1717261 Project Management Checklist

Embed Size (px)

Citation preview

  • 8/3/2019 1717261 Project Management Checklist

    1/11

    Overview

    Project Number

    Project Purpose

    Project Sponsor

    Project Manager

    Tracking Project Progress

    Contract Administration

    Planning ActivitiesEstimating Activities

    Human Resources

    Quality Management

    Inspections

    Procurement Procurement Planning

    The EPO project management checklists are intended to assist the project manager in planning, executing

    and controlling projects. The checklists consist of Yes/No questions based on the knowledge areas in thePMBOK 2004 edition. If the answer to a question is No, review the explanation provided and consider

    what needs to be done in your organization or on your project to move to a Yes answer. Suggested EPO

    e-Books and Templates are identified to facilitate the change from No to Yes answers.

    Managing Issues & Changes

    Closing the Project

    Planning the Scope

    The content list below can be used to jump to a selected topic.

    PMBOK Knowledge Area Project Management Topic

    Obtaining Project ApprovalIntegration

    Initiating the Project

    Sponsoring Department

    Performing Department

    Project Management Checklist

    Project Information

    Project Name

    Scope

    Time

    Communications

    Monitoring Project Costs

    Cost Estimating Project Costs

    Establishing the Budget

    Stakeholder Identification

    Quality

    Risk Risk Identification

    Evaluating Bids & Proposals

    Risk Assessment

    Risk Response Planning

    Planning the Work

    Reporting Project StatusCommunications Planning

    Testing

    Developing the Schedule

    Monitoring the Schedule

    Human Resource Planning

    Managing the Team

    PO Template 2006 Gord Gibben, PMP Version 7.

  • 8/3/2019 1717261 Project Management Checklist

    2/11

    Integration

    Question Y/N Explanation EPO Template EPO e-book

    Is there a well-defined process to

    identify potential projects?

    The first step in the project approval process is the

    identification of potential projects. This can be part of a

    strategic or annual planning process or triggered by some

    external business event.

    Potential Project

    Identification

    Project Prioritization

    & Approval

    Has a project sponsor been identified

    for each potential project?

    The project sponsor is a key interface between the project

    team and senior management. Project sponsors are oftenresponsible for providing resources and setting direction for

    the project.

    Potential Project

    Identification

    Project Prioritization

    & Approval

    Does a screening & prioritization

    process exist for potential projects?

    The needs of potential projects will often surpass the

    available resources and finances. Prioritization will

    establish the relative importance of competing projects and

    screen out projects will low importance or poor benefits.

    Potential Project

    Identification, Project

    Priority & Approval

    Project Prioritization

    & Approval

    Are potential projects prioritized by

    business management prior to

    approval?

    Prioritization is not an approval process; rather it is a

    screening and ranking process. The output from

    prioritization is a list of projects that have been ranked

    according to their relative importance.

    Project Priority &

    Approval

    Project Prioritization

    & Approval

    Does a Project Approval Committee

    exist to review and approve projects?Project prioritization should be done by department

    managers and division Vice Presidents. Project approvals

    are obtained from executives who belong to a Project

    Approval Committee.

    Project Business

    Case, Project Priority

    & Approval

    Project Prioritization

    & Approval

    Is a business case prepared for each

    project approval? The Project Business Case describes the project costs and

    benefits to enable a business decision whether or not to

    proceed with the project.

    Project Business

    Case

    Project Prioritization

    & Approval

    Is a business need assessment

    conducted for each potential project?The Business Need Assessment provides an analysis of the

    high level business requirement being addressed by the

    project and an opportunity to comment on the relative

    importance of the project.

    Project Business

    Case

    Project Prioritization

    & Approval

    Is a cost/benefit analysis completed

    for each project? The cost benefit analysis is performed to determine if the

    benefits of completing the project outweigh the costs of

    performing the work

    Cost Benefit

    Analysis

    Project Prioritization

    & Approval

    Are objective criteria such as Return

    on Investment (ROI) or payback

    period used to prioritize and approveprojects?

    Return on Investment (ROI) is a percentage based on the

    net income from a project divided by the costs of the project.The payback period for a project is the time it takes for the

    benefits of a project to repay its costs.

