPERATOR EXAM

    I POINTQuestion 80

    Unit 3 plant conditions:• Date 4/5• Time1100• 3KVID panelboard de-energized

    Current conditions:• Timel200• DC panelboard 3DIC is de-energized

    Based on the above conditions, which ONE of the following states the actions requiredby Tech Spec 3.8.8 (Distribution Systems-Operating) AND the bases behind thedifferent Completion Times for inoperable Vital Instrument and Control panelboards?

    REFERENCE PROVIDED

    A. Restore either 3KVIC OR 3KVID within 24 hours I KVIA AND KVIB have shortercompletion times due to being the source of power for the ES Digital Channels

    B. Restore either 3KVIC OR 3KVID within 24 hours I KVIA AND KVIB have shortercompletion times due to providing power for SK and SL breakers protective relaying

    C. Enter LCO 3.0.3 immediately I KVIA AND KVIB have shorter completion times dueto being the source of power for the ES Digital Channels

    D. Enter LCO 3.0.3 immediately I KVIA AND KVIB have shorter completion times dueto providing power for SK and SL breakers protective relaying

    2010A NRC SENIOR REACTOR OPERATOR EXAM

    1 POINT Question 80

    Unit 3 plant conditions: • Date 4/5 • Time = 1100 • 3KVID panelboard de-energized

    Current conditions: • Time = 1200 • DC panelboard 3DIC is de-energized

    Based on the above conditions, which ONE of the following states the actions required by Tech Spec 3.8.8 (Distribution Systems-Operating) AND the bases behind the different Completion Times for inoperable Vital Instrument and Control panelboards?

    REFERENCE PROVIDED

    A. Restore either 3KVIC OR 3KVID within 24 hours / KVIA AND KVIB have shorter completion times due to being the source of power for the ES Digital Channels

    B. Restore either 3KVIC OR 3KVID within 24 hours / KVIA AND KVIB have shorter completion times due to providing power for SK and SL breakers protective relaying

    C. Enter LCO 3.0.3 immediately / KVIA AND KVIB have shorter completion times due to being the source of power for the ES Digital Channels

    D. Enter LCO 3.0.3 immediately / KVIA AND KVIB have shorter completion times due to providing power for SK and SL breakers protective relaying

  • 2010A NRC SENIOR REACTOR OPERATOR EXAM

    1 POINTQuestion 81

    Unit I initial conditions:• Reactor trip from 100% power• Both Main Feedwater pumps trip• EFDW pumps will not start

    Current conditions:• Rule 3 in progress• LOHT tab initiated• ALL SCM’s> 0°F

    Based on the above conditions, which ONE of the following would result in a transferout of the LOHT tab?

    A. Pressurizer level = 375 inches

    B. RCS heats up and results in ANY SCM = 0°F

    C. HPI Forced Cooling is established and verified

    D. Condensate Booster Pump feed is established

    2010A NRC SENIOR REACTOR OPERATOR EXAM

    1 POINT Question 81

    Unit 1 initial conditions: • Reactor trip from 100% power • Both Main Feedwater pumps trip • EFDW pumps will not start

    Current conditions: • Rule 3 in progress • LOHT tab initiated • ALL SCM's> OaF

    Based on the above conditions, which ONE of the following would result in a transfer out of the LOHT tab?

    A. Pressurizer level = 375 inches

    B. RCS heats up and results in ANY SCM = OaF

    C. HPI Forced Cooling is established and verified

    D. Condensate Booster Pump feed is established

  • 2010A NRC SENIOR REACTOR OPERATOR EXAM

    I POINTQuestion 82

    Unit 1 initial conditions:• Startup in progress• Reactor in MODE 3• Source Range NI’s 2 & 4 OOS• Source Range NI’s 1 & 3 = 834 cps increasing• Wide Range NI’s I thru 4 = 5E-5% increasing

    Current conditions:• Source Range NI-I = 0 cps• 1SA-051A8 (NI-i TEST/FAIL) actuates

    Based on the above conditions, which ONE of the following describes the reason for theNI-i indications AND the Tech Specs impact on the startup?

