Upload
others
View
0
Download
0
Embed Size (px)
Citation preview
20 December 2017
Amec Foster Wheeler Reference No.: TT163003.9000
CH2M HILL Canada Limited
245 Consumers Road
North York, Ontario, M2J 1R3
Canada
Attention: Mr. Rob Wiersma
Dear Sir:
Re: ADDENDEM TO GEOTECHNICAL INVESTIGATION REPORT
(TT163003, dated 16 June 2016)
PROPOSED TEMPORARY BRIDGES A TO F
HIGHLAND SEWERSHED TRUNK SEWER REHABILITATION
SOUTH MIMICO SITE, TORONTO, ONTARIO
Amec Foster Wheeler Environment & Infrastructure, a Division of Amec Foster Wheeler
Americas Limited (“Amec Foster Wheeler”), is pleased to submit this letter report to
provide the results of geotechnical investigation and slope stability analysis for the six
proposed temporary bridges A to F to be constructed at the South Mimico site in the City
of Toronto, Ontario.
This report should be considered as an addendum to Amec Foster Wheeler’s previously-
submitted geotechnical investigation report titled “Geotechnical Investigation Report,
Highland Sewershed Trunk Sewer Rehabilitation, South Mimico Site, Toronto, Ontario”,
Reference No.: TT163003, dated 16 June 2016. Therefore, the previous 2016 report should
be considered as an integral part of this letter report. All the precautionary statements
on how to use the report and the Report Limitations included in the 2016 report are
applicable to this letter report.
This letter report supersedes all reports previously submitted for the six proposed
bridges.
CH2M HILL Canada Limited
Addendum to Geotechnical Investigation Report
(TT163003, dated 16 June 2016)
Proposed Temporary Bridges A to F
Highland Sewershed Trunk Sewer Rehabilitation
South Mimico Site, Toronto, Ontario Page 2 of 15
Amec Foster Wheeler Environment & Infrastructure
50 Vogell Road
Richmond Hill, Ontario, L4B 3K6
Canada
Tel. No.: (905) 403-5014
amecfw.com
1.0 INTRODUCTION
The purpose of the geotechnical investigation was to characterize the subsurface
conditions at the six proposed bridge foundation locations by means of drilling a total of
eight (8) boreholes (BH 17-1 to BH 17-8) and to provide recommendations on the
geotechnical design of bridge foundations. These eight boreholes were drilled to provide
additional subsurface soil information to the previously-drilled boreholes (BH 4, BH 6,
BH 7 and BH 8, with Record of Boreholes shown in Appendix A) reported in the 2016
report, resulting in two boreholes for each proposed bridge (i.e., one on each bank).
The six proposed temporary bridges (A to F) will be constructed over South Mimico
Creek, as shown on Figure Nos. 1 and 2, as parts of access routes for the rehabilitation
construction.
Authorization to proceed with this investigation was received from Mr. Joshua
VanRavenswaay, Staff Consultant of CH2M, on 1 September 2017. The work carried out
for this investigation was completed in accordance with Contract No.: 10201-7-100848-
M0004, dated 8 June 2017 and Amec Foster Wheeler's proposal dated 22 August 2017.
2.0 INVESTIGATION PROCEDURES
The field work for borehole drilling was conducted from 29 September 2017 to 19 October
2017 under full time oversight of Amec Foster Wheeler personnel.
A total of eight (8) boreholes (BH 17-1 to BH 17-8) were advanced within or close to the
proposed bridge foundation locations as shown on Figure No. 2. Among the eight (8)
boreholes, six (6) boreholes were drilled for each bridge at the west bank, and two (2)
boreholes were drilled for Bridges B and E at the east bank, where no existing borehole
information was available.
CH2M HILL Canada Limited
Addendum to Geotechnical Investigation Report
(TT163003, dated 16 June 2016)
Proposed Temporary Bridges A to F
Highland Sewershed Trunk Sewer Rehabilitation
South Mimico Site, Toronto, Ontario Page 3 of 15
Amec Foster Wheeler Environment & Infrastructure
50 Vogell Road
Richmond Hill, Ontario, L4B 3K6
Canada
Tel. No.: (905) 403-5014
amecfw.com
All boreholes were terminated in weathered shale, which could be augered through by
the drilling rig, at depths of between 1.7 m and 4.7 m below grade, using a combination
of track mounted rig and Minute Man (hand-operated rig) equipped with solid stem
augers. As the Minute Man was not sufficiently powerful to drill through the fill, a mini
excavator was used to conduct test pits where granular pavement present at ground
surface.
Due to access difficulty, a small drilling equipment (“Minute Man”) was used at all
borehole locations except for BH 17-6. Soil sampling for these boreholes was conducted
by freely dropping a 32 kg (70 lbs.) hammer for a vertical distance of 0.76 m (30 inches)
to drive a 50 mm (2 inch) diameter O.D. split-barrel (split spoon) sampler into the ground.
Half of the number of blows by the smaller hammer weight was recorded as SPT ‘N’
value of the soil.
Soil samples were taken at 0.76 m interval, while performing Standard Penetration Test
(SPT) in accordance with ASTM D1586. The SPT sampling consisted of freely dropping
a 63.5 kg (140 lb) hammer for a vertical distance of 0.76 m (30 inches) to drive a 50 mm (2
inch) diameter O.D. split-barrel (split spoon) sampler into the ground. The number of
blows of the hammer required to drive the sampler into the relatively-undisturbed
ground by a vertical distance of 0.30 m (12 inches) was recorded as SPT ‘N’ value of the
soil which indicated the compactness of cohesionless soils or implied the consistency of
cohesive soils. The results of SPT are shown in the Record of Boreholes.
The MTM NAD 27 coordinates system was used to survey the as-drilled borehole
locations upon completion of drilling, and the geodetic ground elevations of the
boreholes were surveyed using the elevations of the maintenance hole covers provided
by CH2M, as shown in Figure No. 2 and Table 2.1.
CH2M HILL Canada Limited
Addendum to Geotechnical Investigation Report
(TT163003, dated 16 June 2016)
Proposed Temporary Bridges A to F
Highland Sewershed Trunk Sewer Rehabilitation
South Mimico Site, Toronto, Ontario Page 5 of 15
Amec Foster Wheeler Environment & Infrastructure
50 Vogell Road
Richmond Hill, Ontario, L4B 3K6
Canada
Tel. No.: (905) 403-5014
amecfw.com
The soil samples were transported to Amec Foster Wheeler’s Advanced Soil Laboratory in Scarborough (Toronto). All the soil samples were re- examined and selected samples were tested for water contents, Atterberg Limits and grain size distribution. The test results are shown on the Record of Boreholes and summarized in Section 3.0.
3.0 SUBSURFACE CONDITIONS
Based on the OGS Map M2544, Bedrock Geology of Ontario, the underlying bedrock at
the site is the Georgian Bay Formation, which comprises shale, dolostone, interbedded
siltstone and minor limestone.
