Upload
lim-chong-sin
View
218
Download
0
Embed Size (px)
Citation preview
8/8/2019 19099Canyon Express Slugging and Liquids Handling
1/15
Copyright 2001, Offshore Technology Conference
This paper was prepared for presentation at the 2001 Offshore Technology Conference held inHouston, Texas, 30 April3 May 2001.
This paper was selected for presentation by the OTC Program Committee following review ofinformation contained in an abstract submitted by the author(s). Contents of the paper, aspresented, have not been reviewed by the Offshore Technology Conference and are subject tocorrection by the author(s). The material, as presented, does not necessarily reflect any
position of the Offshore Technology Conference or its officers. Electronic reproduction,distribution, or storage of any part of this paper for commercial purposes without the writtenconsent of the Offshore Technology Conference is prohibited. Permission to reproduce in printis restricted to an abstract of not more than 300 words; illustrations may not be copied. Theabstract must contain conspicuous acknowledgment of where and by whom the paper waspresented.
AbstractThe Canyon Express development is a three operator
(TotalFinaElf, BP, and Marathon Oil Company) subsea
development consisting of the transport of gas-condensate
from deepwater (~7000 feet) subsea reservoirs to a host
platform via dual 47-mile 12-inch nominal OD flowlines.Thethree developments are Camden Hills (Marathon, Pioneer
Natural Resources USA, Inc., and TotalFinaElf), Aconcagua
(TotalFinaElf, Pioneer Natural Resources USA, Inc., andMariner Energy, Inc.) and Kings Peak (BP). The Canyon
Express development is unique in that it involves ultra-
deepwater reservoirs from three individual operators flowing
into a common subsea multi-phase gathering system in which
the operating pressure is lowered over time as dictated by
reservoir decline. The flowline fluid is predominantly methane
gas along with a liquid phase consisting of condensate,
produced water, and methanol (injected for hydrate
inhibition). To verify the operability of the system it was
necessary to perform transient simulations of the flowline to
predict the behavior of the fluid in the flowline.
The primary objective behind the transient simulations was
to determine the impact of the liquids in the flowline on thetopside facilities and evaluate system performance during both
upset and normal conditions. The software used to perform
these simulations was Scandpowers OLGA-2000 version
1.01. Scenarios and time points where potential problems due
to liquids were identified as well as appropriate techniques to
control the any associated liquid slugs. The results from this
work will form the basis of the operational procedures to be
developed for the Canyon Express flowline system.
IntroductionTotalFinaElf, BP, Marathon Oil Company, Pioneer N
Resources USA, Inc., and Mariner Energy Inc. int
jointly develop three deepwater fields in the Gulf of M
region. The fields are the Marathon-operated Camden HMississippi Canyon (MC) 348 block, TotalFinaElf-op
Aconcagua in MC305 block, and BP-operated Kings P
DeSoto Canyon (DC) 133 , DC177, and MC217 block
production consists primarily of methane gas with v
volumes of water and condensate. Methanol is to be inje
the wellhead for hydrate inhibition. Maximum prod
rates from each field range from 100 to 225 MMSCF
approximately 200 to 450 BPD of condensate, 300
BPD of water, and 450 to 1400 BPD of methanol.
The production from the wells will be transported v
12-inch nominal O.D. flowlines from the Camden Hil
at approximately 7200-foot water depth, to the Aco
field at approximately 7050-foot water depth, then to
Peak field at approximately 6600-foot water depth, and
to a host platform fixed structure located on the cont
shelf. The twin flowlines (East and West) form a pi
system via a loop connecting the two flowlines at the fl
ends. The flowlines are separated by a pigging valve,
will remain closed during the normal operation of the s
Thus, the flowlines will operate independently of the
Analysis of the flowline gas/liquid behavior under v
operating scenarios is required to establish and
operability. The flowline tie-ins of the individual wells
follows:
East Flowline
(2) Camden Hills (MC348-1, MC348-2)(1) Aconcagua (MC305-3)
(1) Kings Peak (DC177-2)
West Flowline(2) Aconcagua (MC305-1, MC305-2)
(3) Kings Peak (MC217-3, MC217-2, DC133-2)
The layout is shown schematically in Figure 1.
OTC 13073
Canyon Express Slugging and Liquids Handling
Bryan K. Wallace, Marathon Oil Company, Ravi Gudimetla and Geir Saether, Intec Engineering Inc.
8/8/2019 19099Canyon Express Slugging and Liquids Handling
2/15
2 B. WALLACE, R. GUDIMETLA, G. SAETHER OTC
The operation of the Canyon Express production system
will consist of a gradual reduction in topside pressure over
time (Early Life Host Platform Arrival Pressure of 2000 psig
through to Late Life Arrival Pressure of 500 psig) to maximize
recovery from the wells. As the gas rate and reservoir pressure
decline over time, liquid loading in the wells and flowlines
will increase. As the liquid loading in the flowlines increase,
various production problems due to liquid slugging may occurduring both normal production and transient situations (system
restarts, flow increases, etc.) if liquids are not properly
managed. Thus, the handling and management of temporary
increased liquid flowrate and volume is a significant aspect in
determining the operability of the Canyon Express system.
