92
JULY 2010 WELD RANGE IRON ORE PROJECT CONCEPTUAL CLOSURE PLAN

20100719 Weld Range CCP WE Edit PDF KCQA 2 Conceptual Closure Plan 2010.pdf · Weld Range Iron Ore Project Conceptual Closure Plan July 2010 ii Document Status Approved for Issue

  • Upload
    others

  • View
    0

  • Download
    0

Embed Size (px)

Citation preview

Page 1: 20100719 Weld Range CCP WE Edit PDF KCQA 2 Conceptual Closure Plan 2010.pdf · Weld Range Iron Ore Project Conceptual Closure Plan July 2010 ii Document Status Approved for Issue

 

 

 

 

 

      

 

JULY 2010

   

WELD RANGE IRON ORE PROJECT

CONCEPTUAL CLOSURE PLAN

 

Page 2: 20100719 Weld Range CCP WE Edit PDF KCQA 2 Conceptual Closure Plan 2010.pdf · Weld Range Iron Ore Project Conceptual Closure Plan July 2010 ii Document Status Approved for Issue

 

Weld Range Iron Ore Project 

Conceptual Closure Plan 

 

July 2010    

 

This page has been left blank intentionally. 

Page 3: 20100719 Weld Range CCP WE Edit PDF KCQA 2 Conceptual Closure Plan 2010.pdf · Weld Range Iron Ore Project Conceptual Closure Plan July 2010 ii Document Status Approved for Issue

 

Weld Range Iron Ore Project 

Conceptual Closure Plan 

 

July 2010    

 

ii 

 

 

 

 

 

 

Document Status 

Approved for Issue Rev.  Author Reviewer/s Date

Name Distributed To Date

1  T. Souster  W. Ennor  March 2009       

2  T. Souster  W. Ennor  Dec 2009       

3  R Gabbitus  M Wood  May 2010       

4  R Gabbitus  M Wood  July 2010       

             

 

ecologia  Environment  (2010).    Reproduction  of  this  report  in  whole  or  in  part  by  electronic, mechanical or chemical means including photocopying, recording or by any information storage and retrieval  system,  in  any  language,  is  strictly  prohibited without  the  express  approval  of  Sinosteel Midwest Corporation Pty Ltd and/or ecologia Environment. 

Restrictions on Use 

This  report has been prepared  specifically  for Sinosteel Midwest Corporation Pty Ltd.   Neither  the report nor  its  contents may be  referred  to or quoted  in any  statement,  study,  report, application, prospectus, loan, or other agreement document, without the express approval of Sinosteel Midwest Corporation Pty Ltd and/or ecologia Environment. 

 

ecologia Environment 

1025 Wellington Street 

WEST PERTH WA 6005 

Phone:  08 9322 1944 

Fax:  08 9322 1599 

Email:  [email protected] 

 

 

Page 4: 20100719 Weld Range CCP WE Edit PDF KCQA 2 Conceptual Closure Plan 2010.pdf · Weld Range Iron Ore Project Conceptual Closure Plan July 2010 ii Document Status Approved for Issue

 

Weld Range Iron Ore Project 

Conceptual Closure Plan 

 

July 2010    

 

iii 

This page has been left blank intentionally 

Page 5: 20100719 Weld Range CCP WE Edit PDF KCQA 2 Conceptual Closure Plan 2010.pdf · Weld Range Iron Ore Project Conceptual Closure Plan July 2010 ii Document Status Approved for Issue

 

Weld Range Iron Ore Project 

Conceptual Closure Plan 

 

July 2010    

 

iv 

TABLE OF CONTENTS 

CHECKLIST .....................................................................................................................................VII 1 INTRODUCTION ................................................................................................................ 1 1.1 PURPOSE ...................................................................................................................................1 1.2 PROJECT DESCRIPTION..............................................................................................................1 1.3 TENEMENT INFORMATION .......................................................................................................7 1.4 CONTACT INFORMATION..........................................................................................................9 2 CLOSURE OBJECTIVES...................................................................................................... 11 2.1 END LAND USE ........................................................................................................................12 3 BASELINE ENVIRONMENTAL DATA.................................................................................. 13 3.1 CLIMATE ..................................................................................................................................13 3.2 CLIMATE AND METEOROLOGY................................................................................................14 3.3 GEOMORPHOLOGY .................................................................................................................15 3.4 LAND SYSTEMS AND SOILS......................................................................................................15 3.5 GEOLOGY.................................................................................................................................16 3.6 GROUNDWATER......................................................................................................................17 3.7 BIOLOGICAL.............................................................................................................................19 4 LEGAL OBLIGATIONS ....................................................................................................... 21 4.1 GUIDELINES AND CODES OF PRACTICE ...................................................................................22 5 POLICY............................................................................................................................ 25 6 STAKEHOLDER CONSULTATION....................................................................................... 27 7 PLANNING ...................................................................................................................... 29 7.1 RISK ASSESSMENT ...................................................................................................................29 7.2 PROJECT CONDITION REPORTS...............................................................................................30 7.3 COMPLETION CRITERIA AND PERFORMANCE INDICATORS....................................................30 7.4 TARGETED RESEARCH .............................................................................................................34 8 FINANCIAL PROVISION.................................................................................................... 35 8.1 COST ESTIMATE.......................................................................................................................35 8.2 CLOSURE SCHEDULE................................................................................................................37 8.3 ACCOUNTING STANDARDS .....................................................................................................37 8.4 ADEQUATE SECURITIES ...........................................................................................................37 8.5 REVIEW....................................................................................................................................39 9 GENERAL REHABILITATION AND CLOSURE STRATEGIES ................................................... 41 9.1 WASTE LANDFORM.................................................................................................................41

Page 6: 20100719 Weld Range CCP WE Edit PDF KCQA 2 Conceptual Closure Plan 2010.pdf · Weld Range Iron Ore Project Conceptual Closure Plan July 2010 ii Document Status Approved for Issue

 

Weld Range Iron Ore Project 

Conceptual Closure Plan 

 

July 2010    

 

9.2 CONTAMINATED SITES............................................................................................................43 9.3 SURFACE WATER.....................................................................................................................45 9.4 GROUNDWATER......................................................................................................................49 9.5 DECOMMISSIONING................................................................................................................50 9.6 VISUAL AMENITY AND HERITAGE ...........................................................................................52 9.7 REHABILITATION OF NATIVE VEGETATION AND TOPSOIL ......................................................53 10 SPECIFIC CLOSURE STRATEGIES ....................................................................................... 57 10.1 BEEBYN AND MADOONGA PIT CLOSURE ................................................................................57 10.2 WASTE ROCK DUMPS..............................................................................................................60 10.3 OVERBURDEN STOCKPILES......................................................................................................63 10.4 BORROW PITS AND HAUL ROADS ...........................................................................................66 10.5 DEWATERING BOREFIELDS AND PIPELINES ............................................................................67 10.6 POWER GENERATING AND SUPPLY INFRASTRUCTURE...........................................................67 10.7 ACCOMMODATION VILLAGE AND AMENITIES........................................................................68 11 MONITORING AND MAINTENANCE................................................................................. 69 11.1 MONITORING, REPORTING AND RECORD KEEPING................................................................69 11.2 MAINTENANCE........................................................................................................................70 12 CONTINGENCY PLANNING............................................................................................... 71 12.1 WALKAWAY.............................................................................................................................71 12.2 TEMPORARY CLOSURE ............................................................................................................73 12.3 RELINQUISHMENT...................................................................................................................73 13 REVIEW AND REVISION................................................................................................... 75 14 REFERENCES.................................................................................................................... 77

 

Page 7: 20100719 Weld Range CCP WE Edit PDF KCQA 2 Conceptual Closure Plan 2010.pdf · Weld Range Iron Ore Project Conceptual Closure Plan July 2010 ii Document Status Approved for Issue

 

Weld Range Iron Ore Project 

Conceptual Closure Plan 

 

July 2010    

 

vi 

TABLES 

Table 1.1 – Key Aspects of the Weld Range Iron Ore Project ..................................................................3 Table 1.2– Weld Range Tenements held by or applied for by SMC .........................................................8 Table 1.3 – Prospecting Licenses Applied for in Substitution for TR 70/3902H.......................................9 Table 4.1 – Legislation Applicaple to the Project. ..................................................................................21 Table 4.2 – Guidelines and Codes of Practice. .......................................................................................22 Table 6.1 – Stakeholder Consultation. ...................................................................................................27 Table 7.1 – Closure Criteria ....................................................................................................................32 Table 8.1 – Closure Cost Estimate ..........................................................................................................36 Table 8.2 Mine Closure Schedule ...........................................................................................................37 Table 8.3 – Unconditional Performance Bonds for SMC Tenements .....................................................38 Table 10.1 – Monitoring for sailinty, pH and leaching of contaminates for pit lakes ............................58 Table 11.1 – Timing of Closure Monitoring ............................................................................................69

FIGURES 

Figure 1.1 – Project location and infrastructure layout. ..........................................................................5

Figure  3.1  – Western Murchison  Subregions  and  SurroundsL MUR1  –  Eastern Murchison, MUR2  ‐ Western Murchison (Based on IBRA Version 6.1 Thackway and Cresswell 1995). ...........13

Figure 3.2 – Summary of Climatic Data for Meekatharra Airport (BOM, 2009).....................................14

Figure 9.1 – Madoonga Mine Pit and Waste Dump Drainage................................................................47

Figure 10.1 – Indicative Cross Section of Surfacewater Diversion Trench and Abandument Bund.......59

Figure 10.2 – Cross Section of the Proposed Waste Dump Design ........................................................62

Figure 10.3 – PAF Waste Rock Surrounded by NAF Waste Rock............................................................63

Figure 11.1 – Maintenance Actions........................................................................................................70

Figure 12.1 – Sudden Closure Strategy ..................................................................................................72

Figure 12.1 – Temporay Closure Strategy ..............................................................................................74  

 

 

Page 8: 20100719 Weld Range CCP WE Edit PDF KCQA 2 Conceptual Closure Plan 2010.pdf · Weld Range Iron Ore Project Conceptual Closure Plan July 2010 ii Document Status Approved for Issue

 

Weld Range Iron Ore Project 

Conceptual Closure Plan 

 

July 2010    

 

vii 

This page has been left blank intentionally 

Page 9: 20100719 Weld Range CCP WE Edit PDF KCQA 2 Conceptual Closure Plan 2010.pdf · Weld Range Iron Ore Project Conceptual Closure Plan July 2010 ii Document Status Approved for Issue

 

Weld Range Iron Ore Project 

Conceptual Closure Plan 

 

July 2010    

 

viii 

CHECKLIST 

Required Information Y/N NA

Page No Comments

1 Has the closure plan been endorsed with the mine manager signature and company seal and an endorsement certificate attached? 

Y  xi  

2 Has a closure plan checklist been completed, signed, dated and attached to the closure plan? 

Y  Viii to x  

3 Has an introduction been added, containing a brief summary of the operation? 

Y xii to xiii 

 

Mine Information

4 Have all relevant personnel and their up to date contact information been listed in the mine information section? 

Y  9  

5 Has the location of the mine site been described on a regional and local scale? 

Y  1  

6  Has appropriately scaled regional and local maps been attached?  Y  5   

7 Has an appropriately scaled map showing all tenement boundaries and the associated mine infrastructure and disturbed areas been attached? 

Y  5  

8 Are aerial maps attached to show terrain and landscape in relation to tenement boundaries and mine disturbance? 

Y  5  

9 Has information on any historic disturbance and/or environmental liabilities been included? 

NA  NA  

Updated Information

10 If this is an annual closure plan update, is there an updated information section included? 

Y  ii  

Conditions Compliance

11 Have all environmental conditions relating to closure objectives been listed? 

NA    

12 Has a description of required works been included alongside each condition listed? 

NA    

Environmental & Rehabilitation Commitments

13 Has a list of all environmental & rehabilitation mining approval commitments been included? 

Y 41 to 57 

 

14 Has the environmental & rehab mining approval commitments been referenced with the relevant approval document? 

Y 41 to 57 

 

15 Have all disturbance types (domains) been given their own headings within the closure plan? 

Y 41 to 57 

 

Page 10: 20100719 Weld Range CCP WE Edit PDF KCQA 2 Conceptual Closure Plan 2010.pdf · Weld Range Iron Ore Project Conceptual Closure Plan July 2010 ii Document Status Approved for Issue

 

Weld Range Iron Ore Project 

Conceptual Closure Plan 

 

July 2010    

 

ix 

16 Have multiple waste landforms (WD & TSF) been identified separately within the closure plan? 

N   

 

Closure Criteria & Standards

17 Has closure objectives, criteria, standards and commitments been discussed under each disturbance type (Domain)? 

Y 30 and 32 to 33 

 

Monitoring & Research Trials

20  Has information on monitoring & research programs been included?   Y 34 and 69 

 

Decommissioning Plan

21 If this is a final closure plan, has a detailed decommissioning plan been attached? 

N    

Stakeholders

22  Has a list of all identified stakeholders been included?  Y  27   

23  Have all stakeholder contact details been included?  NA     

24  Have all stakeholder interests in the closure process been discussed?   Y  27   

Risk Analysis

25  Has the operations risk analysis process been explained?  Y 29 to 30 

 

26 Has a list of all identified risks to closure objectives been added, in order of highest risk to lowest risk? 

NA    

27  Has risk mitigation plans/processes been detailed?  NA     

28 Has all risk mitigation options been detailed including rationale for implementing selected plans/processes 

NA    

Rehabilitation Resources

29 Has the quantity, quality and storage requirements for closure rehab resources been discussed? 

Y  53  

30 Have contingency plans been explained for potential deficiencies in the quantity and quality of rehab resources at closure? 

NA   

 

Waste Characterisation

31 Has a waste characterisation program been carried out across the operation? 

41 to 43 and 60 to 63 

 

32 Has all potentially hazardous materials to rehabilitation been identified? 

41 to 43 and 60 to 63 

 

Page 11: 20100719 Weld Range CCP WE Edit PDF KCQA 2 Conceptual Closure Plan 2010.pdf · Weld Range Iron Ore Project Conceptual Closure Plan July 2010 ii Document Status Approved for Issue

 

Weld Range Iron Ore Project 

Conceptual Closure Plan 

 

July 2010    

 

33 Have risk mitigation plans/processes been detailed for each hazardous material identified. 

NA     

Education Program

34  Has the operations mine closure education program been included?  NA    

Financial Provisioning

35 Has a calculations table been included to show projected costs of closure? 

Y  36  

36 Has a separate calculations table been included to show projected cost of closure within 12 months? 

Y  37   

Unexpected Closure

37 Has the operations commitments to rehabilitation upon unexpected closure been included? 

Y 71 and 72 

 

38 Has a contingency plan for environmental commitments upon unexpected closure been included? 

Y  72  

Post- Mining Land Use

39 Has the proposed post‐mining land use for the operation been discussed? 

Y  12  

40 Has approval for any proposed change to rehab commitments been included? 

NA    

Heritage

41 Has any heritage issue that may affect the closure objectives been identified? 

Y  52  

42 Has risk mitigation plans/processes for potential heritage issues been included? 

Y  53  

Care & Maintenance (temporary closure)

43 Has the operations commitments to rehabilitation in the case of temporary closure (care & maintenance) been included? 

Y 71 and 73 to 74 

 

44 Has the closure plan been addressed to the relevant Environmental Inspector and DMP office? 

NA    

Submissions

45 Have the correct amount of hard copies been included in the submission? 

NA    

 

Page 12: 20100719 Weld Range CCP WE Edit PDF KCQA 2 Conceptual Closure Plan 2010.pdf · Weld Range Iron Ore Project Conceptual Closure Plan July 2010 ii Document Status Approved for Issue

 

Weld Range Iron Ore Project 

Conceptual Closure Plan 

 

July 2010    

 

xi 

I hereby certify that to the above checklist accurately reflects the  information contained within this mine closure plan. 

Name:     

Position: 

Company: 

 

Signed:            Date: 

ENDORSEMENT CERTIFICATE 

I hereby  certify  that all  closure objectives,  standards and  commitments made  in  this mine closure plan will be  completed within  the  timeframes, and  to  the  standards  stated.    I also  certify  that all information contained within this mine closure plan is correct and accurate at time of submission. 

 

Name:     

Position:   

Company:   

Sign:              Date: 

 

Company Seal: 

 

 

 

Page 13: 20100719 Weld Range CCP WE Edit PDF KCQA 2 Conceptual Closure Plan 2010.pdf · Weld Range Iron Ore Project Conceptual Closure Plan July 2010 ii Document Status Approved for Issue

 

Weld Range Iron Ore Project 

Conceptual Closure Plan 

 

July 2010    

 

xii 

EXECUTIVE SUMMARY 

Sinosteel  Midwest  Corporation  Ltd  (SMC)  is  an  incorporated  entity,  set  up  to  conduct  mineral exploration, engineering, environmental and economic  studies  into  the  feasibility  to mine at Weld Range.   Weld Range  is  located  85  km  southwest of Meekatharra  and 60  km northwest of Cue  in Western Australia. 

The Weld Range  Iron Ore Project  (the Project)  is a direct shipping  iron ore project with high grade outcrops over a 60 km strike length.  Two ore bodies (Beebyn and Madoonga) have been identified at Weld Range, both of which are narrow and  long with  strike  lengths  in  the order of 3  km.  SMC  is targeting  to  export  15 million  tonnes  per  annum  of  iron  ore  over  a  15  year  period.  The  Public Environmental Review (PER) document addresses the first 11 years of planned operations. 

This  Conceptual  Closure  Plan  has  been  developed  to  provide  more  certainty  to  the  long  term elements of the mine planning cycle and to provide greater flexibility around the shorter term mine planning.   This Conceptual Closure Plan forms part of the documentation that will be submitted for environmental approval with the Weld Range Iron Ore Project PER (Assessment number 1714). 

Site closure, both at the end of the mine life or running concurrently with mining activities, is a critical component of mine management, and ensures there are no ongoing adverse environmental impacts. By developing a closure plan as part of the planning stages of the Project, SMC is demonstrating that areas  impacted by  the Project will be  left  in a condition acceptable to regulators, post‐mining  land users and the community. 

Planning for mine closure seeks to address the social, environmental, financial and safety aspects of mine closure.   The aim  is to prevent or minimise  long‐term environmental  impacts and to create a self‐sustaining  natural  ecosystem  or  alternate  land  use  based  on  an  agreed  set  of  objectives (ANZMEC, 2000).    In undertaking mine closure activities at areas  impacted by the Project, SMC will fulfil the following objectives: 

• Ensure,  as  far  as  practicable,  that  rehabilitation  achieves  a  long  term,  safe,  stable  and functioning  landform  which  is  consistent  with  the  surrounding  landscape  and  pre‐existing environmental values. 

• Conduct  effective  consultation  to  enable  stakeholders,  including  regulatory  agencies,  non‐government  organisations  and  other  interested  parties,  to  have  their  interests  considered during the mine closure process. 

• Ensure that commitments made to stakeholders and regulators are fulfilled. 

• Ensure that public safety is protected.  

• Minimise negative impacts to the surrounding environment. 

• Ensure legislative requirements are met. 

• Re‐establish  landforms and vegetation communities to meet the agreed post‐mining  land use requirements. 

• Achieve  closure  completion  criteria,  as  confirmed  by monitoring,  to  allow  for  effective  and complete relinquishment of tenements.  

• Fulfil all commitments in this Conceptual Closure Plan. 

• Release SMC from further liability. 

Page 14: 20100719 Weld Range CCP WE Edit PDF KCQA 2 Conceptual Closure Plan 2010.pdf · Weld Range Iron Ore Project Conceptual Closure Plan July 2010 ii Document Status Approved for Issue

 

Weld Range Iron Ore Project 

Conceptual Closure Plan 

 

July 2010    

 

xiii 

As  this  Project  is  currently  in  the  approvals  phase,  a  Final  Closure  Plan  is  not  feasible.    This Conceptual  Closure  Plan  proposes  closure  principles  that  will  guide  the  management  of  mine landforms, water resources, revegetation, infrastructure and support facilities. 

The Conceptual Closure Plan will be regularly updated throughout the anticipated initial 11 year mine life  in  order  to  consider  the  needs  of  stakeholders  and  address  environmental  impacts.    A  Final Closure Plan will be drafted at least two years prior to mine closure. 

