2 Installation - Issues and Solutions

Embed Size (px)

Citation preview

  • 7/28/2019 2 Installation - Issues and Solutions

    1/53

    11 Successful Implementation & Improved Operation

    Installation Issues and Solutions

    Andreas AgostinIndustrial Network Sales Specialist Asia PacificMTL Instruments Singapore, part of Cooper Crouse-Hinds

    22.02.2012 Kuala Lumpur

  • 7/28/2019 2 Installation - Issues and Solutions

    2/53

    22 Successful Implementation & Improved Operation

    Introduction

    Fieldbus is in use since 19981

    , yet still new formany customers today.

    This presentation will look at the installation issues

    and the lessons learned, so that you canbenefits from their experience.

    1 Shell Malampaya is one of the early, larger projects. 1600 FF instruments are in use. The project produced first gas in

    Oct 2001. Source: J. Seaver, Shell Philippines Exploration B.V., Malampaya Deep Water Gas-to-Power Project:

    Malampaya Subsea Development, Offshore Technology Conference, 6 May-9 May 2002, Houston, Texas.

  • 7/28/2019 2 Installation - Issues and Solutions

    3/53

    33 Successful Implementation & Improved Operation

    Introduction

    The pictures you will see are collected from realprojects; they are neither simulated nor demo.

    We will look at Control room: cabinet design and wiring

    Field: Wiring, field junction boxes, field device installation.

    Processes typically involve explosion protection methods

    intrinsic safety (I.S. / Ex i; energy limitation by a barrier)

    or explosion proof (Ex d; protection by explosionproof

    enclosure).

    Many examples use IS as this is a key product of my

    company and that is where I get involved.

  • 7/28/2019 2 Installation - Issues and Solutions

    4/53

    44 Successful Implementation & Improved Operation

    Disclaimer

    All products shown serve as EXAMPLE only.In particular, problems shown in conjunction with a product

    serve as example only.

    The brand/make/model of the product serving as example

    is IRRELEVANT.

    Problems highlighted serve as example only, are do in no

    way express problems with a particular product,

    model or brand.

  • 7/28/2019 2 Installation - Issues and Solutions

    5/53

    55 Successful Implementation & Improved Operation

    The conventional system

  • 7/28/2019 2 Installation - Issues and Solutions

    6/53

    66 Successful Implementation & Improved Operation

    Control room Conventional wiring

    2nd

    level 1st

    leveljunction box Marshalling

    and barrierControl system

  • 7/28/2019 2 Installation - Issues and Solutions

    7/5377 Successful Implementation & Improved Operation

    Control room Conventional wiring

    Marshalling: to group AI / AO / DI / DO / etc

  • 7/28/2019 2 Installation - Issues and Solutions

    8/5388 Successful Implementation & Improved Operation

    Control room Conventional wiring

  • 7/28/2019 2 Installation - Issues and Solutions

    9/5399 Successful Implementation & Improved Operation

    Control room Conventional wiring

    Long wires, standard length

    Allows pre-fabrication of wire

    (ferrules, mounting)

    Conventional signals (4-20mA,

    RTD, thermocouple, 0-

    5V/10V/24V) slow, hardware

    filtered, length less important

  • 7/28/2019 2 Installation - Issues and Solutions

    10/531010 Successful Implementation & Improved Operation

    Field Conventional wiring

    Quality (material) Safety

    Location / access

    Weight/size,

    10

  • 7/28/2019 2 Installation - Issues and Solutions

    11/531111 Successful Implementation & Improved Operation

    Fieldbus versus conventional

  • 7/28/2019 2 Installation - Issues and Solutions

    12/531212 Successful Implementation & Improved Operation

    Control room DCS wiring EXAMPLES

    Fieldbus

    Conventional

  • 7/28/2019 2 Installation - Issues and Solutions

    13/531313 Successful Implementation & Improved Operation

    Control room DCS wiring EXAMPLES

    Installations do not haveto look messy. They

    can be very nice, too.

    Fieldbus

    Conventional

  • 7/28/2019 2 Installation - Issues and Solutions

    14/531414 Successful Implementation & Improved Operation

    Control room DCS wiring EXAMPLESFieldbus Conventional

  • 7/28/2019 2 Installation - Issues and Solutions

    15/531515 Successful Implementation & Improved Operation

    Control room DCS wiring EXAMPLES

    Fieldbus Fieldbus

  • 7/28/2019 2 Installation - Issues and Solutions

    16/531616 Successful Implementation & Improved Operation

    Control room DCS wiring

    Important:

    do not use individual wires to

    wire cabinet. Use fieldbus cable

    and shield properly.

    Why?

    Higher signal

    frequency protect

    them against

    disturbances.

    Individual wires will

    cause crosstalk from

    one wire to another

    communication faults

    can occur.?

  • 7/28/2019 2 Installation - Issues and Solutions

    17/531717 Successful Implementation & Improved Operation

    Fieldbus CableRecommended:

    Type A cable: Shielded twisted pair

    Other cable is possible, but there are limitations in termsof achievable cable distance and electromagneticcompatibility (EMC).

