    CHAPTER 2

    STAGES FOR CONSTRUCTION 

    1. Building

    2. Retaining walls, Drainage

    3. Road, Highway, Bridges

    4. Airports, Offshore/Marine structure

  • 8/17/2019 2 1 Building

    3/75

    BUILDING

  • 8/17/2019 2 1 Building

    4/75

    At the end of lectures, student will be able to :

    - Identify setting out works involve in building

    construction, i.e., site clearing, setting out and

    establish the building datum level. (CO1:PO2)

    - identify the accommodations, storage and security

    requirements during the building construction

    stage. (CO1:PO2)- describe the detail building stages involved during

    the building construction process. (CO1:PO2)

    LESSON OUT OME

  • 8/17/2019 2 1 Building

    5/75

    BUILDINGAny man-made structure used or intended for

    supporting or sheltering any use or

    continuous occupancy.

    1. Site works and setting out

    2. Accommodation, storage and security

    3. Detail building stages

  • 8/17/2019 2 1 Building

    6/75

    CONSTRUCTION SITE

    A building or construction site can be considered as a

    temporary factory employing the necessary resources

    to successfully fulfill a contract.

  • 8/17/2019 2 1 Building

    7/75

    1. SITE WORKS AND SETTING

    OUT  

    Contractors responsibility after beinggiven possession and site layout planand detail drawings necessary

    Commencing tasks:-a. Clearing the site

    b. Setting out the building

    c. Establishing a datum level

  • 8/17/2019 2 1 Building

    8/75

    Construction documents

    ARCHITECTDRAWING

    ENGINEERSDRAWING

    SCHEDULES/PLANNING

    SPECIFICATIONBILL OF

    QUANTITIESCONTRACTDOCUMENT

  • 8/17/2019 2 1 Building

    9/75

  • 8/17/2019 2 1 Building

    10/75

    SITE INVESTIGATION

    Soil investigation include the following:-

    a) Land surveying

    • Boundaries determination and set up

    • Establishing a datum level (TBM)

    b) Assessment and testing

    • Sampling of media such as soil, water or air.

    c) Availability of materials and basic supply• Construction materials

    •  Available road and drainage systems

    • Electrical and water supply

    • Environments

  • 8/17/2019 2 1 Building

    11/75

    Clearing the Site

    May involve:-

    Demolition of existing buildings (by experiencedcontractor)

    Grubbing out bushes and trees (by manual ormechanical means, or by specialist for the large trees)

    Removal of soil to reduce levels following to BuildingRegulation C1 (sterilize the top 300 mm to contain plantlife and decaying vegetation)

  • 8/17/2019 2 1 Building

    12/75

  • 8/17/2019 2 1 Building

    13/75

    Removal of tree trunks

  • 8/17/2019 2 1 Building

    14/75

    Grubbing of trees, shrubs and roots

  • 8/17/2019 2 1 Building

    15/75

    Site clearing work carried out 

  • 8/17/2019 2 1 Building

    16/75

    Excavator heaping up top soil

  • 8/17/2019 2 1 Building

    17/75

    Earthwork operation

  • 8/17/2019 2 1 Building

    18/75

    Setting Out the Site

    1. Establish a base line from which the whole of thebuilding can be set out.

    Marked on site clearly so that it can be re-established at

    any time Using steel tape (30 meters and not stretchable is more

    suitable)

    Marked each corner with a stout peg

    Check on the right angle and correct lengths (advisableusing different method)

  • 8/17/2019 2 1 Building

    19/75

  • 8/17/2019 2 1 Building

    20/75

  • 8/17/2019 2 1 Building

    21/75

  • 8/17/2019 2 1 Building

    22/75

    a) SITE BOUNDARY  The surveyor must to determine the site boundary of the

    construction area to avoid trespass to the anotherconstruction area.

    The boundary had determine

  • 8/17/2019 2 1 Building

    23/75

    Land surveyor

    determine the

    OGL

    b LEVELING 

    The land surveyor willdetermine the original ground

    level for the land and mark a

    survey peg for drain, pipes,cables and main sewerage

    treatment plant (MSTP), also

    the road complying with theJabatan Pengairan dan Saliran

    (JPS).

  • 8/17/2019 2 1 Building

    24/75

    Setting Out the Site

    2. Set up profile board-after the main buildinglines

    Should set up clear of the foundations trench

    positions to locate the trench, foundations andwalls

    Required at all trench and wall intersections

    2.0

  • 8/17/2019 2 1 Building

    25/75

     Typical profile board

  • 8/17/2019 2 1 Building

    26/75

    Establishing a Datum Level

    All levels in a building are taken from a fixedpoint called a ‘datum’ 

    Should establish after the setting out and

    related to ordnance benchmark

    An arrow with a horizontal mark above thearrow

    The centerline of the horizontal being theactual level indicated on an ordnance surveymaps

  • 8/17/2019 2 1 Building

    27/75

  • 8/17/2019 2 1 Building

    28/75

    Rise and fall method:

    Staff reading at A = 2.500 m

    Staff reading at B = 0.750 m

    Ground level at A = 100 m above ordinance datum(AOD)

    Level at B = 100 m + rise (− fall if declining) 

    Level at B = 100 m + (2.500 − 0.750) = 101.750 m.

