    fischer FIRE STOP range

    fischer FIRE STOPSystemsProduct range for passive fire protection

    Peter Dengler, fischerwerke, Waldachtal

    S90-rated C30 cushionfire stop for cables

    T1 fire stop compound C2 mortar M3

    Fire stop types ID Fire stop constructions

    Cable fire stops C Numerical hierarchy with single-digit

    Pipe fire stops T numbers for LAR/LAR solutions andCombination pipe and cable fire stops M multi-digit numbers for tested and

    Grouting for fire dampers V approved systems.

    fischer FIRE STOP systems

    In early 2007 fischerwerke launched a newproduct range for passive fire protection.The fischer FIRE STOP products offercomprehensive fire protection solutions forbuilding service installations, therebycomplementing the SaMontec and fixingsystem product lines. As a full-rangesupplier, fischer now offers a completeproduct assortment with fire approvals.

  • 8/7/2019 2009-connectit-02_en

    2/4

    9FIRE STOP

    Construction facilities rely on building ser-vice systems with the associated piping,ductwork and cable ways for their properperformance. The service distribution sys-tems require a host of wall and floor pene-trations, ideally through suitably designedopenings. Fire-rated walls and floors mustbe resealed to ensure the integrity of thefire barrier or compartment. Fire stop sys-tems, whose purpose is to provide an effec-tive barrier to the spread of fire, represent agood-practice solution to these require-ments. As a passive fire precaution, theyreduce or minimise the hazards posed byfire and smoke by ensuring local fire con-tainment.

    Fire stop systems for building service elementsThe installations required for the distribu-tion of services within buildings include thepiping, ductwork, conduits and cable ways

    of the power, heating, sanitary, refrigera-tion, ventilation and air-conditioning sys-tems. The building services elements maybe broken down into cable, pipework and

    ventilation components. This division is re-flected by the statutory building controlframework and the common guidelinesadopted by all 16 German federal states,specifically the Pipe and Cable InstallationDirective (LAR) and the Ventilation SystemDirective (LAR).

    fischers FIRE STOP range features bothtrade-specific and cross-trade solutions.The fire stops take on a variety of forms,including board (e.g. S90-rated M10 combi-nation board fire stop), mortar, blocks, foamand cushions.

    Fire stops to LAR(Pipe and Cable Installation Directive)For penetrations through space-enclosingbuilding elements, the provisions cover thefollowing individual types of service run inseparate or shared openings:

    Electrical cables no limit on diameter Non-combustible pipes diameter< 160 mm

    Combustible pipes diameter < 32 mm

    Constructions complying with LAR specifi-cations are deemed adequate for serviceruns within these size limits. fischer FIRESTOP products for such applications includethe FDB fire protection compound, for sys-tems C1 and T1, and the FM3 mortar, inconjunction with the FBV anti-corrosionfleece for pipes, in systems C2 and T2.

    For service runs beyond these size limitsand for several services penetrating a singleopening where the spacing requirementscannot be met, the LAR requires tested andapproved fire stop systems certified forspecific applications under building controllegislation (national technical approvals orbuilding control test certificates). It alsorequires the on-site marking/designation ofthe installed fire stops. fischer providesself-adhesive signs to designate the sys-tems. Moreover, applicators in some casesrequire instruction in the use of the fire stop

    systems and the fischer ACADEMY nowoffers special courses for its FIRE STOPcustomers.

    S90-rated M10 combinationboard fire stop

    S90-rated C20 cable mortarfire stop

    S90-rated C40 cable blockfire stop

    S90-rated C30 cable cushionfire stop

    R90-rated T60 fire stopsleeve

    V2 mortar M3

    Buildingelements (wall / floor)

    Building material type Finishes etc.

    Fire-resistance period F30 to F180

    Trades

    Insulation Utility service type

    Installationtype: (cable/pipe)

    Combustible Non-combustible

    Diagram showing various requirements placed on fire stops

    Fire stop

    Type (C,M,T,V) Construction

  • 8/7/2019 2009-connectit-02_en

    3/4

    10

    Test standard 4102 includes different parts. Building materials are classified in non-flammable (A1, A2) and flammable (B1, B2, B3) classes of building materials.Building members can be composed of different building materials. The relevant parts of DIN 4102 are listed below.

    DIN 4102 Content Building members Classification

    Part 3 Fire walls and non-load-bearing outside Walls and ceilings Wwalls, terms, requirements and tests

    Part 5 List and application of classified building materials, building members and special components

    Part 6 Fire protection seals, seals in lift shaft Doors, gates Twalls and in fire-resistant glazing; terms,requirements and tests

    Part 9 Cable fire stops, terms, requirements Ventilation systems Land tests Fire stop flaps K

    Part 11 Cable jackets, pipe fire stops, installation Pipe fire stops Rshafts and channels, seals for their inspection Installation channels Iopenings; terms, requirements and tests and shafts

    Part 12 Function maintenance of electrical cable systems Function maintenance ERequirements and test of electrical systems

    Part 13 Fire protection glazing; terms, requirements No heat crossing Fand tests With heat crossing G

    The duration of fire resistance specifies the resistance to fire over a certain period of time (in minutes).Building components are classified in fire resistance classes (F 30 F 180 or e.g. R90, L90, S30, K90 . . . ).

