Upload
others
View
0
Download
0
Embed Size (px)
Citation preview
ES-401 Site-Specific SRO Written Examination Form ES-401-8Cover Sheet
U.S. Nuclear Regulatory Commission
Site-Specific SRO Written Examination
Applicant Information
Name:
Date: 04107/2010 Facility/Unit: Oconee
Region: I II III IV Reactor Type: W LICE E1BWGE LI
Start Time: Finish Time:
Instructions
Use the answer sheets provided to document your answers. Staple this cover sheeton top of the answer sheets. To pass the examination you must achieve a final gradeof at least 80.00 percent overall, with 70.00 percent or better on the SRO-only itemsif given in conjunction with the RO exam; SRO-only exams given alone require a final gradeof 80.00 percent to pass. You have 8 hours to complete the combined examination,and 3 hours if you are only taking the SRO portion.
Applicant Certification
All work done on this examination is my own. I have neither given nor received aid.
Applicant’s Signature
Results
RO/SRO-Only/Total Examination Values 75 / 25 / 100 Points
Applicant’s Scores
_____
/
_____
/
_____
Points
Applicant’s Grade
_____
I
_____
/
_____
Percent
ES-401 Site-Specific SRO Written Examination Cover Sheet
Form ES-401-8
U.S. Nuclear Regulatory Commission
Site-Specific SRO Written Examination
Applicant Information
Name:
Date: 04/07/2010 Facility/Unit: Oconee
Region: I D II ~ III D IV D Reactor Type: W DeE DBw~GE D
Start Time: Finish Time:
Instructions
Use the answer sheets provided to document your answers. Staple this cover sheet on top of the answer sheets. To pass the examination you must achieve a final grade of at least 80.00 percent overall, with 70.00 percent or better on the SRO-only items if given in conjunction with the RO exam; SRO-only exams given alone require a final grade of 80.00 percent to pass. You have 8 hours to complete the combined examination, and 3 hours if you are only taking the SRO portion.
Applicant Certification
All work done on this examination is my own. I have neither given nor received aid.
Applicant's Signature
Results
RO/SRO-OnlylTotal Examination Values 75 / ~ / 100 Points
Applicant's Scores / -- / -- Points
Applicant's Grade / -- / -- Percent
2010A NRC SENIOR REACTOR OPERATOR EXAM
I POINTQuestion 76
Unit 2 initial conditions:• Time=1300• Reactor power = 100%
Current conditions:• Time=1310• RCS pressure = 52 psig slowly decreasing• Reactor Building pressure = 52 psig slowly decreasing• All SCM’s = 0°F• 2RIA-57 = 92 R/hr slowly increasing• 2RIA-58 = 45 R/hr slowly increasing• Average of 5 highest CETC’s = 312°F decreasing• NO RBCU’s can be started• NO RBS Pumps can be started
Based on the above conditions, which ONE of the following is the Emergency ActionLevel Classification?
REFERENCE PROVIDED
A. Alert based on Loss of Fuel Clad Barrier and Potential Loss of Containment Barrier
B. Alert based on Loss of RCS Barrier and Potential Loss of Containment Barrier
C. Site Area Emergency based on Loss of RCS Barrier and Loss of ContainmentBarrier
D. Site Area Emergency based on Loss of Fuel Clad Barrier and Loss of ContainmentBarrier
2010A NRC SENIOR REACTOR OPERATOR EXAM
1 POINT Question 76
Unit 2 initial conditions: • Time = 1300 • Reactor power = 100%
Current conditions: • Time = 1310 • RCS pressure = 52 psig slowly decreasing • Reactor Building pressure = 52 psig slowly decreasing • All SCM's = OaF • 2RIA-57 = 92 Rlhr slowly increasing • 2RIA-58 = 45 Rlhr slowly increasing • Average of 5 highest CETC's = 312°F decreasing • NO RBCU's can be started • NO RBS Pumps can be started
Based on the above conditions, which ONE of the following is the Emergency Action Level Classification?
REFERENCE PROVIDED
A. Alert based on Loss of Fuel Clad Barrier and Potential Loss of Containment Barrier
B. Alert based on Loss of RCS Barrier and Potential Loss of Containment Barrier
C. Site Area Emergency based on Loss of RCS Barrier and Loss of Containment Barrier
D. Site Area Emergency based on Loss of Fuel Clad Barrier and Loss of Containment Barrier
2010A NRC SENIOR REACTOR OPERATOR EXAM
I POINTQuestion 77
Unit 1 plant conditions:• Reactor power = 100%• CC CRD Return Flow = 125 gpm slowly decreasing• CC Return Flow = 563 gpm decreasing• Letdown Temperature = 138°F stable• The following alarms have actuated:
o 1SA-91B-1 (CC CRD Return Flow Low).o ISA-21C-1 (HP Letdown Temperature High)o 1SA-91C-1 (CC Component Cooling Return Flow Low)
Based on the above conditions:(1) Which ONE of the following describes a required action from the associated ARG(s)
to mitigate this event?AND(2) If the ARG directed actions are NOT successful, which Abnormal Procedure is
required to be entered first?
