2007-12 U Girder Colorado Dylgo

Embed Size (px)

Citation preview

  • 8/10/2019 2007-12 U Girder Colorado Dylgo

    1/75

    Design and Construction of CurvedDesign and Construction of Curved

    Precast Girder Bridge Projects in ColoradoPrecast Girder Bridge Projects in Colorado

  • 8/10/2019 2007-12 U Girder Colorado Dylgo

    2/75

    Current Colorado ProjectsCurrent Colorado Projectsusing Curved Precast Girdersusing Curved Precast Girders

    1.1. IH25 / SH270 Ramp K, DenverIH25 / SH270 Ramp K, Denver

    2.2. SH270 / IH76 Ramp Y, DenverSH270 / IH76 Ramp Y, Denver

    3.3. E470 / IH70, Ramp H, DenverE470 / IH70, Ramp H, Denver4.4. SH58 / IH70, Ramp A, GoldenSH58 / IH70, Ramp A, Golden

    5.5. Austin Bluffs Overpass, ColoradoAustin Bluffs Overpass, Colorado

    SpringsSprings

    6.6. IH25 Viaduct, TrinidadIH25 Viaduct, Trinidad

  • 8/10/2019 2007-12 U Girder Colorado Dylgo

    3/75

    Curved Girder Bridge QuantitiesCurved Girder Bridge Quantities

    Project Bridge S.F.L.F. Curved

    Precast

    IH25 / SH270 Ramp K 66,740 s.f. 2,840 l.f.

    IH76 / SH270 Ramp Y 77,248 s.f. 4,544 l.f.

    IH70 / SH58 Ramp A 79,995 s.f. 4,095 l.f.

    Austin Bluffs 57,715 s.f. 2,380 l.f.

    IH25 Trinidad 65,728 s.f. 4,141 l.f.

    IH70 / E470 Ramp H 75,952 s.f. 3,232 l.f.

    Total 414,378 s.f. 21,232 l.f.

  • 8/10/2019 2007-12 U Girder Colorado Dylgo

    4/75

    270 Ramp K270 Ramp K

    The first of manyThe first of manyContractor Alternate Design to Steel Base BidContractor Alternate Design to Steel Base Bid

    Plant Manufactured Precast Girders and Panels.Plant Manufactured Precast Girders and Panels.Limited Time Line for final Design / ApprovalLimited Time Line for final Design / Approval(4 months)(4 months)

    Involved Close Cooperation Between DOT,Involved Close Cooperation Between DOT,Engineer, Sub Contractors and ContractorEngineer, Sub Contractors and ContractorDesigned by Summit Engineering, Littleton, CODesigned by Summit Engineering, Littleton, CO

    and PBS&J, Denverand PBS&J, DenverBuilt byBuilt by SemaSema ConstructionConstruction

  • 8/10/2019 2007-12 U Girder Colorado Dylgo

    5/75

    E470 Ramp HE470 Ramp HContractor Design/Build Project.Contractor Design/Build Project.

    Currently Under Construction.Currently Under Construction.Connector Ramp from E470 Toll Road toConnector Ramp from E470 Toll Road toInterstate 70.Interstate 70.

    Combination of Simple Span and shoredCombination of Simple Span and shoredconstruction. Spans from 100 to 200 construction. Spans from 100 to 200 3434 U84 Girders, 11 SpansU84 Girders, 11 Spans

    1200 Horizontal Curvature1200 Horizontal CurvatureDesigned by DMJM Harris, DenverDesigned by DMJM Harris, DenverBuilt by Lawrence Construction Co, Littleton, COBuilt by Lawrence Construction Co, Littleton, CO

  • 8/10/2019 2007-12 U Girder Colorado Dylgo

    6/75

    270 Ramp Y270 Ramp YUnder Construction.Under Construction.

    Flyover Connector from EB SH270 to EBFlyover Connector from EB SH270 to EBInterstate 76.Interstate 76.40 Precast Girders, 12 Spans.40 Precast Girders, 12 Spans.

