11
Crown Copyright and database rights 2019. OS 100031961. 2000 2m offset from existing boathouse 8308 17000 300 300 2308 2000 2000 2000 2308 2000 001 / 04 Schematic Elevation - Hoveton Marsh Fish Barrier (1:100) Gate Overhanging branches to be cut-back in advance of piling works Alignment of fish barrier set out to avoid tree trunks and root balls as is reasonably possible. Tree removal to be assessed. 001 / 03 Schematic Plan - Layout of Piles for Hoveton Marsh Fish Barrier (1:100) 100 UBP steel piles (cut-off 300mm above bank level) Screen (extending 100mm above bank level) Timber cill Timber board side wall cut-off 1200 screen height Stop-boarded Stop-boarded Existing profile 1200 200 1200 1000 1000 1000 1200 1732 100 Water depths recorded on 27th Aug 2019 2000 2000 Very loose fine to medium SAND Plastic amorphous PEAT Medium dense very gravelly fine to medium SAND. Gravel angular to subangular. Medium dense very gravelly fine to medium SAND. Gravel angular to subangular. Soft grey silty CLAY. Plastic amorphous PEAT Medium dense very gravelly fine to medium SAND. Gravel angular to subangular. Very gravelly fine to medium SAND. Gravel angular to subangular. Soft to firm grey silty CLAY. River channel locally dredged / de-silted to suit. Cill boards inserted to ensure that clear height above bed >100mm. Timber cut off to extend well into PEAT to form effective cut-off. Horizontal truss formed in sliding hollow sections to be site drilled and bolted. 355 UBP Steel piles (cut-off 300mm above bank level) 305 UBP 88 100kN UNFACTORED 100kN UNFACTORED 100kN UNFACTORED 100kN UNFACTORED Horizontal truss formed in sliding hollow sections to be site drilled and bolted. 355 305 (see elevations for weights) UBP steel pile. Screwpiles to form tension compression couple. Pile and Cap designed by screwpile specialist. 30.00° Hydraulic cut-off formed 3m into peat. Subject to further testing of peat to validate design parameters. Bed upstream and downstream of screen desilted, TENSAR TRIAX TX-G Geogrid laid over peat. 350mm of rip-rap 40mm to 150mm laid over membranes. Membrane turned up and lapped back into themselves at upstream and down stream end. TRIAX Grid to be physically joined to adjoining sheets using proprietary clips suitable for the system. Allow to fixed geogrid to top of cut-off panel using oak batten (75mm sq) and SS coach bolts. Cut off suspended on chains with turn-buckles, to eye bolt through cut-off panel. 8000 8000 3000 Solid oak web infill above top of cut-off, bolted to Pile using Stainless Steel Bolt and isolating sleeve. UNFACTORED LOAD AS INDICATED ON PLAN 001 / 05 Schematic Section - Fish Barrier Piles (1:100) Ground Strata - See GI Ground Strata - See GI Bearing piles Vertical screw piles Raking screw piles Waling beam Eel Traps -See Drawing 010 25mm steel plate framed each side in Oak on top and sides, Oak bolted to steelplate using isolated SS M20 bolts, with nuts and washers counter bored into sawn oak frame and isolating sleeve @ 600c/c. 2 No. SS Eye bolt through roadplate and isolator sleeve, for suspension of plate. 001 / 06 Detail - Hydraulic cut-off (1:50) 3000 Elevation Plan 1. DIMENSIONS: ● Are in millimetres unless otherwise stated. ● Marked thus (*) or c. are approximate. ● All levels are in metres to Site Datum. 2. SPECIFICATION: All works to be carried out in accordance with the Environment Agency Minimum Technical Requirements which shall be the Civil Engineering Specification for the Water Industry (CESWI). Hoveton Marshes Barrier Location 001 / 01 Location Plan 001 / 02 Site Plan - Hoveton Marshes Fish Barrier (1:1250) Access route Proposed Hoveton Marshes Fish Barrier Detailed Design As shown P. Kibel SAFETY HEALTH & ENVIRONMENTAL INFORMATION Managing flow & stage levels in Hoveton Broad. - Monitor flow levels & flood warnings. Caution the Broad is both fluvial & tidal. Up to 0.5m fluctuation in water levels under tidal surges - Check adequacy of pontoon for environment (draft, anchorage & mooring) and plant & loading requirements. Managing flow velocities through & across barrier works - Monitor velocities. Risk of falls from height - Check depth of dredging. -Check adequate edge protection and access provision. Lifting - Check cranage lifting facilities & constraints. - Check access weight & size restrictions for cranage on pontoon. Interface with public & other site operations - Check adequate warning signs in place. - Liaise with operators of the Broad. Services - Check for services. Stability of Piling Works - Carry out inspection of working area - Check for conflict with trees & overhanging branche. Carry clearance works in advance of piling works. It is assumed that all works will be carried out by a competent contractor working, where appropriate, to an approved method statement Refer to Designer's Risk Assessment and pre-construction phase plan. C1 C2 CONSTRUCTION C3 C4 C5 C6 C7 P01 Draft issue 30 / 09 / 19 P02 For consultation 02 / 10 / 19 P03 For consultation 13 / 11 / 19 P04 Piles revised and reconfigured to address GI findings of very deep strata of peat. Location of eel trap & fykes added following consultation with EA Fisheries. 13/01/21 M.Lakin / J. BLyth J.Blyth / M.Lakin

2000 & ENVIRONMENTAL INFORMATION

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: 2000 & ENVIRONMENTAL INFORMATION

Crown Copyright and database rights 2019. OS 100031961.

2

0

0

0

2m offset from

existing boathouse

8308

17

00

0

30

0

30

0

23082000 2000

2000 2308 2000

001 / 04 Schematic Elevation - Hoveton Marsh Fish Barrier

(1:100)

Gate

Overhanging branches

to be cut-back in

advance of piling works

Alignment of fish barrier set out

to avoid tree trunks and root balls

as is reasonably possible. Tree

removal to be assessed.

001 / 03 Schematic Plan - Layout of Piles for Hoveton Marsh Fish Barrier

(1:100)

100

UBP steel piles

(cut-off 300mm above bank level)

Screen

(extending 100mm above bank level)

Timber cill

Timber board

side wall cut-off

1200 screen heightStop-boarded Stop-boarded

Existing profile

12

00

20

0

12

00

10

00

10

00

10

00

12

00

17

32

10

0

Water depths recorded on

27th Aug 2019

2000

2000

Very loose fine to

medium SAND

Plastic amorphous

PEAT

Medium dense very

gravelly fine to medium

SAND. Gravel angular

to subangular.

Medium dense very

gravelly fine to medium

SAND. Gravel angular

to subangular.

Soft grey silty CLAY.

Plastic amorphous

PEAT

Medium dense very

gravelly fine to medium

SAND. Gravel angular

to subangular.

Very gravelly fine to

medium SAND. Gravel

angular to subangular.

Soft to firm grey silty CLAY.

River channel locally dredged /

de-silted to suit. Cill boards

inserted to ensure that clear

height above bed >100mm.

Timber cut off to extend well into

PEAT to form effective cut-off.

Horizontal truss formed in

sliding hollow sections

to be site drilled and bolted.

355 UBP Steel piles

(cut-off 300mm above bank level)

305 UBP 88

100kN

UNFACTORED

100kN

UNFACTORED

100kN

UNFACTORED

100kN

UNFACTORED

Horizontal truss formed in

sliding hollow sections

to be site drilled and bolted.

355 305 (see elevations for

weights) UBP steel pile.

Screwpiles to form tension

compression couple. Pile

and Cap designed by

screwpile specialist.

3

0

.0

0

°

Hydraulic cut-off formed 3m into

peat. Subject to further testing of

peat to validate design parameters.

Bed upstream and downstream of screen

desilted, TENSAR TRIAX TX-G Geogrid laid over

peat. 350mm of rip-rap 40mm to 150mm laid

over membranes. Membrane turned up and

lapped back into themselves at upstream and

down stream end. TRIAX Grid to be physically

joined to adjoining sheets using proprietary clips

suitable for the system.

Allow to fixed geogrid to top of cut-off panel using

oak batten (75mm sq) and SS coach bolts.

Cut off suspended on chains

with turn-buckles, to eye bolt

through cut-off panel.

80008000

30

00

Solid oak web infill above top of

cut-off, bolted to Pile using

Stainless Steel Bolt and isolating

sleeve.

UNFACTORED

LOAD AS

INDICATED

ON PLAN

001 / 05 Schematic Section - Fish Barrier Piles

(1:100)

Ground Strata - See GI

Ground Strata - See GI

Bearing piles

Vertical screw piles

Raking screw piles

Waling beam

Eel Traps

-See Drawing 010

25mm steel plate framed each side in Oak on

top and sides, Oak bolted to steelplate using

isolated SS M20 bolts, with nuts and washers

counter bored into sawn oak frame and

isolating sleeve @ 600c/c.

2 No. SS Eye bolt through roadplate and

isolator sleeve, for suspension of plate.

001 / 06 Detail - Hydraulic cut-off

(1:50)

3000

Elevation

Plan

1. DIMENSIONS:

● Are in millimetres unless otherwise stated.

● Marked thus (*) or c. are approximate.

● All levels are in metres to Site Datum.

2. SPECIFICATION:

All works to be carried out in accordance with the

Environment Agency Minimum Technical Requirements

which shall be the Civil Engineering Specification for the

Water Industry (CESWI).

Hoveton Marshes Barrier Location

001 / 01 Location Plan

001 / 02 Site Plan - Hoveton Marshes Fish Barrier

(1:1250)

Access route

Proposed Hoveton Marshes

Fish Barrier

Detailed Design

As shown

P. Kibel

SAFETY HEALTH

& ENVIRONMENTAL

INFORMATION

Managing flow & stage levels in Hoveton Broad.

- Monitor flow levels & flood warnings. Caution the

Broad is both fluvial & tidal. Up to 0.5m fluctuation in

water levels under tidal surges

- Check adequacy of pontoon for environment (draft,

anchorage & mooring) and plant & loading

requirements.

Managing flow velocities through & across

barrier works

- Monitor velocities.