    A. Loss of +1 5V Power supply / Suspend the startup

    B. Loss of +1 5V Power supply I Startup may continue

    C. Source range becomes saturated I Suspend the startup

    D. Source range becomes saturated I Startup may continue

    2010A NRC SENIOR REACTOR OPERATOR EXAM

    1 POINT Question 82

    Unit 1 initial conditions: • Startup in progress • Reactor in MODE 3 • Source Range Nl's 2 & 4 OOS • Source Range Nl's 1 & 3 = 834 cps increasing • Wide Range NI's 1 thru 4 = 5E-5% increasing

    Current conditions: • Source Range NI-1 = 0 cps • 1 SA-05/A8 (NI-1 TEST/FAIL) actuates

    Based on the above conditions, which ONE of the following describes the reason for the NI-1 indications AND the Tech Specs impact on the startup?

    A. Loss of +15V Power supply / Suspend the startup

    B. Loss of +15V Power supply / Startup may continue

    C. Source range becomes saturated / Suspend the startup

    D. Source range becomes saturated / Startup may continue

  • 2010A NRC SENIOR REACTOR OPERATOR EXAM

    I POINTQuestion 83

    Unit I plant conditions:• ALL SCM = 0°F stable• RCS pressure = 855 psig slowly decreasing• LOCA CD tab in progress• LPI suction source is the RBES• HPI aligned for piggyback operation• 1LP-15 failed closed

    Based on the above conditions, which ONE of the following states...

    (1) if LPI ES analog channels are allowed to be manually bypassed in accordance withthe LOCA CD tab?AND

    (2) the MAXIMUM allowed HPI flow if ILP-15 will not open?

    LPI ES

    _____

    be bypassed AND the MAXIMUM allowed HPI flow is

    _____

    gpm.

    A. may I 750

    B. may NOT I 750

    C. may I 500

    D. may NOT I 500

    2010A NRC SENIOR REACTOR OPERATOR EXAM

    1 POINT Question 83

    Unit 1 plant conditions: • ALL SCM = O°F stable • RCS pressure = 855 psig slowly decreasing • LOCA CD tab in progress • LPI suction source is the RBES • HPI aligned for piggyback operation • 1 LP-15 failed closed

    Based on the above conditions, which ONE of the following states ...

    (1) if LPI ES analog channels are allowed to be manually bypassed in accordance with the LOCA CD tab? AND

    (2) the MAXIMUM allowed HPI flow if 1LP-15 will not open?

    LPI ES __ be bypassed AND the MAXIMUM allowed HPI flow is __ gpm.

    A. may / 750

    B. may NOT / 750

    C. may / 500

    D. may NOT / 500

  • 2010A NRC SENIOR REACTOR OPERATOR EXAM

    I POINTQuestion 84

    Unit 1 initial conditions:• Reactor power = 70% stable• 1B1 RCP has been secured• ICS is in manual

    Current conditions:• Group 2 Rod 4 drops into core

    Based on the above conditions, which ONE of the following describes the direction thatwill be provided to the RO AND the maximum time allowed by APII (Unit Runback) tocarry out the directions?

    Reduce Core Thermal Power to <

    _______

    within hour(s).

    A. 60% I I

    B. 60% I 2

    C. 45% I 1

    D. 45% I 2

    2010A NRC SENIOR REACTOR OPERATOR EXAM

    1 POINT Question 84

    Unit 1 initial conditions: • Reactor power = 70% stable • 1 B1 RCP has been secured • ICS is in manual

    Current conditions: • Group 2 Rod 4 drops into core

    Based on the above conditions, which ONE of the following describes the direction that will be provided to the RO AND the maximum time allowed by AP/1 (Unit Runback) to carry out the directions?

    Reduce Core Thermal Power to ~ ___ within ___ hour(s).

    A. 60% I 1

    B. 60% I 2

    C. 45% I 1

    D. 45% I 2

  • 2010A NRC SENIOR REACTOR OPERATOR EXAMI POINT

    Question 85

    Unit 2 initial conditions:• Reactor power = 100% stable

    Current conditions:• Reactor trip occurs• Main Turbine does NOT trip• Manual Turbine trip is unsuccessful

    Based on the above conditions, which ONE of the following describes actions requiredby the EOP AND the MAXIMUM time allowed by NSD 202 (Reportability) prior tonotifying the NRC?

    A. Place BOTH EHC pumps in PULL TO LOCK I eight hours

    B. Place BOTH EHC pumps in PULL TO LOCK I four hours

    C. Initiate Rule 5 (MSLB) I eight hours

    D. Initiate Rule 5 (MSLB) I four hours

    Question 85

    2010A NRC SENIOR REACTOR OPERATOR EXAM 1 POINT

    Unit 2 initial conditions: • Reactor power = 100% stable

    Current conditions: • Reactor trip occurs • Main Turbine does NOT trip • Manual Turbine trip is unsuccessful

    Based on the above conditions, which ONE of the following describes actions required by the EOP AND the MAXIMUM time allowed by NSD 202 (Reportability) prior to notifying the NRC?