 

Page 15: 20100719 Weld Range CCP WE Edit PDF KCQA 2 Conceptual Closure Plan 2010.pdf · Weld Range Iron Ore Project Conceptual Closure Plan July 2010 ii Document Status Approved for Issue

 

Weld Range Iron Ore Project 

Conceptual Closure Plan 

 

July 2010    

     

1 INTRODUCTION 

1.1 PURPOSE  

SMC  is  an  emerging  iron  ore  producer  in  the Midwest  Region  of Western  Australia.    SMC  is  an incorporated  entity  established  to  conduct  mineral  exploration,  engineering,  environmental  and economic studies into the feasibility to mine at Weld Range and, upon successful completion of these studies, implementation of the Project. 

The Project is a direct shipping iron ore project with high grade outcrops over a 60 km strike length.  Two  ore  bodies  (Beebyn  and Madoonga)  have  been  identified  at Weld Range,  both  of which  are narrow and long with strike lengths in the order of 3 km. SMC is targeting to export 15 million tonnes per  annum  of  iron  ore  over  a  15  year  period.  The  Public  Environmental  Review  (PER)  document addresses the first 11 years of planned operations. 

This  Conceptual  Closure  Plan  outlines  closure  issues  related  to  the  infrastructure  and  activities incorporated with the mining, processing, and disposal of waste ore for the Project.  

This document has been prepared to meet commitments made  in the Weld Range Iron Ore Project Public Environmental Review, as follows:   

Commitment 20: 

A Conceptual Mine Closure Plan has been developed in alignment with AMEC Mine Closure Guidelines (2000) and ANZMECC Strategic Framework for Mine Closure (2000).  During the life of mine, the plan will be reviewed and updated as required to ensure information remain current. 

Commitment 21: 

Twenty‐four months prior to mine closure, a Mine Closure Plan will be finalised  in consultation with the DEC and DoIR.  The plan will define appropriate closure criteria necessary for the establishment of safe landforms and self sustaining ecosystems, and set out procedures for monitoring in order to meet compliance with the closure criteria. 

1.2 PROJECT DESCRIPTION 

SMC proposes to develop the Project to initially mine and process approximately 15 million tonnes of direct shipping ore (DSO) per annum over 11 years.  Mining will occur at two main deposits, namely Beebyn and Madoonga.  The primary crushed ore from the pits will be transported via road train to the Central Processing Facility, located approximately midway between the pits and comprising road train  unloading/tipping,  screening,  secondary  crushing,  stockyards  and  train  load‐out.   Other  key items of infrastructure include an accommodation village, airport and interconnecting roads. 

The  extent  of  the  land  disturbance,  including  land  cleared  for  associated  infrastructure,  will  be approximately 4074 ha.  Construction of the Project is expected to commence in 2012. 

Fresh water produced  from pit dewatering activities at Beebyn will be utilised  in mine processing activities and saline water will be discharged via a pipeline to an evaporation pond in close proximity to the Madoonga Pit. 

Page 16: 20100719 Weld Range CCP WE Edit PDF KCQA 2 Conceptual Closure Plan 2010.pdf · Weld Range Iron Ore Project Conceptual Closure Plan July 2010 ii Document Status Approved for Issue

 

Weld Range Iron Ore Project 

Conceptual Closure Plan 

 

July 2010    

     

The Project includes: 

• two open pits; 

• a central processing plant; (crushing and screening); 

• ROM pads; 

• dewatering infrastructure; 

• evaporation pond; 

• waste rock dumps; 

• a tailings storage facility and washing plant; 

• administration buildings; 

• laboratory; 

• workshops; 

• airstrip and associated infrastructure; 

• access roads, haul roads and tracks; 

• storm water drainage; 

• oily water treatment; 

• RO plant; 

• 18 dewatering bores; 

• two power stations and a number of generators; 

• Madoonga and Beebyn pit offices; 

• hydrocarbon bulk storage facility; 

• explosive storage facility; 

• sewage plant; and 

• an accommodation village.  

Table 1.1 below highlights  the key aspects of  the Project.   Figure 1.1  shows  the  site plan and  the regional context of the Project.  

 

Page 17: 20100719 Weld Range CCP WE Edit PDF KCQA 2 Conceptual Closure Plan 2010.pdf · Weld Range Iron Ore Project Conceptual Closure Plan July 2010 ii Document Status Approved for Issue

 

Weld Range Iron Ore Project 

Conceptual Closure Plan 

 

July 2010    

     

Table 1.1 – Key Aspects of the Weld Range Iron Ore Project 

Key Aspect  Description 

Mining operations   

Proposed operation commencement  2013 

Project life span (this proposal)  11 years 

Anticipated year of decommissioning for Beebyn and Madoonga 

2024 

Proposed mine locations   Beebyn and Madoonga 

Size of ore body  218.8 million tonnes (Mt) (dry, Beebyn and Madoonga) 

Ore type  Haematite / Goethite 

Ore mining rate   15 Mtpa 

Overburden mining rate  85 Mtpa (subject to final pit design) (wet) 

Total product  137 Mt (Beebyn and Madoonga) 

Stripping ratio (overburden: ore)  5.3:1 

Total waste  723 Mt  

Beebyn and Madoonga mining areas   

Clearing for pits and overburden stockpiles  1811.5 ha  

Madoonga pit details   

Mining floor RL  ~300 mRL 

Water table RL  ~480 mRL 

Overburden stockpiles Overburden will be placed on the northern slopes of the range to minimise potential impacts to flora and fauna.  

Beebyn pit details   

Mining floor RL  ~300 mRL 

Water table RL  ~480 mRL 

Overburden stockpiles Overburden will be placed to minimise potential impacts to flora and fauna.  

Processing equipment   

Crushing, screening, stockpiling and rail car loading. 

The ore will be crushed, screened and stockpiled as lump and fines iron ore prior to being re‐claimed and loaded onto railway wagons by an automatic rail car loader.   

 

 

Page 18: 20100719 Weld Range CCP WE Edit PDF KCQA 2 Conceptual Closure Plan 2010.pdf · Weld Range Iron Ore Project Conceptual Closure Plan July 2010 ii Document Status Approved for Issue

 

Weld Range Iron Ore Project 

Conceptual Closure Plan 

 

July 2010    

     

Key Aspects  Description 

Processing requirements   

Beneficiation (Future) 

Lower grade fines ore will be stockpiled for future processing in a beneficiation plant to wash away the minus 63 micron material and any alumina above the marketable threshold for fines.  

A tailings dam for rejected fines will be constructed.   

The total area required for the tailings dam is estimated to be 46.5 ha.  

Indicative dimensions:    280 m x 280 m x 5 m 

Volume of tailings to dam     210,000 m3/a 

Total solids deposited:    162,000 t/a 

Assumed settled density:    2.0 – 2.5 t/m3 

Volume of settled slimes:    64,800 – 81,000 m3/a 

Dam capacity:      392,000 m3 

Life:        11 years 

Mine site infrastructure   

Power source 

On site diesel generator plant 

The CPF will be powered by stand alone power station powered by 12 x 1 MW diesel generators. 

Beebyn will be supplied by a 3 MW power station (installed capacity). 

Madoonga will be supplied by a 3 MW power station (installed capacity). 

The accommodation village will be supplied by a 2 MW power station (installed capacity).  

The airstrip will be supplied with a 50 kW power station (installed capacity). 

Water source  From mine dewatering at Beebyn 

Evaporation pond 

3,000 m L x 1,100 m W x 1.3 m D; 

area approximately 3.3 km2 and  

0.3 m freeboard included. 

Infiltration and evaporation 

Anticipated annual water requirement 

3.19 GLpa to 4.96 GLpa 

Ancillary infrastructure 

ROM pad (at Madoonga and Beebyn) for delivering ore from the mine 

Mineral processing plant 

Stacker and re‐claim equipment 

Train load out facility 

Administration and central facilities 

Powerhouse 

Magazines 

Turkey nest dam 

Airstrip and Accommodation village 

Access roads 

Borefield 

Provision for future tailings dam (46.5 ha) 

Estimated clearing area for infrastructure ancillary infrastructure 

2188 ha 

Total estimated clearing   4074 ha (40.7 km2) 

Page 19: 20100719 Weld Range CCP WE Edit PDF KCQA 2 Conceptual Closure Plan 2010.pdf · Weld Range Iron Ore Project Conceptual Closure Plan July 2010 ii Document Status Approved for Issue

Proposed Beebyn Pit

E51/907

E20/492

E20/625

E20/635

M20/403

M20/402

M20/311E20/625

E20/625

E20/641

E20/457

E20/625

E20/641

P51/2611

P20/2082

P51/2613P51/2612

P51/2610P51/2609

P51/2608P51/2607P51/2606

P51/2605

P20/2083P20/2084

P20/2085P20/2086

E20/633

E20/595

P51/2552

P20/2016

P20/2077

P51/2581

P20/2080

E20/633

E51/1354

M20/419

555000

555000

560000

560000

565000

565000

570000

570000

575000

575000

580000

580000

585000

585000

590000

590000

7015

000

7015

000

7020

000

7020

000

7025

000

7025

000

7030

000

7030

000

7035

000

7035

000

Map Reference: 852_WRPProjection Details: MGA 50, GDA 94Date: 18 Nov 2009

Proposed Alternative Infrastucture: Option 2³ 0 2 41

Kilometers

1:100,000@ A3

Legend

Access Road

Accommodation Village

Airstrip

Borrow Pit Area

Central Processing Facility

Haul Road

Primary Crushing & Screening Infrastructure

Beebyn Pit

Beebyn Waste Dump

Madoonga Pit

Madoonga Waste Dump

Midwest Live Tenements

Midwest Pending Tenements

Figure 1.1: WELD RANGE PROJECT

Page 20: 20100719 Weld Range CCP WE Edit PDF KCQA 2 Conceptual Closure Plan 2010.pdf · Weld Range Iron Ore Project Conceptual Closure Plan July 2010 ii Document Status Approved for Issue

 

Weld Range Iron Ore Project 

Conceptual Closure Plan 

 

July 2010    

     

 

This page has been left intentionally blank. 

Page 21: 20100719 Weld Range CCP WE Edit PDF KCQA 2 Conceptual Closure Plan 2010.pdf · Weld Range Iron Ore Project Conceptual Closure Plan July 2010 ii Document Status Approved for Issue

 

Weld Range Iron Ore Project 

Conceptual Closure Plan 

 

July 2010    

     

1.3 TENEMENT INFORMATION 

SMC  is  the  applicant  or  registered  holder  of  all  of  the  Project  tenements,  except  for  Temporary Reserve 70/3902H (TR) which is discussed below.  The Project tenements were applied for or granted pursuant  to  the  Mining  Act  1978  (WA).    The  Project  tenements  are  detailed  in  Table  1.2  and comprise: 

• three granted and two ungranted mining leases; 

• nine granted and one ungranted exploration license; 

• twenty granted prospecting licenses; 

• one granted Temporary Reserve under a State Agreement (status further detailed below). 

The  TR  70/3902H  was  granted  pursuant  to  the  State  Agreement  scheduled  to  the  Iron  Ore (Murchison)  Agreement  Authorisation  Act  1973  (WA)  (State  Agreement).    Pursuant  to  the  State Agreement, SMC was granted rights of occupancy  in respect of the TR 70/3902H; these rights were periodically renewed by the relevant Minister until the 7th November 2008.  These rights provided for the sole and exclusive purpose of searching and prospecting  for  iron ore.   Following  the Minister’s refusal  to  extend  SMC’s  rights  of  occupancy  in  respect  of  the  TR  70/3902H,  SMC  applied  for  14 prospecting  licences  over  the  land  underlying  the  TR  70/3902H  (Replacement  Tenure).    The Prospecting License Applications were lodged on 14th November 2008, and were granted by the WA Department of Mines & Petroleum on 5th March 2009 (see Table 1.3). 

The  land  underlying  the  TR  70/3902H  is  currently  exempt  from  Divisions  1–5  of  the Mining  Act.  Accordingly, third parties cannot apply for an exploration license or any other type of tenement over the  area underlying  that  land.   As  at  the date of  this  report,  SMC  is only  entitled  to  explore  and prospect for iron ore and other minerals on the land underlying the Project tenements.  SMC will not be able to mine iron ore or any other minerals unless one or more mining leases are granted over the land underlying the Project tenements. 

Page 22: 20100719 Weld Range CCP WE Edit PDF KCQA 2 Conceptual Closure Plan 2010.pdf · Weld Range Iron Ore Project Conceptual Closure Plan July 2010 ii Document Status Approved for Issue

 

Weld Range Iron Ore Project 

Conceptual Closure Plan 

 

July 2010    

     

Table 1.2– Weld Range Tenements held by or applied for by SMC 

Tenement  Holder  Area  Date Granted 

P51/2581  SMC  24 ha  11/03/2009 

E20/595  SMC  1 block  04/05/2008 

P51/2552  SMC  50.326 ha  26/10/2007 

M20/419  Macdonald  507 ha  Ungranted 

E20/457  SMC  7 blocks  25/09/2006 

E20/459  SMC  2 blocks  25/09/2006 

E20/492  SMC  5 blocks  27/03/2007 

E51/907  SMC  33 blocks  19/09/2006 

M20/402  SMC  960 ha  27/08/1998 

M20/403  SMC  991 ha  27/08/1998 

TR70/3902  SMC  2,310 ha  06/10/1966 

E20/635  SMC  4 blocks  06/02/2007 

E20/633  SMC  2 blocks  05/03/2007 

E20/641  SMC  3 blocks  10/08/2007 

E51/1354  SMC  63 blocks  Ungranted 

E20/625  SMC  27 blocks  04/05/2008 

P20/2077  SMC  23.8 ha  15/07/2009 

P20/2078  SMC  23.8 ha  15/07/2009 

P20/2016  SMC  48 ha  05/08/2009 

P20/2080  SMC  23.5 ha  15/07/2009 

M20/503  SMC  56.8 ha  Ungranted 

M20/311  SMC  834 ha  03/04/1996 

Total  

Sinosteel Midwest  Corporation  Limited  (SMC)  is  listed  as  the  tenement  holder  (or  applicant)  in  all  but  one  of  the tenements  in this table.   SMC tenements are managed by Hetherington Exploration and Mining Titles Pty Ltd; whilst M20/419 is managed by the tenement holder Stanley Macdonald (SMC is the beneficial owner of this tenement). 

Page 23: 20100719 Weld Range CCP WE Edit PDF KCQA 2 Conceptual Closure Plan 2010.pdf · Weld Range Iron Ore Project Conceptual Closure Plan July 2010 ii Document Status Approved for Issue

 

Weld Range Iron Ore Project 

Conceptual Closure Plan 

 

July 2010    

     

Table 1.3 – Prospecting Licenses Applied for in Substitution for TR 70/3902H 

Tenement  Holder  Area 

P51/2605  SMC  198.143 ha 

P51/2606  SMC  198.148 ha 

P51/2607  SMC  198.154 ha 

P51/2608  SMC  198.160 ha 

P51/2609  SMC  198.166 ha 

P51/2610  SMC  198.171 ha 

P51/2611  SMC  198.177 ha 

P51/2612  SMC  198.183 ha 

P51/2613  SMC  198.185 ha 

P20/2082  SMC  195.214 ha 

P20/2083  SMC  198.128 ha 

P20/2084  SMC  198.041 ha 

P20/2085  SMC  197.954 ha 

P20/2086  SMC  197.868 ha 

1.4 CONTACT INFORMATION 

The  following SMC personnel can be contacted  regarding any queries with  this Conceptual Closure Plan: 

Head Office 

Mr Wayne Ennor (Manager Project Approvals) 

Sinosteel Midwest Corporation  

PO Box 529 

WEST PERTH WA 6872 

Ph: (08) 9429 4888   

Email: [email protected]  

 

 

Page 24: 20100719 Weld Range CCP WE Edit PDF KCQA 2 Conceptual Closure Plan 2010.pdf · Weld Range Iron Ore Project Conceptual Closure Plan July 2010 ii Document Status Approved for Issue

 

Weld Range Iron Ore Project 

Conceptual Closure Plan 

 

July 2010    

     

10 

This page has been left blank intentionally 

Page 25: 20100719 Weld Range CCP WE Edit PDF KCQA 2 Conceptual Closure Plan 2010.pdf · Weld Range Iron Ore Project Conceptual Closure Plan July 2010 ii Document Status Approved for Issue

 

Weld Range Iron Ore Project 

Conceptual Closure Plan 

 

July 2010    

     

11 

2 CLOSURE OBJECTIVES 

Planning for mine closure seeks to address the social, environmental, financial and safety aspects of mine  closure.    The  purpose  of mine  closure  is  to  prevent  or minimise  long‐term  environmental impacts and to create a self‐sustaining natural ecosystem or alternate  land use based on an agreed set  of  criteria  (derived  from  the  Australia  and  New  Zealand  Minerals  and  Energy  Council (ANZMEC/MCA Strategic Framework for Mine Closure, 2000).   

To meet  this  requirement SMC has adopted  the ANZMEC/MCA objectives  for mine  closure, which are: 

• To enable all stakeholders to have their interests considered during the mine closure process; 

• To ensure the process of closure occurs in an orderly, cost effective and timely manner; 

• To  ensure  the  cost of  closure  is  adequately  represented  in  company  accounts  and  that  the community is not left with a liability; 

• To ensure there  is clear accountability and adequate resources for the implementation of the closure plan; 

• To establish a set of indicators that will demonstrate the successful completion of the closure process; and 

• To reach a point where the company has met agreed completion criteria to the satisfaction of the responsible authorities. 

SMC  are  committed  to  fulfilling  the  above  objectives,  and  in undertaking  closure  activities  at  the Weld Range project site, SMC will fulfil the following project specific objectives: 

• Ensure,  as  far  as  practicable,  that  rehabilitation  achieves  a  long  term,  safe,  stable  and functioning  landform  which  is  consistent  with  the  surrounding  landscape  and  pre‐existing environmental values. 

• Conduct  effective  consultation  to  enable  stakeholders,  including  regulatory  agencies,  non‐government  organisations  and  other  interested  parties,  to  have  their  interests  considered during the mine closure process. 

• Ensure that commitments made to stakeholders and regulators are fulfilled. 

• Ensure that public safety is protected. 

• Minimise negative impacts to the surrounding environment. 

• Ensure legislative requirements are met. 

• Re‐establish  landforms and vegetation communities to meet the agreed post‐mining  land use requirements. 

• Achieve  closure  completion  criteria,  as  confirmed  by monitoring,  to  allow  for  effective  and complete relinquishment of tenements. 

• Fulfil all commitments in this Closure Plan. 

 

Page 26: 20100719 Weld Range CCP WE Edit PDF KCQA 2 Conceptual Closure Plan 2010.pdf · Weld Range Iron Ore Project Conceptual Closure Plan July 2010 ii Document Status Approved for Issue

 

Weld Range Iron Ore Project 

Conceptual Closure Plan 

 

July 2010    

     

12 

The Project closure objectives will be achieved by: 

• Establishing, through survey and  investigation, a baseline of the environment prior to project disturbance. 

• Allocating appropriate cost and resource provision requirements. 

• Planning mining and associated activities to best fit with closure concepts. 

• Consulting with  stakeholders  to determine post closure  land use and completion criteria  for the project areas. 

• Undertaking  environmental monitoring  to  ensure  that  rehabilitation  techniques  have  been successful in achieving post closure land‐use criteria. 

2.1 END LAND USE 

Final land use is expected to comprise of pastoralism with some restricted zones to ensure the future safety of people and wildlife.  

The  landscape  will  comprise  rehabilitated  waste  and  fines  rejects  stockpiles,  with  final  slopes ensuring  long‐term stability, a mine pit that will form pit  lakes.   Surface drainage will be reinstated where possible or diverted to reduce the likelihood of ponding after heavy rains. 

SMC will undertake further community consultation to develop and define the end land use options for its operations and also undertake environmental, social and economic assessments to ensure the selected options are sustainable.  

An overview of the conceptual options for closure and rehabilitation of the major mining features is provided in the following sections. 

 

 

Page 27: 20100719 Weld Range CCP WE Edit PDF KCQA 2 Conceptual Closure Plan 2010.pdf · Weld Range Iron Ore Project Conceptual Closure Plan July 2010 ii Document Status Approved for Issue

 

Weld Range Iron Ore Project 

Conceptual Closure Plan 

 

July 2010    

     

13 

3 BASELINE ENVIRONMENTAL DATA 

3.1 CLIMATE  

3.1.1 Bioregions and Major Physiographic Units 

The  Interim Biogeographic Regionalisation  for Australia  (IBRA) categorises  the Australian continent into  regions  of  similar  geology,  landform,  vegetation,  fauna  and  climate  (IBRA,  2000).    The Weld Range  lies  in the Murchison Biogeographic Region, Western Murchison sub region which  lies within the Eremaean botanical province or the arid zone of Western Australia, as illustrated below in Figure 3.1. 