    Span Lengths from 100 to 230.Span Lengths from 100 to 230.Numerous traffic crossings and creek crossing.Numerous traffic crossings and creek crossing.760 Radius horizontal curve.760 Radius horizontal curve.

    Colorado DOT Design.Colorado DOT Design.Value Engineering by Summit EngineeringValue Engineering by Summit EngineeringEdward Kraemer & Sons, Castle Rock COEdward Kraemer & Sons, Castle Rock CO

  • 8/10/2019 2007-12 U Girder Colorado Dylgo

    7/75

    Ramp Y, Unit 2 Erected over IH76 & SH76Ramp Y, Unit 2 Erected over IH76 & SH76

  • 8/10/2019 2007-12 U Girder Colorado Dylgo

    8/75

    Falsework Bents Adjacent to IH76 TrafficFalsework Bents Adjacent to IH76 Traffic

  • 8/10/2019 2007-12 U Girder Colorado Dylgo

    9/75

    SH 58 Ramp ASH 58 Ramp AUnder VE Design and Construction.Under VE Design and Construction.

    Flyover Connector from EB Interstate 70 to WBFlyover Connector from EB Interstate 70 to WBSH 58 into Golden.SH 58 into Golden.3838 -- U86 Precast Girders, 11 Spans.U86 Precast Girders, 11 Spans.

    Span Lengths from 150 to 235.Span Lengths from 150 to 235.820 Horizontal Curvature.820 Horizontal Curvature.Numerous traffic crossings and creek crossing.Numerous traffic crossings and creek crossing.

    CH2M Hill Design.CH2M Hill Design.Value Engineering by Summit EngineeringValue Engineering by Summit EngineeringAmes Construction Co, Denver, COAmes Construction Co, Denver, CO

  • 8/10/2019 2007-12 U Girder Colorado Dylgo

    10/75

    SH 58 Ramp ASH 58 Ramp A

    Erection to begin November 2007Erection to begin November 2007

  • 8/10/2019 2007-12 U Girder Colorado Dylgo

    11/75

    Austin Bluffs Overpass Austin Bluffs OverpassUnder Construction.Under Construction.2424 -- U85 Precast Girders, Dual Bridges, 4 Spans.U85 Precast Girders, Dual Bridges, 4 Spans.Span Lengths from 110 to 210.Span Lengths from 110 to 210.950 Radius Curve in two spans.950 Radius Curve in two spans.Major Urban traffic crossing and creek crossing.Major Urban traffic crossing and creek crossing.CH2M Hill Design.CH2M Hill Design.Value Engineering by Summit EngineeringValue Engineering by Summit Engineering

    Lawrence Construction Co, Littleton, COLawrence Construction Co, Littleton, CO

  • 8/10/2019 2007-12 U Girder Colorado Dylgo

    12/75

    Austin Bluffs Austin Bluffs

  • 8/10/2019 2007-12 U Girder Colorado Dylgo

    13/75

    IH25 Viaduct, TrinidadIH25 Viaduct, TrinidadContractor Alternate Design and Construction.Contractor Alternate Design and Construction.Early stages of construction.Early stages of construction.

    Elevated Viaduct through downtown Trinidad. 24Elevated Viaduct through downtown Trinidad. 24-- U85 Precast Girders, Dual Bridges, 4 Spans.U85 Precast Girders, Dual Bridges, 4 Spans.Span Lengths from 100 to 265.Span Lengths from 100 to 265.

    Major Urban project with numerous traffic, riverMajor Urban project with numerous traffic, riverand railroad crossings.and railroad crossings.Base design, precast segmental.Base design, precast segmental.

    Value Engineering by TSH Engineers and SummitValue Engineering by TSH Engineers and SummitEngineeringEngineeringLawrence Construction Co, Littleton, COLawrence Construction Co, Littleton, CO

    se recast oncrete or t esese recas oncre e or ese

  • 8/10/2019 2007-12 U Girder Colorado Dylgo

    14/75

    y use recast oncrete or t esey use recas oncre e or eseTypes of Bridges?Types of Bridges?

