T h e A u d i t o r - G e n e r a l Report No.20 2011–12
Assurance Report
Defence Materiel Organisation
A u s t r a l i a n N a t i o n a l A u d i t O f f i c e
ANAO Report No.20 2011–12 2010–2011 Major Projects Report 2
© Commonwealth
of Australia 2011 ISSN 1036–7632 ISBN 0 642 81222 5
COPYRIGHT INFORMATION This work is copyright. Apart from any use as
permitted under the Copyright Act 1968, no part may be reproduced
by any process without prior written permission from the
Commonwealth. Requests and inquiries concerning reproduction and
rights should be addressed to: Executive Director Corporate
Management Branch Australian National Audit Office 19 National
Circuit BARTON ACT 2600 Or via email:
[email protected]
ANAO Report No.20 2011–12 2010–2011 Major Projects Report
3
Canberra ACT 20 December 2011 Dear Mr President Dear Mr Speaker The
Australian National Audit Office has undertaken a review of the
status of selected Defence equipment acquisition projects as at 30
June 2011 as presented by the Defence Materiel Organisation in
accordance with the authority contained in the Auditor-General Act
1997. Pursuant to Senate Standing Order 166 relating to the
presentation of documents when the Senate is not sitting, I present
the report of this review to the Parliament. The report is titled
2010–11 Major Projects Report. Following its presentation and
receipt, the report will be placed on the Australian National Audit
Office’s Homepage—http://www.anao.gov.au. Yours sincerely Ian
McPhee Auditor-General The Honourable the President of the Senate
The Honourable the Speaker of the House of Representatives
Parliament House Canberra ACT
ANAO Report No.20 2011–12 2010–2011 Major Projects Report 2
© Commonwealth
of Australia 2011 ISSN 1036–7632 ISBN 0 642 81222 5
COPYRIGHT INFORMATION This work is copyright. Apart from any use as
permitted under the Copyright Act 1968, no part may be reproduced
by any process without prior written permission from the
Commonwealth. Requests and inquiries concerning reproduction and
rights should be addressed to: Executive Director Corporate
Management Branch Australian National Audit Office 19 National
Circuit BARTON ACT 2600 Or via email:
[email protected]
ANAO Report No.20 2011–12 2010–2011 Major Projects Report
3
Canberra ACT 20 December 2011 Dear Mr President Dear Mr Speaker The
Australian National Audit Office has undertaken a review of the
status of selected Defence equipment acquisition projects as at 30
June 2011 as presented by the Defence Materiel Organisation in
accordance with the authority contained in the Auditor-General Act
1997. Pursuant to Senate Standing Order 166 relating to the
presentation of documents when the Senate is not sitting, I present
the report of this review to the Parliament. The report is titled
2010–11 Major Projects Report. Following its presentation and
receipt, the report will be placed on the Australian National Audit
Office’s Homepage—http://www.anao.gov.au. Yours sincerely Ian
McPhee Auditor-General The Honourable the President of the Senate
The Honourable the Speaker of the House of Representatives
Parliament House Canberra ACT
ANAO Report No.20 2011–12 2010–2011 Major Projects Report 4
AUDITING FOR AUSTRALIA The Auditor-General is head of the
Australian National Audit Office (ANAO). The ANAO assists the
Auditor-General to carry out his duties under the Auditor-General
Act 1997 to undertake performance audits, financial statement
audits and assurance reviews of Commonwealth public sector bodies
and to provide independent reports and advice for the Parliament,
the Australian Government and the community. The aim is to improve
Commonwealth public sector administration and accountability. For
further information contact: The Publications Manager Australian
National Audit Office GPO Box 707 Canberra ACT 2601 Telephone: (02)
6203 7505 Fax: (02) 6203 7519 Email:
[email protected] ANAO
audit reports and information about the ANAO are available at our
internet address: http://www.anao.gov.au
Assurance Review Team
Dr Carolyn Cuello Ben Watson Sean Neubeck Anora Harris
Anne Kent Evan Moraitis
ANAO Report No.20 2011–12 2010–2011 Major Projects Report
5
Auditor-General’s Foreword
..................................................................................
11 Summary
...................................................................................................................
13
Introduction
...........................................................................................................
13 Report objective and review scope
.......................................................................
16 Overall conclusion
................................................................................................
17
1. 2010–11 MPR Review
..........................................................................................
29 Introduction
...........................................................................................................
29 Report structure
....................................................................................................
29 Review approach
..................................................................................................
32 Review outcomes
.................................................................................................
36
2. Projects’ Performance
..........................................................................................
43 Introduction
...........................................................................................................
43 Cost performance
.................................................................................................
47 Schedule performance
..........................................................................................
58 Capability performance
.........................................................................................
71
3. Governance and Business Processes
..................................................................
81 Introduction
...........................................................................................................
81 Governance framework for Major Projects
............................................................ 81
Business Processes for Major Projects
.................................................................
84
Part 2. DMO Major Projects Report
.....................................................................
93
CEO DMO Foreword
.................................................................................................
95 Executive Summary
...................................................................................................
97 1. DMO Strategic Performance in 2010-11
..............................................................109
Introduction
..........................................................................................................109
DMO Overview
....................................................................................................110
DMO Strategic Risk Environment
........................................................................115
DMO Wide Risk Management Framework
...........................................................120
Project Lessons Learned
.....................................................................................121
Governance
.........................................................................................................125
Other Business Improvements
.............................................................................128
Base Date Dollar Budget Management
................................................................135
Out-turned Budget Management
.........................................................................136
2. Summary of Major Project Performance in 2010-11
...........................................139 Introduction
..........................................................................................................139
Performance Overview
........................................................................................140
ANAO Report No.20 2011–12 2010–2011 Major Projects Report 4
AUDITING FOR AUSTRALIA The Auditor-General is head of the
Australian National Audit Office (ANAO). The ANAO assists the
Auditor-General to carry out his duties under the Auditor-General
Act 1997 to undertake performance audits, financial statement
audits and assurance reviews of Commonwealth public sector bodies
and to provide independent reports and advice for the Parliament,
the Australian Government and the community. The aim is to improve
Commonwealth public sector administration and accountability. For
further information contact: The Publications Manager Australian
National Audit Office GPO Box 707 Canberra ACT 2601 Telephone: (02)
6203 7505 Fax: (02) 6203 7519 Email:
[email protected] ANAO
audit reports and information about the ANAO are available at our
internet address: http://www.anao.gov.au
Assurance Review Team
Dr Carolyn Cuello Ben Watson Sean Neubeck Anora Harris
Anne Kent Evan Moraitis
ANAO Report No.20 2011–12 2010–2011 Major Projects Report
5
Auditor-General’s Foreword
..................................................................................
11 Summary
...................................................................................................................
13
Introduction
...........................................................................................................
13 Report objective and review scope
.......................................................................
16 Overall conclusion
................................................................................................
17
1. 2010–11 MPR Review
..........................................................................................
29 Introduction
...........................................................................................................
