    Exterior Cladding provide a weather tightenvelope.

    Transfer Structural Loads I.e. wind & liveloads to the supporting secondary framing.

    Provides lateral bracing to the roofs purlins &wall girts.

  • 7/31/2019 1pre Engineered Building System

    6/40

    Purlins & girts receive loads from the roof & wall

    covering & transfer to the main building frame.

    Purlins & girts provide lateral bracing to the building

    columns & rafter preventing lateral bulking of thecompression flanges.

  • 7/31/2019 1pre Engineered Building System

    7/40

    Moment resisting frames provideslateral stability & transfer the roof & wall

    loads to the foundation through anchorbolts.

  • 7/31/2019 1pre Engineered Building System

    8/40

    Roof & wall cross bracing provides longitudinalstability to the building.

    Transfer of the wind loads acting on the buildingend walls to the foundation.

  • 7/31/2019 1pre Engineered Building System

    9/40

  • 7/31/2019 1pre Engineered Building System

    10/40

  • 7/31/2019 1pre Engineered Building System

    11/40

    !"#$%$&

    '$!" Early

    1900s

    1940s

    CONCEPT OF METAL BUILDINGS ORIGINATEDIN U.S.

    SIMPLE INDUSTRIAL STRUCTURES USINGS

    TRUSS RAFTERS, STRAIGHT COLUMNS,SECTIONAL ROOFS & WALL. WEDGE PINS FOR

    CONNECTIONS.

    MASS PRODUCTION OF NISSEN AND QUONSETHOUSING AND STORAGE MODULES FOR US

    ARMY DURING WORLD WAR II

    METAL BUILDING SYSTEM RECOGNIZED AS A

    FAVOURABLE METHOD OF CONSTRUCTION

    OVER CONVENTIONAL METHODS

  • 7/31/2019 1pre Engineered Building System

    12/40

    PEB INDUSTRY EVOLUTION / HISTORY

    COMPUTERISED DESIGN ALLOWED BLDGS TO BETAILORED TO INDIVIDUAL CUST. REQUIREMENTS

    ROLL FORMING LINES ALLOWED CONTINUOUS SPAN COLDROLLED Z-PURLINS

    COLOR COATED PANELS AND FACTORY INSULATEDPANELS IMPROVED ARCHITECTURAL APPEARANCE

    MAJOR INCREASE IN DESIGN POSSIBILITIES CONTRIBUTED

    TO THE BOOM IN METAL BUILDINGS

    THE TERM PRE-ENGINEERED BUILDINGS CAME INTOEXISTENCE

    Late1950s &Early1960s

  • 7/31/2019 1pre Engineered Building System

    13/40

    !"#$%$&'$!"

    TODAY PRE ENGG. METAL BLDGS. DOMINATE

    THE LOW RISE BLDG. MARKET.

    PRECISION ROLL FORMING LINES FOR THE

    CLADDING AND SEC. MEMBERS.

    AUTO. PROD. LINES FOR STRUCT. SECTIONS.

    HIGH QUALITY PAINT SYSTEMS FOR STEEL AND

    CLADDING.

    MBMA STATISTICS SHOW, ABOUT 60 % OF LOW

    RISE INDUSTRIAL AND COMM. BLDGS. IN THEU.S.A. USE THE P.E.B. SYSTEM.

    1990

  • 7/31/2019 1pre Engineered Building System

    14/40

    Pre Engineered Building System is computer

    assisted, and design to create a building for a

    specific use.

    The complete building system is Pre Engineered

    to facilitate easy production & assembly on site.

  • 7/31/2019 1pre Engineered Building System

    15/40

    Contd..

    In PEB System a superior corrosion protection ofa thin coating of resin applied on the top of theAluminium Zinc coating make Galvalume sheet.

    Galvalume steel is a steel sheet product with ahighly corrosion resistance steel, aluminium zinc

    alloy hard dip coating.

    A clear organic acrylic resin coating is then

    applied & then thermally cured.

    A colour coating is given on the top surface for a

    bright appearance with a colour of thecustomers choice.

  • 7/31/2019 1pre Engineered Building System

    16/40

    (#(()$!*)!