Risk of falls from height

- Check depth of dredging.

-Check adequate edge protection and access

provision.

Lifting

- Check cranage lifting facilities & constraints.

- Check access weight & size restrictions for

cranage on pontoon.

Interface with public & other site operations

- Check adequate warning signs in place.

- Liaise with operators of the Broad.

Services

- Check for services.

Stability of Piling Works

- Carry out inspection of working area

- Check for conflict with trees & overhanging

branche. Carry clearance works in advance of piling

works.

It is assumed that all works will be carried out by a

competent contractor working, where appropriate, to an

approved method statement

Refer to Designer's Risk Assessment and pre-construction

phase plan.

C1

C2

CONSTRUCTION

C3

C4

C5

C6

C7

P01 Draft issue 30 / 09 / 19

P02 For consultation 02 / 10 / 19

P03 For consultation 13 / 11 / 19

P04 Piles revised and reconfigured to address GI

findings of very deep strata of peat.

Location of eel trap & fykes added following

consultation with EA Fisheries.

13/01/21

M.Lakin / J. BLyth

J.Blyth / M.Lakin

AutoCAD SHX Text
Hoveton Marshes
AutoCAD SHX Text
Drain
AutoCAD SHX Text
001 2595 P04
AutoCAD SHX Text
Hoveton Great Broad
AutoCAD SHX Text
Restoration Project -
AutoCAD SHX Text
Fish Barriers
AutoCAD SHX Text
at Hoveton Marshes, The Dam & Foxborrow Dyke
AutoCAD SHX Text
Issue
AutoCAD SHX Text
Drawing No.
AutoCAD SHX Text
TITLE
AutoCAD SHX Text
PROJECT
AutoCAD SHX Text
Project No.
AutoCAD SHX Text
Current Issue Signatures
AutoCAD SHX Text
Copyright reserved
AutoCAD SHX Text
Description
AutoCAD SHX Text
Grid
AutoCAD SHX Text
Client
AutoCAD SHX Text
Filename:
AutoCAD SHX Text
Datum
AutoCAD SHX Text
Original
AutoCAD SHX Text
Size
AutoCAD SHX Text
Scales
AutoCAD SHX Text
Issue
AutoCAD SHX Text
Status
AutoCAD SHX Text
Approver
AutoCAD SHX Text
Checker
AutoCAD SHX Text
A1
AutoCAD SHX Text
C
AutoCAD SHX Text
Author
AutoCAD SHX Text
Date
AutoCAD SHX Text
Hoveton Marsh Barrier
AutoCAD SHX Text
Location & Site Plan
AutoCAD SHX Text
and
AutoCAD SHX Text
Schematic Plan & Elevation
AutoCAD SHX Text
For Information Purposes only Not for construction
Page 2: 2000 & ENVIRONMENTAL INFORMATION

Crown Copyright and database rights 2019. OS 100031961.

4

0

0

0

4m offset from

existing barrier

24000

17

00

0

30

0

20002000 4000

2000 2000 2000 2000

17

32

002 / 04 Schematic Elevation - The Dam Fish Barrier

(1:100)

Gate

c. 2m overhang of branches

to be cut-back in advance

of piling works

002 / 03 Schematic Plan - Layout of Piles for The Dam Fish Barrier

(1:100)

4000

2000 2000 2000

2000 2000 20002000

24000

2000 2000

2000 2000

13

00

15

00

2000 2000 2000

15

00

15

00

1600 screen heights 1300 screen heights

Fully

boarded

cut-off

Fully

boarded

cut-off

2000

c.4m overhang of branches

to be cut-back in advance

of piling works

4000

Existing profile

90

0

14

00

14

50

15

0

Screen

(extending 100mm above bank level)

Timber cill

Timber board

side wall cut-off

Water depths recorded on

27th Aug 2019

17

32

Very loose fine to

medium SAND

Plastic amorphous

PEAT

Medium dense very

gravelly fine to medium

SAND. Gravel angular

to subangular.

Medium dense very

gravelly fine to medium

SAND. Gravel angular

to subangular.

Soft grey silty CLAY.

Plastic amorphous

PEAT

Medium dense very

gravelly fine to medium

SAND. Gravel angular

to subangular.

Very gravelly fine to

medium SAND. Gravel

angular to subangular.

Soft to firm grey silty CLAY.

355 UBP Steel piles

(cut-off 300mm above bank level)

Vertical and inclined

screwpile to form tension /

compression couple. Pile

and cap designed by

screwpile specialist in mild

steel allowing for corosion

for 15 year design life.

Horizontal truss formed in

sliding hollow sections

to be site drilled and bolted.

305 UBP 88 305 UBP 88305 UBP 88

150kN

UNFACTORED

100kN

UNFACTORED

100kN

UNFACTORED

150kN

UNFACTORED

Horizontal truss formed in

sliding hollow sections

to be site drilled and bolted.

355 305 (see elevations for

weights) UBP steel pile.

Screwpiles to form tension

compression couple. Pile

and Cap designed by

screwpile specialist.

3

0

.0

0

°

Hydraulic cut-off formed 3m into

peat. Subject to further testing of

peat to validate design parameters.

Bed upstream and downstream of screen

desilted, TENSAR TRIAX TX-G Geogrid laid over

peat. 350mm of rip-rap 40mm to 150mm laid

over membranes. Membrane turned up and

lapped back into themselves at upstream and

down stream end. TRIAX Grid to be physically

joined to adjoining sheets using proprietary clips

suitable for the system.

Allow to fixed geogrid to top of cut-off panel using

oak batten (75mm sq) and SS coach bolts.

Cut off suspended on chains

with turn-buckles, to eye bolt

through cut-off panel.

80008000

30

00

Solid oak web infill above top of

cut-off, bolted to Pile using

Stainless Steel Bolt and isolating

sleeve.

UNFACTORED

LOAD AS

INDICATED

ON PLAN

002 / 05 Schematic Section - Fish Barrier Piles

(1:100)

Bearing piles

Vertical screw pile

Raking screw pile

Waling beam

Ground Strata - See GI

Ground Strata - See GI

Alignment of fish barrier set out

to avoid tree trunks and root balls

as is reasonably possible. Tree

removal to be assessed.

River channel locally dredged / de-silted to

suit. Cill boards inserted to ensure that clear

height above bed >100mm. Timber cut off to

extend well into PEAT to form effective cut-off.

Eel Fyke

-See Drawing 011

Eel Fyke

-See Drawing 011

25mm steel plate framed each side in Oak on

top and sides, Oak bolted to steelplate using

isolated SS M20 bolts, with nuts and washers

counter bored into sawn oak frame and

isolating sleeve @ 600c/c.

2 No. SS Eye bolt through roadplate and

isolator sleeve, for suspension of plate.

002 / 06 Detail - Hydraulic cut-off

(1:50)

3000

Elevation

Plan

1. DIMENSIONS:

● Are in millimetres unless otherwise stated.

● Marked thus (*) or c. are approximate.

● All levels are in metres to Site Datum.

3. SPECIFICATION:

All works to be carried out in accordance with the

Environment Agency Minimum Technical Requirements

which shall be the Civil Engineering Specification for the

Water Industry (CESWI).

002 / 01 Location Plan

002 / 02 Site Plan - The Dam Fish Barrier

(1:1250)

Access route

Proposed

The Dam Fish Barrier

Existing barrier

(To be retained)

Detailed Design

As shown

P. Kibel

SAFETY HEALTH

& ENVIRONMENTAL

INFORMATION

Managing flow & stage levels in Hoveton Broad.

- Monitor flow levels & flood warnings. Caution the

Broad is both fluvial & tidal. Up to 0.5m fluctuation in

water levels under tidal surges

- Check adequacy of pontoon for environment (draft,

anchorage & mooring) and plant & loading

requirements.

Managing flow velocities through & across

barrier works

- Monitor velocities.

Risk of falls from height

- Check depth of dredging.

-Check adequate edge protection and access

provision.

Lifting

- Check cranage lifting facilities & constraints.

- Check access weight & size restrictions for

cranage on pontoon.

Interface with public & other site operations

- Check adequate warning signs in place.

- Liaise with operators of the Broad.

Services

- Check for services.

Stability of Piling Works

- Carry out inspection of working area

- Check for conflict with trees & overhanging

branche. Carry clearance works in advance of piling

works.

It is assumed that all works will be carried out by a

competent contractor working, where appropriate, to an

approved method statement

Refer to Designer's Risk Assessment and pre-construction

phase plan.

C1

C2

CONSTRUCTION

C3

C4

C5

C6

C7

The Dam Barrier Location

Access route for pontoon

P01 Draft issue 30 / 09 / 19

P02 For consultation 02 / 10 / 19

P03 For consultation 13 / 11 / 19

P04 Piles revised and reconfigured to address GI

findings of very deep strata of peat.

Location of eel trap & fykes added following

consultation with EA Fisheries.

13/01/21

M.Lakin / J. BLyth

J.Blyth / M.Lakin

AutoCAD SHX Text
MHW & MLW
AutoCAD SHX Text
Blackcurrant Carr
AutoCAD SHX Text
NTL
AutoCAD SHX Text
NTL
AutoCAD SHX Text
002 2595 PO4
AutoCAD SHX Text
Hoveton Great Broad
AutoCAD SHX Text
Restoration Project -
AutoCAD SHX Text
Fish Barriers
AutoCAD SHX Text
at Hoveton Marshes, The Dam & Foxborrow Dyke
AutoCAD SHX Text
Issue
AutoCAD SHX Text
Drawing No.
AutoCAD SHX Text
TITLE
AutoCAD SHX Text
PROJECT
AutoCAD SHX Text
Project No.
AutoCAD SHX Text
Current Issue Signatures
AutoCAD SHX Text
Copyright reserved
AutoCAD SHX Text
Description
AutoCAD SHX Text
Grid
AutoCAD SHX Text
Client
AutoCAD SHX Text
Filename:
AutoCAD SHX Text
Datum
AutoCAD SHX Text
Original
AutoCAD SHX Text
Size
AutoCAD SHX Text
Scales
AutoCAD SHX Text
Issue
AutoCAD SHX Text
Status
AutoCAD SHX Text
Approver
AutoCAD SHX Text
Checker
AutoCAD SHX Text
A1
AutoCAD SHX Text
C
AutoCAD SHX Text
Author
AutoCAD SHX Text
Date
AutoCAD SHX Text
The Dam Barrier
AutoCAD SHX Text
Location & Site Plan
AutoCAD SHX Text
and
AutoCAD SHX Text
Schematic Plan & Elevation
Page 3: 2000 & ENVIRONMENTAL INFORMATION

6

2

0

0

Crown Copyright and database rights 2019. OS 100031961.

