    No Fear Implementation

    Presented By: Mario Sanvitale

    1st

    Milestone Limited

    21 September 2011

  • 8/13/2019 15.30 - Mario Sanvitale

    2/23

    2

    Safe Harbor Statement

    The following presentation represents the opinion of

    Milestone and the Presenter.

    It is intended for information

    purposes only.

    It is not a commitment on behalf of Oracle and cannot

    be incorporated into any contract directly with Oracle.

  • 8/13/2019 15.30 - Mario Sanvitale

    3/23

    3

    Background

    Oracle Primavera is the market leading application for Project Planning and

    Scheduling in the many industries.

    The vast majority of participants in these organisations would like to use

    Primavera to manage projects both for themselves and on behalf of theirclients.

    Key to successful implementation is early, visible, meaningful output to

    allow quick gains to be achieved.

  • 8/13/2019 15.30 - Mario Sanvitale

    4/23

    4

    Why Milestone?

    Milestone has been implementing Primavera solutions for over 16 years

    During this time we have been successful in all business sizes, from very small to

    the largest.

    We have used various Implementation Methodologies to maximise the benefit and

    minimise the risk .

    Typically, these follow a standard process and format . . . .

  • 8/13/2019 15.30 - Mario Sanvitale

    5/23

    5

    Implementation Methodologies

    Initiatio

    nand

    PlanningInit

    iationand

    Planning

    Executio

    nand

    Control

    Executio

    nand

    Control

    CloseOu

    t

    CloseOu

    t

    Kick

    off

    Proj

    ectCha

    rter

    Rea

    dinessA

    ssessm

    ent

    Docume

    nt(RAD)

    Readin

    ess

    Assess

    ment

    Design

    Prototy

    pe&

    Test

    11

    Pilot

    Rollou

    t

    Assess

    ment

    Kickoff

    Kickoff

    Prove

    Prove--

    outoutGoL

    iveGoL

    iveMai

    ntain

    Mainta

    in

    Inst

    allation

    Cor

    eTeam

    Training

    Des

    ignDocu

    ment

    Prot

    otypeD

    atabase

    Fun

    ctionalT

    esting

    Loa

    dTesting

    Pilo

    tTeam

    Training

    andMe

    ntoring

    with

    lived

    ata

    Productio

    nServer

    Configu

    ration

    Wor

    kstationCo

    nfigurat

    ion

    Roll

    -outTraining&

    Mentor

    ing

    Les

    sonsLea

    rned

    Fina

    lAssess

    ment

    Report

    Servic

    ePack

    age

    ClientD

    elivera

    bles

    22

    33

    44

    55

    66

    Initiatio

    nand

    PlanningInit

    iationand

    PlanningInit

    iationand

    PlanningInit

    iationand

    Planning

    Executio

    nand

    Control

    Executio

    nand

    Control

    Executio

    nand

    Control

    Executio

    nand

    Control

    CloseOu

    t

    CloseOu

    t

    CloseOu

    t

    CloseOu

    t

    Kick

    off

    Proj

    ectCha

    rter

    Rea

    dinessA

    ssessm

    ent

    Docume

    nt(RAD)

    Readin

    ess

    Assess

    ment

    Design

    Prototy

    pe&

    Test

    11

    Pilot

    Rollou

    t

    Assess

    ment

    Kickoff

    Kickoff

    Prove

    Prove--

    outoutGoL

    iveGoL

    iveMai

    ntain

    Mainta

    in

    Kickoff

    Kickoff

    Prove

    Prove--

    outoutGoL

    iveGoL

    iveMai

    ntain

    Mainta

    in

    Inst

    allation

    Cor

    eTeam

    Training

    Des

    ignDocu

    ment

    Prot

    otypeD

    atabase

    Fun

    ctionalT

    esting

    Loa

    dTesting

    Pilo

    tTeam

    Training

    andMe

    ntoring

    with

    lived

    ata

    Productio

    nServer

    Configu

    ration

    Wor

    kstationCo

    nfigurat

    ion

    Roll

    -outTraining&

    Mentor

    ing

    Les

    sonsLea

    rned

    Fina

    lAssess

    ment

    Report

    Servic

    ePack

    age

    ClientD

    elivera

    bles

    22

    33

    44

    55

    66

    1.ReadinessAssessment

    1.Readiness

    1.ReadinessAssessment

    Assessment

    2.Design

    2.Design2.Design

    3.PrototypeandTest

    3.Prototypeand

    3.PrototypeandTestTest

    4.Pilot

    4.Pilot4.Pilot

    5.Rollout

    5.Rollout5.Rollout

    6.Assessment

    6.Assessment

    6.Assessment

    Step

    Initiation/Planning

    Initiation/Planning

    Execution/Control

    Execution/Control

    Closeout

    Closeout

    1. ReadinessAssessment

    1. Readiness1. ReadinessAssessmentAssessment

    2. Design

    2. Design2. Design

    3. Prototype andTest

    3. Prototype and3. Prototype andTestTest

    4. Pilot

    4. Pilot4. Pilot

    5. Rollout

    5. Rollout5. Rollout

    6. Assessment

    6. Assessment6. Assessment

    Kickoff, Project Charter,Readiness Assessment

    Document (RAD)