The objective of this paper is to describe the dynamic
simulations, using OLGA 2000 version 1.01, performed to:
Determine the approximate range and duration ofincreased liquid flow expected over the field life for
different production scenarios,
Summarize the range of liquid volume computed
Identify specific scenarios during the field life where
liquid management problems arise.
Studied ScenariosWith input from the various Canyon Express partners, specific
steady-state and non-steady-state scenarios were identified for
dynamic modeling to predict slug volumes (if any) that could
be present with each specific scenario. The scenarios were
simulated for early (2000 psig arrival), mid (1000 psig arrival)
and late (500 psig arrival) field life conditions to show the
effect of increased liquid loading due to decreased flowline
pressure and water production. These pressures were used to
differentiate between the times in the field life are shown in
the Design Data and Assumptions section of this paper. In
addition, all simulations were performed for the East flowline
only as this line is expected to have lower gas flowrates,
higher water rates, and lower pressure which results in a
greater potential for liquids management problems.
The scenarios where significant variations in liquid
flowrate may occur are as follows:
Steady-State Operation (Low Flow). For normal operation
where the gas flowrate is too low to maintain steady flow,
liquid and pressure builds up in the flowline until the flowline
pressure is high enough to push the liquid slug out of the
flowline and onto the platform topsides facilities. For this
scenario, the liquid rate to the topsides would fluctuate due to
the cyclical loading and unloading of flowline liquid content.
As long as the HP Separator can adequately handle the liquidfluctuations, the operation could tolerate "slight slugging" but
not require any slug tank capacity. If the periodic slugs were
in excess of topsides liquid handling capability then the slug
tank must be sized such that the predicted periodic slug
volume could be contained thus allowing for continued
operation at the design gas flowrate. Modeling this scenario
also helped to evaluate the operating envelope of the
production system. The operating envelope involves finding
the lowest flowline production rate, at which the syste
operate without the creation of slugs whose size is great
the capacity of the topside facilities.
System Shutdown and Restart. This is indicat
situations where all wells on a flowline are shutdown
extended period and subsequently restarted. Durin
shutdown, liquids are expected to settle at low spots in tdue to gravity. Upon restart of the wells, these liquids
transported out of the flowline in the form of temporary
liquid flowrates. The analysis was centered on evaluati
increased liquidvolume and to determine ifthese slugs
excess of the liquid handling capacity of the topside faci
Increase of Gas Flow. This is indicative of bringing
on-line or increasing the flowrate from a well. For a c
host platform arrival pressure, the higher the gas flo
lower the steady-state liquid holdup in the flowline. As
flow from the wells is increased the flowline liquid con
reduced from the steady-state volume of the lower flo
with the shutdown and restart case, during the period inthe higher liquid content is being displaced there
temporary increase in liquid flow to the topsides. The
rapid the gas flow increase, the higher the liquid rate
topsides facilities. Therefore, an increase in gas flowrat
be limited to a rate that results in manageable liquid volu
Increase of Liquid Flow. An increase of associated
from one or more wells (e.g. increased water flowrate
breakthrough) will result in a higher steady-state
flowrate to the topsides facilities. If the liquid flow
excess of the topsides capacity then the high liquid cu
would need choked back as the slug tank is design
intended for transient liquid flow increases and not co
high liquid flows.
Pigging and Rapid Flowline Depressurization. Al
pigging and flowline depressurization were consider
evaluated in the design and are important fact
determining adequate topside facility capacity for
management, neither topic is discussed in this paper.
Design Data and Assumptions
Flowline Fluid Composition. Canyon Express hydro
fluid is predominantly methane (~99 mol%) with a
condensate in the quantity of 2 Bbls/MMSCF at stoc
conditions. Additional liquids in the flowline include prwater and methanol injected upstream of the choke a
wellhead for hydrate inhibition.
Flowline Route Profiles and Properties. The East fl
route profile, shown in Figure 2, was obtained directl
flowline alignment sheets. The flowline and riser o
diameter is 12.75-inches. The flowline wall thickness
based on mechanical requirements and codes.
8/8/2019 19099Canyon Express Slugging and Liquids Handling
3/15
OTC 13073 CANYON EXPRESS SLUGGING AND LIQUIDS HANDLING
Reservoir Data. Each field operator in the Canyon Express
system has independently modeled their respective reservoirs.
For this work the specific reservoir data was compiled and
used as the basis for input to the transient simulations and for
evaluation of the results. Due to confidentiality issues, the
reservoir data are not stated in this paper. The parameters used
for input and evaluation include: water production per zone
over time, production rate over time, and correspondingreservoir pressure over time.