    A. Place BOTH EHC pumps in PULL TO LOCK I eight hours

    B. Place BOTH EHC pumps in PULL TO LOCK I four hours

    C. Initiate Rule 5 (MSLB) I eight hours

    D. Initiate Rule 5 (MSLB) I four hours

  • 2010A NRC SENIOR REACTOR OPERATOR EXAM

    I POINTQuestion 86

    Unit I initial conditions:• Reactor in MODE 3• 1A2 and 1B2 RCP5 operating

    Current conditions:• RCS leakage = 140 gpm• All SCM’s = 45°F stable• Pressurizer level = 200 inches stable• 1A2 RCP Motor Upper Guide Bearing temperature = 195°F slowly increasing• 1 B2 RCP Motor Stator Temperature = 235°F slowly increasing

    Based on the above conditions, which ONE of the following describes the actionsrequired by AP/1 6 (Abnormal Reactor Coolant Pump Operation) AND which EOP tabwould provide guidance for a plant cooldown if ALL RCP’s are secured?

    Trip the

    A. 1A2 RCP / Forced Cooldown

    B. 1A2 RCP / LOCA Cooldown

    C. 1B2 RCP / Forced Cooldown

    D. I B2 RCP / LOCA Cooldown

    2010A NRC SENIOR REACTOR OPERATOR EXAM

    1 POINT Question 86

    Unit 1 initial conditions: • Reactor in MODE 3 • 1 A2 and 1 B2 RCPs operating

    Current conditions: • RCS leakage = 140 gpm • All SCM's = 45°F stable • Pressurizer level = 200 inches stable • 1A2 RCP Motor Upper Guide Bearing temperature = 195°F slowly increasing • 1 B2 RCP Motor Stator Temperature = 235°F slowly increasing

    Based on the above conditions, which ONE of the following describes the actions required by AP/16 (Abnormal Reactor Coolant Pump Operation) AND which EOP tab would provide guidance for a plant cooldown if ALL RCP's are secured?

    Trip the ...

    A. 1 A2 RCP / Forced Cooldown

    B. 1 A2 RCP / LOCA Cooldown

    C. 1 B2 RCP / Forced Cooldown

    D. 1 B2 RCP / LOCA Cooldown

  • 2010A NRC SENIOR REACTOR OPERATOR EXAMI POINT

    Question 87

    Unit 3 plant conditions:• Reactor power = 100%• 3A RBCU tagged out

    Based on the above conditions, which ONE of the following would require immediateentry into LCO 3.0.3 AND describes actions that are required once LCO 3.0.3 is enteredin accordance with OMP 2-23 (Operations Shift Manager Rules Of Practice)?

    A. 3LPSW-19 (3B RBCU INLET) fails closed I Must determine a time to begin powerreduction within 1 hour

    B. 3LPSW-19 (3B RBCU INLET) fails closed I Must actually initiate a power reductionwithin 1 hour

    C. 3A RBS Pump declared inoperable I Within 1 hour determine a time to initiatepower reduction

    D. 3A RBS Pump declared inoperable I Must actually initiate a power reduction within1 hour

    Question 87

    2010A NRC SENIOR REACTOR OPERATOR EXAM 1 POINT

    Unit 3 plant conditions: • Reactor power = 100% • 3A RBCU tagged out

    Based on the above conditions, which ONE of the following would require immediate entry into LCO 3.0.3 AND describes actions that are required once LCO 3.0.3 is entered in accordance with OMP 2-23 (Operations Shift Manager Rules Of Practice)?

    A. 3LPSW-19 (3B RBCU INLET) fails closed / Must determine a time to begin power reduction within 1 hour

    B. 3LPSW-19 (3B RBCU INLET) fails closed / Must actually initiate a power reduction within 1 hour

    C. 3A RBS Pump declared inoperable / Within 1 hour determine a time to initiate power reduction

    D. 3A RBS Pump declared inoperable / Must actually initiate a power reduction within 1 hour

  • 2010A NRC SENIOR REACTOR OPERATOR EXAM

    I POINTQuestion 88

    Plant initial conditions:• All three ONS units reactor power = 100%• STBY Buses 1 AND 2 energized from Central Switchyard

    Current conditions:• STBY Bus 1 locks out

    Based on the above conditions, which ONE of the following describes the operability ofthe Keowee Underground power path AND if Oconee Unit 1 experienced aLOCA/LOOP from where would the MFB5 receive power?