A. (1) Decrease letdown flow using I HP-7 (LETDOWN CONTROL)
(2) AP/32 (Loss of Letdown)
B. (I) Decrease letdown flow using 1 HP-7 (LETDOWN CONTROL)
(2) AP/20 (Loss of Component Cooling)
C. (1) Verify CC Surge Tank level> 12 inches and start the standby CC pump
(2) AP/32 (Loss of Letdown)
D. (1) Verify CC Surge Tank level> 12 inches and start the standby CC pump
(2) AP/20 (Loss of Component Cooling)
2010A NRC SENIOR REACTOR OPERATOR EXAM
1 POINT Question 77
Unit 1 plant conditions: • Reactor power = 100% • CC CRD Return Flow = 125 gpm slowly decreasing • CC Return Flow = 563 gpm decreasing • Letdown Temperature = 138°F stable • The following alarms have actuated:
o 1SA-9/B-1 (CC CRD Return Flow Low). o 1 SA-2/C-1 (HP Letdown Temperature High) o 1 SA-9/C-1 (CC Component Cooling Return Flow Low)
Based on the above conditions: (1) Which ONE of the following describes a required action from the associated ARG(s)
to mitigate this event? AND (2) If the ARG directed actions are NOT successful, which Abnormal Procedure is
required to be entered first?
A. (1) Decrease letdown flow using 1 HP-7 (LETDOWN CONTROL)
(2) AP/32 (Loss of Letdown)
B. (1) Decrease letdown flow using 1 HP-7 (LETDOWN CONTROL)
(2) AP/20 (Loss of Component Cooling)
C. (1) Verify CC Surge Tank level> 12 inches and start the standby CC pump
(2) AP/32 (Loss of Letdown)
D. (1) Verify CC Surge Tank level> 12 inches and start the standby CC pump
(2) AP/20 (Loss of Component Cooling)
2010A NRC SENIOR REACTOR OPERATOR EXAM
I POINTQuestion 78
Unit I initial conditions:• Datel2/0I• TimeO800• Reactor Power = 100%• All Pressurizer heater breakers trip open and cannot be reclosed
Current conditions:• Date 12/04• Time 2200
Based on the above conditions, which ONE of the following is the HIGHER RCStemperature (degrees F) that is in compliance with the requirements of Tech SpecsAND the bases for the Pzr heater power supply requirements in TS 3.4.9 (Pressurizer)?
REFERENCE PROVIDED
A. 320 I ensure ability to perform a subcooled cooldown while on natural circulationduring an extended loss of power
B. 320 / ensure ability to control pressure and remain subcooled during an extendedloss of power
C. 375 I ensure ability to perform a natural circulation cooldown during an extendedloss of power
D. 375 / ensure ability to control pressure and remain subcooled during an extendedloss of power
2010A NRC SENIOR REACTOR OPERATOR EXAM
1 POINT Question 78
Unit 1 initial conditions: • Date = 12/01 • Time = 0800 • Reactor Power = 100% • All Pressurizer heater breakers trip open and cannot be reclosed
Current conditions: • Date = 12/04 • Time = 2200
Based on the above conditions, which ONE of the following is the HIGHER RCS temperature (degrees F) that is in compliance with the requirements of Tech Specs AND the bases for the Pzr heater power supply requirements in TS 3.4.9 (Pressurizer)?
REFERENCE PROVIDED
A. 320 / ensure ability to perform a subcooled cooldown while on natural circulation during an extended loss of power
B. 320 / ensure ability to control pressure and remain subcooled during an extended loss of power
C. 375 / ensure ability to perform a natural circulation cool down during an extended loss of power
D. 375 / ensure ability to control pressure and remain subcooled during an extended loss of power
2010A NRC SENIOR REACTOR OPERATOR EXAM
I POINTQuestion 79
Unit 1 initial conditions:• Reactor power = 75% stable• ICSinMANUAL• lB HPIP tagged out• The following alarms actuate:
o ISA-I/Al (RPCHANNELATRIP)o 1SA-l/Bl (RPCHANNELBTRIP)
Current conditions:• Reactor power = 34% slowly decreasing• BOTH Main Feedwater pumps are operating• All SCM’s = 0°F stable
Based on the above conditions, which ONE of the following describes the EOP tab thatwill be directed first AND the guidance the SRO will provide to the RO?
A. UNPP I Trip the Main Turbine
B. UNPP / Throttle Feedwater to control RCS temperature
C. LOSCM / Fully depressurize BOTH Steam Generators
D. LOSCM / Throttle Feedwater to control RCS temperature
2010A NRC SENIOR REACTOR OPERATOR EXAM
1 POINT Question 79
Unit 1 initial conditions: • Reactor power = 75% stable • ICS in MANUAL • 1 B HPIP tagged out • The following alarms actuate:
o 1SA-1/A1 (RP CHANNEL A TRIP) o 1SA-1/B1 (RP CHANNEL B TRIP)
Current conditions: • Reactor power = 34% slowly decreasing • BOTH Main Feedwater pumps are operating • All SCM's = OaF stable
Based on the above conditions, which ONE of the following describes the EOP tab that will be directed first AND the guidance the SRO will provide to the RO?
A. UNPP I Trip the Main Turbine
B. UNPP I Throttle Feedwater to control RCS temperature
C. LOSCM I Fully depressurize BOTH Steam Generators
D. LOSCM I Throttle Feedwater to control RCS temperature
2010A NRC SENIOR REACTOR OPERATOR EXAM
I POINTQuestion 80
Unit 3 plant conditions:• Date 4/5• Time1100• 3KVID panelboard de-energized
Current conditions:• Timel200• DC panelboard 3DIC is de-energized
Based on the above conditions, which ONE of the following states the actions requiredby Tech Spec 3.8.8 (Distribution Systems-Operating) AND the bases behind thedifferent Completion Times for inoperable Vital Instrument and Control panelboards?
