Upload
sexyakshay2623
View
215
Download
0
Embed Size (px)
Citation preview
7/29/2019 1power Scenario
1/46
SUDHIR CHOPADE
7/29/2019 1power Scenario
2/46
Why to study power scenario?
Why demand supply mismatch?
What are the characteristics of electricity? Growth of power sector?
Challenges to meet ?
What are power sector reforms ?
Electricity act 2003
Important organizations in power sector with their roles and
responsibilities What is future of electricity market?
7/29/2019 1power Scenario
3/46
1 peta joule = 1015joules = 238.84 x 1012 caloriesOne billion kilowatt hour of electricity = 3.60 peta joules of
energy.
7/29/2019 1power Scenario
4/46
7/29/2019 1power Scenario
5/46
Growth of demand of electricity in India
7/29/2019 1power Scenario
6/46
7/29/2019 1power Scenario
7/46
Challenges in front of power sector.
In case of developing countries, the energy sector assumesa critical importance in view of the ever-increasing energyneeds.
Energy is one of the major inputs for the economic
development of any country. It requires huge investment and proper planning and long
execution time.
.
Lot of socio-economic factors are involved.
Electricity can not be stored so has to be generated whenrequired.
7/29/2019 1power Scenario
8/46
Various options available to meet electricity demand and
challenges
8
7/29/2019 1power Scenario
9/46
7/29/2019 1power Scenario
10/46
Coal reserves available in the world
10
7/29/2019 1power Scenario
11/46
7/29/2019 1power Scenario
12/46
ENERGY SCENARIO
12
7/29/2019 1power Scenario
13/46
ENERGY SCENARIO
13
7/29/2019 1power Scenario
14/46
7/29/2019 1power Scenario
15/46
680 720 760 880 920 960800 84 0
NN
EE
NE
B
DESH-
NEPALBHUTAN
82.50
J&K
HP
PUNJABHARIAN
A
RAJASTHAN UP
MP
BIHARASSAM
MNP
MIZTRP
NG
ME
MYANMAR
SKMDELHI
NERNER
KND
Generation Resources
Load Centers
Weather
Seasons
SS
WW
SRI
ORISSA
L
MAHARASHTRA
KARNATAKA
TAMILNADU
AP
LAKSHADWEE
P
A&N
PONDICHERYGOA
DIUDAMAN
LANKA
CTGR
7/29/2019 1power Scenario
16/46
7/29/2019 1power Scenario
17/46
FOR EASEY CONTROL AND MONITERING OF
POWER SECTOR IT IS DEVIDED IN FIVE
REGIONS
WR - WESTERN REGION
NR - NORTHERN REGIONSR - SOUTHERN REGION
ER - EASTEN REGION
NER - NOR TH EASTERN REGION
7/29/2019 1power Scenario
18/46
EASTERN
NORTHERN
REGION NORTH-EASTERN
REGION
REGIONAL
GRIDS
Deficit Region
Snow fed run-of the river hydro
Highly weather sensitive load
Adverse weather conditions: Fog & Dust
Storm
Very low load
High hydro potential
1 February 2013ERLDC:POWERGRID 181-Feb-13 POWERGRID - NRLDC 18
SOUTHERN
REGION
WESTERNREGION
REGION
Industrial load and agricultural load
Low load
High coal reserves
Pit head base load plants
High load (40% agricultural load)
Monsoon dependent hydro
7/29/2019 1power Scenario
19/46
NEW Grid
South
GridOctober 1991East and Northeast
synchronized
March 2003
West synchronized
With East & Northeast
August 2006
North synchronized
With Central Grid
INDIA
32,87,263 sq. km area
More than 120 crore people
Installed Capacity of 178 GW
1 February 2013ERLDC:POWERGRID 19
South
West
North
East
Northeast
Five Regional Grids
Five Frequencies
Central Grid
7/29/2019 1power Scenario
20/46
N-E-W Grid
EASTERN
REGION
NORTHERN
REGION
NORTH-
EASTERN
REGION
1
The
ElectricalRegions
1 February 2013ERLDC:POWERGRID 201-Feb-13 POWERGRID - NRLDC 20
SOUTH Grid
SOUTHERN
REGION
GION
2
7/29/2019 1power Scenario
21/46
7/29/2019 1power Scenario
22/46
HIGHLIGHTS
Thomas Alva Edison invented Electric Lamp in 1884.
18thNov.1897 first generating station in India (Asia) started at Sidrapong
(Darjiling) [ 3 X 65 KW, 1PH]
Installed capacity of India as on 15thAug 1947 was 1362 MW
Generating capacity has grown from 1712 MW in 1950 to more than 200,000
.
The growth in the transmission lines has been from 2708 ckm in 1950 to more
than 200,000 ckm today.
About 90% of 587,000 villages have been electrified, balance to be electrified by
2015.
65% households have access to Electricity, balance to be covered by 2015.
