Upload
others
View
0
Download
0
Embed Size (px)
Citation preview
16-18 January 2012 CERN Christian Boccard
Outline
1 - COLD BPM
2 - STRIPLINE COUPLER
3 - WARM BPM
4 - COLLIMATOR BPM
Christian Boccard, (CERN BE/BI)
Cold BPMs
Arc Beam Position Monitor (Arc type+ DS) 864
Special BPM for end of arcs 12
BPM with Rotated Beam Screen 20
Enlarged Aperture BPM 36
Directional Stripline Coupler 8
Combined pick-ups for RF 16
Warm BPMs
Warm LHC BPM adapted for Elliptic shape 16
Enlarged Warm BPM 28
Enlarged Warm BPM with Quick flanges 16
Diam 80 Warm BPM for Roman Pots 12
Warm Directional Stripline Coupler 16
Beam Dumping System
BPM Aperture 80mm for Interlock System 8
BPM Aperture 130mm for Interlock System 8
Other Special BPMs
Trigger for Experiments 8
Long Striplines for Transverse Damper,
Tune & Chromaticity Measurements 14
RF Wideband Transverse pick-up 2
Total 30 Equipment Codes 1092
Dump RF &
BI
Cleaning Cleaning
Buttons …. or Striplines ?
Simple & robust More expensive to build
Removable from outside of chamber More parts: less reliable ?
Less cumbersome Require precise machining
Well adapted to LHC short pulses More sensitive but more heat load
Little effect on longitudinal impedance
Final choice (1996) was Buttons for the arcs (and Directional Couplers around
experimental areas…)
• Our feedtroughs are the only vacuum chamber non welded component ! (use Helicoflex ®
gaskets)
• Choice of feedtrough technology: Glass-metal was preferred to Brazed Ceramic
• Systematic LN2 cycling tests done by contractor
• Tests and pairing at CERN:
• vacuum tests & mechanical data on samples
• AB/BI measures final capacitance on all buttons
• Pairing is done on amplitude response
Brazing
Ceramic
Metallic
Pin
Stainless Steel Body
Glass-Ceramic
Classical Ceramic Seal Glass-Ceramic Seal
Prone to cracks
& fissures
Excellent adhesion
to all surface blemishes
BPM are housed in the
Technical Service Module
We must share this
crowded area.
BPM is also used for
Interconnect and VAC:
responsibility change with
function.
BPM became a Vacuum
component when welded to
the beam screen.(BPMs are
used to feed beam Screen
capillaries with super fluid
helium at 1.9 K )
Then became an
Interconnect component
when welded to the cold
mass.
Exceptions require same
amount of work !
Cooling Tube Feedthroughs
BPM Body
Beam Screen
BPM Body
Cooling Tube Feedthroughs
Button Electrodes Drift tube
Cooling Tube Feedthroughs
BPM Body
Beam Screen
BPM Body
Cooling Tube Feedthroughs
Button Electrodes Drift tube
Tooling development of the ‘monolithic’ first BPM for Arcs was lengthly and costly.
Later the design of Enlarged cold BPM and Coupler evolved to a modular design basis.
To standardize components and tooling.
Re-use of VAC Plug-In module from dipoles
Cooling Tube Feedthrough Module
BPMY Support
BPMY Body
Cold Bore
Beam Screen Enlarged cold BPM
Stripline Coupler
• Tight mechanical tolerances: nice but…
• Should be maintained during production
• Machining cost is proportional
• 3 axis Dimensional checks are also expensive
• Help to design: ANSYS 3D analysis of temperature or mechanical constraints.
• Cold Material: Specify forged austenitic stainless steel of type AISI 316LN
• ~ 60 leaks found in LHC (not on BPMs) due to macro-inclusion in material. Can affect thickness up to some milimeters.
• (CERN specification 1001-Ed. 3-02.08.1999)
• Electroplated inner copper layer of the BPM body is 100 um 20 um (for longitudinal impedance)
• witness samples are required to assure clean material and Copper plating quality:, e.g. adherence, blisters.
• nickel not allowed, use gold strike.
• Welds should be re-qualified regularly during production.
from A. Gerardin
Deformation contours due to Helicoflex washers surface pressure
• Insulator Spec: UHV, cryo temp, radiations, losses -> Ultem
• Coupler Feedthroughs: same technology as buttons
• Gold - Rhodium Sliding contact do not stick at cryo temp
• Electron Beam welding of a 2mm pin on washer
• Electrode gap is not easy to trim
• Achieved directivity : 24 dB at 70MHz -> not enough
• 50um error from cross-talk for 25ns spaced beam
• False triggers on electronic.
• Cryo tests to measure contact resistance
Strong specification: – The cables must be cryogenically compatible, radiation
resistant, mechanically preformed , have low heat leak and VSWR.
– In addition the cable must be electrically stable when subjected to the above mentioned radiation, flexing, and temperature gradients.
– Leading to the choice of silicon dioxide foam (SIO2) dielectric
– Contract awarded for 4500 units in 2001
– electrical length difference less than 10ps for the 4 cables of each BPM.
– Gold reference used to ease production and logistic
Integration is a challenge
– First prototype was not mountable in SSS !