REFERENCE PROVIDED
A. Restore either 3KVIC OR 3KVID within 24 hours I KVIA AND KVIB have shortercompletion times due to being the source of power for the ES Digital Channels
B. Restore either 3KVIC OR 3KVID within 24 hours I KVIA AND KVIB have shortercompletion times due to providing power for SK and SL breakers protective relaying
C. Enter LCO 3.0.3 immediately I KVIA AND KVIB have shorter completion times dueto being the source of power for the ES Digital Channels
D. Enter LCO 3.0.3 immediately I KVIA AND KVIB have shorter completion times dueto providing power for SK and SL breakers protective relaying
2010A NRC SENIOR REACTOR OPERATOR EXAM
1 POINT Question 80
Unit 3 plant conditions: • Date 4/5 • Time = 1100 • 3KVID panelboard de-energized
Current conditions: • Time = 1200 • DC panelboard 3DIC is de-energized
Based on the above conditions, which ONE of the following states the actions required by Tech Spec 3.8.8 (Distribution Systems-Operating) AND the bases behind the different Completion Times for inoperable Vital Instrument and Control panelboards?
REFERENCE PROVIDED
A. Restore either 3KVIC OR 3KVID within 24 hours / KVIA AND KVIB have shorter completion times due to being the source of power for the ES Digital Channels
B. Restore either 3KVIC OR 3KVID within 24 hours / KVIA AND KVIB have shorter completion times due to providing power for SK and SL breakers protective relaying
C. Enter LCO 3.0.3 immediately / KVIA AND KVIB have shorter completion times due to being the source of power for the ES Digital Channels
D. Enter LCO 3.0.3 immediately / KVIA AND KVIB have shorter completion times due to providing power for SK and SL breakers protective relaying
2010A NRC SENIOR REACTOR OPERATOR EXAM
1 POINTQuestion 81
Unit I initial conditions:• Reactor trip from 100% power• Both Main Feedwater pumps trip• EFDW pumps will not start
Current conditions:• Rule 3 in progress• LOHT tab initiated• ALL SCM’s> 0°F
Based on the above conditions, which ONE of the following would result in a transferout of the LOHT tab?
A. Pressurizer level = 375 inches
B. RCS heats up and results in ANY SCM = 0°F
C. HPI Forced Cooling is established and verified
D. Condensate Booster Pump feed is established
2010A NRC SENIOR REACTOR OPERATOR EXAM
1 POINT Question 81
Unit 1 initial conditions: • Reactor trip from 100% power • Both Main Feedwater pumps trip • EFDW pumps will not start
Current conditions: • Rule 3 in progress • LOHT tab initiated • ALL SCM's> OaF
Based on the above conditions, which ONE of the following would result in a transfer out of the LOHT tab?
A. Pressurizer level = 375 inches
B. RCS heats up and results in ANY SCM = OaF
C. HPI Forced Cooling is established and verified
D. Condensate Booster Pump feed is established
2010A NRC SENIOR REACTOR OPERATOR EXAM
I POINTQuestion 82
Unit 1 initial conditions:• Startup in progress• Reactor in MODE 3• Source Range NI’s 2 & 4 OOS• Source Range NI’s 1 & 3 = 834 cps increasing• Wide Range NI’s I thru 4 = 5E-5% increasing
Current conditions:• Source Range NI-I = 0 cps• 1SA-051A8 (NI-i TEST/FAIL) actuates
Based on the above conditions, which ONE of the following describes the reason for theNI-i indications AND the Tech Specs impact on the startup?
A. Loss of +1 5V Power supply / Suspend the startup
B. Loss of +1 5V Power supply I Startup may continue
C. Source range becomes saturated I Suspend the startup
D. Source range becomes saturated I Startup may continue
2010A NRC SENIOR REACTOR OPERATOR EXAM
1 POINT Question 82
Unit 1 initial conditions: • Startup in progress • Reactor in MODE 3 • Source Range Nl's 2 & 4 OOS • Source Range Nl's 1 & 3 = 834 cps increasing • Wide Range NI's 1 thru 4 = 5E-5% increasing
Current conditions: • Source Range NI-1 = 0 cps • 1 SA-05/A8 (NI-1 TEST/FAIL) actuates
Based on the above conditions, which ONE of the following describes the reason for the NI-1 indications AND the Tech Specs impact on the startup?
A. Loss of +15V Power supply / Suspend the startup
B. Loss of +15V Power supply / Startup may continue
C. Source range becomes saturated / Suspend the startup
D. Source range becomes saturated / Startup may continue
2010A NRC SENIOR REACTOR OPERATOR EXAM
I POINTQuestion 83
Unit I plant conditions:• ALL SCM = 0°F stable• RCS pressure = 855 psig slowly decreasing• LOCA CD tab in progress• LPI suction source is the RBES• HPI aligned for piggyback operation• 1LP-15 failed closed
Based on the above conditions, which ONE of the following states...
(1) if LPI ES analog channels are allowed to be manually bypassed in accordance withthe LOCA CD tab?AND
(2) the MAXIMUM allowed HPI flow if ILP-15 will not open?
LPI ES
_____
be bypassed AND the MAXIMUM allowed HPI flow is
_____
gpm.
A. may I 750
B. may NOT I 750
C. may I 500
D. may NOT I 500
2010A NRC SENIOR REACTOR OPERATOR EXAM
1 POINT Question 83
Unit 1 plant conditions: • ALL SCM = O°F stable • RCS pressure = 855 psig slowly decreasing • LOCA CD tab in progress • LPI suction source is the RBES • HPI aligned for piggyback operation • 1 LP-15 failed closed
Based on the above conditions, which ONE of the following states ...
(1) if LPI ES analog channels are allowed to be manually bypassed in accordance with the LOCA CD tab? AND
(2) the MAXIMUM allowed HPI flow if 1LP-15 will not open?
LPI ES __ be bypassed AND the MAXIMUM allowed HPI flow is __ gpm.
