19099Canyon Express Slugging and Liquids Handling

Embed Size (px)

Citation preview

  • 8/8/2019 19099Canyon Express Slugging and Liquids Handling

    1/15

    Copyright 2001, Offshore Technology Conference

    This paper was prepared for presentation at the 2001 Offshore Technology Conference held inHouston, Texas, 30 April3 May 2001.

    This paper was selected for presentation by the OTC Program Committee following review ofinformation contained in an abstract submitted by the author(s). Contents of the paper, aspresented, have not been reviewed by the Offshore Technology Conference and are subject tocorrection by the author(s). The material, as presented, does not necessarily reflect any

    position of the Offshore Technology Conference or its officers. Electronic reproduction,distribution, or storage of any part of this paper for commercial purposes without the writtenconsent of the Offshore Technology Conference is prohibited. Permission to reproduce in printis restricted to an abstract of not more than 300 words; illustrations may not be copied. Theabstract must contain conspicuous acknowledgment of where and by whom the paper waspresented.

    AbstractThe Canyon Express development is a three operator

    (TotalFinaElf, BP, and Marathon Oil Company) subsea

    development consisting of the transport of gas-condensate

    from deepwater (~7000 feet) subsea reservoirs to a host

    platform via dual 47-mile 12-inch nominal OD flowlines.Thethree developments are Camden Hills (Marathon, Pioneer

    Natural Resources USA, Inc., and TotalFinaElf), Aconcagua

    (TotalFinaElf, Pioneer Natural Resources USA, Inc., andMariner Energy, Inc.) and Kings Peak (BP). The Canyon

    Express development is unique in that it involves ultra-

    deepwater reservoirs from three individual operators flowing

    into a common subsea multi-phase gathering system in which

    the operating pressure is lowered over time as dictated by

    reservoir decline. The flowline fluid is predominantly methane

    gas along with a liquid phase consisting of condensate,

    produced water, and methanol (injected for hydrate

    inhibition). To verify the operability of the system it was

    necessary to perform transient simulations of the flowline to

    predict the behavior of the fluid in the flowline.

    The primary objective behind the transient simulations was

    to determine the impact of the liquids in the flowline on thetopside facilities and evaluate system performance during both

    upset and normal conditions. The software used to perform

    these simulations was Scandpowers OLGA-2000 version

    1.01. Scenarios and time points where potential problems due

    to liquids were identified as well as appropriate techniques to

    control the any associated liquid slugs. The results from this

    work will form the basis of the operational procedures to be

    developed for the Canyon Express flowline system.

    IntroductionTotalFinaElf, BP, Marathon Oil Company, Pioneer N

    Resources USA, Inc., and Mariner Energy Inc. int

    jointly develop three deepwater fields in the Gulf of M

    region. The fields are the Marathon-operated Camden HMississippi Canyon (MC) 348 block, TotalFinaElf-op

    Aconcagua in MC305 block, and BP-operated Kings P

    DeSoto Canyon (DC) 133 , DC177, and MC217 block

    production consists primarily of methane gas with v

    volumes of water and condensate. Methanol is to be inje

    the wellhead for hydrate inhibition. Maximum prod

    rates from each field range from 100 to 225 MMSCF

    approximately 200 to 450 BPD of condensate, 300

    BPD of water, and 450 to 1400 BPD of methanol.

    The production from the wells will be transported v

    12-inch nominal O.D. flowlines from the Camden Hil

    at approximately 7200-foot water depth, to the Aco

    field at approximately 7050-foot water depth, then to

    Peak field at approximately 6600-foot water depth, and

    to a host platform fixed structure located on the cont

    shelf. The twin flowlines (East and West) form a pi

    system via a loop connecting the two flowlines at the fl

    ends. The flowlines are separated by a pigging valve,

    will remain closed during the normal operation of the s

    Thus, the flowlines will operate independently of the

    Analysis of the flowline gas/liquid behavior under v

    operating scenarios is required to establish and

    operability. The flowline tie-ins of the individual wells

    follows:

    East Flowline

    (2) Camden Hills (MC348-1, MC348-2)(1) Aconcagua (MC305-3)

    (1) Kings Peak (DC177-2)

    West Flowline(2) Aconcagua (MC305-1, MC305-2)

    (3) Kings Peak (MC217-3, MC217-2, DC133-2)

    The layout is shown schematically in Figure 1.

    OTC 13073

    Canyon Express Slugging and Liquids Handling

    Bryan K. Wallace, Marathon Oil Company, Ravi Gudimetla and Geir Saether, Intec Engineering Inc.

  • 8/8/2019 19099Canyon Express Slugging and Liquids Handling

    2/15

    2 B. WALLACE, R. GUDIMETLA, G. SAETHER OTC

    The operation of the Canyon Express production system

    will consist of a gradual reduction in topside pressure over

    time (Early Life Host Platform Arrival Pressure of 2000 psig

    through to Late Life Arrival Pressure of 500 psig) to maximize

    recovery from the wells. As the gas rate and reservoir pressure

    decline over time, liquid loading in the wells and flowlines

    will increase. As the liquid loading in the flowlines increase,

    various production problems due to liquid slugging may occurduring both normal production and transient situations (system

    restarts, flow increases, etc.) if liquids are not properly

    managed. Thus, the handling and management of temporary

    increased liquid flowrate and volume is a significant aspect in

    determining the operability of the Canyon Express system.