6.2m offset from

existing barrier

16308

17

00

0

30

0

2308 2000

2000 2000 2000

003 / 04 Schematic Elevation - Foxborrow Fish Barrier

(1:100)

Gate

c.3m overhang of

branches to be cut-back in

advance of piling works.

3no. trees on water line.

Alignment of fish barrier set out

to avoid tree trunks and root balls

as is reasonably possible. Tree

removal to be assessed.

003 / 03 Schematic Plan - Layout of Piles for Foxborrow Fish Barrier

(1:100)

2000 200023082000

16308

20002000200020002000

16

00

16

00

Existing profile

3000

c.1m overhang of

branches to be

cut-back in advance

of piling works. 1 no.

tree to be removed.

1000

12

00

16

00

20

0

16

00

16

00

16

80

Screen

(extending 100mm above bank level)

Timber cill

Timber board

side wall cut-off

10

0

Water depths recorded on

27th Aug 2019

17

32

2

7

6

9

2000

2000

12

00

Very loose fine to

medium SAND

Plastic amorphous

PEAT

Medium dense very

gravelly fine to medium

SAND. Gravel angular

to subangular.

Medium dense very

gravelly fine to medium

SAND. Gravel angular

to subangular.

Soft grey silty CLAY.

Plastic amorphous

PEAT

Medium dense very

gravelly fine to medium

SAND. Gravel angular

to subangular.

Very gravelly fine to

medium SAND. Gravel

angular to subangular.

Soft to firm grey silty CLAY.

River channel locally dredged /

de-silted to suit. Cill boards inserted to

ensure that clear height above bed

>100mm. Timber cut off to extend well

into PEAT to form effective cut-off.

Vertical and inclined

screwpile to form tension /

compression couple. Pile

and cap designed by

screwpile specialist in mild

steel allowing for corosion

for 15 year design life.

3

0

.0

0

°

Horizontal truss formed in

sliding hollow sections

to be site drilled and bolted.

355 UBP Steel piles

(cut-off 300mm above bank level)

305 UBP 88

100kN

UNFACTORED

100kN

UNFACTORED

100kN

UNFACTORED

100kN

UNFACTORED

Horizontal truss formed in

sliding hollow sections

to be site drilled and bolted.

355 305 (see elevations for

weights) UBP steel pile.

Screwpiles to form tension

compression couple. Pile

and Cap designed by

screwpile specialist.

3

0

.0

0

°

Hydraulic cut-off formed 3m into

peat. Subject to further testing of

peat to validate design parameters.

Bed upstream and downstream of screen

desilted, TENSAR TRIAX TX-G Geogrid laid over

peat. 350mm of rip-rap 40mm to 150mm laid

over membranes. Membrane turned up and

lapped back into themselves at upstream and

down stream end. TRIAX Grid to be physically

joined to adjoining sheets using proprietary clips

suitable for the system.

Allow to fixed geogrid to top of cut-off panel using

oak batten (75mm sq) and SS coach bolts.

Cut off suspended on chains

with turn-buckles, to eye bolt

through cut-off panel.

80008000

30

00

Solid oak web infill above top of

cut-off, bolted to Pile using

Stainless Steel Bolt and isolating

sleeve.

UNFACTORED

LOAD AS

INDICATED

ON PLAN

003 / 05 Schematic Section - Fish Barrier Piles

(1:100)

Bearing piles

Vertical screw piles

Raking screw piles

Waling beam

Ground Strata - See GI

Ground Strata - See GI

Eel Trap

(to facilitate

downstream

migration of eels)

Eel Fyke

(to facilitate

downstream

migration of eels)

Eel Fyke

(to facilitate

downstream

migration of eels)

Eel Fyke

(to facilitate

downstream

migration of eels)

Eel Fyke

(to facilitate

downstream

migration of eels)

Eel Fyke

(to facilitate

downstream

migration of eels)

Eel Fyke

-See Drawing 011

Eel Fyke

-See Drawing 011

25mm steel plate framed each side in Oak on

top and sides, Oak bolted to steelplate using

isolated SS M20 bolts, with nuts and washers

counter bored into sawn oak frame and

isolating sleeve @ 600c/c.

2 No. SS Eye bolt through roadplate and

isolator sleeve, for suspension of plate.

003 / 06 Detail - Hydraulic cut-off

(1:50)

3000

Elevation

Plan

1. DIMENSIONS:

● Are in millimetres unless otherwise stated.

● Marked thus (*) or c. are approximate.

● All levels are in metres to Site Datum.

2. SPECIFICATION:

All works to be carried out in accordance with the

Environment Agency Minimum Technical Requirements

which shall be the Civil Engineering Specification for the

Water Industry (CESWI).

003 / 01 Location Plan

003 / 02 Site Plan - Foxborrow Fish Barrier

(1:1250)

Access route

Proposed Foxborrow Dyke

Fish Barrier

Existing barrier

(To be retained)

Detailed Design

As shown

M.Lakin / J. BLyth

P. Kibel

SAFETY HEALTH

& ENVIRONMENTAL

INFORMATION

Managing flow & stage levels in Hoveton Broad.

- Monitor flow levels & flood warnings. Caution the

Broad is both fluvial & tidal. Up to 0.5m fluctuation in

water levels under tidal surges

- Check adequacy of pontoon for environment (draft,

anchorage & mooring) and plant & loading

requirements.

Managing flow velocities through & across

barrier works

- Monitor velocities.

Risk of falls from height

- Check depth of dredging.

-Check adequate edge protection and access

provision.

Lifting

- Check cranage lifting facilities & constraints.

- Check access weight & size restrictions for

cranage on pontoon.

Interface with public & other site operations

- Check adequate warning signs in place.

- Liaise with operators of the Broad.

Services

- Check for services.

Stability of Piling Works

- Carry out inspection of working area

- Check for conflict with trees & overhanging

branche. Carry clearance works in advance of piling

works.

It is assumed that all works will be carried out by a

competent contractor working, where appropriate, to an

approved method statement

Refer to Designer's Risk Assessment and pre-construction

phase plan.

C1

C2

CONSTRUCTION

C3

C4

C5

C6

C7

Hoveton Marshes Barrier Location

Access route for pontoon

P01 Draft issue 30 / 09 / 19

P02 For consultation 02 / 10 / 19

P03 For consultation 13 / 11 / 19

P04 Piles revised and reconfigured to address GI

findings of very deep strata of peat.

Location of eel trap & fykes added following

consultation with EA Fisheries.

13 / 01 / 21

J.Blyth / M.Lakin

AutoCAD SHX Text
Foxborrow Dike
AutoCAD SHX Text
NTL
AutoCAD SHX Text
MHW & MLW
AutoCAD SHX Text
NTL
AutoCAD SHX Text
003 2595 PO4
AutoCAD SHX Text
Hoveton Great Broad
AutoCAD SHX Text
Restoration Project -
AutoCAD SHX Text
Fish Barriers
AutoCAD SHX Text
at Hoveton Marshes, The Dam & Foxborrow Dyke
AutoCAD SHX Text
Issue
AutoCAD SHX Text
Drawing No.
AutoCAD SHX Text
TITLE
AutoCAD SHX Text
PROJECT
AutoCAD SHX Text
Project No.
AutoCAD SHX Text
Current Issue Signatures
AutoCAD SHX Text
Copyright reserved
AutoCAD SHX Text
Description
AutoCAD SHX Text
Grid
AutoCAD SHX Text
Client
AutoCAD SHX Text
Filename:
AutoCAD SHX Text
Datum
AutoCAD SHX Text
Original
AutoCAD SHX Text
Size
AutoCAD SHX Text
Scales
AutoCAD SHX Text
Issue
AutoCAD SHX Text
Status
AutoCAD SHX Text
Approver
AutoCAD SHX Text
Checker
AutoCAD SHX Text
A1
AutoCAD SHX Text
C
AutoCAD SHX Text
Author
AutoCAD SHX Text
Date
AutoCAD SHX Text
Foxborrow Barrier
AutoCAD SHX Text
Location & Site Plan
AutoCAD SHX Text
and
AutoCAD SHX Text
Schematic Plan & Elevation
Page 4: 2000 & ENVIRONMENTAL INFORMATION

004 / 02 Elevation - Fish Barrier

(1:10)

Sequence of installation:

1. Pre-fit fixed pile wall plates (L) and channels guides (G) to piles (A).

2. Install piles (A). Tolerance +/-50mm

3. Install fenders (C), notching and fixing into fixing to pile wall plates (L)

4. Lower sub-frame screen guide system (E), with pre-fitted cill boards (J) into position, and fix onto fenders (C).

5. Apply timber wedges (I) to prevent excess movement between sub-frame (E) & guides (G).

5. Lower wedge wire screens (F) into position.

30

0

Fre

eb

oa

rd

va

rie

s

c.1

50

- 2

00

mm

004 / 01 Plan - Fish Barrier

(1:10)

2000 (+/- 50mm)

℄pile

℄pile

Ch

an

ne

l d

ep

th

va

rie

s

Min

.