Flowline Fluid Rates. The basis for the transient simulations
cover conditions representing early life, mid life, and late life
flowline operation as outlined in Table 1. This covers an initial
host platform arrival pressure of 2000 psig, end of life arrival
pressure of 500 psig, and includes an intermediate operation
with an arrival pressure of 1000 psig. The liquid flow from the
individual wells assumed in the flowline during these periods
are consistent with the liquid predicted in the reservoir models
and steady-state flowline simulations :
The liquid flow values used in the simulations were
obtained from the steady-state simulations and thereservoir performance predictions provided from each
Canyon Express partner.
The host platform arrival pressures and predicted gasflowrates for each case were obtained from the steady-state
simulations.
Host Platform Topside Facilities. Included in the OLGA
dynamic simulation of the flowline was modeling of the HP
Separator operation and its respective outlet liquid flows.
Figure 3 shows the flow schematic diagram of the topside inlet
facilities for one of the two flowlines. The process flow path
of the production is summarized as follows:
The multi-phase flow from the Canyon Expressflowlines is routed to its respective inlet HP Separator.
The gas phase from the HP separators is compressedand dehydrated.
During normal operation, the separated liquidproduction flows from the Canyon Express two-phase
HP Separators to further liquid processing facilities.
This includes separation facilities for the water,
methanol, and condensate.
Any liquid from the flowline that flows into the HPSeparator in excess of its normal processing capacity is
routed to a 2400 barrel slug tank on the topsides.
The dynamic modeling performed with OLGA 2000
included simulation of the HP Separator operation and its
respective liquid outlet flows. This provided a prediction of
the effect and response of the host platform inlet separator and
its resultant normal flow to the downstream liquid facilities
and emergency flow to the slug tank. The topside modeling
portion of the flowline simulation, illustrated in Figure 3,
included the HP inlet separator only. To adequately represent
the normal liquid flow from the separator the normal outlet
flow was constrained to the capacity of the downstream
equipment. Any flow in excess of this constraint was routed to
an emergency dump (slug tank). The OLGA modeling
inlet separation did not permit application of a constr
the emergency dump liquid flowrate. Conformance
identified liquid flow constraints to the slug tank
confirmed and adhered to via iteration of the simulation
topside basis assumed for separator simulation is as follo
A normal liquid level was defined for the two-pha
Separator. A level of 1.25 feet above the normal lthe HP separator results in liquid flow to the eme
dump (slug tank). A 4" liquid level control valve
liquid outlet line was modeled and tuned to maint
normal liquid level setpoint. The emergency dump
when the HP separator liquid level reaches 0.05 feet
the defined normal level.
A maximum outlet liquid flow constraint from tSeparator was used to simulate the liquid ha
limitation of downstream facilities for liquid from th
flowline. Any flow above this value would result
liquid level rising in the HP separator. This fl
constraint differed for the three periods modeled
downstream facilities service both flowlines and thline liquid flow varies over time. The total liqui
constraint value used was consistent with the capa
the downstream liquid handling facilities.
The flow of liquid from the HP Separator to the sluvia the emergency dump is limited by a fixed
(installed to limit gas blowby) in the line. Constraint
flowrate on the emergency dump liquid within the
was not possible as this is not an OLGA capability
value was manually adhered to by verification fro
simulation output and modifying as necessary.
System Modeling and Analysis SummaryThe transient simulations for the Canyon Express system
performed using OLGA 2000 version 1.01. Data gen
from steady-state modeling was used as the initial inp
the transient model and the OLGA model was then ru
steady-state condition. Flowline operation was manipul
simulate both steady-state operation and the variou
steady-state scenarios described above to determi
ultimate effect of operational changes on flowline
loading and host platform topside facilities.
The following sections briefly summarize the sim
procedure and results for each of the scenarios. Critica
where significant slug volumes occur for a specific sc
are discussed in more detail within the respective section
Steady-State Operation Procedure and Summary
Simulation Procedure. The objective of these simu
was as follows :
Determine if flow instabilities due to sluggingduring the normal steady-state operation o
flowlines for various flowrates across the ra
potential operating conditions.
8/8/2019 19099Canyon Express Slugging and Liquids Handling
4/15
4 B. WALLACE, R. GUDIMETLA, G. SAETHER OTC
If slugging were present at design production rates, then
flowline diameter, gas rates, and operating pressure would
need to be modified. The simulation procedure was to run at
various flowrates for a specific arrival pressure. Each
simulation continued until a steady-state condition was
reached. A steady-state condition was defined as when the
liquid content in the flowline remained constant or when
steady cyclic fluctuations were observed in the liquid contentand exit liquid rates as shown in Figure 6. The former is
indicative of higher flowrate conditions where liquids are
swept out of the line at constant rates due to the higher gas
sweeping velocity. The latter is indicative of increased liquids
production due to an increase in water production combined
with lower gas sweeping velocities.