    Fieldbus is a digital high speed (31kBit/s)communication, a current modulated signalsuperimposed on the DC power.

  • 7/28/2019 2 Installation - Issues and Solutions

    18/531818 Successful Implementation & Improved Operation

    Fieldbus Cable

    Shielded pair

    principle

    Foil

    shield

    Foil plus

    braided

    shield

    SWA

    SWA

    Multi-pair

    Multi-pair (multi-trunk)

    Pl t thi

  • 7/28/2019 2 Installation - Issues and Solutions

    19/531919 Successful Implementation & Improved Operation

    Please not this way

    Images obscured

    Brand is irrelevant.

  • 7/28/2019 2 Installation - Issues and Solutions

    20/532020 Successful Implementation & Improved Operation

    Control room DCS wiring

  • 7/28/2019 2 Installation - Issues and Solutions

    21/53

    2121 Successful Implementation & Improved Operation

    Fieldbus system Field wiring

    ? Parallel wiring

    (terminals)

    special wiring

    blocks

    (daisy chaining)

  • 7/28/2019 2 Installation - Issues and Solutions

    22/53

    2222 Successful Implementation & Improved Operation

    Fieldbus system Field junction boxes

    Principle of wiring distribution in junction box:all devices are in parallel

    Source: FF AG 140 Rev. 1

  • 7/28/2019 2 Installation - Issues and Solutions

    23/53

    2323 Successful Implementation & Improved Operation

    Fieldbus system Field junction boxes

    Please not this way

  • 7/28/2019 2 Installation - Issues and Solutions

    24/53

    2424 Successful Implementation & Improved Operation24

    Fieldbus system Field junction boxes

    Use dedicatedwiring blocks

    with built-in

    electronic

    short circuit

    protection.

    LEDs: - built-in s/c protection

  • 7/28/2019 2 Installation - Issues and Solutions

    25/53

    2525 Successful Implementation & Improved Operation

    Good Wiring Practices

    Test segment wiring before connecting components Avoid damaging the wire when removing insulation Ground the cable shield only at one point (at the control

    room end) Insulate the ungrounded end of the cable shield (at the

    instrument) Ground armor on both sides (potential equalization) Use crimp ferrules

    Ferrule diameter must fit wire Crimp tool must fit ferrule

    Ferrule must fit terminals Maintain polarity and associated color codes throughoutthe segment

  • 7/28/2019 2 Installation - Issues and Solutions

    26/53

    2626 Successful Implementation & Improved Operation

    Good Wiring Practices

    Lessons learned:

    Torque screwdriver Wire end ferrules

    Right (!) wire strippers

    Fieldbus tester

    Harms

    wire strands

    Choose

    right size

  • 7/28/2019 2 Installation - Issues and Solutions

    27/53

    2727 Successful Implementation & Improved Operation

    Fieldbus Design Tools(Examples)

  • 7/28/2019 2 Installation - Issues and Solutions

    28/53

    2828 Successful Implementation & Improved Operation

    Project Procedure

    Best practice: Bench test

    Functional tests and interoperability test

    FAT

    SAT

  • 7/28/2019 2 Installation - Issues and Solutions

    29/53

    2929 Successful Implementation & Improved Operation

    Installation Guidelines

    Cable Tests

    Experience has shown that new cable irregularities areso infrequent that it is more efficient to check cableafter installation

    Cable Installation Verify that cable is properly installed, bypassing impact

    from wiring components Segment Checkout

    Check of proper wiring of wiring components Device installation

    Check of proper device installation Loop checkout

    Functional test

  • 7/28/2019 2 Installation - Issues and Solutions

    30/53

    3030 Successful Implementation & Improved Operation

    Installation tools

    Portable fieldbus diagnostic test equipment(Handhelds)

    Measures relevant fieldbus

    parameters Establish baseline

    after commissioning

  • 7/28/2019 2 Installation - Issues and Solutions

    31/53

    3131 Successful Implementation & Improved Operation

    Handheld diagnostic tools

    Handheld

    Diagnostic

    ToolDevice 1 Device 3Device 2

    T

    Device Coupler

    & Terminator

    (non-IS) Spurs

    FFPS

    T

    FF Power Supply

    & Conditioner

    &Terminator

    24VDC

    Host

    Computer

    H1 Interface

    Connect at respective location to obtain accurate measurement.

  • 7/28/2019 2 Installation - Issues and Solutions

    32/53

    3232 Successful Implementation & Improved Operation

    Handheld diagnostic tools

    Handheld

    Diagnostic

    Tool

    FFPS

    T

    FF Power Supply

    & Conditioner

    &Terminator

    24VDC

    Host

    Computer

    H1 Interface

    Fieldbus

    barrier

    Device 1 Device 3Device 2

    Fieldbus barrier

    & Terminator

    Intrinsically

    Safe Spurs

    T

    Fieldbus

    barrier

    To measure at fieldbus barrier/IS segments, Handheld needs to be Ex i approved.

    Important since the galvanic isolation of fieldbus barrier impacts on measurement.