    Cost Benefit

    Analysis

    Project Prioritization

    & Approval

    Are project approvals based on

    business, financial and technical

    criteria?The Project Approval Committee (or a similar group of

    senior management) needs to balance the business,

    financial and technical criteria from a corporate perspective

    when granting approvals to proposed projects

    Project Business

    Case

    Project Prioritization

    & Approval

    Has a Project Charter been

    prepared?

    The Project Charter is the document that formally

    acknowledges the existence of the project. It may be

    prepared by the Project Sponsor, the Project Manager, or as

    a collaborative effort.

    Project Charter Project Initiation &

    Scope Planning

    Are project assumptions

    documented?

    Assumptions are conditions upon which the project is

    based. They often involve a degree of risk and express

    situations that the project may encounter. Theseassumptions must be communicated to project

    stakeholders and confirmed where required.

    Constraints &

    Assumptions

    Checklist

    Project Initiation &

    Scope Planning

    Have project constraints been

    documented?

    Constraints are restrictions that will impact project

    management options. Because these constraints will limit

    the project management approaches or alternatives

    available, it is imperative that both Project Sponsor and

    Project Manager share an understanding of these

    limitations

    Constraints &

    Assumptions

    Checklist

    Project Initiation &

    Scope Planning

    Has the Project Manager been

    assigned and his/her authority

    defined?

    The Project Manager should be assigned prior to project

    initiation and his/her authority should be defined and agreed

    to by the project sponsor.

    Project Charter Project Initiation &

    Scope Planning

    Are project team tracking meetings

    held to monitor progress and discuss

    issues?

    Project team tracking meetings should be held on a regular

    basis to discuss progress on activities and status of high

    priority risks and open issues, changes and decisions.

    Team Tracking

    Meeting

    Project Tracking

    Do project team members report time

    spent on project activities?

    Time reports should be completed on a regular basis (daily

    or weekly) by team members and reviewed by team leads or

    the project manager.

    Time Report,

    Tracking View

    Project Tracking

    Is there a process in place to manage

    project issues?

    An issue is a situation that occurs outside the control of the

    project team that must be resolved in order for progress to

    continue. In most cases, the issue must be resolved by a

    certain date or there will be an adverse affect on the project

    deliverables, target dates or costs. The resolution to the

    issue needs to be documented and understood by all

    parties affected.

    Project Issue,

    Change

    Management Log

    Issue & Change

    Management

    Is a formal change management

    process used on the project?

    Change is a constant on projects; it is a reality of project

    management. Changes require deviations from project planand can impact project scope, cost or schedule. The

    changes must be handled through five Change

    Management processes: identification, evaluation,

    recommendation, approval, and incorporation.

    Change Request,

    Change

    Management Log

    Issue & Change

    Management

    Does a Project Steering Committee

    exist to help manage issues and

    changes?

    The Project Steering Committee consists of various project

    stakeholders. The specific make up of the Project Steering

    Committee will vary from project to project and will depend

    on a number of factors

    Project Steering

    Committee

    Stakeholder

    Management

    Is there a process in place to escalate

    important project decisions?

    The Project Manager, in conjunction with the project team

    and/or Project Steering Committee will have to make

    important decisions during the project that will affect its

    outcome. In some cases the decision will be made by the

    project team and communicated to those affected. In other

    cases, the decision will be escalated to the Project SteeringCommittee for approval.

    Decision Request,

    Change

    Management Log

    Issue & Change

    Management

    I th i l t l t I t d i i i l ti ti A ti It I & Ch

    Managing Issues & Changes

    Project Management Checklist

    Obtaining Project Approval

    Initiating the Project

    Tracking Project Progress

  • 8/3/2019 1717261 Project Management Checklist

    3/11

    Integration

    Have lessons learned from the

    project been documented for future

    projects

    Project lessons describe what worked well on the project.

    This will provide an opportunity to carry these successes

    over to future projects. Challenges and opportunities

    encountered on the project provide recommendations for

    improvement on future projects.

    Project Closure

    Report

    Project Review &

    Closure

    Has an assessment of the overall

    project been conducted?

    The purpose of the project review is to:

    Assess the project management techniques used on the

    project and recommend changes where applicable,

    Review the application of the organizations project

    management framework and identify improvements to the

    framework based on lessons learned on projects, Assess the feasibility of continuing with the project (or

    program) and provide validation to terminate the project if

    necessary.

    Project Review

    Report, Project

    Closure Report

    Project Review &

    Closure

    Has a review of the project business

    case been conducted?