Summary of Steady-State Operation Results.
The initial analysis concerning transient modeling was to
determine the flowline liquid content and flowrate for various
gas flowrates and pressures in the range of flowline operation.
Liquid management problems are generally observed at lower
gas velocities and higher liquid content resulting in higher
pressures at the wellheads and fluctuations in liquid rates atthe topsides. Figures 4 and 5 illustrate the resulting liquid
loading and wellhead pressure at different flowline outlet
pressures and produced water content.
Figure 4 shows the predicted liquid content in the flowline
for various gas flowrates in the Canyon Express operating
envelope. The graph illustrates the following:
Liquid content increases as the flow rates for each casedecrease as shown in the top graph.
Higher liquid contents are observed for the higherpressure cases compared to the lower pressure cases at
similar rates as there is less velocity in the flowline.
(e.g. 100 MMSCFD at 2000 psig arrival shows a 7000
barrel liquid content versus 5000 barrels for the 100
MMSCFD at 1000 psig case).
Operation at 20 MMSCFD for all three cases shows aliquid content of approximately 20,000 barrels.
Figure 5 shows the predicted wellhead pressure (end of
the flowline) for various gas flowrates in the Canyon Express
operating envelope. In general, a change in gas flow rate
affects the pressure at the end of the flowline. For dry gas, a
decrease in gas flowrate should result in a decrease in pressure
drop across the flowline. The graph illustrates the following:
For the Canyon Express multiphase flow a decrease ingas flowrate results in an increase in liquid content.
This additional liquid effectively reduces the cross-
sectional area of the flowline and creates pockets of
liquid and hydrostatic head that the gas must overcome.
At higher gas flowrates the pressure drop across theflowline decreases as gas flow through the flowline is
reduced. This is due to the relatively insignificant
change in flowline liquid content at these flowrates.
At lower gas flowrates the pressure drop across theflowline actually increases as gas flow through the
flowline decreases. This is due to a significant increase
in flowline liquid content at the lower gas flowrates.
The transition point between higher flowrates andflowrates (as illustrated by the inflection) can b
on the early life curve at 150 MMSCFD. This is
the flowline pressure drop moves from gas
dominant to liquid content dominant.
Figures 4 and 5 illustrate that lower gas flowrates
necessarily result in lower flowline pressure drop
resultant increase in liquid content at lower gassignificantly increases the pressure at the end of the flow
As ascertained from these graphs, flow instabilit
sudden liquid increase at the platform over time), is li
occur at low flowrates which might occur anytime durin
life. Thus analysis was performed to determine the
slugging potential and system operability for a range
flowrates. A summary of this analysis per time is as fol
Early Life. Theliquid flowrate was constant at thegas flowrates. Slight liquid fluctuations were observ
low gas flowrate of 20 MMSCFD but no liquid vol
excess of HP Separator capability was predicted.
Mid Life. The liquid flowrate was constant at the
gas flowrates. Slight liquid fluctuations were also obat low gas flowrate of 20 MMSCFD but no liquid v
in excess of HP Separator capability was predicted.
Late Life. Theliquid flowrate was constant at the gas flowrates. Slight liquid fluctuations were obser
the low gas flowrates of 20 MMSCFD and 40 MM
but no liquid volume in excess of HP Separator cap
was predicted.
For the low gas flowrates, liquid fluctuation occur
the large total liquid content in the flowline begins to
flow at the flowline low spots. When the appropriate p
build up behind the liquid occurs, these liquid slugs are
further down the flowline eventually reaching the tseparator. This process is cyclic as the liquid buildup v
in the flowline fluctuates when the liquid slugs e
flowline. This operation would continue as long as su
reservoir pressure exists to move the slugs of liquid.
Liquid slugging during steady-state operation was
occur for the late life, low flowrate case from the
simulator results. Most notable, as shown in Figures 6
for the late life, low flowrate case, are fluctuations i
liquid flowrate, total flowline liquid content, and HP sep
liquid level.
Figure 6 shows liquid flowrate at the flowline outl
section prior to the separator and also the total flowline
content. The graph illustrates the following:
The fluctuations observed for liquid flowrate inthat some degree of slugging is present. If no sl
were present, the plotted line would be leve
reaching steady-state conditions.
Although the liquid flowrate varies between 0 anBPD, the flowline liquid content only between
and 15,000 bbls. The liquid content differential
bbls between the high and low values indicate t
slugging conditions are very slight.
8/8/2019 19099Canyon Express Slugging and Liquids Handling
5/15
OTC 13073 CANYON EXPRESS SLUGGING AND LIQUIDS HANDLING
The operability at the low flowrate is evident in Figure 7
which shows the liquid level in the separator for this case. The
graph illustrates the following:
Although fluctuations in liquid are present, the inletseparator can adequately handle the liquid flow to the
topsides at the normal liquid level setpoint with only
slight oscillations in the separator level
Shut-In / Start-Up Simulation Procedure and Summary.