7/29/2019 1power Scenario
23/46
Power Sector: largest contributor to GHG emissions. (58%)
T&D losses: 18 to 62%
High Commercial losses
India: 6th Largest electricity utilizing country next to USA,
China Ja an UK and France.
India to achieve : 4th rank by next five year plan.
The per capita consumption of electricity is estimated at1000
kWh approx.
7/29/2019 1power Scenario
24/46
Year All India IC (MW)
1947 1362
1966-67 End of 2stPlan - 10092
1971-72 End of 3stPlan - 15254
1976-77 End of 4rdPlan - 21469
1981-82 End of 5th Plan - 32345
- th -
1991-92 End of 7th Plan - 690651996-97 End of 8th Plan - 85919
2001-02 End of 9th Plan - 104917
2006-07 End of 10th Plan - 144565
2011-12 End of 11th Plan - 213069
7/29/2019 1power Scenario
25/46
104917
144565
213069Instal
led
Capacit
1362 465314709
30214
66086
1947 1961 1971 1981 1991 2002 2008 2012
y
year
7/29/2019 1power Scenario
26/46
MW %
9th Plan End 78441 69189 (9252) (11.8)
FY 02-03 81492 71547 (9945) (12.2)
FY 03-04 84574 75066 (9508) (11.2)
FY 04-05 87906 77652 (10254) (11.7)
FY 05-06 93255 81792 (11463) (12.3)
FY 06-07 100715 86818 (13897) (13.8)
FY 07-08 108866 90793 (18073) (16.6)
FY 08-09 109809 94634 (15175) (13.8)
Surplus/DeficitPeriod Peak Demand (MW) Peak Met (MW)
Year wise power and energy deficit in India
MUs %
9th Plan End 522537 483350 (39187) (7.5)
FY 02-03 545983 497890 (48093) (8.8)
FY 03-04 559264 519398 (39866) (7.1)
FY 04-05 591373 548115 (43258) (7.3)
FY 05-06 631757 578819 (52938) (8.4)
FY 06-07 690587 624495 (66092) (9.6)
FY 07-08 739345 666007 (73338) (9.9)
FY 08-09 645789 574562 (71227) (11.0)
Period Energy Requirement (MUs) Energy Availability (MUs) Surplus/Deficit
7/29/2019 1power Scenario
27/46
7/29/2019 1power Scenario
28/46
7/29/2019 1power Scenario
29/46
7/29/2019 1power Scenario
30/46
By the year 2012, Indias peak demand would be 157,107 MW with energy
requirement of 975 BU.
Capacity to increase to 212,000 MW by year 2012 to meet the peak
demand of 1,57,107 MW.
157107 *115705
8149278037
Peak
Peak
Peak
Peak
r
equirement
r
equirement
r
equirement
r
equirement
inMW
inMW
inMW
inMW
yearyearyearyear
7/29/2019 1power Scenario
31/46
Projected economic growth for the year 2012 of 7 to 8%
Necessitates commensurate growth of commercial energy
particularly electricity
Present shortages of 7% in power supply and 10.6% in peak
requirement
enera ng capac y o , , requ re o o v a e
the shortages
Additional capacity Requirement
Indian economy is growing at a rate of approx 8%
Power demand in India is growing at a rate of approx.6%
Target 58,504 MW is to be added ( in 2008-2012) for
achieving objective of Power for All by 2012
7/29/2019 1power Scenario
32/46
99.00 %2200022245VII (1985-90)
72.30 %1422619666VI (1980-85)
%ACHIEVEMETOF TARGET
ACHIEVEDMW
TARGET MWPLAN
----------------58564XI (2007-12)
34.00%2118057139X (2002-07)
60.00 %2430940245IX (1997-02)
53.77 %1642230538VIII (1992-97)
7/29/2019 1power Scenario
33/46
Installed Capacity Requirement
(at 8% growth rate)
9621000
1200
)
Projected installed capacity requirements in India
206303
445
655
0
200
400
600
800
2011-12 2016-17 2021-22 2026-27 2031-32
Year
Capacity(G
7/29/2019 1power Scenario
34/46
7/29/2019 1power Scenario
35/46
Average plant load factor of Thermal power stations in
the country has improved during the ninth plan.
It increases from a level of64.66% in 1996/97 to 77%approx.
21 numbers of thermal power stations with an
aggregate installed capacity of 25237.5 MW operated
above 90% PLF.
7/29/2019 1power Scenario
36/46
MW 11th Plan (FY08 -12) 12th Plan (FY13 -17)
Central 39,865 39,365
State 27,952 12,300
Private 10,760 30,340
Total 78,577 82,000
7/29/2019 1power Scenario
37/46
A heavily coal dependent route of sectoral development is not
environmentally sustainable due to huge quantity of fly ash and
Green House Gases (GHG)emissions.
causes serious environmental problems and health hazards
Power sector should and perhaps would, continue to
support the dominant role of Coal however Environmental
.
Medium / long term measures need to be evolved and
implemented.