    Colorado Preference for Concrete Structures.Colorado Preference for Concrete Structures.Setup Costs were nominal.Setup Costs were nominal.Concrete Alternate less expensive.Concrete Alternate less expensive.Speed of Fabrication.Speed of Fabrication.Design Impact not significant.Design Impact not significant.Composite construction, splicing and postComposite construction, splicing and posttensioning girders extends the span rangetensioning girders extends the span rangeShoring not required over traffic.Shoring not required over traffic.Design used established techniques on newDesign used established techniques on newapplication.application.Attractive appearance.Attractive appearance.

  • 8/10/2019 2007-12 U Girder Colorado Dylgo

    15/75

    Why use U Girders?Why use U Girders?

    Very Robust Cross Section.Very Robust Cross Section.

    Less Girders for a given deck width.Less Girders for a given deck width.Flexible shape to modify.Flexible shape to modify.

    Attractive Aesthetics.Attractive Aesthetics.Easier to route post tensioningEasier to route post tensioning ..

  • 8/10/2019 2007-12 U Girder Colorado Dylgo

    16/75

    Why use U Girders?Why use U Girders?

    Girder Set and in Service.Girder Set and in Service.Minimal Repairs toMinimal Repairs to SpalledSpalled Flange.Flange.Manitowoc 888 wasManitowoc 888 was totalledtotalled ..

  • 8/10/2019 2007-12 U Girder Colorado Dylgo

    17/75

    Whats the Catch?Whats the Catch?

    Extensive Shoring Necessary.Extensive Shoring Necessary.

    Girders are very heavy.Girders are very heavy.Stability must be designed for and maintainedStability must be designed for and maintaineduntil superstructure is self supporting.until superstructure is self supporting.

    More field and erection Engineering required.More field and erection Engineering required.Blending of Precast and Post Tensioned industriesBlending of Precast and Post Tensioned industriesand technologies.and technologies.

    Slower construction cycle during Erection.Slower construction cycle during Erection.More complex multiple phase constructionMore complex multiple phase construction ..

  • 8/10/2019 2007-12 U Girder Colorado Dylgo

    18/75

    270 Ramp Y Cost Comparisons270 Ramp Y Cost Comparisons

    Item Steel Design Curved Precast

    Girder Cost $5,125,000 $3,086,240

    Erection Costs $1,025,000 $890,000

    Falsework $50,000 $250,000

    Post Tensioning $0 $506,000

    Total $6,200,000 $4,732,240

    Cost / Ft. $1393 / lf $1063

  • 8/10/2019 2007-12 U Girder Colorado Dylgo

    19/75

    270 Ramp Roadway Layout270 Ramp Roadway Layout

  • 8/10/2019 2007-12 U Girder Colorado Dylgo

    20/75

    270 Ramp Cross Section270 Ramp Cross Section

  • 8/10/2019 2007-12 U Girder Colorado Dylgo

    21/75

    Bridge ConfigurationBridge Configuration8 Spans, 6 and 2 span continuous8 Spans, 6 and 2 span continuousunits.units.

    Span Lengths from 140 to 200 Span Lengths from 140 to 200 Pier Heights from 10 to 45 Pier Heights from 10 to 45

    Spliced ConstructionSpliced ConstructionPhased Erection w/ staged postPhased Erection w/ staged post

    tensioningtensioning

  • 8/10/2019 2007-12 U Girder Colorado Dylgo

    22/75

    Phased ConstructionPhased Construction

  • 8/10/2019 2007-12 U Girder Colorado Dylgo

    23/75

    Typical Girder Cross SectionTypical Girder Cross Section Ramp KRamp K

  • 8/10/2019 2007-12 U Girder Colorado Dylgo

    24/75

    Typical Girder Cross SectionTypical Girder Cross Section Ramp YRamp Y

  • 8/10/2019 2007-12 U Girder Colorado Dylgo

    25/75

    Ramp K CIP Lid SlabRamp K CIP Lid Slab

    R A & Y

  • 8/10/2019 2007-12 U Girder Colorado Dylgo

    26/75

    Ramps A & YRamps A & Y

    Precast Panel Lid SlabPrecast Panel Lid Slab

  • 8/10/2019 2007-12 U Girder Colorado Dylgo

    27/75

    PrePre --Casting of GirdersCasting of Girders

    Up to 120 long, 265 Kip max weightUp to 120 long, 265 Kip max weight

    Curved FormsCurved FormsPost TensionedPost Tensioned

    Precast Anchor BlocksPrecast Anchor BlocksBlock Outs for CIP Anchor BlocksBlock Outs for CIP Anchor BlocksSecondary Casting of Diaphragms,Secondary Casting of Diaphragms,Bottom Slab Thickening and Lid SlabBottom Slab Thickening and Lid Slab