Based on the soil conditions encountered at the boreholes, the soil profile comprised, in
descending order, topsoil, sandy gravel and /or sandy silt fill, silty clay, weathered shale
which could be augered through and shale bedrock which typically caused auger refusal.
The subsurface soil conditions are briefly described herein and additional information is
provided in the Record of Boreholes.
3.1 Stratigraphic Units
3.1.1 Ground Surface Cover
Topsoil
Topsoil was present at the ground surface of Boreholes BH 17-1 to BH 17-3, BH 17-7 and
BH 17-8. The thickness of topsoil varied from 100 mm to 225 mm. Water contents of the
topsoil varied from 12 % to 15 %.
Sandy Gravel Fill
Sandy gravel fill was present at the ground surface of Boreholes BH 17-4 to BH 17-6 with
a thickness of 0.3 m to 0.9 m. Water contents of the sandy gravel fill were between 3 %
and 7 %.
CH2M HILL Canada Limited
Addendum to Geotechnical Investigation Report
(TT163003, dated 16 June 2016)
Proposed Temporary Bridges A to F
Highland Sewershed Trunk Sewer Rehabilitation
South Mimico Site, Toronto, Ontario Page 6 of 15
Amec Foster Wheeler Environment & Infrastructure
50 Vogell Road
Richmond Hill, Ontario, L4B 3K6
Canada
Tel. No.: (905) 403-5014
amecfw.com
3.1.2 Fill Soils
Brown to grey sandy silt fill was found at all the borehole locations below the ground
surface cover at the site, and extended to a depth of 1.1 m to 2.1 m below the existing
grade. The sandy silt fill contained rock fragments, trace to some clay, trace gravel, rootles
and organic matter. Water contents for the sandy silt fill ranged from 4 % and 12 %.
3.1.3 Silty Clay
Native brown to grey silty clay was found below the sandy silt fill at Boreholes BH 17-2,
BH 17-3, BH 17-7 and BH 17-8; and extended to depths varying between 1.7 m and 2.6 m
below the existing grade. The silty clay contained some sand and trace gravel.
SPT ‘N’ values for the silty clay were ranged from 16 blows per 0.3 m to higher than 25
blows per 0.05 m (very stiff to hard in consistency), and its water contents ranged from 4
% to 9 %.
Grain size distribution and Atterberg Limits for the silty and clay are shown on Record
of Boreholes and in Appendix B, and summarized in Table 3.1.
Table 3.1 – Results of Laboratory Testing (Silty Clay)
Location Borehole
No
Sample
No.
Depth
(m)
Grain Size Distribution Atterberg Limits
Gravel
(%)
Sand
(%)
Silt
(%)
Clay
(%)
Liquid
Limit
Plastic
Limit
Plasticity
Index
Bridge B BH 17-2 SS 4 2.3 – 2.5 2 15 47 36 38 19 19
Bridge B BH 17-3 SS 4 1.5 – 1.6 0 18 48 34 35 17 18
Bridge E BH 17-7 SS 4 1.5 – 1.8 3 22 50 25 33 19 14
Bridge F BH 17-8 SS 4 1.5 – 2.0 1 10 59 30 39 21 18
CH2M HILL Canada Limited
Addendum to Geotechnical Investigation Report
(TT163003, dated 16 June 2016)
Proposed Temporary Bridges A to F
Highland Sewershed Trunk Sewer Rehabilitation
South Mimico Site, Toronto, Ontario Page 7 of 15
Amec Foster Wheeler Environment & Infrastructure
50 Vogell Road
Richmond Hill, Ontario, L4B 3K6
Canada
Tel. No.: (905) 403-5014
amecfw.com
3.1.4. Weathered Shale
Weathered shale of the Georgian Bay Formation, which could be augered through, was
encountered at all borehole locations below the sandy silt fill at Boreholes BH 17-1, BH
17-4 to BH 17-6 or the native silty clay at Boreholes BH 17-2, BH 17-3, BH 17-7 and BH 17-
8. The weathered shale extended to about 4.6 m below grade at Borehole BH 17-6 and to
the borehole termination depths of 1.7 m to 2.9 m at the rest of boreholes.
SPT ‘N’ values for the weathered shale ranged from 25 blow per 0.15 m to 50 blows per
0.05 m, and the water contents ranged from 4 % to 9 %.
Auger refusal was encountered within the weathered shale at all the boreholes drilled by
the Minute Man. The auger refusal could be due to the presence of sound shale bedrock.
3.1.5. Shale Bedrock
Shale bedrock was found at 4.6 m below grade at Borehole BH 17-6 location. Auger
refusal occurred at the termination depth of 4.7 m below the existing grade.
3.2 Groundwater Conditions
Groundwater was encountered at 0.9 m and 4.6 m below grade at BH 17-5 and BH 17-6,
respectively, upon completion of drilling. The remaining boreholes were dry.
It should be noted that groundwater level can fluctuate and can be higher during spring
months, precipitation and/or high creek water levels.
4.0 DISCUSSIONS AND RECOMMENDATIONS
The subsurface soil conditions at the proposed temporary bridge locations are provided
in this letter report, together with discussion and recommendations for bridge
foundations. General discussion and recommendations of geotechnical and
CH2M HILL Canada Limited
Addendum to Geotechnical Investigation Report
(TT163003, dated 16 June 2016)
Proposed Temporary Bridges A to F
Highland Sewershed Trunk Sewer Rehabilitation
South Mimico Site, Toronto, Ontario Page 4 of 15
Amec Foster Wheeler Environment & Infrastructure
50 Vogell Road
Richmond Hill, Ontario, L4B 3K6
Canada
Tel. No.: (905) 403-5014
amecfw.com
Table 2.1 – Maintenance Hole Elevations
Maintenance
Hole No. Location
Geodetic
The coordinates and geodetic elevations for the boreholes are shown on the Record of
Boreholes and summarized in Table 2.2.
Table 2.2 – Borehole Locations
Borehole
No.