    The objective of this paper is to describe the dynamic

    simulations, using OLGA 2000 version 1.01, performed to:

    Determine the approximate range and duration ofincreased liquid flow expected over the field life for

    different production scenarios,

    Summarize the range of liquid volume computed

    Identify specific scenarios during the field life where

    liquid management problems arise.

    Studied ScenariosWith input from the various Canyon Express partners, specific

    steady-state and non-steady-state scenarios were identified for

    dynamic modeling to predict slug volumes (if any) that could

    be present with each specific scenario. The scenarios were

    simulated for early (2000 psig arrival), mid (1000 psig arrival)

    and late (500 psig arrival) field life conditions to show the

    effect of increased liquid loading due to decreased flowline

    pressure and water production. These pressures were used to

    differentiate between the times in the field life are shown in

    the Design Data and Assumptions section of this paper. In

    addition, all simulations were performed for the East flowline

    only as this line is expected to have lower gas flowrates,

    higher water rates, and lower pressure which results in a

    greater potential for liquids management problems.

    The scenarios where significant variations in liquid

    flowrate may occur are as follows:

    Steady-State Operation (Low Flow). For normal operation

    where the gas flowrate is too low to maintain steady flow,

    liquid and pressure builds up in the flowline until the flowline

    pressure is high enough to push the liquid slug out of the

    flowline and onto the platform topsides facilities. For this

    scenario, the liquid rate to the topsides would fluctuate due to

    the cyclical loading and unloading of flowline liquid content.

    As long as the HP Separator can adequately handle the liquidfluctuations, the operation could tolerate "slight slugging" but

    not require any slug tank capacity. If the periodic slugs were

    in excess of topsides liquid handling capability then the slug

    tank must be sized such that the predicted periodic slug

    volume could be contained thus allowing for continued

    operation at the design gas flowrate. Modeling this scenario

    also helped to evaluate the operating envelope of the

    production system. The operating envelope involves finding

    the lowest flowline production rate, at which the syste

    operate without the creation of slugs whose size is great

    the capacity of the topside facilities.

    System Shutdown and Restart. This is indicat

    situations where all wells on a flowline are shutdown

    extended period and subsequently restarted. Durin

    shutdown, liquids are expected to settle at low spots in tdue to gravity. Upon restart of the wells, these liquids

    transported out of the flowline in the form of temporary

    liquid flowrates. The analysis was centered on evaluati

    increased liquidvolume and to determine ifthese slugs

    excess of the liquid handling capacity of the topside faci

    Increase of Gas Flow. This is indicative of bringing

    on-line or increasing the flowrate from a well. For a c

    host platform arrival pressure, the higher the gas flo

    lower the steady-state liquid holdup in the flowline. As

    flow from the wells is increased the flowline liquid con

    reduced from the steady-state volume of the lower flo

    with the shutdown and restart case, during the period inthe higher liquid content is being displaced there

    temporary increase in liquid flow to the topsides. The

    rapid the gas flow increase, the higher the liquid rate

    topsides facilities. Therefore, an increase in gas flowrat

    be limited to a rate that results in manageable liquid volu

    Increase of Liquid Flow. An increase of associated

    from one or more wells (e.g. increased water flowrate

    breakthrough) will result in a higher steady-state

    flowrate to the topsides facilities. If the liquid flow

    excess of the topsides capacity then the high liquid cu

    would need choked back as the slug tank is design

    intended for transient liquid flow increases and not co

    high liquid flows.

    Pigging and Rapid Flowline Depressurization. Al

    pigging and flowline depressurization were consider

    evaluated in the design and are important fact

    determining adequate topside facility capacity for

    management, neither topic is discussed in this paper.

    Design Data and Assumptions

    Flowline Fluid Composition. Canyon Express hydro

    fluid is predominantly methane (~99 mol%) with a

    condensate in the quantity of 2 Bbls/MMSCF at stoc

    conditions. Additional liquids in the flowline include prwater and methanol injected upstream of the choke a

    wellhead for hydrate inhibition.

    Flowline Route Profiles and Properties. The East fl

    route profile, shown in Figure 2, was obtained directl

    flowline alignment sheets. The flowline and riser o

    diameter is 12.75-inches. The flowline wall thickness

    based on mechanical requirements and codes.

  • 8/8/2019 19099Canyon Express Slugging and Liquids Handling

    3/15

    OTC 13073 CANYON EXPRESS SLUGGING AND LIQUIDS HANDLING

    Reservoir Data. Each field operator in the Canyon Express

    system has independently modeled their respective reservoirs.

    For this work the specific reservoir data was compiled and

    used as the basis for input to the transient simulations and for

    evaluation of the results. Due to confidentiality issues, the

    reservoir data are not stated in this paper. The parameters used

    for input and evaluation include: water production per zone

    over time, production rate over time, and correspondingreservoir pressure over time.