    The purpose of the business case review is to compare the

    achievement of business objectives and project benefits

    with what was originally forecast

    Project Closure

    Report

    Project Review &

    Closure

    Has the project team provided an

    assessment of challenges and

    successes from their perspective?

    The Project Team Review section should be completed by

    the team and submitted to the project reviewers for

    inclusion in the Project Closure Report

    Project Closure

    Report

    Project Review &

    Closure

    Has a review of the technology and

    lifecycle processes been conducted?

    The technical review focuses on the technology and

    lifecycle processes used on the project.Project Closure

    Report

    Project Review &

    Closure

  • 8/3/2019 1717261 Project Management Checklist

    4/11

    cope

    Question Y/N Explanation EPO Template EPO e-book

    Have project objectives and critical

    success factors been identified?

    Project objectives are the goals of the project. Critical succes

    factors (CSF) are the project objectives that must be met for

    the project to be considered successful.

    Project Scope

    Statement

    Project Initiation &

    Scope Planning

    Have scope inclusion and exclusion

    criteria been identified?

    Inclusion and exclusion criteria identify the specific

    deliverables, products, and services to be provided by the

    project and explicitly define the items to be excluded from the

    project. This will define the scope boundary from both sides.

    Project Scope

    Statement

    Project Initiation &

    Scope Planning

    Has the project strategy been defined

    and agreed to by the project sponsor?

    The project strategy defines the approach to be followed on

    the project. It should clarify the methods, techniques and tool

    to be used.

    Project Scope

    Statement

    Project Initiation &

    Scope Planning

    Has a scope management matrix been

    prepared and agreed to by the project

    sponsor?

    The scope management matrix identifies the relative priorities

    of the three dimensions of the triple constraint (time, cost, and

    product).

    Scope Management

    Plan

    Project Initiation &

    Scope Planning

    Has a scope stability assessment been

    prepared?

    An assessment of the project scope stability will indicate the

    likelihood that the project scope may change and the potentia

    magnitude of such a change.

    Scope Management

    Plan

    Project Initiation &

    Scope Planning

    Has a scope change management

    approach been prepared?

    Successful change management on a project starts with an

    agreement on the methods to be followed to identify and

    evaluate changes.

    Scope Management

    Plan

    Project Initiation &

    Scope Planning

    Has a project Work Breakdown

    Structure (WBS) been prepared?

    The Work Breakdown Structure (WBS) provides an initial

    decomposition of project deliverables into smaller packages o

    work to support planning and estimating activities

    Work Package,

    WBS Planning

    View

    Work Breakdown

    Structure Planning

    Have project Work Packages been

    prepared and assigned?

    Work packages are discreet units of work that are assigned t

    individuals, teams, or external contractors. They can be used

    to subdivide the work according to discipline or to prescribe a

    deliverable to be completed by a contractor

    Work Package,

    WBS Assignment

    View

    Work Breakdown

    Structure Planning

    Project Management Checklist

    Planning the Scope

    Planning the Work

    EPO Template 2006 Gord Gibben, PMP Version 7.0

  • 8/3/2019 1717261 Project Management Checklist

    5/11

    Time

    Question Y/N Explanation EPO Template EPO e-book

    Has a project activity list been

    prepared?

    The activity list is an extension of the WBS and identifies all

    the activities required to produce WBS deliverables.Activity Plan, Activity

    Planning View

    Activity Planning &

    Estimating

    Does each project activity have a

    tangible deliverable?

    The activity name should consist of an action verb (produce,

    prepare, develop, install, etc) and an object of that verb thatnames the activity deliverable

    Activity Plan, Activity

    Planning View

    Activity Planning &

    Estimating

    Has a project network diagram been

    created?

    The activity sequencing is shown using a Project Network

    Diagram which illustrates how the project activities will flow

    from beginning to end. It is created by establishing the

    dependencies among project deliverables

    Activity Plan, Activity

    Sequencing View

    Activity Scheduling

    Have activity dependencies been

    established? Dependencies can be mandatory (based on required

    completion of deliverables) or discretionary (based on

    preferred sequence of activities).

    Activity Plan, Activity

    Sequencing View

    Activity Scheduling

    Have activity duration and effort

    estimates been prepared?

    Activity estimates have two components:

    Duration estimates (in days) provide an indication of how

    long a task will take and are used for critical pathscheduling.