Drilling Date Borehole
Depth (m)
NAD 27 Geodetic
Ground
Elevation (m) From To Easting Northing
BH 17-1 Sep.29, 17 Oct. 19, 17 1.7 304284 4832884 101.1
BH 17-2 Sep. 29, 2017 2.9 304336 4832794 100.3
BH 17-3 Oct. 10, 17 Oct. 12, 17 1.9 304371 4832759 99.3
BH 17-4 Oct. 6, 17 Oct. 19, 17 2.3 304468 4832650 97.7
BH 17-5 Oct. 6, 17 1.7 304502 4832573 95.6
BH 17-6 Oct. 13, 17 4.7 304765 4832433 92.7
BH 17-7 Oct. 5, 17 2.2 304785 4832395 93.7
BH 17-8 Oct. 5, 17 2.6 304871 4832277 92.4
Elevation (m)
MH 322-025-1 Bridge A location, west bank of South Mimico Creek 101.4
MH 322-024-1 Bridge B location, west bank of South Mimico Creek 100.9
MH 322-023-1 Bridge B location, east bank of South Mimico Creek 99.6
MH 322-021-1 Bridge C location, west bank of South Mimico Creek 98.0
MH 322-019-1 Bridge D location, east bank of South Mimico Creek 96.0
MH 322-017-1 Bridge E location, east bank of South Mimico Creek 94.6
MH 322-016-1 Bridge E location, west bank of South Mimico Creek 94.0
MH 322-014-1 Bridge F location, west bank of South Mimico Creek 92.6
CH2M HILL Canada Limited
Addendum to Geotechnical Investigation Report
(TT163003, dated 16 June 2016)
Proposed Temporary Bridges A to F
Highland Sewershed Trunk Sewer Rehabilitation
South Mimico Site, Toronto, Ontario Page 8 of 15
Amec Foster Wheeler Environment & Infrastructure
50 Vogell Road
Richmond Hill, Ontario, L4B 3K6
Canada
Tel. No.: (905) 403-5014
amecfw.com
hydrogeological aspects for the South Mimico site provided in Amec Foster Wheeler’s
previously-submitted geotechnical investigation report titled “Geotechnical
Investigation Report, Highland Sewershed Trunk Sewer Rehabilitation, South Mimico
Site, Toronto, Ontario”, Reference No.: TT163003, dated 16 June 2016, should be
considered where applicable.
According to the information by CH2M, the proposed temporary bridges will be Acrow
Panel Bridge or equivalent with an open truss system. The bridge lengths vary from 21.4
m to 49.0 m, while the width is 3.15 m for Bridge B and 4.20 m for the rest of the bridges,
as shown on Drawing C40 to C42 in Appendix C.
Based on the soil profiles encountered, spread/strip footings founded on native silt and
clay, silty clay, or weathered shale should be capable of supporting the bridge abutment
foundations.
4.1 Foundation
Based on the soil conditions encountered in Boreholes BH 17-1 to BH 17-8, and BH 4 to BH 8, the weathered shale should be capable of supporting spread/strip footings for the proposed bridges. Due to the shallow depth of the weathered shale, the bridge footings should be founded on or within the weathered shale. The recommended geotechnical reactions / resistances for the weathered shale, according to the Canadian Highway Bridge Design Code, are summarized in Table 4.1.
CH2M HILL Canada Limited
Addendum to Geotechnical Investigation Report
(TT163003, dated 16 June 2016)
Proposed Temporary Bridges A to F
Highland Sewershed Trunk Sewer Rehabilitation
South Mimico Site, Toronto, Ontario Page 9 of 15
Amec Foster Wheeler Environment & Infrastructure
50 Vogell Road
Richmond Hill, Ontario, L4B 3K6
Canada
Tel. No.: (905) 403-5014
amecfw.com
Table 4.1 - Founding Stratum and Soil Bearing Capacity for Bridge Foundations
Bridge Reference
Borehole
Founding
Stratum
Approximate
Depth
Below Grade
(m)
Geodetic
Elevation
(m)
Geotechnical
Pressure
Reaction at
SLS
(kPa)
Factored
Geotechnical
Pressure
Resistance
(Factored ULS)*
(kPa)
A
BH 8 Weathered
shale 1.4 100.2 400 600
BH 17-1 Weathered
shale 1.2 99.9 400 600
B
BH 17-3 Weathered
shale 1.3 98.0 400 600
BH 17-2 Weathered
shale 2.1 98.2 400 600
C
BH 7 Weathered
shale 1.4 100.2 400 600
BH 17-4 Weathered
shale 2.0 95.7 400 600
D
BH 6 Weathered
shale 1.4 96.7 400 600
BH 17-5 Weathered
shale 1.4 94.2 400 600
E
BH 17-6 Weathered
shale 1.2 91.5 400 600
BH 17-7 Weathered
shale 1.1 92.6 400 600
F
BH 4 Weathered
shale 2.5 90.1 400 600
BH 17-8 Weathered
shale 1.4 90.9 400 600
Note: * A resistance factor of Φ = 0.5 has been applied to the Ultimate Limit State (ULS) values
provided.
CH2M HILL Canada Limited
Addendum to Geotechnical Investigation Report
(TT163003, dated 16 June 2016)
Proposed Temporary Bridges A to F
Highland Sewershed Trunk Sewer Rehabilitation
South Mimico Site, Toronto, Ontario Page 10 of 15
Amec Foster Wheeler Environment & Infrastructure
50 Vogell Road
Richmond Hill, Ontario, L4B 3K6
Canada
Tel. No.: (905) 403-5014
amecfw.com
Engineered fill, if used, should be constructed as mentioned in the 2016 report and
designed with a SLS value of 150 kPa and a factored ULS value of 225 kPa.
The Serviceability Limit State (SLS) bearing values correspond to settlements of up to
25 mm.
In order to achieve the SLS/ULS soil bearing pressures provided in Table 4.1, the exposed
subgrade should be free of loose/soft, disturbed wet or otherwise deleterious materials.
The subgrade should be inspected and evaluated by a Geotechnical Engineer to confirm
that the proposed footings are founded on the competent subgrade which is capable of
the design loads. The exposed subgrade should not be disturbed by construction
activities.
4.2 Earthquake Considerations
In conformance with the criteria in Table 4.1, Section 4 of the Canadian Highway Bridge
Design Code (S6-14) from CSA on 16 February 2015, the project site should be classified
as Site Class C – “Very Dense Soil and Soft Rock”.
4.3 Slope Stability of Creek Bank
The South Mimico Creek meandered on the study site and generally drained
southbound. Along the creek, bank erosion was observed at several locations as
evidenced by the exposed soil surface and shale outcrop. The creek water level was about
0.2 m to 0.8 m deep during the field investigation, and the photographs for the bridge
profiles are provided in Appendix D.
A total of seven (7) slope stability analyses were conducted with respect to the proposed
temporary Bridge A to F locations, as per the site conditions. The analytical model, as
shown in Figure Nos. 3 to 16, considered a 1.5 m wide bridge footing founded on granular
“A” pad (if necessary), or the weathered shale with a bearing pressure of 400 kPa (SLS
value). A surcharge of 16 kPa was applied on the bridge approach to represent traffic
CH2M HILL Canada Limited
Addendum to Geotechnical Investigation Report
(TT163003, dated 16 June 2016)
Proposed Temporary Bridges A to F
Highland Sewershed Trunk Sewer Rehabilitation
South Mimico Site, Toronto, Ontario Page 11 of 15
Amec Foster Wheeler Environment & Infrastructure
50 Vogell Road
Richmond Hill, Ontario, L4B 3K6
Canada
Tel. No.: (905) 403-5014
amecfw.com
load according to the Canadian Highway Bridge Design Code. In addition, a small soil
ramp to the bridge abutment was included. The bridge foundation was located about 3.5
m from the top of the slope according to CH2M's drawings in Appendix C.