10

0m

m

004 / 03 Plan - Gate

(1:10)

004 / 04 Elevation - Gate

(1:10)

A

A Pile

(steel - UBP)

C Fenders

(timber)

F Removable

wedge-wire screens

(metalwork)

G Fixed guide rail

(metalwork)

E Sub-frame guide

system for screens

(metalwork)

B Screen lifting handle

(stainless steel)

J Cill boards

(timber)

K Dredged sub-grade

D Sub-frame rail

(metalwork)

Bank level

Channel bed level

Cill level

B C D E FG H I

A Pile

(steel - UBP)

F Removable

wedge-wire screens

(metalwork)

G Fixed guide rail

for cill boards (J)

(metalwork)

L RHS Gate frame

(metalwork)

B Screen lifting handle

(metalwork)

J Cill boards

(timber)

K Dredged sub-grade

M Adjustable hinge

(timber)

H Isolating clip (not shown)

Scre

en

h

eig

ht

I Web plate wedges

Cut to suit installation

(timber)

(not shown)

J PFC Waling

(steel)

(not shown)

K Steel Waling / pile connection

Adjustable to for tolerance

(steel UEA)

(not shown)

J KL

L Web plates

(timber)

(not shown)

2000

2308

2200

1. DIMENSIONS:

● Are in millimetres unless otherwise stated.

● Marked thus (*) or c. are approximate.

● All levels are in metres to Site Datum.

2. SPECIFICATION:

All works to be carried out in accordance with the

Environment Agency Minimum Technical Requirements

which shall be the Civil Engineering Specification for the

Water Industry (CESWI).

Detailed Design

As shown

M.Lakin

P. Kibel

SAFETY HEALTH

& ENVIRONMENTAL

INFORMATION

Managing flow & stage levels in Hoveton Broad.

- Monitor flow levels & flood warnings. Caution the

Broad is both fluvial & tidal. Up to 0.5m fluctuation in

water levels under tidal surges

- Check adequacy of pontoon for environment (draft,

anchorage & mooring) and plant & loading

requirements.

Managing flow velocities through & across

barrier works

- Monitor velocities.

Risk of falls from height

- Check depth of dredging.

-Check adequate edge protection and access

provision.

Lifting

- Check cranage lifting facilities & constraints.

- Check access weight & size restrictions for

cranage on pontoon.

Interface with public & other site operations

- Check adequate warning signs in place.

- Liaise with operators of the Broad.

Services

- Check for services.

Stability of Piling Works

- Carry out inspection of working area

- Check for conflict with trees & overhanging

branche. Carry clearance works in advance of piling

works.

It is assumed that all works will be carried out by a

competent contractor working, where appropriate, to an

approved method statement

Refer to Designer's Risk Assessment and pre-construction

phase plan.

C1

C2

CONSTRUCTION

C3

C4

C5

C6

C7

P01 Draft issue 30 / 09 / 19

P02 For consultation 02 / 10 / 19

P03 For consultation 13 / 11 / 19

P04 Piles revised and reconfigured to address GI

findings of very deep strata of peat.

Location of eel trap & fykes added following

consultation with EA Fisheries.

13 / 01 / 21

J.Blyth

AutoCAD SHX Text
004 2595 P04
AutoCAD SHX Text
Hoveton Great Broad
AutoCAD SHX Text
Restoration Project -
AutoCAD SHX Text
Fish Barriers
AutoCAD SHX Text
at Hoveton Marshes, The Dam & Foxborrow Dyke
AutoCAD SHX Text
Issue
AutoCAD SHX Text
Drawing No.
AutoCAD SHX Text
TITLE
AutoCAD SHX Text
PROJECT
AutoCAD SHX Text
Project No.
AutoCAD SHX Text
Current Issue Signatures
AutoCAD SHX Text
Copyright reserved
AutoCAD SHX Text
Description
AutoCAD SHX Text
Grid
AutoCAD SHX Text
Client
AutoCAD SHX Text
Filename:
AutoCAD SHX Text
Datum
AutoCAD SHX Text
Original
AutoCAD SHX Text
Size
AutoCAD SHX Text
Scales
AutoCAD SHX Text
Issue
AutoCAD SHX Text
Status
AutoCAD SHX Text
Approver
AutoCAD SHX Text
Checker
AutoCAD SHX Text
A1
AutoCAD SHX Text
C
AutoCAD SHX Text
Author
AutoCAD SHX Text
Date
AutoCAD SHX Text
Plan & Elevation of
AutoCAD SHX Text
Typical barrier & gate
AutoCAD SHX Text
For Information Purposes only Not for construction
Page 5: 2000 & ENVIRONMENTAL INFORMATION

005 / 05 Detail - Extruded Weir Strip

(1:1)

19

.8

15.7

5.1

14

.2

1000 grade UHMW polyethylene

wear strip . Ref no. PIE 233 by

Penine (- see www.penine.org) -

or similar approved. Lengths cut

to suit from standard lengths e.g.

10ft, 20ft or coils up to 500ft, in

standard white colour.

Wear strip fixed to screen rail

using stainless steel 4Ø self-

tapping screws @ top, middle &

bottom locations (3no. per side -

6no. total per screen unit).

Dim

en

sio

n A

390

39

0

390

60

5 5

30

40

150

10Ø

120 120

Hoveton Marsh

390mm 1200mm 17 kg 10

The Dam

390mm 1500mm 21 kg 20

390mm 1400mm 20 kg 8

Foxborrow Dyke

390mm 1600mm 22 kg 20

Barriers

390mm 1100mm 15 kg 4Gates

Barriers

Gates

Barriers

Gates 390mm 1500mm 21 kg 4

390mm 1300mm 18 kg 12Barriers

005 / 01 Elevation - Wedge Wire Screen Unit

(1:5)

005 / 01 Side Elevation

- Wedge Wire Screen Unit

(1:5)

005 / 01 Plan - Wedge Wire Screen Unit

(1:5)

005 / 03 Plan

- Wedge Wire Screen Unit

(1:5)

005 / 06 Table - Wedge Wire Screen Sizes

(1:5)

O/A frame width Dimension A Approx frame weightLocation No. of frames

6.35mmØ Cross-rods

28SB wedge wire profile

by Screen Systems

(Wireworkers) Ltd or

similar approved

60mm wide x 5mm deep

rectangular bar

(plastic wear strip not

indicated for clarity)

30mm wide x 5mm deep

rectangular bar

10mmØ bar bent to form handle

Extruded wear strip

Snap on plastic strip to

isolate stainless steel from

dissimilar metal frame

- See Detail 005 / 05

P01 Draft issue for comment 13 / 11 / 19

NOTES:

1. DIMENSIONS:

● Are in millimetres unless otherwise stated.

● Marked thus (*) or c. are approximate.

● All levels are in metres to Site Datum.

2. SPECIFICATION:

All works to be carried out in accordance with the Civil

Engineering Specification for the Water Industry (CESWI).

All technical requirements clauses apply unless stated as

deleted, amended or augmented in accordance with the

Contract Works Information documentation.

3. WEDGE WIRE SCREENS:

● Provision & fabrication by:

Screen Systems (Wireworkers) Ltd

Haydock Lane Industrial Estate

Haydock Lane

St Helens

WA11 9UW

01942 272895

or similar approved.

● 28SB (stainless steel gr 316L) WedgeWire

● Aperture Size = 2mm,

● 6.35mmØ cross-rods at 50mm centres.

4. STEELWORK:

● All stainless steel to BS5950.

●All fabricated steelwork structures executed to conform to

BS EN 1090-2.

● All other associated steelwork e.g. solid bar 5mm thk

framing in stainless steel 316L, amply welded to wedge wire.

Welding of wedge wire to framing to be 6FW unless

otherwise stated or other approved.

5. WEAR STRIP:

● 1000 grade UHMW polyethylene wear strip . Ref no. PIE

233 by Penine (- see www.penine.org) - or similar approved.

Lengths cut to suit from standard lengths e.g. 10ft, 20ft or

coils up to 500ft, in standard white colour.

Detailed Design

As shown

M.Lakin

P. Kibel

SAFETY HEALTH

& ENVIRONMENTAL

INFORMATION

Managing flow & stage levels in Hoveton Broad.

- Monitor flow levels & flood warnings. Caution the

Broad is both fluvial & tidal. Up to 0.5m fluctuation in

water levels under tidal surges

- Check adequacy of pontoon for environment (draft,

anchorage & mooring) and plant & loading

requirements.

Managing flow velocities through & across

barrier works

- Monitor velocities.

Risk of falls from height

- Check depth of dredging.

-Check adequate edge protection and access

provision.

Lifting

- Check cranage lifting facilities & constraints.

- Check access weight & size restrictions for

cranage on pontoon.

Interface with public & other site operations

- Check adequate warning signs in place.

- Liaise with operators of the Broad.

Services

- Check for services.

Stability of Piling Works

- Carry out inspection of working area

- Check for conflict with trees & overhanging

branche. Carry clearance works in advance of piling

works.

It is assumed that all works will be carried out by a

competent contractor working, where appropriate, to an

approved method statement

Refer to Designer's Risk Assessment and pre-construction

phase plan.

C1

C2

CONSTRUCTION

C3

C4

C5

C6

C7

P02 No issue

P03 No issue

P04 Minor change to drawing layout only 13 / 01 / 21

J.Blyth

SAFETY HEALTH

& ENVIRONMENTAL

INFORMATION

Caution - Sharp Edges

- All sharp edges and burrs to be removed.

Caution - Lifting

- Check adequate lifting facilities & constraints.

Check - All fabricated elements are clean and free

from dust, and burrings on completion.

It is assumed that all works will be carried out by a

competent contractor working, where appropriate, to an

approved method statement

!

FABRICATION

!

!

