Upload
alif-affza
View
213
Download
0
Embed Size (px)
Citation preview
8/17/2019 2 1 Building
1/75
ONSTRU TION
TE HNOLOGY
CEM 571
8/17/2019 2 1 Building
2/75
CHAPTER 2
STAGES FOR CONSTRUCTION
1. Building
2. Retaining walls, Drainage
3. Road, Highway, Bridges
4. Airports, Offshore/Marine structure
8/17/2019 2 1 Building
3/75
BUILDING
8/17/2019 2 1 Building
4/75
At the end of lectures, student will be able to :
- Identify setting out works involve in building
construction, i.e., site clearing, setting out and
establish the building datum level. (CO1:PO2)
- identify the accommodations, storage and security
requirements during the building construction
stage. (CO1:PO2)- describe the detail building stages involved during
the building construction process. (CO1:PO2)
LESSON OUT OME
8/17/2019 2 1 Building
5/75
BUILDINGAny man-made structure used or intended for
supporting or sheltering any use or
continuous occupancy.
1. Site works and setting out
2. Accommodation, storage and security
3. Detail building stages
8/17/2019 2 1 Building
6/75
CONSTRUCTION SITE
A building or construction site can be considered as a
temporary factory employing the necessary resources
to successfully fulfill a contract.
8/17/2019 2 1 Building
7/75
1. SITE WORKS AND SETTING
OUT
Contractors responsibility after beinggiven possession and site layout planand detail drawings necessary
Commencing tasks:-a. Clearing the site
b. Setting out the building
c. Establishing a datum level
8/17/2019 2 1 Building
8/75
Construction documents
ARCHITECTDRAWING
ENGINEERSDRAWING
SCHEDULES/PLANNING
SPECIFICATIONBILL OF
QUANTITIESCONTRACTDOCUMENT
8/17/2019 2 1 Building
9/75
8/17/2019 2 1 Building
10/75
SITE INVESTIGATION
Soil investigation include the following:-
a) Land surveying
• Boundaries determination and set up
• Establishing a datum level (TBM)
b) Assessment and testing
• Sampling of media such as soil, water or air.
c) Availability of materials and basic supply• Construction materials
• Available road and drainage systems
• Electrical and water supply
• Environments
8/17/2019 2 1 Building
11/75
Clearing the Site
May involve:-
Demolition of existing buildings (by experiencedcontractor)
Grubbing out bushes and trees (by manual ormechanical means, or by specialist for the large trees)
Removal of soil to reduce levels following to BuildingRegulation C1 (sterilize the top 300 mm to contain plantlife and decaying vegetation)
8/17/2019 2 1 Building
12/75
8/17/2019 2 1 Building
13/75
Removal of tree trunks
8/17/2019 2 1 Building
14/75
Grubbing of trees, shrubs and roots
8/17/2019 2 1 Building
15/75
Site clearing work carried out
8/17/2019 2 1 Building
16/75
Excavator heaping up top soil
8/17/2019 2 1 Building
17/75
Earthwork operation
8/17/2019 2 1 Building
18/75
Setting Out the Site
1. Establish a base line from which the whole of thebuilding can be set out.
Marked on site clearly so that it can be re-established at
any time Using steel tape (30 meters and not stretchable is more
suitable)
Marked each corner with a stout peg
Check on the right angle and correct lengths (advisableusing different method)
8/17/2019 2 1 Building
19/75
8/17/2019 2 1 Building
20/75
8/17/2019 2 1 Building
21/75
8/17/2019 2 1 Building
22/75
a) SITE BOUNDARY The surveyor must to determine the site boundary of the
construction area to avoid trespass to the anotherconstruction area.
The boundary had determine
8/17/2019 2 1 Building
23/75
Land surveyor
determine the
OGL
b LEVELING
The land surveyor willdetermine the original ground
level for the land and mark a
survey peg for drain, pipes,cables and main sewerage
treatment plant (MSTP), also
the road complying with theJabatan Pengairan dan Saliran
(JPS).