    Keowee Underground Power path is and Unit Is MFBs would be energizedfrom

    _______

    A. OPERABLE / CT-I

    B. OPERABLE ICT-5

    C. NOT OPERABLE / CT-l

    D. NOT OPERABLE I CT-5

    2010A NRC SENIOR REACTOR OPERATOR EXAM

    1 POINT Question 88

    Plant initial conditions: • All three ONS units reactor power = 100% • STBY Buses 1 AND 2 energized from Central Switchyard

    Current conditions: • STBY Bus 1 locks out

    Based on the above conditions, which ONE of the following describes the operability of the Keowee Underground power path AND if Oconee Unit 1 experienced a LOCAILOOP from where would the MFBs receive power?

    Keowee Underground Power path is ___ and Unit 1 s MFBs would be energized from ---

    A. OPERABLE / CT-1

    B. OPERABLE / CT-5

    C. NOT OPERABLE / CT-1

    D. NOT OPERABLE / CT-5

  • 2010A NRC SENIOR REACTOR OPERATOR EXAMI POINT

    Question 89

    Unit I plant conditions:• Reactor power = 20% stable• IA Main Feedwater Pump in service

    Based on the above conditions, which ONE of the following will require entry into theEOP AND describes the initial actions directed by the EOP if the NEO dispatched toverify ALL MSRV’s have reseated reports that one of the MSRV’s is still passing steam?

    A. FDWPT Exhaust Vacuum = 23.2 inches HG I Transfer to EHT tab

    B. FDWPT Exhaust Vacuum = 23.2 inches HG I Manually decrease SG pressure

    C. Feedwater pump bearing oil pressure = 3.1 psig I Transfer to EHT tab

    D. Feedwater pump bearing oil pressure = 3.1 psig I Manually decrease SC pressure

    Question 89

    2010A NRC SENIOR REACTOR OPERATOR EXAM 1 POINT

    Unit 1 plant conditions: • Reactor power = 20% stable • 1 A Main Feedwater Pump in service

    Based on the above conditions, which ONE of the following will require entry into the EOP AND describes the initial actions directed by the EOP if the NEO dispatched to verify ALL MSRV's have reseated reports that one of the MSRV's is still passing steam?

    A. FDWPT Exhaust Vacuum = 23.2 inches HG / Transfer to EHT tab

    B. FDWPT Exhaust Vacuum = 23.2 inches HG / Manually decrease SG pressure

    C. Feedwater pump bearing oil pressure = 3.1 psig / Transfer to EHT tab

    D. Feedwater pump bearing oil pressure = 3.1 psig / Manually decrease SG pressure

  • 2010A NRC SENIOR REACTOR OPERATOR EXAM

    I POINTQuestion 90

    Unit 1 initial conditions:• Reactor in MODE 6• Spent Fuel Pool in Refueling Cooling Mode alignment• Defueling in progress

    Current conditions:• Fuel Transfer Canal level decreasing

    Based on the above conditions, which ONE of the following describes why AP/26directs stopping all LPI pumps AND the reason the AP only requires establishingContainment Closure (vs. restoring containment to OPERABLE)?

    A. Determine if leak is on discharge of LPI pumps / fuel handling accidents will NOTresult in significant Containment pressurization

    B. Determine if leak is on discharge of LPI pumps I with an OPERABLE Containmentthe Main Purge system cannot be used to clean up RB atmosphere

    C. Allow closing of 1SF-I and 1SF-2 I fuel handling accidents will NOT result insignificant Containment pressurization

    D. Allow closing of 1SF-I and I SF-2 I with an OPERABLE Containment the MainPurge system cannot be used to clean up RB atmosphere

    2010A NRC SENIOR REACTOR OPERATOR EXAM

    1 POINT Question 90

    Unit 1 initial conditions: • Reactor in MODE 6 • Spent Fuel Pool in Refueling Cooling Mode alignment • Defueling in progress

    Current conditions: • Fuel Transfer Canal level decreasing

    Based on the above conditions, which ONE of the following describes why AP/26 directs stopping all LPI pumps AND the reason the AP only requires establishing Containment Closure (vs. restoring containment to OPERABLE)?