29 Report structure
....................................................................................................
29 Review approach
..................................................................................................
32 Review outcomes
.................................................................................................
36
2. Projects’ Performance
..........................................................................................
43 Introduction
...........................................................................................................
43 Cost performance
.................................................................................................
47 Schedule performance
..........................................................................................
58 Capability performance
.........................................................................................
71
3. Governance and Business Processes
..................................................................
81 Introduction
...........................................................................................................
81 Governance framework for Major Projects
............................................................ 81
Business Processes for Major Projects
.................................................................
84
Part 2. DMO Major Projects Report
.....................................................................
93
CEO DMO Foreword
.................................................................................................
95 Executive Summary
...................................................................................................
97 1. DMO Strategic Performance in 2010-11
..............................................................109
Introduction
..........................................................................................................109
DMO Overview
....................................................................................................110
DMO Strategic Risk Environment
........................................................................115
DMO Wide Risk Management Framework
...........................................................120
Project Lessons Learned
.....................................................................................121
Governance
.........................................................................................................125
Other Business Improvements
.............................................................................128
Base Date Dollar Budget Management
................................................................135
Out-turned Budget Management
.........................................................................136
2. Summary of Major Project Performance in 2010-11
...........................................139 Introduction
..........................................................................................................139
Performance Overview
........................................................................................140
ANAO Report No.20 2011–12 2010–2011 Major Projects Report 6
Part 3. Auditor-General’s Review, CEO DMO Statement and
Project Data Summary Sheets
........................................................................................173
Independent Review Report by the Auditor-General
.................................................175
Statement by the CEO DMO
.....................................................................................179
Project Data Summary Sheets
..................................................................................183
AIR WARFARE DESTROYER
..............................................................................................
185 AIRBORNE EARLY WARNING AND CONTROL AIRCRAFT
............................................. 197 MULTI ROLE
HELICOPTER
.................................................................................................
207 BRIDGING AIR COMBAT CAPABILITY
...............................................................................
219 OVERLANDER
......................................................................................................................
235 AMPHIBIOUS SHIPS (LHD) PROJECT
...............................................................................
247 NEW AIR COMBAT CAPABILITY
.........................................................................................
259 ARMED RECONNAISSANCE HELICOPTER
......................................................................
271 F/A-18 HORNET UPGRADE
.................................................................................................
281 C-17 GLOBEMASTER III HEAVY AIRLIFTER
.....................................................................
295 AIR TO AIR REFUELLING CAPABILITY
..............................................................................
303 GUIDED MISSILE FRIGATE UPGRADE IMPLEMENTATION
............................................ 317 F/A-18 HORNET
UPGRADE STRUCTURAL REFURBISHMENT
...................................... 331 BUSHMASTER PROTECTED
MOBILITY VEHICLE
........................................................... 339
NEXT GENERATION SATCOM CAPABILITY
.....................................................................
351 HIGH FREQUENCY MODERNISATION
..............................................................................
361 SM-1 MISSILE REPLACEMENT
..........................................................................................
373 ADDITIONAL MEDIUM LIFT HELICOPTERS
......................................................................
385 ARMIDALE CLASS PATROL BOAT
.....................................................................................
395 ANZAC ANTI-SHIP MISSILE DEFENCE 2B
........................................................................
407 COLLINS REPLACEMENT COMBAT SYSTEM
..................................................................
419 REPLACEMENT HEAVYWEIGHT TORPEDO
....................................................................
431 COLLINS CLASS SUBMARINE RELIABILITY AND SUSTAINABILITY
.............................. 443 INDIAN OCEAN REGION UHF SATCOM
............................................................................
455 ANZAC ANTI-SHIP MISSILE DEFENCE 2A
........................................................................
465 FOLLOW ON STAND OFF WEAPON
..................................................................................
475 ARTILLERY REPLACEMENT PROJECT
.............................................................................
487 BATTLEFIELD COMMAND SUPPORT
................................................................................
499
Appendices
.............................................................................................................509
Appendix 1: Guidance for Readers of the DMO’s 2010-11 MPR Project
Data Summary Sheet
....................................................................511
Appendix 2: Types of Acquisition Undertaken by the DMO
...............................522 Appendix 3: Categorising
Acquisitions
..............................................................523
Appendix 4: Project Maturity Scores – Monitoring Progress
.............................524 Appendix 5: JCPAA Report 422:
REVIEW OF THE 2009-10 DEFENCE
MATERIEL ORGANISATION MAJOR PROJECTS REPORT .......529 Appendix 6:
Glossary
........................................................................................533
Series Titles
..............................................................................................................541
Current Better Practice Guides
.................................................................................544
ANAO Report No.20 2011–12 2010–2011 Major Projects Report
7
Abbreviations
ANAO
Australian National Audit Office
AOR Acquisition Overview Report
ARH Armed Reconnaissance Helicopter
ASMD AntiShip Missile Defence
AWD Air Warfare Destroyer
COTS CommercialOffTheShelf
DEFMIS
Defence Financial Management Information System
DMO Defence Materiel Organisation
FFG
Fast Frigate Guided (Guided Missile Frigate)
FIC
Fundamental Inputs to Capability
FMR Final Materiel Release
FMS Foreign Military Sales
FOC Final Operational Capability
Hw Heavyweight
ANAO Report No.20 2011–12 2010–2011 Major Projects Report 6
Part 3. Auditor-General’s Review, CEO DMO Statement and
Project Data Summary Sheets
........................................................................................173
Independent Review Report by the Auditor-General
.................................................175
Statement by the CEO DMO
.....................................................................................179
Project Data Summary Sheets
..................................................................................183
AIR WARFARE DESTROYER
..............................................................................................
185 AIRBORNE EARLY WARNING AND CONTROL AIRCRAFT
............................................. 197 MULTI ROLE
HELICOPTER
.................................................................................................
207 BRIDGING AIR COMBAT CAPABILITY
...............................................................................
219 OVERLANDER
......................................................................................................................
235 AMPHIBIOUS SHIPS (LHD) PROJECT
...............................................................................
247 NEW AIR COMBAT CAPABILITY
.........................................................................................
259 ARMED RECONNAISSANCE HELICOPTER
......................................................................
271 F/A-18 HORNET UPGRADE
.................................................................................................
281 C-17 GLOBEMASTER III HEAVY AIRLIFTER
.....................................................................
295 AIR TO AIR REFUELLING CAPABILITY
..............................................................................
303 GUIDED MISSILE FRIGATE UPGRADE IMPLEMENTATION
............................................ 317 F/A-18 HORNET
UPGRADE STRUCTURAL REFURBISHMENT
...................................... 331 BUSHMASTER PROTECTED
MOBILITY VEHICLE
........................................................... 339
NEXT GENERATION SATCOM CAPABILITY
.....................................................................
351 HIGH FREQUENCY MODERNISATION
..............................................................................
361 SM-1 MISSILE REPLACEMENT
..........................................................................................