  • 7/28/2019 2 Installation - Issues and Solutions

    33/53

    3333 Successful Implementation & Improved Operation

    Earthing/Grounding

    Grounding in the control room One point grounding only

    Continuous shield from control room to the field

    Shield not connected at the field instrument

    Connect cable armor at both ends (potential

    equalization)

  • 7/28/2019 2 Installation - Issues and Solutions

    34/53

    3434 Successful Implementation & Improved Operation

    Earthing/Grounding

    Device 1 Device 3Device 2

    T

    Wiring Block

    & TerminatorFFPS

    T

    FF Power Supply

    & Conditioner

    &Terminator

    24VDC

    Host

    Computer

    H1 Interface

  • 7/28/2019 2 Installation - Issues and Solutions

    35/53

    3535 Successful Implementation & Improved Operation

    Fieldbus

    barrier

    Device 1 Device 3Device 2

    Fieldbus barrier

    & Terminator

    Intrinsically

    Safe Spurs

    T

    Fieldbus

    barrier

    Earthing/Grounding

    FFPS

    T

    FF Power Supply

    & Conditioner

    &Terminator

    24VDC

    Host

    Computer

    H1 Interface

  • 7/28/2019 2 Installation - Issues and Solutions

    36/53

    3636 Successful Implementation & Improved Operation

    Local field junction box for 4

    instruments. Rust prevented

    proper grounding, so that

    separate ground connection

    was required

  • 7/28/2019 2 Installation - Issues and Solutions

    37/53

    3737 Successful Implementation & Improved Operation

    Field Fieldbus wiring

    Green: fieldbus

    Red: Power (Motors, etc)

    For easy maintenance

  • 7/28/2019 2 Installation - Issues and Solutions

    38/53

    3838 Successful Implementation & Improved Operation

    Troubleshooting

  • 7/28/2019 2 Installation - Issues and Solutions

    39/53

    3939 Successful Implementation & Improved Operation

    Daisy chaining not recommended

  • 7/28/2019 2 Installation - Issues and Solutions

    40/53

    4040 Successful Implementation & Improved Operation

    Troubleshooting

    Electrical welding can generate significant surges

  • 7/28/2019 2 Installation - Issues and Solutions

    41/53

    4141 Successful Implementation & Improved Operation

    Bend radius too tight, Upward facing gland risks water ingress

    Two cables into one gland

    prevents sealing of gland

    Water ingress caused corrosion of wire and terminals

  • 7/28/2019 2 Installation - Issues and Solutions

    42/53

    4242 Successful Implementation & Improved Operation

    Water ingress caused corrosion of wire and terminals

  • 7/28/2019 2 Installation - Issues and Solutions

    43/53

    4343 Successful Implementation & Improved Operation

    Cable jacket stripped back too far

    Troubleshooting

    Wires coming out of ferrules

  • 7/28/2019 2 Installation - Issues and Solutions

    44/53

    4444 Successful Implementation & Improved Operation

    Wires coming out of ferrules

  • 7/28/2019 2 Installation - Issues and Solutions

    45/53

    4545 Successful Implementation & Improved Operation

    Troubleshooting

    Earth stud not connected internal

    surge protectors not working

  • 7/28/2019 2 Installation - Issues and Solutions

    46/53

    4646 Successful Implementation & Improved Operation

    Troubleshooting

    Ground not connected

  • 7/28/2019 2 Installation - Issues and Solutions

    47/53

    4747 Successful Implementation & Improved Operation

    Troubleshooting

    Poor cable (shield) quality

  • 7/28/2019 2 Installation - Issues and Solutions

    48/53

    4848 Successful Implementation & Improved Operation

    Troubleshooting

    Grounding concept failure-prone

  • 7/28/2019 2 Installation - Issues and Solutions

    49/53

    4949 Successful Implementation & Improved Operation

    Troubleshooting

    Water marks, fungus inside junction box

  • 7/28/2019 2 Installation - Issues and Solutions

    50/53

    5050 Successful Implementation & Improved Operation

    Troubleshooting

    Wire squeezed by enclosure lid water ingress

    http://forums.fieldbus.org/showthread.php?t=1298

  • 7/28/2019 2 Installation - Issues and Solutions

    51/53

    5151 Successful Implementation & Improved Operation

  • 7/28/2019 2 Installation - Issues and Solutions

    52/53

    5252 Successful Implementation & Improved Operation

    Conclusion

    Fieldbus is robust if the installation is adjusted to

    the requirements of a digital communication line

    Do not simply copy 4-20 methods

    Use fieldbus smartly (e.g. eliminate marshalling)

    Good wiring practices are more important thanon 4-20 due to bus structure

    Train your installers on fieldbus practices

  • 7/28/2019 2 Installation - Issues and Solutions

    53/53

    Installation Issues and Solutions

    Andreas AgostinIndustrial Network Sales Specialist Asia Pacific

    MTL Instruments Singapore, part of Cooper Crouse-Hinds

    22.02.2012 Kuala Lumpur

    [email protected]

    Ph: +65 97585161