Slope stability analyses were carried out using the software package GeoStudio
SLOPE/W (Version 7.17) produced by GEO-SLOPE International Limited, employing the
Morgenstern-Price method of analyses with circular slip surfaces. The weathered shale
was considered conservatively as soil through which circular slip surfaces were
applicable.
The following conservative soil parameters were considered for the slope stability
analyses, as shown in Table 4.2.
Table 4.2 - Geotechnical Parameters for Slope Stability Analyses
Soil Type
Unit Weight: γ Effective Stress Analysis
(kN/m3) Cohesion: c’
(kPa)
Friction Angle: ’
(°)
Foundation 24 200* 0
Engineered Fill (slope grade) 21 0 30
Gravel (staging area) 21 0 30
Granular “A” Pad 21 0 30
Sandy Silt/Silty Sand Fill 18 0 28
Sandy Silt / Silty Sand 18 0 28
Silty Clay / Clayey Silt Fill 19 20 5
Silty Clay 19 25 5
Weathered Shale 22 25 30
CH2M HILL Canada Limited
Addendum to Geotechnical Investigation Report
(TT163003, dated 16 June 2016)
Proposed Temporary Bridges A to F
Highland Sewershed Trunk Sewer Rehabilitation
South Mimico Site, Toronto, Ontario Page 12 of 15
Amec Foster Wheeler Environment & Infrastructure
50 Vogell Road
Richmond Hill, Ontario, L4B 3K6
Canada
Tel. No.: (905) 403-5014
amecfw.com
Two cases were considered - one with measured groundwater level and with dry creek
(Figure Nos. 3 to 9) and the other with a groundwater level at 2 year flood line and with
rapid drawdown from 2 year flood line (Figure Nos. 10 to 16). As the creek bottom was
not shown in CH2M’ drawings, the creek bottom was assumed 0.5 m below the creek
water surface in the analyses. The calculated minimum factors of safety for the two cases
are summarized in Table 4.3.
Table 4.3 - Calculated Minimum Safety Factor against Slope Instability
Case of Analysis Figure
No. Location
Corresponding
Borehole
Groundwater
Elevation (m)
Factor of
Safety
Measured
groundwater
level and dry
creek
3 Bridge A (east bank) BH 8 – 1.89
4 Bridge A (west bank) BH 17-1 – 1.73
5 Bridge B (west bank) BH 17-2 – 1.76
6 Bridge C (east bank) BH 7 98.6 1.71
7 Bridge D (west bank) BH 6 97.0 1.53
8 Bridge E (east bank) BH 17-7 – 2.18
9 Bridge F (west bank) BH 4 - 2.15
Groundwater
level at 2 year
flood line and
rapid drawdown
of creek
10 Bridge A (east bank) BH 8 101.2 1.65
11 Bridge A (west bank) BH 17-1 101.2 1.58
12 Bridge B (west bank) BH 17-2 99.0 1.59
13 Bridge C (east bank)* BH 7 97.5 1.74
14 Bridge D (west bank)* BH 6 95.9 1.65
15 Bridge E (east bank) BH 17-7 93.0 1.90
16 Bridge F (west bank) BH 4 90.3 1.99
Note: * 2 year flood line is lower than the measured groundwater level
CH2M HILL Canada Limited
Addendum to Geotechnical Investigation Report
(TT163003, dated 16 June 2016)
Proposed Temporary Bridges A to F
Highland Sewershed Trunk Sewer Rehabilitation
South Mimico Site, Toronto, Ontario Page 13 of 15
Amec Foster Wheeler Environment & Infrastructure
50 Vogell Road
Richmond Hill, Ontario, L4B 3K6
Canada
Tel. No.: (905) 403-5014
amecfw.com
According to Ontario Ministry of Natural Resources (MNR) “Technical Guide – River
and Stream Systems: Erosion Hazard Limit”, the common range of minimum Factor of
Safety is 1.2 to 1.5 for slope stability analysis. The slope stability analysis results
presented in Table 4.3 indicate that the proposed bridge footings founded on weathered
shale and located at least 3.5 m from the eroded creek bank (Drawing C40 to C42) should
be stable against slope instability since the minimum calculated factor of safety is 1.53 at
proposed Bridge B location under high groundwater level and 2 year flood line of the
creek. The rest of slope stability analyses performed should meet the MNR requirement
for 'a study using accepted geotechnical and engineering principles'.
It should be noted that the bank erosion was observed at the west bank of the proposed
Bridge B location (BH 17-2 location), the bank itself is not stable and could be eroded
further. The foundation for the proposed bridges should not impose any additional
loading onto the existing slopes (creek banks) between the bridge foundations and the
existing creek banks. The eroded banks should be protected against further erosion
during the bridge construction as a precaution.
As mentioned earlier, the actual width of the bridge footing depends on the actual bridge
loading and structural design which are not known at the time of this slope stability
analysis. Should the bridge footing width and location be significantly different from
those shown in the analysis (Figure Nos. 3 to 14), a new slope stability analysis may be
required.
4.4 Recommendations for Proposed Bridge Foundations
The bridge foundation founded on weathered shale should be stable against slope
instability if it is located at least 3.5 m from the top of bank slope as shown in CH2M's
drawings in Appendix C. All creek banks should be protected against creek erosion as
required by Ontario Ministry of Natural Resources (MNR) “Technical Guide – River and
Stream Systems: Erosion Hazard Limit”.
As a summary, the following recommendations should be considered in designing the
foundations for the proposed bridges:
CH2M HILL Canada Limited
Addendum to Geotechnical Investigation Report
(TT163003, dated 16 June 2016)
Proposed Temporary Bridges A to F
Highland Sewershed Trunk Sewer Rehabilitation
South Mimico Site, Toronto, Ontario Page 14 of 15
Amec Foster Wheeler Environment & Infrastructure
50 Vogell Road
Richmond Hill, Ontario, L4B 3K6
Canada
Tel. No.: (905) 403-5014
amecfw.com
a. Found the bridge footings on the weathered shale, native silty clay or granular
“A” pad at a minimum distance of 3.5 m from the crest of the creek bank. Design
the footing with the SLS value of 400 kPa such than all vertical and horizontal
loads are supported by the weathered shale (e.g., footing with load eccentricity),
or SLS value of 150 kPa by the native silty clay /silt and clay without imposing
any additional load onto the existing creek bank within the 3.5 m distance.
b. Alternatively, as planned by CH2M (Drawing C40 to C42 in Appendix C), replace
the incompetent existing fill with engineered fill (compacted Granular 'A' pad)
with the following considerations:
Place the Granular 'A' pad at a minimum distance of 3.5 m from the crest of
the creek bank.
The width of the Granular 'A' pad should extend at least 0.5 m from the
edges of the footing.
No additional fill and surcharge loads should be placed between the
Granular 'A' pad and the existing creek bank.
Design the footing with a SLS value of 150 kPa such than all vertical and
horizontal loads are supported by the Granular 'A' pad and the weathered
shale without imposing any additional load onto the existing creek bank
within the 3.5 m distance.