AutoCAD SHX Text
005 2595 P04
AutoCAD SHX Text
Hoveton Great Broad
AutoCAD SHX Text
Restoration Project -
AutoCAD SHX Text
Fish Barriers
AutoCAD SHX Text
at Hoveton Marshes, The Dam & Foxborrow Dyke
AutoCAD SHX Text
Issue
AutoCAD SHX Text
Drawing No.
AutoCAD SHX Text
TITLE
AutoCAD SHX Text
PROJECT
AutoCAD SHX Text
Project No.
AutoCAD SHX Text
Current Issue Signatures
AutoCAD SHX Text
Copyright reserved
AutoCAD SHX Text
Description
AutoCAD SHX Text
Grid
AutoCAD SHX Text
Client
AutoCAD SHX Text
Filename:
AutoCAD SHX Text
Datum
AutoCAD SHX Text
Original
AutoCAD SHX Text
Size
AutoCAD SHX Text
Scales
AutoCAD SHX Text
Issue
AutoCAD SHX Text
Status
AutoCAD SHX Text
Approver
AutoCAD SHX Text
Checker
AutoCAD SHX Text
A1
AutoCAD SHX Text
C
AutoCAD SHX Text
Author
AutoCAD SHX Text
Date
AutoCAD SHX Text
Wedge Wire Screens
AutoCAD SHX Text
Plan & Elevations
AutoCAD SHX Text
For Information Purposes only Not for construction
Page 6: 2000 & ENVIRONMENTAL INFORMATION

O/A frame width Dimension A Approx frame weightLocation

Hoveton Marsh

1700mm 1400mm kg

No. of frames

3

The Dam

1700mm 1900mm kg 8

Foxborrow Dyke

1700mm 2000mm kg 2

Barriers

Barriers

Barriers

005 / 04 Table - Frame Sizes

(1:5)

1700mm 2200mm kg 3Barriers

006 / 01 Elevation - Frame

(1:5)

1700

Dim

en

sio

n A

1700

10

07

57

5

425 425425

70 325

425

70325

006 / 02 Plan - Frame

(1:5)

006 / 03 Side Elevation - Frame

(1:5)

27

25

Ø

1

4

70

100 x 50 X 10 PFC

75 x 50 UEA

100 x 50 X 10 PFC

75 x 50 UEA

75 x 50 UEA

flange removed locally

100 x 50 X 10 PFC

25 x 100 Timber plate (planed or cut to site

measurement as necessary for fit). D30 oak

countersunk screwed to sub-frame @ 300 c/c.

325

NOTES

1. LEVELS & DIMENSIONS:

● Are in millimetres unless otherwise stated.

● Marked thus (*) are approximate.

● All levels are in metres to Site Datum.

2. SPECIFICATION:

All works to be carried out in accordance with the Civil

Engineering Specification for the Water Industry (CESWI).

All technical requirements clauses apply unless stated as

deleted, amended or augmented in accordance with the

Contract Works Information documentation.

3. STEELWORK:

● All steelwork to BS5950.

● All steelwork to be grade S355.

4. FABRICATION:

● Fabrication drawings to be prepared by the fabricator.

●All fabricated structural steelwork structures executed to

conform to BS EN 1090-2.

●Size & fitment of gate components to suit fabrication

tolerances and checked for fit prior to deliver to site.

●All SHS to SHS & SHS to RHS welds to be full continuous

butt welds to suit thickness of member size.

●All plate to section welds full continuous 6FW or

stitch-welded as indicated (e.g. 50 -150: 50weld, 100miss).

5. PAINT SYSTEM:

Either:

● Steelwork to be hot-dipped galvanised:

● Steelwork to be prepared in accordance with the the

Galvanizer's Association Best Practice Guide for Venting

and Draining.

Or:

● Roller applied paint system applied to external areas only.

Applied at the factory / fabrication yard.

● 1no. primer coat of Sigmacover 280 two-part epoxy paint

(grey) or similar to be applied in accordance with

manufacturer's instructions.

● 1no. top semi-gloss coat of Sigmacover 2 two-part epoxy

paint (colour e.g. grey - to be confirmed) or similar to be

applied in accordance with manufacturer's instructions.

● Touch-up application applied on site to cover over excess

sika-flex areas or scratched & / damaged paintwork areas.

Detailed Design

As shown

M.Lakin

P. Kibel

SAFETY HEALTH

& ENVIRONMENTAL

INFORMATION

Managing flow & stage levels in Hoveton Broad.

- Monitor flow levels & flood warnings. Caution the

Broad is both fluvial & tidal. Up to 0.5m fluctuation in

water levels under tidal surges

- Check adequacy of pontoon for environment (draft,

anchorage & mooring) and plant & loading

requirements.

Managing flow velocities through & across

barrier works

- Monitor velocities.

Risk of falls from height

- Check depth of dredging.

-Check adequate edge protection and access

provision.

Lifting

- Check cranage lifting facilities & constraints.

- Check access weight & size restrictions for

cranage on pontoon.

Interface with public & other site operations

- Check adequate warning signs in place.

- Liaise with operators of the Broad.

Services

- Check for services.

Stability of Piling Works

- Carry out inspection of working area

- Check for conflict with trees & overhanging

branche. Carry clearance works in advance of piling

works.

It is assumed that all works will be carried out by a

competent contractor working, where appropriate, to an

approved method statement

Refer to Designer's Risk Assessment and pre-construction

phase plan.

C1

C2

CONSTRUCTION

C3

C4

C5

C6

C7

P01 Draft issue comment 13 / 11 / 19

P02 No issue

P03 No issue

J.Blyth

P04 Minor change to drawing layout only 13 / 01 / 21

SAFETY HEALTH

& ENVIRONMENTAL

INFORMATION

Caution - Sharp Edges

- All sharp edges and burrs to be removed.

Caution - Lifting

- Check adequate lifting facilities & constraints.

Check - All fabricated elements are clean and free

from dust, and burrings on completion.

It is assumed that all works will be carried out by a

competent contractor working, where appropriate, to an

approved method statement

!

FABRICATION

!

!

AutoCAD SHX Text
006 2595 P04
AutoCAD SHX Text
Hoveton Great Broad
AutoCAD SHX Text
Restoration Project -
AutoCAD SHX Text
Fish Barriers
AutoCAD SHX Text
at Hoveton Marshes, The Dam & Foxborrow Dyke
AutoCAD SHX Text
Issue
AutoCAD SHX Text
Drawing No.
AutoCAD SHX Text
TITLE
AutoCAD SHX Text
PROJECT
AutoCAD SHX Text
Project No.
AutoCAD SHX Text
Current Issue Signatures
AutoCAD SHX Text
Copyright reserved
AutoCAD SHX Text
Description
AutoCAD SHX Text
Grid
AutoCAD SHX Text
Client
AutoCAD SHX Text
Filename:
AutoCAD SHX Text
Datum
AutoCAD SHX Text
Original
AutoCAD SHX Text
Size
AutoCAD SHX Text
Scales
AutoCAD SHX Text
Issue
AutoCAD SHX Text
Status
AutoCAD SHX Text
Approver
AutoCAD SHX Text
Checker
AutoCAD SHX Text
A1
AutoCAD SHX Text
C
AutoCAD SHX Text
Author
AutoCAD SHX Text
Date
AutoCAD SHX Text
Screen Frames
AutoCAD SHX Text
Plan & Elevations
AutoCAD SHX Text
For Information Purposes only Not for construction
Page 7: 2000 & ENVIRONMENTAL INFORMATION

Board

length

Board

width

Approx

board weight

Location No.

of boards *

007 / 01 Elevation - Assemble Cill Boards in Frame

(1:5)

007 / 03 End Elevation

- Cill Boards in Frame

(1:5)

Hoveton Marsh

400mm 75mm 6kg 36

The Dam

400mm 75mm 6kg 76

Foxborrow Dyke

400mm 2000mm 6kg 52

Barriers

Barriers

Barriers

007 / 05 Table - Cill Boards

(1:5)

2150mm* 100mm 39kg 3Gates

007 / 02 Plan - Assemble Cill Boards in Frame

(1:5)

Board

depth

200mm

Gates

Gates

3950mm* 200mm 72kg 4Barriers 100mm

1750mm* 100mm 32kg 20Barriers

200mm

200mm

200mm

200mm

200mm

* Subject to site measurement and re-measurement of numbers on site to suit

007 / 04 Plan - Assembled Cill Timbers in Bank Bays

(1:5)

2150mm* 100mm 39kg 2200mm

007 / 04 Plan - Assembled Cill Timbers in Gate Bay

(1:5)

20

0

85

c.7

5

10

07

5

c.2

5

Locking fastener

Glavanised mild steel

countersunk M8 coach screw

Timber wedge to secure stop-log

prior to installing locking fastener

Cill timber

- See 007 / 09-011

Stop-board timber

- See 007 / 06-08

Stop-board timber

- See 007 / 06-08

Stop-board timber

- See 007 / 06-08

Steel frame

- See Drawing 006

Locking fastener

Glavanised mild steel

countersunk M8 coach screw

Timber wedge to secure stop-log

prior to installing locking fastener

Gate cill timber

Projection to suit gate

position to achieve flush fit

2150

1750

007 / 06 Plan - Cill Board

(1:10)

400

75

007 / 07 Side Elevation

- Cill Board

(1:10)

400

200

007 / 08 End Elevation

- Cill Board

(1:10)

200

75

Length - Subject to site measurement

007 / 10 Side Elevation - Gate Cill

(1:10)

Length - Subject to site measurement

007 / 11 End Elevation

- Gate Cill

(1:10)

200

75

007 / 09 Plan - Gate Cill

(1:10)

75

100

25

Subject to site

measurement

NOTES

1. LEVELS & DIMENSIONS:

● Are in millimetres unless otherwise stated.

● Marked thus (*) are approximate.

● All levels are in metres to Site Datum.

2. SPECIFICATION:

All works to be carried out in accordance with the Civil

Engineering Specification for the Water Industry (CESWI).

All technical requirements clauses apply unless stated as

deleted, amended or augmented in accordance with the

Contract Works Information documentation.

3. TIMBER

●All timber shall be in accordance with BS5268.

●All timber shall be strength class D30 oak or similar to

provide a durable, robust timber suitable for a target 20 year

design life, service Class 3.

●All timber shall carry the Forest Stewardship Council (FSC)

trademark or other label from an equivalent internationally

recognised, globally applicable, independent certification

scheme for good forest management.

●Tropical hardwood will not be used.

●The purchase of recycled timber is preferable to the

purchase of virgin timber from a waste hierarchy and

resource use perspective. Recycled timber is defined as

timber which is being used for a different purpose than the

purpose for which the tree was originally felled.

●All timberwork shall be subject to site measurement & / or

fabricated elements prior to commencement of cutting

boards.

●All oak timbers to be untreated, relying upon the natural

tannins within the wood.

4. STEELWORK:

● All steelwork to BS5950.

● All steelwork to be grade S355.