A. may / 750
B. may NOT / 750
C. may / 500
D. may NOT / 500
2010A NRC SENIOR REACTOR OPERATOR EXAM
I POINTQuestion 84
Unit 1 initial conditions:• Reactor power = 70% stable• 1B1 RCP has been secured• ICS is in manual
Current conditions:• Group 2 Rod 4 drops into core
Based on the above conditions, which ONE of the following describes the direction thatwill be provided to the RO AND the maximum time allowed by APII (Unit Runback) tocarry out the directions?
Reduce Core Thermal Power to <
_______
within hour(s).
A. 60% I I
B. 60% I 2
C. 45% I 1
D. 45% I 2
2010A NRC SENIOR REACTOR OPERATOR EXAM
1 POINT Question 84
Unit 1 initial conditions: • Reactor power = 70% stable • 1 B1 RCP has been secured • ICS is in manual
Current conditions: • Group 2 Rod 4 drops into core
Based on the above conditions, which ONE of the following describes the direction that will be provided to the RO AND the maximum time allowed by AP/1 (Unit Runback) to carry out the directions?
Reduce Core Thermal Power to ~ ___ within ___ hour(s).
A. 60% I 1
B. 60% I 2
C. 45% I 1
D. 45% I 2
2010A NRC SENIOR REACTOR OPERATOR EXAMI POINT
Question 85
Unit 2 initial conditions:• Reactor power = 100% stable
Current conditions:• Reactor trip occurs• Main Turbine does NOT trip• Manual Turbine trip is unsuccessful
Based on the above conditions, which ONE of the following describes actions requiredby the EOP AND the MAXIMUM time allowed by NSD 202 (Reportability) prior tonotifying the NRC?
A. Place BOTH EHC pumps in PULL TO LOCK I eight hours
B. Place BOTH EHC pumps in PULL TO LOCK I four hours
C. Initiate Rule 5 (MSLB) I eight hours
D. Initiate Rule 5 (MSLB) I four hours
Question 85
2010A NRC SENIOR REACTOR OPERATOR EXAM 1 POINT
Unit 2 initial conditions: • Reactor power = 100% stable
Current conditions: • Reactor trip occurs • Main Turbine does NOT trip • Manual Turbine trip is unsuccessful
Based on the above conditions, which ONE of the following describes actions required by the EOP AND the MAXIMUM time allowed by NSD 202 (Reportability) prior to notifying the NRC?
A. Place BOTH EHC pumps in PULL TO LOCK I eight hours
B. Place BOTH EHC pumps in PULL TO LOCK I four hours
C. Initiate Rule 5 (MSLB) I eight hours
D. Initiate Rule 5 (MSLB) I four hours
2010A NRC SENIOR REACTOR OPERATOR EXAM
I POINTQuestion 86
Unit I initial conditions:• Reactor in MODE 3• 1A2 and 1B2 RCP5 operating
Current conditions:• RCS leakage = 140 gpm• All SCM’s = 45°F stable• Pressurizer level = 200 inches stable• 1A2 RCP Motor Upper Guide Bearing temperature = 195°F slowly increasing• 1 B2 RCP Motor Stator Temperature = 235°F slowly increasing
Based on the above conditions, which ONE of the following describes the actionsrequired by AP/1 6 (Abnormal Reactor Coolant Pump Operation) AND which EOP tabwould provide guidance for a plant cooldown if ALL RCP’s are secured?
Trip the
A. 1A2 RCP / Forced Cooldown
B. 1A2 RCP / LOCA Cooldown
C. 1B2 RCP / Forced Cooldown
D. I B2 RCP / LOCA Cooldown
2010A NRC SENIOR REACTOR OPERATOR EXAM
1 POINT Question 86
Unit 1 initial conditions: • Reactor in MODE 3 • 1 A2 and 1 B2 RCPs operating
Current conditions: • RCS leakage = 140 gpm • All SCM's = 45°F stable • Pressurizer level = 200 inches stable • 1A2 RCP Motor Upper Guide Bearing temperature = 195°F slowly increasing • 1 B2 RCP Motor Stator Temperature = 235°F slowly increasing
Based on the above conditions, which ONE of the following describes the actions required by AP/16 (Abnormal Reactor Coolant Pump Operation) AND which EOP tab would provide guidance for a plant cooldown if ALL RCP's are secured?
Trip the ...
A. 1 A2 RCP / Forced Cooldown
B. 1 A2 RCP / LOCA Cooldown
C. 1 B2 RCP / Forced Cooldown
D. 1 B2 RCP / LOCA Cooldown
2010A NRC SENIOR REACTOR OPERATOR EXAMI POINT
Question 87
Unit 3 plant conditions:• Reactor power = 100%• 3A RBCU tagged out
Based on the above conditions, which ONE of the following would require immediateentry into LCO 3.0.3 AND describes actions that are required once LCO 3.0.3 is enteredin accordance with OMP 2-23 (Operations Shift Manager Rules Of Practice)?
A. 3LPSW-19 (3B RBCU INLET) fails closed I Must determine a time to begin powerreduction within 1 hour
B. 3LPSW-19 (3B RBCU INLET) fails closed I Must actually initiate a power reductionwithin 1 hour
C. 3A RBS Pump declared inoperable I Within 1 hour determine a time to initiatepower reduction
D. 3A RBS Pump declared inoperable I Must actually initiate a power reduction within1 hour
Question 87
2010A NRC SENIOR REACTOR OPERATOR EXAM 1 POINT
Unit 3 plant conditions: • Reactor power = 100% • 3A RBCU tagged out
Based on the above conditions, which ONE of the following would require immediate entry into LCO 3.0.3 AND describes actions that are required once LCO 3.0.3 is entered in accordance with OMP 2-23 (Operations Shift Manager Rules Of Practice)?
