Agenda
Project Mission Statement and Critical Success Factors
Overall Status of Project
Process Task and Funding Tools Update
Data Collection Task Update
GIS Task Update
Project Management Tools and Software Integration
Participation at Upcoming Conferences
Discussion and Wrap-up
Project Mission Statement
•Develop technology tools to help identify, prioritize, manage, track and
accelerate water, wastewater, and stormwater projects in a
cost-effective and efficient manner throughout West Virginia.
2. Identify appropriate data to be collected and from whom, and collect it in a timely manner.
3. Develop user-friendly technology tools that support the screening, evaluation, prioritization and tracking of projects.
1. Develop an efficient and effective process to track and manage projects
Critical Success Factors
Process and Funding Tools Task
Data Collection Task
GIS and Project Management and Tracking Tools Tasks
GIS Task
Stakeholder Outreach
4. Maintain, update and distribute data.
5. Communicate purpose and educate on results.
OVERALL PROJECT UPDATE
Overall progress to date— Scope flowchart
Summary of top challenges— Changing the existing process — Locating “Served” and “Service” for 660 utilities that
are not in one place
— Integrating multiple software packages for WDA/IJDC to seamlessly use
— Locating servers for most efficient system operation
Jul ‘09
PHASE I – Assessment
Aug ‘09 Sep ‘09 Oct ‘09 Nov ‘09 Dec ‘09 Jan ‘10 Feb ‘10 Mar ‘10 Apr ‘10 May ‘10 Jun ‘10 Jul ‘10 Aug ‘10 Sep ‘10 Oct‘10 Nov ‘10 Dec ‘10
Wor
ksho
p #2
Wor
ksho
p #1
Wor
ksho
p #3
Wor
ksho
p #4
Wor
ksho
p #5
Wor
ksho
p #6
Wor
ksho
p #7
Wor
ksho
p #8
Wor
ksho
p #9
Develop Project Management Tools
Workshop #1 – Kickoff Workshop #2 – Identify data needsWorkshop #3 – GIS implementation and interfacesWorkshop #4 – GIS database designWorkshop #5 – Review funding procedures, dev. criteria/metricsWorkshop #6 – Dev. format/capabilities/interface for project prior. toolsWorkshop #7 – Demo project prioritization toolsWorkshop #8 – Project management process reviewWorkshop #9 – Demo project management tools
CPS Report
WEST VIRGINIA COMPREHENSIVE PLANNING STUDY A SCOPE FLOW CHART
Data Collection
Plan
GIS Impl.Plan
PHASE II – Geographic Information Systems (GIS)
Comprehensive Planning Study (CPS) Stakeholders
Develop GIS
Evaluate Collected Data, Identify Data Gaps and Develop Additional Data
Collect Stakeholder Data
West Virginia Water Development Authority / Infrastructure and Jobs Development Council
Evaluate/Develop Funding Process
Develop Project Funding Tools
Task 2 – Project Mgmt and Communications• Task 2.1 – Project and Financial Management
– PQM Workshop– Monthly Progress Meetings and Reports (IN PROGRESS)– Action Item Lists (IN PROGRESS)– Workshops (IN PROGRESS)– Billing and Financial Status Reports (IN PROGRESS)– Project Schedule (IN PROGRESS)
• Task 2.2 – Project Communication Protocol (COMPLETE)– WDA/IJDC/Stakeholders to CDM– CDM to WDA/IJDC– CDM to/from Stakeholders– Participants and/or CDM with Media– Public
Overview of Project Scope, Schedule and Upcoming Workshops
Task 3 – Phase I Assessment• Task 3.1 – Data Collection Plan• Task 3.2 – Collect Stakeholder Data (IN PROGRESS)• Task 3.3 – Evaluate Collected Data, Identify Gaps, Develop
additional data
Task 4 – Phase II GIS• Task 4.1 – Develop GIS Implementation Plan• Task 4.2 – Develop GIS
Task 5 – Proj. Prioritization and Management Tools
• Task 5.1 – Rev./Eval. Funding Approval and Mgmt Process• Task 5.2 – Develop Project Funding Tools• Task 5.3 – Develop Project Management Tools
Task 6 – CPS Report
Overview of Project Scope, Schedule and Upcoming Workshops
PROCESS TASK AND FUNDING TOOLS UPDATE
Review of Existing Process Approach
– Workshop to assess current process
– Comparison with other states– Summit with key stakeholders
and establish “Process Task Force”
– Ongoing meetings with stakeholders to move process change forward
Evaluate Existing Funding Process– Available funds not utilized– Many projects not well defined
when application submitted– Many communities not able to
initiate a viable project without assistance.
SLIDE 10
Propose Changes to Funding Process– Split process to consider planning/ preliminary
design projects and construction projects separately.
– Support project initiation– Include regional review– Determine appropriate mix of funds
0.10%0.30%
0.50%0.70%
0.90%1.10%
1.30%1.50%
1.70%1.90%
2.10%2.30%
2.50%2.70%
2.90%More
0
5
10
15
20
25
30
35
Annual Water Rates as % of MHI
Bin
Freq
uenc
y
Next Steps– Finalize process and implement– Design simple funding tool
PROCESS TASK AND FUNDING TOOLS UPDATE
DATA COLLECTION TASK UPDATE
1. Completing data collection for pilot (Harrison, Jefferson, Mingo, McDowell, Wyoming Counties)
2. Reviewing collected data for accuracy
3. Formatting data for GIS
4. Data collection is proceeding in other counties (for example, Hampshire, Hardy, Marshall, Lewis)
GIS Task Goals– Custom GIS Environment– Extensive GIS Database– Decision Support System– Project Ranking Tools– Project Management Tools
GIS TASK UPDATE
GIS Task Update– GIS Data Being Acquired (Data Collection
Plan)– GIS Implementation Plan
Complete– GIS Databases
Designed– GIS Environment
Specifications Development
GIS TASK UPDATE
The Next Few Months…– GIS Databases Being Developed– GIS Environment Specified (HW, SW,
Management)– MOUs for Data Sharing Developed– Implementation
Strategy Finalized– HW and SW
Purchases
GIS TASK UPDATE
PROJECT MGMT TOOLS & SOFTWARE INTEGRATION
Project Management Tools – to begin soon Software Integration – New Partners
DreamCatcher – web access and applications
ImageServ – Data Imaging and Warehouse EnAble – Financial/Funding Software Financial Accounting/Bookkeeping
Software Servers – WV Office of Technology
EnAble Financial Software
Accounting SoftwareCash Management
Commitments
Investments
Loans/Grants
DSS
Draws
Repayments
Available Funds
Bonds
DreamCatcherData Warehouse
WDA/IJDCWebsite
(single login)
ImageServData Warehouse
Workflow
Tracks Life of Application
WDA/IJDC/DWTRF
Document Proj Completion
- Reporting
- Technical Review
- Correspondence
- Draws
Tracks Life of Project
Funding Tools
Project Mgmt/Tracking Tools
Reports when App is Proj
GIS Tools
Cost Estimating Tools
A GIS
PMAccess
PublicAccess
Applicant &
ReviewerAccess
eForms and Images
Application
User RolesPM (Internal)
ReviewersAdministrators
ApplicantsPublic (no login req’d)
PublicAccess
SecureAccess
Participation at Upcoming Conferences
WV GIS ConferenceJune 7-10, 2010
WV Rural Water Association Annual Conf.September 12-15, 2010