1404_UBC Seismic Risk Assessment_Building Report_June 18-2012

  • Upload
    arno

  • View
    2.304

  • Download
    0

Embed Size (px)

DESCRIPTION

UBC's seismic risk assessment of campus buildings conducted in 2012.

Citation preview

  • GLOTMAN SIMPSON JM ENGINEERING Consulting Engineers Consulting Structural Engineer

    Suite 608 318 Homer Street, Vancouver, BC 604-683-0595

    UNIVERSITY OF BRITISH COLUMBIA

    SEISMIC RISK ASSESSMENT REPORT

    (SUMMARY OF HIGH & VERY-HIGH

    SEISMIC RISK BUILDINGS)

    Project No. 1404 June 14, 2012

  • GLOTMAN SIMPSON JM ENGINEERING Consulting Engineers Consulting Structural Engineer

    Suite 608 318 Homer Street, Vancouver, BC 604-683-0595

    TABLE OF CONTENTS

    Page No.

    Executive Summary. 1

    1. Introduction. 5 2. Existing Delcan Documentation And Evaluation Criteria. 5 3. UBC Report Expectations. 6 4. Seismic Assessment Evaluation Methodology For This Report. 6 5. Ranking Criteria For Medium, High & Very High Seismic Risk Buildings. 8

    6. Reduced Ranking of Seven Buildings From High/Very High To Medium. 9 7. Possible Re-Ranking Of Buildings Based On Full Seismic Analysis. 10 8. Possible Re-Ranking Of Building Based On Full Seismic Analysis and Fixing The Failure Mechanism. 10 9. Possible Re-Ranking Of Buildings Based On Fixing The Failure Mechanism Only (Quick Fix).... 10

    10. Comments On Costing Of Seismic Upgrades 11

    11. Special Condition Building 724 Powerhouse...... 11 12. Performance Based Seismic Design Benefits For UBC... 12 Appendix Individual Building Data Sheets

  • GLOTMAN SIMPSON JM ENGINEERING Consulting Engineers Consulting Structural Engineer

    Suite 608 318 Homer Street, Vancouver, BC 604-683-0595

    Page 1

    EXECUTIVE SUMMARY JM Engineering (partnered with Glotman-Simpson Consulting Engineers) was retained by The University of British Columbia to conduct a seismic review of 49 buildings previously ranked high and very high in the Delcan Report dated Dec 1994 titled Screening Study With Respect To Behaviour Under seismic Loading of University Controlled Campus Buildings. Our review was based entirely on structural related issues unlike the Delcan study which also included non-structural issues such as building importance, building size, building area, use, occupancy density, and duration of use. The ranking criteria of very high, high, and medium risk are outlined in section 5 of the report. We generally followed the 1992 NRC Guidelines for Seismic Evaluation of Existing Buildings however we focused on the structural elements only. Our review was conducted using the 2006 BC Building Code seismic design criteria and seismic design philosophy. The 1992 NRC guideline document is still currently in use as a method of ranking buildings. It was agreed with UBC that buildings designed after 1994 need not be reviewed. It is our opinion that these buildings should have been designed with a competent lateral resisting system in place with sufficient ductility and capacity to warrant a ranking of low or medium risk. In this report, a total of 49 buildings from the original list supplied by UBC were reviewed which included 13 very high risk and 36 high risk buildings as previously ranked in the Delcan report. After completion of our seismic review, we determined there were 28 very high risk, 12 high risk and 7 buildings that were downgraded to medium risk. Note Buildings 308 & 308-1 (Leonard Klink Building), and 344 & 344-1 (University Center) have been combined into 308 and 344 since the additions to these main buildings created essentially one building from a structural point of view. The seven buildings downgraded to medium from high or very high risk in Delcans report was a result of conducting a more thorough investigation of the structural framing systems and conducting site visits to each building. In all cases we found that these buildings exhibited sufficient lateral framing and ductility to warrant a reduction in risk ranking. From the list of buildings we reviewed, we recommend that a full seismic analysis be conducted on 4 buildings (449 Food, Nutrition and Health, 467 Health Sciences Parkade, 624 George Cunningham Addition, 864 Wesbrook Building) to possibly down grade the risk level to medium. There are another 4 buildings (017 Old Administration Building, 023 Henry Angus Tower, 052 Fraser River Parkade, 536 Woodward Library) where we recommend conducting a full seismic analysis coupled with fixing of the failure mechanism(s) to enable a down grade in the ranking to medium.