A. 3LPSW-19 (3B RBCU INLET) fails closed / Must determine a time to begin power reduction within 1 hour
B. 3LPSW-19 (3B RBCU INLET) fails closed / Must actually initiate a power reduction within 1 hour
C. 3A RBS Pump declared inoperable / Within 1 hour determine a time to initiate power reduction
D. 3A RBS Pump declared inoperable / Must actually initiate a power reduction within 1 hour
2010A NRC SENIOR REACTOR OPERATOR EXAM
I POINTQuestion 88
Plant initial conditions:• All three ONS units reactor power = 100%• STBY Buses 1 AND 2 energized from Central Switchyard
Current conditions:• STBY Bus 1 locks out
Based on the above conditions, which ONE of the following describes the operability ofthe Keowee Underground power path AND if Oconee Unit 1 experienced aLOCA/LOOP from where would the MFB5 receive power?
Keowee Underground Power path is and Unit Is MFBs would be energizedfrom
_______
A. OPERABLE / CT-I
B. OPERABLE ICT-5
C. NOT OPERABLE / CT-l
D. NOT OPERABLE I CT-5
2010A NRC SENIOR REACTOR OPERATOR EXAM
1 POINT Question 88
Plant initial conditions: • All three ONS units reactor power = 100% • STBY Buses 1 AND 2 energized from Central Switchyard
Current conditions: • STBY Bus 1 locks out
Based on the above conditions, which ONE of the following describes the operability of the Keowee Underground power path AND if Oconee Unit 1 experienced a LOCAILOOP from where would the MFBs receive power?
Keowee Underground Power path is ___ and Unit 1 s MFBs would be energized from ---
A. OPERABLE / CT-1
B. OPERABLE / CT-5
C. NOT OPERABLE / CT-1
D. NOT OPERABLE / CT-5
2010A NRC SENIOR REACTOR OPERATOR EXAMI POINT
Question 89
Unit I plant conditions:• Reactor power = 20% stable• IA Main Feedwater Pump in service
Based on the above conditions, which ONE of the following will require entry into theEOP AND describes the initial actions directed by the EOP if the NEO dispatched toverify ALL MSRV’s have reseated reports that one of the MSRV’s is still passing steam?
A. FDWPT Exhaust Vacuum = 23.2 inches HG I Transfer to EHT tab
B. FDWPT Exhaust Vacuum = 23.2 inches HG I Manually decrease SG pressure
C. Feedwater pump bearing oil pressure = 3.1 psig I Transfer to EHT tab
D. Feedwater pump bearing oil pressure = 3.1 psig I Manually decrease SC pressure
Question 89
2010A NRC SENIOR REACTOR OPERATOR EXAM 1 POINT
Unit 1 plant conditions: • Reactor power = 20% stable • 1 A Main Feedwater Pump in service
Based on the above conditions, which ONE of the following will require entry into the EOP AND describes the initial actions directed by the EOP if the NEO dispatched to verify ALL MSRV's have reseated reports that one of the MSRV's is still passing steam?
A. FDWPT Exhaust Vacuum = 23.2 inches HG / Transfer to EHT tab
B. FDWPT Exhaust Vacuum = 23.2 inches HG / Manually decrease SG pressure
C. Feedwater pump bearing oil pressure = 3.1 psig / Transfer to EHT tab
D. Feedwater pump bearing oil pressure = 3.1 psig / Manually decrease SG pressure
2010A NRC SENIOR REACTOR OPERATOR EXAM
I POINTQuestion 90
Unit 1 initial conditions:• Reactor in MODE 6• Spent Fuel Pool in Refueling Cooling Mode alignment• Defueling in progress
Current conditions:• Fuel Transfer Canal level decreasing
Based on the above conditions, which ONE of the following describes why AP/26directs stopping all LPI pumps AND the reason the AP only requires establishingContainment Closure (vs. restoring containment to OPERABLE)?
A. Determine if leak is on discharge of LPI pumps / fuel handling accidents will NOTresult in significant Containment pressurization
B. Determine if leak is on discharge of LPI pumps I with an OPERABLE Containmentthe Main Purge system cannot be used to clean up RB atmosphere
C. Allow closing of 1SF-I and 1SF-2 I fuel handling accidents will NOT result insignificant Containment pressurization
D. Allow closing of 1SF-I and I SF-2 I with an OPERABLE Containment the MainPurge system cannot be used to clean up RB atmosphere
2010A NRC SENIOR REACTOR OPERATOR EXAM
1 POINT Question 90
Unit 1 initial conditions: • Reactor in MODE 6 • Spent Fuel Pool in Refueling Cooling Mode alignment • Defueling in progress
Current conditions: • Fuel Transfer Canal level decreasing
Based on the above conditions, which ONE of the following describes why AP/26 directs stopping all LPI pumps AND the reason the AP only requires establishing Containment Closure (vs. restoring containment to OPERABLE)?
A. Determine if leak is on discharge of LPI pumps / fuel handling accidents will NOT result in significant Containment pressurization
B. Determine if leak is on discharge of LPI pumps / with an OPERABLE Containment the Main Purge system cannot be used to clean up RB atmosphere
C. Allow closing of 1 SF-1 and 1 SF-2 / fuel handling accidents will NOT result in significant Containment pressurization
D. Allow closing of 1 SF-1 and 1 SF-2 / with an OPERABLE Containment the Main Purge system cannot be used to clean up RB atmosphere
2010A NRC SENIOR REACTOR OPERATOR EXAMI POINT
Question 91
Unit I plant conditions:• Reactor power = 100%• 1RC-1 fails open• 1 RC-3 will NOT close
Based on the above conditions, which ONE of the following describes the initialresponse of I HP-120 (RC VOLUME CONTROL) valve position AND the action(s)required by AP144 (Abnormal Pressurizer Pressure Control)?