8/17/2019 2 1 Building
24/75
Setting Out the Site
2. Set up profile board-after the main buildinglines
Should set up clear of the foundations trench
positions to locate the trench, foundations andwalls
Required at all trench and wall intersections
2.0
8/17/2019 2 1 Building
25/75
Typical profile board
8/17/2019 2 1 Building
26/75
Establishing a Datum Level
All levels in a building are taken from a fixedpoint called a ‘datum’
Should establish after the setting out and
related to ordnance benchmark
An arrow with a horizontal mark above thearrow
The centerline of the horizontal being theactual level indicated on an ordnance surveymaps
8/17/2019 2 1 Building
27/75
8/17/2019 2 1 Building
28/75
Rise and fall method:
Staff reading at A = 2.500 m
Staff reading at B = 0.750 m
Ground level at A = 100 m above ordinance datum(AOD)
Level at B = 100 m + rise (− fall if declining)
Level at B = 100 m + (2.500 − 0.750) = 101.750 m.
Alternative height of collimation (HC) method:
HC at A = Reduced level (RL) + staff reading = 100 m + 2.500 = 102.500 (AOD)
Level at B = HC at A − staff reading at B
= 102.500 − 0.750 = 101.750 m
8/17/2019 2 1 Building
29/75
Sloping Sites
Three methods in reducing levels:-
1. Cut and Fill - usual method, the amountof cut will equal the amount of fill
2. Cut – Advantages of havingundisturbed soil over the site, buthaving disadvantages of cost ofremoving the spoil from the site
3. Fill – Not to be recommended, deepfoundation would be needed, the riskof settlement and the amount of fillshould be limited to 600 mm
8/17/2019 2 1 Building
30/75
Sloping sites
8/17/2019 2 1 Building
31/75
Accommodation,
Storage and
Security
SITE OFFICE
8/17/2019 2 1 Building
32/75
SITE OFFICE
HOARDING
PROJECT SIGNBOARD
8/17/2019 2 1 Building
33/75
Accommodation
Regulations 1996 (Health, safety andwelfare)
Requirements defers due to numbers of siteworkers and duration of contract
Staff accommodations usually:-
semi-portable units
mobile caravans or cabins
Facilities provided:-
First aid, stretcher ambulance, first aidroom, shelter and clothing, meals room,washing facilities and sanitary facilities
8/17/2019 2 1 Building
34/75
Semi-portable Units
8/17/2019 2 1 Building
35/75
Mobile Caravans OrCabins
8/17/2019 2 1 Building
36/75
Storage
Type of storage depend on:- Durability
Vulnerability to damage
Vulnerability to theft
Examples..
Cement and plaster (in bag form) – dry store free from
moist air
Aggregates and sand – clean firm base, separate
different materials and grade, watch on moisture content
Bricks and blocks – stacked in stable piles, covered
adequately
8/17/2019 2 1 Building
37/75
8/17/2019 2 1 Building
38/75
Protection fencing
Typical fencing details
8/17/2019 2 1 Building
39/75
Typical fencing details
Cleft chestnut pale fencing
8/17/2019 2 1 Building
40/75
Chain link fence with concrete
posts2
Cl b d d f ith
8/17/2019 2 1 Building
41/75
Close boarded fence with
concrete post
Security and Protection
8/17/2019 2 1 Building
42/75
Security and Protection-
fencing- Hoardings
Close boarded fences of barriers erectedadjacent to a highway or public footpath
Prevent unauthorized persons obtainingaccess to site and protect public from dustand noise
Necessary to obtain written permission fromthe local authority to erect a hoarding(Highways Act 1980)
8/17/2019 2 1 Building
43/75
Hoardings
Two forms:-
Vertical hoardings
a series of closed boarded panels securely fixed to
resist wind load and accidental impact loadCan be free standing or fixed by stays by the external
walls of an existing building
Fan hoardings
To protect persons from falling objects
Place at a level above the normal traffic height andensure any falling debris is directed back towards thebuilding or scaffold
T i l f t di g
8/17/2019 2 1 Building
44/75
Typical free standing
vertical hoarding1
Typical fan hoarding
8/17/2019 2 1 Building
45/75
Typical fan hoarding
2
8/17/2019 2 1 Building
46/75
BUILDING STAGES
Order of construction Excavation and timberingFoundationsConcrete floors
Reinforced concrete framesRoofsBrickwork Internal fixtures and fittings
InsulationPlumbing and wiringPainting and decorating
8/17/2019 2 1 Building
47/75
Excavation and Timbering
Before a foundation can be laid, it is necessary to excavate a trench of therequired depth and width (by hand or mechanical excavator)
Timbering – term used to cover temporary supports to the sides of
excavations and is sometimes called planking and strutting
Type and amount – depend on the depth, nature of subsoil, weather conditionsand duration
Typical example of trench
8/17/2019 2 1 Building
48/75
Typical example of trench
excavations
8/17/2019 2 1 Building
49/75
Trench excavation
8/17/2019 2 1 Building
50/75
FOUNDATIONS
Foundation is the base on which a building rests and its purpose is to safely transfer the load of a building tosuitable subsoil
Building regulations :-
Safely sustain and submit to the ground the combineddead and imposed loads so as not to imposed anysettlement or other movement in any part of the buildingor of any adjoining buildings or works
Be a such a depth, or be so constructed, as to avoid anydamage by swelling, shrinkage or freezing of the subsoil
Be capable of resisting attack by deleterious material, such assulphates, in the subsoil
8/17/2019 2 1 Building
51/75
Foundation
Shallow foundations – transfer loads to subsoil at apoint near to the ground floor of the building…padfooting, strip, rafts , combinations..