    Flowline Fluid Rates. The basis for the transient simulations

    cover conditions representing early life, mid life, and late life

    flowline operation as outlined in Table 1. This covers an initial

    host platform arrival pressure of 2000 psig, end of life arrival

    pressure of 500 psig, and includes an intermediate operation

    with an arrival pressure of 1000 psig. The liquid flow from the

    individual wells assumed in the flowline during these periods

    are consistent with the liquid predicted in the reservoir models

    and steady-state flowline simulations :

    The liquid flow values used in the simulations were

    obtained from the steady-state simulations and thereservoir performance predictions provided from each

    Canyon Express partner.

    The host platform arrival pressures and predicted gasflowrates for each case were obtained from the steady-state

    simulations.

    Host Platform Topside Facilities. Included in the OLGA

    dynamic simulation of the flowline was modeling of the HP

    Separator operation and its respective outlet liquid flows.

    Figure 3 shows the flow schematic diagram of the topside inlet

    facilities for one of the two flowlines. The process flow path

    of the production is summarized as follows:

    The multi-phase flow from the Canyon Expressflowlines is routed to its respective inlet HP Separator.

    The gas phase from the HP separators is compressedand dehydrated.

    During normal operation, the separated liquidproduction flows from the Canyon Express two-phase

    HP Separators to further liquid processing facilities.

    This includes separation facilities for the water,

    methanol, and condensate.

    Any liquid from the flowline that flows into the HPSeparator in excess of its normal processing capacity is

    routed to a 2400 barrel slug tank on the topsides.

    The dynamic modeling performed with OLGA 2000

    included simulation of the HP Separator operation and its

    respective liquid outlet flows. This provided a prediction of

    the effect and response of the host platform inlet separator and

    its resultant normal flow to the downstream liquid facilities

    and emergency flow to the slug tank. The topside modeling

    portion of the flowline simulation, illustrated in Figure 3,

    included the HP inlet separator only. To adequately represent

    the normal liquid flow from the separator the normal outlet

    flow was constrained to the capacity of the downstream

    equipment. Any flow in excess of this constraint was routed to

    an emergency dump (slug tank). The OLGA modeling

    inlet separation did not permit application of a constr

    the emergency dump liquid flowrate. Conformance

    identified liquid flow constraints to the slug tank

    confirmed and adhered to via iteration of the simulation

    topside basis assumed for separator simulation is as follo

    A normal liquid level was defined for the two-pha

    Separator. A level of 1.25 feet above the normal lthe HP separator results in liquid flow to the eme

    dump (slug tank). A 4" liquid level control valve

    liquid outlet line was modeled and tuned to maint

    normal liquid level setpoint. The emergency dump

    when the HP separator liquid level reaches 0.05 feet

    the defined normal level.

    A maximum outlet liquid flow constraint from tSeparator was used to simulate the liquid ha

    limitation of downstream facilities for liquid from th

    flowline. Any flow above this value would result

    liquid level rising in the HP separator. This fl

    constraint differed for the three periods modeled

    downstream facilities service both flowlines and thline liquid flow varies over time. The total liqui

    constraint value used was consistent with the capa

    the downstream liquid handling facilities.

    The flow of liquid from the HP Separator to the sluvia the emergency dump is limited by a fixed

    (installed to limit gas blowby) in the line. Constraint

    flowrate on the emergency dump liquid within the

    was not possible as this is not an OLGA capability

    value was manually adhered to by verification fro

    simulation output and modifying as necessary.

    System Modeling and Analysis SummaryThe transient simulations for the Canyon Express system

    performed using OLGA 2000 version 1.01. Data gen

    from steady-state modeling was used as the initial inp

    the transient model and the OLGA model was then ru

    steady-state condition. Flowline operation was manipul

    simulate both steady-state operation and the variou

    steady-state scenarios described above to determi

    ultimate effect of operational changes on flowline

    loading and host platform topside facilities.

    The following sections briefly summarize the sim

    procedure and results for each of the scenarios. Critica

    where significant slug volumes occur for a specific sc

    are discussed in more detail within the respective section

    Steady-State Operation Procedure and Summary

    Simulation Procedure. The objective of these simu

    was as follows :

    Determine if flow instabilities due to sluggingduring the normal steady-state operation o

    flowlines for various flowrates across the ra

    potential operating conditions.

  • 8/8/2019 19099Canyon Express Slugging and Liquids Handling

    4/15

    4 B. WALLACE, R. GUDIMETLA, G. SAETHER OTC

    If slugging were present at design production rates, then

    flowline diameter, gas rates, and operating pressure would

    need to be modified. The simulation procedure was to run at

    various flowrates for a specific arrival pressure. Each

    simulation continued until a steady-state condition was

    reached. A steady-state condition was defined as when the

    liquid content in the flowline remained constant or when

    steady cyclic fluctuations were observed in the liquid contentand exit liquid rates as shown in Figure 6. The former is

    indicative of higher flowrate conditions where liquids are

    swept out of the line at constant rates due to the higher gas

    sweeping velocity. The latter is indicative of increased liquids

    production due to an increase in water production combined

    with lower gas sweeping velocities.

    Summary of Steady-State Operation Results.

    The initial analysis concerning transient modeling was to

    determine the flowline liquid content and flowrate for various

    gas flowrates and pressures in the range of flowline operation.