IHP-120 valve position will initially
______
AND AP144 will direct actions to
A. remain approximately the same I trip the reactor and secure the IAI and 1A2RCP’s
B. remain approximately the same I enter AP129, decrease power to
2010A NRC SENIOR REACTOR OPERATOR EXAMI POINT
Question 92
Unit 3 initial conditions:• Reactor power= 100%• The volume of active TSP required by SLC 16.6.10 (Trisodium Phosphate) is
NOT met
Current conditions:• LOCA/LOOP occurs
Based on the above conditions, which ONE of the following describes the consequenceof the inadequate TSP volume AND when TSP performs its credited function?
A. ECCS acceptance criteria may be exceeded I During the injection phase
B. ECCS acceptance criteria may be exceeded I During the recirculation phase
C. Acceptable offsite dose limits may be exceeded I During the injection phase
D. Acceptable offsite dose limits may be exceeded I During the recirculation phase
Question 92
2010A NRC SENIOR REACTOR OPERATOR EXAM 1 POINT
Unit 3 initial conditions: • Reactor power = 100% • The volume of active TSP required by SLC 16.6.10 (Trisodium Phosphate) is
NOT met
Current conditions: • LOCAILOOP occurs
Based on the above conditions, which ONE of the following describes the consequence of the inadequate TSP volume AND when TSP performs its credited function?
A. ECCS acceptance criteria may be exceeded / During the injection phase
B. ECCS acceptance criteria may be exceeded / During the recirculation phase
C. Acceptable offsite dose limits may be exceeded / During the injection phase
D. Acceptable offsite dose limits may be exceeded / During the recirculation phase
2010A NRC SENIOR REACTOR OPERATOR EXAMI POINT
Question 93
Unit 3 initial conditions:• Reactor power= 100%• Fuel movement in Unit 3 Spent Fuel Pool
Current conditions:• 3RIA-6 (SFP) in HIGH alarm• 3RIA-41 (SFP Gas) in HIGH alarm• 3SA-81B9 (PROCESS MONITOR RADIATION HIGH) in alarm
Based on the above conditions, which ONE of the following describes the AbnormalProcedure of the highest priority and the Outside Air Booster Fans that will be started aspart of the mitigating actions?
A. AP/9 (Spent Fuel Damage) I Unit 3 Outside Air Booster Fans ONLY
B. API9 (Spent Fuel Damage) I Unit I and 2 AND Unit 3 Outside Air Booster Fans
C. APII8 (Abnormal Release of Radioactivity) I Unit 3 Outside Air Booster Fans ONLY
D. API18 (Abnormal Release of Radioactivity) I Unit 1 and 2 AND Unit 3 Outside AirBooster Fans
Question 93
2010A NRC SENIOR REACTOR OPERATOR EXAM 1 POINT
Unit 3 initial conditions: • Reactor power = 100% • Fuel movement in Unit 3 Spent Fuel Pool
Current conditions: • 3RIA-6 (SFP) in HIGH alarm • 3RIA-41 (SFP Gas) in HIGH alarm • 3SA-8/B9 (PROCESS MONITOR RADIATION HIGH) in alarm
Based on the above conditions, which ONE of the following describes the Abnormal Procedure of the highest priority and the Outside Air Booster Fans that will be started as part of the mitigating actions?
A. AP/9 (Spent Fuel Damage) / Unit 3 Outside Air Booster Fans ONLY
B. AP/9 (Spent Fuel Damage) / Unit 1 and 2 AND Unit 3 Outside Air Booster Fans
C. AP/18 (Abnormal Release of Radioactivity) / Unit 3 Outside Air Booster Fans ONLY
D. AP/18 (Abnormal Release of Radioactivity) / Unit 1 and 2 AND Unit 3 Outside Air Booster Fans
2010A NRC SENIOR REACTOR OPERATOR EXAMI POINT
Question 94
Which ONE of the following describes a condition that would require making a plantpage to implement Emergency Dose Limits AND whether that leakage would beincluded when calculating RCS Pressure Boundary leakacie (gpm) as defined in TechSpec 3.4.13 (RCS Operational Leakage)?
A. 45 gpm SGTR / no
B. 45gpmSGTR / yes
C. 125 gpm RCS leak in RCP suction pipe weld / no
D. 125 gpm RCS leak in RCP suction pipe weld / yes
Question 94
2010A NRC SENIOR REACTOR OPERATOR EXAM 1 POINT
Which ONE of the following describes a condition that would require making a plant page to implement Emergency Dose Limits AND whether that leakage would be included when calculating RCS Pressure Boundary leakage (gpm) as defined in Tech Spec 3.4.13 (RCS Operational Leakage)?
A. 45 gpm SGTR / no
B. 45 gpm SGTR / yes
C. 125 gpm RCS leak in RCP suction pipe weld / no
D. 125 gpm RCS leak in RCP suction pipe weld / yes
2010A NRC SENIOR REACTOR OPERATOR EXAMI POINT
Question 95
Unit 2 initial conditions:• Refueling in progress• FTC level = 22 feet stable• No water additions are being made to the system• 2A LPI train is operable and in service
Current conditions:• Refueling SRO desires stopping the 2A LPI Pump to aid in inserting a fuel
assembly• 2A LPI pump has been in continuous operation for the previous 24 hours
Based on the above conditions, which ONE of the following describes whether the 2ALPI pump may be stopped in accordance with OPI2IA/1502/007 (Operations Defueling/Refueling Responsibilities) and the Tech Spec bases for requiring only I OPERABLEDHR loop in this condition?