Simulation Procedure. For early, mid, and late life cases, a
simulation of steady-state operation, followed by a total line
shut-in and subsequent full restart was performed to determine
instantaneous slug volumes during startup scenarios. The
objectives of these analyses were as follows:
Determine increased liquid volume using a ramp-uprate (time period in which gas rate goes from zero to
operating rate with a linear increase in flow rate) per
well typical to a field start-up.
Verify that the predicted slug volume is within theliquid handling capabilities of the host platform topside
facilities. The host platform topsides capability was
assumed to be adequate if the accumulated slug volume
was less than the slug tank capacity.
Determine pressure requirements at the wells at restartconsidering liquid holdup for each time point.
The simulation procedure for each case was as follows :
Run simulation with the four wells until a steady-statecondition is reached.
Shut-in all four wells for 24 hours to allow liquidcontent in the flowline to settle to the lowest points.
Start-up the wells one at a time starting with the furthest
well and working forward up the flowline. Each well isramped to full rate over a six hour period. The start-up
of a next well is three hours after the previous start-up.
Summary of Shut-Down and Startup Results
Early Life. Liquid flowrate to the host platform eventuallyincreases above normal liquid rates due to the displacement
of the liquid volume which gravity flowed to the end of the
flowline during the shut-in period. The transient higher
liquid flow did not result in a problem for the separator.
Mid Life. Similar to early life results. The increased liquidflow slightly increased the HP separator level above
normal but never reached the high-high level.
Late Life. Liquid flowrate to the host platform increases
significantly during the transient period after restart. Thisis due to the displacement of the liquid which settles in the
flowline during the shut-in period. The increased liquid
flow (for this staggered start-up scenario simulated) was in
excess of the HP separator capability and thus required the
use of the slug tank (450 barrels accumulated). This
volume is within the capacity of the slug tank.
Whether or not a slugging problem exists for the cases
described above was determined from examining several
outputs from the OLGA simulation. Most notably, the liquid
flowrate, flowline content, HP separator level fluctuatio
slug tank accumulated liquid volume were reviewed.
graphs are shown in Figures 8 thru 10 for the late life ca
Figure 8 shows the liquid volume flow at the la
section upstream of the separator and the total liquid c
in the flowline. The graph illustrates the following:
The wells flow into the flowline is shutdown at h
The wells remain closed for 24 hours to allow theholdup in the line to settle.
After the wells are restarted at hour 48, the content in the flowline rises to almost 8000 b
additional liquid from the restarted wells is intr
into the flowline. This increase occurs as the ga
are low and the liquid in the line present befo
shutdown is yet to be displaced.
After liquid flow to the host facility recommencehour 60, the instantaneous flow to the inlet separa
increases to a maximum of nearly 5500 BPD whi
above the capacity of the liquid flow from the inl
separator to the downstream liquid processing fac
Figure 9 shows the separator level and portrays the rlevel between the oil phase and water/methanol phase
liquid in the separator. The graph illustrates the followin
The relative volume of water/methanol decreasesliquid first arrives at the platform following the s
This higher flow of oil in the initial return of the
due to the separation of the oil and water phases
liquid holdup of the flowline during the shut-in p
The high volume of water/methanol in the flliquid content results in a high flow of water/me
approximately 6 hours after the re-establishm
liquid flow. The water/methanol and oil in the se
varies until steady-state operation is re-establishe
The level in the separator cannot be maintainednormal liquid level and eventually reaches the
high level which activates flow into the eme
dump (flow to the slug tank).
Figure 10 shows the accumulated volume of liqui
flowed to the slug tank over the transient period.
simulation predicted liquid flow through the emergency
it was vital to determine whether the topside slug tank
adequate size to receive the liquid slug volume predic
this case. The graph illustrates the following:
The 450 bbl accumulation predicted is well belcapacity of the 2400 bbl slug tank. In addition, a
start-up period may greatly reduce the 450 bbl va
The great majority of the liquid volume flowing islug tank is the water / methanol phase. This is the separation of the oil phase from the w
methanol phase for the liquids which were resi
the flowline during the shutdown period. The
liquids into the separator after restart are predom
oil phase and arrive at a manageable flowrate as
rate is still low. The subsequent liquid is predom
water / methanol and flowing at a higher rate due
higher gas rates as the wells reach full flow.
8/8/2019 19099Canyon Express Slugging and Liquids Handling
6/15
6 B. WALLACE, R. GUDIMETLA, G. SAETHER OTC
Flow Increase Simulation Procedure and Result Summary.