 Figure 3.1 – Western Murchison Subregions and SurroundsL MUR1 – Eastern Murchison, MUR2 ‐ Western 

Murchison (Based on IBRA Version 6.1 Thackway and Cresswell 1995). 

The Western Murchison subregion comprises predominately Mulga (Acacia aneura) low woodlands, with an understorey often rich in ephemerals (usually with hummock grasses).  The substrate consists primarily of outcrop and  fine  textured Quaternary alluvial and eluvial  surfaces  (extensive hardpan wash plains that dominate and characterise the subregion) mantling granitic and greenstone strata.  Where  occluded  drainage  features  occur,  vegetation  is  dominated  by  saltbush  shrub  lands  on calcareous soils and Halosarcia low shrub lands on saline alluvia.  The Western Murchison subregion contains  the  headwaters  of  the  Murchison  and  Wooramel  Rivers,  which  drain  the  subregion westwards to the coast. 

Grazing  of  native  pastures  accounts  for  most  land  use,  although  unoccupied  Crown  land, conservation reserves and mining are also significant land uses (Thackway and Cresswell, 1995). 

Page 28: 20100719 Weld Range CCP WE Edit PDF KCQA 2 Conceptual Closure Plan 2010.pdf · Weld Range Iron Ore Project Conceptual Closure Plan July 2010 ii Document Status Approved for Issue

 

Weld Range Iron Ore Project 

Conceptual Closure Plan 

 

July 2010    

     

14 

3.2 CLIMATE AND METEOROLOGY 

Meteorological  data  has  been  recorded  at  the  Bureau  of Meteorology  (BOM) weather  station  at Meekatharra airport.   

Climate 

Weld  Range  is  located  in  the Midwest  region  of WA,  approximately  80  km  west  south‐west  of Meekatharra.   The region experiences hot, dry summers and mild winters.  A high pressure band or subtropical ridge dominates the weather pattern throughout the year.  During the warmer months, a low  pressure  trough  is  located  to  the  south,  resulting  in  southerly  and  south‐easterly  winds.  Occasional cold fronts bring little rain to the region whereas tropical cloud bands bring the most rains during the winter months. 

Temperature 

Mean  maximum  temperatures  range  from  38.2°C  in  January  to  19°C  in  July.    Mean  minimum temperatures range from 24.3°C in January to 7.4°C in July.  Very hot summers and mild winters are representative of the region (Figure 3.2). 

Rainfall 

The late summer and early winter months (February and June) provide the most rainfall over the year (Figure  3.2).    The  total  annual  rainfall  in  this  region  is  very  low  (less  than  250 mm  per  annum). September  is the driest month of the year, receiving on average  less than 5 mm of rainfall over the entire month.  This dry environment has the potential to result in higher particulate emissions from mining activities. 

Figure 3.2 – Summary of Climatic Data for Meekatharra Airport (BOM, 2009). 

Relative Humidity 

The morning (9 am) mean relative humidity  is consistently higher than the afternoon (3 pm) mean. On average, humidity  increases  to between 41% and 63%  in  the winter months and decreases  to between  16%  and  28%  in  the  summer months.    This  low humidity  can  increase  the potential  for higher particulate emissions from mining activities. 

 

Page 29: 20100719 Weld Range CCP WE Edit PDF KCQA 2 Conceptual Closure Plan 2010.pdf · Weld Range Iron Ore Project Conceptual Closure Plan July 2010 ii Document Status Approved for Issue

 

Weld Range Iron Ore Project 

Conceptual Closure Plan 

 

July 2010    

     

15 

Winds 

The seasonal and annual wind roses for Meekatharra indicate the following: 

• for January to March, eastern and south‐eastern winds are predominant; 

• for April to June, the main winds are from the east; 

• for July to September, the winds are primarily from the east or south; and 

• for October to December, the wind pattern is similar to July to September but the wind speed is generally higher. 

The overall wind  speed  rages between 2 m/s and 5 m/s.   The  frequency of wind  speeds between 5 m/s and 10 m/s reduces gradually to the point that very  few hours have an hourly average wind speed greater than 10 m/s. 

3.3 GEOMORPHOLOGY 

3.3.1 Topography 

The topography of the area  is dominated by the Weld Range – a  long band of steep ridges that run southwest to northeast and extend over a distance of more than 60 km.  The Project tenements are situated within these ridges.  The elevation ranges from approximately 460 m to 730 m RL.  The slope angles in the area of the Weld Range vary from less than 5 % to greater than 90 %.  Away from the ridges the topography is very flat.   

There are some clearly delineated drainage channels within the Weld Range itself, however the land to the north has only few well defined channels and is characterised by numerous mud flats and salt pans.   There  is a significant salt pan  in a depression immediately north of the Madoonga tenement.  The available topographic data indicates a minimum elevation of 482.7 mAHD in this salt pan. 

3.3.2 Banded Ironstone Formation 

The  BIF  ranges  of  the Midwest  are  of  very  significant  biodiversity  value  because  of  their  unique geology, soils and relative isolation.  The values of the ranges are related to the presence of endemic plant species, rare and restricted plant species and highly restricted and distinct plant communities and ecological communities.   The  ranges are also very distinct  features  in  their  regional  landscape and in many cases possess outstanding landscape values.  They also have fauna conservation values although  these are  less well documented  than  for  flora.   There are, however, differences between the various BIF ranges in terms of their biodiversity conservation and mineral prospectively/resource values. 

3.4 LAND SYSTEMS AND SOILS 

Curry et al. (1994) undertook a regional survey of the Murchison River catchment and surrounds to document and prepare an  inventory of  the  land  systems present and  the conditions of each.   The area surveyed (88,360 km2) was situated between Meekatharra and Mount Magnet to the east, and the catchments of the Greenough and Wooramel Rivers in the west. 

Page 30: 20100719 Weld Range CCP WE Edit PDF KCQA 2 Conceptual Closure Plan 2010.pdf · Weld Range Iron Ore Project Conceptual Closure Plan July 2010 ii Document Status Approved for Issue

 

Weld Range Iron Ore Project 

Conceptual Closure Plan 

 

July 2010    

     

16 

Most of the surrounding area within the Project lies within the Yarrameedie, Violet and Jundee land systems, with  smaller  areas  of  the  Sherwood, Mileura, Norie,  Cunyu,  Kalli, Gabanintha,  Breberle, Koonmarra, Waguin, Wiluna, Yandil and Yanganoo land systems also present.  These land systems  

The Weld land system is described as rugged ranges and ridges of mainly Archaean metamorphosed sedimentary rock supporting acacia shrublands (Curry et al. 1994).  It is 350 km2 in area and consists of two distinct and widely separated localities ‐ Weld Range and Jack Hills. 

The  Yarrameedie  system  is  largely  associated  with  the  Weld  system  in  the  Project  area.    It  is described as undulating stony interfluves, drainage floors and pediment (foothill) plains below major ranges of crystalline rocks (mainly Weld  land system) supporting sparse Mulga shrublands (Curry et al. 1994).  The two other major land systems in the project area, the Violet and Jundee land systems, both support scattered Mulga shrublands over plains.  They both occur on the plains below the Weld Range. 

The Mileura land system is unique in the Project area as it consists of seasonally inundated claypans supporting  halophytic  shrublands.    These  shrublands  form  unique  habitats  with  species  such  as Slender‐billed Thornbill and White‐winged Fairy‐wren restricted to these habitat types. 

The weathering of the Archaean and overlying Proterozoic rock has been occurring since the tertiary period, producing  the sediments  that  form  the soils of  the surrounding plains.   The soils  therefore vary from shallow, stony soils and  loams on the rocky slopes of the hills and ridges, to deeper, red earths on the lower slopes and outwashes.  These outwashes are derived from the weathering of the parent rock and include the calcareous soils from the mafic rock.  They are characteristically infertile and acidic (Markey & Dillon, 2006). 

3.5 GEOLOGY 

3.5.1 Regional Geology 

The Weld  Range  is  found  on  the  northern  extent  of  the  Yilgarn  Craton.    The  Yilgarn  Craton  is described  by  Curry  et  al.  (1994)  as  a  gently  undulating  landscape,  composed  of  Archaean  rocks, dominantly granite with north  to northwest  trending belts of greenstone  rocks.   These greenstone rocks form hill ranges which are separated widely by the very flat plains derived from colluvium and alluvium.    Soils  are mainly  shallow,  sandy  and  infertile,  and  across most  of  the  lower  areas  are distinctively underlain by red‐brown siliceous hardpan. 

The Weld Range is one of the several linear greenstone belt ridges representing the northern extent of  the  Yilgarn  Craton.    It  is  composed  dominantly  of Hematite  (red), Magnetite  (black)  and  Silica (white) BIF rock, embedded with Dolerite, Jaspilite and greenstone, a type of metamorphic rock that owes its colour to the presence of a green mineral such as chlorite.  BIF is erosion resistant and forms the rocky outcrops and steep ridges that are characteristic of the Weld Range.  The mineralization of BIF is resultant in the formation of iron ore and as a result, these ranges have developed significant deposits (Markey & Dillon, 2006). 

3.5.2 Geology of Madoonga and Beebyn 

Steeply dipping, east‐northeast‐striking BIFs are known to occur  in three ridges at Weld Range: the North, Central and South Ranges.  The BIFs are interleaved with metabasic rocks that show doleritic and  lesser basaltic and gabbroic textures.   The BIFs within the North, Central and South Ranges are referred to as the Madoonga, Lulworth and Wilgie Mia beds, respectively.  Iron mineralisation within the three ranges is not continuous and occurs as 44 distinct iron ore lenses, named W1 to W44.  Of 

Page 31: 20100719 Weld Range CCP WE Edit PDF KCQA 2 Conceptual Closure Plan 2010.pdf · Weld Range Iron Ore Project Conceptual Closure Plan July 2010 ii Document Status Approved for Issue

 

Weld Range Iron Ore Project 

Conceptual Closure Plan 

 

July 2010    

     

17 

these 44 lenses, the Madoonga (W14) and Beebyn (W7, W8, W9, W10 and W11) ore bodies form the focus of this PER. 

The Madoonga  deposit  contains  a  steeply  south‐southeast‐dipping  rock  sequence  that  comprises, from north to south, felsic sedimentary rocks, and a 60 to 250 m thick BIF and a 20 to 50 m thick zone of deeply weathered and altered rocks within which the iron mineralisation is hosted.  Sediments and sedimentary  rocks  lie  above  an  erosional  unconformity  on  the  iron  mineralisation  and  deeply weathered  rocks.    The  sedimentary  rocks  comprise  ferruginous  conglomerate  and pisolitic  gravels that have a thickness up to 20 m and locally have high Fe grades (>60% Fe). 

The Beebyn deposit  contains numerous  steeply  southeast dipping BIFs  interlayed with dolerite, of which the most economically important is approximately 40 m thick.  Least altered and unweathered BIFs contain millimetre  to centimetre  thick bands rich  in  iron, silica and Fe‐silicate and sone of the bands are carbonate  rich.   These mineralised  zones are offset by up  to 100 m by  late  sub vertical northwest striking faults (SRK, 2010). 

3.6 GROUNDWATER 

3.6.1 Regional Hydrogeology 

The  Weld  Range  area  is  located  within  the  East  Murchison  Groundwater  Management  Unit.  Groundwater occurs at  relatively  shallow depths  (typically 5 – 50 m bgl) beneath  the alluvial plain around Weld Range, and occurs within the bedrock sequence that forms Weld Range.   Recharge to the  system  occurs  from  rainfall  infiltration mainly  through  creek  beds  and  to  a  lesser  extent  on floodplains.    Some  groundwater  recharge  can  be  expected  through  the  creek  beds  between  the ridges that form Weld Range. 

Two main types of aquifers can be identified around the Weld Range: 

1. Shallow aquifers located in the superficial sediments: 

• Quaternary  sediments  that  overly  calcrete,  palaeochannels,  and  fractured  rock:  these sediments  are  not  known  to  be  major  aquifers,  and  are  only  utilised  by  wells  and boreholes for stock watering.  The groundwater is neutral to alkaline with a high salinity. 

• Tertiary  limestone and calcrete  sediments:  these  sediments have  the highest potential for  shallow water  supply.    The  groundwater  is  alkaline with pH  greater  than 8  and  is hyposaline. 

• Tertiary palaeochannels sediments:  these sediments may have the potential to contain large volumes of alkaline and saline groundwater. 

2. The  fractured  and  weathered  rock  aquifers  are  located  in  the  rocks  of  low  primary permeability.  They are currently the main source of water in the areas and the borehole yields vary  from  near  zero  to  a  possible  several  hundred  cubic  metres  per  day.    The  main groundwater  yielding  zones within  this  sequence  are  associated with  vuggy  and  cavernous zones, and larger scale structures (along fault and shear zones).  This groundwater is normally acidic to neutral, with a low salinity. 

3.6.2 Project Hydrogeology 

As part of the Prefeasibility Study  for the Project, SRK conducted a comprehensive hydrogeological investigation  in 2007  and 2008.    SRK  completed  further  fieldwork between March  and November 

Page 32: 20100719 Weld Range CCP WE Edit PDF KCQA 2 Conceptual Closure Plan 2010.pdf · Weld Range Iron Ore Project Conceptual Closure Plan July 2010 ii Document Status Approved for Issue

 

Weld Range Iron Ore Project 

Conceptual Closure Plan 

 

July 2010    

     

18 

2009  to  provide  additional  hydrological  data  to  enhance  the  regional  understanding  of  the hydrological setting around the Project.   

A borehole and well survey was performed  in a 30 – 40 km radius area around the Weld Range to collect baseline hydrogeological  information  that  included water  levels, pH  and  conductivity  (SRK, 2010).  A total of 58 boreholes and wells were included in this survey.  Parameters were measured in selected locations approximately every four months to allow a comparison of data to be made and an assessment of any changes in aquifer conditions.   

Extensive  investigations were also performed  in  the proposed pit areas of Beebyn and Madoonga.  Structural logging of 29 drill holes in Beebyn and 24 drill holes in Madoonga (totalling approximately 11,500 m) provided additional insight to rock conditions (SRK, 2010a). 

The Prefeasibility Study conducted by SRK determined areas of insufficient knowledge.  The bankable feasibility  Study  fieldwork  investigations were developed  to  address  the  identified  gaps  and were conducted  between March  2009  and November  2009  to provide  the outstanding hydrogeological data. 

Extensive  investigations  were  performed  in  the  proposed  pit  areas.    Structural  logging  of  eight geotechnical  drill  holes  in  Beebyn  and  11  in Madoonga  (totally  approximately  4,500 m)  provided additional insight to rock conditions. 

All  the  information gathered during the  field  investigation was compiled to construct a preliminary conceptual  hydrogeological  model  of  the  area.    A  total  for  seven  hydrogeological  units  were determined and the spatial distribution of these unites were defined.  Three units contain most of the groundwater generated in the Project area.  On a regional scale, the unconsolidated sediments that cover all  the  flatlands north and  south of  the  range provide water  for agricultural activities  in  the area.    A  significant  palaeochannel  was  identified  in  The  Gap  area.    This  palaeochannel  itself  is relatively impermeable.  However, a fracture zone located below the palaeochannel is believed to be highly permeable and  could  contribute considerable  inflow  into  the Madoonga pit.   The  third unit holding significant amounts of groundwater  is the BIF.   Drilling through this unit proved challenging as  large amount of water were encountered because of  the high hydraulic conductivity values and high  storage  capacity.    Pumping  tests  performed  in  his  unit  confirmed  these  observations  and geochemical  observations  confirmed  that  recharge  is  higher  in  the  BIF  aquifer  than  in  the unconsolidated sediments. 

The conceptual model was used as a basis  for constructing a numerical groundwater model, which was  then  constructed  using  FEFLOW®.    The  entire  Project  area  was modelled,  all  the  identified hydrogeological  units  were  incorporated  into  the  model  and  properties  derived  from  the hydrogeological investigations were assigned to the units (SRK 2010a). 

3.6.2.1 Hydrogeological Characterisation 

Water level and quality data (pH and Total Dissolved Solids (TDS)) were collected three times during the  Prefeasibility  Study  (PFS)  investigations.   Groundwater  samples  from  regional boreholes were taken and analysed in July/August 2007 and June 2008.  This sampling programme was developed to provide initial data for a monitoring programme for the Project. 

The regional borehole survey was repeated for the BFS in November 2009.  The data collected during the survey in October/November 2009 was used for updating a conceptual model and calibration of the groundwater model.   A total of 58 boreholes and wells were surveyed during the  investigation.  These  boreholes  were  located  in  the  catchment  surrounding Weld  Range  on  Beebyn,  Glen  and 

Page 33: 20100719 Weld Range CCP WE Edit PDF KCQA 2 Conceptual Closure Plan 2010.pdf · Weld Range Iron Ore Project Conceptual Closure Plan July 2010 ii Document Status Approved for Issue

 

Weld Range Iron Ore Project 

Conceptual Closure Plan 

 

July 2010    

     

19 

Madoonga pastoral stations.  The depth of the wells and boreholes varied from 2.36 to 23.39 m bgl.  They were all placed in the shallow aquifer. 

Regional Groundwater Levels 

The water level contour map of November 2009 indicates a movement of the groundwater from the north towards the southeast following the tertiary palaeochannels drainage direction.   The regional water elevations range between 510.15 m RL (Outcamp Well) along the northern margin to 427.15 m RL (7 Mile Well) along the southern margin of the investigated areas, the wells are 45 km apart (SRK, 2010). 

Water level contour maps in the Madoonga and Beebyn areas indicate slightly elevated groundwater levels.   The elevation of the water  level mound  in the Weld Range ranges from 482.24 to 507.78 m RL.    The  dominant  foliation  and  dolerite  intrusions  in  the Weld  Range  strike  across  the  general drainage direction of the groundwater.  Because of the low permeability of the dolerite, a mounding of the water on the northern side of the range is expected, except where a preferential pathway has been formed by cross‐cutting structural features (e.g. The Gap at Madoonga). 

Regional Groundwater Salinities 

Contouring of  the groundwater salinity data  indicates  that  the regional groundwater  is  fresh  (TDS< 500  mg/l)  to  marginal  (500<TDS<1,500  mg/l),  except  in  the  boreholes  or  wells  located  in  the palaeochannels.  The areas of higher groundwater salinity correspond to lower topographic areas and surface drainage  systems.   The higher  salinity  in  these  surficial  aquifers due  to  the  shallow water table  and  the  high  evaporation  rate  of  the  area;  the water  evaporates  as  soon  as  it  reaches  the surface or even in the vadose zone just below the surface.  This results in the deposition of numerous minerals and salts in and around the lower topography areas and subsequently increases the salinity of  the  immediate  groundwater.    When  this  occurs  the  water  quality  then  becomes  brackish (1,500<TDS<5,000 mg/l) varying from 2,643 mg/l (7 Mile Well) to 4,900 mg/l (Gap Bore) to saline with the highest salinity measured at MDWB01 (48,000 mg/l), M_WBG_01R (46,000 mg/l) and M‐LTM‐04 (35,000 mg/l).  The boreholes that have the highest salinity reflect the proximity of these boreholes to the Tertiary palaeochannel (SRK 2010a). 

3.7 BIOLOGICAL  

3.7.1 Flora 

To date, 27 priority taxa have been recorded in surveys carried out by ecologia and the DEC at Weld Range.    These  priority  flora  species  are  located  across  a  range  of  vegetation  communities  and landforms and include six Priority 1, 18 Priority 3 and three Priority 4 species.  Table 5‐3 summarises the distribution of these taxa.  

The  conservation  significance  of  two  land  systems  occurring within  the  Project  area  ‐ Weld  and Yarrameedie  –  is  rated  as  regionally  significant  as  they  are mapped  over  small  areas  of Western Australia and the Murchison. 

Three of Beard’s vegetation units ‐ Acacia aneura and Acacia quadrimarginea scrub (a 1.14 Si), Acacia aneura and Acacia grasbyi low woodland (a 1.17 Li) and Acacia aneura, Acacia ramulosa and Acacia linophylla (now Acacia ramulosa var. linophylla) low woodland (a 1.9 Li) ‐ are considered to have high regional significance due to their limited distribution in Western Australia. 

Page 34: 20100719 Weld Range CCP WE Edit PDF KCQA 2 Conceptual Closure Plan 2010.pdf · Weld Range Iron Ore Project Conceptual Closure Plan July 2010 ii Document Status Approved for Issue

 

Weld Range Iron Ore Project 

Conceptual Closure Plan 

 

July 2010    

     

20 

One of the vegetation units recorded by the DEC at Weld Range is regionally significant – Community 6 ‐ Acacia sp. Weld Range, A. aneura and A. speckii shrubland over Eremophila spp. and Heliotropium ovalifolium on dolerite. 

