7/29/2019 1733 Asphalt Paving at MRF
1/2
UNIT COST
EXTENDED
COST UNIT COST
EXTENDED
COST UNIT COST
EXTENDED
COST
1 MOBILIZATION LS 1.00 $3,000.00 $3,000.00 $2,900.00 $2,900.00 $1,800.00 $1,800.00
2REMOVE AND DISPOSE ASPHALT PAVEMENT AND RECYCLED ASPHALTPAVEMENT SECTION, 14" SY 109.00 $10.00 $1,090.00 $10.00 $1,090.00 $18.00 $1,962.00
3 REMOVE AND DISPOSE RECYCLED ASPHALT PAVEMENT, 14" SY 224.00 $10.00 $2,240.00 $8.50 $1,904.00 $15.50 $3,472.00
4 UNCLASSIFIED EXCAVATION, DIGOUTS WITH SUGAR ROCK CY 20.00 $50.00 $1,000.00 $63.32 $1,266.40 $75.00 $1,500.00
5 GEOTEXTILE FABRIC SY 50.00 $3.00 $150.00 $3.00 $150.00 $5.00 $250.00
6 RECYCLED ASPHALT PAVEMENT PATCHING, 10" (BASE) SY 185.00 $22.00 $4,070.00 $10.05 $1,859.25 $11.50 $2,127.50
7 RECYCLED ASPHALT PAVEMENT PATCHING, 14" (FULL DEPTH) SY 224.00 $25.00 $5,600.00 $13.41 $3,003.84 $13.50 $3,024.00
8 AC PATCHING, CLASS G, TYPE 1, 4" SY 109.00 $30.00 $3,270.00 $26.00 $2,834.00 $30.00 $3,270.00
9 AC SKIN PATCH OR OVERLAY, CLASS G, TYPE 1, 2" TON 100.00 $120.00 $12,000.00 $95.00 $9,500.00 $110.00 $11,000.00
10 CRACK SEALING LF 650.00 $2.50 $1,625.00 $1.94 $1,261.00 $2.00 $1,300.00
11 FLUSH SEAL SY 19,400.00 $0.30 $5,820.00 $0.22 $4,268.00 $0.75 $14,550.00
12 COVER AGGREGATE TON 190.00 $65.00 $12,350.00 $44.62 $8,477.80 $52.00 $9,880.00
13 ASPHALT FOR SURFACE TREATMENT TON 15.00 $750.00 $11,250.00 $697.34 $10,460.10 $1,100.00 $16,500.00
14 CONCRETE PAVEMENT, REINFORCED, 8" SY 76.00 $90.00 $6,840.00 $100.00 $7,600.00 $97.00 $7,372.00
15 PAVEMENT MARKING PAINT, 4" WHITE LF 1,760.00 $0.25 $440.00 $0.15 $264.00 $0.30 $528.00
16 PAVEMENT MARKING PAINT, 4" YELLOW LF 2,800.00 $0.25 $700.00 $0.15 $420.00 $0.30 $840.00
17 PAVEMENT MARKING PAINT, 12" WHITE LF 15.00 $0.50 $7.50 $2.49 $37.35 $0.80 $12.00
18 PAVEMENT MARKING PAINT, TURN ARROW EA 2.00 $50.00 $100.00 $37.38 $74.76 $16.50 $33.00
BID TABULATION
ASPHALT PAVING REPAIR AT MATERIAL RECOVERY FACILITY / CO-COMPOST PLANT
PROJECT NO. SWO08-1733 / CIP NO. 50731
BID LETTING DATE: JUNE 10, 2008
ITEM
NO. DESCRIPTION OF ITEM UNIT
QTY
(EST)
HILLS MATERIALS COMPANYSIMON CONTRACTORS OF
SD, INC.ENGINEER'S ESTIMATE
Asphalt Paving Repair at Material Recovery Facility / Co-Compost Plant
Project No. SWO08-1733 / CIP No. 50731
Page 1 of 2
7/29/2019 1733 Asphalt Paving at MRF
2/2
UNIT COST
EXTENDED
COST UNIT COST
EXTENDED
COST UNIT COST
EXTENDED
COST
ITEM
NO. DESCRIPTION OF ITEM UNIT
QTY
(EST)
HILLS MATERIALS COMPANYSIMON CONTRACTORS OF
SD, INC.ENGINEER'S ESTIMATE
19 PAVEMENT MARKING PAINT, "ONLY" SIGN EA 1.00 $100.00 $100.00 $24.92 $24.92 $17.50 $17.50
$71,652.50 $57,395.42 $79,438.00
20 REMOVE CURB AND GUTTER LF 124.00 $10.00 $1,240.00 $3.36 $416.64 $6.00 $744.00
21REMOVE AND DISPOSE ASPHALT PAVEMENT AND RECYCLED ASPHALT
PAVEMENT SECTION, 14" SY 260.00 $10.00 $2,600.00 $5.50 $1,430.00 $11.00 $2,860.00
22 UNCLASSIFIED EXCAVATION, DIGOUTS WITH SUGAR ROCK CY 200.00 $50.00 $10,000.00 $45.00 $9,000.00 $60.00 $12,000.00
23 GEOTEXTILE FABRIC SY 310.00 $3.00 $930.00 $3.00 $930.00 $3.00 $930.00
24 RECYCLED ASPHALT PAVEMENT, 10" CY 190.00 $12.00 $2,280.00 $17.84 $3,389.60 $24.00 $4,560.00
25 ASPHALT CONCRETE, CLASS G, TYPE 1, 4" TON 70.00 $120.00 $8,400.00 $87.00 $6,090.00 $107.00 $7,490.00
26 CURB AND GUTTER LF 124.00 $30.00 $3,720.00 $32.00 $3,968.00 $23.51 $2,915.24
$29,170.00 $25,224.24 $31,499.24
$100,822.50 $82,619.66 $110,937.24
Contract awarded to Hills Materials Company in the amount of
$82,619.66 at the June 16, 2008 Council Meeting.
I certify that, to the best of my knowledge, this is a true tabulation of bids received for this project.
____________________________________________________
Keith Johnson, Project Manager Date
TOTAL BASE BID
ADD-ON ALTERNATE NUMBER ONE
TOTAL ADD-ON ALTERNATE NUMBER ONE
TOTAL BASE BID AND ADD-ON ALTERNATE NUMBER ONE
Asphalt Paving Repair at Material Recovery Facility / Co-Compost Plant
Project No. SWO08-1733 / CIP No. 50731
Page 2 of 2