Simulation Procedure. The objective of these cases was as
follows :
Determine for early, mid and late field life, the effect onthe topside liquids handling of bringing a well on line
(no flow to full flow) with the other wells on the
flowline already flowing.The increase in gas rate also results in a subsequent
increase in liquid rate as represented by the gas / liquid ratios
listed in Table 1. This scenario required thorough study as it
will be a standard operation with a significant potential for
liquid slugging. For each case, the well to be brought on-line
was MC305-3 as this is the highest flowrate well. Higher gas
flow will cause the higher liquid content to be displaced from
the line at a higher rate than the start-up of the other wells.
Using this well is a conservative case for this scenario. The
effect of the higher gas flowrates on liquid content is
illustrated in Figure 4 which was previously described. The
simulation procedure for each point was as follows :
Run simulation with three wells on-line (MC305-3shutdown) until a steady-state condition is reached.
Start-up well MC305-3 at various ramp-up speeds(instantaneous through up to seven days) to determine
the ramp-up achievable for each case that does not
overwhelm the liquid handling at the host platform.
Summary of Results
- Early Life. The liquid rate to the host platform from theflowline is increased for a short period as the higher gas
velocity displaces the additional liquid content (600
barrels) associated with lower flow. The instantaneous
(immediate increase from no flow to full flow) ramp-up
case caused a small volume (
8/8/2019 19099Canyon Express Slugging and Liquids Handling
7/15
OTC 13073 CANYON EXPRESS SLUGGING AND LIQUIDS HANDLING
Figure 13 shows the accumulated liquid into the slug tank
over time for the instantaneous, 12, 48, and 60 hour ramp-up
periods. The graph illustrates the following:
For the instantaneous cases, predicted accumulatedvolume is greater than the slug tank capacity.
For the 12 hour case, the total predicted accumulatedvolume is just below the capacity of the slug tank.
For the 48 and 60 hour cases, the total predictedaccumulated volume is well less than the capacity of
the slug tank.
For the late life case, longer ramp-up times are required
due to the large liquid holdup present in the line. The specific
ramp-up period identified where the accumulated volume did
not exceed the slug tank volume was 120 hours. Figure 14
shows the accumulated liquid volumes in the slug tank for the
instantaneous, 48, 96, and 120 hour cases. The graph
illustrates the following:
For the instantaneous, 48, and 96 hour cases, predictedaccumulated volume is greater than slug tank capacity.
For the 120 hour case, the total predicted accumulated
volume is below the capacity of the slug tank.
Liquid Flow Increase Simulation Procedure and ResultSummary.
Simulation Procedure. The objective of these cases was as
follows :
Determine if a significantly increased liquid rate resultsin slugging which overwhelms the topside liquid
handling facilities.
These simulations were performed only for the late life flow
conditions as this is the worst case scenario for significant
impact on the topsides liquids handling. For the liquid
volume associated with the late life flow of 75 MMSCFD, thewater production (and associated methanol dosing) of one well
was increased to simulate an instantaneous increase in liquid
rate in the flowline. This would be indicative of water
breakthrough in a single well and illustrates the resultant
impact on the host platform liquid handling facilities. The
simulation procedure for this analysis was as follows.
Run simulation with all four wells operating at the latelife flowrate until a steady-state condition is reached.
Increase the water production ratio at MC348-1 tosimulate a sudden increase in liquid rate in the
flowline. The ratios for MC348-1 were increased
from 8 bbls / MMSCF to 25, 50, and 100 bbls /
MMSCF respectively. The gas flowrate for MC348-1in the late life case is 20 MMSCFD. The methanol
flowrate ratio of 1.5 times the water rate is held
constant.
Summary of Results
25 BBL/MMSCF: This water rate increase resulted in anincreased flow of 850 BPD per day (water/methanol).
Total liquid flow increased to 1290 BPD. The liquid
handling facilities as modeled are capable of handling the
excess liquids for this case with no flow to the slu
The pressure at MC348-1 increases with higher fl
liquid content.
50 BBL/MMSCF: This water rate increase resulteflow increase of 2100 BPD of liquid (water/met
Total liquid flow increased to 2540 BPD. The
liquid exceeded slug tank volume in 2.75 days fol
arrival at host platform. The pressure at Mincreases with higher flowline liquid content.
100 BBL/MMSCF: This water rate increase resultflow increase of 4600 BPD of liquid (water/met
Total liquid flow increased to 5040 BPD. The
liquid exceeded the slug tank volume in 1 day fol
arrival at host platform. The pressure at M
increases significantly with higher flowline liquid co
Figure 15 illustrates the results outlined above.
Conclusions No steady-state operation scenarios were identi
which liquid slug volumes were present in excessHP Separator liquid handling capability. For th
majority of cases investigated there was no liquid sl
predicted.
Non-steady-state scenarios were identified which reincreased liquid flow in excess of topside ca
However, there are cases where slug volumes co
operationally mitigated via procedures in which the
inlet flow rates were reduced by controlling the fl
gas rate (e.g. slower ramp-up of well).
