11 Successful Implementation & Improved Operation
Installation Issues and Solutions
Andreas AgostinIndustrial Network Sales Specialist Asia PacificMTL Instruments Singapore, part of Cooper Crouse-Hinds
22.02.2012 Kuala Lumpur
7/28/2019 2 Installation - Issues and Solutions
2/53
22 Successful Implementation & Improved Operation
Introduction
Fieldbus is in use since 19981
, yet still new formany customers today.
This presentation will look at the installation issues
and the lessons learned, so that you canbenefits from their experience.
1 Shell Malampaya is one of the early, larger projects. 1600 FF instruments are in use. The project produced first gas in
Oct 2001. Source: J. Seaver, Shell Philippines Exploration B.V., Malampaya Deep Water Gas-to-Power Project:
Malampaya Subsea Development, Offshore Technology Conference, 6 May-9 May 2002, Houston, Texas.
7/28/2019 2 Installation - Issues and Solutions
3/53
33 Successful Implementation & Improved Operation
Introduction
The pictures you will see are collected from realprojects; they are neither simulated nor demo.
We will look at Control room: cabinet design and wiring
Field: Wiring, field junction boxes, field device installation.
Processes typically involve explosion protection methods
intrinsic safety (I.S. / Ex i; energy limitation by a barrier)
or explosion proof (Ex d; protection by explosionproof
enclosure).
Many examples use IS as this is a key product of my
company and that is where I get involved.
7/28/2019 2 Installation - Issues and Solutions
4/53
44 Successful Implementation & Improved Operation
Disclaimer
All products shown serve as EXAMPLE only.In particular, problems shown in conjunction with a product
serve as example only.
The brand/make/model of the product serving as example
is IRRELEVANT.
Problems highlighted serve as example only, are do in no
way express problems with a particular product,
model or brand.
7/28/2019 2 Installation - Issues and Solutions
5/53
55 Successful Implementation & Improved Operation
The conventional system
7/28/2019 2 Installation - Issues and Solutions
6/53
66 Successful Implementation & Improved Operation
Control room Conventional wiring
2nd
level 1st
leveljunction box Marshalling
and barrierControl system
7/28/2019 2 Installation - Issues and Solutions
7/5377 Successful Implementation & Improved Operation
Control room Conventional wiring
Marshalling: to group AI / AO / DI / DO / etc
7/28/2019 2 Installation - Issues and Solutions
8/5388 Successful Implementation & Improved Operation
Control room Conventional wiring
7/28/2019 2 Installation - Issues and Solutions
9/5399 Successful Implementation & Improved Operation
Control room Conventional wiring
Long wires, standard length
Allows pre-fabrication of wire
(ferrules, mounting)
Conventional signals (4-20mA,
RTD, thermocouple, 0-
5V/10V/24V) slow, hardware
filtered, length less important
7/28/2019 2 Installation - Issues and Solutions
10/531010 Successful Implementation & Improved Operation
Field Conventional wiring
Quality (material) Safety
Location / access
Weight/size,
10
7/28/2019 2 Installation - Issues and Solutions
11/531111 Successful Implementation & Improved Operation
Fieldbus versus conventional
7/28/2019 2 Installation - Issues and Solutions
12/531212 Successful Implementation & Improved Operation
Control room DCS wiring EXAMPLES
Fieldbus
Conventional
7/28/2019 2 Installation - Issues and Solutions
13/531313 Successful Implementation & Improved Operation
Control room DCS wiring EXAMPLES
Installations do not haveto look messy. They
can be very nice, too.
Fieldbus
Conventional
7/28/2019 2 Installation - Issues and Solutions
14/531414 Successful Implementation & Improved Operation
Control room DCS wiring EXAMPLESFieldbus Conventional
7/28/2019 2 Installation - Issues and Solutions
15/531515 Successful Implementation & Improved Operation
Control room DCS wiring EXAMPLES
Fieldbus Fieldbus
7/28/2019 2 Installation - Issues and Solutions
16/531616 Successful Implementation & Improved Operation
Control room DCS wiring
Important:
do not use individual wires to
wire cabinet. Use fieldbus cable
and shield properly.
Why?
Higher signal
frequency protect
them against
disturbances.
Individual wires will
cause crosstalk from
one wire to another
communication faults
can occur.?
7/28/2019 2 Installation - Issues and Solutions
17/531717 Successful Implementation & Improved Operation
Fieldbus CableRecommended:
Type A cable: Shielded twisted pair
Other cable is possible, but there are limitations in termsof achievable cable distance and electromagneticcompatibility (EMC).
