Upload
shah-aizat
View
224
Download
1
Embed Size (px)
Citation preview
7/26/2019 153691706 Relay Coordination Guidelines
1/16
Over current & Earth fault relay co-ordination
Over current fault relay co-ordination:
Let us consider one small section of Aditya cement plant,Sambhupura and let
us see how over current and earth relay co-ordination is done on it.
Over Current Relay Co-ordination Guidelines:
7/26/2019 153691706 Relay Coordination Guidelines
2/16
1. Over current relays are co-ordinated from load end till the source. Generally
the operating time of relay at load end is assumed to be at .! seconds and
considering this assumption operating time of bac" up relays are calculated.
#. $iscrimination time for relays on series element is considered as .% and
for non-series elements discrimination time is considered as .&.
&. 'or calculation of ()S of upstream*bac"up relay, the downstream relay
having higher operating time is considered.
!. Generally it is preferable to have the plug setting +amperes of upstream
relays to be eual or little more than plug setting +amperes of downstream
relays.
%. nstantaneous settings for upstream relays are provided so as to provide
protection against the close in faults occurring at the respective buses
such that respective relays trip much before the ma/imum fault current flows
through them. nstantaneous settings should be provided such that they
should have a discrimination of about .& second with thermal curve of theirbac" up relay.
0. ut for transformer primary relays instantaneous setting should be set such
that the relays don2t trip for charging current but protect the transformer
against close in faults.
3. (ime grading is an important criterion for instantaneous protection. (he
relays should be time graded in such a way that bac" up relays trip
instantaneously with certain standard time delay, such that for any fault at
lower stream, the upstream relays don2t undergo cascaded tripping.
7/26/2019 153691706 Relay Coordination Guidelines
3/16
4. As per the standard convention, instantaneous time delay of .% seconds
is provided for relays at e/treme load end and at transformer primary.
5. n case of phase overcurrent protection generally an instantaneous time
delay of .# seconds should e/ist between primary and it2s bac"up.
1.n case where condition of critical clearing time needs to be satisfied, there
the instantaneous time delay is "ept as .1% seconds between two relays
acting as primary and bac" up.
11. f there is a fault at one voltage level then the relay at that voltage level
should trip instantaneously and it2s bac" up at a different voltage level
should trip thermally.
1#.t is always advisable to run co-ordination 6 simulation in )i-power, to chec"
whether the relays operate in co-ordination with proper time discrimination.
7onsidering the above guidelines let us proceed to perform the overcurrentrelay co-ordination of the section considered above.
Relay.No.104:
7/26/2019 153691706 Relay Coordination Guidelines
4/16
Let the operating time of relay.8o.1! be .! seconds
(he three-phase fault current viewed by relay no. 1! is &phf1! 9 #%05&.&3 A
:lug settingof relay.8o.1! in amperes 9 &0 A.
(herefore ()S of relay 1! is ()S 9 .!;*.1!9.11
Since the ()S range of ?@ %#1 relay is in range of .% = 1 in steps of .%
Bence above calculated ()S is appro/imated to .1%
8ow as per the appro/imated ()S, recalculated operating time is C
(op?1!2 9 .1%;.1!* 9 .%#&4 sec.
Relay.No.100:
Since relay.8o.1 is in the same series element as relay no. 1! hence
discrimination time between them is .% sec.
Bence remote operating time for relay no. 1 is (op?1remote9 .%#&4 D .% 9 .%3 sec.
?emote fault current viewed by relay no. 1 is remote9 53&.1# A
:lug setting of relay no.1 is 1! A
(herefore ()S of relay 1 9 .%3&4;*.1! 9 .10
ut as step value is .% hence appro/imated ()S of relay no.1 is .#
7lose in fault current viewed by relay no.1 is &phf19 &1104.%3 A
Bence close in operating time of relay no. 1 is
(op?19.#;.1!* 9 .!%&! sec.
Note:f )9 E #, then
) 9 # +eyond )9#, relay is considered to be saturated. Bence in the above
calculation as ) 9 +&1104.%3*1!E# hence )9# has been considered.
