Extension of Building Neutrino Platform General Meetings N.Lopez – M.Manfredi EHN1 civil engineering project status 19 February (5 th week) Ground surveys to determine own features (top soil thick, water table depth..). Septic tank survey and site entrance area arrangement (5 th week) Existing networks research. Valve installation by SIG on the potable water network. Done (2/4): Site work side