Deep foundations – transfer the loads to a subsoilsome distance below the ground floor of thebuilding…..pile foundations
8/17/2019 2 1 Building
52/75
PROBLEM……………
Underground water
Pipe line….electrical, water,
sewerage, drainageSink hole
Ground settlement
CONSTRUCTION
8/17/2019 2 1 Building
53/75
CONSTRUCTIONFOUNDATION…
8/17/2019 2 1 Building
54/75
BEAM…
A beam is a structural element that is capable ofwithstanding load primarily by resisting bending. Thebending force induced into the material of the beam asa result of the external load, own weight and external
reactions to these loads is called a bending moment(wikipedia).
Beam can be:
Suspended beam…simply @ fixed support.
Non suspended..cantiliver @ on ground.
Method of construction depends on type of materialsused.
8/17/2019 2 1 Building
55/75
BEAM….
8/17/2019 2 1 Building
56/75
SLAB…
A broad flat square or rectangular piece of wood, stone orother solid material used to construct buildings, pavements,patios, paths in horizontal plane
Can be suspended or non suspended
Method of construction depends on type of materials used
8/17/2019 2 1 Building
57/75
SLAB…
8/17/2019 2 1 Building
58/75
COLUMN…
A column in structural engineering is a verticalstructural element that transmits, throughcompression, the weight of the structureabove to other structural elements below. For
the purpose of wind or earthquakeengineering, columns may be designed toresist lateral forces
8/17/2019 2 1 Building
59/75
8/17/2019 2 1 Building
60/75
WALL…
A wall is a usually solid structure that defines andsometimes protects an area.
Most commonly, a wall delineates a building andsupports its superstructure, separates space inbuildings into rooms, or protects or delineates a spacein the open air.
There are three principal types of structural walls:building walls, exterior boundary walls, and retainingwalls.
8/17/2019 2 1 Building
61/75
8/17/2019 2 1 Building
62/75
BRICKWORK…
ROOF…
8/17/2019 2 1 Building
63/75
ROOF…
A roof is the covering on the uppermost partof a building. A roof protects the buildingand its contents from the effects of weather.Structures that require roofs range from aletter box to a cathedral or stadium,dwellings being the most numerous .
The elements in the design of a roof are :-
the material
the construction
the durability
8/17/2019 2 1 Building
64/75
ROOF CONSTRUCTION….
8/17/2019 2 1 Building
65/75
Types of roof
Flat Roofs
8/17/2019 2 1 Building
66/75
Types of roof Sloping Roofs
8/17/2019 2 1 Building
67/75
Types of roof
Gable Roofs
8/17/2019 2 1 Building
68/75
Types of roof
Salt Box
8/17/2019 2 1 Building
69/75
Types of roof
Gambrel Roof
8/17/2019 2 1 Building
70/75
Types of roof
Mansard Roof
8/17/2019 2 1 Building
71/75
8/17/2019 2 1 Building
72/75
Types of roof
Hip Roof
8/17/2019 2 1 Building
73/75
END OF LECTURE …………
ANYQUESTIONS
…..
CAN YOU IDENTIFY AND
8/17/2019 2 1 Building
74/75
CAN YOU IDENTIFY AND
BRIEFLY EXPLAIN…….
the setting out works involve in building construction, i.e., siteclearing, setting out and establish the building datum level.(CO1)
the accommodations, storage and security requirements
during the building construction stage. (CO1) describe the detail building stages involved during the
building construction process. (CO1)
8/17/2019 2 1 Building
75/75
END..……
THANK
YOU