@/actly the calculations for relay no. 1% and ?elay.8o 11 are made and
results are same as above.
7/26/2019 153691706 Relay Coordination Guidelines
5/16
Let the operating time of relay.8o.3 be .50% sec +7alculated similarly as
above.
And the operating time of relay.8o.00 be 1.55 sec. +7alculated similarly as
above.
Relay.No.6:
'or calculation of operating time for relay no.0, operating time of relay no.1
and relay no. 11 is considered and out of them whichever2s operating time is
higher that operating time is considered for calculation of ()S of the relay no.0.
but as relay.8o.00 has an higher operating time of 1.55 sec hence operating time ofrelay. 8o.00 is considered for ()S calculation of ?0.
Bence operating time of relay ?09operating time of relay.8o.00Ddiscrimination time.
Operating time of relay ?0, (op?0 9 1.55 D .& 9 #.#5 sec.
7lose in fault current viewed by relay no.0 is &phf09 %#0!.& A
:lug setting of relay ?0 in amperes 914 A
Bence ()S of relay ?0 9 #.#5;*.1! 9.&%%
Appro/imating the above result we get ()S 9.!So recalculating the operating time as per new ()S,
(op029.!;.1!* 9 #.%4 sec.
Relay.No.:
Operating time of relay.8o.% for remote fault is (op%remote9 #.%4D.% 9 #.0& sec
?emote fault current as viewed by relay no.% 9 %#0!.& A
:lug setting of relay no.% in amperes 9 14 A
()S of relay no. % 9 #.0&;*.1! 9 .!1
Appro/imating the ()S as per the step value of ?@ %#1 we get ()S9.!%
?emote operating time as per appro/imated ()S
(op%remote2 9 .!%;.1!* 9#.5 sec
7/26/2019 153691706 Relay Coordination Guidelines
6/16
7lose in fault current &phf% 9 4410.4 A
7lose in operating time of relay no.% is given asC
(op?% 9 .!%;.1!* 91.5% sec.
!nstantaneous "ettin# :
Relay.No. 104: $%eeder
7lose in fault current viewed by relay.8o.1! is &phf1!9 #%35&.3 A
7( ?atio 9 !*1
(herefore pEE is set such that the relay trips instantaneously before the
ma/imum fault current and has a discrimination of .& with thermal curve of it2s
bac" up relay.
Bence if relay is set at &F then the relay trips at 1# A which is much
before the ma/imum fault current and discrimination of .& is maintained with
the thermal curve of it2s bac" up relay.
'actor to be entered in )i-power database 9 & +for relays at load end directly
the instantaneous factor is entered in database
nstantaneous time delay tpEE 9 .% sec
Relay.No. 100:$'ransfor(er )ri(ary
?ated current of relay.8o. 1 , rated 9 1&1.# A
?emote fault current 9 53&.1# A
7harging current 9 1;?ated current 9 1&1# A
ac" up current 91.&;?ated current 9 1#0%.0 A
Since !char#* !+ac,, hence charg is considered for instantaneous calculation
nstantaneous setting, pEE 9 charg*7( ratio 9 1&1#*#9 0.%0
7/26/2019 153691706 Relay Coordination Guidelines
7/16
Appro/imating the above value to nearest whole number we get pEE 9 3 times
or 3F.(he factor to be entered in database 9 3 / 7( ratio*?emote fault
current 9 1.!!
nstantaneous phase time setting 9 .% sec.
nstantaneous setting for ?elay no. 1% is e/actly same as that of relay
no.1! 6 instantaneous setting for ?elay no. 11 is e/actly same as that of
relay no.1.
Relay.No.6:$%eeder
7lose in fault current viewed by relay no.1! is &phf1!9 %#0!.& A
7( ?atio 9 #*1
(herefore pEE is set such that the relay trips instantaneously before the
ma/imum fault current and has a discrimination of .& with thermal curve of it2s
bac" up relay.
