1733 Asphalt Paving at MRF

  • Upload
    ffldcad

  • View
    221

  • Download
    0

Embed Size (px)

Citation preview

  • 7/29/2019 1733 Asphalt Paving at MRF

    1/2

    UNIT COST

    EXTENDED

    COST UNIT COST

    EXTENDED

    COST UNIT COST

    EXTENDED

    COST

    1 MOBILIZATION LS 1.00 $3,000.00 $3,000.00 $2,900.00 $2,900.00 $1,800.00 $1,800.00

    2REMOVE AND DISPOSE ASPHALT PAVEMENT AND RECYCLED ASPHALTPAVEMENT SECTION, 14" SY 109.00 $10.00 $1,090.00 $10.00 $1,090.00 $18.00 $1,962.00

    3 REMOVE AND DISPOSE RECYCLED ASPHALT PAVEMENT, 14" SY 224.00 $10.00 $2,240.00 $8.50 $1,904.00 $15.50 $3,472.00

    4 UNCLASSIFIED EXCAVATION, DIGOUTS WITH SUGAR ROCK CY 20.00 $50.00 $1,000.00 $63.32 $1,266.40 $75.00 $1,500.00

    5 GEOTEXTILE FABRIC SY 50.00 $3.00 $150.00 $3.00 $150.00 $5.00 $250.00

    6 RECYCLED ASPHALT PAVEMENT PATCHING, 10" (BASE) SY 185.00 $22.00 $4,070.00 $10.05 $1,859.25 $11.50 $2,127.50

    7 RECYCLED ASPHALT PAVEMENT PATCHING, 14" (FULL DEPTH) SY 224.00 $25.00 $5,600.00 $13.41 $3,003.84 $13.50 $3,024.00

    8 AC PATCHING, CLASS G, TYPE 1, 4" SY 109.00 $30.00 $3,270.00 $26.00 $2,834.00 $30.00 $3,270.00

    9 AC SKIN PATCH OR OVERLAY, CLASS G, TYPE 1, 2" TON 100.00 $120.00 $12,000.00 $95.00 $9,500.00 $110.00 $11,000.00

    10 CRACK SEALING LF 650.00 $2.50 $1,625.00 $1.94 $1,261.00 $2.00 $1,300.00

    11 FLUSH SEAL SY 19,400.00 $0.30 $5,820.00 $0.22 $4,268.00 $0.75 $14,550.00

    12 COVER AGGREGATE TON 190.00 $65.00 $12,350.00 $44.62 $8,477.80 $52.00 $9,880.00

    13 ASPHALT FOR SURFACE TREATMENT TON 15.00 $750.00 $11,250.00 $697.34 $10,460.10 $1,100.00 $16,500.00

    14 CONCRETE PAVEMENT, REINFORCED, 8" SY 76.00 $90.00 $6,840.00 $100.00 $7,600.00 $97.00 $7,372.00

    15 PAVEMENT MARKING PAINT, 4" WHITE LF 1,760.00 $0.25 $440.00 $0.15 $264.00 $0.30 $528.00

    16 PAVEMENT MARKING PAINT, 4" YELLOW LF 2,800.00 $0.25 $700.00 $0.15 $420.00 $0.30 $840.00

    17 PAVEMENT MARKING PAINT, 12" WHITE LF 15.00 $0.50 $7.50 $2.49 $37.35 $0.80 $12.00

    18 PAVEMENT MARKING PAINT, TURN ARROW EA 2.00 $50.00 $100.00 $37.38 $74.76 $16.50 $33.00

    BID TABULATION

    ASPHALT PAVING REPAIR AT MATERIAL RECOVERY FACILITY / CO-COMPOST PLANT

    PROJECT NO. SWO08-1733 / CIP NO. 50731

    BID LETTING DATE: JUNE 10, 2008

    ITEM

    NO. DESCRIPTION OF ITEM UNIT

    QTY

    (EST)

    HILLS MATERIALS COMPANYSIMON CONTRACTORS OF

    SD, INC.ENGINEER'S ESTIMATE

    Asphalt Paving Repair at Material Recovery Facility / Co-Compost Plant

    Project No. SWO08-1733 / CIP No. 50731

    Page 1 of 2

  • 7/29/2019 1733 Asphalt Paving at MRF

    2/2

    UNIT COST

    EXTENDED

    COST UNIT COST

    EXTENDED

    COST UNIT COST

    EXTENDED

    COST

    ITEM

    NO. DESCRIPTION OF ITEM UNIT

    QTY

    (EST)

    HILLS MATERIALS COMPANYSIMON CONTRACTORS OF

    SD, INC.ENGINEER'S ESTIMATE

    19 PAVEMENT MARKING PAINT, "ONLY" SIGN EA 1.00 $100.00 $100.00 $24.92 $24.92 $17.50 $17.50

    $71,652.50 $57,395.42 $79,438.00

    20 REMOVE CURB AND GUTTER LF 124.00 $10.00 $1,240.00 $3.36 $416.64 $6.00 $744.00

    21REMOVE AND DISPOSE ASPHALT PAVEMENT AND RECYCLED ASPHALT

    PAVEMENT SECTION, 14" SY 260.00 $10.00 $2,600.00 $5.50 $1,430.00 $11.00 $2,860.00

    22 UNCLASSIFIED EXCAVATION, DIGOUTS WITH SUGAR ROCK CY 200.00 $50.00 $10,000.00 $45.00 $9,000.00 $60.00 $12,000.00

    23 GEOTEXTILE FABRIC SY 310.00 $3.00 $930.00 $3.00 $930.00 $3.00 $930.00

    24 RECYCLED ASPHALT PAVEMENT, 10" CY 190.00 $12.00 $2,280.00 $17.84 $3,389.60 $24.00 $4,560.00

    25 ASPHALT CONCRETE, CLASS G, TYPE 1, 4" TON 70.00 $120.00 $8,400.00 $87.00 $6,090.00 $107.00 $7,490.00

    26 CURB AND GUTTER LF 124.00 $30.00 $3,720.00 $32.00 $3,968.00 $23.51 $2,915.24

    $29,170.00 $25,224.24 $31,499.24

    $100,822.50 $82,619.66 $110,937.24

    Contract awarded to Hills Materials Company in the amount of

    $82,619.66 at the June 16, 2008 Council Meeting.

    I certify that, to the best of my knowledge, this is a true tabulation of bids received for this project.

    ____________________________________________________

    Keith Johnson, Project Manager Date

    TOTAL BASE BID

    ADD-ON ALTERNATE NUMBER ONE

    TOTAL ADD-ON ALTERNATE NUMBER ONE

    TOTAL BASE BID AND ADD-ON ALTERNATE NUMBER ONE

    Asphalt Paving Repair at Material Recovery Facility / Co-Compost Plant

    Project No. SWO08-1733 / CIP No. 50731

    Page 2 of 2