Coal, Power and Manufacturing groups need to work together to effectively mitigate the concerns
7/29/2019 1power Scenario
38/46
Power Sector was governed by
Indian Electricity Act, 1910
Electricity (Supply) Act, 1948
Indian Electricity Rules, 1956
Provisions of these Acts were obsolete a new Act was required in line with present
business practices.
e new ct nee s to prov e or sector mon tor ng w t n u t rewar s or
efficiency and penalties for violation.
To address these multifaceted issues, it required:
Separation (unbundling) of business activities into Generation, Transmission
and Distribution to identify the inefficient and loss making business.
Privatization of business, if the performance does not improve.
Independent electricity regulatory mechanism for monitoring
7/29/2019 1power Scenario
39/46
Post Independence, power sector entities were PSUs (NTPC, PGCIL,
DVC, etc.), SEBs and Private Utilities (CESC, TPC, REL, AEC, etc).
Tariff fixed by Central/State Power Ministry.
Minimum accountability for technical competency, efficient operations,
financial viability.
Poor O & M practices, political interference in SEB functioning.
No independent mechanism for monitoring sector performance.
Government subsidies available to SEBs only, highly subsidized tariffs to
certain consumer categories.
High T & D losses and huge commercial losses.
By 1980s, financial condition of SEBs started deteriorating.
7/29/2019 1power Scenario
40/46
Electricity reforms begun in 1991 and proceeded inthree phases and are still ongoing.
Thefirst phasefocused on increasing investment in power generation to sustain 8%
annual economic growth.
Insecond phase states began their own reforms as unbundling of SEBs into separate
entities as Generation, Transmission and Distribution to improve efficiency. This second phase of reforms included the establishment of independent State
Electricity Regulatory Commissions (SERCs). A primary motivation for creating
inde endent re ulators was rationali ation o tari s.
At the same time, an independent regulator, insulated from political pressure, would bein a better position to set tariffs to ensure that consumers were protected while
companies profit.
Athird phase of reforms emerged at the end of the 1990s, as the central government
attempted to coordinate a reform strategy for India as a whole which sought toimprove the distribution of electricity.
All states are eligible for the grants and loans, and those with the best performance in
reaching specific milestones earn extra rewards
7/29/2019 1power Scenario
41/46
Generation de-licensed. Captive Generation encouraged through waiver of open access surcharge and
connectivity to grid for evacuating surplus power.
Combined Generation/Distribution de-licensed in rural areas.
CEA clearance required for Hydro projects only. Rural Electrification to be done by Panchayats, Cooperative Societies, NGOs,
Franchisees etc.
CTU/STU to lan & develo transmission network.
Private sector participation in Transmission and Distribution. Non discriminatory Transmission Open Access introduced.
Distribution Open Access introduced in phases.
Distribution licensees can undertake generation & vice versa.
Mandatory setting up of CERC/SERC for tariff determination. State Government to pay subsidy through budget.
Trading as a distinct activity, CERC/SERC to fix trading margins.
Re-structuring of SEBs.
Metered supply of electricity mandatory.
7/29/2019 1power Scenario
42/46
Perspective planning, policy formulation, processing of projects for investment
decision,
Administration and enactment of legislation in regard to thermal, hydro power
generation, transmission and distribution.
Administration of EA, 2003, the Energy Conservation Act , 2001 and issuing
clarifications
Undertake amendments to these Acts, in conformity with the Government's policy
objectives.
Rural Electrification policy.
Hydro Power development.
Procurement of power by distribution license through competitive bidding.
National Electricity Policy and Plan.
National Tariff Policy.
Tariff bidding for transmission projects.
Mega and Ultra Mega Power Plant.
7/29/2019 1power Scenario
43/46
Regulate the tariff of GENCOs owned / controlled by Central
Government or GENCOs selling to more than one State.
Regulate and determine tariff for inter-State transmission.
Issue transmission / trading license for inter-State operations.
Adjudicate upon disputes involving GENCOs or licensee and
refer any dispute for arbitration; Levy fees/charges and specify Grid Code.
Specify and enforce standards for quality, continuity and
reliability of service by licensees.
Fix trading margin for inter-State trading.
7/29/2019 1power Scenario
44/46
Tariff determination for intra-sate generation, transmission &
distribution.
egu a e power purc ase an procuremen process.
Promote competition, efficiency and economy.
Dispute resolution and arbitration between licensees.
7/29/2019 1power Scenario
45/46
Advise the Central Government for improving the sector.
Formulate short-term and perspective plans for sector development andco-ordinate planning process.
Specify technical and safety standards for construction, operation andmaintenance of power plants and lines.
Specify conditions for installation of meters. Assist in the timely completion of projects and specify measures for skill
enhancement.
Training and manpower development.
Collect power sector data and carry out studies relating to cost, efficiency,
competitiveness Publish sector reports and investigations.
Promote research in all areas of the sector.
Advise any State Government, licensees or GENCOs to enable optimum
utilization of resources. Advise the appropriate Government/ CERC / SERCs on all technical
matters relating to the power sector.
Monitoring the implementation of power projects.
7/29/2019 1power Scenario
46/46