    DIN 4102 Test Standard

    The following fischer FIRE STOP con-structions are currently available as systemsolutions:

    Mineral fibre board fire stops for 30-,60- and 90-minute fire resistance in sys-tems C10, C11, M10 and T10. The water-proof and paintable coating and fillercompounds FAB and FAS likewiseprovide all the benefits of universalapplication.

    Mortar fire stops for 90-minute fire resis-tance in systems C20, M20 and T20. Thelightweight mortar FMO offers a highcoverage of as much as 2.7 litres/kg.Moreover, the possibility of incorporatingmineral fibre board as permanent shut-tering in floor fire stops obviates theneed for external shuttering.

    Cushion fire stops for 90-minute fire resis-tance in system C30. Available in four sizes(S, M, L, XL), the FBK fire stop cushionsfit perfectly into the opening around thecable or cable support systems.

    Block fire stops for 30-, 60-, 90- and 120-minute fire resistance in systems C40and C41. The FBB fire stop is a block forall seasons and can be applied withoutancillary materials and in conjunctionwith the FBS fire stop foam.

    Foam barriers for 30- and 90-minute fireresistance in systems C50 and C51. TheFBS fire stop foam is ideal for smalleropenings and highly economical, withonly 75 mm thickness in walls with 30-minute fire resistance.

    The FBM fire stop sleeve for 90-minutefire resistance in system T60 can beeither plugged on and incorporated ininfill mortar. A sound-control insert isincluded.

    Fire stops to LAR(Ventilation System Directive)

    The LAR sets out the fire-resistancerequirements for ventilation ducts and asso-ciated shutter units. It also specifies therequirements relating to shutter devices

    (fire and smoke dampers), which are nor-mally cast into solid building elements. TheFM3 mortar in system V2 is provided for thisapplication.

  • 8/7/2019 2009-connectit-02_en

    4/4

    11FIRE STOP

    Examples for anchor applicationsApplication Regulations for use Anchor details Suitable anchors / plugs

    DIN 4102, Part 4,

    8.5.7.5

    Steel anchors with construction

    approval > M8; double depth butanchored at a minimum depth of 6 cm;max. theoretical load 500 kN peranchor and max. 6 N/mm2 withreference to steel cross-section or fireprotection certificate by approvedtesting station.

    Zykon anchor bolt FZA

    Zykon hammerset anchor FZEA IIAnchor bolt FAZ IIAnchor bolt FAZ A4/CNail anchor FNA IIInjection mortar FIS VHigh performance anchor FH IICeiling nail FDNConcrete screw FBS

    Fire-protected ventilation systems and utilityinstallations L30 to L120

    Sprinkler systems

    General pipe systems

    Cable routes

    Heavy pipe systems and cable routes

    VdS guidelines forsprinkler systems

    (new directivepublished in 2008)

    Made of non-flammable materialand tested and approved by VdS;

    minimum M8.

    Zykon anchor bolt FZAZykon hammerset anchor FZEA II

    Anchor bolt FAZ IIAnchor bolt FAZ A4/CHammerset anchor EAHigh performance anchor FH IIHollow-ceiling anchor FHY

    DIN 4102, Part 4,8.5.7.5

    Steel anchors with constructionapproval > M8; double depth butanchored at a minimum depth of 6 cm;max. theoretical load 500 kN per

    anchor and max. 6 N/mm2 withreference to steel cross-section or fireprotection certificate by approvedtesting station.

    Nail anchor FNA IIZykon hammerset anchor FZEA IIAnchor bolt FAZ IIAnchor bolt FAZ A4/C

    Hammerset anchor EAConcrete screw FBSHollow-ceiling anchor FHYCeiling nail FDN

    DIN 4102, Part 4,8.5.7.5 and DIN 4102,Part 12 for functionmaintenance

    Steel anchors with constructionapproval > M8; double depth but an-chored at a minimum depth of 6 cm;max. theoretical load 500 kN peranchor and max. 6 N/mm2 withreference to steel cross-section or fireprotection certificate by approvedtesting station.

    Zykon anchor bolt FZAZykon hammerset anchor FZEA IIAnchor bolt FAZ IIAnchor bolt FAZ A4/CHigh performance anchor FH IIHollow-ceiling anchor FHYHammerset anchor EANail anchor FNA IIConcrete screw FBSInjection mortar FIS V

    DIN 4102, Part 4,8.5.7.5

    Steel anchors with constructionapproval > M8; double depth butanchored at a minimum depth of6 cm; max. theoretical load 500 kNper anchor and max. 6 N/mm2 withreference to steel cross-section orfire protection certificate by approv-ed testing station.

    Anchor bolt FAZ IIAnchor bolt FAZ A4/CHigh performance anchor FH IIZykon hammerset anchor FZEA IIHighbond anchor FHB IIZykon anchor bolt FZAInjection mortar FIS V