    Liquid management problems are generally observed at lower

    gas velocities and higher liquid content resulting in higher

    pressures at the wellheads and fluctuations in liquid rates atthe topsides. Figures 4 and 5 illustrate the resulting liquid

    loading and wellhead pressure at different flowline outlet

    pressures and produced water content.

    Figure 4 shows the predicted liquid content in the flowline

    for various gas flowrates in the Canyon Express operating

    envelope. The graph illustrates the following:

    Liquid content increases as the flow rates for each casedecrease as shown in the top graph.

    Higher liquid contents are observed for the higherpressure cases compared to the lower pressure cases at

    similar rates as there is less velocity in the flowline.

    (e.g. 100 MMSCFD at 2000 psig arrival shows a 7000

    barrel liquid content versus 5000 barrels for the 100

    MMSCFD at 1000 psig case).

    Operation at 20 MMSCFD for all three cases shows aliquid content of approximately 20,000 barrels.

    Figure 5 shows the predicted wellhead pressure (end of

    the flowline) for various gas flowrates in the Canyon Express

    operating envelope. In general, a change in gas flow rate

    affects the pressure at the end of the flowline. For dry gas, a

    decrease in gas flowrate should result in a decrease in pressure

    drop across the flowline. The graph illustrates the following:

    For the Canyon Express multiphase flow a decrease ingas flowrate results in an increase in liquid content.

    This additional liquid effectively reduces the cross-

    sectional area of the flowline and creates pockets of

    liquid and hydrostatic head that the gas must overcome.

    At higher gas flowrates the pressure drop across theflowline decreases as gas flow through the flowline is

    reduced. This is due to the relatively insignificant

    change in flowline liquid content at these flowrates.

    At lower gas flowrates the pressure drop across theflowline actually increases as gas flow through the

    flowline decreases. This is due to a significant increase

    in flowline liquid content at the lower gas flowrates.

    The transition point between higher flowrates andflowrates (as illustrated by the inflection) can b

    on the early life curve at 150 MMSCFD. This is

    the flowline pressure drop moves from gas

    dominant to liquid content dominant.

    Figures 4 and 5 illustrate that lower gas flowrates

    necessarily result in lower flowline pressure drop

    resultant increase in liquid content at lower gassignificantly increases the pressure at the end of the flow

    As ascertained from these graphs, flow instabilit

    sudden liquid increase at the platform over time), is li

    occur at low flowrates which might occur anytime durin

    life. Thus analysis was performed to determine the

    slugging potential and system operability for a range

    flowrates. A summary of this analysis per time is as fol

    Early Life. Theliquid flowrate was constant at thegas flowrates. Slight liquid fluctuations were observ

    low gas flowrate of 20 MMSCFD but no liquid vol

    excess of HP Separator capability was predicted.

    Mid Life. The liquid flowrate was constant at the

    gas flowrates. Slight liquid fluctuations were also obat low gas flowrate of 20 MMSCFD but no liquid v

    in excess of HP Separator capability was predicted.

    Late Life. Theliquid flowrate was constant at the gas flowrates. Slight liquid fluctuations were obser

    the low gas flowrates of 20 MMSCFD and 40 MM

    but no liquid volume in excess of HP Separator cap

    was predicted.

    For the low gas flowrates, liquid fluctuation occur

    the large total liquid content in the flowline begins to

    flow at the flowline low spots. When the appropriate p

    build up behind the liquid occurs, these liquid slugs are

    further down the flowline eventually reaching the tseparator. This process is cyclic as the liquid buildup v

    in the flowline fluctuates when the liquid slugs e

    flowline. This operation would continue as long as su

    reservoir pressure exists to move the slugs of liquid.

    Liquid slugging during steady-state operation was

    occur for the late life, low flowrate case from the

    simulator results. Most notable, as shown in Figures 6

    for the late life, low flowrate case, are fluctuations i

    liquid flowrate, total flowline liquid content, and HP sep

    liquid level.

    Figure 6 shows liquid flowrate at the flowline outl

    section prior to the separator and also the total flowline

    content. The graph illustrates the following:

    The fluctuations observed for liquid flowrate inthat some degree of slugging is present. If no sl

    were present, the plotted line would be leve

    reaching steady-state conditions.

    Although the liquid flowrate varies between 0 anBPD, the flowline liquid content only between

    and 15,000 bbls. The liquid content differential

    bbls between the high and low values indicate t

    slugging conditions are very slight.

  • 8/8/2019 19099Canyon Express Slugging and Liquids Handling

    5/15

    OTC 13073 CANYON EXPRESS SLUGGING AND LIQUIDS HANDLING

    The operability at the low flowrate is evident in Figure 7

    which shows the liquid level in the separator for this case. The

    graph illustrates the following:

    Although fluctuations in liquid are present, the inletseparator can adequately handle the liquid flow to the

    topsides at the normal liquid level setpoint with only

    slight oscillations in the separator level

    Shut-In / Start-Up Simulation Procedure and Summary.