373 ADDITIONAL MEDIUM LIFT HELICOPTERS
......................................................................
385 ARMIDALE CLASS PATROL BOAT
.....................................................................................
395 ANZAC ANTI-SHIP MISSILE DEFENCE 2B
........................................................................
407 COLLINS REPLACEMENT COMBAT SYSTEM
..................................................................
419 REPLACEMENT HEAVYWEIGHT TORPEDO
....................................................................
431 COLLINS CLASS SUBMARINE RELIABILITY AND SUSTAINABILITY
.............................. 443 INDIAN OCEAN REGION UHF SATCOM
............................................................................
455 ANZAC ANTI-SHIP MISSILE DEFENCE 2A
........................................................................
465 FOLLOW ON STAND OFF WEAPON
..................................................................................
475 ARTILLERY REPLACEMENT PROJECT
.............................................................................
487 BATTLEFIELD COMMAND SUPPORT
................................................................................
499
Appendices
.............................................................................................................509
Appendix 1: Guidance for Readers of the DMO’s 2010-11 MPR Project
Data Summary Sheet
....................................................................511
Appendix 2: Types of Acquisition Undertaken by the DMO
...............................522 Appendix 3: Categorising
Acquisitions
..............................................................523
Appendix 4: Project Maturity Scores – Monitoring Progress
.............................524 Appendix 5: JCPAA Report 422:
REVIEW OF THE 2009-10 DEFENCE
MATERIEL ORGANISATION MAJOR PROJECTS REPORT .......529 Appendix 6:
Glossary
........................................................................................533
Series Titles
..............................................................................................................541
Current Better Practice Guides
.................................................................................544
ANAO Report No.20 2011–12 2010–2011 Major Projects Report
7
Abbreviations
ANAO
Australian National Audit Office
AOR Acquisition Overview Report
ARH Armed Reconnaissance Helicopter
ASMD AntiShip Missile Defence
AWD Air Warfare Destroyer
COTS CommercialOffTheShelf
DEFMIS
Defence Financial Management Information System
DMO Defence Materiel Organisation
FFG
Fast Frigate Guided (Guided Missile Frigate)
FIC
Fundamental Inputs to Capability
FMR Final Materiel Release
FMS Foreign Military Sales
FOC Final Operational Capability
Hw Heavyweight
ANAO Report No.20 2011–12 2010–2011 Major Projects Report 8
IMR Initial Materiel Release
IOC Initial Operational Capability
JSF Joint Strike Fighter
LHD Landing Helicopter Docks
MAA Materiel Acquisition Agreement
MOTS MilitaryOffTheShelf
MOU Memorandum Of Understanding
MPR Major Projects Report
MRH90 MultiRole Helicopter
MRM Materiel Release Milestone
RCS Replacement Combat System
R&S Reliability and Sustainability
SADI
Skilling Australia’s Defence Industry
SATCOM Satellite Communication
ANAO Overview ANAO Report No.20 2011–12
2010–2011 Major Projects Report
9
Part 1: ANAO Overview
ANAO Report No.20 2011–12 2010–2011 Major Projects Report 8
IMR Initial Materiel Release
IOC Initial Operational Capability
JSF Joint Strike Fighter
LHD Landing Helicopter Docks
MAA Materiel Acquisition Agreement
MOTS MilitaryOffTheShelf
MOU Memorandum Of Understanding
MPR Major Projects Report
MRH90 MultiRole Helicopter
MRM Materiel Release Milestone
RCS Replacement Combat System
R&S Reliability and Sustainability
SADI
Skilling Australia’s Defence Industry
SATCOM Satellite Communication
ANAO Overview ANAO Report No.20 2011–12
2010–2011 Major Projects Report
9
Part 1: ANAO Overview
ANAO Overview ANAO Report No.20 2011–12 2010–2011 Major Projects
Report 10
ANAO Overview ANAO Report No.20 2011–12
2010–2011 Major Projects Report
11
Auditor-General’s Foreword Managing major Defence
equipment acquisitions that successfully
deliver front line capability for
the Australian Defence Force
represents a significant
challenge, not unique
to Australia. As major Defence equipment acquisitions
are often expensive and technically
complex, there are significant risks,
not only
to delivering within budget and on schedule, but also
to delivering the
required capability.
This fourth review of the
status of selected Defence equipment
acquisition
projects builds on the work undertaken by the Defence Materiel Organisation
(DMO) and the Australian National
Audit Office (ANAO) to improve
the transparency and public
accountability for major Defence
equipment acquisitions. The
2010–11 Major Projects Report (MPR)
includes 28 projects with approved
budgets totalling $46.1 billion,
which is over half of the
approved budget for the DMO’s
major capital investment program
($79.5 billion).
The preparation of the MPR has
received strong ongoing support from
the
Government and the Joint Committee of Public Accounts and Audit (JCPAA).
In April 2011, the second examination of the MPR by the JCPAA culminated in
the publishing of JCPAA Report
422, Review of the
2009–10 Defence Materiel
Organisation Major Projects Report. Report 422 made nine recommendations
to further progress and improve
the transparency and accountability
of major Defence equipment
acquisitions. Action already taken by
the DMO to implement
the JCPAA’s recommendations contributed to the enhancement of
this MPR, in terms of improved reporting on each of the three key elements of
the MPR: cost, schedule and
capability. As the DMO
further progresses the
implementation of these recommendations, future MPRs will also benefit.
In addition,
the Foreign Affairs, Defence and Trade References Committee
is
currently undertaking an inquiry into Procurement procedures for Defence capital
projects. This report, which covers DMO’s most significant procurements, along
with other ANAO reports on
Defence acquisitions, provides relevant
information to assist the Committee in its deliberations.
ANAO Overview ANAO Report No.20 2011–12 2010–2011 Major Projects
Report 10
ANAO Overview ANAO Report No.20 2011–12
2010–2011 Major Projects Report
11
Auditor-General’s Foreword Managing major Defence
equipment acquisitions that successfully
deliver front line capability for
the Australian Defence Force
represents a significant
challenge, not unique
to Australia. As major Defence equipment acquisitions
are often expensive and technically
complex, there are significant risks,
not only
to delivering within budget and on
schedule, but also to delivering
the required capability.
This fourth review of the
status of selected Defence equipment
acquisition
projects builds on the work undertaken by the Defence Materiel Organisation
(DMO) and the Australian National
Audit Office (ANAO) to improve
the transparency and public
accountability for major Defence
equipment acquisitions. The
2010–11 Major Projects Report (MPR)
includes 28 projects with approved
budgets totalling $46.1 billion,
which is over half of the
approved budget for the DMO’s
major capital investment program
($79.5 billion).
The preparation of the MPR has
received strong ongoing support from
the
Government and the Joint Committee of Public Accounts and Audit (JCPAA).