    Effort estimates (in hours) are used to determine the

    amount of work (by each resource) required to produce a

    deliverable. Effort estimates are variable by resource and

    will be used when resource leveling the project schedule.

    Both duration and effort estimates need to be done for each

    activity.

    Activity Plan, Activity

    Estimating View

    Activity Planning &

    Estimating

    Have PERT duration estimating

    techniques been used?

    Using PERT estimating, three duration estimates are

    prepared for each activity: optimistic (O), pessimistic (P)

    and most likely (M).

    Activity Plan, Activity

    Estimating View

    Activity Planning &

    Estimating

    Have resource effort estimates been

    prepared for each activity?

    The effort required to perform an activity is dependent on

    the resources assigned. Because effort is variable by

    resource, it should be estimated for each resource assigned

    to an activity.

    Activity Plan, Activity

    Estimating View

    Activity Planning &

    Estimating

    Has the project critical path been

    identified?

    The critical path is defined as the sequence of activities with

    the longest duration. The critical path activities should be

    associated with production of important project deliverables

    and not support tasks.

    Activity Scheduling

    View

    Activity Scheduling

    Have resource leveling techniques

    been applied to the project schedule?

    Resource leveling is necessary when:

    One resource is assigned to multiple activities and their

    over allocation must be leveled out by extending the

    duration of some activities.

    Too many activities are assigned to one resource and

    some activities must be transferred to other resources.

    Multiple resources (with varying availability) are assigned

    to one activity.

    There are times in the schedule when resources are not

    fully occupied and will need work. Activity dependenciescan be shifted to level off peaks and fill in valleys of

    resource usage

    Activity Plan,

    Resource Leveling

    View

    Activity Scheduling

    Have duration compression

    techniques been applied to the

    project schedule?

    To meet fixed end dates, the duration of the project critical

    path may need to be shortened. This duration compression

    can be accomplished through fast tracking or crashing the

    schedule.

    Activity Scheduling

    View

    Activity Scheduling

    Have schedule milestones been

    established?

    Schedule milestones (evenly distributed throughout the

    schedule) are established for status tracking and reportingActivity Scheduling

    View

    Activity Scheduling

    Has a baseline project schedule been

    established?

    A project baseline provides a foundation for tracking &

    reporting and managing the effects of change.Activity Scheduling

    View

    Activity Scheduling

    Has a schedule management planbeen prepared?

    The Schedule Management Plan describes how thePMBOK time management processes will be carried out on

    the project

    ScheduleManagement Plan

    Project ScheduleManagement

    Is progress tracked and the schedule

    updated on a regular basis?

    Updating the schedule on a regular basis enables

    forecasting:

    Finish dates of activities started or already in progress,

    Estimated start dates of activities not yet started

    Schedule Update

    View

    Project Schedule

    Management

    Have schedule variance thresholds

    been established?

    Schedule variance reporting procedures should include:

    Frequency of reporting schedule variances

    Responsibility for explaining schedule variances,

    Variance thresholds that will trigger explanation.

    Schedule

    Management Plan

    Project Schedule

    Management

    Are procedures in place to re-

    establish the schedule baseline?

    Approved change requests can be incorporated into the

    project baselines. A new baseline schedule and/or project

    budget (depending on the nature of the change) isestablished

    Schedule

    Management Plan

    Project Schedule

    Management

    Monitoring the Schedule

    Project Management Checklist

    Planning Activities

    Estimating Activities

    Developing the Schedule

  • 8/3/2019 1717261 Project Management Checklist

    6/11

    ost

    Question Y/N Explanation EPO Template EPO e-book

    Has a project cost estimate been

    prepared?

    Project cost estimates provide senior management

    stakeholders with the financial information to:

    Compare costs of potential projects competing for approval,

    Compare the costs of an initiative to the tangible benefits

    associated with delivery,

    Determine the financial commitment required to complete

    the project,

    Reliable project cost estimates are essential when managing

    the expectations of funding authority stakeholders.

    Project Cost

    Estimate

    Project Estimating &

    Budgeting

    Have estimates been prepared for

    labor, equipment, supplies, expenses

    and financing costs to be incurred by

    the project?

    Project estimates and budgets are both based on the project

    accounts which, in turn, must be tied to the corporate financia

    Chart of Accounts. The structure of the financial chart of

    accounts will vary from one organization to another

    Project Cost

    Estimate, Project

    Budget

    Project Estimating &

    Budgeting

    Have estimating assumptions been

    recorded?