    A. Determine if leak is on discharge of LPI pumps / fuel handling accidents will NOT result in significant Containment pressurization

    B. Determine if leak is on discharge of LPI pumps / with an OPERABLE Containment the Main Purge system cannot be used to clean up RB atmosphere

    C. Allow closing of 1 SF-1 and 1 SF-2 / fuel handling accidents will NOT result in significant Containment pressurization

    D. Allow closing of 1 SF-1 and 1 SF-2 / with an OPERABLE Containment the Main Purge system cannot be used to clean up RB atmosphere

  • 2010A NRC SENIOR REACTOR OPERATOR EXAMI POINT

    Question 91

    Unit I plant conditions:• Reactor power = 100%• 1RC-1 fails open• 1 RC-3 will NOT close

    Based on the above conditions, which ONE of the following describes the initialresponse of I HP-120 (RC VOLUME CONTROL) valve position AND the action(s)required by AP144 (Abnormal Pressurizer Pressure Control)?

    IHP-120 valve position will initially

    ______

    AND AP144 will direct actions to

    A. remain approximately the same I trip the reactor and secure the IAI and 1A2RCP’s

    B. remain approximately the same I enter AP129, decrease power to

  • 2010A NRC SENIOR REACTOR OPERATOR EXAMI POINT

    Question 92

    Unit 3 initial conditions:• Reactor power= 100%• The volume of active TSP required by SLC 16.6.10 (Trisodium Phosphate) is

    NOT met

    Current conditions:• LOCA/LOOP occurs

    Based on the above conditions, which ONE of the following describes the consequenceof the inadequate TSP volume AND when TSP performs its credited function?

    A. ECCS acceptance criteria may be exceeded I During the injection phase

    B. ECCS acceptance criteria may be exceeded I During the recirculation phase

    C. Acceptable offsite dose limits may be exceeded I During the injection phase

    D. Acceptable offsite dose limits may be exceeded I During the recirculation phase

    Question 92

    2010A NRC SENIOR REACTOR OPERATOR EXAM 1 POINT

    Unit 3 initial conditions: • Reactor power = 100% • The volume of active TSP required by SLC 16.6.10 (Trisodium Phosphate) is

    NOT met

    Current conditions: • LOCAILOOP occurs

    Based on the above conditions, which ONE of the following describes the consequence of the inadequate TSP volume AND when TSP performs its credited function?

    A. ECCS acceptance criteria may be exceeded / During the injection phase

    B. ECCS acceptance criteria may be exceeded / During the recirculation phase

    C. Acceptable offsite dose limits may be exceeded / During the injection phase

    D. Acceptable offsite dose limits may be exceeded / During the recirculation phase

  • 2010A NRC SENIOR REACTOR OPERATOR EXAMI POINT

    Question 93

    Unit 3 initial conditions:• Reactor power= 100%• Fuel movement in Unit 3 Spent Fuel Pool

    Current conditions:• 3RIA-6 (SFP) in HIGH alarm• 3RIA-41 (SFP Gas) in HIGH alarm• 3SA-81B9 (PROCESS MONITOR RADIATION HIGH) in alarm

    Based on the above conditions, which ONE of the following describes the AbnormalProcedure of the highest priority and the Outside Air Booster Fans that will be started aspart of the mitigating actions?

    A. AP/9 (Spent Fuel Damage) I Unit 3 Outside Air Booster Fans ONLY

    B. API9 (Spent Fuel Damage) I Unit I and 2 AND Unit 3 Outside Air Booster Fans

    C. APII8 (Abnormal Release of Radioactivity) I Unit 3 Outside Air Booster Fans ONLY

    D. API18 (Abnormal Release of Radioactivity) I Unit 1 and 2 AND Unit 3 Outside AirBooster Fans

    Question 93

    2010A NRC SENIOR REACTOR OPERATOR EXAM 1 POINT

    Unit 3 initial conditions: • Reactor power = 100% • Fuel movement in Unit 3 Spent Fuel Pool

    Current conditions: • 3RIA-6 (SFP) in HIGH alarm • 3RIA-41 (SFP Gas) in HIGH alarm • 3SA-8/B9 (PROCESS MONITOR RADIATION HIGH) in alarm

    Based on the above conditions, which ONE of the following describes the Abnormal Procedure of the highest priority and the Outside Air Booster Fans that will be started as part of the mitigating actions?