In April 2011, the second examination of the MPR by the JCPAA culminated in
the publishing of JCPAA Report
422, Review of the
2009–10 Defence Materiel
Organisation Major Projects Report. Report 422 made nine recommendations
to further progress and improve
the transparency and accountability
of major Defence equipment
acquisitions. Action already taken by
the DMO to implement
the JCPAA’s recommendations contributed to the enhancement of
this MPR, in terms of improved reporting on each of the three key elements of
the MPR: cost, schedule and
capability. As the DMO
further progresses the
implementation of these recommendations, future MPRs will also benefit.
In addition,
the Foreign Affairs, Defence and Trade References Committee
is
currently undertaking an inquiry into Procurement procedures for Defence capital
projects. This report, which covers DMO’s most significant procurements, along
with other ANAO reports on
Defence acquisitions, provides relevant
information to assist the Committee in its deliberations.
ANAO Overview ANAO Report No.20 2011–12 2010–2011 Major Projects
Report 12
2010–2011 Major Projects Report
13
Summary Introduction 1.
Major Defence equipment acquisition projects
(Major Projects) are the
subject of considerable Parliamentary and public interest, in view of their high
cost, planned contribution to national security and the challenges
involved in
completing Major Projects within budget, on time and to the required level of
capability.
2. The Defence Materiel Organisation
(DMO) contributes to the
development and sustainment of
capability for
the Australian Defence Force
(ADF) and expended some $5.6 billion on major and minor capital acquisition
projects in 2010–11.1
3.
Over the next 15 years, the Government intends to replace or upgrade
up to 55 per cent of
the ADF’s equipment.2 This will
include the purchase of
equipment in all of the major elements of ADF capability, including Land, Air,
Sea and Joint capabilities, as
publicised in the Defence White
Paper. These procurements by
the DMO do not generate new
capability for the Defence
Organisation until they have been successfully introduced into service with the
ADF. Thus, while the DMO’s role is only part of the introduction into service
of new capability, it is a significant one.
2010–11 Major Projects Report projects 4.
This fourth report covers 28 of the DMO’s Major Projects, an increase of
six projects on last year’s report and an increase of 19 projects when compared
to the first Major Projects Report
(MPR), which was tabled
in Parliament in
November 2008. The 28 Major Projects and their approved budgets are set out
in Table 1.
5. In total, the approved budgets
for the 28 Major Projects amount
to
$46.1 billion, as at 30 June 2011. This represents over half of the budget for the
DMO’s approved major capital investment program ($79.5 billion).
1 Department of Defence, Defence Annual Report 2010–11, Volume 2
Defence Materiel Organisation,
p. 25. 2 Minister for Defence Materiel, the Hon. Jason Clare MP,
Defence Skills Plan to Meet the Challenges
Ahead, Brisbane 2011.
ANAO Overview ANAO Report No.20 2011–12 2010–2011 Major Projects
Report 12
2010–2011 Major Projects Report
13
Summary Introduction 1.
Major Defence equipment acquisition projects
(Major Projects) are the
subject of considerable Parliamentary and public interest, in view of their high
cost, planned contribution to national security and the challenges
involved in
completing Major Projects within budget, on time and to the required level of
capability.
2. The Defence Materiel Organisation
(DMO) contributes to the
development and sustainment of
capability for
the Australian Defence Force
(ADF) and expended some $5.6 billion on major and minor capital acquisition
projects in 2010–11.1
3.
Over the next 15 years, the Government intends to replace or upgrade
up to 55 per cent of
the ADF’s equipment.2 This will
include the purchase of
equipment in all of the major elements of ADF capability, including Land, Air,
Sea and Joint capabilities, as
publicised in the Defence White
Paper. These procurements by
the DMO do not generate new
capability for the Defence
Organisation until they have been successfully introduced into service with the
ADF. Thus, while the DMO’s role is only part of the introduction into service
of new capability, it is a significant one.
2010–11 Major Projects Report projects 4.
This fourth report covers 28 of the DMO’s Major Projects, an increase of
six projects on last year’s report and an increase of 19 projects when compared
to the first Major Projects Report
(MPR), which was tabled
in Parliament in
November 2008. The 28 Major Projects and their approved budgets are set out
in Table 1.
5. In total, the approved budgets
for the 28 Major Projects amount
to
$46.1 billion, as at 30 June 2011. This represents over half of the budget for the
DMO’s approved major capital investment program ($79.5 billion).
1 Department of Defence, Defence Annual Report 2010–11, Volume 2
Defence Materiel Organisation,
p. 25. 2 Minister for Defence Materiel, the Hon. Jason Clare MP,
Defence Skills Plan to Meet the Challenges
Ahead, Brisbane 2011.
ANAO Overview ANAO Report No.20 2011–12 2010–2011 Major Projects
Report 14
6.
The ANAO’s review of these Major Projects is in addition to its regular
program of performance audits and financial statement audit work conducted
in the Defence portfolio.
Role of the Joint Committee of Public Accounts and Audit
7. The
Joint Committee of Public Accounts and Audit
(JCPAA) has been influential in
establishing the MPR, and has
taken an active role in the
development of the MPR program.3 In April 2011 the Committee published its
second report on its review of
the annual MPR.4 The report
made nine recommendations to further
progress and improve the
accountability and
transparency of major Defence equipment acquisitions
including with respect to
the presentation of financial data
by the DMO, which was the
subject of
audit qualification in prior years.
3 The guidelines for the 2010–11 MPR, which were endorsed by the
JCPAA in May 2011, set out the
requirements for the DMO project offices to provide complete and
accurate Project Data Summary Sheets and supporting information for
the ANAO to review.
4 Joint Committee of Public Accounts and Audit, Report 422, Review
of the 2009–10 Defence Materiel Organisation Major Projects Report,
April 2011, p. iii.