If the bridge footing is placed on the Granular 'A' pad without being
covered by a minimum 1.2 m thick soil, the bridge footing may undergo
movement due to freezing and thawing.
5.0 CLOSURE
This report should be read in conjunction with Amec Foster Wheeler’s previously-
submitted geotechnical investigation report “Geotechnical Investigation Report,
Highland Sewershed Trunk Sewer Rehabilitation, South Mimico Site, Toronto, Ontario”,
Reference No.: TT163003, dated 16 June 2016.
CH2M HILL Canada Limited
Addendum to Geotechnical Investigation Report
(TT163003, dated 16 June 2016)
Proposed Temporary Bridges A to F
Highland Sewershed Trunk Sewer Rehabilitation
South Mimico Site, Toronto, Ontario Page 15 of 15
Amec Foster Wheeler Environment & Infrastructure
50 Vogell Road
Richmond Hill, Ontario, L4B 3K6
Canada
Tel. No.: (905) 403-5014
amecfw.com
Linda Ji, M.Sc., P. Eng., P. Geo. Prapote Boonsinsuk, Ph.D., P. Eng.
Project Manager/Geotechnical Engineer Principal Geotechnical Engineer
This report has been prepared by Linda Ji, M. Sc., P. Eng. and P. Geo., and reviewed by
Prapote Boonsinsuk, Ph.D., P. Eng.
The Report Limitations included in the 2016 report are an integral part of this report.
Sincerely,
Amec Foster Wheeler Environment & Infrastructure,
a Division of Amec Foster Wheeler Americas Limited
FIGURES
REV. NO.:
A
DATE:
OCTOBER 2017
PROJECT NO:
TT163003.9000
FIGURE No.
1
N.T.S. -
PROJECTION:
-
DATUM:
DWN BY:
CHK'D BY:
SCALE:
WJ
KW
SITE LOCATION PLAN
PROJECT
TITLE
SOUTH MIMICO SITE, TORONTO, ONTARIO
CLIENT LOGOCLIENT
Amec Foster Wheeler Environment & Infrastructure
104 Crockford Boulevard, Scarborough, ON, M1R 3C3
CH2M HILL
Canada Limited
N
Bridge 'A'
Bridge 'B'
Bridge 'C'
Bridge 'D'
Bridge 'E'
Bridge 'F'
SITE
ADDENDUM TO GEOTECHNICAL INVESTIGATION REPORT
PROPOSED TEMPORARY BRIDGES A TO F
HIGHLAND SEWERSHED TRUNK SEWER REHABILITATION
K
e
n
r
id
g
e
A
v
e
F
a
ir
m
a
r
A
v
e
E
ld
e
r
id
g
e
A
v
e
C
lu
e
s
o
n
P
k
K
ir
k
B
r
a
d
d
e
n
R
d
E
B
e
r
n
ic
e
A
v
e
E
d
w
a
lte
r
A
v
e
B
e
th
n
a
l A
v
e
O
a
k
fie
ld
D
r
T
i
z
z
a
r
d
A
v
e
B
e
a
u
c
o
u
r
t
R
d
C
a
le
d
o
n
R
d
P
r
in
c
e
E
d
w
a
r
d
D
r
S
G
r
e
n
v
ie
w
B
lv
d
S
G
r
e
n
v
ie
w
B
lv
d
S
G
r
e
n
v
ie
w
B
lv
d
S
R
i
d
g
e
g
a
t
e
C
r
e
s
K
ir
k
B
r
a
d
d
e
n
R
d
W
N
o
r
s
e
m
a
n
S
t
Pla
nnin
g B
oundary
M
im
ic
o
C
re
e
k
M
im
ic
o
C
r
e
e
k
T
r
l
BH 17-1
BH 17-2
BH 17-3
BH 17-4
BH 17-5
BH 17-6
BH 17-7
BH 17-8
Berry
Road Park
R
O
Y
A
L
Y
O
R
K
R
O
A
D
MH322-025-1
MH322-024-1
MH322-023-1
MH322-021-1
MH322-019-1
MH322-017-1
MH322-016-1
MH322-014-1
TEMPORARY
BRIDGE 'E'
TEMPORARY
BRIDGE 'D'
TEMPORARY
BRIDGE 'C'
TEMPORARY
BRIDGE 'B'
TEMPORARY
BRIDGE 'A'
TEMPORARY
BRIDGE 'F'
MH322-026-1
BH 8
BH 7
BH 6
BH 4
0 100 200m
APPROXIMATE SCALE
REV. NO.:
A
DATE:
OCTOBER 2017
PROJECT NO:
TT163003.9000
FIGURE No.
2
AS SHOWN -
PROJECTION:
-
DATUM:
DWN BY:
CHK'D BY:
SCALE:
WJ
KW
BOREHOLE LOCATION PLAN
PROJECT
TITLE
ADDENDUM TO GEOTECHNICAL INVESTIGATION REPORT
PROPOSED TEMPORARY BRIDGES A TO F
HIGHLAND SEWERSHED TRUNK SEWER REHABILITATION
SOUTH MIMICO SITE, TORONTO, ONTARIO
CLIENT LOGOCLIENT
Amec Foster Wheeler Environment & Infrastructure
104 Crockford Boulevard, Scarborough, ON, M1R 3C3
CH2M HILL
Canada Limited
N
50 150
LEGEND
BOREHOLE LOCATION
BOREHOLE LOCATION (2016 Investigation)
EXISTING SEWER
1.89
Weathered Shale
Silty Sand Fill
GravelEngineered Fill
Foundation
Silty Sand Fill
Bearing Pressure = 400 kPa
Figure No. 3 Slope Stability Analysis for Proposed Temporary Bridge A (East Bank)
Measured Groundwater Level with Dry Creek
Surcharge: 16 kPa
Sandy Silt
Distance
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 3094.0
95.0
96.0
97.0
98.0
99.0
100.0
101.0
102.0
103.0
104.0
Ele
va
tio
n
94.0
95.0
96.0
97.0
98.0
99.0
100.0
101.0
102.0
103.0
104.0
Name: Foundation Unit Weight: 24 kN/m³ Cohesion: 200 kPa Phi: 0 °
Name: Gravel Unit Weight: 21 kN/m³ Cohesion: 0 kPa Phi: 30 °
Name: Silty Sand Fill Unit Weight: 18 kN/m³ Cohesion: 0 kPa Phi: 28 °
Name: Sandy Silt Unit Weight: 18 kN/m³ Cohesion: 0 kPa Phi: 28 °
Name: Wheathered Shale Unit Weight: 22 kN/m³ Cohesion: 25 kPa Phi: 30 °
Name: Engineered Fill Unit Weight: 21 kN/m³ Cohesion: 0 kPa Phi: 30 °
CH2M HILLCanada Limited
Addendum Geotechnical Investigation Report
Proposed Temporary Bridge A, BH 8 Location
Highland Sewershed Trunk Sewer Rehabilitation, South Mimico Site
Amec Foster Wheeler Reference Number: TT163003.9000
1.73
Weathered Shale
Sandy Silt Fill Sandy Silt Fill
GravelEngineered Fill
Foundation
Bearing Pressure = 400 kPa
Figure No. 4 Slope Stability Analysis for Proposed Temporary Bridge A (West Bank)
Measured Goundwater Level with Dry Creek
Surcharcge: 16 kPa
Distance
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 3095.0