    Simulation Procedure. For early, mid, and late life cases, a

    simulation of steady-state operation, followed by a total line

    shut-in and subsequent full restart was performed to determine

    instantaneous slug volumes during startup scenarios. The

    objectives of these analyses were as follows:

    Determine increased liquid volume using a ramp-uprate (time period in which gas rate goes from zero to

    operating rate with a linear increase in flow rate) per

    well typical to a field start-up.

    Verify that the predicted slug volume is within theliquid handling capabilities of the host platform topside

    facilities. The host platform topsides capability was

    assumed to be adequate if the accumulated slug volume

    was less than the slug tank capacity.

    Determine pressure requirements at the wells at restartconsidering liquid holdup for each time point.

    The simulation procedure for each case was as follows :

    Run simulation with the four wells until a steady-statecondition is reached.

    Shut-in all four wells for 24 hours to allow liquidcontent in the flowline to settle to the lowest points.

    Start-up the wells one at a time starting with the furthest

    well and working forward up the flowline. Each well isramped to full rate over a six hour period. The start-up

    of a next well is three hours after the previous start-up.

    Summary of Shut-Down and Startup Results

    Early Life. Liquid flowrate to the host platform eventuallyincreases above normal liquid rates due to the displacement

    of the liquid volume which gravity flowed to the end of the

    flowline during the shut-in period. The transient higher

    liquid flow did not result in a problem for the separator.

    Mid Life. Similar to early life results. The increased liquidflow slightly increased the HP separator level above

    normal but never reached the high-high level.

    Late Life. Liquid flowrate to the host platform increases

    significantly during the transient period after restart. Thisis due to the displacement of the liquid which settles in the

    flowline during the shut-in period. The increased liquid

    flow (for this staggered start-up scenario simulated) was in

    excess of the HP separator capability and thus required the

    use of the slug tank (450 barrels accumulated). This

    volume is within the capacity of the slug tank.

    Whether or not a slugging problem exists for the cases

    described above was determined from examining several

    outputs from the OLGA simulation. Most notably, the liquid

    flowrate, flowline content, HP separator level fluctuatio

    slug tank accumulated liquid volume were reviewed.

    graphs are shown in Figures 8 thru 10 for the late life ca

    Figure 8 shows the liquid volume flow at the la

    section upstream of the separator and the total liquid c

    in the flowline. The graph illustrates the following:

    The wells flow into the flowline is shutdown at h

    The wells remain closed for 24 hours to allow theholdup in the line to settle.

    After the wells are restarted at hour 48, the content in the flowline rises to almost 8000 b

    additional liquid from the restarted wells is intr

    into the flowline. This increase occurs as the ga

    are low and the liquid in the line present befo

    shutdown is yet to be displaced.

    After liquid flow to the host facility recommencehour 60, the instantaneous flow to the inlet separa

    increases to a maximum of nearly 5500 BPD whi

    above the capacity of the liquid flow from the inl

    separator to the downstream liquid processing fac

    Figure 9 shows the separator level and portrays the rlevel between the oil phase and water/methanol phase

    liquid in the separator. The graph illustrates the followin

    The relative volume of water/methanol decreasesliquid first arrives at the platform following the s

    This higher flow of oil in the initial return of the

    due to the separation of the oil and water phases

    liquid holdup of the flowline during the shut-in p

    The high volume of water/methanol in the flliquid content results in a high flow of water/me

    approximately 6 hours after the re-establishm

    liquid flow. The water/methanol and oil in the se

    varies until steady-state operation is re-establishe

    The level in the separator cannot be maintainednormal liquid level and eventually reaches the

    high level which activates flow into the eme

    dump (flow to the slug tank).

    Figure 10 shows the accumulated volume of liqui

    flowed to the slug tank over the transient period.

    simulation predicted liquid flow through the emergency

    it was vital to determine whether the topside slug tank

    adequate size to receive the liquid slug volume predic

    this case. The graph illustrates the following:

    The 450 bbl accumulation predicted is well belcapacity of the 2400 bbl slug tank. In addition, a

    start-up period may greatly reduce the 450 bbl va

    The great majority of the liquid volume flowing islug tank is the water / methanol phase. This is the separation of the oil phase from the w

    methanol phase for the liquids which were resi

    the flowline during the shutdown period. The

    liquids into the separator after restart are predom

    oil phase and arrive at a manageable flowrate as

    rate is still low. The subsequent liquid is predom

    water / methanol and flowing at a higher rate due

    higher gas rates as the wells reach full flow.

  • 8/8/2019 19099Canyon Express Slugging and Liquids Handling

    6/15

    6 B. WALLACE, R. GUDIMETLA, G. SAETHER OTC

    Flow Increase Simulation Procedure and Result Summary.

    Simulation Procedure. The objective of these cases was as

    follows :

    Determine for early, mid and late field life, the effect onthe topside liquids handling of bringing a well on line

    (no flow to full flow) with the other wells on the

    flowline already flowing.The increase in gas rate also results in a subsequent

    increase in liquid rate as represented by the gas / liquid ratios

    listed in Table 1. This scenario required thorough study as it

    will be a standard operation with a significant potential for

    liquid slugging. For each case, the well to be brought on-line

    was MC305-3 as this is the highest flowrate well. Higher gas

    flow will cause the higher liquid content to be displaced from

    the line at a higher rate than the start-up of the other wells.