ANAO Overview ANAO Report No.20 2011–12
2010–2011 Major Projects Report
15
Table 1 2010–11 MPR projects and approved budgets at 30 June
2011
Project DMO Abbreviation Approved
Budget $m
Air Warfare Destroyer Build (SEA 4000 Ph 3) AWD Ships 7 931.8
Airborne Early Warning and Control Aircraft (AIR 5077 Ph 3)
Wedgetail 3 859.5
Multi-Role Helicopter (AIR 9000 Ph 2/4/6) MRH90 Helicopters 3
753.7
Bridging Air Combat Capability (AIR 5349 Ph 1/2)* Super Hornet 3
578.5
Field Vehicles and Trailers (LAND 121 Ph 3) Overlander Vehicles 3
263.9
Amphibious Ships (LHD) (JP 2048 Ph 4A/4B) LHD Ships 3 122.6
New Air Combat Capability (AIR 6000 Ph 2A/2B)* Joint Strike Fighter
2 666.8
Armed Reconnaissance Helicopter (AIR 87 Ph 2) ARH Tiger Helicopters
2 060.3
F/A-18 Hornet Upgrade (AIR 5376 Ph 2) Hornet Upgrade 1 917.5
C-17 Globemaster III Heavy Airlifter (AIR 8000 Ph 3) C-17 Heavy
Airlift 1 848.9
Air to Air Refuelling Capability (AIR 5402) Air to Air Refuel 1
828.5
Guided Missile Frigate Upgrade Implementation (SEA 1390 Ph 2.1) FFG
Upgrade 1 528.9
F/A-18 Hornet Upgrade Structural Refurbishment (AIR 5376 Ph 3.2)
Hornet Refurb 951.3
Bushmaster Protected Mobility Vehicle (LAND 116 Ph 3) Bushmaster
Vehicles 929.8
Next Generation SATCOM Capability (JP 2008 Ph 4) Next Gen Satellite
880.9
High Frequency Modernisation (JP 2043 Ph 3A) HF Modernisation
670.8
SM-1 Missile Replacement (SEA 1390 Ph 4B)* SM-2 Missile 612.0
Additional Medium Lift Helicopters (AIR 9000 Ph 5C)* Additional
Chinook 584.6
Armidale Class Patrol Boat (SEA 1444 Ph 1) Armidales 537.2
ANZAC Anti-Ship Missile Defence (SEA 1448 Ph 2B) ANZAC ASMD 2B
462.0
Collins Replacement Combat System (SEA 1439 Ph 4A) Collins RCS
450.4
Replacement Heavyweight Torpedo (SEA 1429 Ph 2) Hw Torpedo
425.4
Collins Class Submarine Reliability and Sustainability (SEA 1439 Ph
3) Collins R&S 411.4
Indian Ocean Region UHF SATCOM (JP 2008 Ph 5A)* UHF SATCOM
407.2
ANZAC Anti-Ship Missile Defence (SEA 1448 Ph 2A) ANZAC ASMD 2A
389.5
Follow On Stand Off Weapon (AIR 5418 Ph 1) Stand Off Weapon
343.3
Artillery Replacement (LAND 17 Ph 1A)* 155mm Howitzer 326.1
Battlefield Command Support (LAND 75 Ph 3.4) * Battle Comm. Sys.
325.9
Total 46 068.7
Source: 2010–11 MPR, Part 3, Project Data Summary Sheets.
Note: *Indicates the project is included in the MPR program for the
first time in the 2010–11 Report. For Bridging Air Combat
Capability (AIR 5349), only Phase 2 was reported for the first time
in 2010–11.
ANAO Overview ANAO Report No.20 2011–12 2010–2011 Major Projects
Report 14
6.
The ANAO’s review of these Major Projects is in addition to its regular
program of performance audits and financial statement audit work conducted
in the Defence portfolio.
Role of the Joint Committee of Public Accounts and Audit
7. The
Joint Committee of Public Accounts and Audit
(JCPAA) has been influential in
establishing the MPR, and has
taken an active role in the
development of the MPR program.3 In April 2011 the Committee published its
second report on its review of
the annual MPR.4 The report
made nine recommendations to further
progress and improve the
accountability and
transparency of major Defence equipment acquisitions
including with respect to
the presentation of financial data
by the DMO, which was the
subject of
audit qualification in prior years.
3 The guidelines for the 2010–11 MPR, which were endorsed by the
JCPAA in May 2011, set out the
requirements for the DMO project offices to provide complete and
accurate Project Data Summary Sheets and supporting information for
the ANAO to review.
4 Joint Committee of Public Accounts and Audit, Report 422, Review
of the 2009–10 Defence Materiel Organisation Major Projects Report,
April 2011, p. iii.
ANAO Overview ANAO Report No.20 2011–12
2010–2011 Major Projects Report
15
Table 1 2010–11 MPR projects and approved budgets at 30 June
2011
Project DMO Abbreviation Approved
Budget $m
Air Warfare Destroyer Build (SEA 4000 Ph 3) AWD Ships 7 931.8
Airborne Early Warning and Control Aircraft (AIR 5077 Ph 3)
Wedgetail 3 859.5
Multi-Role Helicopter (AIR 9000 Ph 2/4/6) MRH90 Helicopters 3
753.7
Bridging Air Combat Capability (AIR 5349 Ph 1/2)* Super Hornet 3
578.5
Field Vehicles and Trailers (LAND 121 Ph 3) Overlander Vehicles 3
263.9
Amphibious Ships (LHD) (JP 2048 Ph 4A/4B) LHD Ships 3 122.6
New Air Combat Capability (AIR 6000 Ph 2A/2B)* Joint Strike Fighter
2 666.8
Armed Reconnaissance Helicopter (AIR 87 Ph 2) ARH Tiger Helicopters
2 060.3
F/A-18 Hornet Upgrade (AIR 5376 Ph 2) Hornet Upgrade 1 917.5
C-17 Globemaster III Heavy Airlifter (AIR 8000 Ph 3) C-17 Heavy
Airlift 1 848.9
Air to Air Refuelling Capability (AIR 5402) Air to Air Refuel 1
828.5
Guided Missile Frigate Upgrade Implementation (SEA 1390 Ph 2.1) FFG
Upgrade 1 528.9
F/A-18 Hornet Upgrade Structural Refurbishment (AIR 5376 Ph 3.2)
Hornet Refurb 951.3
Bushmaster Protected Mobility Vehicle (LAND 116 Ph 3) Bushmaster
Vehicles 929.8
Next Generation SATCOM Capability (JP 2008 Ph 4) Next Gen Satellite
880.9
High Frequency Modernisation (JP 2043 Ph 3A) HF Modernisation
670.8
SM-1 Missile Replacement (SEA 1390 Ph 4B)* SM-2 Missile 612.0
Additional Medium Lift Helicopters (AIR 9000 Ph 5C)* Additional
Chinook 584.6
Armidale Class Patrol Boat (SEA 1444 Ph 1) Armidales 537.2
ANZAC Anti-Ship Missile Defence (SEA 1448 Ph 2B) ANZAC ASMD 2B
462.0
Collins Replacement Combat System (SEA 1439 Ph 4A) Collins RCS
450.4
Replacement Heavyweight Torpedo (SEA 1429 Ph 2) Hw Torpedo
425.4
Collins Class Submarine Reliability and Sustainability (SEA 1439 Ph
3) Collins R&S 411.4
Indian Ocean Region UHF SATCOM (JP 2008 Ph 5A)* UHF SATCOM
407.2
ANZAC Anti-Ship Missile Defence (SEA 1448 Ph 2A) ANZAC ASMD 2A
389.5
Follow On Stand Off Weapon (AIR 5418 Ph 1) Stand Off Weapon
343.3
Artillery Replacement (LAND 17 Ph 1A)* 155mm Howitzer 326.1
Battlefield Command Support (LAND 75 Ph 3.4) * Battle Comm. Sys.
325.9
Total 46 068.7
Source: 2010–11 MPR, Part 3, Project Data Summary Sheets.
Note: *Indicates the project is included in the MPR program for the
first time in the 2010–11 Report. For Bridging Air Combat
Capability (AIR 5349), only Phase 2 was reported for the first time
in 2010–11.
ANAO Overview ANAO Report No.20 2011–12 2010–2011 Major Projects
Report 16
Report objective and review scope 9.