    A. AP/9 (Spent Fuel Damage) / Unit 3 Outside Air Booster Fans ONLY

    B. AP/9 (Spent Fuel Damage) / Unit 1 and 2 AND Unit 3 Outside Air Booster Fans

    C. AP/18 (Abnormal Release of Radioactivity) / Unit 3 Outside Air Booster Fans ONLY

    D. AP/18 (Abnormal Release of Radioactivity) / Unit 1 and 2 AND Unit 3 Outside Air Booster Fans

  • 2010A NRC SENIOR REACTOR OPERATOR EXAMI POINT

    Question 94

    Which ONE of the following describes a condition that would require making a plantpage to implement Emergency Dose Limits AND whether that leakage would beincluded when calculating RCS Pressure Boundary leakacie (gpm) as defined in TechSpec 3.4.13 (RCS Operational Leakage)?

    A. 45 gpm SGTR / no

    B. 45gpmSGTR / yes

    C. 125 gpm RCS leak in RCP suction pipe weld / no

    D. 125 gpm RCS leak in RCP suction pipe weld / yes

    Question 94

    2010A NRC SENIOR REACTOR OPERATOR EXAM 1 POINT

    Which ONE of the following describes a condition that would require making a plant page to implement Emergency Dose Limits AND whether that leakage would be included when calculating RCS Pressure Boundary leakage (gpm) as defined in Tech Spec 3.4.13 (RCS Operational Leakage)?

    A. 45 gpm SGTR / no

    B. 45 gpm SGTR / yes

    C. 125 gpm RCS leak in RCP suction pipe weld / no

    D. 125 gpm RCS leak in RCP suction pipe weld / yes

  • 2010A NRC SENIOR REACTOR OPERATOR EXAMI POINT

    Question 95

    Unit 2 initial conditions:• Refueling in progress• FTC level = 22 feet stable• No water additions are being made to the system• 2A LPI train is operable and in service

    Current conditions:• Refueling SRO desires stopping the 2A LPI Pump to aid in inserting a fuel

    assembly• 2A LPI pump has been in continuous operation for the previous 24 hours

    Based on the above conditions, which ONE of the following describes whether the 2ALPI pump may be stopped in accordance with OPI2IA/1502/007 (Operations Defueling/Refueling Responsibilities) and the Tech Spec bases for requiring only I OPERABLEDHR loop in this condition?

    A. 2A LPI Pump may be stopped for up to 1 hour per 8 hour period.FTC level is within TS limits and provides adequate backup decay heat removal.

    B. 2A LPI Pump may be stopped for up to 1 hour per 8 hour period.Spent Fuel Cooling system provides adequate backup decay heat removal.

    C. 2A LPI Pump may NOT be stoppedFTC level is below TS limits and cannot provide adequate backup decay heatremoval.

    D. 2A LPI Pump may NOT be stoppedSpent Fuel Cooling system can NOT provide adequate backup decay heat removal.

    Question 95

    2010A NRC SENIOR REACTOR OPERATOR EXAM 1 POINT

    Unit 2 initial conditions: • Refueling in progress • FTC level = 22 feet stable • No water additions are being made to the system • 2A LPI train is operable and in service

    Current conditions: • Refueling SRO desires stopping the 2A LPI Pump to aid in inserting a fuel

    assembly • 2A LPI pump has been in continuous operation for the previous 24 hours

    Based on the above conditions, which ONE of the following describes whether the 2A LPI pump may be stopped in accordance with OP/21A11502/007 (Operations Defueling IRefueling Responsibilities) and the Tech Spec bases for requiring only 1 OPERABLE DHR loop in this condition?

    A. 2A LPI Pump may be stopped for up to 1 hour per 8 hour period. FTC level is within TS limits and provides adequate backup decay heat removal.

    B. 2A LPI Pump may be stopped for up to 1 hour per 8 hour period. Spent Fuel Cooling system provides adequate backup decay heat removal.

    C. 2A LPI Pump may NOT be stopped FTC level is below TS limits and cannot provide adequate backup decay heat removal.

    D. 2A LPI Pump may NOT be stopped Spent Fuel Cooling system can NOT provide adequate backup decay heat removal.

  • 2010A NRC SENIOR REACTOR OPERATOR EXAM

    I POINTQuestion 96

    Unit I plant conditions:• Reactor power = 75% stable• Regulating rods positioned in the Unacceptable region of the rod curves provided

    in the COLR

    Which ONE of the following describes the

    (1) direction that will be given to the OATC based on the above plant conditions...AND

    (2) consequences of continued power operations while in the Unacceptable Operationregion of the rod curves in the COLR in accordance with the bases forTS 3.2.1(Regulating Rods Position Limits)?

    RCS boration using

    _____

    is reciuired to begin within 15 minutes AND...