    Estimating assumptions should be documented for reference

    during cost control and to help support the management of

    risks, issues and changes.

    Project Cost

    Estimate

    Project Estimating &

    Budgeting

    Has a budget been established for costracking and control? The project budget, which forms the baseline for cost control,is a time phased distribution of project costs. An estimate

    becomes a budget when costs are allocated to time phases

    (usually months or years).

    Project Budget Project Estimating &Budgeting

    Has a project cost management plan

    been prepared?

    The Cost Management Plan establishes how the project

    estimating, budgeting and cost control processes will occurCost Management

    Plan

    Project Cost

    Management

    Have funding release amounts been

    defined for the project?

    Typically, funding is based on budget amounts and is release

    in increments before money is spent on the project.Cost Management

    Plan

    Project Cost

    Management

    Are earned value performance

    indicators used to report schedule and

    cost variance?

    Using earned value performance measurements, the cost an

    schedule variances are calculated as follows:

    Cost Variance (CV) = Earned Value Actual Costs

    Schedule Variance (SV) = Earned Value Planned Value

    Earned Value

    Performance

    Calculator,

    Performance Report

    View, Project

    Earned Value

    Performance

    Reporting

    Are earned value performance indices

    used to forecast project completion

    costs and variances?

    Earned value calculations provide a means of estimating

    project completion costs based on actual cost and schedule

    performance.

    Earned Value

    Performance

    Calculator,

    Performance Report

    View, Project

    Performance Report

    Earned Value

    Performance

    Reporting

    Are actual costs being recorded on the

    project?

    Actual cost expenditures incurred by the project can be

    captured using timesheets or the organizations cost

    accounting process

    Project Cost

    Tracking

    Project Cost

    Management

    Are procedures in place to re-establish

    the cost baseline?

    Approved change requests can be incorporated into the

    project baselines. A new baseline schedule and/or projectbudget (depending on the nature of the change) is establishe

    Cost Management

    Plan

    Project Cost

    Management

    Project Management Checklist

    Estimating Project Costs

    Establishing the Budget

    Monitoring Project Costs

    EPO Template 2006 Gord Gibben, PMP Version 7.

  • 8/3/2019 1717261 Project Management Checklist

    7/11

    ua ty

    Question Y/N Explanation EPO Template EPO e-book

    Has a Quality Management Plan been

    prepared for the project?

    The Quality Management Plan describes how the project

    management team will manage the quality of deliverables

    produced on the project.

    Quality

    Management Plan

    Quality

    Management

    Are formal quality control techniques

    being applied to the project?

    Quality control is the process of:

    1. Measuring deliverables to determine if quality standards ar

    being met,2. Monitoring results to determine compliance with quality

    standards.

    Control Chart,

    Pareto Diagram

    Quality

    Management

    Are project deliverables subjected to

    formal inspections? Inspections provide a mechanism to detect defects early and

    improve the overall quality of project products. This will, in

    turn, improve productivity and motivate team members to

    produce better quality deliverables

    Inspection Report Software

    Inspections &

    Deliverable Reviews

    Does a formal review and acceptance

    process exist for project deliverables?

    The primary objective of a deliverable review is to gain

    acceptance of a product so that work can proceed on to the

    next phase or step. This acceptance should be based on

    predefined acceptance criteria.

    Deliverable

    Acceptance

    Software

    Inspections &

    Deliverable Reviews

    Are acceptance criteria defined for

    review and testing of projectdeliverables?

    Acceptance criteria describe the conditions required for the

    project deliverables to be accepted by the project sponsor.The acceptance criteria should be prepared early in the

    project; initial acceptance criteria should be included in the

    Project Charter to ensure that the project sponsor and the

    project team are in agreement throughout the project.

    Acceptance Criteria,

    Acceptance TestTracking

    Software Test

    Planning &Execution

    On software development projects, are

    test scripts and test cases defined for

    software testing?

    Test scripts identify the business functions to be tested. Test

    cases should be defined for each business function identified

    in the test script. They are designed to exercise the

    applications response to both good and bad test data

    Test Case Software Test

    Planning &

    Execution

    During software testing, are defects

    recorded and prioritized for resolution?