96.0
97.0
98.0
99.0
100.0
101.0
102.0
103.0
104.0
Ele
va
tio
n
95.0
96.0
97.0
98.0
99.0
100.0
101.0
102.0
103.0
104.0
CH2M HILL Canada Limited
Addendum Geotechnical Investigation Report
Proposed Temporary Bridge A, BH 17-1 Location
Highland Sewershed Trunk Sewer Rehabilitation, South Mimico Site
Amec Foster Wheeler Reference Number: TT163003.9000
Name: Foundation Unit Weight: 24 kN/m³ Cohesion: 200 kPa Phi: 0 °
Name: Gravel Unit Weight: 21 kN/m³ Cohesion: 0 kPa Phi: 30 °
Name: Weathered Shale Unit Weight: 22 kN/m³ Cohesion: 25 kPa Phi: 30 °
Name: Engineered Fill Unit Weight: 21 kN/m³ Cohesion: 0 kPa Phi: 30 °
Name: Sandy Silt Fill Unit Weight: 18 kN/m³ Cohesion: 0 kPa Phi: 28 °
1.76
Weathered Shale
Silty Clay
Sandy Silt Fill
Gravel Engineered Fill
Foundation
Sandy Silt Fill
Bearing Pressure = 400kPa
Silty Clay
Figure No. 5 Slope Stability Analysis for Proposed Temporary Bridge B (West Bank)
Measured Groundwater Level with Dry Creek
Surcharge = 16kPa
Distance
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 3093.0
94.0
95.0
96.0
97.0
98.0
99.0
100.0
101.0
102.0
Ele
va
tio
n
93.0
94.0
95.0
96.0
97.0
98.0
99.0
100.0
101.0
102.0
Name: Foundation Unit Weight: 24 kN/m³ Cohesion: 200 kPa Phi: 0 °
Name: Gravel Unit Weight: 21 kN/m³ Cohesion: 0 kPa Phi: 30 °
Name: Sandy Silt Fill Unit Weight: 18 kN/m³ Cohesion: 0 kPa Phi: 28 °
Name: Silty Clay Unit Weight: 19 kN/m³ Cohesion: 25 kPa Phi: 5 °
Name: Wheathered Shale Unit Weight: 22 kN/m³ Cohesion: 25 kPa Phi: 30 °
Name: Engineered Fill Unit Weight: 21 kN/m³ Cohesion: 0 kPa Phi: 30 °
CH2M HILLCanada Limited
Addendum Geotechnical Investigation Report
Proposed Temporary Bridge B, BH 17-2 Location
Highland Sewershed Trunk Sewer Rehabilitation, South Mimico Site
Amec Foster Wheeler Reference Number: TT163003.9000
1.71
Silty Clay
Weathered Shale
Name: Foundation Unit Weight: 24 kN/m³ Cohesion: 200 kPa Phi: 0 °
Name: Gravel Unit Weight: 21 kN/m³ Cohesion: 0 kPa Phi: 30 °
Name: Sandy Silt Unit Weight: 18 kN/m³ Cohesion: 0 kPa Phi: 28 °
Name: Silty Clay Unit Weight: 19 kN/m³ Cohesion: 25 kPa Phi: 5 °
Name: Wheathered Shale Unit Weight: 22 kN/m³ Cohesion: 25 kPa Phi: 30 °
Name: Engineered Fill Unit Weight: 21 kN/m³ Cohesion: 0 kPa Phi: 30 °
Figure No. 6 Slope Stability Analysis for Proposed Temporary Bridge C (East Bank)
Measured Groundwater Level with Dry Creek
Engineered FillFoundation
Bearing Pressure = 400kPa
Surcharge = 16 kPa
Gravel
Distance
4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 3495.0
96.0
97.0
98.0
99.0
100.0
101.0
102.0
103.0
104.0
Ele
va
tio
n
95.0
96.0
97.0
98.0
99.0
100.0
101.0
102.0
103.0
104.0
CH2M HILLCanada Limited
Addendum Geotechnical Investigation Report
Proposed Temporary Bridge C, BH 7 Location
Highland Sewershed Trunk Sewer Rehabilitation, South Mimico Site
Amec Foster Wheeler Reference Number: TT163003.9000
1.53
Weathered Shale
GravelSilty Clay/Clayey Silt Fill
Engineered FillFoundation
Figure No. 7 Slope Stability Analysis for Proposed Temporary Bridge D (West Bank)
Measured Groundwater Level with Dry Creek
Bearing Pressure = 400 kPa
Surcharge = 16 kPa
Distance
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 2891.0
92.0
93.0
94.0
95.0
96.0
97.0
98.0
99.0
100.0
Ele
va
tio
n
91.0
92.0
93.0
94.0
95.0
96.0
97.0
98.0
99.0
100.0
CH2M HILL Canada Limited
Addendum Geotechnical Investigation Report
Proposed Temporary Bridge D, BH 6 Location
Highland Sewershed Trunk Sewer Rehabilitation, South Mimico Site
Amec Foster Wheeler Reference Number: TT163003.9000
Name: Foundation Unit Weight: 24 kN/m³ Cohesion: 200 kPa Phi: 0 °
Name: Gravel Unit Weight: 21 kN/m³ Cohesion: 0 kPa Phi: 30 °
Name: Weathered Shale Unit Weight: 21 kN/m³ Cohesion: 25 kPa Phi: 30 °
Name: Engineered Fill Unit Weight: 21 kN/m³ Cohesion: 0 kPa Phi: 30 °
Name: Silty Clay / Clayey Silt Fill Unit Weight: 19 kN/m³ Cohesion: 20 kPa Phi: 5 °
2.18
Weathered Shale
Silty Clay
Sandy Silt Fill Sandy Silt Fill
GravelEngineered FillFoundation
Name: Foundation Unit Weight: 24 kN/m³ Cohesion: 200 kPa Phi: 0 °
Name: Gravel Unit Weight: 21 kN/m³ Cohesion: 0 kPa Phi: 30 °
Name: Weathered Shale Unit Weight: 22 kN/m³ Cohesion: 25 kPa Phi: 30 °
Name: Engineered Fill Unit Weight: 21 kN/m³ Cohesion: 0 kPa Phi: 30 °
Name: Sandy Silt Fill Unit Weight: 18 kN/m³ Cohesion: 0 kPa Phi: 28 °
Name: Silty Clay Unit Weight: 19 kN/m³ Cohesion: 25 kPa Phi: 5 °
Name: Amourstone Cover Unit Weight: 24 kN/m³ Cohesion: 25 kPa Phi: 30 °
Bearing Pressure = 400 kPa
Silty Clay
Figure No. 8 Slope Stability Analysis for Proposed Temporary Bridge E (West Bank)
Measured Goundwater Level with Dry Creek
Amourstone Cover
Surcharcge: 16 kPa
Distance
-5 -4 -3 -2 -1 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 2287.0