    Using this well is a conservative case for this scenario. The

    effect of the higher gas flowrates on liquid content is

    illustrated in Figure 4 which was previously described. The

    simulation procedure for each point was as follows :

    Run simulation with three wells on-line (MC305-3shutdown) until a steady-state condition is reached.

    Start-up well MC305-3 at various ramp-up speeds(instantaneous through up to seven days) to determine

    the ramp-up achievable for each case that does not

    overwhelm the liquid handling at the host platform.

    Summary of Results

    - Early Life. The liquid rate to the host platform from theflowline is increased for a short period as the higher gas

    velocity displaces the additional liquid content (600

    barrels) associated with lower flow. The instantaneous

    (immediate increase from no flow to full flow) ramp-up

    case caused a small volume (

  • 8/8/2019 19099Canyon Express Slugging and Liquids Handling

    7/15

    OTC 13073 CANYON EXPRESS SLUGGING AND LIQUIDS HANDLING

    Figure 13 shows the accumulated liquid into the slug tank

    over time for the instantaneous, 12, 48, and 60 hour ramp-up

    periods. The graph illustrates the following:

    For the instantaneous cases, predicted accumulatedvolume is greater than the slug tank capacity.

    For the 12 hour case, the total predicted accumulatedvolume is just below the capacity of the slug tank.

    For the 48 and 60 hour cases, the total predictedaccumulated volume is well less than the capacity of

    the slug tank.

    For the late life case, longer ramp-up times are required

    due to the large liquid holdup present in the line. The specific

    ramp-up period identified where the accumulated volume did

    not exceed the slug tank volume was 120 hours. Figure 14

    shows the accumulated liquid volumes in the slug tank for the

    instantaneous, 48, 96, and 120 hour cases. The graph

    illustrates the following:

    For the instantaneous, 48, and 96 hour cases, predictedaccumulated volume is greater than slug tank capacity.

    For the 120 hour case, the total predicted accumulated

    volume is below the capacity of the slug tank.

    Liquid Flow Increase Simulation Procedure and ResultSummary.

    Simulation Procedure. The objective of these cases was as

    follows :

    Determine if a significantly increased liquid rate resultsin slugging which overwhelms the topside liquid

    handling facilities.

    These simulations were performed only for the late life flow

    conditions as this is the worst case scenario for significant

    impact on the topsides liquids handling. For the liquid

    volume associated with the late life flow of 75 MMSCFD, thewater production (and associated methanol dosing) of one well

    was increased to simulate an instantaneous increase in liquid

    rate in the flowline. This would be indicative of water

    breakthrough in a single well and illustrates the resultant

    impact on the host platform liquid handling facilities. The

    simulation procedure for this analysis was as follows.

    Run simulation with all four wells operating at the latelife flowrate until a steady-state condition is reached.

    Increase the water production ratio at MC348-1 tosimulate a sudden increase in liquid rate in the

    flowline. The ratios for MC348-1 were increased

    from 8 bbls / MMSCF to 25, 50, and 100 bbls /

    MMSCF respectively. The gas flowrate for MC348-1in the late life case is 20 MMSCFD. The methanol

    flowrate ratio of 1.5 times the water rate is held

    constant.

    Summary of Results

    25 BBL/MMSCF: This water rate increase resulted in anincreased flow of 850 BPD per day (water/methanol).

    Total liquid flow increased to 1290 BPD. The liquid

    handling facilities as modeled are capable of handling the

    excess liquids for this case with no flow to the slu

    The pressure at MC348-1 increases with higher fl

    liquid content.

    50 BBL/MMSCF: This water rate increase resulteflow increase of 2100 BPD of liquid (water/met

    Total liquid flow increased to 2540 BPD. The

    liquid exceeded slug tank volume in 2.75 days fol

    arrival at host platform. The pressure at Mincreases with higher flowline liquid content.

    100 BBL/MMSCF: This water rate increase resultflow increase of 4600 BPD of liquid (water/met

    Total liquid flow increased to 5040 BPD. The

    liquid exceeded the slug tank volume in 1 day fol

    arrival at host platform. The pressure at M

    increases significantly with higher flowline liquid co

    Figure 15 illustrates the results outlined above.

    Conclusions No steady-state operation scenarios were identi

    which liquid slug volumes were present in excessHP Separator liquid handling capability. For th

    majority of cases investigated there was no liquid sl

    predicted.

    Non-steady-state scenarios were identified which reincreased liquid flow in excess of topside ca

    However, there are cases where slug volumes co

    operationally mitigated via procedures in which the

    inlet flow rates were reduced by controlling the fl

    gas rate (e.g. slower ramp-up of well).