    Tests can be executed either manually or through the use of

    an automated testing tool that pumps test cases through the

    application. In both cases it is important to record test results

    track defects and assign priorities to deal with defects

    Defect report,

    Defect Tracking Log

    Software Test

    Planning &

    Execution

    Project Management Checklist

    Quality Management

    Inspections

    Testing

    EPO Template 2006 Gord Gibben, PMP Version 7.0

  • 8/3/2019 1717261 Project Management Checklist

    8/11

    uman esources

    Question Y/N Explanation EPO Template EPO e-book

    Have project roles been defined? Assigning the right resources to project activities is critical to

    meeting project objectives. To ensure that everyone

    understands their contribution, resources can be classified

    into a number of roles.

    Project Human

    Resource Plan

    Human Resource

    Planning

    Have the project resource requirement

    been identified?

    Defining resource requirements for a project is one of the mo

    important planning processes. Each project will have uniqueresource requirements and may require a different emphasis

    on project roles.

    Project Human

    Resource Plan

    Human Resource

    Planning

    Have the project resource constraints

    been identified?

    Resource availability constraints such as commitment levels

    dependencies on another project to release the resource

    should be identified and agreed to with the resources

    functional manager

    Project Human

    Resource Plan

    Human Resource

    Planning

    Have project resources been assigned

    to project deliverables?

    Once the project resources have been identified, they can be

    assigned to Work Packages in the Work Breakdown Structur

    (WBS) using a Responsibility Assignment Matrix

    Responsibility

    Assignment Matrix

    Human Resource

    Planning

    Has a project resource training plan

    been prepared?

    Some of the resources assigned to the project will require

    training to perform their roles and produce their deliverables.

    This may occur when:

    New technology is being adopted on a project,

    A software package has been purchased,

    Employees are provided with career development

    opportunities on projects.

    Resource Skills

    Assessment,

    Resource Training

    Plan

    Human Resource

    Planning

    Is a project kick-off event planned? The project team kick-off meeting is the first team meeting to

    be held on a project. The primary purpose of the team kick-of

    meeting is to obtain commitment from team members and ke

    stakeholders.

    Team Kick-off

    Meeting

    Team Management

    Do project team members understand

    their roles on the project and how they

    will work together?

    To encourage constructive behaviors, curtail subversive

    behaviors and guide the team through the development stage

    a Team Charter should be prepared. The Team Charter is an

    agreement that states:

    What the team wants to accomplish,

    Why the team is important,

    How the team will work together to accomplish its goals

    Team Charter Team Development

    Have open communication channels

    been established within the project

    team?

    The groundwork for open communications within the project

    team is laid with the Team Communications PlanTeam

    Communications

    Plan

    Team Management

    Project Management Checklist

    Human Resource Planning

    Managing the Team

    EPO Template 2006 Gord Gibben, PMP Version 7.0

  • 8/3/2019 1717261 Project Management Checklist

    9/11

    Communications

    Question Y/N Explanation EPO Template EPO e-book

    Have project stakeholders been

    identified?

    According to the PMI PMBOK 2000 (section 2.2), project

    stakeholders are:

    Individuals and organizations that are actively involved in

    the project, or whose interests may be positively or

    negatively affected as a result of project execution or project

    completion; they may also exert influence over the projectand its results.

    Stakeholder

    Identification

    Stakeholder

    Identification &

    Analysis

    Has the stake in the project and the

    required commitment from each

    stakeholder been identified?

    Each stakeholders stake in the project will take one of three

    forms:

    1. Providing a product or service which contributes to the

    project objectives.

    2. Receiving or using a product or service delivered by the

    project.

    3. Interested in the project outcome

    The required commitment of each stakeholder is critical to

    the level of planned communication.

    Stakeholder

    Identification,

    Stakeholder Analysis

    Stakeholder

    Identification &

    Analysis

    Have the communication needs of

    each stakeholder been identified?

    The stakeholder communication needs should consider:

    Preferred communication medium,

    Constraints on technology access that may affect

    communications,

    Recommended reporting frequency, Special information needs of each stakeholder.

    Stakeholder

    Identification,

    Stakeholder Analysis

    Stakeholder

    Identification &

    Analysis

    Have the priorities, support and

    influence of key stakeholders been

    identified?

    It is important to determine the schedule, cost and product

    quality priorities and support of key stakeholders.

    Stakeholder influence is their ability to make or influence

    decisions related to project objectives.