Detailed Design

As shown

M.Lakin

P. Kibel

SAFETY HEALTH

& ENVIRONMENTAL

INFORMATION

Managing flow & stage levels in Hoveton Broad.

- Monitor flow levels & flood warnings. Caution the

Broad is both fluvial & tidal. Up to 0.5m fluctuation in

water levels under tidal surges

- Check adequacy of pontoon for environment (draft,

anchorage & mooring) and plant & loading

requirements.

Managing flow velocities through & across

barrier works

- Monitor velocities.

Risk of falls from height

- Check depth of dredging.

-Check adequate edge protection and access

provision.

Lifting

- Check cranage lifting facilities & constraints.

- Check access weight & size restrictions for

cranage on pontoon.

Interface with public & other site operations

- Check adequate warning signs in place.

- Liaise with operators of the Broad.

Services

- Check for services.

Stability of Piling Works

- Carry out inspection of working area

- Check for conflict with trees & overhanging

branche. Carry clearance works in advance of piling

works.

It is assumed that all works will be carried out by a

competent contractor working, where appropriate, to an

approved method statement

Refer to Designer's Risk Assessment and pre-construction

phase plan.

C1

C2

CONSTRUCTION

C3

C4

C5

C6

C7

P01 Draft issue for comment 13 / 11 / 19

P04 Piles revised and reconfigured to address GI

findings of very deep strata of peat.

Cill board lengths adjusted to suit.

13 / 01 /21

J.Blyth

P02 No issue

P03 No issue

AutoCAD SHX Text
007 2595 P04
AutoCAD SHX Text
Hoveton Great Broad
AutoCAD SHX Text
Restoration Project -
AutoCAD SHX Text
Fish Barriers
AutoCAD SHX Text
at Hoveton Marshes, The Dam & Foxborrow Dyke
AutoCAD SHX Text
Issue
AutoCAD SHX Text
Drawing No.
AutoCAD SHX Text
TITLE
AutoCAD SHX Text
PROJECT
AutoCAD SHX Text
Project No.
AutoCAD SHX Text
Current Issue Signatures
AutoCAD SHX Text
Copyright reserved
AutoCAD SHX Text
Description
AutoCAD SHX Text
Grid
AutoCAD SHX Text
Client
AutoCAD SHX Text
Filename:
AutoCAD SHX Text
Datum
AutoCAD SHX Text
Original
AutoCAD SHX Text
Size
AutoCAD SHX Text
Scales
AutoCAD SHX Text
Issue
AutoCAD SHX Text
Status
AutoCAD SHX Text
Approver
AutoCAD SHX Text
Checker
AutoCAD SHX Text
A1
AutoCAD SHX Text
C
AutoCAD SHX Text
Author
AutoCAD SHX Text
Date
AutoCAD SHX Text
Timber Boards
AutoCAD SHX Text
Plan & Elevations
AutoCAD SHX Text
For Information Purposes only Not for construction
Page 8: 2000 & ENVIRONMENTAL INFORMATION

Gate

length

Gate

height

Gate weight

(exc. screens)

Location No.

of gates

Hoveton Marsh

Foxborrow Dyke

008 / 05 Table - Gate

(1:5)

2100mm 1600mm 200kg 1Gate

Gate

* Subject to site measurement

2100mm 1200mm 185kg 2 (1 handed)

Gate length

Ga

te

h

eig

ht

2000 (gate clearance)

008 / 02 Elevation - Gate

(1:5)

008 / 01 Plan - Gate

(1:5)

008 / 03 Section - Gate

(1:5)

40 100

50

60

60

c.85

50 32550 50 50 325 50 50 325 50 50 325 50

Ga

te

h

eig

ht

45

Perimeter

60 x 40 X 3 RHS

(Full butt welds)

Screen Guides

100 x 50 PFC

(Cont. 6mm FW to RHS)

Brace

60 x 30 X 3 RHS

(Full butt welds)

Gate perimeter

60 x 40 X 3 RHS

(Full butt welds)

Gate strut

60 x 30 X 3 RHS

(Full butt welds)

Perimeter

60 x 40 X 3 RHS

(Full butt welds)

Perimeter

60 x 40 X 3 RHS

(Full butt welds)

Brace

60 x 30 X 3 RHS

(Full butt welds)

Hinge

Hinge

All dims subject to fabrication

100 x 100 EA with M20 x 75 mm

long threaded hinge pin fully

6FW with locking nyloc nut

10mm thk plate

6mmFW 50mm

stitch welded to RHS

M20 x 150 mm long threaded eye

collar bolt with locking Nyloc nuts

to adjust gate angle

Locking bar

All dims subject to fabrication

100 x 50 PFC

In fill plate

5mm plate

stitch welded

(50-150) 3FW to

gate PFC & RHS

75 notch cut in 60 x 60 x 3 SHS

to accommodate gate locking pin

Locking position

60 x 30 X 3 RHS

(6FW to RHS)

14

0

10

50

20

0

Top of UBP gate post

UBP Pile

100

NOTES

1. LEVELS & DIMENSIONS:

● Are in millimetres unless otherwise stated.

● Marked thus (*) are approximate.

● All levels are in metres to Site Datum.

2. SPECIFICATION:

All works to be carried out in accordance with the Civil

Engineering Specification for the Water Industry (CESWI).

All technical requirements clauses apply unless stated as

deleted, amended or augmented in accordance with the

Contract Works Information documentation.

3. STEELWORK:

● All steelwork to BS5950.

● All steelwork to be grade S355.

4. FABRICATION:

● Fabrication drawings to be prepared by the fabricator.

●All fabricated structural steelwork structures executed to

conform to BS EN 1090-2.

●Size & fitment of gate components to suit fabrication

tolerances and checked for fit prior to deliver to site.

●All SHS to SHS & SHS to RHS welds to be full continuous

butt welds to suit thickness of member size.

●All plate to section welds full continuous 6FW or

stitch-welded as indicated (e.g. 50 -150: 50weld, 100miss).

Detailed Design

As shown

M.Lakin

P. Kibel

SAFETY HEALTH

& ENVIRONMENTAL

INFORMATION

Managing flow & stage levels in Hoveton Broad.

- Monitor flow levels & flood warnings. Caution the

Broad is both fluvial & tidal. Up to 0.5m fluctuation in

water levels under tidal surges

- Check adequacy of pontoon for environment (draft,

anchorage & mooring) and plant & loading

requirements.

Managing flow velocities through & across

barrier works

- Monitor velocities.

Risk of falls from height

- Check depth of dredging.

-Check adequate edge protection and access

provision.

Lifting

- Check cranage lifting facilities & constraints.

- Check access weight & size restrictions for

cranage on pontoon.

Interface with public & other site operations

- Check adequate warning signs in place.

- Liaise with operators of the Broad.

Services

- Check for services.

Stability of Piling Works

- Carry out inspection of working area

- Check for conflict with trees & overhanging

branche. Carry clearance works in advance of piling

works.

It is assumed that all works will be carried out by a

competent contractor working, where appropriate, to an

approved method statement

Refer to Designer's Risk Assessment and pre-construction

phase plan.

C1

C2

CONSTRUCTION

C3

C4

C5

C6

C7

P01 Draft issue for comment 13 / 11 / 19

P04 Piles revised and reconfigured to address GI

findings of very deep strata of peat.

Gate posts revised to UBP.

13 / 01 / 21

P02 No issue

P03 No issue

J.Blyth

SAFETY HEALTH

& ENVIRONMENTAL

INFORMATION

Caution - Sharp Edges

- All sharp edges and burrs to be removed.

Caution - Lifting

- Check adequate lifting facilities & constraints.

Check - All fabricated elements are clean and free

from dust, and burrings on completion.

It is assumed that all works will be carried out by a

competent contractor working, where appropriate, to an

approved method statement

!

FABRICATION

!

!

AutoCAD SHX Text
008 2595 P04
AutoCAD SHX Text
Hoveton Great Broad
AutoCAD SHX Text
Restoration Project -
AutoCAD SHX Text
Fish Barriers
AutoCAD SHX Text
at Hoveton Marshes, The Dam & Foxborrow Dyke
AutoCAD SHX Text
Issue
AutoCAD SHX Text
Drawing No.
AutoCAD SHX Text
TITLE
AutoCAD SHX Text
PROJECT
AutoCAD SHX Text
Project No.
AutoCAD SHX Text
Current Issue Signatures
AutoCAD SHX Text
Copyright reserved
AutoCAD SHX Text
Description
AutoCAD SHX Text
Grid
AutoCAD SHX Text
Client
AutoCAD SHX Text
Filename:
AutoCAD SHX Text
Datum
AutoCAD SHX Text
Original
AutoCAD SHX Text
Size
AutoCAD SHX Text
Scales
AutoCAD SHX Text
Issue
AutoCAD SHX Text
Status
AutoCAD SHX Text
Approver
AutoCAD SHX Text
Checker
AutoCAD SHX Text
A1
AutoCAD SHX Text
C
AutoCAD SHX Text
Author
AutoCAD SHX Text
Date
AutoCAD SHX Text
Hoveton & Foxborrow Gates
AutoCAD SHX Text
Plan & Elevations
AutoCAD SHX Text
For Information Purposes only Not for construction
Page 9: 2000 & ENVIRONMENTAL INFORMATION

Gate

length

Gate

height

Gate weight

(exc. screens)

Location No.

of gates

The Dam

009 / 05 Table - Gate

(1:5)

Gate 4100mm 1500mm 325kg 1

Gate length

Ga

te

h

eig

ht

3646 gate clearance

20

0

009 / 02 Elevation - Gate

(1:10)

009 / 01 Plan - Gate

(1:10)

009 / 03 Section - Gate

(1:10)

40

100

50

60

60

15

00

45

50 50 50

325

50

Perimeter

60 x 40 X 3 RHS

(Full butt welds)

Brace

60 x 30 X 3 RHS

(Full butt welds)

Gate perimeter

60 x 40 X 3 RHS

(Full butt welds)

Gate strut

60 x 30 X 3 RHS

(Full butt welds)

Perimeter

60 x 40 X 3 RHS

(Full butt welds)

Perimeter

60 x 40 X 3 RHS

(Full butt welds)

Brace

60 x 30 X 3 RHS

(Full butt welds)

Hinge

Hinge

All dims subject to fabrication

100 x 100 EA with M20 x 75 mm

long threaded hinge pin fully

6FW with locking nyloc nut

10mm thk plate

6mmFW welded

to RHS

M20 x 150 mm long threaded eye

collar bolt with locking Nyloc nuts

to adjust gate angle

Locking bar

All dims subject to fabrication

60 x 60 x 3 SHS

3mmFW 50-150

stitch welded to

SHS gate post

M20 locking bar with flat plate & lifting

handle to provide double shear locking

position to prevent gate twist

100 x 50 PFC

In fill plate

5mm plate

stitch welded

(50-150) 3FW to

gate PFC & RHS

Brace

60 x 30 X 3 RHS

(Full butt welds)

Gate Post

UBP Pile

75 notch cut in 60 x 60 x 3 SHS

to accommodate gate locking pin

Locking position

60 x 30 X 3 RHS

(6FW to RHS)

4000

14

0

10

50

100

Top of UBP gate post

NOTES

1. LEVELS & DIMENSIONS:

● Are in millimetres unless otherwise stated.