    Step Major Components

    Kickoff Prove-out Go Live Maintain

    Installation, Core

    Team Training,Design Document

    Prototype Database,

    Functional Testing,Load Testing

    Pilot Team Training

    and Mentoring with

    Livedata

    Production Server Configuration,Workstation Configuration, Roll-out Training & Mentoring

    Lessons Learned,

    Production Surveillanceand Support

  • 8/13/2019 15.30 - Mario Sanvitale

    6/23

    6

    Implementation Methodologies

    Lets look at a typical process in more detail:

  • 8/13/2019 15.30 - Mario Sanvitale

    7/23

    7

    Implementation Methodologies

    Initiation andPlanning

    Initiation andPlanning

    Execution andControl

    Execution andControl

    Close OutClose Out

    Kickoff

    Project Charter

    Readiness AssessmentDocument (RAD)

    ReadinessAssessment

    Design

    Prototype &Test

    11

    Pilot

    Rollout

    Assessment

    KickoffKickoff ProveProve --outout Go LiveGo Live MaintainMaintain

    Installation

    Core Team Training

    Design Document

    Prototype Database

    Functional Testing

    Load Testing

    Pilot Team Trainingand Mentoring withlive data

    Production Server Configuration

    Workstation Configuration

    Roll-out Training & Mentoring

    Lessons Learned

    Final AssessmentReport

    Service Package Client Deliverables

    22

    33

    44

    55

    66

    Initiation andPlanning

    Initiation andPlanning

    Initiation andPlanning

    Initiation andPlanning

    Execution andControl

    Execution andControl

    Execution andControl

    Execution andControl

    Close OutClose OutClose OutClose Out

    Kickoff

    Project Charter

    Readiness AssessmentDocument (RAD)

    ReadinessAssessment

    Design

    Prototype &Test

    11

    Pilot

    Rollout

    Assessment

    KickoffKickoff ProveProve --outout Go LiveGo Live MaintainMaintainKickoffKickoff ProveProve --outout Go LiveGo Live MaintainMaintain

    Installation

    Core Team Training

    Design Document

    Prototype Database

    Functional Testing

    Load Testing

    Pilot Team Trainingand Mentoring withlive data

    Production Server Configuration

    Workstation Configuration

    Roll-out Training & Mentoring

    Lessons Learned

    Final AssessmentReport

    Service Package Client Deliverables

    22

    33

    44

    55

    66

  • 8/13/2019 15.30 - Mario Sanvitale

    8/23

    8

    What you need for a full implementation

    Have support from all impacted business units at all levels

    Fully understand criteria for success

    Articulate these at early stage

    Know what existing internal processes are to be incorporated

    Have available resources to implement system

    Make available IT resources

    Culturally accept business disruption

  • 8/13/2019 15.30 - Mario Sanvitale

    9/23

    9

    Implementation Methodologies

    . . . . . For some this approach is appropriate, BUT

    For many implementations this will not succeed.

    This may be due to size, resources, budgets, maturity, ormany other factors.

    The reason starts right at the beginning with

    Differences in Understanding:

  • 8/13/2019 15.30 - Mario Sanvitale

    10/23

    10

    Differences in Understanding

    Customer

    Knows how his business operates fully (hopefully!)

    Doesnt have the same deep understanding of the solution as the supplier

    Has an expectation of an end result

    Supplier

    Knows his solution fully (again hopefully!)

    Doesnt have same deep understanding of the business as the customer

    Has an expectation of an end result

  • 8/13/2019 15.30 - Mario Sanvitale

    11/23

    11

    . . . . . . so what?

    During implementation understanding grows on both sides to bring:

    Scope creep

    Changes to expectations, in functions and output

    Leading to revised deliverables

    More resources needed prior to go live

    Altered cultural impact

    New IT requirements

    Longer deployment schedule

    . . . . . delayed benefits

    . . . . . . . . . . . . . . . . . . . added costs

    . . . . . . . . . . . . . . . . . . . . . . . . . . . . . reduced enthusiasm

  • 8/13/2019 15.30 - Mario Sanvitale

    12/23

    12

    How can we do this better?