Three vegetation units mapped by ecologia during  the current  survey are considered  to have high local  conservation  significance.    Communities  1  and  2  and  their  associated  sub‐communities  are restricted to the BIF ridges and outcrops, which are the target of mining activities.  Community 4 (and associated sub‐communities) appears to be the only known community in which the two undescribed species of interest, Acacia sp. nov. (aff. kochii) and Hemigenia sp. nov. (aff. exilis), occur.  Community 7  (and  associated  sub‐communities)  has  a  limited  distribution  in  the  Project  area  and  is  the  only recorded habitat for the priority three species Tecticornia cymbiformis at Weld Range. 

3.7.2 Vertebrate Fauna 

Fives conservation significant fauna species have been recorded in the project area: 

• Long‐tailed Dunnart (Sminthopsis longicaudata) (DEC Priority 3); 

• Peregrine Falcon (Falco peregrinus) (WCA Schedule 4); 

• Bush Stone‐curlew (Burhinus grallarius) (DEC Priority 4); 

• Slender‐billed Thornbill (Acanthiza iredalei) (EPBC Act Vulnerable); and 

• A fossorial skink (Lerista eupoda) (DEC Priority 1). 

3.7.3 Invertebrate Fauna 

Forty  five  invertebrate  species of  interest were collected  from  the Weld Range SRE survey.   These included  eight  species  of  scorpions,  six  species  of  pseudoscorpions,  15  species  of mygalomorph spiders, one species of millipede, 10 species of centipedes, four species of isopod and one species of land snail.   The most  important species  identified as either being  likely to represent SRE species or belonging to the category of protected fauna under the Wildlife Conservation Act (1950) were: 

• the Shield‐back Spider; Idiosoma nigrum (Schedule 1 species; Mygalomorph spider);  

• Aurococrypta lugubris (Mygalomorph spider); 

• Cethegus ‘fugax complex’ (Mygalomorph spider); 

• Pleuroxia sp. (land snail); and  

• Antichiropus sp. ‘Weld Range’ (Millipede). 

Page 35: 20100719 Weld Range CCP WE Edit PDF KCQA 2 Conceptual Closure Plan 2010.pdf · Weld Range Iron Ore Project Conceptual Closure Plan July 2010 ii Document Status Approved for Issue

 

Weld Range Iron Ore Project 

Conceptual Closure Plan 

 

July 2010    

     

21 

4 LEGAL OBLIGATIONS 

Mine  closure  is  subject  to  both  federal  and  state  legislation  and  SMC  is  required  to meet  legal obligations during design, operation and closure phases of the Project. 

The Weld Range Iron Ore Project is being assessed by the Department of Mines and Petroleum (DMP) under the Mining Act 1978 and by the Environmental Protection Authority under the Environmental Protection  Act  1986  through  a  Public  Environmental  Review.    This  Conceptual  Closure  Plan  is consistent  with  the  environmental  objectives  outlined  in  the Weld  Range  Iron  Ore  Project  PER document.  

This  plan  aims  to  incorporate  requirements  under  the Mining  Act  1978  and  fulfil  the  conditions placed on SMC’s tenements. 

Additional legislation that may be applicable to mine closure is included in Table 4.1.  

Table 4.1 – Legislation Applicaple to the Project. 

Legislation  Responsible Government Agency 

Commonwealth Legislation 

Environmental Protection and Biodiversity Conservation Act 1999 

Department of Environment and Heritage 

Native Title Act 1993  National Native Title Tribunal 

Protection of Moveable Cultural Heritage Act 1986 

Protection of Moveable Cultural Heritage Act 1986 

National Greenhouse and Energy Reporting Act 2007 

Department of Climate  

Change 

State Government Legislation  

Aboriginal Heritage Act 1972  Department of Indigenous Affairs 

Agricultural and Related Resources Protection Act 1976 

Department of Agriculture, Western Australia 

Bush Fires Act 1954  Bush Fires Board 

Conservation and Land Management Act 1984  Department of Environment and Conservation  

Contaminated Sites Act 2003  Department of Environment and Conservation 

Country Areas Water Supply Act 1947  Department of Industry and Resources 

Dangerous Goods Act 1961  Department of Industry and Resources 

Dangerous Goods Regulations 1992  Department of Consumer and Employment Protection 

Environmental Protection Act 1986  Department of Environment and Conservation 

Explosives and Dangerous Goods Act 1961  Department of Industry and Resources 

Explosives and Dangerous Goods (Dangerous Goods Handling and Storage) Regulations 1992 

Department of Industry and Resources 

Health Act 1911  Department of Health 

Page 36: 20100719 Weld Range CCP WE Edit PDF KCQA 2 Conceptual Closure Plan 2010.pdf · Weld Range Iron Ore Project Conceptual Closure Plan July 2010 ii Document Status Approved for Issue

 

Weld Range Iron Ore Project 

Conceptual Closure Plan 

 

July 2010    

     

22 

Legislation  Responsible Government Agency 

Heritage of Western Australia Act 1990  Heritage Council of Western Australia 

Mining Act 1978  Department of Industry and Resources 

Mines Safety and Inspection Act 1994  Department of Consumer and Employee Protection 

Occupational Safety and Health Act 1984  Department of Consumer and Employment Protection  

Public Works Act 1902  Department of Housing and Works 

Rights in Water and Irrigation Act 1914  Department of Environment and Conservation 

Soil and Land Conservation Act 1945  Department of Agriculture, Western Australia 

Waterways Conservation Act 1976  Department of Environment and Conservation 

Wildlife Conservation Act 1950  Department of Environment and Conservation 

4.1 GUIDELINES AND CODES OF PRACTICE 

The Guidelines and Codes of Practice outlined below were used in the preparation of this document, and contain material relevant to this Closure Plan are outlined in Table 4.2.   

Table 4.2 – Guidelines and Codes of Practice.   

Aspect  Guidelines 

General/ Closure 

ANZMEC/MCA (2000), Strategic Framework for Mine Closure. Australian and New Zealand Minerals and Energy Council and Minerals Council of Australia.  Canberra, ACT. 

Chamber of Minerals and Energy of Western Australia Inc (1999) Mine Closure Guidelines for Minerals Operations in Western Australia. 

Department of Industry and Resources, (2006). Guidelines for Mining in Arid Environments. 

Department of Industry and Resources, (2006). Guidelines for Mining Proposals in Western Australia. 

Minerals Council of Australia (2000) Code for Environmental Management. 

Department of Tourism, Industry and Resources, (2006). Mine Closure and Completion: Leading Practice Sustainable Development Program for the Mining Industry. 

Ministerial Council of Minerals and Petroleum Resources, Minerals Council of Australia (2003). Strategic Framework for Tailings Management. 

EPA Guidance No. 33 (2008). Environmental Guidance for Planning and Development. 

Department of Mines and Energy, (1997). Safety Bund Walls around Abandoned Open Pit Mines. 

Department of Industry and Resources (2009) Environmental Notes on Mining – Care and Maintenance September 2009.  

Water 

Water and Rivers Commission, (2000). Mine Void Resource Issues in Western Australia. 

Department of Water, (Draft, February 2009). Pilbara Water in Mining Guideline. 

National Health and Medical Research Council (2004). Australian Drinking Water Guidelines. 

ANZECC / ARMCANZ (2000). Australian New Zealand Guidelines for Fresh and Marine Water Quality. 

Water and Rivers Commission (2000). State‐wide Policy No. 5 Environmental Water Provisions for Western Australia. 

EPA Position Statement No. 4. Environmental Protection of Wetlands. 

Tailings and Waste 

Department of Industry and Resources (2001). Environmental Notes on Mining Waste Rock Dumps. 

Department of Industry and Resources (1999) Guidelines on the Safe Design and Operating Standards for Tailings Storage. 

Department of Tourism, Industry and Resources (2007). Tailings Management. 

Page 37: 20100719 Weld Range CCP WE Edit PDF KCQA 2 Conceptual Closure Plan 2010.pdf · Weld Range Iron Ore Project Conceptual Closure Plan July 2010 ii Document Status Approved for Issue

 

Weld Range Iron Ore Project 

Conceptual Closure Plan 

 

July 2010    

     

23 

Aspect  Guidelines 

Water and Rivers Commission (2000). Water Protection Guidelines No. 2‐ Mining and Mineral Processing‐ Tailings facilities. 

Australian Standard 1940 – The Storage and Handling of Flammable and Combustible Liquids (AS 1940‐1993) 

Rehabilitation 

Australian Mining Industry Council (1989), Mine Rehabilitation Handbook. 

Department of Tourism, Industry and Resources, (2006). Mine Rehabilitation: Leading Practice Sustainable Development Program for the Mining Industry. 

Environment Australia (1998). Landform Design for Rehabilitation. 

Flora and Fauna 

National Strategy for Ecologically Sustainable Development (1992) Commonwealth of Australia. 

EPA Position Statement No. 6: Towards Sustainability. 

EPA Guidance Statement No. 55 Implementing Best Practice in proposals submitted to the EIA process. 

EPA Position Statement No 3: Terrestrial Biological Surveys as an element of Biodiversity Protection. 

EPA Position Statement No. 2 Environmental Protection of Native Vegetation in WA. 

EPA Position Statement No. 9 Environmental Offsets. 

EPA Guidance Statement No. 51. Terrestrial Flora and Vegetation Surveys Environmental Impact Assessment in WA. 

EPA Guidance Statement No. 54. Consideration of Subterranean Fauna in Groundwater and Caves during EIA in WA. 

EPA Guidance Statement No. 3. Separation Distances between Industrial and Sensitive Land Uses. 

EPA Guidance Statement No. 56. Terrestrial Fauna Surveys for Environmental Impact Assessment in WA. 

 

 

 

 

 

 

Page 38: 20100719 Weld Range CCP WE Edit PDF KCQA 2 Conceptual Closure Plan 2010.pdf · Weld Range Iron Ore Project Conceptual Closure Plan July 2010 ii Document Status Approved for Issue

 

Weld Range Iron Ore Project 

Conceptual Closure Plan 

 

July 2010    

     

24 

This page has been left blank intentionally. 

 

Page 39: 20100719 Weld Range CCP WE Edit PDF KCQA 2 Conceptual Closure Plan 2010.pdf · Weld Range Iron Ore Project Conceptual Closure Plan July 2010 ii Document Status Approved for Issue

 

Weld Range Iron Ore Project 

Conceptual Closure Plan 

 

July 2010    

     

25 

5 POLICY 

 

Page 40: 20100719 Weld Range CCP WE Edit PDF KCQA 2 Conceptual Closure Plan 2010.pdf · Weld Range Iron Ore Project Conceptual Closure Plan July 2010 ii Document Status Approved for Issue

 

Weld Range Iron Ore Project 

Conceptual Closure Plan 

 

July 2010    

     

26 

This page has been left blank intentionally. 

 

Page 41: 20100719 Weld Range CCP WE Edit PDF KCQA 2 Conceptual Closure Plan 2010.pdf · Weld Range Iron Ore Project Conceptual Closure Plan July 2010 ii Document Status Approved for Issue

 

Weld Range Iron Ore Project 

Conceptual Closure Plan 

 

July 2010    

     

27 

6 STAKEHOLDER CONSULTATION 

ANZMEC  (2000)  highlights  the  importance  of  enabling  all  stakeholders  to  have  their  interests considered during the closure process. 

SMC has been in consultation with key government agencies, Non‐Government Organisations (NGOs) as well as the local communities since the commencement of the feasibility studies. 

Further consultation with government agencies,  the general public, private  landowners,  interested NGO’s  and  other  stakeholders  will  continue  throughout  the  operation  of  the mine  and  closure process.   The closure process will not be viewed as complete until commitments made by SMC  to stakeholders concerning site closure have been met. 

Stakeholders  identified as having an  interest  in the Weld Range  Iron Ore Project are  listed  in Table 6.1.  

Table 6.1 – Stakeholder Consultation. 

Stakeholder Department  Name 

DPI ‐ Statutory Planning Div.  Peter Zadien 

DPI ‐ Land Titles  Nick Schoeffer, Steve Burgess 

DoIR ‐ Investment Facilitation  Peter King 

DoIR ‐ Minerals  Karen Pye, Andrew Bartleet 

DoH ‐ Environmental Health  Dianne Katcherian 

DoCEP ‐ Major Hazards  Richard Craddock, Anil Atri 

DIA  Richard Riordan, Denis Callaghan 

EPA Service Unit  Andrew Napier, Sue Osborne 

DEC ‐ Environment Division ‐ Geraldton  Beth Mckernan 

DEC ‐ Parks and Conservation Div.  Nick Woolfrey, Norm Caporn 

DEC ‐ Environment Division‐ Part V  Peter Skitmore, Danielle Ayre, Emma Jones 

DoW  Susan Worley 

Cue Shire  Brian Seal 

Wildflower Society of WA  Bryan Moyle 

Native Title Claimants  Wajarri Yamatji 

Landowners David  Leach  ‐  Beebyn  Station,  Zane  and  Carolyn  Day  – Madoonga Station, Morrie Sievwright – Glen Station. 

Conservation Council of WA  Tim Nicol 

The Conceptual Closure Plan will be reviewed based on input from stakeholders to ensure all parties are agreed on final land use, decommissioning and rehabilitation procedures. 

A copy of the Conceptual Closure Plan will be publicly available as part of the Project PER.    

Page 42: 20100719 Weld Range CCP WE Edit PDF KCQA 2 Conceptual Closure Plan 2010.pdf · Weld Range Iron Ore Project Conceptual Closure Plan July 2010 ii Document Status Approved for Issue

 

Weld Range Iron Ore Project 

Conceptual Closure Plan 

 

July 2010    

     

28 

This page has been left blank intentionally 

 

Page 43: 20100719 Weld Range CCP WE Edit PDF KCQA 2 Conceptual Closure Plan 2010.pdf · Weld Range Iron Ore Project Conceptual Closure Plan July 2010 ii Document Status Approved for Issue

 

Weld Range Iron Ore Project 

Conceptual Closure Plan 

 

July 2010    

     

29 

7 PLANNING 

A  key  objective  of  ANZMEC  (2000)  is  to  ensure  that  the  process  of  closure  occurs  in  an orderly, timely and cost‐effective manner. 

Mine closure should be integral to the life‐of‐mine plan, should reflect a risk‐based approach and  should  be  reviewed  and  updated  as  required.    SMC  have  ensured  that mine  closure strategies have been  incorporated  into each  stage of  the planning process,  from planning and design, to construction, operations and decommissioning. 

SMC has undertaken extensive public consultation (Section 6) throughout the planning stage of  the proposal concerning  final  landforms, and all Weld Range work areas and associated construction will be in compliance with the appropriate legislation.  

Mine infrastructure including haul roads, plants, administration buildings, workshops, water supply,  the TSFS and overburden  stockpiles have been planned  to  consider  the  following, which may influence the success of mine closure: 

• alignment with natural topographic landforms in the area; 

• use of pre disturbed areas to minimise the impact of clearing on native vegetation; 

• consideration of natural drainage lines and flooding zones; 

• minimise impacts on groundwater levels and quality; 

• avoidance of conservation significant flora; 

• avoidance of Schedule 1 Idiosoma nigrum populations; and 

• avoidance of indigenous heritage sites. 

7.1 RISK ASSESSMENT 

A  comprehensive  risk  assessment  was  undertaken  to  inform  all  environmental  impact assessment documentation.  The risk assessment was completed in April 2009.   

The assessment highlighted the following as having the potential to influence mine closure: 

• waste landform (waste rock stockpiles, tailings storage facility) design and location; 

• contamination from pit lakes; 

• topsoil storage; 

• impacts of mine  infrastructure to surface water flows and water quality during flood events; 

• impacts to surface water and surrounding environment from dewatering and surplus water disposal; 

• vegetation disturbance and weed dispersal;  

• progressive rehabilitation with appropriate species; and 

• financial provisioning for mine closure.  

Page 44: 20100719 Weld Range CCP WE Edit PDF KCQA 2 Conceptual Closure Plan 2010.pdf · Weld Range Iron Ore Project Conceptual Closure Plan July 2010 ii Document Status Approved for Issue

 

Weld Range Iron Ore Project 

Conceptual Closure Plan 

 

July 2010    

     

30 

Consequently preliminary controls have been developed (and described in Section 9 and 10) to  manage  the  extent  to  which  these  factors  may  impact  on  closure  objectives  and completion criteria. 

SMC  have  developed,  and  will  use,  the  following  ‘hierarchy  of  control’ methodology  in planning for project closure: 

• elimination of risk; 

• substitution with a lower risk; 

• engineering to reduce the impact of the risk; 

• administrative procedures and training; and 

• remediation to mitigate impacts. 

7.2 PROJECT CONDITION REPORTS 

In order to appropriately determine closure objectives, surveys and investigations have been conducted including: 

• flora and fauna surveys including stygofauna, troglofauna and short range endemics;  

• hydrogeology  assessments  on  the  impact  of  groundwater  extraction,  surface water flows and water quality; 

• geochemical and physical analysis of waste rock material; and 

• heritage studies including archaeological and ethnographic heritage surveys. 

The  data  gathered  from  these  assessments  has  been  used  to  develop  this  Conceptual Closure Plan. 

7.3 COMPLETION CRITERIA AND PERFORMANCE INDICATORS 

Completion criteria are an agreed  set of environmental  indicators, which upon being met, will  demonstrate  that  agreed  outcomes  have  been  achieved  and  hence  the  site may  be deemed  closed.    These  criteria  are  inextricably  linked  to  management  and  monitoring programmes. 

SMC  will  consult with  all  stakeholders  and  interested  parties  throughout  the  life  of  the Project  to ensure  the agreed  completion  criteria are and  / or will be met, or alternatives agreed to as necessary. 

The  Strategic  Framework  for Mine Closure published by ANZMEC/MCA  (2000)  states  that completion criteria should: 

• Reflect the specific environmental and socio‐economic circumstances of the site. 

• Be  flexible  enough  to  adapt  to  changing  circumstances without  compromising  the agreed end objective. 

• Undergo periodic review and modification in light of improved knowledge or changed circumstances.  

Page 45: 20100719 Weld Range CCP WE Edit PDF KCQA 2 Conceptual Closure Plan 2010.pdf · Weld Range Iron Ore Project Conceptual Closure Plan July 2010 ii Document Status Approved for Issue

 

Weld Range Iron Ore Project 

Conceptual Closure Plan 

 

July 2010    

     

31 

The  proposed  completion  criteria  for  the  Project  have  been  developed,  taking  into consideration the following factors: 

• public health and safety; 

• regulatory requirements;  

• SMC’s Environmental Policy; 

• expectations of stakeholders; 

• geotechnical stability and the suitability of final landforms; 

• sustainability of revegetated areas and surrounding ecosystems; 

• no unapproved disturbance of heritage areas; and 

• post‐closure land use objectives. 

The  closure  criteria and  interim  rehabilitation  targets are  summarised  in Table 7.1 below, and detailed aspects are contained in the remaining sections of this document. 

 

 

Page 46: 20100719 Weld Range CCP WE Edit PDF KCQA 2 Conceptual Closure Plan 2010.pdf · Weld Range Iron Ore Project Conceptual Closure Plan July 2010 ii Document Status Approved for Issue

 

Weld Range Iron Ore Project 

Conceptual Closure Plan 

 

July 2010    

     

32 

Table 7.1 – Closure Criteria 

Aspect  Objective  Interim Rehabilitation Target 

Final Landform  

C1: Final landforms will be developed such that they will remain structurally and chemically stable, safe to humans and provide a sustainable habitat for flora and fauna without ongoing maintenance.  

C2: Landforms will conform to the requirements of agreed post‐closure land use. 

C3: Access to pit lakes will be prohibited to ensure pit lakes are safe to humans and to minimise the occurrence of fauna mortality. 

Safety and abandonment structures are in place and final landforms have been shaped to design criteria. 

Contamination 

C4: There shall be no contamination of groundwater, surface water and surrounding environment from the inappropriate storage or handling of chemicals and hydrocarbons.  

C5: Known contaminated sites are remediated to agreed levels as soon as possible.  

Conduct an ongoing ground and surface water monitoring program that demonstrates pollutant levels at potentially contaminated sites are within regulatory requirements. 

Surface Water  C6: No change in the long term quantity or quality of surface water, so that existing and potential environmental values, including ecosystem maintenance are protected. 

Monitoring program for surface water indicates no reduction in quality as compared to pre‐disturbed state. 