Fieldbus is a digital high speed (31kBit/s)communication, a current modulated signalsuperimposed on the DC power.
7/28/2019 2 Installation - Issues and Solutions
18/531818 Successful Implementation & Improved Operation
Fieldbus Cable
Shielded pair
principle
Foil
shield
Foil plus
braided
shield
SWA
SWA
Multi-pair
Multi-pair (multi-trunk)
Pl t thi
7/28/2019 2 Installation - Issues and Solutions
19/531919 Successful Implementation & Improved Operation
Please not this way
Images obscured
Brand is irrelevant.
7/28/2019 2 Installation - Issues and Solutions
20/532020 Successful Implementation & Improved Operation
Control room DCS wiring
7/28/2019 2 Installation - Issues and Solutions
21/53
2121 Successful Implementation & Improved Operation
Fieldbus system Field wiring
? Parallel wiring
(terminals)
special wiring
blocks
(daisy chaining)
7/28/2019 2 Installation - Issues and Solutions
22/53
2222 Successful Implementation & Improved Operation
Fieldbus system Field junction boxes
Principle of wiring distribution in junction box:all devices are in parallel
Source: FF AG 140 Rev. 1
7/28/2019 2 Installation - Issues and Solutions
23/53
2323 Successful Implementation & Improved Operation
Fieldbus system Field junction boxes
Please not this way
7/28/2019 2 Installation - Issues and Solutions
24/53
2424 Successful Implementation & Improved Operation24
Fieldbus system Field junction boxes
Use dedicatedwiring blocks
with built-in
electronic
short circuit
protection.
LEDs: - built-in s/c protection
7/28/2019 2 Installation - Issues and Solutions
25/53
2525 Successful Implementation & Improved Operation
Good Wiring Practices
Test segment wiring before connecting components Avoid damaging the wire when removing insulation Ground the cable shield only at one point (at the control
room end) Insulate the ungrounded end of the cable shield (at the
instrument) Ground armor on both sides (potential equalization) Use crimp ferrules
Ferrule diameter must fit wire Crimp tool must fit ferrule
Ferrule must fit terminals Maintain polarity and associated color codes throughoutthe segment
7/28/2019 2 Installation - Issues and Solutions
26/53
2626 Successful Implementation & Improved Operation
Good Wiring Practices
Lessons learned:
Torque screwdriver Wire end ferrules
Right (!) wire strippers
Fieldbus tester
Harms
wire strands
Choose
right size
7/28/2019 2 Installation - Issues and Solutions
27/53
2727 Successful Implementation & Improved Operation
Fieldbus Design Tools(Examples)
7/28/2019 2 Installation - Issues and Solutions
28/53
2828 Successful Implementation & Improved Operation
Project Procedure
Best practice: Bench test
Functional tests and interoperability test
FAT
SAT
7/28/2019 2 Installation - Issues and Solutions
29/53
2929 Successful Implementation & Improved Operation
Installation Guidelines
Cable Tests
Experience has shown that new cable irregularities areso infrequent that it is more efficient to check cableafter installation
Cable Installation Verify that cable is properly installed, bypassing impact
from wiring components Segment Checkout
Check of proper wiring of wiring components Device installation
Check of proper device installation Loop checkout
Functional test
7/28/2019 2 Installation - Issues and Solutions
30/53
3030 Successful Implementation & Improved Operation
Installation tools
Portable fieldbus diagnostic test equipment(Handhelds)
Measures relevant fieldbus
parameters Establish baseline
after commissioning
7/28/2019 2 Installation - Issues and Solutions
31/53
3131 Successful Implementation & Improved Operation
Handheld diagnostic tools
Handheld
Diagnostic
ToolDevice 1 Device 3Device 2
T
Device Coupler
& Terminator
(non-IS) Spurs
FFPS
T
FF Power Supply
& Conditioner
&Terminator
24VDC
Host
Computer
H1 Interface
Connect at respective location to obtain accurate measurement.
7/28/2019 2 Installation - Issues and Solutions
32/53
3232 Successful Implementation & Improved Operation
Handheld diagnostic tools
Handheld
Diagnostic
Tool
FFPS
T
FF Power Supply
& Conditioner
&Terminator
24VDC
Host
Computer
H1 Interface
Fieldbus
barrier
Device 1 Device 3Device 2
Fieldbus barrier
& Terminator
Intrinsically
Safe Spurs
T
Fieldbus
barrier
To measure at fieldbus barrier/IS segments, Handheld needs to be Ex i approved.
Important since the galvanic isolation of fieldbus barrier impacts on measurement.