    What we really want is a solution that is:

    Easy to implement

    Quick to implement

    Minimises business disruptionDelivers productivity early

    Delivers decision support output early

    Acts as a knowledge-base in itself

    Is capable of expansion

  • 8/13/2019 15.30 - Mario Sanvitale

    13/23

    13

    What can be done?

    Recognising this, we decided to address these needs

    We had the experience, and had been witness to some of the

    effects!

    The solution we developed was presented to Oracle

    It was accepted as an Oracle Accelerate product

    Milestone was awarded Oracle Accelerate Specialization

    The first Oracle Primavera Partner in the world to achieve this

  • 8/13/2019 15.30 - Mario Sanvitale

    14/23

    14

    Milestones Solution

    Rapid Results, which includes:

    Modular solution (basic scheduling, cost, resource)

    Fixed price by module

    Variable to meet business needs:

    Schedule driven (eg Capital Projects, Construction, etc)

    Resource-driven (eg IT projects)

    Pre configured software

    Ready to use templates

    Ready to use reports and dashboards

    Solution focused training

    Optional Hosting via LoadSpringa fully secure service to reduce costs,

    overheads and IT support requirements

  • 8/13/2019 15.30 - Mario Sanvitale

    15/23

    15

    Typical Project Lifecycle

  • 8/13/2019 15.30 - Mario Sanvitale

    16/23

    16

    Key Benefits

    Fully Scalable Solution

    Minimal Business Disruption

    Produces industry-standard output from initial installation

    Avoids infrastructure delays

    Identify future road map with genuine understanding on both sides

    . . . . . and not just how to use the standard system effectively . . . .

  • 8/13/2019 15.30 - Mario Sanvitale

    17/23

    17

    Future Integration: Oracle Solutions

    Primavera plug-in additional modules

    Business Process Modelling, User Productivity Kit, BI Publisher, Universal Content Management

    Primavera Risk AnalysisRisk management and simulation

    Primavera TimesheetsProgress reporting

    Primavera P6 AnalyticsExtended reporting facilities

    Primavera Contract ManagerCost management and document

    control

    AutoVueDocument viewing and collaboration

    InspireSAP Integration

  • 8/13/2019 15.30 - Mario Sanvitale

    18/23

    18

    Optional Training and Consultancy

    Certificated Oracle University courses

    Specialist training using Milestone trainers

    Oracle User Productivity Kit

    Expert consultancy

    Custom integration with other applications

    To enable continuous improvement and the on-going development of your system Milestones

    Professional Service Team can support you via a number of consulting and training options.

  • 8/13/2019 15.30 - Mario Sanvitale

    19/23

    19

    Future Integration: Other Applications

    To achieve and benefit from the next level of efficiency gains, review the

    data flow between project controls software (Primavera) and other businesscritical applications, such as: Estimating and Cost Management (e.g. Hard Dollar)

    Other ERP/Financial Systems (e.g. SAP, Maximo)

    Third party or in-house time recording (e.g. eTimeMachine)

    Other reporting systems (e.g. Business Objects, Cognos, etc)

  • 8/13/2019 15.30 - Mario Sanvitale

    20/23

    20

    Results

    Basically, this approach takes away any fear of the unknown

    It provides:

    Speedy productivity

    Early Return on InvestmentGreater potential for management acceptance

    Minimal business disruption

    Best use of scarce resources

    Better understanding of best practice

    Managed Project Controls Environment

    Genuine process for future-proofing

    . . . . . Minimal fear of failure, maximum opportunities for success

  • 8/13/2019 15.30 - Mario Sanvitale

    21/23

    21

  • 8/13/2019 15.30 - Mario Sanvitale

    22/23

    22

    Our Credentials

    Including:

    Oracle UniversityEducation Partner

    Primary Partner of the ECITB for over 6 years

    PRINCE2Practitioner Consultants

    Deputy Chair of UKOUG Primavera SIG Director of Best Practice User Group

    Our credentials are proof of our commitment to quality, and they help demonstrate our

    deep understanding and proactive assessment of Project, Programme and Portfolio

    Management solutions.

  • 8/13/2019 15.30 - Mario Sanvitale

    23/23

    23

    1stMilestone LimitedWestgate House

    Westgate

    London

    W5 1YY

    Tel: +44 (0) 20 8991 3305

    Fax: +44 (0) 20 8991 3306

    [email protected]

    www.milestoneuk.com