Diversion drains, surrounding the mine pits, will be in tact following mine closure 

Ground Water C7: The quality and quantity of ground water is maintained, so that existing and potential environmental values, including ecosystem maintenance are protected. 

Monitoring program for ground water indicates no reduction in level and quality as compared to pre‐disturbed state. 

Decommissioning C8: All project infrastructure that is not required for post closure land use will be removed or disposed of appropriately. 

Infrastructure has been removed and rehabilitation commenced to simulate the pre‐disturbance state as closely as possible. 

Page 47: 20100719 Weld Range CCP WE Edit PDF KCQA 2 Conceptual Closure Plan 2010.pdf · Weld Range Iron Ore Project Conceptual Closure Plan July 2010 ii Document Status Approved for Issue

 

Weld Range Iron Ore Project 

Conceptual Closure Plan 

 

July 2010    

     

33 

Aspect  Objective  Interim Rehabilitation Target 

Visual Amenity and Heritage 

C9: Ensure that aesthetic values and public interaction with the landscape are considered, and measures are adopted to reduce the visual impacts on the landscape. 

C10:Maintain and protect any significant landscape, indigenous heritage and geo‐heritage values. 

Progressively integrate rehabilitated areas with the natural environment. 

Rehabilitation of Native Vegetation and Topsoil 

C11: Impacted areas are returned to self‐sustaining vegetation communities and fauna habitats that reflect pre‐disturbed state. 

C12: Weed species cover is identified and contained to minimise spread into weed free areas. 

C13: Topsoil remains viable and has the capacity to support a safe, stable and functioning ecosystem that meets the requirements of the post‐mining land use, where it exists. 

Deep ripping has been conducted in rehabilitation areas. 

Flora species have been identified for use in rehabilitation and seed collection where possible, and reflect principles of vegetation succession.  

Permanent photographic record points and monitoring/analog transect locations have been defined. 

Fencing has been erected around rehabilitation target areas to quarantine them from grazing 

Adequate topsoil and subsoil material has been provided for progressive rehabilitation where possible..  

 

 

 

Page 48: 20100719 Weld Range CCP WE Edit PDF KCQA 2 Conceptual Closure Plan 2010.pdf · Weld Range Iron Ore Project Conceptual Closure Plan July 2010 ii Document Status Approved for Issue

 

Weld Range Iron Ore Project 

Conceptual Closure Plan 

 

July 2010    

     

34 

7.4 TARGETED RESEARCH 

Research, where feasible and required, will be conducted to investigate the following: 

• geotechnical and erosion control monitoring; 

• groundwater monitoring; 

• surface water monitoring; 

• rehabilitation monitoring; and  

• physical and chemical soil testing.  

Research into the Idiosoma nigrum Population Genetic Study will be carried out prior to construction commencing  and during  the  life of  the Project.   The  study will  assist  in  the management of each population  as  a  separate  entity,  ensuring  maximum  genetic  diversity  and  that  rehabilitation associated with the Project takes into account mechanisms of recolonisation. 

Page 49: 20100719 Weld Range CCP WE Edit PDF KCQA 2 Conceptual Closure Plan 2010.pdf · Weld Range Iron Ore Project Conceptual Closure Plan July 2010 ii Document Status Approved for Issue

 

Weld Range Iron Ore Project 

Conceptual Closure Plan 

 

July 2010    

     

35 

8 FINANCIAL PROVISION 

Provision  of  adequate  financial  resources  for  closure  is  critical  in  order  to  ensure  that  all  closure requirements  are  reached,  as  agreed  via  consultation,  and  to  finalise  the  Project without  leaving residual company or community liability. 

The ANZMECC Strategic Framework for Mine Closure (2000) objective for closure costing is to ensure the cost of closure is adequately represented in company accounts and that the community is not left with a liability.  ANZMEC (2000) also states that clear accountability and adequate resources must be provided for the implementation of the closure plan. 

Planning for closure commenced  in the feasibility stage and will continue throughout the  life of the mine. 

8.1 COST ESTIMATE 

Table 8.1 details a conceptual cost estimates  for closure  for  the Project, which are based on bond calculations.      Cost  estimates will  be  developed  in  detail  during  the Operational  Closure  Plan  to include  progressive  rehabilitation,  final  closure  activities,  monitoring  and  long‐term  site management.    These  estimates  do  not  include  return  on  sale  of  assets  or  costs  recovered  from salvage of materials. 

Development of a final closure cost model will incorporate the following actions: 

• Conduct technical review and analysis of risk and cost benefit. 

• Quantify subjective factors and analyse aspects with uncertainty. 

• Manage closure of the Project as a self‐funded operation and ensure the Project Business Plan includes costs, revenues, profit / loss and cash flows. 

• Assess closure costs in terms of economic, technical, and social feasibility. 

• Determine that closure does not incur long‐term liabilities to SMC or to the community. 

• Comprehensively  review  costs  on  a  regular  pre‐determined  basis  and  taking  inflation  into account. 

• Determine that closure financial provisioning remains flexible to cope with unexpected events, new technologies, operational change or change in community or regulator expectations. 

• Determine  that  cost  estimates  include  management  of  the  project  related  social  and environmental issues. 

• Include associated monitoring and long‐term site management costs. 

• Determine  that  closure  cost  estimates don’t  rely on  return  from  sale of  assets  and  salvage value. 

• Provision  for  adequate  form  and  amount  of  surety  and  upon  closure,  determine  that requirements for release of surety are met. 

• Periodically review assurance levels as closure needs, environmental risks or economic factors dictate. 

Page 50: 20100719 Weld Range CCP WE Edit PDF KCQA 2 Conceptual Closure Plan 2010.pdf · Weld Range Iron Ore Project Conceptual Closure Plan July 2010 ii Document Status Approved for Issue

 

Weld Range Iron Ore Project 

Conceptual Closure Plan 

 

July 2010    

     

36 

Table 8.1 – Closure Cost Estimate 

Weld Range Project  Approximate Area (ha)  Cost per ha ($)  Total Cost ($) 

Beebyn Pit and Waste Dumps  1098  12000  13,176,000 

Madoonga Pit and Waste Dumps  715.5  12000  8,586,000 

Madoonga Pit Infrastructure  72.6  5000  363,000 

Central  Processing  Facility  –  Plant  and Infrastructure 

450  10000  4,500,000 

Evaporation Pond  674  12000  8,088,000 

Accommodation Village  161.3  5000  806,500 

Airstrip  55  5000  275,000 

Access Tracks and Haul Roads  549  5000  2,745,000 

ANFO   40.3  10000  403,000 

Borrow  258.4  10000  2,584,000 

TOTAL  4074 (40.7 km2)     

TOTAL COST      41,526,500 

 

 

Page 51: 20100719 Weld Range CCP WE Edit PDF KCQA 2 Conceptual Closure Plan 2010.pdf · Weld Range Iron Ore Project Conceptual Closure Plan July 2010 ii Document Status Approved for Issue

 

Weld Range Iron Ore Project 

Conceptual Closure Plan 

 

July 2010    

     

37 

8.2 CLOSURE SCHEDULE 

SMC closure schedule is detailed below in Table 8.2.  

Table 8.2 Mine Closure Schedule 

Project Stage  Activity  Cost Estimate Basis  Reliability 

Pre‐Feasibility 

Discussions with stakeholders on project impacts. 

Conceptual closure planning. 

Costing broad and determined through experience. 

Variable 

Prior to construction 

Conceptual closure planning. 

Discussions with stakeholders on end land use. 

Environmental bonds. 

Variable 

Construction  Progressive rehabilitation.  Preliminary.  +/‐ 25% 

Operations  Progressive rehabilitation.  Budgetary.  +/‐ 25% 

2 years prior to decommissioning 

Detailed engineering planning of closure. 

Quoted costing of major elements of closure. 

Progressive rehabilitation. 

Controlled.  +/‐ 15% 

Annually prior to decommissioning. 

Progressive decommissioning of project components no longer required. 

Progressive rehabilitation.  

Reviewed and updated. 

+/‐ 15% 

8.3 ACCOUNTING STANDARDS 

SMC will  establish  a  closure  provision  in  accordance with  the  requirements  of Australian Accounting Standards Board 137 ‐ Provisions, Contingent Liabilities and Contingent Assets. 

This accounting provision  is a  full  liability provision and an amount of money has been set aside  to  cover  all  final  rehabilitation  costs.    This  amount  shall  be  reviewed  regularly  to ensure that enough resources are available for closure.  

8.4 ADEQUATE SECURITIES 

Unconditional  Performance  Bonds  are  lodged  with  the  Department  of  Industry  and Resources  in  accordance with  the Mining Act 1978.   The bond  is  a  contract between  the Minister for State Development and a bank or third party of financial standing acceptable to the Minister.  The bank or third party providing the bond remains liable to the Minister even when the tenement owner is in bankruptcy or liquidation. 

The bond may be reduced throughout the  life of the Project where rehabilitation has been carried  out  and  has  clearly  demonstrated  stability  under  at  least  average  seasonal conditions.  The bond will be retired when the rehabilitation has met all completion criteria and  standards  set  out  in  approval  documents,  annual  environmental  reports  and decommissioning  plans,  and when  the Department  of  Industry  and  Resources  is  satisfied 

Page 52: 20100719 Weld Range CCP WE Edit PDF KCQA 2 Conceptual Closure Plan 2010.pdf · Weld Range Iron Ore Project Conceptual Closure Plan July 2010 ii Document Status Approved for Issue

 

Weld Range Iron Ore Project 

Conceptual Closure Plan 

 

July 2010    

     

38 

that  the  rehabilitated area  is  safe,  stable, erosion  is  comparable  to  the  surrounding areas and the biological system is sustainable under a range of seasonal conditions representative of that climate (Department of Industry and Resources, 2009) 

Details  of  SMCs  Unconditional  Performance  Bonds  held  for  tenements  held  by  SMC  are detailed in Table 8.3. 

Table 8.3 – Unconditional Performance Bonds for SMC Tenements 

Tenement Number 

Bond Amount Date Last Increase was 

Requested Brief description of infrastructure covered 

by bond 

P51/2581  NA     

E20/595  NA     

P51/2552  NA     

M20/419  NA     

E20/457  NA     

E20/459  NA     

E20/492  $10,000  03/05/2010  Drilling pads and tracks 

E51/907  $117,000  26/06/2009  Drilling pads and tracks 

M20/402  $28,000  28/05/2009  Exploration camp, firebreak, camp ext. 

M20/403  NA     

TR70/3902  NA     

E20/635  NA     

E20/633  NA     

E20/641  $19,000  03/05/2010  Drilling pads and tracks 

E51/1354  NA     

E20/625  $20,000  06/2006  Drilling pads and tracks 

P20/2077  NA     

P20/2078  NA     

P20/2016  NA     

P20/2084  $40,000  11/2009  Drilling pads and tracks 

P20/2085  $10,000  11/2009  Drilling pads and tracks 

M20/503  NA     

M20/311  NA     

Total $ 244,000

 

Page 53: 20100719 Weld Range CCP WE Edit PDF KCQA 2 Conceptual Closure Plan 2010.pdf · Weld Range Iron Ore Project Conceptual Closure Plan July 2010 ii Document Status Approved for Issue

 

Weld Range Iron Ore Project 

Conceptual Closure Plan 

 

July 2010    

     

39 

8.5 REVIEW 

This cost estimate will be reviewed annually during operations to adjust for inflation and re‐assessment to account for changing standards and expectations.  

The  financial provisioning will be reviewed  following any alteration to the cost‐estimate to ensure it is appropriate to adequately cover the costs of rehabilitation and decommissioning. 

 

Page 54: 20100719 Weld Range CCP WE Edit PDF KCQA 2 Conceptual Closure Plan 2010.pdf · Weld Range Iron Ore Project Conceptual Closure Plan July 2010 ii Document Status Approved for Issue

 

Weld Range Iron Ore Project 

Conceptual Closure Plan 

 

July 2010    

     

40 

This page has been left blank intentionally. 

 

Page 55: 20100719 Weld Range CCP WE Edit PDF KCQA 2 Conceptual Closure Plan 2010.pdf · Weld Range Iron Ore Project Conceptual Closure Plan July 2010 ii Document Status Approved for Issue

 

Weld Range Iron Ore Project 

Conceptual Closure Plan 

 

July 2010    

     

41 

9 GENERAL REHABILITATION AND CLOSURE STRATEGIES 

9.1 WASTE LANDFORM 

SMC will undertake appropriate consultation  throughout  the planning stage of  the Project concerning final landforms and all Project work areas.  

With  the  size  and  scale  of  operations,  the  Project will  have  a  significant  impact  on  the surrounding  areas.    Changing  the  existing  landform with  the mining  of  the  pit  void  and construction  of  the mine waste  dumps will  be  the most  significant  visual  impact  of  the mining operation. 

The  potential  impacts  of  the  Project  on  the  geology  and  landform  resources  would  be associated with the following: 

• Permanent landform modification as a result of mine pits. 

• Permanent new landforms as a result of the TSF and waste dump areas. 

• Short  to  medium  term  changes  to  the  landscape  as  a  result  of  construction  of infrastructure. 

The Project area  is surrounded by flat plains and will cover an area approximately 4074 ha.  The proposed pit areas and external waste dumps  (at Beebyn and Madoonga) will have a footprint  of  1098  ha  and  715.5  ha,  a  height  of  600 m  RL  and  560 m  RL  and  20°  slopes respectively. 

On completion of mining, approximately 100 m3 of the mine deposit will be  left open.   It  is anticipated this void will fill up with water to form pit lakes.   

9.1.1 Closure Objectives 

The objectives for management of final landforms are to: 

• Maintain and protect any significant landscape, indigenous heritage and geo‐heritage values and maintain the integrity, ecological functions and environment values of the soil, drainage lines and landforms. 

• Meet post‐mining land use requirements. 

9.1.2 Completion Criteria 

The following are the desired outcomes concerning the development of landforms: 

• Project landforms have been shaped and rehabilitated as per stakeholder consultation and condition requirements. 

• All Project infrastructure has been removed and rehabilitation of the site to final land use requirements has been completed. 

Page 56: 20100719 Weld Range CCP WE Edit PDF KCQA 2 Conceptual Closure Plan 2010.pdf · Weld Range Iron Ore Project Conceptual Closure Plan July 2010 ii Document Status Approved for Issue

 

Weld Range Iron Ore Project 

Conceptual Closure Plan 

 

July 2010    

     

42 

C1:   Final  landforms  will  be  developed  such  that  they  will  remain  structurally  and chemically  stable,  safe  to humans  and provide  a  sustainable habitat  for  flora  and fauna without ongoing maintenance.  

C2:   Landforms will conform to the requirements of agreed post‐closure land use. 

C3:   Access to pit  lakes will be prohibited to ensure pit  lakes are safe to humans and to minimise the occurrence of fauna mortality. 

9.1.3 Management Actions 

SMC  will  undertake  public  consultation  throughout  the  planning  stage  of  the  Project concerning final landforms and all Project work areas. 

To  ensure  the  development  of  safe  and  environmentally  appropriate  landforms  and  to minimise long term visual impacts resulting from the Project, SMC will: 

• Establish completion criteria, including landform design, for each landform. 

• SMC  will  conduct  research  in  order  to  determine  what  angle  of  slope  would  be suitable, based on the type of material  in the waste dump.   The most stable,  lowest erosion  potential  and  natural  looking  landform  will  be  created.    Berms  will  be removed or made less steep and will slope outwards to prevent water pooling on the face  of  the  dump  which  could  lead  to  erosion  including  tunnel  erosion  and  gully formation. 

• A crestal bund shall be installed around the top of the dump and incorporated into the slope.  This bund has the purpose of retaining water from rainfall on top of the dump to  prevent  further  runoff  down  the  face  of  the  dump  and  therefore  reducing  the potential for erosion. 

• Topsoil  will  be  spread  and  then  ripped  to  bring  up  some  rock  from  the  layer immediately under the topsoil.  This will help to prevent erosion by “rock armouring” the  face of  the dump.   Lose dead vegetation,  tree branches etc, will  then be spread over this surface to further enhance erosion control by preventing rainfall runoff from concentrating in one area, slowing the flow of runoff down the face of the dump and promoting the dispersion of runoff across the whole face. 

• Implement  rehabilitation  methods,  as  described  in  Section  9.7.3,  to  achieve  the required landform. 

• Revegetate the site to the required land‐use objective. 

• The end  land use  for  the area will be determined  in  consultation with  stakeholders and agreed with the administering authority. during the life of the mine; 

• Sloped landforms will be covered with topsoil and then deep ripped to a minimum of 1 m on contour; 

• Ensure rip lines are horizontal for the entire length. 

• Monitor the site to determine that agreed outcomes are being achieved. 

• Undertake remedial actions as necessary to remedy any deviations from the required objective. 

Page 57: 20100719 Weld Range CCP WE Edit PDF KCQA 2 Conceptual Closure Plan 2010.pdf · Weld Range Iron Ore Project Conceptual Closure Plan July 2010 ii Document Status Approved for Issue

 

Weld Range Iron Ore Project 

Conceptual Closure Plan 

 

July 2010    

     

43 

• Record all actions at the site. 

• Leave residual pit voids as run‐of‐mine (ROM) where geotechnically stable, and profile as necessary to achieve long term closure objectives. 

• Restrict access to the TSF once mining and processing ceases.  Access restrictions will remain until the tailings have consolidated and dried sufficiently to support machinery and allow rehabilitation to be completed.  Rehabilitation will be undertaken to ensure that the TSF is safe and stable and potential erosion is minimised. 

• Ensure  revegetation  efforts  will  be  aimed  at  establishing  local  native  vegetation suitable to domain characteristics. 

A major  cause  of  erosion  on  newly  created  landforms  is  the  lack  of  adequate  drainage control.    Therefore  design  and  construction  of  drainage  control measures  will  take  into account the predicted 1 in 100 ARI flood events. 

Reshaping of landforms aims to produce slopes with angles, lengths and shapes compatible with  the  surrounding  landscape,  suitable  for  the proposed  land use  and not prone  to  an unacceptable  rate of  erosion.   On  finalisation of  the Project,  the  following  landforms will require earth works reshaping: 

• waste rock dumps; 

• ROM pads, borrow pits; and  

• haul roads. 

Specific closure strategies for key infrastructure are described in Section 10. 

9.2 CONTAMINATED SITES 

Acid forming waste rock and hazardous materials such as fuels, process reagents, lubricants, detergents,  explosives,  solvents  and  paints  can  be  detrimental  to  plant  growth  and may result in contamination of both surface and groundwater. 

If  these  materials  are  not  properly  managed,  they  may  have  the  potential  to  cause atmospheric, soil or water contamination and could potentially pose ongoing risks to human health and the environment. 

Under  the Contaminated Sites Act 2003 a site  is considered  to be contaminated  if  it has a substance present at above background concentrations that presents, or has the potential to present, a risk of harm to human health, the environment or any environmental value. 

There are no recognised contaminated sites within the project footprint. 

Waste rock has been assessed as predominately non acid forming (NAF) with approximately 11%  of  the Madoonga  and  1%  of Beebyn waste material  expected  to  be potentially  acid forming (PAF). 

The  potential  exists  for  contamination  to  occur  during  the  life  of  the  Project  due  to  the handling and  storage of hydrocarbons and chemicals.   This potential will be minimised by ensuring hazardous materials  are  stored  in  appropriately bunded  areas  and  any  spills  are cleaned up promptly and appropriately. 

Page 58: 20100719 Weld Range CCP WE Edit PDF KCQA 2 Conceptual Closure Plan 2010.pdf · Weld Range Iron Ore Project Conceptual Closure Plan July 2010 ii Document Status Approved for Issue

 

Weld Range Iron Ore Project 

Conceptual Closure Plan 

 

July 2010    

     

44 

Potential contamination sources may include workshops and plant and fuel storage facilities.  Potential impacts relevant to closure include: 

• Contamination of soil, groundwater and surface water sources within the Weld Range are as a result of inappropriate storage or handling of chemicals and hydrocarbon. 

• Contamination of soil, groundwater and surface water within the Weld Range area as a result of inappropriate management of PAF materials and potential leachate. 

• Contamination of groundwater from leachate from pit lakes.  

9.2.1 Objectives 

There  are no  existing  contaminated  sites within  the Project  footprint.   Closure objectives include: 

• Ensure no contaminated sites occur through Project operations.  

• Ensure  any  contamination  that  occurs  is  investigated  and  remediated  as  soon  as possible. 

• Any significant spills will be reported to the DEC and recorded through SMC’s incident reporting system. 