    Tongue at Expansion Diaphragms Tongue at Expansion Diaphragms

  • 8/10/2019 2007-12 U Girder Colorado Dylgo

    28/75

    Curved Girder FormworkCurved Girder FormworkPrecaster: Encon BridgePrecaster: Encon Bridge

  • 8/10/2019 2007-12 U Girder Colorado Dylgo

    29/75

    Reinforcing Cage in FormsReinforcing Cage in FormsPrior to CastingPrior to Casting

  • 8/10/2019 2007-12 U Girder Colorado Dylgo

    30/75

    Typical Girder Cross SectionTypical Girder Cross Section

  • 8/10/2019 2007-12 U Girder Colorado Dylgo

    31/75

    Girders in Storage AreaGirders in Storage Area

  • 8/10/2019 2007-12 U Girder Colorado Dylgo

    32/75

    E i C di iE i C di i

  • 8/10/2019 2007-12 U Girder Colorado Dylgo

    33/75

    Erection ConditionsErection ConditionsGirders supported on FalseworkGirders supported on FalseworkTorsionalTorsional Bracing.Bracing.P/C Panels or CIP lid slabs to controlP/C Panels or CIP lid slabs to controltorsiontorsionCantilevered constructionCantilevered constructionTemporary post tensioningTemporary post tensioningStrongbackStrongback FalseworkFalseworkHeavy lifts with limited crane radiiHeavy lifts with limited crane radiiComplicated site conditions.Complicated site conditions.Multiple traffic closuresMultiple traffic closuresStaged Post Tensioning.Staged Post Tensioning.

  • 8/10/2019 2007-12 U Girder Colorado Dylgo

    34/75

    Girders Supported on FalseworkGirders Supported on Falsework

  • 8/10/2019 2007-12 U Girder Colorado Dylgo

    35/75

    Falsework Design at Pier 5Falsework Design at Pier 5

  • 8/10/2019 2007-12 U Girder Colorado Dylgo

    36/75

    Girder ErectionGirder Erection

  • 8/10/2019 2007-12 U Girder Colorado Dylgo

    37/75

    Precast Girder Weight = 250 KPrecast Girder Weight = 250 K

    Maximum Lift = 330 KMaximum Lift = 330 K300 and 240 Ton Hydraulic Cranes300 and 240 Ton Hydraulic Cranes

  • 8/10/2019 2007-12 U Girder Colorado Dylgo

    38/75

    Erection PlanErection Plan Girders 10 L&RGirders 10 L&R

  • 8/10/2019 2007-12 U Girder Colorado Dylgo

    39/75

    Setting Girder at Pier 2Setting Girder at Pier 2

  • 8/10/2019 2007-12 U Girder Colorado Dylgo

    40/75

    Girder suspended over pierGirder suspended over pierGrout Bearing installed prior to castingGrout Bearing installed prior to castingdiaphragmdiaphragm

    Eliminates manufactured bearingsEliminates manufactured bearings

  • 8/10/2019 2007-12 U Girder Colorado Dylgo

    41/75

    Completed Pier DiaphragmCompleted Pier Diaphragm

    ddl

  • 8/10/2019 2007-12 U Girder Colorado Dylgo

    42/75

    Straddle Bents over HOV LaneStraddle Bents over HOV Lane

    Continuous traffic maintained during constructionContinuous traffic maintained during construction