87.5
88.0
88.5
89.0
89.5
90.0
90.5
91.0
91.5
92.0
92.5
93.0
93.5
94.0
94.5
95.0
95.5
96.0
Ele
va
tio
n
87.0
87.5
88.0
88.5
89.0
89.5
90.0
90.5
91.0
91.5
92.0
92.5
93.0
93.5
94.0
94.5
95.0
95.5
96.0
CH2M HILL Canada Limited
Addendum Geotechnical Investigation Report
Proposed Temporary Bridge E, BH 17-7 Location
Highland Sewershed Trunk Sewer Rehabilitation, South Mimico Site
Amec Foster Wheeler Reference Number: TT163003.9000
2.15
Weathered Shale
Silty Clay/Clayey Silt Fill
Gravel
Name: Foundation Unit Weight: 24 kN/m³ Cohesion: 200 kPa Phi: 0 °
Name: Gravel Unit Weight: 21 kN/m³ Cohesion: 0 kPa Phi: 30 °
Name: Weathered Shale Unit Weight: 22 kN/m³ Cohesion: 25 kPa Phi: 30 °
Name: Engineered Fill Unit Weight: 21 kN/m³ Cohesion: 0 kPa Phi: 30 °
Name: Silty Clay / Clayey Silt Fill Unit Weight: 19 kN/m³ Cohesion: 20 kPa Phi: 5 °
Engineered FillFoundation
Silty Clay/Clayey Silt Fill
Bearing Pressure = 400 kPa
Figure No. 9 Slope Stability Analysis for Proposed Temporary Bridge F (West Bank)
Measured Groundwater Level with Dry Creek
Surcharge = 16 kPa
Distance
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 3085.0
86.0
87.0
88.0
89.0
90.0
91.0
92.0
93.0
94.0
Ele
va
tio
n
85.0
86.0
87.0
88.0
89.0
90.0
91.0
92.0
93.0
94.0
CH2M HILL Canada Limited
Addendum Geotechnical Investigation Report
Proposed Temporary Bridge F, BH 4 Location
Highland Sewershed Trunk Sewer Rehabilitation, South Mimico Site
Amec Foster Wheeler Reference Number: TT163003.9000
1.65
Figure No. 10 Slope Stability Analysis for Proposed Temporary Bridge A (East Bank)
Groundwater Level at 2 Year Flood Line with Rapid Drawdown of Creek Water Level
Weathered Shale
Name: Foundation Unit Weight: 24 kN/m³ Cohesion: 200 kPa Phi: 0 °
Name: Gravel Unit Weight: 21 kN/m³ Cohesion: 0 kPa Phi: 30 °
Name: Silty Sand Fill Unit Weight: 18 kN/m³ Cohesion: 0 kPa Phi: 28 °
Name: Sandy Silt Unit Weight: 18 kN/m³ Cohesion: 0 kPa Phi: 28 °
Name: Wheathered Shale Unit Weight: 22 kN/m³ Cohesion: 25 kPa Phi: 30 °
Name: Engineered Fill Unit Weight: 21 kN/m³ Cohesion: 0 kPa Phi: 30 °
Silty Sand Fill
GravelEngineered Fill
Foundation
Silty Sand Fill
Bearing Pressure = 400 kPa
Surcharge: 16 kPa
Sandy Silt
Distance
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 3094.0
95.0
96.0
97.0
98.0
99.0
100.0
101.0
102.0
103.0
104.0
Ele
va
tio
n
94.0
95.0
96.0
97.0
98.0
99.0
100.0
101.0
102.0
103.0
104.0
CH2M HILLCanada Limited
Addendum Geotechnical Investigation Report
Proposed Temporary Bridge A, BH 8 Location
Highland Sewershed Trunk Sewer Rehabilitation, South Mimico Site
Amec Foster Wheeler Reference Number: TT163003.9000
1.58
Weathered Shale
Sandy Silt Fill Sandy Silt Fill
Gravel
Figure No. 11 Slope Stability Analysis for Proposed Temporary Bridge A (West Bank)
Groundwater Level at 2 Year Flood Line with Rapid Drawdown of Creek Water Level
Engineered FillFoundation
Bearing Pressure = 400 kPa
Surcharcge: 16 kPa
Distance
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 3095.0
96.0
97.0
98.0
99.0
100.0
101.0
102.0
103.0
104.0
Ele
va
tio
n
95.0
96.0
97.0
98.0
99.0
100.0
101.0
102.0
103.0
104.0
CH2M HILL Canada Limited
Addendum Geotechnical Investigation Report
Proposed Temporary Bridge A, BH 17-1 Location
Highland Sewershed Trunk Sewer Rehabilitation, South Mimico Site
Amec Foster Wheeler Reference Number: TT163003.9000
Name: Foundation Unit Weight: 24 kN/m³ Cohesion: 200 kPa Phi: 0 °
Name: Gravel Unit Weight: 21 kN/m³ Cohesion: 0 kPa Phi: 30 °
Name: Weathered Shale Unit Weight: 22 kN/m³ Cohesion: 25 kPa Phi: 30 °
Name: Engineered Fill Unit Weight: 21 kN/m³ Cohesion: 0 kPa Phi: 30 °
Name: Sandy Silt Fill Unit Weight: 18 kN/m³ Cohesion: 0 kPa Phi: 28 °
1.59
Figure No. 12 Slope Stability Analysis for Proposed Temporary Bridge B (West Bank)
Groundwater Level at 2 Year Flood Line with Repid Drawdown of Creek Water Level
Weathered Shale
Silty Clay
Sandy Silt Fill
Gravel Engineered Fill
Foundation
Sandy Silt Fill
Bearing Pressure = 400kPa
Silty Clay
Surcharge = 16kPa
Distance
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 3093.0
94.0
95.0
96.0
97.0
98.0
99.0
100.0
101.0
102.0
Ele
va
tio
n
93.0
94.0
95.0
96.0
97.0
98.0
99.0
100.0
101.0
102.0
Name: Foundation Unit Weight: 24 kN/m³ Cohesion: 200 kPa Phi: 0 °
Name: Gravel Unit Weight: 21 kN/m³ Cohesion: 0 kPa Phi: 30 °
Name: Sandy Silt Fill Unit Weight: 18 kN/m³ Cohesion: 0 kPa Phi: 28 °
Name: Silty Clay Unit Weight: 19 kN/m³ Cohesion: 25 kPa Phi: 5 °
Name: Wheathered Shale Unit Weight: 22 kN/m³ Cohesion: 25 kPa Phi: 30 °
Name: Engineered Fill Unit Weight: 21 kN/m³ Cohesion: 0 kPa Phi: 30 °
CH2M HILLCanada Limited
Addendum Geotechnical Investigation Report
Proposed Temporary Bridge B, BH 17-2 Location
