Upload
aurman7
View
224
Download
4
Embed Size (px)
DESCRIPTION
2. Experiences With LNG Worldwide
Citation preview
1 LNG Conference June 12, 2007
Experiences with LNG Worldwide
LNG Conference 12 June 2007
by Thomas Dahlgren and Steen Rasmussen, COWI
LNG Conference June 12, 20072
COWI LNG Experience
� COWI has been involved in the planning and design of more than10 major LNG Terminals since 2002
� Experience has been gained predominantly in the Middle East and Africa and to a lesser degree in North America and Europe
LNG Conference June 12, 20078
Example LNG Terminal - EgyptianLNG
� Design Year: 2002
� Vessel size: 137,000 m3
� Train size: 3.6 MTA
� Transfer rate: about 7-8000m3/hour
� Storage tank size: two tanks each with 140,000 m3 capacity
LNG Conference June 12, 200710
Example LNG Terminal - Port of Ras Laffan, Qatar
� Design Year: 2006
� Maximum vessel size: 267,000 m3
� Train size: 7.8 MTA
� Transfer rate: about 14,000m3/hour
LNG Conference June 12, 200713
Key challenges with smallerreceiving terminals
� Local approval - many sees LNG vessels and storage tanks as highexplosion risks - this is major concern in f.ex. the US.
� Securing supply. Many countries are planning smaller import terminals (around 2-3 MTA) but are facing difficulties in securingsupply as the export countries give priority to large import clientssuch as Japan, Korea, US etc.
� Distribution - how to fit the LNG into the existing distribution system. Can it compete with piped gas where this is an option?
LNG Conference June 12, 200715
LNG Satellite
LNG station constructed at the demand area at distance from LNG receiving terminal is so called "LNG Satellite".
Generally, LNG tank, LNG vaporizer, BOG treatment unit, Calorific control unit and Odorization unit are installed in LNG Satellite.
LNG Conference June 12, 200716
LNG Container
LNG container in addition to previous tank lorry for LNG inland transportation.
LNG inland transportation cost is drastically reduced by way of using this LNG container on railway.
Furthermore, on-site LNG supply is easily realized simply by way of putting this LNG container within the battery limit of the customer’s site.
LNG Conference June 12, 200719
13.52437*2472*12192
23 50040 FT
10.952490*2500*9122
20 00030 FT
Capacityton
DimensionW*H*L mm
WeightKg
Container
Composite Insulation Vessels
LNG Conference June 12, 200720
Vacuum insulation(Composite System)
Outer VesselInner vesselGas phase
Liquid phase
Customer
Pressurizer combination typeUnderdevelopment
Customer
LNG Supply
LNG Delivery EquipmentLNG Container
LNG
LNG
LNG Supply
Unloading Pressurizer
Unloading Pressurizer
12.4 t5.6 t20 ft cont.
19.8 t10.9 t30 ft cont.
23.5 t13.5 t40 ft cont.
Total weight
Load weight
Size
Specifications