    A. 1A BHUT I required shutdown margin may not exist

    B. 1A BHUT I Quadrant Power Tilt limits may be exceeded

    C. Unit I CBAST I required shutdown margin may not exist

    D. Unit 1 CBAST I Quadrant Power Tilt limits may be exceeded

    2010A NRC SENIOR REACTOR OPERATOR EXAM

    1 POINT Question 96

    Unit 1 plant conditions: • Reactor power = 75% stable • Regulating rods positioned in the Unacceptable region of the rod curves provided

    in the COLR

    Which ONE of the following describes the ...

    (1) direction that will be given to the OATC based on the above plant conditions ... AND

    (2) consequences of continued power operations while in the Unacceptable Operation region of the rod curves in the COLR in accordance with the bases for TS 3.2.1 (Regulating Rods Position Limits)?

    RCS boration using __ is required to begin within 15 minutes AND ...

    A. 1A BHUT / required shutdown margin may not exist

    B. 1A BHUT / Quadrant Power Tilt limits may be exceeded

    C. Unit 1 CBAST / required shutdown margin may not exist

    D. Unit 1 CBAST / Quadrant Power Tilt limits may be exceeded

  • 2010A NRC SENIOR REACTOR OPERATOR EXAMI POINT

    Question 97

    Unit 3 plant conditions:• LPI aligned to normal DHR mode using 3A LPI pump• Both SG levels = 65% OR increasing using 3A and 3B MDEFWP’s• LR Cooldown pressure = 290 psig stable• 3TA and 3TB de-energized• CETC’s = 196°F stable• RCS Tcold = 205°F stable• 3A LPI Cooler Outlet temperature = 195°F stable

    Based on the above conditions, which ONE of the following describes the current plantMODE AND if the SG’s can be used as a backup method of heat removal in accordancewith Tech Specs?

    A. MODE4 I no

    B. MODE 4 I yes

    C. MODE5 I no

    D. MODE 5 I yes

    Question 97

    2010A NRC SENIOR REACTOR OPERATOR EXAM 1 POINT

    Unit 3 plant conditions: • LPI aligned to normal DHR mode using 3A LPI pump • Both SG levels = 65% OR increasing using 3A and 3B MDEFWP's • LR Cooldown pressure = 290 psig stable • 3T A and 3TB de-energized • CETC's = 196°F stable • RCS Tcold = 205°F stable • 3A LPI Cooler Outlet temperature = 195°F stable

    Based on the above conditions, which ONE of the following describes the current plant MODE AND if the SG's can be used as a backup method of heat removal in accordance with Tech Specs?

    A. MODE 4 / no

    B. MODE 4 / yes

    C. MODE 5 / no

    D. MODE 5 / yes

  • 2010A NRC SENIOR REACTOR OPERATOR EXAM

    I POINTQuestion 98

    Which ONE of the following describes the maximum dose (TEDE) that a non-volunteercan receive while saving a life and whose approval is required per RP/0/BI1 000/11(Planned Emergency Exposure).

    A. 10 rem / Emergency Coordinator

    B. 10 rem / Site Vice President

    C. 25 rem / Emergency Coordinator

    D. 25 rem / Site Vice President

    2010A NRC SENIOR REACTOR OPERATOR EXAM

    1 POINT Question 98

    Which ONE of the following describes the maximum dose (TEDE) that a non-volunteer can receive while saving a life and whose approval is required per RP/O/B/1000/11 (Planned Emergency Exposure).

    A. 10 rem 1 Emergency Coordinator

    B. 10 rem 1 Site Vice President

    C. 25 rem 1 Emergency Coordinator

    D. 25 rem 1 Site Vice President

  • 2010A NRC SENIOR REACTOR OPERATOR EXAM

    I POINTQuestion 99

    Plant conditions:

    • All 3 Units reactor power = 100%

    • 1SA-3/B6 (FIRE ALARM) actuated

    • NED’s dispatched to the Turbine Building Basement (Unit I and 2 Powdex area)

    Current conditions:

    • NEO reports: Fire location is TBB/K28. Heavy smoke and rolling flames (5-loft.)spreading out from the Powdex Alarm Panel

    Based on the above conditions, which ONE of the following describes the unit(s)requiring a reactor trip AND who is allowed to serve as a Fire Brigade leader inaccordance with the bases of SLC 16.13.1 (Minimum Station Staffing Requirements)?