Highland Sewershed Trunk Sewer Rehabilitation, South Mimico Site
Amec Foster Wheeler Reference Number: TT163003.9000
1.74
Figure No. 13 Slope Stability Analysis for Proposed Temporary Bridge C (East bank)
Groundwater Level at 2 Year Flood Line with Repid Drawdown of Creek Water Level
Silty Clay
Weathered Shale
Engineered FillFoundation
Bearing Pressure = 400kPa
Surcharge = 16 kPa
Gravel
Distance
4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 3495.0
96.0
97.0
98.0
99.0
100.0
101.0
102.0
103.0
104.0
Ele
va
tio
n
95.0
96.0
97.0
98.0
99.0
100.0
101.0
102.0
103.0
104.0
CH2M HILLCanada Limited
Addendum Geotechnical Investigation Report
Proposed Temporary Bridge C, BH 7 Location
Highland Sewershed Trunk Sewer Rehabilitation, South Mimico Site
Amec Foster Wheeler Reference Number: TT163003.9000
Name: Foundation Unit Weight: 24 kN/m³ Cohesion: 200 kPa Phi: 0 °
Name: Gravel Unit Weight: 21 kN/m³ Cohesion: 0 kPa Phi: 30 °
Name: Sandy Silt Unit Weight: 18 kN/m³ Cohesion: 0 kPa Phi: 28 °
Name: Silty Clay Unit Weight: 19 kN/m³ Cohesion: 25 kPa Phi: 5 °
Name: Wheathered Shale Unit Weight: 22 kN/m³ Cohesion: 25 kPa Phi: 30 °
Name: Engineered Fill Unit Weight: 21 kN/m³ Cohesion: 0 kPa Phi: 30 °
1.65
Weathered Shale
Figure No. 14 Slope Stability Analysis for Proposed Temporary Bridge D (West Bank)
Groundwater Level at 2 Year Flood Line with Rapid Drawdown of Creek Water Level
GravelSilty Clay/Clayey Silt Fill
Engineered FillFoundation
Bearing Pressure = 400 kPa
Surcharge = 16 kPa
Distance
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 2891.0
92.0
93.0
94.0
95.0
96.0
97.0
98.0
99.0
100.0
Ele
va
tio
n
91.0
92.0
93.0
94.0
95.0
96.0
97.0
98.0
99.0
100.0
CH2M HILL Canada Limited
Addendum Geotechnical Investigation Report
Proposed Temporary Bridge D, BH 6 Location
Highland Sewershed Trunk Sewer Rehabilitation, South Mimico Site
Amec Foster Wheeler Reference Number: TT163003.9000
Name: Foundation Unit Weight: 24 kN/m³ Cohesion: 200 kPa Phi: 0 °
Name: Gravel Unit Weight: 21 kN/m³ Cohesion: 0 kPa Phi: 30 °
Name: Weathered Shale Unit Weight: 21 kN/m³ Cohesion: 25 kPa Phi: 30 °
Name: Engineered Fill Unit Weight: 21 kN/m³ Cohesion: 0 kPa Phi: 30 °
Name: Silty Clay / Clayey Silt Fill Unit Weight: 19 kN/m³ Cohesion: 20 kPa Phi: 5 °
1.90
Weathered Shale
Silty Clay
Sandy Silt Fill Sandy Silt Fill
Gravel
Figure No. 15 Slope Stability Analysis for Proposed Temporary Bridge E (West Bank)
Groundwater Level at 2 Year Flood Line with Rapid Drawdown of Creek Water Level
Engineered FillFoundation
Name: Foundation Unit Weight: 24 kN/m³ Cohesion: 200 kPa Phi: 0 °
Name: Gravel Unit Weight: 21 kN/m³ Cohesion: 0 kPa Phi: 30 °
Name: Weathered Shale Unit Weight: 22 kN/m³ Cohesion: 25 kPa Phi: 30 °
Name: Engineered Fill Unit Weight: 21 kN/m³ Cohesion: 0 kPa Phi: 30 °
Name: Sandy Silt Fill Unit Weight: 18 kN/m³ Cohesion: 0 kPa Phi: 28 °
Name: Silty Clay Unit Weight: 19 kN/m³ Cohesion: 25 kPa Phi: 5 °
Name: Amourstone Cover Unit Weight: 24 kN/m³ Cohesion: 25 kPa Phi: 30 °
Bearing Pressure = 400 kPa
Silty Clay
Surcharcge: 16 kPa
Amourstone Cover
Distance
-5 -4 -3 -2 -1 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 2287.0
87.5
88.0
88.5
89.0
89.5
90.0
90.5
91.0
91.5
92.0
92.5
93.0
93.5
94.0
94.5
95.0
95.5
96.0
Ele
va
tio
n
87.0
87.5
88.0
88.5
89.0
89.5
90.0
90.5
91.0
91.5
92.0
92.5
93.0
93.5
94.0
94.5
95.0
95.5
96.0
CH2M HILL Canada Limited
Addendum Geotechnical Investigation Report
Proposed Temporary Bridge E, BH 17-7 Location
Highland Sewershed Trunk Sewer Rehabilitation, South Mimico Site
Amec Foster Wheeler Reference Number: TT163003.9000
1.99
Weathered Shale
Figure No. 16 Slope Stability Analysis for Proposed Temporary Bridge F (West Bank)
Groundwater Level at 2 Year Flood Line with Rapid Drawdown of Creek Water Level
Silty Clay/Clayey Silt Fill
GravelEngineered Fill
Foundation
Silty Clay/Clayey Silt Fill
Bearing Pressure = 400 kPa Surcharge = 16 kPa
Distance
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 3085.0
86.0
87.0
88.0
89.0
90.0
91.0
92.0
93.0
94.0
Ele
va
tio
n
85.0
86.0
87.0
88.0
89.0
90.0
91.0
92.0
93.0
94.0
CH2M HILL Canada Limited
Addendum Geotechnical Investigation Report
Proposed Temporary Bridge F, BH 4 Location
Highland Sewershed Trunk Sewer Rehabilitation, South Mimico Site
Amec Foster Wheeler Reference Number: TT163003.9000
Name: Foundation Unit Weight: 24 kN/m³ Cohesion: 200 kPa Phi: 0 °
Name: Gravel Unit Weight: 21 kN/m³ Cohesion: 0 kPa Phi: 30 °
Name: Weathered Shale Unit Weight: 22 kN/m³ Cohesion: 25 kPa Phi: 30 °
Name: Engineered Fill Unit Weight: 21 kN/m³ Cohesion: 0 kPa Phi: 30 °
Name: Silty Clay / Clayey Silt Fill Unit Weight: 19 kN/m³ Cohesion: 20 kPa Phi: 5 °
RECORD OF BOREHOLES