9.2.2 Completion Criteria 

The  following  completion  criteria  for  contaminated  locations will  be  observed  before  or during closure: 

• All known contaminated  sites have been  investigated and  remediated  to acceptable levels. 

• Specific criteria will be determined for each specific contamination situation. 

C4:   Contamination  of  groundwater,  surface water  and  surrounding  environment  from the  inappropriate  storage  or  handling  of  chemicals  and  hydrocarbons  will  be prevented.  

C5:   Known contaminated sites are remediated to agreed levels as soon as possible.  

9.2.3 Management Actions 

To reduce the risk of soil or water contamination and to ensure that the site is remediated to agreed standards, SMC will: 

• Regularly inspect areas where contamination is likely to occur. 

• Develop criteria to be met by remediation and a timeframe for remediation activities. 

• Determine appropriate remediation methods and implemented remediation actions. 

• Undertake  monitoring  and/or  testing  using  appropriate,  recognised  methods,  to demonstrate  reduction  of  any  contamination  to  acceptable  levels  using  an independent auditor. 

Page 59: 20100719 Weld Range CCP WE Edit PDF KCQA 2 Conceptual Closure Plan 2010.pdf · Weld Range Iron Ore Project Conceptual Closure Plan July 2010 ii Document Status Approved for Issue

 

Weld Range Iron Ore Project 

Conceptual Closure Plan 

 

July 2010    

     

45 

• Keep appropriate records of all actions and results.   

9.3 SURFACE WATER 

Surface water drainage lines flowing off the Weld Range will be affected by the development of  infrastructure  and  waste  dumps,  which  may  in  turn  impact  the  nearby  Beebyn  and Madoonga creeks.  Some vegetation units occur on these drainage lines and are likely to be influenced by changes in surface water flow. 

Permanent changes to the pattern of flows due to post closure landforms are likely to result in  geomorphic  changes  to  drainage  lines  around  and  downstream  of  the mine  site.    The degree of change will depend on how post closure  flows are distributed compared  to  the natural  distribution  of  flows.    SMC’s  aim  is  to  ensure  post  closure  flows  are  as  close  as possible to natural conditions. 

Potential impacts relevant to closure include: 

• Drainage stability and erosion of mine closure landforms.  

• Permanent  changes  to  the pattern of overland  and  sheet  flow  and  the  subsequent changes to vegetation distribution. 

9.3.1 Objectives 

The closure objectives for surface waters are: 

• To  restore  baseline  flow  regimes, where  possible,  in  areas  affected  by mining  and closure works.  

• To maintain baseline surface water quality.  

• To  ensure  stability  of  permanent  diversions,  creek  reconstructions  and  other constructed water management works left after mine closure.  

• To ensure stability of drainage from landforms created by mining.  

• The integrity, ecological functions and environmental values of wetlands and drainage systems interacting with the proposal are maintained.  

• Contaminated waters have been  controlled  and  contained on  site  to prevent  entry into  groundwater,  natural  drainage  systems  and  surrounding  vegetation  and remediation has been undertaken as necessary. 

9.3.2 Completion Criteria 

The following are the desired outcomes concerning surface water: 

• Water use related infrastructure has been effectively decommissioned, as per agreed post  land  use  intentions,  and  natural  drainage  patterns  are  reinstated  as  far  as possible dependent on site layout and water management scenarios. 

• Where practicable,  surface water drainage has been  reinstated  to mimic pre‐mining drainage. 

Page 60: 20100719 Weld Range CCP WE Edit PDF KCQA 2 Conceptual Closure Plan 2010.pdf · Weld Range Iron Ore Project Conceptual Closure Plan July 2010 ii Document Status Approved for Issue

 

Weld Range Iron Ore Project 

Conceptual Closure Plan 

 

July 2010    

     

46 

C6:   No change in the long term quantity or quality of surface water, so that existing and potential environmental values, including ecosystem maintenance are protected. 

9.3.3 Management Actions 

The Beebyn and Madoonga mine  site  infrastructure will be  located outside  the estimated 100‐year ARI design  flood extents of  the main  creeks.   Flood protection measures will be required  to  protect  the  site  infrastructure, waste  dumps  and mine  pits  from  inundation caused by sheet flow and localised flooding of minor waterways. 

To ensure the appropriate management of surface water during and post mine closure, SMC will: 

• Design diversion drains to divert runoff from undisturbed areas around or through the mining operations where possible, with an allowance for 0.5 m freeboard.   Diversion drains around the mine site infrastructure and waste dump drainage will be designed to capture and divert the 10 year ARI design flood event, while mine pit diversions will capture and divert  the 100‐year ARI design  flood event.   Portions of  the Madoonga waste dump drainage are located within the 100‐year ARI flood risk area (Figure 9.1).  This drainage will require safety bunds constructed down gradient of the drains and at a level appropriate to maintain a minimum 0.5 m freeboard above floodwaters. 

• Design diversion channels with sufficient capacity for a nominated rainfall event, while minimising earthworks and the channel footprint. 

• Ensure channels are the appropriate width and depth and have bed gradient and side batters to minimise channel velocities and ensure a stable channel profile. 

• Ensure all waste rock stockpiles are bunded appropriately to contain  internal surface water runoff for treatment and to divert external surface water.  A crestal bund shall be  installed around the top of the dump and  incorporated  into the slope.   This bund has the purpose of retaining water from rainfall on top of the dump to prevent further runoff down the face of the dump and therefore reduces the potential for erosion. 

• Develop and implement a monitoring program for surface water level and quality. 

• Implement systems and practices to avoid pollution events during the operational life of the mine. 

• Manage  all  pollution  events  immediately  to  reduce  impact  on  surface  and  ground water. 

• Rehabilitate all disturbed areas relevant to the project to reduce erosion and facilitate integration into the natural drainage system. 

• Record all actions and results.   

Page 61: 20100719 Weld Range CCP WE Edit PDF KCQA 2 Conceptual Closure Plan 2010.pdf · Weld Range Iron Ore Project Conceptual Closure Plan July 2010 ii Document Status Approved for Issue

560

550

540530

520

510

500

490

570

580

590

600 610

620 630640

500

620580

620

510

600

530510

500

590

610

490

580

560

530

500

490

570

580

520

600

510

500

580

500

490

590

610

MSP01

MSP02

MDD06

MDD07

MD

D05

MDD03

MDD04

MD

D08

MDD02 MDD01M

DD

10

MD

D11

557000

557000

558000

558000

559000

559000

560000

560000 561000

561000

7017000

7017000

7018000

7018000

7019000

7019000

7020000

7020000

DRG NO

TITLE

CHKDRN

CLIENT

DATE

WELD RANGE IRON ORE PROJECTMADOONGA MINE PIT ANDWASTE DUMP DRAINAGE

DG 28-11-20080

REV

13292 FIGURE 9.1SA

REV REVISION DESCRIPTION

LOCALITY

A FOR INFORMATION ONLY

±

0 400 800 1,200 1,600

Meters

Legend

Diversions

Flood Plain

Sump Pump Sediment Ponds (Not to Scale)

Waste Dump Sediment Ponds (Not to Scale)

Mine Pit Stage 1

Mine Pit Stage 2

Mine Pit Stage 3

Waste Dump

INFORMATION ONLYNOT TO BE USED

FOR CONSTRUCTION

Pro

duce

d by

Dar

ryl G

illgr

en G

eom

atic

s W

orle

yPar

sons

WA

NOTES

WORLEYPARSONS PROJECT

DATUM

SCALE @ A31:12,000GCS GDA 1994 MGA z50S

Project Location: G:\150-13923_Weld_Range\GIS

B FOR CUSTOMER REVIEW

FOR USE0

DG

DG

SA

SA

3-12-2008

5-12-2008

Page 62: 20100719 Weld Range CCP WE Edit PDF KCQA 2 Conceptual Closure Plan 2010.pdf · Weld Range Iron Ore Project Conceptual Closure Plan July 2010 ii Document Status Approved for Issue

 

Weld Range Iron Ore Project 

Conceptual Closure Plan 

 

July 2010    

     

48 

This page has been left blank intentionally. 

 

Page 63: 20100719 Weld Range CCP WE Edit PDF KCQA 2 Conceptual Closure Plan 2010.pdf · Weld Range Iron Ore Project Conceptual Closure Plan July 2010 ii Document Status Approved for Issue

 

Weld Range Iron Ore Project 

Conceptual Closure Plan 

 

July 2010    

     

49 

9.4 GROUNDWATER 

The Project will have minimal  impact on groundwater quality  through  spillages of  liquid chemicals and hydrocarbons and the disposal of various forms of solid and liquid wastes. 

Drilling at Weld Range has suggested that: 

• Groundwater  moves  from  the  north  towards  the  south‐east  following  the  tertiary palaeochannels drainage direction. 

• The regional water elevations range between 510.15 m RL (Outcamp Well) along the northern margin to about 427.15 m RL (7 Mile Well) along the southern margin of the investigated area, these wells are 45 km apart. 

• The elevation of the water level mound ranges from 482.24 to 507.78 m RL. 

• The groundwater is fresh (TDS < 500 mg/l) to marginal (500 < TDS < 1,500 mg/l), except in the boreholes or wells  located on  the palaeochannels.   The areas of higher groundwater salinity correspond  to  lower  topographic  areas  and  surface  drainage  systems.    Owing  to  the  high evaporation rate; the water evaporates as soon as it reaches the surface or even in the vadose zone  just below the surface.   This results  in the deposition of numerous minerals and salts  in and  around  the  lower  topography  areas  and  subsequently  increases  the  salinity  of  the immediate groundwater.   The water quality  then becomes brackish  (1,500<TDS<5,000 mg/l) varying  from  2,643 mg/l  (7 Mile Well)  to  4,900 mg/l  (Gap  Bore)  to  saline with  the  highest salinity  measured  at  MDWB01  (48,000  mg/l),  M_WBG_01R  (46,000  mg/l)  and  M‐LTM‐04 (35,000 mg/l).    The  boreholes  that  have  the  highest  salinity  reflect  the  proximity  of  these boreholes to the tertiary palaeochannel (SRK 2010a). 

• The  average  regional  groundwater  is mildly  acidic  (pH of 5.4)  to mildly  alkaline  (pH of 8.5), indicated from the contouring of the groundwater pH data. 

Potential impacts to groundwater arising from the Project and relevant to closure include: 

• Lasting disruption to the natural groundwater flow processes as a result of mining operations. 

• Pollution  from  chemical  and  hydrocarbon  materials  and  waste  water  streams  from  the operation. 

• Degradation and contamination of groundwater sources from inappropriately constructed and managed TSF and waste rock stockpiles.  

• Lasting ecological impacts from the drawdown resulting from pit dewatering. 

Following cessation of dewatering, natural recharge and  inflow processes will result  in water  levels recovering  to  pre‐mining  levels.    Consequently,  there  are  unlikely  to  be  any  significant  long‐term impacts on water quality or groundwater  flow as a  result of  this Project.   Numerical groundwater modelling  will  be  undertaken  to  simulate  the  closure  strategy  and  confirm  the  viability  of  the preferred closure option. 

Modelling completed  in  the PER predicts  that  in  the  first year post‐mining pit  lakes will develop  in both Beebyn and Madoonga, as inflow enters into the pits.  The water level in the pit lakes of Beebyn will rise up to 480 m RL while in Madoonga the pit water level will reach 430 m RL after 25 years post mining.   

Page 64: 20100719 Weld Range CCP WE Edit PDF KCQA 2 Conceptual Closure Plan 2010.pdf · Weld Range Iron Ore Project Conceptual Closure Plan July 2010 ii Document Status Approved for Issue

 

Weld Range Iron Ore Project 

Conceptual Closure Plan 

 

July 2010    

     

50 

The concentration of solutes within the pit lakes will increase over time due to high evaporation and low precipitation  in the area.   However these  lakes will act as sinks as they will be below the water table level.  Therefore no impact to surrounding groundwater will be expected. 

9.4.1 Objectives 

The closure objectives for groundwater are: 

• The  quality  and  quantity  of  groundwater  is  maintained,  so  that  existing  and  potential environmental values, including ecosystem maintenance are protected. 

• Hydraulic continuity along the aquifer system will be reinstated post closure. 

9.4.2 Completion Criteria 

The following are the desired outcomes concerning groundwater: 

• Contaminated  waters  have  been  controlled  and  contained  on  site  to  prevent  entry  into groundwater and remediation has occurred.  

• Groundwater levels, quality and flow processes return to pre‐mining conditions. 

C7:   The  quality  and  quantity  of  ground  water  is  maintained,  so  that  existing  and  potential environmental values, including ecosystem maintenance are protected. 

9.4.3 Management Actions 

To ensure the appropriate management of groundwater during and post mine closure, SMC will: 

• Prevent  groundwater  pollution  and  contamination  through  appropriate waste management practices, as outlined in the Project Environmental Management Plan. 

• Develop and implement a monitoring program for groundwater level and quality. 

9.5 DECOMMISSIONING 

During the decommissioning phase of the Project, all  infrastructure that cannot be used by another party will be removed or buried and the disturbed areas rehabilitated.  

Decommissioning will comprise the safe dismantling and removal of  infrastructure, the appropriate disposal of waste materials and  the  return of  impacted areas  to a variety of vegetation  types and fauna habitats that simulate the pre‐disturbance state as closely as possible (or  in accordance with agreed post‐mining land use).   

This may include the removal of: 

• crushing and screening plant and processing buildings; 

• fuel and bulk storage facilities; 

• workshops; 

• dewatering equipment and surplus water disposal equipment; 

• offices and accommodation village; and 

• support infrastructure including road train and train loading facilities. 

Page 65: 20100719 Weld Range CCP WE Edit PDF KCQA 2 Conceptual Closure Plan 2010.pdf · Weld Range Iron Ore Project Conceptual Closure Plan July 2010 ii Document Status Approved for Issue

 

Weld Range Iron Ore Project 

Conceptual Closure Plan 

 

July 2010    

     

51 

Where  the  removal of non‐visible  infrastructure, or  features  that have been  incorporated  into  the natural  landscape may cause more environmental damage than  if  left  in situ, their retention will be discussed with the relevant authorities at the time. 

9.5.1 Objectives 

The objectives of decommissioning are to: 

• Remove or appropriately dispose of project infrastructure that is not required for post closure land uses. 

• Modify,  as  required,  any  infrastructure  that will  remain  to  ensure  its  long  term  safety  and viability. 

• Dispose of all waste material appropriately and in accordance to agreed outcomes. 

9.5.2 Completion Criteria 

The following are the desired outcomes concerning Project decommissioning: 

• Appropriate removal and/or modification of all required infrastructure. 

• Stable long term structural integrity is achieved. 

• Public and environmental health and safety is protect.; 

• Local ground and surface water characteristics are preserved. 

• Successful rehabilitation occurs to support sustainable habitat for native fauna and flora. 

• Consideration of post closure land uses is undertaken. 

C8:   All project  infrastructure  that  is not  required  for post closure  land use will be  removed or disposed of appropriately. 

9.5.3 Management Actions 

To ensure appropriate decommissioning of Project infrastructure, SMC will: 

• Identify  what  infrastructure  will  remain  and  what  will  be  removed  in  consultation  with stakeholders. 

• Ensure  that  any  Project  infrastructure  that will  not  be  used  by  a  post  closure  land  user  is removed. 

• Rehabilitate disturbed areas  to suit post closure  land uses and to reflect the pre‐disturbance condition. 

Following  the  removal  of  infrastructure  and  re‐profiling  of  the  land  surface,  additional  surface treatment works will be implemented including: 

• Rehabilitation management actions as outlined in Section 9.7.3. 

• Maintenance of sediment traps where required (e.g. recently rehabilitated areas) to reduce the potential for the migration of sediments. 

• Undertake  contamination  remediation  and  rehabilitate  all  sites  to  the  agreed  completion criteria. 

Page 66: 20100719 Weld Range CCP WE Edit PDF KCQA 2 Conceptual Closure Plan 2010.pdf · Weld Range Iron Ore Project Conceptual Closure Plan July 2010 ii Document Status Approved for Issue

 

Weld Range Iron Ore Project 

Conceptual Closure Plan 

 

July 2010    

     

52 

• At  the  completion  of mining,  haul  roads  that  have  not  been  rehabilitated  as  part  of  the progressive rehabilitation programme will be re‐profiled (including removal of portions of haul road  embankment  where  necessary)  to  blend  in  with  surrounding  topography.    Where necessary, road surfaces will be re‐profiled  to allow  free drainage and minimise  interference with surface flows. 

9.6 VISUAL AMENITY AND HERITAGE 

Due  to  the  isolated nature of  the project  location  it  is not anticipated  that  the Project will have a significant impact on visual amenity of locals or tourists. 

However  the mine will  result  in highly  visible, permanent  changes  to  the  landscape  and  SMC  are committed  to  reducing  these visual  impacts and maintaining post closure  the amenity and original uses of the area. 

9.6.1 Objectives 

• Ensure  that  aesthetic  values  and  public  experience  of  the  landscape  are  considered,  and measures are adopted to reduce the visual impacts on the landscape. 

• Protect, as far as possible, the heritage values of the area. 

9.6.2 Completion Criteria 

The following are the desired outcomes concerning aesthetics and indigenous heritage: 

• Aboriginal heritage  sites have not been disturbed without approval  from  the Department of Indigenous Affairs (DIA) and the areas traditional custodians. 

• All sites have been signed off by stakeholders and responsible authorities. 

C9:   Ensure  that aesthetic values and public  interaction with  the  landscape are considered, and measures are adopted to reduce the visual impacts on the landscape. 

C10:  Maintain and protect any significant landscape, indigenous heritage and geo‐heritage values. 

9.6.3 Management Actions 

To ensure that amenity values of the area are maintained, SMC will: 

• Consult with relevant stakeholders throughout the life of the project to determine appropriate end land use. 

• Mining  landforms  will  be  rehabilitated  consistent  with  landscape  values  of  the  area  and sympathetic to natural mesa. 

• Use of  concave  slopes  to assist  the engineered  structures  to appear more natural and offer more resistance to erosion than linear slopes.  

• Use of endemic plant species to ensure that rehabilitation is sustainable and comparable to the surrounding environment. 

• Placement of additional waste rock material on the top surface of the structures to break up the  uniformity  of  the  flat  surface  and  contouring  of  the  top  surface  to  prevent  water 

Page 67: 20100719 Weld Range CCP WE Edit PDF KCQA 2 Conceptual Closure Plan 2010.pdf · Weld Range Iron Ore Project Conceptual Closure Plan July 2010 ii Document Status Approved for Issue

 

Weld Range Iron Ore Project 

Conceptual Closure Plan 

 

July 2010    

     

53 

overtopping  the  embankments  and  causing  excessive  erosion.    A  store  and  release  cover system will be employed to provide suitable habitat for reseeding with endemic species. 

• Progressive  rehabilitation  of  all  areas,  removal  of  stream  diversion  drains  and  ponds,  re‐contouring of the landscape and revegetation with endemic species. 

• The  surrounding  landscape  will  be  considered  when  deciding  on  the  location,  design  and colour of mine infrastructure.  

• Following completion of mining operations and processing, remaining infrastructure that does not have any post‐mine benefit will be demolished, removed and the area rehabilitated. 

9.7 REHABILITATION OF NATIVE VEGETATION AND TOPSOIL 

Minimising or controlling  the disturbance  footprint of  the Project  is  the most effective method  for ensuring  that  closure  objectives  with  respect  to  a  functioning  ecosystem  are  met.    Vegetation disturbance refers to the direct impact of clearing as well as indirect disturbance through the spread of weeds, fire, altered hydrology, soil or water contamination and dust. 

Rehabilitation is the process used to repair the impacts of mining on the environment.  The long‐term objectives of rehabilitation can vary from simply converting an area to a safe and stable condition, to restoring the pre‐mining conditions as closely as possible to support the future sustainability of the site (DoIR, 2006b). 

Rehabilitation normally comprises the following: 

• Developing designs for appropriate landforms for the mine site. 

• Creating  landforms  that will  behave  and  evolve  in  a  predictable manner,  according  to  the design principles established. 

• Establishing appropriate sustainable ecosystems. 

9.7.1 Objectives 

The closure objectives for rehabilitation are: 

• Minimise the loss of native vegetation and plant communities. 

• Protect Priority flora within the Project area. 

• Protection of Idiosoma and Cethegus. 

• Ensure  that  rehabilitation achieves a  safe,  stable and  functioning ecosystem  that meets  the requirements of the post‐mining land use. 

• Undertake progressive rehabilitation to minimize open areas as far as possible and reduce the likelihood of weed infestation. 

• Weed outbreaks as a result of project activities have been assessed and controlled in a manner agreed with stakeholders and responsible authorities. 