    Operation with a reduced slug tank volume (

  • 8/8/2019 19099Canyon Express Slugging and Liquids Handling

    8/15

    8 B. WALLACE, R. GUDIMETLA, G. SAETHER OTC

    Figure 1- Schematic Model of Canyon Express Production System

    Figure 2: East Flowline Route Profile used in OLGA Simulations

    CANYON EXPRESS DEVELOPMENTEAST FLOWLINE ROUTE PROFILE

    TRANSIENT STUDY BASIS

    HOST PLATFORM

    177-2

    305-3

    348-2

    348-1

    -8000

    -7000

    -6000

    -5000

    -4000

    -3000

    -2000

    -1000

    0

    1000

    0 20 40 60 80 100 120 140 160 180 200 220 240 260

    Distance (1000 ft)

    Elevation(ft)

    WEST

    EAST

    CANYON EXPRESS DEVELOPMENT

    FLOWLINE SCHEMATIC

    TRANSIENT STUDY BASIS

    KINGS

    PEAK

    BP

    CAMDEN

    HILLS

    MARATHON

    HOST

    PLATFORM

    ACONCAGUA

    TOTALFINAELF

    MC

    348-1

    MC

    348-2

    MC

    305-3

    4 miles

    MC

    305-1

    MC

    305-2

    MC

    217-3

    DC

    133-2

    MC

    217-2

    DC

    177-2

    11 miles 32 miles

    DUAL 12"PIPELINES

    GAS EXPORT

  • 8/8/2019 19099Canyon Express Slugging and Liquids Handling

    9/15

    OTC 13073 CANYON EXPRESS SLUGGING AND LIQUIDS HANDLING

    Table 1: Basis for Transient Simulations

    Figure 3- HP Separator Model Used in OLGA 2000

    Case Early Mid Late

    Water Rate (bbls /mmscf) 0.7 2.5 8.0

    Methanol Rate (bbls/bbl

    water)1.5 1.5 1.5

    Condensate Rate (bbls/mmscf) 2.0 2.0 2.0

    Host Arrival Pressure (psig) 2000 1000 500

    Host Separator Pressure (psig) 1750 750 486

    East Line Wells Flow (mmscfd)

    MC348-1 50 31 20

    MC348-2 50 50 10

    MC305-3 60 55 35

    DC177-2 50 14 10

    Total 210 150 75

    MULTIPHASE INLET HP SEPARATOR

    LC60"

    HLL 3 ft - 9 in

    SLUG TANK

    EMERGENCY

    DUMP

    NORMAL

    FLOW

    FC

    CONSTRAINT

    2600 to 2800 BPD

    CANYON EXPRESS DEVELOPMENT

    TRANSIENT STUDY HP SEPARATOR BASIS

    TO

    INLET

    CHOKE

    LC

    NLL 2 ft - 6 in

    CANYON

    EXPRESS

    FLOW

    HLL 3 ft - 9 in

    NLL 2 ft - 6 in

  • 8/8/2019 19099Canyon Express Slugging and Liquids Handling

    10/15

    10 B. WALLACE, R. GUDIMETLA, G. SAETHER OTC

    Figure 4 - Flowline Liquid Content at Various Gas Flowrates

    Figure 5 - Pressure at End of Flowline at Various Gas Flowrates

    Liquid Content East Flowline

    Early = 2000 psia, 0.7 H2O, Mid = 1000 psia, 2.5 H2O, Late = 500 psia, 8 H2O

    0

    5000

    10000

    15000

    20000

    25000

    0 50 100 150 200 250

    Gas Flowrate (mmscf/d)

    Liquidcontent(bbls)

    Early life

    Mid life

    Late life

    Subsea Inlet Pressure East Flowline

    Early = 2000 psia, 0.7 H2O, Mid = 1000 psia, 2.5 H2O, Late = 500 psia, 8 H2O

    0

    500

    1000

    1500

    2000

    2500

    3000

    3500

    4000

    4500

    0 50 100 150 200 250

    Gas Flowr ate (m ms cf/d)

    PressureatCamdenHills(psia)

    Early life

    Mid life

    Late life

  • 8/8/2019 19099Canyon Express Slugging and Liquids Handling

    11/15

    OTC 13073 CANYON EXPRESS SLUGGING AND LIQUIDS HANDLING

    Figure 6 - Late LifeSteady-State Operation at 40 MMSCFDLiquid Flowrate at Separator and Flowline Liquid Content

    Figure 7 - Late LifeSteady-State Operation at 40 MMSCFDHost Platform HP Separator Liquid Level

    LIQUID FLOWRATE

    LIQUID CONTENT

    0

    500

    1000

    1500

    2000

    2500

    3000

    3500

    4000

    0 12 24 36 48 60 72 84 96 108 120 132 144

    Time (Hrs)

    LiquidFlowrateatSeparator(BPD

    )

    13250

    13500

    13750

    14000

    14250

    14500

    14750

    15000

    15250

    FlowlineLiquidContent(Bbls)

    Actual Liquid Level

    High-High Liquid

    Level

    2.00

    2.25

    2.50

    2.75

    3.00

    3.25

    3.50

    3.75

    4.00

    0 12 24 36 48 60 72 84 96 108 120 132 144

    Time (Hrs)

    SeparatorLiquidLevel(ft)

  • 8/8/2019 19099Canyon Express Slugging and Liquids Handling

    12/15

    12 B. WALLACE, R. GUDIMETLA, G. SAETHER OTC

    Figure 8: Late LifeFull Flow / Shutdown / Re-Start (75-0-75 MMSCFD):Liquid Flowrate at Separator and Total Liquid Content