Bence if relay is set at 1%F then the relay trips at & A which is much
before the ma/imum fault current and discrimination of .& is maintained with
the thermal curve of it2s bac" up relay.
'actor to be entered in )i- :ower database 9 &*%#0!.& 9 .%3. nstantaneous phase time setting for relay.8o.0 is done ta"ing the higher
instantaneous time setting of relays connected to its outgoing feeder and then
adding an instantaneous time delay of .1% sec to it.
Since the instantaneous phase time setting for relay. 8o 3 is .&% sec, hence
the instantaneous phase setting of relay.8o.0 is .% sec+.&% secD .1% sec.
Relay.No. :$'ransfor(er )ri(ary
?ated current of relay.8o.%% is rated 9 134!.% A
?emote fault current 9%#0!.& A
7harging current, charg9 1;?ated current 9 134!% A
ac" up current, ac" 91.&; ?emote fault current 9 04!&.%5 A
7/26/2019 153691706 Relay Coordination Guidelines
8/16
Since charg E ac" , hence charg is considered for instantaneous
calculation
nstantaneous setting, pEE 9 charg*7( ratio 9 134!%*# 9 4.5
Appro/imating the above value to nearest whole number we get pEE 9 5
times or 5F.
(he factor to be entered in )i- :ower database 9 5 / 7( ratio*?emote fault
current 9 &.!1
nstantaneous phase time setting 9 .% sec
(he :hase co-ordination curves are given in the figure 1.1 below.
7/26/2019 153691706 Relay Coordination Guidelines
9/16
%i#ure 1.1. )hase Co-ordination curves
7/26/2019 153691706 Relay Coordination Guidelines
10/16
Earth %ault Relay Co-ordination :
Earth Relay Co-ordination Guidelines:
7/26/2019 153691706 Relay Coordination Guidelines
11/16
1. n case of single line to ground fault the plug setting of the relay depends upon
the single line to ground fault current viewed by the relay and the setting range of
the relay used. Generally plug setting of 1F - #F is set for the relay, as an
unbalance of about 1F always e/ists in the system.
#. ?elay used should be sensitive enough to operate for an single line to ground
fault occurring in it2s one but should not trip for too low SLG current.
&. (he :lug setting should be provided such that the plug setting current+amperes
of upstream relays should be either eual to or greater than plug setting current
+amperes of the downstream relays.
!. 'or transformers having delta-star configuration or vice versa, the relay located
at transformer primary can2t be co-ordinated with relay located at transformer
secondary because delta windings isolate the fault current from the healthy side
and hence SLG fault current doesn2t find a path to flow to the other side. n such a
case relay located on star side should be set so as to only operate for close in fault
current.
%. n case of earth overcurrent protection generally an instantaneous time delay
of .# seconds should e/ist between primary and it2s bac"up.
?est all other guidelines are similar to that of over current fault co-ordination
8ow let us see how earth relay co-ordination is set using the above guidelines.
Relay.No. 104:
7/26/2019 153691706 Relay Coordination Guidelines
12/16
(he single line to fault current viewed by relay.8o.1! is, slgf1! 9 #44&&.& A
(he plug setting 9 %F of 7( ratio 9 .%;!9 # A
Let the relay operating time be 9.! sec
(herefore ()S of relay.8o.1! 9 .!; 9 .130
Bere )9#
Appro/imating the ()S as per step value of ?@ %#1 is 9 .#
So new operating time as per the appro/imated ()S
(opSLG1!9 .#;.1!* 9.!%& sec
As relay. 8o 1 is on delta side of transformer hence no co-ordination is not
possible with relay.8o 1!.
Relay.No. 100:
(he single line to fault current viewed by relay.8o.1! is, slgf1! 9 !00.0 A
(he plug setting 9 1F of 7( ratio 9 .1;#9 # A
Let the relay operating time for close in fault be 9.% sec
(herefore ()S of relay.8o.1! 9 .%;*.1! 9 .#
Appro/imating the ()S as per step value of ?@ %#1 9 .%
8ew operating time as per appro/imated ()S is given as
(opSLG1 9 .%;.1!* 9.11& sec
(he operating time of relay.8o 3 is (opSLG3 9 .35 sec +calculated similarly as
above.