The objective of this report is to provide:
•
a formal conclusion on the review of the Project Data Summary Sheets
(PDSSs) by the AuditorGeneral (contained in Part 3 of this report);
•
comprehensive information on the status of projects as reflected in the
PDSSs prepared by the DMO;
• ANAO analysis on the
three key elements of
the MPR: cost, schedule
and capability, in particular longitudinal analysis of projects over time;
and
•
further insights and context by the DMO on issues highlighted during
the year (not included in the scope of the review by the ANAO).
10.
The ANAO’s review of the PDSSs was conducted under an agreement
with the DMO, and was performed
in accordance with the Australian
Standard on Assurance Engagements
(ASAE) 3000.5 The agreement excluded
from the scope of the ANAO’s review PDSS data on the achievement of future
dates or events (including
forecasts on delivering key capabilities, also called
Measures of Materiel Capability Performance), and major risks and issues. By
its nature, this information relates to events and depends on circumstances that
have not yet occurred
or may not occur,
or have occurred but have not yet
been identified. Accordingly, the
conclusion of this
review does not provide
any assurance in relation to this information.6
11. While our work is appropriate
for the purpose of providing a
review report in accordance with
ASAE 3000, our review is not
as extensive as
individual project performance audits conducted by the ANAO, in terms of the
nature and scope of project issues covered, and the extent to which evidence is
required by the ANAO. Consequently, the level of assurance provided by this
review
in relation to the 28 Major Projects
is less than that typically provided
by our performance audits.
5 Australian Standard on Assurance Engagements (ASAE) 3000
Assurance Engagements other than
Audits or Reviews of Historical Financial Information, issued by
the Australian Auditing and Assurance Standards Board.
6 Further information on the scope of the review is set out in
paragraphs 1.9 and 1.10.
ANAO Overview ANAO Report No.20 2011–12
2010–2011 Major Projects Report
17
Overall conclusion 12. This fourth MPR has
progressed the development of an
annual reporting program focused on
improved transparency and accountability
for
performance relating to cost, schedule and progress towards delivering the key
capabilities of Defence Major Projects. The
report builds on the data analysis
introduced in
the 2008–09 MPR and provides a basis
for greater longitudinal
analysis of project performance in future years.
13. Overall, the program
is well placed to incorporate a
further two new
projects in the 2011–12 MPR and the removal of one project, to bring the total
number of Major Projects reported to 29.7
Review conclusion 14. Under arrangements with
the DMO, the ANAO has agreed
to review
specified PDSS data and present a formal review conclusion.
15. The conclusion of the review
of the PDSSs was that, except
for the noninclusion of project
expenditure history in Section 2.2
expressed in base date dollars8
for three of the
11 Major Projects specified in
the guidelines as
being required to report expenditure in base date dollars (as explained further
in paragraph 1.23), nothing has come to the attention of the ANAO that causes
us to believe that the information in the PDSSs, within the scope of our review,
has not been prepared, in all
material respects, in accordance with
the
guidelines on completing the PDSSs.
Projects’ performance 16. The data reviewed
in the PDSSs centre on
three major dimensions of
project performance: cost,
schedule, and the progress
towards delivering the
planned capability. 7 The JCPAA endorsed the inclusion
of the Future Naval Aviation Combat System Helicopter project
(AIR 9000 Phase 8) and Counter Rocket Artillery & Mortar
project (LAND 19 Phase 7A) and the removal of the Hornet Structural
Refurbishment project (AIR 5376 Phase 3.2), in September 2011, as
proposed by the DMO in consultation with the ANAO.
8 By converting the actual expenditure on a project to base date
dollars, an assessment is able to be made of the performance of the
project against its originally approved budget (base date dollars).
Base date dollars is the amount, adjusted for the impact of
inflation (prices) and foreign exchange movement over the period
from a specified date (usually Second Pass Approval). In order that
the initial budgeted cost of a project can be compared to the
actual expenditure over time, in like terms, the financial tables
in the PDSSs also adjust for real variations to budgeted costs,
which involve: changes in the quantities of equipment or
capability; transfers to the Defence Support Group to fund the
acquisition of facilities and transfers to other projects; and
budgetary adjustments such as the impact of efficiency
dividends.
ANAO Overview ANAO Report No.20 2011–12 2010–2011 Major Projects
Report 16
Report objective and review scope 9.
The objective of this report is to provide:
•
a formal conclusion on the review of the Project Data Summary Sheets
(PDSSs) by the AuditorGeneral (contained in Part 3 of this report);
•
comprehensive information on the status of projects as reflected in the
PDSSs prepared by the DMO;
• ANAO analysis on the
three key elements of
the MPR: cost, schedule
and capability, in particular longitudinal analysis of projects over time;
and
•
further insights and context by the DMO on issues highlighted during
the year (not included in the scope of the review by the ANAO).
10.
The ANAO’s review of the PDSSs was conducted under an agreement
with the DMO, and was performed
in accordance with the Australian
Standard on Assurance Engagements
(ASAE) 3000.5 The agreement excluded
from the scope of the ANAO’s review PDSS data on the achievement of future
dates or events (including
forecasts on delivering key capabilities, also called
Measures of Materiel Capability Performance), and major risks and issues. By
its nature, this information relates to events and depends on circumstances that
have not yet occurred
or may not occur,
or have occurred but have not yet
been identified. Accordingly, the
conclusion of this
review does not provide
any assurance in relation to this information.6
11. While our work is appropriate
for the purpose of providing a
review report in accordance with
ASAE 3000, our review is not
as extensive as
individual project performance audits conducted by the ANAO, in terms of the
nature and scope of project issues covered, and the extent to which evidence is
required by the ANAO. Consequently, the level of assurance provided by this
review
in relation to the 28 Major Projects
is less than that typically provided
by our performance audits.
5 Australian Standard on Assurance Engagements (ASAE) 3000
Assurance Engagements other than
Audits or Reviews of Historical Financial Information, issued by
the Australian Auditing and Assurance Standards Board.
6 Further information on the scope of the review is set out in
paragraphs 1.9 and 1.10.
ANAO Overview ANAO Report No.20 2011–12
2010–2011 Major Projects Report
17
Overall conclusion 12. This fourth MPR has
progressed the development of an
annual reporting program focused on
improved transparency and accountability
for
performance relating to cost, schedule and progress towards delivering the key
capabilities of Defence Major Projects. The
report builds on the data analysis
introduced in
the 2008–09 MPR and provides a basis
for greater longitudinal
analysis of project performance in future years.
13. Overall, the program
is well placed to incorporate a
further two new
projects in the 2011–12 MPR and the removal of one project, to bring the total
number of Major Projects reported to 29.7
Review conclusion 14. Under arrangements with
the DMO, the ANAO has agreed
to review
specified PDSS data and present a formal review conclusion.