> new design produced
– Forming not as accurate as specified
Additional Configurations
– Design of 5 different configurations required for other SSS types
– cabling of BPMS in Q2 is done in the tunnel during interconnection
– Connector nuts are locked by twisted wires
Taylor Hobson sphere
Support of fiducial
Magnetic centering
• Forms part of a Work Package Sub-contracted for the 480 SSS magnets
• Procedure – Weld beam screen to BPM body – Select pairs of buttons for mounting – Mount button feedthroughs – Perform leak test of assembly – Insert BPM/beam screen assembly in magnet – Spot weld BPM to support – Measure and adjust position and tilt of BPM – Weld BPM to support – Measure position and tilt of BPM – Install and connect cryo cables – Mount warm feedthrough on cryostat – Perform electrical test of BPM system
• Worries – Sub-contracting started slowly – Technology transfer repeated many times – Magnet does not wait: Non Conformities to be treated rapidly.
• Carefully design and integrate your instrument
• Then do your best to make reality close to that …
• Fiducialize the BPM on their supports
• Helicoflex aluminium gaskets proved to be leaking above temperature of 280 C. Conflat more adapted to this case.
• Bakeout temperature of BPM was then limited to 200 C to avoid any problem (lower temperature is compensated by a longer time)
• But hard to control this, errors are not admitted. the colour of stainless steel after bakeout reveal the reached temperature :
– No change <200
– Yellow 220
– Brown 260
– Purple 280
– Blue 300
• Budget – Cryo cables budget was under estimated
• Design
– Reliability was one of the important parameter taken in account during the design phase leading to technology and material choices.
– Experience from previous machine at CERN and similar machines proved to be extremely valuable
• Specification
– Many of the issues related to material could have been avoided if treated at the project level
• Integration – We learn all along the project. “What I would change if I would do it once again”
• Construction & Installation – Everything was slower then planned due to the large scale of the project
• Operation
– No leaks except overheated BPMs – Not enough directivity from couplers to avoid false triggers.
First development of a variable aperture
BPM for the LHC collimation system.
0.2 mm Left jaw (Carbon
example)
Graphite or
Tungsten
Material jaw
The LHC Beam Collimator
6s
LHC Collimators must clean the
beam halo at given positions so that
the rest of the machine is protected.
To this purpose collimators insert
absorbing materials into the vacuum
pipe.
Absorbing jaws are movable and
can be placed as close as 0.25 mm to
the circulating beam !
Nominal distance at 7 TeV: ≥ 1 mm.
80 kg TNT
High stored energy : 360 MJ at 7TeV !
The LHC collimation was conceived as a staged
system:
Phase I collimators:
• Designed to ensure maximum robustness against
abnormal beam losses in operating conditions.
Phase II collimators:
• Complement phase I and able to reach nominal intensity
and energy.
Constraints:
• Improve collimation efficiency.
• Keep low longitudinal impedance
• gain factor ≥10 in set-up time
Phase I jaw
Phase II
jaw
Standard setup method relies on centering
collimator jaws by detecting beam loss.
• Procedure is lengthy and can only be
performed with pilot fill.
• Big worries about risks, reproducibility,
systematic effects and time lost for physics.
The integration of pick-ups into jaws will
allow:
• deterministic centering of jaws around
circulating beam.
• Improvement in set-up time.
• Continuously follow orbit drifts,
• Allow tighter collimator settings, …
High precision (<10 um) and stability
(averaged, not bunch by bunch)
And:
• Protect components from accident cases.
• Withstand a bakeout temperature of 250 º C
during 48H.
• Operate under strong radiation (200 Mgy/y).
• Maintain Ultra High Vacuum.
• Very accurate geometric stability .
• Low-Z material.
Center pair of
buttons (in case ..)
button in the tapering
Prototype build with the implementation of 4 buttons in Jaws
Graphite
Cu jaw
support
Ineffectiveness of center pair of buttons on
closed jaw operation
Based on experience gained with demonstrator -> Implementation of 2 BPMs
Cross-section of jaw tapering.
fine positioning
system
BPM housing
cooling circuits
molybdenum back-stiffener
Embedded BPM
GlidCop®
absorbing material
• Flat surface for housing the button in recess
of the beam
• Less smooth transition.
• longitudinal trapped modes are mainly
generated by the transition region.
Phase I jaw tapering Tapering with button Phase II
Key component: the RF cables
The coaxial cables needed should:
• Be small, robust and flexible enough to
follow the jaw motion during the thousand of
cycles expected.
• Be vacuum compatible (choice of materials,
reliability, cleanliness and outgassing rate)
Only SiO2 Cables meet the
specification ! • They also provide exceptionally low
hysteresis vs temperature and motion, with
phase and loss values returning to the same
values.
But:
• SiO2 dielectric is Hydrophilic and cables are
backfilled with Neon gas (chosen for low
molecular mass).
cable routing up to the button fixture.
-> Issue in case of leak in the beam vacuum !
BPM Cables
But if vacuum degrades we stop LHC !
• Stress simulations show that
they should survive at least 30
000 cycles.
• Cable failure means no BPM
anymore because cover tank is
welded.
Agreement of measured non
linearities with simulations results.
No noise seen due to
upstream scraping.
correlation between the centres
measured with the in-jaw BPMs and
the BLM dependent method.
Adjustable
Stand
Collimator
assembly
Embedded BPMs Collimators:
• Mission to replace all moveable collimators in
the Ring with new collimators equipped with
BPM
• Start production in 2012 of 20 tertiary collimators
(TCTP) with installation of 8 of them during LS1.
• Production of 2 Secondary collimators (TCSP)
for point 6.
• Baseline for other collimators, and ideas for
Beam Beam Long Range Compensator.
• Development of a calibration system.
• Tertiary Collimators with Embedded
BPMs will be based on Phase II concept.
• BPM design is based on experience and
good results gained with demonstrator
installed in the SPS.
• Should achieve requested precision and
stability performance.
From demonstrator installed in the SPS to… Tertiary Collimators with Embedded BPMs