• Rehabilitation measures and methods utilised comply with agreed and approved rehabilitation management guidelines. 

• Practices fulfil commitments made to stakeholders and regulators regarding closure outcomes.  

Page 68: 20100719 Weld Range CCP WE Edit PDF KCQA 2 Conceptual Closure Plan 2010.pdf · Weld Range Iron Ore Project Conceptual Closure Plan July 2010 ii Document Status Approved for Issue

 

Weld Range Iron Ore Project 

Conceptual Closure Plan 

 

July 2010    

     

54 

9.7.2 Completion Criteria 

The following are the desired outcomes concerning the rehabilitation of native vegetation: 

• SMC will  comply with  and  ANZMEC‐MCA  Strategic  Framework  for Mine  Closure  (2000),  to return the mine site, where practicable, to a viable self‐sustaining ecosystem that is adequately financed, implemented and monitored within all jurisdictions. 

• Overburden stockpiles and disturbed sites have been constructed according  to  the approved design criteria. 

• Rehabilitation has occurred progressively where possible and areas have been revegetated to meet the agreed post‐mining land uses. 

C11:   Impacted areas are  returned  to  self‐sustaining vegetation  communities and  fauna habitats that reflect pre‐disturbed state. 

C12:  Weed species cover is identified and contained to minimise spread into weed free areas. 

C13:  Topsoil  remains  viable  and  has  the  capacity  to  support  a  safe,  stable  and  functioning ecosystem that meets the requirements of the post‐mining land use, where it exists 

9.7.3 Management Actions 

To ensure the Project site  is adequately rehabilitated during mine operation and post mine closure, SMC will: 

• Control clearing in accordance with the Project EMP. 

• Management of Idiosoma nigrum as outlined in the Conservation Management Plan. 

• Management of Cethegus sp. as outlined in the Conservation Management Plan. 

• Management of feral animals as outlined in the Project EMP. 

• Rehabilitation will be carried out progressively over the life of the Project. 

• Rip on contours  to relieve compaction, reduce erosion and  improve water  infiltration.   Deep ripping will be undertaken where  the soil or waste material  is of  low permeability.    In areas where  the  soil  or  waste  material  is  of  high  permeability  scarifying  on  contours  will  be undertaken.   On steep slopes this may require terracing or benching.  All ripping, terracing or benching will be surveyed to ensure that they are on contours. 

• Re‐establish  stable  landforms with  erosion  control measures  for  long  term  stability will  be undertaken. 

• Where available, utilise  topsoil  to provide a  foundation  into which native vegetation will be planted and/or  seeded.   Topsoil or other  suitable material will be applied at an appropriate depth, in the order of 100 mm where practicable, to achieve revegetation. 

• Ensure  direct  seeding  and/or  planting  is  undertaken  to  encourage  vegetation  growth  to stabilise  surfaces  and  aid  the  integration  of  landforms  into  the  surrounding  landscape  and ecosystems. Seeding and/or planting will be undertaken prior  to  the wet season  (as soon as possible after earthworks) using seed and plants native to the Project area. 

Page 69: 20100719 Weld Range CCP WE Edit PDF KCQA 2 Conceptual Closure Plan 2010.pdf · Weld Range Iron Ore Project Conceptual Closure Plan July 2010 ii Document Status Approved for Issue

 

Weld Range Iron Ore Project 

Conceptual Closure Plan 

 

July 2010    

     

55 

• Topsoil will be spread and then ripped to bring up some rock from the layer immediately under the topsoil.  This will help to prevent erosion by “rock armouring” the face of the dump.  Loose dead vegetation,  tree branches etc, will  then be spread over  this surface  to  further enhance erosion control by preventing rainfall runoff from concentrating in one area, slowing the flow of runoff down the face of the dump and promoting the dispersion of runoff across the whole face. 

• Local provenance seeds will be collected from the impacted project area prior to disturbance.  Local provenance seeds will be stored separately and used in their respective local areas during rehabilitation. 

• Reporting  procedures will  be  established  to  ensure  that  results  of  all  trials  and  actions  are properly recorded, referenced, and available for other personnel and for long‐term reference. 

• Rehabilitation  monitoring  will  be  carried  out  until  revegetation  meets  the  designated completion  criteria  and  is  signed  off  by  the DMP.    In  response  to monitoring  results,  infill planting and weed control will be implemented as necessary. 

• Visual  inspection of  rehabilitated areas will be  carried out  following  rain  to ensure  that any potential erosion issues are identified early and can be repaired before they become severe. 

• Photographic  monitoring  will  be  undertaken.    This  will  consist  of  establishing  fixed photographic points (adequately marked with a long lasting item such as metal star picket) and taking photographs from each of these points. 

• Quantitative  assessment  of  the  progress  of  revegetation  will  be  undertaken.    Replicate monitoring quadrats  (20 m  x 20 m) will be established and  total plant  species  richness and plant cover index will be recorded. 

 

 

Page 70: 20100719 Weld Range CCP WE Edit PDF KCQA 2 Conceptual Closure Plan 2010.pdf · Weld Range Iron Ore Project Conceptual Closure Plan July 2010 ii Document Status Approved for Issue

 

Weld Range Iron Ore Project 

Conceptual Closure Plan 

 

July 2010    

     

56 

This page has been left blank intentionally. 

 

 

Page 71: 20100719 Weld Range CCP WE Edit PDF KCQA 2 Conceptual Closure Plan 2010.pdf · Weld Range Iron Ore Project Conceptual Closure Plan July 2010 ii Document Status Approved for Issue

 

Weld Range Iron Ore Project 

Conceptual Closure Plan 

 

July 2010    

     

57 

10 SPECIFIC CLOSURE STRATEGIES 

Where specific closure strategies are required, closure objectives, strategies and completion criteria have  been  developed  to  deal  with  these  aspects.    These  project  components  are  listed  in  the following section and they will be decommissioned and rehabilitated in accordance with Section 9 of this document.   

10.1 BEEBYN AND MADOONGA PIT CLOSURE 

Beebyn and Madoonga will be developed as conventional open cut mines.  The proposed operations at Weld Range are expected to have a disturbance footprint of about 4074 ha (40.7 km²), or 18% of the total area occupied by the Weld Range (approximately 22,500 ha (225 km2). 

The proposed pits and waste dumps will have a total footprint of 1811.5 ha and a strike length of 6 km.  The pits will have an anticipated combined production rate of 15 Mtpa, over an initial 11 years.  The two deposits are some 22 km apart, with ore from Madoonga and Beebyn planned to be primary crushed  and  hauled  via  road  train  to  the  CPF.    Both  deposits will  be mined  in  parallel  to  enable blending the higher Beebyn iron (Fe) grades with the lower Madoonga Fe grades as well as allowing more control of contaminant grades. 

The Beebyn and Madoonga deposits differ in several respects.  Madoonga, the western ore body, is the larger of the two deposits but has the lower Fe grade.  The deposit contains a broadly continuous BIF  horizon,  which  strikes  ENE  and  dips  steeply  (>70°).    The  iron mineralisation  is  complex  and contains semi‐continuous ore  lenses separated by thin units of  ‘waste’ material.    In some cases the ore lenses contain units of internal ‘waste’ material. 

The Beebyn  deposit  is  the  lower  tonnage  and  higher  Fe  grade of  the  two deposits.    This deposit contains three definable BIF units that are disrupted by N‐S striking sub‐vertical faults.  The BIF units are ENE‐striking and dip steeply (>70°) to the SSE. 

Both ore bodies are  long (≥3 km) and relatively narrow (5 ‐30 m).   The deposits are steeply dipping (almost vertical) and, as a result of the presence of contaminants, do not  lend themselves easily to bulk mining. 

At year 11, on completion of mining, approximately 100 Mm3 of the mine deposit will be left open.  It is anticipated this void will fill up with water to form pit lakes.   

The water  level  in the pit  lakes of Beebyn will rise up to 480 m RL while in Madoonga the pit water level will reach 430 m RL after 25 years post mining.  The simulation indicates a rapid recovery of the water table in the first five years, followed by a slow down of the recovery with time. 

The concentration of solutes within the pit lakes will increase over time due to high evaporation and low precipitation in the area. 

SMC will commit to management of open pits, and pit  lakes,  in accordance with the Department of Industry and Resources Environmental Notes on Mining (Sept 2009) ‐ Care of Maintenance.  In which open pits will be managed with appropriate bunding and surface water drainage structures.   

In order to minimise inadvertent public and fauna access to the pit lakes SMC will construct a surface water  drainage  trench  and  abandonment  bund  surrounding  the  pits  (Figure10.1).    The  diversion trench will be no deeper than 2 m with a gentle slope away from the pit and a steeper slope on the 

Page 72: 20100719 Weld Range CCP WE Edit PDF KCQA 2 Conceptual Closure Plan 2010.pdf · Weld Range Iron Ore Project Conceptual Closure Plan July 2010 ii Document Status Approved for Issue

 

Weld Range Iron Ore Project 

Conceptual Closure Plan 

 

July 2010    

     

58 

pit slide.  This design will ensure animals leave the trench area away from the pit.  The abandonment bund will be approximately 2 m high. 

Pit Lakes 

SMC will commit to the following management strategies in relation to pit lakes: 

• Consideration of the backfilling of mined out areas.  

• Management of the water quality within the pit lakes. 

• Management of potential leaching from the pit shell, including monitoring bores.  

SMC will commit to the management of open pits and pit lakes, in accordance with the Department of  Industry and Resources Environmental Notes on Mining  (Sept 2009)  ‐ Care of Maintenance.    In which open pits will be managed with appropriate bunding and surface water drainage structures, Figure 10.1.   

The  consideration  of  backfilling  pits  has  been  considered;  while  the  results  from  modelling demonstrate that backfilling concurrently with mining is feasible, however only limited quantities of waste are able to be stowed  in‐pit, with the major proportion of the waste being stored in external waste dumps.   

Monitoring of  the groundwater aquifer  surrounding  the pit will be monitored under  the  following periods  as  detailed  in  Table  10.1.    Parameters measured will  include  salinity,  pH  and  leachate  of contaminates.  Monitoring will cease when two consecutive results indicate a stable and acceptable environment similar to that identified prior to the commencement of mining operations as defined in the Ground Water Operating Strategy.   

Table 10.1 – Monitoring for sailinty, pH and leaching of contaminates for pit lakes 

Monitoring Timescale  Period post closure 

Yearly  Closure (0 years) to 4 years 

Every 5 years  Year 5 to 25 years  

 

 

Page 73: 20100719 Weld Range CCP WE Edit PDF KCQA 2 Conceptual Closure Plan 2010.pdf · Weld Range Iron Ore Project Conceptual Closure Plan July 2010 ii Document Status Approved for Issue

 

Weld Range Iron Ore Project 

Conceptual Closure Plan 

 

July 2010    

     

59 

Figure 10.1 – Indicative Cross Section of Surfacewater Diversion Trench and Abandument Bund 

 

 

 

Page 74: 20100719 Weld Range CCP WE Edit PDF KCQA 2 Conceptual Closure Plan 2010.pdf · Weld Range Iron Ore Project Conceptual Closure Plan July 2010 ii Document Status Approved for Issue

 

Weld Range Iron Ore Project 

Conceptual Closure Plan 

 

July 2010    

     

60 

10.2 WASTE ROCK DUMPS 

There  are  no  pre‐existing  overburden  stockpiles  at  the  Project.    Five  waste  rock  dumps  will  be developed (Figure 10.2), three at the Beebyn pit and two at the Madoonga pit.   

The Project is expected to produce at least 273 Mt of waste rock from Madoonga pit and at least 450 Mt from the Beebyn pit.  A small proportion of this waste rock will be PAF, with estimated tonnages of PAF material of 30 Mt at Madoonga (11%) and 4.5 Mt at Beebyn (1%). 

The parameters used for the waste dump design for both the Beebyn and Madoonga areas are listed below and illustrated in Figure 10.2: 

Berm width     10 m    Bench height     10 m 

Overall slope    20 °    Batter slope     30 ° 

Swell       0 %    Tolerance     10 % 

Road width (dual‐lane)  30 m 

The size of the waste dumps has been estimated  from assumed swell factors applied to the  in situ volume mined.  Haulage distances from the open pit designs and the dump designs will be minimised by locating the pit ramps of the pit designs appropriately. 

Beebyn currently has three planned waste dumps.  These include a large dump servicing the Beebyn pit which has been configured so that the dump ramps are aligned with the south wall pit ramps to provide  short waste  haulage.    Smaller waste  dumps  are  planned  to  service  the  Beebyn  pit.    The Beebyn  pit  waste  dumping  area  is  to  the  south  of  the  pit  area  to  minimise  interaction  with infrastructure such as the crushing and screening processes and the rail loop located to the north of the Beebyn pit.   The Beebyn West waste dump  is  located  to  the north of  the pit.   This has been designed  large enough  to accommodate  the waste  from  the eastern pod.   A separate  ramp which aligns with  the pod’s exit  is also allocated  to minimise  the haul distance.   As  the dump  location  is away from the main Beebyn infrastructure, the location of the waste dump is less critical. 

Madoonga’s waste dump area  is planned at the north side of the pit to avoid environmental  issues related to protected fauna located in the valley to the south of the pit.  The Madoonga waste dump is designed  to provide a  large  storage capacity  in  the vicinity of  the Stage 1 pit area as  this cut‐back produces the largest amount of waste.  

Placement Criteria 

The  following  environmental  criteria  were  considered  in  the  planning  of  overburden  stockpile locations: 

• Alignment with natural topographic landforms in the area. 

• Use of existing previously disturbed agricultural areas. 

• Limiting of interference with natural drainage lines. 

• Avoidance of sensitive flora and/or fauna habitat. 

• Avoidance of indigenous heritage sites. 

Page 75: 20100719 Weld Range CCP WE Edit PDF KCQA 2 Conceptual Closure Plan 2010.pdf · Weld Range Iron Ore Project Conceptual Closure Plan July 2010 ii Document Status Approved for Issue

 

Weld Range Iron Ore Project 

Conceptual Closure Plan 

 

July 2010    

     

61 

10.2.1 Closure Objectives 

The closure objectives are to ensure: 

• Rehabilitation achieves a safe, stable, non‐polluting landform consistent with the surrounding landscape. 

• Revegetation  is  consistent  with  the  surrounding  flora  and  land  use,  or  other  land  use  as agreed. 

• There  is a  sufficient cover of vegetation established  to minimise erosion and  to  fulfil agreed rehabilitation commitments. 

• The final landform conforms to design criteria and is resistant to erosive events. 

• To limit contact between PAF and percolating water. 

• To minimise  the  likelihood  that dump effluents will exert a detrimental effect on  local water quality,  for  example,  by  capturing  and  managing  dump  drainage  appropriately,  and  if practicable, locating the PAF material away from existing water courses ands flood areas. 

 

 

Page 76: 20100719 Weld Range CCP WE Edit PDF KCQA 2 Conceptual Closure Plan 2010.pdf · Weld Range Iron Ore Project Conceptual Closure Plan July 2010 ii Document Status Approved for Issue

 

Weld Range Iron Ore Project 

Conceptual Closure Plan 

 

July 2010    

     

62 

Figure 10.2 – Cross Section of the Proposed Waste Dump Design 

 

Page 77: 20100719 Weld Range CCP WE Edit PDF KCQA 2 Conceptual Closure Plan 2010.pdf · Weld Range Iron Ore Project Conceptual Closure Plan July 2010 ii Document Status Approved for Issue

 

Weld Range Iron Ore Project 

Conceptual Closure Plan 

 

July 2010    

     

63 

10.3 OVERBURDEN STOCKPILES 

Overburden  stockpiles  will  require  earthworks  and  subsequent  revegetation  through  seeding  or planting to ensure they are stable and blend into the surrounding landscape.  

Design 

The final form of new overburden stockpiles will conform to the design criteria outlined in the DMP Guideline for Mining in Arid Environment (2007).   

Construction will utilise a bottom up methodology incorporating progressive rehabilitation.  Outside faces of  stockpiles are  to be  constructed  initially and  rehabilitated upon  completion of each  level.  The methodologies  outlined  in  Guidelines  for Mining  in  Arid  Environments  (DoIR,  2007)  will  be applied to the construction of stockpiles. 

PAF 

To meet the waste rock objectives the following management strategy has been proposed:  

The base layer of the dump (A) will be constructed of NAF material (Figure 10.3).  The purpose of this layer will be to raise the PAF material above the original ground and prevent direct contact of PAF material with any water flowing at the interface of the original ground and the dump. 

Figure 10.3 – PAF Waste Rock Surrounded by NAF Waste Rock 

 

The minimum  thickness  of  the  base  layer will  be  determined  based  on  information  such  as  the saturated and unsaturated hydraulic properties of  the base  layer, estimates of  rates of  infiltration into the waste from rainfall, natural seeps and flood levels. 

During construction there is the potential for areas of PAF rock to be uncovered and exposed to rain.  These exposure times will be minimised as far as possible through scheduling mining or dumping and planning  the  location of  the  PAF material  in  the dump.    In order  to  reduce  the  load of oxidation products that could be released from PAF material during construction, a  layer of  low permeability NAF material (B) will be placed over the NAF base layer and under the PAF rock (C).  The purpose of layer B will be to  limit the rate of downward movement of water and therefore reduce the rate of 

Page 78: 20100719 Weld Range CCP WE Edit PDF KCQA 2 Conceptual Closure Plan 2010.pdf · Weld Range Iron Ore Project Conceptual Closure Plan July 2010 ii Document Status Approved for Issue

 

Weld Range Iron Ore Project 

Conceptual Closure Plan 

 

July 2010    

     

64 

release of any AMD produced.    It  is  likely  that a portion of water moving downward  through  the dump will  exit  the dump  at  the base  and  continue  to move downward  towards  the  groundwater table. 

PAF material will be covered on both of the side slopes (batters) and top surface with NAF material.  A  cover  (D) designed  to  limit  the  infiltration of  rain will be  constructed on  the  top  surface of  the dump.    It  will  extend  laterally  beyond  the  PAF material.    The  final  design  of  the  cover  will  be determined  based  on  the  annual  rainfall,  rainfall  intensity  distribution  and  potential evapotranspiration.    The design would  likely  include  features  to promote  runoff  from  the  surface and/or promote retention of infiltrating water near the surface for subsequent evapotranspiration.  

Engineering design of the waste dump will incorporate the following: 

• appropriate slope angles; 

• berms and drains; 

• batters resistant to erosion to maintain the NAF layer; and 

• cut off drains to prevent runoff from undisturbed lands contacting the dumps and to separate dump  run‐off  from water  running off undisturbed  land.   Dump  run‐off will be channelled  to settling ponds to store sediment. 

Topsoil 

Topsoil will be stripped  in advance of the overburden stockpile face and stored.   If possible, topsoil will  be  re‐spread  directly  on  overburden  stockpiles.    Stripped  topsoil  and  subsoil  that  cannot  be directly re‐spread will be stockpiled separately according to the methodologies outlined in Guidelines for Mining in Arid Environments (DoIR, 2007).  

Topsoil stockpiles will be located within the marked overburden stockpile disturbance areas. 

The existing environment within the project areas naturally consists of shallow depths of topsoil and subsoil.   Overburden  stockpiles will be  re‐spread with  topsoil  and  subsoil  to equivalent depths  as those occurring  in undisturbed areas.   To ensure  sufficient volumes of subsoil are available  for  re‐spread on overburden stockpiles, the following measures will be undertaken: 

• Topsoil will be stripped and stored separately at designated topsoil stockpile locations. 

• Weathered material  retrieved  from  pit  excavations will  be  stored  separately  at  designated subsoil stockpile locations. 

• Topsoil will be stripped in advance of overburden stockpile toes over the anticipated stockpile footprints and stored separately at designated topsoil stockpile locations. 

• Subsoil will be stripped in advance of overburden stockpile toes over the anticipated stockpile footprints and stored separately at designated subsoil stockpile locations. 

Where the availability of topsoil and subsoil is less than the quantity indicated for specific sections of the Project, SMC will develop other options  for sourcing  this material,  from approved borrow pits, other disturbed areas or from suitable pit overburden material. 

An assumption with regard to the estimate of subsoil requirement for areas to be rehabilitated is that the surface area needed will be 115% of that of the original area disturbed, due to the convex shape of the final waste dump design. 

Page 79: 20100719 Weld Range CCP WE Edit PDF KCQA 2 Conceptual Closure Plan 2010.pdf · Weld Range Iron Ore Project Conceptual Closure Plan July 2010 ii Document Status Approved for Issue

 

Weld Range Iron Ore Project 

Conceptual Closure Plan 

 

July 2010    

     

65 

Topsoil  will  be  spread  over  a  layer  of  subsoil.    Topsoil  will  be  spread  preferentially  over  the overburden stockpile top level and benches where vegetation establishment is more likely.  