15. The conclusion of the review
of the PDSSs was that, except
for the noninclusion of project
expenditure history in Section 2.2
expressed in base date dollars8
for three of the
11 Major Projects specified in
the guidelines as
being required to report expenditure in base date dollars (as explained further
in paragraph 1.23), nothing has come to the attention of the ANAO that causes
us to believe that the information in the PDSSs, within the scope of our review,
has not been prepared, in all
material respects, in accordance with
the
guidelines on completing the PDSSs.
Projects’ performance 16. The data reviewed
in the PDSSs centre on
three major dimensions of
project performance: cost,
schedule, and the progress
towards delivering the
planned capability. 7 The JCPAA endorsed the inclusion
of the Future Naval Aviation Combat System Helicopter project
(AIR 9000 Phase 8) and Counter Rocket Artillery & Mortar
project (LAND 19 Phase 7A) and the removal of the Hornet Structural
Refurbishment project (AIR 5376 Phase 3.2), in September 2011, as
proposed by the DMO in consultation with the ANAO.
8 By converting the actual expenditure on a project to base date
dollars, an assessment is able to be made of the performance of the
project against its originally approved budget (base date dollars).
Base date dollars is the amount, adjusted for the impact of
inflation (prices) and foreign exchange movement over the period
from a specified date (usually Second Pass Approval). In order that
the initial budgeted cost of a project can be compared to the
actual expenditure over time, in like terms, the financial tables
in the PDSSs also adjust for real variations to budgeted costs,
which involve: changes in the quantities of equipment or
capability; transfers to the Defence Support Group to fund the
acquisition of facilities and transfers to other projects; and
budgetary adjustments such as the impact of efficiency
dividends.
ANAO Overview ANAO Report No.20 2011–12 2010–2011 Major Projects
Report 18
Overview
17. The management of projects’ budgeted
cost has been, to a significant
degree, assisted by routine budget
supplementation to deal with both
price changes (via price
indexation) and
foreign exchange movement (via a whole
ofgovernment ‘no win/no loss’ policy9); and the coverage of certain operating
costs, such as staffing,
from outside projects’ budgeted cost.
In this context,
while projects’ budgeted cost requires careful management by
the DMO, this
dimension of project performance has not been a major issue to date.10
18.
From 1 July 2010, all projects’ approved budgets include the total price
indexation, adjusted for
the Specialist Military Equipment Weighted Average
(SMEWA)11 or other appropriate index,
to the point of the project’s
forecast Final Operational Capability
(FOC). This is defined as the
budget being ‘out turned’.12 In
2010–11, this indexation adjustment
resulted in a oneoff
variation to projects’ total approved budgets of $1.16 billion. Under this model
of price indexation, projects will
only receive further indexation for
fluctuations in the agreed index,
or by Government approved real
cost
increase, where contingency funding has been exhausted or cannot be sourced
internally by the DMO. Once the
forecast FOC has passed,
projects will be expected to
manage price increases beyond the
agreed index within their existing
budget. This will require
close management by the DMO to
avoid project budget deficits,
particularly in an environment of
regular project slippage.
19. While none of the Major
Projects in this report has
exceeded its approved budgeted cost13,
the ANAO’s analysis identified that
the DMO had received a
total of $295 million in price
indexation, between the forecast FOC
and the year ending 30
June 2011, for projects in
the MPR sample, which are
yet to achieve FOC.
9 Defence Portfolio Budget Statements 2010–11, p. 26. 10 In the
2010–11 MPR, the DMO is reporting less than one per cent negative
variation in the total
approved budgeted cost and the total current budgeted cost for the
28 Major Projects. The net variation involves budgeted cost
movements between Second Pass Approval to 30 June 2011 that are not
due to price indexation, foreign exchange, government approved
scope changes and transfers to other areas of Defence. See 2010–11
MPR, Part 2, DMO Executive Summary, Table 1, p. 106.
11 Australian National Audit Office, 2010–11 Major Projects Report,
Part 2, paragraph 2.9, p. 148. 12 Australian National Audit Office,
2010–11 Major Projects Report, Part 2, paragraph 1.79, p. 136. 13
See Table 4, p. 51.
ANAO Overview ANAO Report No.20 2011–12
2010–2011 Major Projects Report
19
20.
Maintaining Major Projects on schedule, the second major dimension of
project performance, remains the most significant challenge for the DMO and
industry contractors; in turn affecting when the capability is made available for
operational release and deployment.
The DMO data indicates that
at
30 June 2011, the total time for the 28 Major Projects to achieve their FOC date
is expected to be almost onethird longer than was originally planned.14
21. In relation to the third
major dimension of project
performance, capability,
the DMO expects
to deliver almost all capabilities associated with
the Major Projects in this
report.15 This assessment by
the DMO was outside
the scope of
the ANAO’s review as explained
in paragraph 10. Nevertheless,
the ANAO continues to engage with
the DMO on developments regarding
materiel capability measures and the revised Materiel Acquisition Agreement
(MAA) framework in order to
enhance our understanding of the
DMO’s assessment of
its own performance in
the delivery of
the materiel element of
key capabilities.
22. There are some indications that
the assessment of capability
is overly optimistic in
some cases. Analysis of the
information available indicates that
some critical capabilities have been unavailable or are expected to be delivered
below that initially approved. For
example, numerous recent issues in
the sustainment of the submarine
capability have gained significant
public and political attention, and
have limited the availability of
this capability to the
Navy. Similarly, in respect of the MRH90 Helicopters, ARH Tiger Helicopters
and Air to Air Refuel projects,
the DMO’s assessment of the
capability expected
to be delivered has declined
in 2010–11 as compared to
the original
planned key capabilities for these platforms (refer to PDSSs in Part 3).
23.
Table 2 provides aggregate DMO data on the approved budgeted cost,
schedule performance and progress
toward delivering capabilities for
the
Major Projects covered in this year’s report.
14 FOC is the point in time at which the final subset of a
capability system that can be operationally
employed is realised. FOC is a capability state endorsed by the
government at Second Pass Approval and reported as having been
reached by Defence’s capability manager (usually the Service
Chief). Major capital equipment can be in Defence service use
before formally achieving FOC, such as in the case of Bushmaster
Vehicles which are in active use by the ADF but have not achieved
FOC.
15 This is discussed further in paragraphs 37 to 39.
ANAO Overview ANAO Report No.20 2011–12 2010–2011 Major Projects
Report 18
Overview
17. The management of projects’ budgeted
cost has been, to a significant
degree, assisted by routine budget
supplementation to deal with both
price changes (via price
indexation) and
foreign exchange movement (via a whole
ofgovernment ‘no win/no loss’ policy9); and the coverage of certain operating
costs, such as staffing,
from outside projects’ budgeted cost.
In this context,
while projects’ budgeted cost requires careful management by
the DMO, this
dimension of project performance has not been a major issue to date.10
18.