● Marked thus (*) are approximate.

● All levels are in metres to Site Datum.

2. SPECIFICATION:

All works to be carried out in accordance with the Civil

Engineering Specification for the Water Industry (CESWI).

All technical requirements clauses apply unless stated as

deleted, amended or augmented in accordance with the

Contract Works Information documentation.

3. STEELWORK:

● All steelwork to BS5950.

● All steelwork to be grade S355.

4. FABRICATION:

● Fabrication drawings to be prepared by the fabricator.

●All fabricated structural steelwork structures executed to

conform to BS EN 1090-2.

●Size & fitment of gate components to suit fabrication

tolerances and checked for fit prior to deliver to site.

●All SHS to SHS & SHS to RHS welds to be full continuous

butt welds to suit thickness of member size.

●All plate to section welds full continuous 6FW or

stitch-welded as indicated (e.g. 50 -150: 50weld, 100miss).

5. PAINT SYSTEM:

Either:

● Steelwork to be hot-dipped galvanised:

● Steelwork to be prepared in accordance with the the

Galvanizer's Association Best Practice Guide for Venting

and Draining.

Or:

● Roller applied paint system applied to external areas only.

Applied at the factory / fabrication yard.

● 1no. primer coat of Sigmacover 280 two-part epoxy paint

(grey) or similar to be applied in accordance with

manufacturer's instructions.

● 1no. top semi-gloss coat of Sigmacover 2 two-part epoxy

paint (colour e.g. grey - to be confirmed) or similar to be

applied in accordance with manufacturer's instructions.

● Touch-up application applied on site to cover over excess

sika-flex areas or scratched & / damaged paintwork areas.

Detailed Design

As shown

M.Lakin

P. Kibel

SAFETY HEALTH

& ENVIRONMENTAL

INFORMATION

Managing flow & stage levels in Hoveton Broad.

- Monitor flow levels & flood warnings. Caution the

Broad is both fluvial & tidal. Up to 0.5m fluctuation in

water levels under tidal surges

- Check adequacy of pontoon for environment (draft,

anchorage & mooring) and plant & loading

requirements.

Managing flow velocities through & across

barrier works

- Monitor velocities.

Risk of falls from height

- Check depth of dredging.

-Check adequate edge protection and access

provision.

Lifting

- Check cranage lifting facilities & constraints.

- Check access weight & size restrictions for

cranage on pontoon.

Interface with public & other site operations

- Check adequate warning signs in place.

- Liaise with operators of the Broad.

Services

- Check for services.

Stability of Piling Works

- Carry out inspection of working area

- Check for conflict with trees & overhanging

branche. Carry clearance works in advance of piling

works.

It is assumed that all works will be carried out by a

competent contractor working, where appropriate, to an

approved method statement

Refer to Designer's Risk Assessment and pre-construction

phase plan.

C1

C2

CONSTRUCTION

C3

C4

C5

C6

C7

P01 Draft issue for comment 13 / 11 / 19

P04 Piles revised and reconfigured to address GI

findings of very deep strata of peat.

Gates adjusted to suit & gates posts rev to UBP

P02 No issue

P03 No issue

J.Blyth

SAFETY HEALTH

& ENVIRONMENTAL

INFORMATION

Caution - Sharp Edges

- All sharp edges and burrs to be removed.

Caution - Lifting

- Check adequate lifting facilities & constraints.

Check - All fabricated elements are clean and free

from dust, and burrings on completion.

It is assumed that all works will be carried out by a

competent contractor working, where appropriate, to an

approved method statement

!

FABRICATION

!

!

13 / 01 /21

AutoCAD SHX Text
009 2595 P02
AutoCAD SHX Text
Hoveton Great Broad
AutoCAD SHX Text
Restoration Project -
AutoCAD SHX Text
Fish Barriers
AutoCAD SHX Text
at Hoveton Marshes, The Dam & Foxborrow Dyke
AutoCAD SHX Text
Issue
AutoCAD SHX Text
Drawing No.
AutoCAD SHX Text
TITLE
AutoCAD SHX Text
PROJECT
AutoCAD SHX Text
Project No.
AutoCAD SHX Text
Current Issue Signatures
AutoCAD SHX Text
Copyright reserved
AutoCAD SHX Text
Description
AutoCAD SHX Text
Grid
AutoCAD SHX Text
Client
AutoCAD SHX Text
Filename:
AutoCAD SHX Text
Datum
AutoCAD SHX Text
Original
AutoCAD SHX Text
Size
AutoCAD SHX Text
Scales
AutoCAD SHX Text
Issue
AutoCAD SHX Text
Status
AutoCAD SHX Text
Approver
AutoCAD SHX Text
Checker
AutoCAD SHX Text
A1
AutoCAD SHX Text
C
AutoCAD SHX Text
Author
AutoCAD SHX Text
Date
AutoCAD SHX Text
The Dam Gate
AutoCAD SHX Text
Plan & Elevations
AutoCAD SHX Text
For Information Purposes only Not for construction
Page 10: 2000 & ENVIRONMENTAL INFORMATION

010 / 02 Schematic Sectional Elevation - Eel Trap

(1:5)

010 / 03 Elevation - View from Downstream

(1:5)

010 / 04 Elevation - View from Upstream

(1:5)

Downstream Upstream

010 / 01 Plan - Eel Trap

(1:5)

1no. req

Assembled trap weight (exc. screen) = 35kg

390

60

0

900

60

0

310 Max. width of trap

To ensure fit between screen frames

Modified wedge

wire screen unit

-See Drawing 005

Guide rail slot for closing off

trap with a handstop.

Subject to fabrication

detailing to suit.

Otter screen 6Ø

bars @ 85mm

centres vert & horiz

Conical fyke with 8

mm perforations

@ 12mm pitch

(open area 40%)

-See Drawing 011

for dims.

Trap sides formed with stainless steel 316 plate with

2mm perforations @ 3.5mm pitch

(open area 30%). Plate lapped and amply stitch-welded

to inside face of angle; so that EA face is external.

Trap bolted to modified

screen for ease of

replacement and

transportation

Water vole escape routes

formed from 76.2Ø x 1.5mm

thk stainless steel tubing x

50mm long. Spot weld to

perforated end plate. Sharp

edges to be removed.

Water vole escape routes in upstream

trap face. Formed from 76.2Ø x 1.5mm

thk stainless steel tubing x 50mm long,

spot weld to perforated end plate.

Sock to prevent upstream

migration of fish through

fyke. To be funnel shape

75mm to 90mm diameter

and 115mm in length to

accommodate installation.

To be silt net or similar.

Cable tie

around fyke

sock to hold

in place

Additional

reinforcement to

stop fyke net

from sliping

3no. proprietary 316 stainless steel

3'' butt hinges x 2'' x 2mm cont. FW

to trap frame to allow lid opening for

release of fish and eels

(Subject to fabrication detailing)

Conical fyke with 8 mm

perforations @ 12mm pitch

(open area 40%)

Trap sides and dn/s face with 1mm

thk stainless steel plate 2mm

perforations @ 3.5mm pitch open

area 30% on top, bottom and

downstream faces

All sharp edges to

be fully radiused by

grinding or routing

M8 set screw bolts x 30 and nyloc nuts

@ equal centres, typically 125mm,

typically arranged as portrayed.

M8 set screw bolts x 30 and nyloc nuts

@ equal centres, typically 125mm,

typically arranged as portrayed. Drill

holes 10Ø.

59

0

M8 set screw bolts x 30 long

and nyloc nuts @ 125mm equal

typically arranged as portrayed.

Eel trap formed

from stainless

steel 40 x 40 x

4thk EA. Cont

butt weld to

form frame.

54

0

40 x 40 x 4thk EA side wall

stiffeners. Sharp edges

radiused-of. Cont. 4FW to trap

frame. (Not shown on end

elevations for clarity).

External flange

formed from 40 x40

x 4thk EA welded to

trap and bolted to

screen.

60

0

30

0

10mmØ bar bent to form

handles. Symmetrically located.

Offset from ends to suit. Subject

to fabrication detailing.

40

40

Eel trap frame formed from

stainless steel 40 x 40 x 4thk

EA. Cont butt weld to form

frame.

Ø

7

6

Ø

7

6

Eel trap frame formed from

stainless steel 40 x 40 x 4thk

EA. Cont butt weld to form

frame.

External flange formed from

40 x40 x 4thk EA welded to

trap and bolted to screen.

Otter screen bars 6Ø @ 85mm

centres vert & horiz

Upstream trap face with 1.5mm

thk stainless steel plate 8mm

perforations @ 12mm pitch,

40% open area.

5

900

31

0 M

ax. w

id

th

o

f tra

p

To

e

nsu

re

fit b

etw

ee

n scre

en

fra

me

s

50

150

Fyke with cont. FW to trap frame

External flange formed from 40

x40 x 4thk EA welded to trap

and bolted to screen with M8

stainless steel set screw bolts

Eel trap frame formed from

stainless steel 40 x 40 x 4thk

EA. Cont butt weld to form

frame.

