11
Basic Factory Physics Prof. Hyun Chung Mar. 17 2015 1 Definitions Manufacturing system: A manufacturing system is an objective-oriented network of processes through which entities flow. 2

17 03 2015 Basic Factory Physics 01

Embed Size (px)

DESCRIPTION

factories phisics

Citation preview

  • Basic Factory PhysicsProf. Hyun Chung

    Mar. 17 2015

    1

    Definitions

    Manufacturing system: A manufacturing system is an objective-oriented network of processes through which entities flow.

    2

  • GT revisited

    Classification: arranging items into groups according to some principles or system where by similar things are brought together by virtue of their similarities and then separated according to their differences

    3

    GT revisited

    Code: A system of symbol (alpha-numeric) used in information processing in which a combination of numbers and letters have a certain meaning

    4

  • Applying GT

    Direct Clustering Algorithm

    Similarity Index

    Dendrogram

    McAuleys single linkage cluster analysis

    5

    Definitions

    Workstation: A workstation is a collection of one or more machines or manual stations that perform (essentially) identical functions.

    Synonyms: station, workcenter, process center

    6

  • Definitions

    Part: A part is a piece of raw material, a component, a subassembly, or an assembly that is worked on at the worstations in a plant

    Synonyms: intermediate product, interim product

    7

    Definitions

    End item: A part that is sold directly to a customer

    Synonyms: product

    The relationship between end items and their constituent parts (raw materials, components, and subassemblies) is maintained in the bill of materials (BOM)

    8

  • Definitions

    Consumable: for the most part, consumables are materials such as bits, chemicals, gases, and lubricants that are used at workstations but do not become part of a product.

    What about glue and solder?

    9

    Definitions

    Routing: A routing describes the sequence of workstations passed through by a part.

    Order: A customer order is a request from a customer for a particular part number, in a particular quantity, to be delivered on a particular time

    10

  • DefinitionsJob: A job refers to a set of physical materials that traverses a routing, along with the associated logical information (e.g., drawings, BOM)

    Every job is triggered by

    an actual customer order

    anticipation of a customer order (forecasted demand)

    11

    Definitions

    Throughput: The average output of a production process (machine, workstation, line, plant) per unit time

    can be defined at various levels

    Synonyms: throughput rate

    12

  • Definitions

    Capacity: An upper limit on the throughput of a production process

    Raw material inventory (RMI): the physical inputs at the start of a production process

    13

    Definitions

    Finished goods inventory (FGI): The stock point at the end of a routing

    used to gather different parts within the plant before further processing or assembly

    14

  • Definitions

    Work in process (WIP): the inventory between the start and end points of production routing

    Synonyms: inventory

    15

    Definitions

    Inventory turns: a commonly used measure of the efficiency with which inventory is used

    Synonyms: turnover ratio = the ratio of throughput to average inventory

    16

  • Definitions

    Cycle time: The cycle time of a given routing is the average time from release of a job at the beginning of the routing until it reaches an inventory point at the end of the routing

    Synonyms: average cycle time, flow time, throughput time, sojourn time

    17

    Definitions

    Lead time: the lead time of a given routing is the time allotted for production of part on that routing

    Synonyms: build time

    18

  • Definitions

    Utilization: the utilization of a workstation is the fraction of time it is not idle for lack of parts.

    includes the fraction of time that workstation is working on parts or has parts waiting and is uable to work on them due to a machine failure, setup, or other detractor.

    19

    Parameters

    Bottleneck rate: the bottleneck rate of the line is the rate (part per unit time or jobs per unit time)of the workstation having the highest long-term utilization

    20

  • Parameters

    Raw process time: the raw process time of the line is the sum of the long-term average process time of each workstation in the line.

    21

    Parameters

    Critical WIP: the critical WIP of the line is the WIP level for which a line with given value of bottleneck rate and raw process time but having no variability achieves maximum throughput with minimum cycle time.

    22