From 1 July 2010, all projects’ approved budgets include the total price
indexation, adjusted for
the Specialist Military Equipment Weighted Average
(SMEWA)11 or other appropriate index,
to the point of the project’s
forecast Final Operational Capability
(FOC). This is defined as the
budget being ‘out turned’.12 In
2010–11, this indexation adjustment
resulted in a oneoff
variation to projects’ total approved budgets of $1.16 billion. Under this model
of price indexation, projects will
only receive further indexation for
fluctuations in the agreed index,
or by Government approved real
cost
increase, where contingency funding has been exhausted or cannot be sourced
internally by the DMO. Once the
forecast FOC has passed,
projects will be expected to
manage price increases beyond the
agreed index within their existing
budget. This will require
close management by the DMO to
avoid project budget deficits,
particularly in an environment of
regular project slippage.
19. While none of the Major
Projects in this report has
exceeded its approved budgeted cost13,
the ANAO’s analysis identified that
the DMO had received a
total of $295 million in price
indexation, between the forecast FOC
and the year ending 30
June 2011, for projects in
the MPR sample, which are
yet to achieve FOC.
9 Defence Portfolio Budget Statements 2010–11, p. 26. 10 In the
2010–11 MPR, the DMO is reporting less than one per cent negative
variation in the total
approved budgeted cost and the total current budgeted cost for the
28 Major Projects. The net variation involves budgeted cost
movements between Second Pass Approval to 30 June 2011 that are not
due to price indexation, foreign exchange, government approved
scope changes and transfers to other areas of Defence. See 2010–11
MPR, Part 2, DMO Executive Summary, Table 1, p. 106.
11 Australian National Audit Office, 2010–11 Major Projects Report,
Part 2, paragraph 2.9, p. 148. 12 Australian National Audit Office,
2010–11 Major Projects Report, Part 2, paragraph 1.79, p. 136. 13
See Table 4, p. 51.
ANAO Overview ANAO Report No.20 2011–12
2010–2011 Major Projects Report
19
20.
Maintaining Major Projects on schedule, the second major dimension of
project performance, remains the most significant challenge for the DMO and
industry contractors; in turn affecting when the capability is made available for
operational release and deployment.
The DMO data indicates that
at
30 June 2011, the total time for the 28 Major Projects to achieve their FOC date
is expected to be almost onethird longer than was originally planned.14
21. In relation to the third
major dimension of project
performance, capability,
the DMO expects
to deliver almost all capabilities associated with
the Major Projects in this
report.15 This assessment by
the DMO was outside
the scope of
the ANAO’s review as explained
in paragraph 10. Nevertheless,
the ANAO continues to engage with
the DMO on developments regarding
materiel capability measures and the revised Materiel Acquisition Agreement
(MAA) framework in order to
enhance our understanding of the
DMO’s assessment of
its own performance in
the delivery of
the materiel element of
key capabilities.
22. There are some indications that
the assessment of capability
is overly optimistic in
some cases. Analysis of the
information available indicates that
some critical capabilities have been unavailable or are expected to be delivered
below that initially approved. For
example, numerous recent issues in
the sustainment of the submarine
capability have gained significant
public and political attention, and
have limited the availability of
this capability to the
Navy. Similarly, in respect of the MRH90 Helicopters, ARH Tiger Helicopters
and Air to Air Refuel projects,
the DMO’s assessment of the
capability expected
to be delivered has declined
in 2010–11 as compared to
the original
planned key capabilities for these platforms (refer to PDSSs in Part 3).
23.
Table 2 provides aggregate DMO data on the approved budgeted cost,
schedule performance and progress
toward delivering capabilities for
the
Major Projects covered in this year’s report.
14 FOC is the point in time at which the final subset of a
capability system that can be operationally
employed is realised. FOC is a capability state endorsed by the
government at Second Pass Approval and reported as having been
reached by Defence’s capability manager (usually the Service
Chief). Major capital equipment can be in Defence service use
before formally achieving FOC, such as in the case of Bushmaster
Vehicles which are in active use by the ADF but have not achieved
FOC.
15 This is discussed further in paragraphs 37 to 39.
ANAO Overview ANAO Report No.20 2011–12 2010–2011 Major Projects
Report 20
Table 2 Longitudinal analysis of schedule performance
2007–08
Total Approved Budgeted Cost
Approved Budgeted Cost Increase/Decrease (In-year)1
$1.1 billion (8.5 per cent)
$4.8 billion (14.5 per cent)
-$3.3 billion (-7.5 per cent)
-$0.1 billion (-0.3 per cent)
Schedule Slippage (Total)1
increase)
increase)
increase)
increase)
39 months 25 months 34 months 30 months
Schedule Slippage (In-year)
Progress toward Delivering Key Capabilities • High level of
confidence that will be delivered (Green)
80 per cent
86 per cent
89 per cent
94 per cent
• Under threat but still considered manageable (Amber)
13 per cent 13 per cent 10 per cent 5 per cent
• At this stage unlikely to be met (Red)
7 per cent 1 per cent 1 per cent 1 per cent
Sources: 2007–08, 2008–09, 2009–10 and 2010–11 MPRs, Parts 2 and
3.
Note 1: As the data for the 28 Major Projects in the 2010–11 MPR
compares results with subsets of projects in the 2009–10 MPR (22 of
the current 28 Major Projects), the 2008–09 MPR (15 of the current
28 Major Projects) and the 2007–08 MPR (nine of the current 28
Major Projects), a comparison of the data across years should be
interpreted in this context.
Note 2: Based on the same 15 projects from the 2008–09 MPR.
Note 3: Based on the same 22 projects from the 2009–10 MPR.
Note 4: The grey section of the table covers data that is not
within the scope of the ANAO’s assurance review. It should also be
noted that the measures used to record progress towards delivering
the key capabilities in the grey section of the table can change
from year to year. Any comparison of the data across years should
therefore be treated with caution.
ANAO Overview ANAO Report No.20 2011–12
2010–2011 Major Projects Report
21
Cost
24. The total budgeted costs for
the Major Projects included in
this year’s MPR have
increased by $7.8 billion
(20 per cent) since
these projects received
Second Pass Approval. The
$7.8 billion is comprised
of price (materials and labour)
variation increases of $7.6 billion16,
real variation (such as scope
changes and budget
transfers between projects) increases of
$3.7 billion, and
foreign exchange rate movement decreases of $3.5 billion.17 Three projects have
had a real budgeted cost increase since Second Pass Approval of greater than
$500 million, namely the MRH90
Helicopters, the Hornet Refurb and
Bushmaster Vehicles (additional quantities/upgrades).
25. Compared to 2009–10, the
strengthening Australian dollar had
less
impact on project budgeted costs in 2010–11. In 2009–10, the budgeted cost of
the 22 projects decreased by
$3.8 billion (11 per cent) as
a result of foreign
exchange movements. In 2010–11, the reduction of the total budgeted cost for
the 28 projects as a result
of foreign exchange movements was
$1.1 billion (three per cent),
although this was offset by a
$1.1 billion increase in the
budgeted cost due to price
indexation. In general, this again
highlights the
yeartoyear volatility that can arise with projects exposed to foreign currency
movements.18
26. In terms&