    Erection over HOV during lane closuresErection over HOV during lane closures

    Straddle Bent Design at HOV LanesStraddle Bent Design at HOV Lanes

  • 8/10/2019 2007-12 U Girder Colorado Dylgo

    43/75

    Straddle Bent Design at HOV LanesStraddle Bent Design at HOV Lanes

    Gi d i OGi d E i HOV L

  • 8/10/2019 2007-12 U Girder Colorado Dylgo

    44/75

    Girder Erection over HOV LaneGirder Erection over HOV Lane

    HOV O T ffiHOV O T ffi

  • 8/10/2019 2007-12 U Girder Colorado Dylgo

    45/75

    HOV Open to TrafficHOV Open to Traffic

    E i Pi 4E ti t Pi 4

  • 8/10/2019 2007-12 U Girder Colorado Dylgo

    46/75

    Erection to Pier 4Erection to Pier 4

    F l k Pi 5F l k t Pi 5

  • 8/10/2019 2007-12 U Girder Colorado Dylgo

    47/75

    Extensive Site Preparation RequiredExtensive Site Preparation RequiredVarying Site ConditionsVarying Site Conditions

    Falsework at Pier 5Falsework at Pier 5

    E ti th h S 5E ti th gh S 5

  • 8/10/2019 2007-12 U Girder Colorado Dylgo

    48/75

    Erection through Span 5Erection through Span 5

    Erection Approaches 270 Bridge andErection Approaches 270 Bridge and

  • 8/10/2019 2007-12 U Girder Colorado Dylgo

    49/75

    pp gpp g

    IH25IH25

    Casting of Anchor Block and Lid SlabCasting of Anchor Block and Lid Slab

  • 8/10/2019 2007-12 U Girder Colorado Dylgo

    50/75

    gg

    at Girders 10 and 13at Girders 10 and 13

    Anchor Block ReinforcingAnchor Block Reinforcing

  • 8/10/2019 2007-12 U Girder Colorado Dylgo

    51/75

    Anchor Block Reinforcing Anchor Block Reinforcing

    Setting Girders 10L&R at Pier 6Setting Girders 10L&R at Pier 6

  • 8/10/2019 2007-12 U Girder Colorado Dylgo

    52/75

    Setting Girders 10L&R at Pier 6Setting Girders 10L&R at Pier 6

    330 Kip Lift weight330 Kip Lift weightCantilevers 54 beyond Pier 6 over 270 BridgeCantilevers 54 beyond Pier 6 over 270 BridgeGirder 10 is restrained to Girder 9 to preventGirder 10 is restrained to Girder 9 to preventtippingtipping

    Girder 10 Tie DownGirder 10 Tie Down

  • 8/10/2019 2007-12 U Girder Colorado Dylgo

    53/75

    Girders 10 L&R Set at Pier 6Girders 10 L&R Set at Pier 6

  • 8/10/2019 2007-12 U Girder Colorado Dylgo

    54/75

    Girders 10 L&R Set at Pier 6Girders 10 L&R Set at Pier 6

  • 8/10/2019 2007-12 U Girder Colorado Dylgo

    55/75

    Girders 10 L&R from 270 BridgeGirders 10 L&R from 270 Bridge

  • 8/10/2019 2007-12 U Girder Colorado Dylgo

    56/75

    Girder Erection from Abutment 9 over IH25Girder Erection from Abutment 9 over IH25

    and On Rampand On Ramp

    Girder Strong Back DesignGirder Strong Back Design

  • 8/10/2019 2007-12 U Girder Colorado Dylgo

    57/75

    Girder Girder

  • 8/10/2019 2007-12 U Girder Colorado Dylgo

    58/75

    StrongStrongBacksBacks

    In PlaceIn Place

    Girders 11 L&R Set over 270 BridgeGirders 11 L&R Set over 270 Bridge

  • 8/10/2019 2007-12 U Girder Colorado Dylgo

    59/75

    Girders 11 L&R Set over 270 BridgeGirders 11 L&R Set over 270 Bridge

  • 8/10/2019 2007-12 U Girder Colorado Dylgo

    60/75

    rec on o r ers omp e e

  • 8/10/2019 2007-12 U Girder Colorado Dylgo

    61/75

    Erected Girders w/ Lid SlabErected Girders w/ Lid Slab

  • 8/10/2019 2007-12 U Girder Colorado Dylgo

    62/75

    Erected Girders w/ Lid SlabErected Girders w/ Lid Slab

    Setting Precast PanelsSetting Precast Panels

  • 8/10/2019 2007-12 U Girder Colorado Dylgo

    63/75

    gg

    Panels installed, overhang forms set andPanels installed, overhang forms set andd k tdeck cast