    Stakeholder Analysis Stakeholder

    Identification &

    Analysis

    Has a project stakeholder

    communications plan been prepared? The Project Stakeholder Communications Plan describes

    how communication will be accomplished with each

    stakeholder.

    Stakeholder

    Communications

    Plan

    Communications

    Planning

    Has a project meeting plan been

    prepared?

    The Project Meeting Plan identifies (for each type of project

    meeting) the:

    Meeting attendees, Objectives of the meeting,

    Agenda items,

    Logistics such as timeframe, frequency and location,

    Technology medium

    Meeting &

    Presentation Plan

    Communications

    Planning

    Have required project presentations

    been planned?

    The Project Presentation Plan identifies (for each type of

    project presentation) the:

    Presentation audience (individuals or groups),

    Objectives of the presentation (what will be

    accomplished),

    Logistics such as timeframe, frequency, and location,

    Equipment required for the presentation (projectors,

    screens, flipcharts, laptops, etc),

    The presentation type (speech, presentation, video)

    Meeting &

    Presentation Plan

    Communications

    Planning

    Has a project document distribution

    plan been prepared?

    The Project Document Distribution Plan describes:

    Original source of the information (previous project or

    deliverable of current project),

    Project repository location of the deliverable (hyperlink to

    Web URL or directory folder name),

    Distribution schedule (completion date or distribution

    frequency)

    Distribution list (based on stakeholder communication

    plan)

    Document

    Distribution Plan

    Communications

    Planning

    Is access to project documentation

    provided for key stakeholders?

    The Project Stakeholders Communications plan should

    describe procedures for:

    Accessing information between scheduled

    communications,

    Updating and refining the communications plan as the

    project progresses.

    Stakeholder

    Communications

    Plan

    Communications

    Planning

    Are project accomplishments

    reported to stakeholders on a regular

    basis?

    The project progress report is used to report on deliverables

    completed and accomplishments during the reporting

    period. It is also used to predict deliverables that will be

    completed during the next reporting period.

    Project Progress

    Report

    Progress & Status

    Reporting

    Is project schedule and cost status

    reported to stakeholders on a regular

    basis?

    Based on project milestones, status reports provide a

    comparison of actual/forecasted completion dates with

    schedule and cost baselines.

    Project Status

    Report, Status View,

    Status Presentation

    Progress & Status

    Reporting

    Is the status of project issues and

    changes reported to stakeholders on

    a regular basis?

    The status of outstanding (or recently resolved) changes

    and issues should be reported to stakeholders regularly.

    The description of the issue should include the impact on

    schedule, cost and deliverable (where known) and a

    resolution required by date. The description of the changeshould include a business justification for the change and

    the impact on cost and schedule.

    Project Progress

    Report, Project

    Status Report

    Progress & Status

    Reporting

    Is the status of high priority project

    risks reported to stakeholders on a

    regular basis?

    A description of the specific risk and triggering event should

    be provided along with the risk priority (high, medium, or

    low). The consequences that arise from the risk occurrence

    should be described and the approved risk decision

    (prevent, mitigate, monitor, or accept) should be indicated

    Project Progress

    Report, Project

    Status Report

    Progress & Status

    Reporting

    Project Management Checklist

    Stakeholder Identification

    Communications Planning

    Reporting Project Status

  • 8/3/2019 1717261 Project Management Checklist

    10/11

    s

    Question Y/N Explanation EPO Template EPO e-book

    Has a risk management plan been

    prepared for the project?

    The risk management plan (prepared early in the planning

    phase of the project) describes how the four risk managemen

    steps (identification, assessment, response planning and

    monitoring/control) will be performed on the project.

    Risk Management

    Plan

    Risk Management

    Have project risk factors beenidentified?

    Risk factors are categories of risk sources that may have animpact on the project cost, schedule, scope or quality

    objectives. Each project risk factor should be considered

    when identifying potential project risk events.

    Risk IdentificationChecklist

    Risk Identification

    Have potential risk events been

    identified?

    The first step in risk assessment is the identification of risk

    events (discreet occurrences of potential problems). The risk

    description must be complete enough to support risk respons

    decisions and preparation of risk response plans.

    Risk Identification

    Checklist, SWOT

    Analysis

    Risk Identification

    Has an assessment of each potential

    risk event been prepared? For each identified risk, an assessment of its urgency, growth

    probability, and impact should be conducted. Each risk shoul

    be described in sufficient detail to be understood by project

    team members, sponsors and management.