Similarly operating time of relay.8o 00 is (opSLG3 9 .!# sec +calculated similarly as
above.
Relay.No. 6:
7/26/2019 153691706 Relay Coordination Guidelines
13/16
'or calculating the operating time of relay.8o.0 ,the highest operating time of the
relay, among the relays, connected to its outgoing feeder is considered. Bere the
operating time of relay.8o 3 is considered for calculation of ()S of relay.8o 0 is
considered.
(opSLG0 9 .35 D .& 9 1.5 sec
Single line to ground fault current at relay.8o 0,SLGf0 9 0!# A
:lug setting 9 1F of 7( ratio 9 # A
Bence ()S of relay.8o 0 is 9 1.5; * .1! 9 .14!
Appro/imating the ()S as per steps provided in ?@ %#1,we get ()S9.#
As per the new ()S, the operating time of relay.8o.0,
(opSLG0 9.#;.1! * 9 1.140 sec,
Relay.No.:
?elay.8o.% can2t be co-ordinated with real.8o.0 as relay.8o % is on delta side.
ut however it should operate for any close in fault.
Single line to ground fault current at relay.8o.%, SLGf%9 1 A
:lug setting 9 1F of 7( ratio 9.1;#9 # A
Let the operating time for the close in fault be (opSLG%
9 .% sec.
Bence ()S 9 .%;*.1! 9 .1
Appro/imating the ()S as per step value we get new ()S 9 .%
Operating time as per appro/imated ()S 9 .%;.1! * 9 .#1 sec.
!nstantaneous settin# :
Relay.No.104:$%eeder
SLG 'ault current viewed by relay.8o.1!, slgf1! 9 #44&&.& A nstantaneous earth setting, oEE 9 &F of 7( ratio 9 &;! 91# A
nstantaneous earth time setting, (oEE 9.% sec
nstantaneous 'actor to be entered in database 9& +load end and delta side of
transformer directly instantaneous factor is entered in )i-power database
7/26/2019 153691706 Relay Coordination Guidelines
14/16
Relay.No.100:$'ransfor(er ri(ary
SLG 'ault current viewed by relay.8o.1!, slgf1 9 !00.0 A
nstantaneous earth setting, oEE 9 %F of 7( ratio 9 %;# 91 A
nstantaneous earth time setting, (oEE 9.% sec nstantaneous 'actor to be entered in database 9 % +load end and delta side of
transformer directly instantaneous factor is entered in )i-power database
Relay.No.6:$%eeder
SLG 'ault current viewed by relay.8o.1!, slgf0 9 0!# A
nstantaneous earth setting, oEE 9 1%F of 7( ratio 9 .1%;# 9& A
nstantaneous phase time setting for relay.8o.0 is done ta"ing the higher instantaneous time setting of relay connected to out going feeders and then adding a time delay of
.# seconds tom it.
nstantaneous earth time setting, (oEE 9 nstantaneous earth time setting of relay.8o.3
D .# sec 9.!% D .# 9 .0% sec
nstantaneous 'actor to be entered in database 9 &*0!# 9 .!03
Relay.No.:$'ransfor(er )ri(ary
SLG 'ault current viewed by relay.8o.1!, slgf% 9 1 A
As per the range of instantaneous earth setting provided by ?@) %!& + .1 = 1#
/ n , relay.8o.% is not sufficient to provide instantaneous earth protection. (he
lowest instantaneous current that can be set is .1;# 9 # A, but the fault
current is 1 A, hence relay is unable to operate instantaneously as relay would
only be able to sense current above # A.
7/26/2019 153691706 Relay Coordination Guidelines
15/16
%i#ure 1.. Earth relay co-ordination curves
7/26/2019 153691706 Relay Coordination Guidelines
16/16
%i#ure 1.4. Earth relay co-ordination curves