  • 8/10/2019 2007-12 U Girder Colorado Dylgo

    64/75

    deck castdeck cast

    Completed StructureCompleted Structure

  • 8/10/2019 2007-12 U Girder Colorado Dylgo

    65/75

    Completed Structurep

    Design Lessons LearnedDesign Lessons LearnedT i l d fl i d d i

  • 8/10/2019 2007-12 U Girder Colorado Dylgo

    66/75

    TorsionalTorsional

    deflections and stresses duringdeflections and stresses during

    erection were critical.erection were critical.Haul weight limits the girderHaul weight limits the girder precastingprecastingand erection more than any other factor.and erection more than any other factor.Limited eccentricity of web tendons.Limited eccentricity of web tendons.Local tendons were effective in longLocal tendons were effective in longspans.spans.Negative moments at interior piersNegative moments at interior pierscontrolled much of the design.controlled much of the design.StrainStrain compatabilitycompatability analysis necessaryanalysis necessarydue to limited compression block.due to limited compression block.Service stresses in deck steel is important.Service stresses in deck steel is important.Lightweight Concrete can significantlyLightweight Concrete can significantlyimpact future long span designs.impact future long span designs.

    Construction SolutionsConstruction Solutionsl l l ll fQ li l i i l ll f

  • 8/10/2019 2007-12 U Girder Colorado Dylgo

    67/75

    Quality control is essential at all stages ofQuality control is essential at all stages ofconstruction.construction.Simplify precast formingSimplify precast formingUse CIP anchor zones.Use CIP anchor zones.Design of economical handling reinforcingDesign of economical handling reinforcingTemporary structure design and bracing is criticalTemporary structure design and bracing is criticalto project success.to project success.Establish continuity as soon as possible.Establish continuity as soon as possible.Create a closed box section early after erection.Create a closed box section early after erection.PrecastersPrecasters and postand post tensionerstensioners must understandmust understandeach other.each other.Evaluate site conditions during design.Evaluate site conditions during design.Make significant allowances for heavy cranesMake significant allowances for heavy cranes

    during erection to handle heavy loads.during erection to handle heavy loads.

  • 8/10/2019 2007-12 U Girder Colorado Dylgo

    68/75

    Gateway Bridge to DowntownGateway Bridge to DowntownColorado Springs from IH25Colorado Springs from IH25

  • 8/10/2019 2007-12 U Girder Colorado Dylgo

    69/75

    Colorado Springs from IH25Colorado Springs from IH25

    Erection support for all spans usingErection support for all spans using

  • 8/10/2019 2007-12 U Girder Colorado Dylgo

    70/75

    StrongbackStrongback FalseworkFalsework

    Seven Continuous Girder LinesSeven Continuous Girder LinesSpliced and Splayed to AccommodateSpliced and Splayed to Accommodate

    Deck Width from 88 to 168Deck Width from 88 to 168

  • 8/10/2019 2007-12 U Girder Colorado Dylgo

    71/75

    Deck Width from 88 to 168Deck Width from 88 to 168

  • 8/10/2019 2007-12 U Girder Colorado Dylgo

    72/75

    Drop in Girders @ Span 3Drop in Girders @ Span 3

  • 8/10/2019 2007-12 U Girder Colorado Dylgo

    73/75

    over UPRRover UPRR

    Demolition began January 2007Demolition began January 2007

  • 8/10/2019 2007-12 U Girder Colorado Dylgo

    74/75

    Open to Traffic, Labor Day 2007Open to Traffic, Labor Day 2007

  • 8/10/2019 2007-12 U Girder Colorado Dylgo

    75/75