7/28/2019 2 Installation - Issues and Solutions
33/53
3333 Successful Implementation & Improved Operation
Earthing/Grounding
Grounding in the control room One point grounding only
Continuous shield from control room to the field
Shield not connected at the field instrument
Connect cable armor at both ends (potential
equalization)
7/28/2019 2 Installation - Issues and Solutions
34/53
3434 Successful Implementation & Improved Operation
Earthing/Grounding
Device 1 Device 3Device 2
T
Wiring Block
& TerminatorFFPS
T
FF Power Supply
& Conditioner
&Terminator
24VDC
Host
Computer
H1 Interface
7/28/2019 2 Installation - Issues and Solutions
35/53
3535 Successful Implementation & Improved Operation
Fieldbus
barrier
Device 1 Device 3Device 2
Fieldbus barrier
& Terminator
Intrinsically
Safe Spurs
T
Fieldbus
barrier
Earthing/Grounding
FFPS
T
FF Power Supply
& Conditioner
&Terminator
24VDC
Host
Computer
H1 Interface
7/28/2019 2 Installation - Issues and Solutions
36/53
3636 Successful Implementation & Improved Operation
Local field junction box for 4
instruments. Rust prevented
proper grounding, so that
separate ground connection
was required
7/28/2019 2 Installation - Issues and Solutions
37/53
3737 Successful Implementation & Improved Operation
Field Fieldbus wiring
Green: fieldbus
Red: Power (Motors, etc)
For easy maintenance
7/28/2019 2 Installation - Issues and Solutions
38/53
3838 Successful Implementation & Improved Operation
Troubleshooting
7/28/2019 2 Installation - Issues and Solutions
39/53
3939 Successful Implementation & Improved Operation
Daisy chaining not recommended
7/28/2019 2 Installation - Issues and Solutions
40/53
4040 Successful Implementation & Improved Operation
Troubleshooting
Electrical welding can generate significant surges
7/28/2019 2 Installation - Issues and Solutions
41/53
4141 Successful Implementation & Improved Operation
Bend radius too tight, Upward facing gland risks water ingress
Two cables into one gland
prevents sealing of gland
Water ingress caused corrosion of wire and terminals
7/28/2019 2 Installation - Issues and Solutions
42/53
4242 Successful Implementation & Improved Operation
Water ingress caused corrosion of wire and terminals
7/28/2019 2 Installation - Issues and Solutions
43/53
4343 Successful Implementation & Improved Operation
Cable jacket stripped back too far
Troubleshooting
Wires coming out of ferrules
7/28/2019 2 Installation - Issues and Solutions
44/53
4444 Successful Implementation & Improved Operation
Wires coming out of ferrules
7/28/2019 2 Installation - Issues and Solutions
45/53
4545 Successful Implementation & Improved Operation
Troubleshooting
Earth stud not connected internal
surge protectors not working
7/28/2019 2 Installation - Issues and Solutions
46/53
4646 Successful Implementation & Improved Operation
Troubleshooting
Ground not connected
7/28/2019 2 Installation - Issues and Solutions
47/53
4747 Successful Implementation & Improved Operation
Troubleshooting
Poor cable (shield) quality
7/28/2019 2 Installation - Issues and Solutions
48/53
4848 Successful Implementation & Improved Operation
Troubleshooting
Grounding concept failure-prone
7/28/2019 2 Installation - Issues and Solutions
49/53
4949 Successful Implementation & Improved Operation
Troubleshooting
Water marks, fungus inside junction box
7/28/2019 2 Installation - Issues and Solutions
50/53
5050 Successful Implementation & Improved Operation
Troubleshooting
Wire squeezed by enclosure lid water ingress
http://forums.fieldbus.org/showthread.php?t=1298
7/28/2019 2 Installation - Issues and Solutions
51/53
5151 Successful Implementation & Improved Operation
7/28/2019 2 Installation - Issues and Solutions
52/53
5252 Successful Implementation & Improved Operation
Conclusion
Fieldbus is robust if the installation is adjusted to
the requirements of a digital communication line
Do not simply copy 4-20 methods
Use fieldbus smartly (e.g. eliminate marshalling)
Good wiring practices are more important thanon 4-20 due to bus structure
Train your installers on fieldbus practices
7/28/2019 2 Installation - Issues and Solutions
53/53
Installation Issues and Solutions
Andreas AgostinIndustrial Network Sales Specialist Asia Pacific
MTL Instruments Singapore, part of Cooper Crouse-Hinds
22.02.2012 Kuala Lumpur