A. 2A LPI Pump may be stopped for up to 1 hour per 8 hour period.FTC level is within TS limits and provides adequate backup decay heat removal.
B. 2A LPI Pump may be stopped for up to 1 hour per 8 hour period.Spent Fuel Cooling system provides adequate backup decay heat removal.
C. 2A LPI Pump may NOT be stoppedFTC level is below TS limits and cannot provide adequate backup decay heatremoval.
D. 2A LPI Pump may NOT be stoppedSpent Fuel Cooling system can NOT provide adequate backup decay heat removal.
Question 95
2010A NRC SENIOR REACTOR OPERATOR EXAM 1 POINT
Unit 2 initial conditions: • Refueling in progress • FTC level = 22 feet stable • No water additions are being made to the system • 2A LPI train is operable and in service
Current conditions: • Refueling SRO desires stopping the 2A LPI Pump to aid in inserting a fuel
assembly • 2A LPI pump has been in continuous operation for the previous 24 hours
Based on the above conditions, which ONE of the following describes whether the 2A LPI pump may be stopped in accordance with OP/21A11502/007 (Operations Defueling IRefueling Responsibilities) and the Tech Spec bases for requiring only 1 OPERABLE DHR loop in this condition?
A. 2A LPI Pump may be stopped for up to 1 hour per 8 hour period. FTC level is within TS limits and provides adequate backup decay heat removal.
B. 2A LPI Pump may be stopped for up to 1 hour per 8 hour period. Spent Fuel Cooling system provides adequate backup decay heat removal.
C. 2A LPI Pump may NOT be stopped FTC level is below TS limits and cannot provide adequate backup decay heat removal.
D. 2A LPI Pump may NOT be stopped Spent Fuel Cooling system can NOT provide adequate backup decay heat removal.
2010A NRC SENIOR REACTOR OPERATOR EXAM
I POINTQuestion 96
Unit I plant conditions:• Reactor power = 75% stable• Regulating rods positioned in the Unacceptable region of the rod curves provided
in the COLR
Which ONE of the following describes the
(1) direction that will be given to the OATC based on the above plant conditions...AND
(2) consequences of continued power operations while in the Unacceptable Operationregion of the rod curves in the COLR in accordance with the bases forTS 3.2.1(Regulating Rods Position Limits)?
RCS boration using
_____
is reciuired to begin within 15 minutes AND...
A. 1A BHUT I required shutdown margin may not exist
B. 1A BHUT I Quadrant Power Tilt limits may be exceeded
C. Unit I CBAST I required shutdown margin may not exist
D. Unit 1 CBAST I Quadrant Power Tilt limits may be exceeded
2010A NRC SENIOR REACTOR OPERATOR EXAM
1 POINT Question 96
Unit 1 plant conditions: • Reactor power = 75% stable • Regulating rods positioned in the Unacceptable region of the rod curves provided
in the COLR
Which ONE of the following describes the ...
(1) direction that will be given to the OATC based on the above plant conditions ... AND
(2) consequences of continued power operations while in the Unacceptable Operation region of the rod curves in the COLR in accordance with the bases for TS 3.2.1 (Regulating Rods Position Limits)?
RCS boration using __ is required to begin within 15 minutes AND ...
A. 1A BHUT / required shutdown margin may not exist
B. 1A BHUT / Quadrant Power Tilt limits may be exceeded
C. Unit 1 CBAST / required shutdown margin may not exist
D. Unit 1 CBAST / Quadrant Power Tilt limits may be exceeded
2010A NRC SENIOR REACTOR OPERATOR EXAMI POINT
Question 97
Unit 3 plant conditions:• LPI aligned to normal DHR mode using 3A LPI pump• Both SG levels = 65% OR increasing using 3A and 3B MDEFWP’s• LR Cooldown pressure = 290 psig stable• 3TA and 3TB de-energized• CETC’s = 196°F stable• RCS Tcold = 205°F stable• 3A LPI Cooler Outlet temperature = 195°F stable
Based on the above conditions, which ONE of the following describes the current plantMODE AND if the SG’s can be used as a backup method of heat removal in accordancewith Tech Specs?
A. MODE4 I no
B. MODE 4 I yes
C. MODE5 I no
D. MODE 5 I yes
Question 97
2010A NRC SENIOR REACTOR OPERATOR EXAM 1 POINT
Unit 3 plant conditions: • LPI aligned to normal DHR mode using 3A LPI pump • Both SG levels = 65% OR increasing using 3A and 3B MDEFWP's • LR Cooldown pressure = 290 psig stable • 3T A and 3TB de-energized • CETC's = 196°F stable • RCS Tcold = 205°F stable • 3A LPI Cooler Outlet temperature = 195°F stable
Based on the above conditions, which ONE of the following describes the current plant MODE AND if the SG's can be used as a backup method of heat removal in accordance with Tech Specs?
A. MODE 4 / no
B. MODE 4 / yes
C. MODE 5 / no
D. MODE 5 / yes
2010A NRC SENIOR REACTOR OPERATOR EXAM
I POINTQuestion 98
Which ONE of the following describes the maximum dose (TEDE) that a non-volunteercan receive while saving a life and whose approval is required per RP/0/BI1 000/11(Planned Emergency Exposure).