    %%) FASTER OCCUPANCY

    SINGLE SOURCE RESPONSIBILITY

    LOWER COST

    FLEXIBILITY IN EXPANSION

    LARGE CLEAR SPANS

    QUALITY CONTROL

    LOW MAINTENANCE ENERGY EFFICIENT ROOF AND

    WALL SYSTEMS

    ARCHITECTURAL VERSATALITY

  • 7/31/2019 1pre Engineered Building System

    17/40

    (++

    +

    PEB System is zero maintenance & superior instrength.

    It is corrosion resistance & feature an attractiveappearance.

    Steel arriving at job site is dry with no residual oilon the surface.

  • 7/31/2019 1pre Engineered Building System

    18/40

    18

    PEB System has protection against non uniform

    weathering.

    Excellent resistant in transit to corrosion &storage strain.

    This system reduces energy loads on buildingsdue to long term bright surface that helps toretain heat reflectivity.

    It is a higher level technology & innovation &

    better product over conventional material.

  • 7/31/2019 1pre Engineered Building System

    19/40

    (%($$!*)!

    %)

    WARE HOUSES

    FACTORIES

    WORKSHOPS

    OFFICES

    GAS STATIONS

    VEHICLE PARKING SHEDS SHOW ROOMS

    AIRCRAFT HANGERS

    SCHOOLS

    SPORTS AND RECREATIONAL FACILITIES

    HOSPITALS

    LABOUR CAMPS

    LOW COST HOUSING

    ETC...

  • 7/31/2019 1pre Engineered Building System

    20/40

    !"#$%#$&"!"#$%#$&"

    ''''''('('))

  • 7/31/2019 1pre Engineered Building System

    21/40

  • 7/31/2019 1pre Engineered Building System

    22/40

  • 7/31/2019 1pre Engineered Building System

    23/40

  • 7/31/2019 1pre Engineered Building System

    24/40

  • 7/31/2019 1pre Engineered Building System

    25/40

  • 7/31/2019 1pre Engineered Building System

    26/40

  • 7/31/2019 1pre Engineered Building System

    27/40

  • 7/31/2019 1pre Engineered Building System

    28/40

  • 7/31/2019 1pre Engineered Building System

    29/40

  • 7/31/2019 1pre Engineered Building System

    30/40

  • 7/31/2019 1pre Engineered Building System

    31/40

  • 7/31/2019 1pre Engineered Building System

    32/40

  • 7/31/2019 1pre Engineered Building System

    33/40

  • 7/31/2019 1pre Engineered Building System

    34/40

  • 7/31/2019 1pre Engineered Building System

    35/40

    The Galvalume sheet manufactured in theworkshop are colour coated & fabricated bycutting to required length & pressing to desiredprofile as per prepared drawings.

    The fabricated sheets & structural memberswere transported to the site of work within aperiod of one week after fabrication.

  • 7/31/2019 1pre Engineered Building System

    36/40

  • 7/31/2019 1pre Engineered Building System

    37/40

    The profiled sheets were positioned in roofing &cladding & fitted on to the structure using selftapping stainless steel screw with neoprene

    washer & then covered with PVC caps of thesame colour as that of the colour coated sheets.

    The roof monitor was also provided along withstainless steel bird mesh fitted in steel frame.

    The roofing system has 5 % of polycarbonatesheets for the natural day light pass into theworkshop specially ordered & manufactured tothe same profile as that of galvalume sheet.

  • 7/31/2019 1pre Engineered Building System

    38/40

    ContdContd

    The roofing system in PEB is latest product &The roofing system in PEB is latest product &since it is made of steel, it is easier to maintainsince it is made of steel, it is easier to maintaincompared to the conventional Sheets.compared to the conventional Sheets.

    It is lighter than conventional Sheets.It is lighter than conventional Sheets.

    TheThe colourcolour coated steelcoated steel GalvalumeGalvalume sheets cansheets canalso be padded with rock wool or a similar productalso be padded with rock wool or a similar productwhich can keep a difference of inside & outsidewhich can keep a difference of inside & outsidetemperature by about 8 Degree centigrade whichtemperature by about 8 Degree centigrade which

    is not possible in conventional Sheets.Thisis not possible in conventional Sheets.Thisrenders better comfort to the people working withinrenders better comfort to the people working withinthereby increasing the productivity also.thereby increasing the productivity also.