Operation with a reduced slug tank volume (
8/8/2019 19099Canyon Express Slugging and Liquids Handling
8/15
8 B. WALLACE, R. GUDIMETLA, G. SAETHER OTC
Figure 1- Schematic Model of Canyon Express Production System
Figure 2: East Flowline Route Profile used in OLGA Simulations
CANYON EXPRESS DEVELOPMENTEAST FLOWLINE ROUTE PROFILE
TRANSIENT STUDY BASIS
HOST PLATFORM
177-2
305-3
348-2
348-1
-8000
-7000
-6000
-5000
-4000
-3000
-2000
-1000
0
1000
0 20 40 60 80 100 120 140 160 180 200 220 240 260
Distance (1000 ft)
Elevation(ft)
WEST
EAST
CANYON EXPRESS DEVELOPMENT
FLOWLINE SCHEMATIC
TRANSIENT STUDY BASIS
KINGS
PEAK
BP
CAMDEN
HILLS
MARATHON
HOST
PLATFORM
ACONCAGUA
TOTALFINAELF
MC
348-1
MC
348-2
MC
305-3
4 miles
MC
305-1
MC
305-2
MC
217-3
DC
133-2
MC
217-2
DC
177-2
11 miles 32 miles
DUAL 12"PIPELINES
GAS EXPORT
8/8/2019 19099Canyon Express Slugging and Liquids Handling
9/15
OTC 13073 CANYON EXPRESS SLUGGING AND LIQUIDS HANDLING
Table 1: Basis for Transient Simulations
Figure 3- HP Separator Model Used in OLGA 2000
Case Early Mid Late
Water Rate (bbls /mmscf) 0.7 2.5 8.0
Methanol Rate (bbls/bbl
water)1.5 1.5 1.5
Condensate Rate (bbls/mmscf) 2.0 2.0 2.0
Host Arrival Pressure (psig) 2000 1000 500
Host Separator Pressure (psig) 1750 750 486
East Line Wells Flow (mmscfd)
MC348-1 50 31 20
MC348-2 50 50 10
MC305-3 60 55 35
DC177-2 50 14 10
Total 210 150 75
MULTIPHASE INLET HP SEPARATOR
LC60"
HLL 3 ft - 9 in
SLUG TANK
EMERGENCY
DUMP
NORMAL
FLOW
FC
CONSTRAINT
2600 to 2800 BPD
CANYON EXPRESS DEVELOPMENT
TRANSIENT STUDY HP SEPARATOR BASIS
TO
INLET
CHOKE
LC
NLL 2 ft - 6 in
CANYON
EXPRESS
FLOW
HLL 3 ft - 9 in
NLL 2 ft - 6 in
8/8/2019 19099Canyon Express Slugging and Liquids Handling
10/15
10 B. WALLACE, R. GUDIMETLA, G. SAETHER OTC
Figure 4 - Flowline Liquid Content at Various Gas Flowrates
Figure 5 - Pressure at End of Flowline at Various Gas Flowrates
Liquid Content East Flowline
Early = 2000 psia, 0.7 H2O, Mid = 1000 psia, 2.5 H2O, Late = 500 psia, 8 H2O
0
5000
10000
15000
20000
25000
0 50 100 150 200 250
Gas Flowrate (mmscf/d)
Liquidcontent(bbls)
Early life
Mid life
Late life
Subsea Inlet Pressure East Flowline
Early = 2000 psia, 0.7 H2O, Mid = 1000 psia, 2.5 H2O, Late = 500 psia, 8 H2O
0
500
1000
1500
2000
2500
3000
3500
4000
4500
0 50 100 150 200 250
Gas Flowr ate (m ms cf/d)
PressureatCamdenHills(psia)
Early life
Mid life
Late life
8/8/2019 19099Canyon Express Slugging and Liquids Handling
11/15
OTC 13073 CANYON EXPRESS SLUGGING AND LIQUIDS HANDLING
Figure 6 - Late LifeSteady-State Operation at 40 MMSCFDLiquid Flowrate at Separator and Flowline Liquid Content
Figure 7 - Late LifeSteady-State Operation at 40 MMSCFDHost Platform HP Separator Liquid Level
LIQUID FLOWRATE
LIQUID CONTENT
0
500
1000
1500
2000
2500
3000
3500
4000
0 12 24 36 48 60 72 84 96 108 120 132 144
Time (Hrs)
LiquidFlowrateatSeparator(BPD
)
13250
13500
13750
14000
14250
14500
14750
15000
15250
FlowlineLiquidContent(Bbls)
Actual Liquid Level
High-High Liquid
Level
2.00
2.25
2.50
2.75
3.00
3.25
3.50
3.75
4.00
0 12 24 36 48 60 72 84 96 108 120 132 144
Time (Hrs)
SeparatorLiquidLevel(ft)