    Risk Assessment,

    Risk Event

    Scenarios

    Risk Assessment &

    Response Planning

    Have high priority project risks been

    identified?The priority of the risk is assigned based on the probability an

    impact assessment. Attention should be focused on high

    probability and high impact risks.

    Risk Assessment,

    Risk Register

    Risk Assessment &

    Response Planning

    Are decision tree techniques used to

    quantify project risks and

    opportunities?

    Decision trees provide a graphical representation of decisions

    and quantify the risks and rewards of these decisions.Decision Tree Decision Analysis

    Has a readiness assessment been

    done to evaluate risks associated with

    one or more alternatives?

    Readiness Assessment footprints are a means to evaluate

    risks associated with one or more alternatives. These risks

    are assessed using eight categories of organizational

    readiness and the corresponding attributes of alternatives

    under consideration.

    Readiness Footprint Readiness

    Assessment

    Has a risk response plan beenprepared for high priority risks? The risk response plan contains preventative actions,corrective actions, risk monitoring and communications plans. Risk Response Plan Risk Assessment &Response Planning

    Have risk response plans evaluated to

    determine their effectiveness?

    Risk response plans often affect more that one risk event.

    Risk responses should be evaluated to determine the affect o

    risk responses on the high priority risk events. The risk

    response evaluation will also help uncover secondary and

    residual risks.

    Risk Response

    Plan, Risk Register

    Risk Assessment &

    Response Planning

    Has a risk monitoring plan been

    implemented for high priority risks?

    The Risk Monitoring plan describes:

    The tracking and control of risks (a continuous process

    involving both the project team and management).

    The preventative action plans to be implemented

    How the status of existing risks and the potential for new

    risks are to be assessed.

    Triggers that alert the project team of a risk occurrence and

    the corrective action to be taken.

    Risk Response

    Plan, Risk Register

    Risk Assessment &

    Response Planning,

    Risk Management

    Project Management Checklist

    Risk Identification

    Risk Assessment

    Risk Response Planning

    EPO Template 2006 Gord Gibben PMP Version 7

  • 8/3/2019 1717261 Project Management Checklist

    11/11

    rocurement

    Question Y/N Explanation EPO Template EPO e-book

    Has a procurement management plan

    been prepared for the project?

    The Procurement Management plan is completed if products

    or services will be purchased for the project from an outside

    supplier. The Procurement Management Plan identifies:

    How services will be procured for the project,

    Procedures for evaluating bids and proposals (including

    approvals required), The types of contracts to be used to procure products or

    services,

    Contract administration and reporting procedures.

    Procurement

    Management Plan

    Procurement

    Planning

    Has a Statement of Work been

    prepared for the procurement items?

    The Statement of Work (SOW) describes the procurement

    item so that prospective sellers can decide if they are capable

    of providing the item and how the work can be undertaken.

    Statement of Work Procurement

    Planning

    Has the project team performed a buy

    vs. build analysis on project

    deliverables?

    Analysis of buy vs. build options is undertaken to determine

    whether the project team can produce the product/service or i

    it should be purchased.

    Procurement

    Management Plan

    Procurement

    Planning

    Have objective evaluation criteria been

    defined for alternative evaluation?

    Proposals should be evaluated against a set of criteria ranked

    as follows:

    Mandatory these are must criteria based on criticalsuccess factors or project objectives.

    Optional these are the want criteria based on

    requirements.

    Alternative Selection Bid & Proposal

    Evaluation

    Is a rational process used to select

    from alternatives and minimize risks

    from selection decisions?

    Project teams frequently must evaluate alternatives and mak

    selection decisions that involve a degree of risk. These

    decisions can be complex; a quantifiable approach is required

    Alternative Selection Bid & Proposal

    Evaluation

    Has a Contract Management Plan bee

    prepared for each contract on the

    project?

    Contract administration is the process of managing the

    contract and the relationship between the buyer and the selle

    The Contract Management Plan describes how a specific

    contract will be administrated during the project

    Contract

    Management Plan

    Contract

    Administration

    Upon completion of the contract, has a

    contract closure report been prepared?

    Contract closure is the process of completing and settling the

    contract, resolving open items and completing contract closurdocumentation.

    Contract Closure

    Report

    Contract

    Administration

    Contract Administration

    Project Management Checklist

    Procurement Planning

    Evaluating Bids & Proposals