Alcatel-Lucent GSM

Move Mixed CS/GPRS Link 

into Dedicated GPRS Link 

MPI95 / MDR6 - CCL

MFS Document

Reconfiguration Method

3BK 17430 0956 QZZZA Ed.05

Page 2: 174300956 Cc Le 05

8/13/2019 174300956 Cc Le 05

http://slidepdf.com/reader/full/174300956-cc-le-05 2/14

Status RELEASED

Short title MPI95 / MDR6

All rights reserved. Passing on and copying of this document, useand communication of its contents not permitted without writtenauthorization from Alcatel-Lucent.

BLANK PAGE BREAK

2  / 14   3BK 17430 0956 QZZZA Ed.05

Page 3: 174300956 Cc Le 05

8/13/2019 174300956 Cc Le 05

http://slidepdf.com/reader/full/174300956-cc-le-05 3/14

Move Mixed CS/GPRS Link into Dedicated GPRS Link

MPI95 / MDR6 - CCL

Identification

Customer

Country

OMC-R Site Name: Address:

Name: Address:

Alcatel-Lucent Representative (s)

Customer Representative (s)

Customer Contractor Representative (s)

Date, Time and Duration of Work Start End Duration

General Remarks from Customer General Remarks from Alcatel-Lucent

3BK 17430 0956 QZZZA Ed.05   3  / 14

Page 4: 174300956 Cc Le 05

8/13/2019 174300956 Cc Le 05

http://slidepdf.com/reader/full/174300956-cc-le-05 4/14

Applicable Documents

Fill in the edition of the applicable documents 

Document Title Document Reference Edition

Move Mixed CS/GPRS Link into Dedicated GPRS Link 3BK 17430 0956 RJZZA

B10 BSS Methods Handbook 3BK 21268 AAAA PCZZA

BSS Configuration Handbook 3BK 21201 AAAA PCZZA

BSS Surveillance Handbook 3BK 21206 AAAA PCZZA

Network Reconfiguration Recommendations 3BK 21269 AAAA PCZZA

Applicable ITL

Information

Fill in the site data.

OMC-R Hostname

User Name

Password

Cases and Options

Enter a cross for the applicable case or option.

C1 Gb resources going through TC are moved to the dedicated MFS-SGSN link

C2  Gb resources going through TC are removed during the move of the link because Gb

capacity is not adapted to requirements

C3 The Ater Mux is a synchronizing one.

O1  New Gb resources are added on the new MFS-SGSN link, if the Gb capacity is not

sufficient

O2  Radio resources are increased because the capacity to support the GPRS is not

sufficient

O3 Reshuffle cell mapping if Multi-GPU/Multi-GP per BSS is used.

4  / 14   3BK 17430 0956 QZZZA Ed.05

Page 5: 174300956 Cc Le 05

8/13/2019 174300956 Cc Le 05

http://slidepdf.com/reader/full/174300956-cc-le-05 5/14

Software & Documentation Versions

Fill in the appropriate INITIAL and FINAL software versions.

For BSS reshuffling methods, the INITIAL and FINAL versions are equal.For installation methods, the INITIAL version is "-" .

Initial Version Final Version

OMC-R

NPA

RNO

LASER

BSS

MFS

DocumentationVersion

3BK 17430 0956 QZZZA Ed.05   5  / 14

Page 6: 174300956 Cc Le 05

8/13/2019 174300956 Cc Le 05

http://slidepdf.com/reader/full/174300956-cc-le-05 6/14

Results Table

Fill in the Results Table according to the following rules: YES: Put a cross here if the task was performed NO: Put a cross here if the task was not performed 

N.A: Put a cross here if the task is not applicable S.A: Enter the number of solved anomalies N.S.A: Enter the number of non-solved anomalies 