8/8/2019 19099Canyon Express Slugging and Liquids Handling
12/15
12 B. WALLACE, R. GUDIMETLA, G. SAETHER OTC
Figure 8: Late LifeFull Flow / Shutdown / Re-Start (75-0-75 MMSCFD):Liquid Flowrate at Separator and Total Liquid Content
Figure 9: Late LifeFull Flow / Shutdown / Re-Start (75-0-75 MMSCFD):Host Platform HP Separator Liquid Level
LIQUID FLOWRATE
SHUTDOWN
RESTART
LIQUID CONTENT
0
500
1000
1500
2000
2500
3000
3500
4000
4500
5000
5500
6000
0 12 24 36 48 60 72 84 96 108 120
Time (Hrs)
LiquidFlowrateatSeparator(BP
D)
5500
5750
6000
6250
6500
6750
7000
7250
7500
7750
8000
8250
8500
FlowlineLiquidContent(Bbls)
Actual Liquid Level
High-High Liquid
Level
SHUTDOWN
RESTART
2.00
2.25
2.50
2.75
3.00
3.25
3.50
3.75
4.00
0 12 24 36 48 60 72 84 96 108 120
Time (Hrs)
SeparatorLiquidLevel(Ft)
8/8/2019 19099Canyon Express Slugging and Liquids Handling
13/15
OTC 13073 CANYON EXPRESS SLUGGING AND LIQUIDS HANDLING
Figure 10 - Late LifeFull Flow / Shutdown / Re-Start (75-0-75 MMSCFD)Liquid Accumulation at Slug Tank
Figure 11 - Mid LifeGas Flow Increase (95 MMSCFD to 150 MMSCFD)Flow Rate at HP Separator for Various Ramp-up Times
WATER / METHANOL
OIL
SLUG TANK CAPACITY
RESTART
SHUTDOWN
0
400
800
1200
1600
2000
2400
2800
0 12 24 36 48 60 72 84 96 108 120
Time (Hrs)
AccumulatedVolumeperPhase(Bb
ls)
RESTARTWELL
0
2000
4000
6000
8000
10000
12000
14000
0 12 24 36 48 60 72 84 96 108 120 132 144 156 168
Time (Hrs)
LiquidFlowrateatSeparator(BPD)
INSTANTANEOUS RAMP-UP
12 HOUR RAMP-UP
48 HOUR RAMP-UP
60 HOUR RAMP-UP
8/8/2019 19099Canyon Express Slugging and Liquids Handling
14/15
14 B. WALLACE, R. GUDIMETLA, G. SAETHER OTC
Figure 12 - Mid LifeGas Flow Increase (95 MMSCFD to 150 MMSCFD)Host Platform HP Separator Liquid Level
Figure 13 - Mid LifeGas Flow Increase (95 MMSCFD to 150 MMSCFD)Liquid Accumulation at Slug Tank at Various Ramp-up Times
INSTANTANEOUS
RAMP-UP
Normal Liquid Level
48 HOUR RAMP-UP
60 HOUR RAMP-UP
RESTARTWELL
High-High Liquid Level
2.00
2.25
2.50
2.75
3.00
3.25
3.50
3.75
4.00
0 12 24 36 48 60 72 84 96 108 120 132 144 156 168
Time (Hrs)
SeparatorLiquidLevel(Ft)
60 HR RAMPUP
48 HR RAMPUP
12 HOUR RAMPUP
0 HOUR RAMPUPSLUG TANKCAPACITY
RESTARTWELL
0
600
1200
1800
2400
3000
0 12 24 36 48 60 72 84 96 108 120 132 144 156 168
Time (Hrs)
AccumulatedLiquidVolume(Bbls)
8/8/2019 19099Canyon Express Slugging and Liquids Handling
15/15
OTC 13073 CANYON EXPRESS SLUGGING AND LIQUIDS HANDLING
Figure 14 - Late LifeGas Flow Increase (95 MMSCFD to 150 MMSCFD)Liquid Accumulation at Slug Tank for Various Ramp-up Times
Figure 15 - Late LifeLiquid Flow IncreaseLiquid Accumulation at Slug Tank for Various Liquid Ratios
120 HR RAMPUP
96 HR RAMPUP
48 HR RAMPUP
0 HR RAMPUP
SLUG TANK
CAPACITY
RESTARTWELL
0
800
1600
2400
3200
4000
4800
5600
6400
7200
0 12 24 36 48 60 72 84 96 108 120 132 144 156 168
Time (Hrs)
AccumulatedLiquidVolume(Bbls)
50 BBL / MMSCF
100 BBL / MMSCF
INCREASELIQUID
SLUG TANK CAPACITY
25 BBL / MMSCF
0
800
1600
2400
3200
4000
4800
5600
6400
7200
0 12 24 36 48 60 72 84 96 108 120
Time (Hrs)
AccumulatedLiquidVolume(Bbls)
WATER RATIO LIQUID
RATE
25 BBL / MMSCF 2,500 BPD
50 BBL / MMSCF 4,000 BPD
100 BBL / MMSCF 6,500 BPD