    REFERENCE PROVIDED

    A. ALL units / SRO ONLY

    B. Unit 2 (only) / SRO ONLY

    C. ALL units / SRO OR an NED with appropriate qualifications

    D. Unit 2 (only) I SRO OR an NED with appropriate qualifications

    2010A NRC SENIOR REACTOR OPERATOR EXAM

    1 POINT Question 99

    Plant conditions:

    • All 3 Units reactor power = 100% • 1 SA-3/B6 (FIRE ALARM) actuated

    • NEO's dispatched to the Turbine Building Basement (Unit 1 and 2 Powdex area)

    Current conditions:

    • NEO reports: Fire location is TBB/K28. Heavy smoke and rolling flames (5-1 Oft.) spreading out from the Powdex Alarm Panel

    Based on the above conditions, which ONE of the following describes the unit(s) requiring a reactor trip AND who is allowed to serve as a Fire Brigade leader in accordance with the bases of SLC 16.13.1 (Minimum Station Staffing Requirements)?

    REFERENCE PROVIDED

    A. ALL units I SRO ONLY

    B. Unit 2 (only) I SRO ONLY

    C. ALL units I SRO OR an NEO with appropriate qualifications

    D. Unit 2 (only) I SRO OR an NEO with appropriate qualifications

  • 2010A NRC SENIOR REACTOR OPERATOR EXAM1 POINT

    Question 100

    Unit 1 initial conditions:• Reactor power = 100%• 1 RIA-59 reading 2 gpm slowly increasing• AP/31 (Primary to Secondary Leakage) in progress

    Current conditions:• Reactor power = 75% decreasing• 1RIA-59 reading 28 gpm increasing

    Based on the above conditions, which ONE of the following describes how the SRO willproceed AND the actions required if during the subsequent RCS cooldown if theisolated steam generator approaches overfill conditions (285” XSUR)?

    A. Continue shutdown under the direction of AP/31 I Initiate SG Blowdown

    B. Continue shutdown under the direction of API3I / Steam the SG to the condenser

    C. Go directly to SGTR tab / Initiate SG Blowdown

    D. Go directly to SGTR tab I Steam the SG to the condenser

    Question 100

    2010A NRC SENIOR REACTOR OPERATOR EXAM 1 POINT

    Unit 1 initial conditions: • Reactor power = 100% • 1 RIA-59 reading 2 gpm slowly increasing • AP/31 (Primary to Secondary Leakage) in progress

    Current conditions: • Reactor power = 75% decreasing • 1 RIA-59 reading 28 gpm increasing

    Based on the above conditions, which ONE of the following describes how the SRO will proceed AND the actions required if during the subsequent RCS cooldown if the isolated steam generator approaches overfill conditions (285" XSUR)?

    A. Continue shutdown under the direction of AP/31 I Initiate SG Blowdown

    B. Continue shutdown under the direction of AP/31 I Steam the SG to the condenser

    C. Go directly to SGTR tab I Initiate SG Blowdown

    D. Go directly to SGTR tab I Steam the SG to the condenser

  • Oconee 2010-301 Exam References

    RO Exam:

    Steam TablesUnit 1 Loop A Narrow Range PT Plot

    SRO Exam:

    RPIOIBII 000/001 (Emergency Classificalion)Technical Specification (T/S) 3.4.9 (Pressurizer)T/S 3.8.8 (Distribution Systems — Operating)Alarm Response Guide 1SA-03 B-6 pages 2-28.

    Oconee 2010-301 Exam References

    RO Exam:

    Steam Tables Unit 1 Loop A Narrow Range PT Plot

    SROExam:

    RP/O/8/10001001 (Emergency Classification) Technical Specification (TIS) 3.4.9 (Pressurizer) TIS 3.8.8 (Distribution Systems - Operating) Alarm Response Guide 1 SA-03 8-6 pages 2-28.

  • CDCD

    CDCD

    CDCD

    (0CD

    (0CD

    COCO

    COCO

    COCO

    11

    4ITO

    CDCO

    COU

    I(.

    )-

    QCD

    CO0

    )U

    )C.

    )1%

    )-

    0CD

    CO0

    )

    C,

    I —I--

    >>

    cD

    II

    II

    II

    I

    C,

    w

    II

    I

    m -<

    II

    II

    IICO

    III

    0 NJ cm ( 7c:7

    COconee 20/0 3D\ Sk:O e,{AW1 ~I

    Q# KEY I SJ 76 B 77 D 78 D 79 B 80 C 81 C 82 A 83 B 84 D 85 B 86 A 87 A 88 D 89 D 90 A 91 A 92 D 93 B 94 A 95 A 96 C 97 D 98 C 99 D 100 D