    Alternative height of collimation (HC) method:

    HC at A = Reduced level (RL) + staff reading = 100 m + 2.500 = 102.500 (AOD)

    Level at B = HC at A − staff reading at B 

    = 102.500 − 0.750 = 101.750 m 

  • 8/17/2019 2 1 Building

    29/75

    Sloping Sites

    Three methods in reducing levels:-

    1. Cut and Fill - usual method, the amountof cut will equal the amount of fill

    2. Cut  –   Advantages of havingundisturbed soil over the site, buthaving disadvantages of cost ofremoving the spoil from the site

    3. Fill  –   Not to be recommended, deepfoundation would be needed, the riskof settlement and the amount of fillshould be limited to 600 mm

  • 8/17/2019 2 1 Building

    30/75

    Sloping sites

  • 8/17/2019 2 1 Building

    31/75

     Accommodation,

    Storage and

    Security

    SITE OFFICE

  • 8/17/2019 2 1 Building

    32/75

    SITE OFFICE

    HOARDING

    PROJECT SIGNBOARD

  • 8/17/2019 2 1 Building

    33/75

     Accommodation

    Regulations 1996 (Health, safety andwelfare)

    Requirements defers due to numbers of siteworkers and duration of contract

    Staff accommodations usually:-

    semi-portable units

    mobile caravans or cabins

    Facilities provided:-

    First aid, stretcher ambulance, first aidroom, shelter and clothing, meals room,washing facilities and sanitary facilities

  • 8/17/2019 2 1 Building

    34/75

    Semi-portable Units

  • 8/17/2019 2 1 Building

    35/75

    Mobile Caravans OrCabins

  • 8/17/2019 2 1 Building

    36/75

    Storage

    Type of storage depend on:- Durability

    Vulnerability to damage

    Vulnerability to theft

    Examples..

    Cement and plaster (in bag form) –  dry store free from

    moist air

    Aggregates and sand –  clean firm base, separate

    different materials and grade, watch on moisture content

    Bricks and blocks –  stacked in stable piles, covered

    adequately

  • 8/17/2019 2 1 Building

    37/75

  • 8/17/2019 2 1 Building

    38/75

    Protection fencing

    Typical fencing details

  • 8/17/2019 2 1 Building

    39/75

     Typical fencing details

    Cleft chestnut pale fencing

  • 8/17/2019 2 1 Building

    40/75

    Chain link fence with concrete

    posts2

    Cl b d d f ith

  • 8/17/2019 2 1 Building

    41/75

    Close boarded fence with

    concrete post

    Security and Protection

  • 8/17/2019 2 1 Building

    42/75

    Security and Protection-

     fencing- Hoardings

    Close boarded fences of barriers erectedadjacent to a highway or public footpath

    Prevent unauthorized persons obtainingaccess to site and protect public from dustand noise

    Necessary to obtain written permission fromthe local authority to erect a hoarding(Highways Act 1980)

  • 8/17/2019 2 1 Building

    43/75

    Hoardings

    Two forms:-

    Vertical hoardings

    a series of closed boarded panels securely fixed to

    resist wind load and accidental impact loadCan be free standing or fixed by stays by the external

    walls of an existing building

    Fan hoardings

    To protect persons from falling objects

    Place at a level above the normal traffic height andensure any falling debris is directed back towards thebuilding or scaffold

    T i l f t di g

  • 8/17/2019 2 1 Building

    44/75

     Typical free standing

     vertical hoarding1

    Typical fan hoarding

  • 8/17/2019 2 1 Building

    45/75

     Typical fan hoarding

    2

  • 8/17/2019 2 1 Building

    46/75

    BUILDING STAGES

    Order of construction Excavation and timberingFoundationsConcrete floors

    Reinforced concrete framesRoofsBrickwork Internal fixtures and fittings

    InsulationPlumbing and wiringPainting and decorating

  • 8/17/2019 2 1 Building

    47/75

    Excavation and Timbering

    Before a foundation can be laid, it is necessary to excavate a trench of therequired depth and width (by hand or mechanical excavator)

    Timbering  –  term used to cover temporary supports to the sides of

    excavations and is sometimes called planking and strutting

    Type and amount –  depend on the depth, nature of subsoil, weather conditionsand duration