Scenario Description

Initial Checks

YES NO N.A S.A N.S.A

Global Checks

Print Gb Configuration

Print Transport Configuration

Performed by Site Date Start Time End Time Duration

C3: Set Synchronize PCM-TPP

YES NO N.A S.A N.S.A

C3: Set Synchronize PCM-TPP

Performed by Site Date Start Time End Time Duration

Stop Traffic on Ater Mux

YES NO N.A S.A N.S.A

Stop Traffic on Ater Mux

Performed by Site Date Start Time End Time Duration

6  / 14   3BK 17430 0956 QZZZA Ed.05

Page 7: 174300956 Cc Le 05

8/13/2019 174300956 Cc Le 05

http://slidepdf.com/reader/full/174300956-cc-le-05 7/14

C1: Move Gb Resources

YES NO N.A S.A N.S.A

C1: Move Gb Resources

Performed by Site Date Start Time End Time Duration

C2: Delete Gb Resources

YES NO N.A S.A N.S.A

C2: Delete Gb Resources

Performed by Site Date Start Time End Time Duration

Configure Transport at MFS

YES NO N.A S.A N.S.A

Configure Transport at MFS

Performed by Site Date Start Time End Time Duration

Modify Mixed Ater Mux into Dedicated Ater Mux

YES NO N.A S.A N.S.A

Modify Mixed Ater Mux into Dedicated Ater Mux

Performed by Site Date Start Time End Time Duration

3BK 17430 0956 QZZZA Ed.05   7  / 14

Page 8: 174300956 Cc Le 05

8/13/2019 174300956 Cc Le 05

http://slidepdf.com/reader/full/174300956-cc-le-05 8/14

Connect Physical Ater Mux

YES NO N.A S.A N.S.A

Connect Physical Ater Mux

Performed by Site Date Start Time End Time Duration

O1: Configure Gb

YES NO N.A S.A N.S.A

O1: Configure Gb

Performed by Site Date Start Time End Time Duration

Set Traffic on Ater Mux

YES NO N.A S.A N.S.A

Set Traffic on Ater Mux

Performed by Site Date Start Time End Time Duration

Set GPRS Traffic

YES NO N.A S.A N.S.A

Set GPRS Traffic

Performed by Site Date Start Time End Time Duration

8  / 14   3BK 17430 0956 QZZZA Ed.05

Page 9: 174300956 Cc Le 05

8/13/2019 174300956 Cc Le 05

http://slidepdf.com/reader/full/174300956-cc-le-05 9/14

Test GPRS Service

YES NO N.A S.A N.S.A

Test GPRS Service

Performed by Site Date Start Time End Time Duration

O2: Configure Radio Interface

YES NO N.A S.A N.S.A

O2: Configure Radio Interface

Performed by Site Date Start Time End Time Duration

Final Checks

YES NO N.A S.A N.S.A

Final Checks

Performed by Site Date Start Time End Time Duration

Final Operations

YES NO N.A S.A N.S.A

Final Operations

Performed by Site Date Start Time End Time Duration

3BK 17430 0956 QZZZA Ed.05   9  / 14

Page 10: 174300956 Cc Le 05

8/13/2019 174300956 Cc Le 05

http://slidepdf.com/reader/full/174300956-cc-le-05 10/14

Reverse Procedure

Stop GPRS Traffic on Ater Mux

YES NO N.A S.A N.S.A

Stop GPRS Traffic on Ater Mux

Performed by Site Date Start Time End Time Duration

C1, O1: Delete Gb Resources

YES NO N.A S.A N.S.A

C1, O1: Delete Gb Resources

Performed by Site Date Start Time End Time Duration

Modify Dedicated Ater Mux into Mixed Ater Mux

YES NO N.A S.A N.S.A

Modify Dedicated Ater Mux into Mixed Ater Mux

Performed by Site Date Start Time End Time Duration

Configure Transport at MFS

YES NO N.A S.A N.S.A

Configure Transport at MFS

Performed by Site Date Start Time End Time Duration

10 / 14   3BK 17430 0956 QZZZA Ed.05

Page 11: 174300956 Cc Le 05

8/13/2019 174300956 Cc Le 05

http://slidepdf.com/reader/full/174300956-cc-le-05 11/14

Connect Physical Ater Mux

YES NO N.A S.A N.S.A

Connect Physical Ater Mux

Performed by Site Date Start Time End Time Duration

Configure GPRS

YES NO N.A S.A N.S.A

C1, C2: Configure Gb Interface

O2: Configure Radio Interface

Performed by Site Date Start Time End Time Duration

Set GPRS Traffic

YES NO N.A S.A N.S.A

Set GPRS Traffic

Performed by Site Date Start Time End Time Duration

Test Call and GPRS Service

YES NO N.A S.A N.S.A

Test Call and GPRS Service

Performed by Site Date Start Time End Time Duration

3BK 17430 0956 QZZZA Ed.05   11 / 14

Page 12: 174300956 Cc Le 05

8/13/2019 174300956 Cc Le 05

http://slidepdf.com/reader/full/174300956-cc-le-05 12/14

Final Checks

YES NO N.A S.A N.S.A

Final Checks

Performed by Site Date Start Time End Time Duration

Final Operations

YES NO N.A S.A N.S.A

Final Operations

Performed by Site Date Start Time End Time Duration

C1, O1: Disconnect MFS-SGSN Link

YES NO N.A S.A N.S.A

C1, O1: Disconnect MFS-SGSN Link

Performed by Site Date Start Time End Time Duration

12 / 14   3BK 17430 0956 QZZZA Ed.05

Page 13: 174300956 Cc Le 05

8/13/2019 174300956 Cc Le 05

http://slidepdf.com/reader/full/174300956-cc-le-05 13/14

Unavailability Duration Sheet

Fill in the unavailability duration sheet according to the following rule: Section Title Title of the paragraph where the unavailability occured Unavailability type    T for traffic interruption , R  for traffic reduction , S  for loss of supervision 

(T,R and S could be held simultaneously)Equipment Equipment with its number (eg BTS-1)Date Date expressed as: yy/mm/dd  Start time Start time expressed as: hh/mm/ss End time End time expressed as: hh/mm/ss 

UnavailabilityType

Equipment Date Start Time End Time

Section Title

Section Title

Section Title

Section Title

Section Title

Section Title

Section Title

Section Title

Section Title

Section Title

Section Title

3BK 17430 0956 QZZZA Ed.05   13 / 14

Page 14: 174300956 Cc Le 05

8/13/2019 174300956 Cc Le 05

http://slidepdf.com/reader/full/174300956-cc-le-05 14/14

Anomaly Sheet

Fill in the unavailability duration sheet according to the following rule: Section Title Title of the paragraph where the anomaly occured  Brief description of the anomaly Summarize the anomaly (details must be in anomaly report)

Anomaly report Anomaly report was sent or no  Solved by Name of the technician who solved the anomaly Date of anomaly solving 

Description   Solved by

Section Title:

Brief description of the anomaly:

Anomaly report: Y/N

Name:

Date:

Section Title:

Brief description of the anomaly:

Anomaly report: Y/N

Name:

Date:

Section Title:

Brief description of the anomaly:

Anomaly report: Y/N

Name:

Date:

Section Title:

Brief description of the anomaly:

Anomaly report: Y/N

Name:

Date:

Section Title:

Brief description of the anomaly:

Anomaly report: Y/N

Name:

Date:

Section Title:

Brief description of the anomaly:

Anomaly report: Y/N

Name:

Date:

14 / 14