18 months Multi Donor Fund for Aceh and Nias. December 14, 2006. The Multi Donor Fund for Aceh and Nias. 15 Donors US$ 655 million ($110 million new pledges) Start May 2005 Support the reconstruction and rehabilitation of Aceh and Nias. Donors – 655 US$ million. - PowerPoint PPT Presentation

Citation preview

  • 18 monthsMulti Donor Fund for Aceh and Nias

    December 14, 2006

  • The Multi Donor Fund for Aceh and Nias15 DonorsUS$ 655 million ($110 million new pledges)Start May 2005

    Support the reconstruction and rehabilitation of Aceh and Nias

  • Donors 655 US$ millionEuropean Commission 253.6 mNetherlands 175.5 mUK 72.4 mWorld Bank 25.0 mSweden 20.0 mNorway 18.0 mDenmark 18.0 mGermany 13.8 mCanada, Belgium, Finland, ADB, USA, (at least 10 million)New Zealand and Ireland (less than $10 million)

  • How we workThe Multi Donor Fund cooperates with the Government (BRR and local government)Civil SocietyInternational NGOsUnited NationsSupport the coordination of the recovery effort

  • What do we finance?In US$

  • Partnership with BRRProject replenishment by BRRKDP +/- US$ 60mHousing +/-US$ 9m

    Co-financing BRR and BRAIRFF US$ 191mSPADAUS$ 14.6mKRRP (KDP Nias)US$ 25.75m

  • Pledges and Disbursements655482214Pledges - $110 million are new pledges received in recent months, from the Netherlands, the United Kingdom, Sweden and Germany.

  • Achieved Results

  • Recovery of Communities US$209m Empowering villagers to recover their communities and houses.Over 6,000 houses rebuilt or under construction and over 2,600 repaired1,900 km roads, 710 bridges, 240 schools, 1,143 irrigation & drainage units, 40 health postsOver 7000 scholarships and over 3,600 micro-credits allocatedOver 27,000 land titles registered in the land book, 7,703 titles distributedGeneration of over 10 million person-days of employment

  • Infrastructure & Transport US$176mTransport of 88,000mt of reconstruction materials Three ports designedinstallation of 11 flood valves and design for 105 more in Banda AcehMaintaining a 52km stretch between Lamno-Calang

    IREP: local governments identify key infrastructure needs which may get financed through IRFF ($ 191 co-financing by BRR)

  • Sustaining the Environment US$32mRemoval of 1,060,000m tsunami waste/ 88,000m municipal waste Clearing 669ha paddies; Recovery of 17,000m3 wood for construction

    Training of forest monitorsIncluding conservation concerns in spatial planning processPlanting of thousands of seedlings

  • Capacity Building US$65m Building capacity of reconstruction stakeholders

    BRR Technical Assistance support (IT, legal and HR functions, Quality assurance team overseeing BRRs portfolio, support BRR in policy development, implementation supportTraining of local government and contractors to manage the rehabilitation and maintenance of district roadsCSO assessment has been completed, first step towards training

  • Portfolio implementation

    Looking forward

  • For more details contact: Sabine JoukesDeputy for Coordination and [email protected] 934 880