    Typical example of trench

  • 8/17/2019 2 1 Building

    48/75

     Typical example of trench

    excavations

  • 8/17/2019 2 1 Building

    49/75

     Trench excavation

  • 8/17/2019 2 1 Building

    50/75

    FOUNDATIONS

    Foundation is the base on which a building rests and its purpose is to safely transfer the load of a building tosuitable subsoil

    Building regulations :-

    Safely sustain and submit to the ground the combineddead and imposed loads so as not to imposed anysettlement or other movement in any part of the buildingor of any adjoining buildings or works

    Be a such a depth, or be so constructed, as to avoid anydamage by swelling, shrinkage or freezing of the subsoil

    Be capable of resisting attack by deleterious material, such assulphates, in the subsoil

  • 8/17/2019 2 1 Building

    51/75

    Foundation

    Shallow foundations –  transfer loads to subsoil at apoint near to the ground floor of the building…padfooting, strip, rafts , combinations..

    Deep foundations –  transfer the loads to a subsoilsome distance below the ground floor of thebuilding…..pile foundations 

  • 8/17/2019 2 1 Building

    52/75

    PROBLEM…………… 

    Underground water

    Pipe line….electrical, water,

    sewerage, drainageSink hole

    Ground settlement

    CONSTRUCTION

  • 8/17/2019 2 1 Building

    53/75

    CONSTRUCTIONFOUNDATION… 

  • 8/17/2019 2 1 Building

    54/75

    BEAM… 

    A beam is a structural element that is capable ofwithstanding load primarily by resisting bending. Thebending force induced into the material of the beam asa result of the external load, own weight and external

    reactions to these loads is called a bending moment(wikipedia).

    Beam can be:

    Suspended beam…simply @ fixed support. 

    Non suspended..cantiliver @ on ground.

    Method of construction depends on type of materialsused.

  • 8/17/2019 2 1 Building

    55/75

    BEAM…. 

  • 8/17/2019 2 1 Building

    56/75

    SLAB… 

    A broad flat square or rectangular piece of wood, stone orother solid material used to construct buildings, pavements,patios, paths in horizontal plane

    Can be suspended or non suspended

    Method of construction depends on type of materials used

  • 8/17/2019 2 1 Building

    57/75

    SLAB… 

  • 8/17/2019 2 1 Building

    58/75

    COLUMN… 

    A column in structural engineering is a verticalstructural element that transmits, throughcompression, the weight of the structureabove to other structural elements below. For

    the purpose of wind or earthquakeengineering, columns may be designed toresist lateral forces

  • 8/17/2019 2 1 Building

    59/75

  • 8/17/2019 2 1 Building

    60/75

    WALL… 

    A wall is a usually solid structure that defines andsometimes protects an area.

     Most commonly, a wall delineates a building andsupports its superstructure, separates space inbuildings into rooms, or protects or delineates a spacein the open air.

    There are three principal types of structural walls:building walls, exterior boundary walls, and retainingwalls.

  • 8/17/2019 2 1 Building

    61/75

  • 8/17/2019 2 1 Building

    62/75

    BRICKWORK… 

    ROOF…

  • 8/17/2019 2 1 Building

    63/75

    ROOF… 

    A roof is the covering on the uppermost partof a building. A roof protects the buildingand its contents from the effects of weather.Structures that require roofs range from aletter box to a cathedral or stadium,dwellings being the most numerous .

    The elements in the design of a roof are :-

    the material

    the construction

    the durability

  • 8/17/2019 2 1 Building

    64/75

    ROOF CONSTRUCTION…. 

  • 8/17/2019 2 1 Building

    65/75

    Types of roof

    Flat Roofs 

  • 8/17/2019 2 1 Building

    66/75

    Types of roof Sloping Roofs 

  • 8/17/2019 2 1 Building

    67/75

    Types of roof

    Gable Roofs 

  • 8/17/2019 2 1 Building

    68/75

    Types of roof

    Salt Box

  • 8/17/2019 2 1 Building

    69/75

    Types of roof

    Gambrel Roof

  • 8/17/2019 2 1 Building

    70/75

    Types of roof

    Mansard Roof

  • 8/17/2019 2 1 Building

    71/75

  • 8/17/2019 2 1 Building

    72/75

    Types of roof

    Hip Roof

  • 8/17/2019 2 1 Building

    73/75

    END OF LECTURE ………… 

    ANYQUESTIONS

    ….. 

    CAN YOU IDENTIFY AND

  • 8/17/2019 2 1 Building

    74/75

    CAN YOU IDENTIFY AND

    BRIEFLY EXPLAIN……. 

    the setting out works involve in building construction, i.e., siteclearing, setting out and establish the building datum level.(CO1)

    the accommodations, storage and security requirements

    during the building construction stage. (CO1) describe the detail building stages involved during the

    building construction process. (CO1)