    Figure 9: Late LifeFull Flow / Shutdown / Re-Start (75-0-75 MMSCFD):Host Platform HP Separator Liquid Level

    LIQUID FLOWRATE

    SHUTDOWN

    RESTART

    LIQUID CONTENT

    0

    500

    1000

    1500

    2000

    2500

    3000

    3500

    4000

    4500

    5000

    5500

    6000

    0 12 24 36 48 60 72 84 96 108 120

    Time (Hrs)

    LiquidFlowrateatSeparator(BP

    D)

    5500

    5750

    6000

    6250

    6500

    6750

    7000

    7250

    7500

    7750

    8000

    8250

    8500

    FlowlineLiquidContent(Bbls)

    Actual Liquid Level

    High-High Liquid

    Level

    SHUTDOWN

    RESTART

    2.00

    2.25

    2.50

    2.75

    3.00

    3.25

    3.50

    3.75

    4.00

    0 12 24 36 48 60 72 84 96 108 120

    Time (Hrs)

    SeparatorLiquidLevel(Ft)

  • 8/8/2019 19099Canyon Express Slugging and Liquids Handling

    13/15

    OTC 13073 CANYON EXPRESS SLUGGING AND LIQUIDS HANDLING

    Figure 10 - Late LifeFull Flow / Shutdown / Re-Start (75-0-75 MMSCFD)Liquid Accumulation at Slug Tank

    Figure 11 - Mid LifeGas Flow Increase (95 MMSCFD to 150 MMSCFD)Flow Rate at HP Separator for Various Ramp-up Times

    WATER / METHANOL

    OIL

    SLUG TANK CAPACITY

    RESTART

    SHUTDOWN

    0

    400

    800

    1200

    1600

    2000

    2400

    2800

    0 12 24 36 48 60 72 84 96 108 120

    Time (Hrs)

    AccumulatedVolumeperPhase(Bb

    ls)

    RESTARTWELL

    0

    2000

    4000

    6000

    8000

    10000

    12000

    14000

    0 12 24 36 48 60 72 84 96 108 120 132 144 156 168

    Time (Hrs)

    LiquidFlowrateatSeparator(BPD)

    INSTANTANEOUS RAMP-UP

    12 HOUR RAMP-UP

    48 HOUR RAMP-UP

    60 HOUR RAMP-UP

  • 8/8/2019 19099Canyon Express Slugging and Liquids Handling

    14/15

    14 B. WALLACE, R. GUDIMETLA, G. SAETHER OTC

    Figure 12 - Mid LifeGas Flow Increase (95 MMSCFD to 150 MMSCFD)Host Platform HP Separator Liquid Level

    Figure 13 - Mid LifeGas Flow Increase (95 MMSCFD to 150 MMSCFD)Liquid Accumulation at Slug Tank at Various Ramp-up Times

    INSTANTANEOUS

    RAMP-UP

    Normal Liquid Level

    48 HOUR RAMP-UP

    60 HOUR RAMP-UP

    RESTARTWELL

    High-High Liquid Level

    2.00

    2.25

    2.50

    2.75

    3.00

    3.25

    3.50

    3.75

    4.00

    0 12 24 36 48 60 72 84 96 108 120 132 144 156 168

    Time (Hrs)

    SeparatorLiquidLevel(Ft)

    60 HR RAMPUP

    48 HR RAMPUP

    12 HOUR RAMPUP

    0 HOUR RAMPUPSLUG TANKCAPACITY

    RESTARTWELL

    0

    600

    1200

    1800

    2400

    3000

    0 12 24 36 48 60 72 84 96 108 120 132 144 156 168

    Time (Hrs)

    AccumulatedLiquidVolume(Bbls)

  • 8/8/2019 19099Canyon Express Slugging and Liquids Handling

    15/15

    OTC 13073 CANYON EXPRESS SLUGGING AND LIQUIDS HANDLING

    Figure 14 - Late LifeGas Flow Increase (95 MMSCFD to 150 MMSCFD)Liquid Accumulation at Slug Tank for Various Ramp-up Times

    Figure 15 - Late LifeLiquid Flow IncreaseLiquid Accumulation at Slug Tank for Various Liquid Ratios

    120 HR RAMPUP

    96 HR RAMPUP

    48 HR RAMPUP

    0 HR RAMPUP

    SLUG TANK

    CAPACITY

    RESTARTWELL

    0

    800

    1600

    2400

    3200

    4000

    4800

    5600

    6400

    7200

    0 12 24 36 48 60 72 84 96 108 120 132 144 156 168

    Time (Hrs)

    AccumulatedLiquidVolume(Bbls)

    50 BBL / MMSCF

    100 BBL / MMSCF

    INCREASELIQUID

    SLUG TANK CAPACITY

    25 BBL / MMSCF

    0

    800

    1600

    2400

    3200

    4000

    4800

    5600

    6400

    7200

    0 12 24 36 48 60 72 84 96 108 120

    Time (Hrs)

    AccumulatedLiquidVolume(Bbls)

    WATER RATIO LIQUID

    RATE

    25 BBL / MMSCF 2,500 BPD

    50 BBL / MMSCF 4,000 BPD

    100 BBL / MMSCF 6,500 BPD