10mmØ bar bent to form

handles. Symmetrically located.

Offset from ends to suit. Subject

to fabrication detailing.

22

3no. proprietary 316 stainless steel

hasp and staple locks welded for client

padlock. Subject to fabrication detailing

3no. proprietary 316 stainless steel 3'' butt

hinges x 2'' x 2mm cont. FW to trap frame to

allow lid opening for release of fish and eels

(Subject to fabrication detailing)

Lid formed from stainless steel 316 plate

with 2mm perforations @ 3.5mm pitch

(open area 30%), framed with & reinforced

with ss 316 40 x 4 thk flat bar across lid at

hinge & lock. NB Base strengthened with

40 x 4 thk plate to mirror lid.

P01 Draft issue for EA Fisheries comment 7 / 10 / 20

J.Rana

Detailed Design

As shown

M.Lakin

P. Kibel

P02 Draft issue for EA Fisheries comment 27/11/20

1. DIMENSIONS:

● Are in millimetres unless otherwise stated.

● Marked thus (*) or c. are approximate.

● All levels are in metres to Site Datum.

2. SPECIFICATION:

All works to be carried out in accordance with the Civil

Engineering Specification for the Water Industry (CESWI).

All technical requirements clauses apply unless stated as

deleted, amended or augmented in accordance with the

Contract Works Information documentation.

3. STEELWORK:

● All stainless steel to BS5950.

●All fabricated steelwork structures executed to conform to

BS EN 1090-2.

● All other associated steelwork e.g. solid bar 5mm thk

framing in stainless steel 316L, amply welded to wedge wire.

● All welds 4FW cont. unless otherwise stated.

● Fasteners to be M8 X 25 hex head set screw bolts x 25mm

long + Nyloc nuts in stainless steel A2 (304).

P04 Revised issue with minor revisions & further 13 / 01 / 21

details provided. Renamed dwg 010.

P03 No issue

SAFETY HEALTH

& ENVIRONMENTAL

INFORMATION

Caution - Sharp Edges

- All sharp edges and burrs to be removed.

Caution - Lifting

- Check adequate lifting facilities & constraints.

Check - All fabricated elements are clean and free

from dust, and burrings on completion.

It is assumed that all works will be carried out by a

competent contractor working, where appropriate, to an

approved method statement

!

FABRICATION

!

!

AutoCAD SHX Text
012
AutoCAD SHX Text
03
AutoCAD SHX Text
03
AutoCAD SHX Text
012
AutoCAD SHX Text
012
AutoCAD SHX Text
02
AutoCAD SHX Text
02
AutoCAD SHX Text
012
AutoCAD SHX Text
010 2595 P04
AutoCAD SHX Text
Hoveton Great Broad
AutoCAD SHX Text
Restoration Project -
AutoCAD SHX Text
Fish Barriers
AutoCAD SHX Text
at Hoveton Marshes, The Dam & Foxborrow Dyke
AutoCAD SHX Text
Issue
AutoCAD SHX Text
Drawing No.
AutoCAD SHX Text
TITLE
AutoCAD SHX Text
PROJECT
AutoCAD SHX Text
Project No.
AutoCAD SHX Text
Current Issue Signatures
AutoCAD SHX Text
Copyright reserved
AutoCAD SHX Text
Description
AutoCAD SHX Text
Grid
AutoCAD SHX Text
Client
AutoCAD SHX Text
Filename:
AutoCAD SHX Text
Datum
AutoCAD SHX Text
Original
AutoCAD SHX Text
Size
AutoCAD SHX Text
Scales
AutoCAD SHX Text
Issue
AutoCAD SHX Text
Status
AutoCAD SHX Text
Approver
AutoCAD SHX Text
Checker
AutoCAD SHX Text
A1
AutoCAD SHX Text
C
AutoCAD SHX Text
Author
AutoCAD SHX Text
Date
AutoCAD SHX Text
Eel Trap
AutoCAD SHX Text
Plan & Elevations
Page 11: 2000 & ENVIRONMENTAL INFORMATION

Ma

x. 3

00

Ø

76

.2

Ø

011 / 02 Sectional Elevation - Eel Fyke

(1:5)

4no. conical fyke with modified screens required (2 per barrier site) using 2mm perforations

011 / 03 Elevation - View from Seaward Side of Eel Fyke

(1:5)

011 / 04 Elevation - View from Broad Side of Eel Fyke

(1:5)

SEAWARD SIDE Hoveton Broad

011 / 01 Plan - Eel Fyke Bolted to Screen (plate not shown in plan for clarity)

(1:5)

4no. conical fyke with modified screens required (2 per barrier site -Foxborrow & The Dam) using 2mm perforations

Fyke Weight = 10 kg (exc. screen)

50035

39

0

30

39

0 S

ta

nd

ard

scre

en

w

id

th

34

5

390

Ø

3

0

0

75

Ø

Ø75

75

- 9

Modified wedge wire screen unit.

Frame formed from 60 x 5mm thick

stainless steel flat bar.

-See Drawing 005 for standard

screen.

Guide rail slot for closing off

fyke with a handstop

Otter screen bars @ 85mm centres

vert & horiz

1mm thick stainless steel conical fyke

with 2mm perforations @ 3.5mm pitch

(open area 30%)

2mm thick conical fyke with 2mm

perforations @ 3.5mm pitch

External 6Ø reinforcement ribs

Fyke bolted to modified screen for ease

of replacement and transportation

Otter screen bars @ 85mm centres

vert & horiz

Solid flat plate to stiffen screen cont

FW weld to end of perforated cone.

Sock to prevent upstream migration

of fish through fyke. To be funnel

shape 75mm to 90mm diameter and

115mm in length to accommodate

installation. To be silt net or similar.

Fyke sock

Cable tie around fyke

sock to hold in place

Additional reinforcement to stop

fyke net from sliping

Ø

3

0

0

463

6Ø bar hoops spot amply spot-welded

to perforated plate cone. Nom. radii R =

125, 170, 215, 260 or similar for nominal

100mm equal spacing of reinforcing ribs

stainless steel 40 x 40 x 4thk EA

frame to end of fyke cone

Solid flat plate to stiffen screen cont

FW weld to end of perforated cone.

External 6Ø reinforcement ribs

76.2Ø x 1.5mm thk stainless steel

tubing x 50mm long. Spot weld to

perforated end plate.

76.2Ø x 1.5mm thk stainless steel tubing

x 50mm long. Sharp edges ground off.

Spot weld to perforated end plate.

011 / 06 Plan - Conical Fyke (screen not shown)

(1:5)

4no. conical fyke with modified screens required (2 per barrier site -Foxborrow & The Dam) using 2mm perforations

30

75

Ø

Fyke sock

22

011 / 05 Plan - Eel Fyke Screen Template

(1:10)

Fyke Screen:

1mm thick stainless steel grade 316 plate with 2mm

perforations @ 3.5mm pitch

(open area 30%). Plate rolled and fixed along seam with

full butt weld to form cone.

Eel Trap Fyke:

1mm thick stainless steel grade 316 plate with 8 mm

perforations @ 12mm pitch (open area 40%). Plate rolled

and fixed along seam with full butt weld to form cone.

-See Drawing 011

173

R 649

8

3

.

2

1

°

Fabricator to form template to check fit first before

pattern cutting & rolling perforated steel plate.

P01 Draft issue for EA Fisheries comment 7 / 10 / 20

J.Rana

Outline

As shown

M.Lakin

P. Kibel

P02 Draft issue for EA Fisheries comment 27/11/20

1. DIMENSIONS:

● Are in millimetres unless otherwise stated.

● Marked thus (*) or c. are approximate.

● All levels are in metres to Site Datum.

2. SPECIFICATION:

All works to be carried out in accordance with the Civil

Engineering Specification for the Water Industry (CESWI).

All technical requirements clauses apply unless stated as

deleted, amended or augmented in accordance with the

Contract Works Information documentation.

3. STEELWORK:

● All stainless steel to BS5950.

●All fabricated steelwork structures executed to conform to

BS EN 1090-2.

● All steelwork in stainless steel 316L.

● Refer to Drawing 005 for screen details.

● All welds FW cont. unless otherwise stated. Weld size not

to exceed substrate thickness unless otheriwse required.

● Fasteners to be M8 X 25 hex head set screw bolts x 25mm

long + Nyloc nuts in stainless steel A2 (304).

P04 Revised issue with minor revisions 13 / 01 / 21

P03 No issue

SAFETY HEALTH

& ENVIRONMENTAL

INFORMATION

Caution - Sharp Edges

- All sharp edges and burrs to be removed.

Caution - Lifting

- Check adequate lifting facilities & constraints.

Check - All fabricated elements are clean and free

from dust, and burrings on completion.

It is assumed that all works will be carried out by a

competent contractor working, where appropriate, to an

approved method statement

!

FABRICATION

!

!

AutoCAD SHX Text
011 2595 P04
AutoCAD SHX Text
Hoveton Great Broad
AutoCAD SHX Text
Restoration Project -
AutoCAD SHX Text
Fish Barriers
AutoCAD SHX Text
at Hoveton Marshes, The Dam & Foxborrow Dyke
AutoCAD SHX Text
Issue
AutoCAD SHX Text
Drawing No.
AutoCAD SHX Text
TITLE
AutoCAD SHX Text
PROJECT
AutoCAD SHX Text
Project No.
AutoCAD SHX Text
Current Issue Signatures
AutoCAD SHX Text
Copyright reserved
AutoCAD SHX Text
Description
AutoCAD SHX Text
Grid
AutoCAD SHX Text
Client
AutoCAD SHX Text
Filename:
AutoCAD SHX Text
Datum
AutoCAD SHX Text
Original
AutoCAD SHX Text
Size
AutoCAD SHX Text
Scales
AutoCAD SHX Text
Issue
AutoCAD SHX Text
Status
AutoCAD SHX Text
Approver
AutoCAD SHX Text
Checker
AutoCAD SHX Text
A1
AutoCAD SHX Text
C
AutoCAD SHX Text
Author
AutoCAD SHX Text
Date
AutoCAD SHX Text
Eel Fyke
AutoCAD SHX Text
Plan & Elevations