Erosion Control 

The overburden stockpiles will be designed to encourage  infiltration and drainage of surface water, minimising surface flow.  The final slope profile of the stockpiles will conform to the following design criteria: 

• Overburden stockpile toe does not extend into the area surrounding the pit where collapse is possible. 

• Bank slopes are restricted to a maximum angle of 20°. 

• Berms are placed every 10 m of vertical height. 

• Berms are sloped into the stockpile at 5° angle. 

• Berms have cross bunds every 30 m of length to reduce water flow along the berm. 

• Peak of overburden stockpiles does not exceed the height of surrounding natural land forms. 

• A crestal bund shall be installed around the top of the dump and incorporated into the slope.  This  bund  has  the  purpose  of  retaining water  from  rainfall  on  top of  the dump  to prevent further runoff down the face of the dump and therefore reduces the potential for erosion.   

Revegetation 

Seeding programs will be conducted prior to the wet season (May – August) on overburden stockpile surfaces that have been respread with top/subsoil.  Provenance seed collection is to occur during the flowering season (generally after spring) one year prior to planned rehabilitation. 

Where possible any cleared vegetation and  litter will be  stockpiled  for  respreading on areas  to be rehabilitated. 

Flora  species  will  be  chosen  for  rehabilitation  based  on  vegetation  communities  identified  in botanical surveys conducted over the project area.  Principles of succession will be incorporated into species  selection,  and  rehabilitation  will  also  include  efforts  to  re‐establish  Priority  Flora  taxa.  Discussions with the DEC will be carried out to ensure that appropriate seed mixes are used over the areas  to be  rehabilitated.   Those  taxa  that  can be propagated easily would also be  suitable  to be replanted as tube stock and could be propagated in advance.   

Revegetation  targets will be set at a density, complexity and diversity of baseline data  to  replicate surrounding  vegetation,  in  consultation  with  DEC.    Completion  criteria  will  be  developed  in consultation with DEC to determine when the rehabilitation can be considered self sustaining. 

10.3.1 Completion Criteria 

• Overburden stockpiles conform to design criteria. 

• Stockpiles meet stability, soil and vegetation criteria as determined through consultation with DEC. 

 

Page 80: 20100719 Weld Range CCP WE Edit PDF KCQA 2 Conceptual Closure Plan 2010.pdf · Weld Range Iron Ore Project Conceptual Closure Plan July 2010 ii Document Status Approved for Issue

 

Weld Range Iron Ore Project 

Conceptual Closure Plan 

 

July 2010    

     

66 

10.4 BORROW PITS AND HAUL ROADS 

At the completion of mining at Weld Range, access roads that have not been rehabilitated as part of the  progressive  rehabilitation  programmes will  be  rehabilitated  (including  removal  of  portions  of road  embankment where  necessary)  to  blend  in with  surrounding  topography.   Where  necessary road  surfaces will be  reshaped  and  ripped  to  allow  free drainage  and minimise  interference with natural surface flows. 

Borrow pits will be progressively  rehabilitated during  the operational  life of  the mine, or  following closure of  the pit.   Sides of  the borrow pits will be battered  to a  slope equal  to or  less  than 20°. Where  required, culvert diversion drains and upslope windrows will be used  to divert surface  flow from entering pits and contributing to waterlogging or erosion.  

Borrow pits will then be ripped and spread with topsoil as per section 9.7. 

10.4.1 Borrow Pits 

The closure objectives are to ensure: 

• The profile of final borrow pits are safe, stable, blend into the surrounding landscape and are not prone to erosion. 

• Borrow pits are contour ripped and spread with topsoil. 

• Pits are free draining. 

• Vegetation is comparable to immediate surrounds in species composition and cover. 

10.4.1.1 Completion Criteria 

• Borrow pit slopes are no greater than 20°. 

• Contour ripping or scarifying has been conducted. 

• Vegetation is comparable to immediate surrounds in species composition and cover. 

10.4.2 Haul Roads 

It is anticipated that haul roads will be utilised for post‐closure land use.  There are several possible outcomes for closure of the haul roads: 

• Haul roads remain as a permanent access road for post‐closure land use. 

• Haul  roads  are  decommissioned  –  the  rehabilitation  procedures  outlined  in  this  conceptual closure plan will be followed. 

• Haul roads remain with a reduced width; roads will be narrowed with rehabilitation on cleared shoulders conducted in accordance with this conceptual closure plan. 

Page 81: 20100719 Weld Range CCP WE Edit PDF KCQA 2 Conceptual Closure Plan 2010.pdf · Weld Range Iron Ore Project Conceptual Closure Plan July 2010 ii Document Status Approved for Issue

 

Weld Range Iron Ore Project 

Conceptual Closure Plan 

 

July 2010    

     

67 

10.5 DEWATERING BOREFIELDS AND PIPELINES 

Following  mine  closure,  all  infrastructure  associated  with  the  pit  dewatering  bores  (including powerlines, bores and pipeline) will be removed unless otherwise agreed. 

The location of water supply infrastructure is yet to be confirmed, but is likely to include: 

• pumps & gen‐sets; 

• delivery pipelines; 

• turkeys‐nest(s); 

• storage tanks; 

• distribution pipelines; and 

• water treatment plant. 

The Madoonga and Beebyn pits are to be serviced by  individual bore fields with associated storage and distribution infrastructure. 

Water for construction purposes will be provided via construction bores supplying a turkeys‐nest and distributed by road tankers. 

Water  for  operational  and  fire  protection  purposes  will  be  provided  via  production  bore  fields feeding into storage tanks, where it will be distributed via pipelines to the appropriate plant areas. 

Rehabilitation works to be undertaken include: 

• Collapse or filling of boreholes. 

• Concrete footings and slabs associated with pumping equipment will be broken up and placed within  areas  of  general  backfill  or  buried  in‐situ  to  a minimum  depth  of  1.5 m  below  the rehabilitated surface. 

General surface treatment and rehabilitation works will then be implemented as described in Section 9.7. 

10.6 POWER GENERATING AND SUPPLY INFRASTRUCTURE 

The  power  supply  to Weld  Range  is  via  diesel  powered  generators with  separate  power  stations proposed  at  each  site  (central processing  facility, Beebyn mine, Madoonga mine,  accommodation village and the airstrip). 

The  following  generation  and  transmission  related  structures  on  the  Project  will  require decommissioning: 

• diesel generators and associated plant; 

• substations; and 

• overhead transmission lines. 

Page 82: 20100719 Weld Range CCP WE Edit PDF KCQA 2 Conceptual Closure Plan 2010.pdf · Weld Range Iron Ore Project Conceptual Closure Plan July 2010 ii Document Status Approved for Issue

 

Weld Range Iron Ore Project 

Conceptual Closure Plan 

 

July 2010    

     

68 

At  the conclusion of mining at Weld Range, all power generating and  supply  infrastructure will be decommissioned and removed from site unless otherwise agreed.   This will  include the breaking up of concrete  footings and slabs for placement within areas of general backfill or burial  in‐situ below the rehabilitated surface (to a minimum depth of 1.5 m) 

General surface treatment and rehabilitation works will then be implemented as described in Section 9.7 

10.7 ACCOMMODATION VILLAGE AND AMENITIES 

The  Weld  Range  accommodation  village  and  associated  amenities  will  be  decommissioned  and removed from site at the completion of mining unless otherwise agreed. 

Decommissioning works to be undertaken include: 

• Removal of accommodation units. • Removal  (i.e.  break  up)  of  concrete  footings  and  slabs  and  placement within  the  areas  of 

general backfill or in‐situ burial to a minimum depth of 1.5 m below the rehabilitated surface. 

General surface treatment and rehabilitation works will then be implemented as described in Section 9.7. 

10.7.1 Sewerage 

Sewerage  plants  will  be  designed  as  modular,  portable  units  which  will  be  removed  on decommissioning.    Liquid output  from  the  sewage plants will be Class A water, while  solid output from the plant will be removed by suitably qualified waste contractors. 

10.7.2 Access Roads and Aerodrome 

At the completion of mining at Weld Range, access roads that have not been rehabilitated as part of the progressive rehabilitation programmes will be re‐profiled (including removal of portions of road embankment where  necessary)  to  blend  in with  surrounding  topography.   Where  necessary  road surfaces will be profiles to allow free drainage and minimise interference with surface flows. 

The  future  of  the  Weld  Range  aerodrome  following  closure  of  the  Weld  Range  Mine  will  be determined in consultation with the administering authority and other relevant stakeholders. 

General surface treatment and rehabilitation works will then be implemented as described in Section 9.7. 

10.7.3 Fuel and Explosives Facilities 

Fuel and explosives storage facilities will require decommissioning, these include:  

• bulk hydrocarbon  storage areas:  total of 3  x 1 ML diesel  fuel  tank(s)  stored adjacent  to  the servicing workshops and managed in accordance with Australian Standard 1940 – The Storage and Handling of Flammable and Combustible Liquids (AS 1940‐1993); 

• explosives storage facility; 

• minor  storage  areas:  servicing work  shops, may  contain oil drums  and other materials may need to be removed and disposed appropriately; and 

• explosives magazines may need to be demobilised. 

General  surface  treatment  and  rehabilitation  works  will  then  be  implemented  as  described  in Sections 9.7.    

Page 83: 20100719 Weld Range CCP WE Edit PDF KCQA 2 Conceptual Closure Plan 2010.pdf · Weld Range Iron Ore Project Conceptual Closure Plan July 2010 ii Document Status Approved for Issue

 

Weld Range Iron Ore Project 

Conceptual Closure Plan 

 

July 2010    

     

69 

11 MONITORING AND MAINTENANCE 

11.1 MONITORING, REPORTING AND RECORD KEEPING 

The  implementation  of  a  monitoring  programme  is  crucial  in  recording  the  success  or otherwise  of  the  mine  closure,  as  well  as  validating  agreed  criteria  for  relinquishment.  Monitoring will address the following areas: 

• biological (flora, fauna and SRE); 

• kinetic testing; 

• surface and groundwater; 

• remediation of contaminated sites and acid rock drainage issues; 

• public safety;  

• landform stability; and 

• revegetation status. 

Post‐closure  monitoring  programs  will  be  developed  in  consultation  with  appropriate regulatory  agencies,  and  will  aim  to  inform  the  development  of  agreed  actions  if  it  is determined  through  monitoring  that  closure  completion  criteria  are  not  being  met.  Monitoring will be undertaken by SMC until the completion criteria have been finalised. 

Table 11.1 describes the proposed timing of closure monitoring for the Weld Range project. 

Table 11.1 – Timing of Closure Monitoring 

Aspect  Monitoring  Criteria  Timing 

Public Safety 

Engineering assessment of stability of final landforms. 

Abandonment bunds in place and adequate signage. 

Agreed closure plan  criteria. 

Safety Bund Walls around Abandoned Open Pit Mines (DME, 1997) 

On closure 

Overburden Stockpiles 

Engineering assessment of stability of final landforms and erosion. 

Agreed closure plan  design criteria. 

On closure then every 6 months. 

Contamination  Contaminated sites assessment. Contaminated Sites Act 2003. 

On closure then every 6 months after remediation if required. 

Acid Drainage and Mineral Leaching 

Assessment of waste rock dumps for acidity and mineral leaching. 

National Handbook “Managing acid and metalliferous drainage” 

On closure then every yea or until completion criteria met. 

Water Ground and surface water assessment 

Groundwater – TDS, SWL, component analysis meet 

On closure then annually for 3 years or until 

Page 84: 20100719 Weld Range CCP WE Edit PDF KCQA 2 Conceptual Closure Plan 2010.pdf · Weld Range Iron Ore Project Conceptual Closure Plan July 2010 ii Document Status Approved for Issue

 

Weld Range Iron Ore Project 

Conceptual Closure Plan 

 

July 2010    

     

70 

Aspect  Monitoring  Criteria  Timing 

requirements. 

Surface – TSS, pH, EC meet requirements. 

Drainage – diversion drains will remain in tact after closure.  

completion criteria is satisfied. 

Rehabilitation Earthworks 

Confirmation that earth works have been completed at all sites in accordance with specifications 

Agreed closure plan design criteria. 

12 months 

Vegetation 

Visual (photographic) assessment of rehabilitated areas. Includes assessment of weed species, vegetation establishment and cover, and erosion. 

Agreed closure plan criteria. 

18 months (6 months after seeding).  

Fauna / SRE  Feral Animal monitoring.   Agreed closure plan criteria.  

 

Maintenance Implement maintenance procedures if required. 

Agreed closure plan maintenance strategies. 

12 months. 

Annually as required until completion criteria is satisfied. 

11.2 MAINTENANCE 

Based  on  monitoring  assessments,  periodic  maintenance  may  be  required  to  ensure rehabilitation success.   Where closure criteria have not been met, remedial action may be required.   Table 11.2  identifies project aspects and actions that will be  implemented  in the event of  incomplete or unsuccessful rehabilitation.   Regular maintenance and  identification of  rehabilitation  problems  at  an  early  stage  will  contribute  to  successful  environmental outcomes and mine closure. 

Figure 11.1 – Maintenance Actions 

Aspect  Possible Maintenance Action 

Contamination and ADML 

- Bioremediation. 

- Transportation for treatment of contaminated soils. 

- Implementation of ADML control measures. 

Vegetation - Reseeding of rehabilitation areas. 

- Removal/spraying of weeds. 

Topsoil viability - Additional ripping/aeration. 

- Application of fertilizers.  

Introduced Fauna - Repairs to stock fencing. 

- Erection of new fencing.  

Page 85: 20100719 Weld Range CCP WE Edit PDF KCQA 2 Conceptual Closure Plan 2010.pdf · Weld Range Iron Ore Project Conceptual Closure Plan July 2010 ii Document Status Approved for Issue

 

Weld Range Iron Ore Project 

Conceptual Closure Plan 

 

July 2010    

     

71 

12 CONTINGENCY PLANNING 

In the event of a temporary suspension of mine operations the Mines Safety and Inspection Regulations  1995  will  be  utilised  to  guide  development  of  a  suspension  plan.    The Department of Mines and Petroleum (DMP) will be notified of the nature of the suspension and measures in place that will limit impact to the environment and ensure health and safety requirements are met.  

The  suspension  plan will  not  consist  of  a  full  rehabilitation  and  closure  strategy  but will incorporate  interim measures.    In  the event that a decision to decommission operations  is made during a suspension period, closure strategies outlined in this Conceptual Closure Plan will be implemented in full in consultation with the relevant authorities. 

As a minimum the suspension plan will include: 

• Maintenance  of  drainage  structures  to  limit  erosion  events  and  sedimentation  of surface water. 

• Removal of  chemicals, hydrocarbons  and other hazardous  substances. This  includes assessment  of  containment  facilities  and  bunds  to  ensure  contamination  is  not possible. 

• Provision of maintenance staff / caretakers to monitor mine conditions. 

• Ensure adequate on‐site facilities for any staff remaining at the operations. 

• Revision  of  reporting  procedures  and  consultation  with  regulators  regarding mine suspension. 

• Removal of domestic and industrial waste products, and waste facilities.   

• Provision  of  adequate  signage,  safety  measures  and  security  to  ensure  no  un‐authorized access to the mine site. 

12.1 WALKAWAY 

In the situation of sudden (unplanned) closure, a decommissioning plan will be immediately prepared and implemented with input from the Conceptual Closure Plan, taking into account the site’s non‐operational status.  Where provision accounts are inadequate to fund the full closure  requirements,  funds will  be  provided  from  other  company  sources.    Figure  12.1 illustrates the sudden closure strategy. 

Page 86: 20100719 Weld Range CCP WE Edit PDF KCQA 2 Conceptual Closure Plan 2010.pdf · Weld Range Iron Ore Project Conceptual Closure Plan July 2010 ii Document Status Approved for Issue

 

Weld Range Iron Ore Project 

Conceptual Closure Plan 

 

July 2010    

     

72 

Figure 12.1 – Sudden Closure Strategy 

 

 

 

 

Page 87: 20100719 Weld Range CCP WE Edit PDF KCQA 2 Conceptual Closure Plan 2010.pdf · Weld Range Iron Ore Project Conceptual Closure Plan July 2010 ii Document Status Approved for Issue

 

Weld Range Iron Ore Project 

Conceptual Closure Plan 

 

July 2010    

     

73 

12.2 TEMPORARY CLOSURE 

Mining  activity may  cease  and  shut  down  on  a  temporary  basis,  with  the  assumption  that  the operation will recommence in the near future.  A decommissioning plan will be immediately prepared and implemented with input from the Conceptual Closure Plan, taking into account the potential for future  operations.    The  Conceptual  Closure  Plan  will  be  reviewed,  as  it may  be  required  to  be implemented if circumstances remain adverse to reopening the operation.  

Rehabilitation  will  be  undertaken  on  all  disturbed  areas,  where  possible  and  economically practicable,  and  site  remediation  works  will  be  undertaken  to  prevent  potential  off‐site contamination.  The site will be placed under care and maintenance until such time as the operation recommences or it is closed indefinitely.  Figure 12.2 illustrates a temporary closure strategy. 

12.3 RELINQUISHMENT 

The unconditional performance bond(s) lodged with the DMP will be retired when the rehabilitation has met all completion criteria and standards set out  in approval documents, annual environmental reports  and  decommissioning  plans.    Once  the  rehabilitated  area  is  safe,  stable,  erosion  is comparable  to  the  surrounding  areas  and  the  biological  system  is  sustainable  under  a  range  of seasonal conditions representative of that climate (DMP, 2008), the management and maintenance of the site will rest with the subsequent owners or the State. 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Page 88: 20100719 Weld Range CCP WE Edit PDF KCQA 2 Conceptual Closure Plan 2010.pdf · Weld Range Iron Ore Project Conceptual Closure Plan July 2010 ii Document Status Approved for Issue

 

Weld Range Iron Ore Project 

Conceptual Closure Plan 

 

July 2010    

     

74 

 

Figure 12.2 – Temporay Closure Strategy 

 

Page 89: 20100719 Weld Range CCP WE Edit PDF KCQA 2 Conceptual Closure Plan 2010.pdf · Weld Range Iron Ore Project Conceptual Closure Plan July 2010 ii Document Status Approved for Issue

 

Weld Range Iron Ore Project 

Conceptual Closure Plan 

 

July 2010    

     

75 

13 REVIEW AND REVISION 

The Conceptual Closure Plan will be reviewed throughout the life of the project and revised into a full Closure Plan at least two years prior to the planned closure of the Weld Range Project. 

 

Page 90: 20100719 Weld Range CCP WE Edit PDF KCQA 2 Conceptual Closure Plan 2010.pdf · Weld Range Iron Ore Project Conceptual Closure Plan July 2010 ii Document Status Approved for Issue

 

Weld Range Iron Ore Project 

Conceptual Closure Plan 

 

July 2010    

     

76 

This page has been left blank intentionally.  

 

Page 91: 20100719 Weld Range CCP WE Edit PDF KCQA 2 Conceptual Closure Plan 2010.pdf · Weld Range Iron Ore Project Conceptual Closure Plan July 2010 ii Document Status Approved for Issue

 

Weld Range Iron Ore Project 

Conceptual Closure Plan 

 

July 2010    

     

77 

14 REFERENCES 

ANZMEC/MCA  (2000), Strategic Framework  for Mine Closure. Australian and New Zealand Minerals and Energy Council and Minerals Council of Australia.  Canberra, ACT  

Department  of  Industry  and  Resources  (2006)  Mine  Closure  and  Completion:  Leading  Practice Sustainable Development Program for the Mining Industry. Commonwealth Government. 

Department of Industry and Resources (1997) Safety Bund Walls Around Abandoned Open Pit Mines. Western Australian Government. 

Department  of  Industry  and  Resources  (2006) Mine  Rehabilitation:  Leading  Practice  Sustainable Development Program for the Mining Industry. Western Australian Government. 

Thorne, A. M., and Tyler, I. M. (1997) Roy Hill (2nd Edition): 1:250,000 Geological Series Explanatory Notes, 22p. 

 

Page 92: 20100719 Weld Range CCP WE Edit PDF KCQA 2 Conceptual Closure Plan 2010.pdf · Weld Range Iron Ore Project Conceptual Closure Plan July 2010 ii Document Status Approved for Issue

 

Weld Range Iron Ore Project 

Conceptual Closure Plan 

 

July 2010    

     

78 

This page has been left blank intentionally.