A. 10 rem / Emergency Coordinator
B. 10 rem / Site Vice President
C. 25 rem / Emergency Coordinator
D. 25 rem / Site Vice President
2010A NRC SENIOR REACTOR OPERATOR EXAM
1 POINT Question 98
Which ONE of the following describes the maximum dose (TEDE) that a non-volunteer can receive while saving a life and whose approval is required per RP/O/B/1000/11 (Planned Emergency Exposure).
A. 10 rem 1 Emergency Coordinator
B. 10 rem 1 Site Vice President
C. 25 rem 1 Emergency Coordinator
D. 25 rem 1 Site Vice President
2010A NRC SENIOR REACTOR OPERATOR EXAM
I POINTQuestion 99
Plant conditions:
• All 3 Units reactor power = 100%
• 1SA-3/B6 (FIRE ALARM) actuated
• NED’s dispatched to the Turbine Building Basement (Unit I and 2 Powdex area)
Current conditions:
• NEO reports: Fire location is TBB/K28. Heavy smoke and rolling flames (5-loft.)spreading out from the Powdex Alarm Panel
Based on the above conditions, which ONE of the following describes the unit(s)requiring a reactor trip AND who is allowed to serve as a Fire Brigade leader inaccordance with the bases of SLC 16.13.1 (Minimum Station Staffing Requirements)?
REFERENCE PROVIDED
A. ALL units / SRO ONLY
B. Unit 2 (only) / SRO ONLY
C. ALL units / SRO OR an NED with appropriate qualifications
D. Unit 2 (only) I SRO OR an NED with appropriate qualifications
2010A NRC SENIOR REACTOR OPERATOR EXAM
1 POINT Question 99
Plant conditions:
• All 3 Units reactor power = 100% • 1 SA-3/B6 (FIRE ALARM) actuated
• NEO's dispatched to the Turbine Building Basement (Unit 1 and 2 Powdex area)
Current conditions:
• NEO reports: Fire location is TBB/K28. Heavy smoke and rolling flames (5-1 Oft.) spreading out from the Powdex Alarm Panel
Based on the above conditions, which ONE of the following describes the unit(s) requiring a reactor trip AND who is allowed to serve as a Fire Brigade leader in accordance with the bases of SLC 16.13.1 (Minimum Station Staffing Requirements)?
REFERENCE PROVIDED
A. ALL units I SRO ONLY
B. Unit 2 (only) I SRO ONLY
C. ALL units I SRO OR an NEO with appropriate qualifications
D. Unit 2 (only) I SRO OR an NEO with appropriate qualifications
2010A NRC SENIOR REACTOR OPERATOR EXAM1 POINT
Question 100
Unit 1 initial conditions:• Reactor power = 100%• 1 RIA-59 reading 2 gpm slowly increasing• AP/31 (Primary to Secondary Leakage) in progress
Current conditions:• Reactor power = 75% decreasing• 1RIA-59 reading 28 gpm increasing
Based on the above conditions, which ONE of the following describes how the SRO willproceed AND the actions required if during the subsequent RCS cooldown if theisolated steam generator approaches overfill conditions (285” XSUR)?
A. Continue shutdown under the direction of AP/31 I Initiate SG Blowdown
B. Continue shutdown under the direction of API3I / Steam the SG to the condenser
C. Go directly to SGTR tab / Initiate SG Blowdown
D. Go directly to SGTR tab I Steam the SG to the condenser
Question 100
2010A NRC SENIOR REACTOR OPERATOR EXAM 1 POINT
Unit 1 initial conditions: • Reactor power = 100% • 1 RIA-59 reading 2 gpm slowly increasing • AP/31 (Primary to Secondary Leakage) in progress
Current conditions: • Reactor power = 75% decreasing • 1 RIA-59 reading 28 gpm increasing
Based on the above conditions, which ONE of the following describes how the SRO will proceed AND the actions required if during the subsequent RCS cooldown if the isolated steam generator approaches overfill conditions (285" XSUR)?
A. Continue shutdown under the direction of AP/31 I Initiate SG Blowdown
B. Continue shutdown under the direction of AP/31 I Steam the SG to the condenser
C. Go directly to SGTR tab I Initiate SG Blowdown
D. Go directly to SGTR tab I Steam the SG to the condenser
Oconee 2010-301 Exam References
RO Exam:
Steam TablesUnit 1 Loop A Narrow Range PT Plot
SRO Exam:
RPIOIBII 000/001 (Emergency Classificalion)Technical Specification (T/S) 3.4.9 (Pressurizer)T/S 3.8.8 (Distribution Systems — Operating)Alarm Response Guide 1SA-03 B-6 pages 2-28.
Oconee 2010-301 Exam References
RO Exam:
Steam Tables Unit 1 Loop A Narrow Range PT Plot
SROExam:
RP/O/8/10001001 (Emergency Classification) Technical Specification (TIS) 3.4.9 (Pressurizer) TIS 3.8.8 (Distribution Systems - Operating) Alarm Response Guide 1 SA-03 8-6 pages 2-28.
CDCD
CDCD
CDCD
(0CD
(0CD
COCO
COCO
COCO
11
4ITO
CDCO
COU
I(.
)-
QCD
CO0
)U
)C.
)1%
)-
0CD
CO0
)
C,
I —I--
>>
cD
II
II
II
I
C,
w
II
I
m -<
II
II
IICO
III
0 NJ cm ( 7c:7
COconee 20/0 3D\ Sk:O e,{AW1 ~I
Q# KEY I SJ 76 B 77 D 78 D 79 B 80 C 81 C 82 A 83 B 84 D 85 B 86 A 87 A 88 D 89 D 90 A 91 A 92 D 93 B 94 A 95 A 96 C 97 D 98 C 99 D 100 D