  • GLOTMAN SIMPSON JM ENGINEERING Consulting Engineers Consulting Structural Engineer

    Suite 608 318 Homer Street, Vancouver, BC 604-683-0595

    Page 2

    In addition, we are of the opinion 3 buildings (091 Botanical Garden Garden Pavilion, 148 Chemistry B Block South Wing, 312 MacLeod Building) could be downgraded to medium if the seismic mechanism is corrected. One building of importance, building 724 the Power House, requires a full seismic analysis and detailed site investigation to verify its ranking. With a post disaster importance, the seismic demand on this structure is significant and the various phases (1924, 1946, 1961, 1969) included many non-ductile detailing, brittle materials (block and tile) and unknown diaphragm connections. The ability to accurately rank this building is beyond the scope of this review, but we are of the opinion the very high ranking is justified at this time. It is worth noting that a random review of 8 geotechnical reports was conducted to determine if soil conditions may affect the building seismic risk ranking. We found that all 8 reports (randomly spread over the campus) exhibited consistent and competent soil capacity. In our opinion, soil conditions will not be a factor in the different risk ranking between buildings. The final building inventory, new risk rating, and priority ranking are as follows:

  • GLOTMAN SIMPSON JM ENGINEERING Consulting Engineers Consulting Structural Engineer

    Suite 608 318 Homer Street, Vancouver, BC 604-683-0595

    Page 3

    BUILDING NAME & NUMBER

    NEW RISK RATING

    & PRIORITY

    RANKING

    1994

    DELCAN REPORT

    RISK RANKING

    VERY HIGH SEISMIC RISK BUILDINGS

    Brittle Glazing Failure

    071-1 Botany Greenhouse 1 Very High 1 High 071-2 Botany Greenhouse 2 Very High - 2 High

    387 Forest Sciences Greenhouse Very High 3 High

    Buildings With Seismic Mechanism And Building Collapse Highly Likely With No Lateral

    System In One Or Both Directions

    002-43 Acadia Park Pre-School Very High 4 High 091 Botanical Garden - Garden Pavilion Very High 5 Very High 523-1 D.H. Copp Building Very High 6 High 523-3 Medical Sciences Block C Very High 7 High 525-3 Medical Sciences Block C Addition Very High 8 High 472 International House Very High 9 High 575 Music Building Very High 10 Very High 625 George Cunningham Building Very High 11 Very High 344 & 344-1 University Center & Addition Very High 12 High 386 MacMillan Building Very High 13 High 148 Chemistry B Block South Wing Very High 14 High 570 Museum Of Anthropology Display Area Very High 15 Very High 430 Osborne Center Unit 1 Very High 16 Very High 052 Fraser River Parkade Very High 17 Very High 785 Thunderbird Stadium Very High 18 High

    Buildings With Seismic Mechanism And Partial Collapse Most Likely But Still Exhibiting

    Some Degree Of Capacity

    144 Chemistry C Block East Wing Very High 19 High 562 Frank Forward Building Very High 20 High 732 Douglas Kenny Building Very High 21 High 023 Henry Angus Office Tower Very High 22 Very High 028 Fred Lasserre Building Very High 23 High 018 General Services Administration Building Very High 24 High 308 & 308-1 Leonard Klinck & Addition Very High 25 High 064 Biological Sciences Building (Center Blk) Very High 26 High 656 Hebb Building Very High 27 Very High 724 Power House Very High 28 Very High

  • GLOTMAN SIMPSON JM ENGINEERING Consulting Engineers Consulting Structural Engineer

    Suite 608 318 Homer Street, Vancouver, BC 604-683-0595

    Page 4

    HIGH SEISMIC RISK BUILDINGS

    Buildings With Seismic Mechanism Likely Resulting In Localized Collapse Only But

    Having A Defined Lateral System With Low Capacity

    540-1 Totem Park Residences Common Blk High 1 High 467 Health Sciences Parkade High 2 High 021 Landscape Architecture Annex High 3 High 431 Osborne Centre Unit 2 High 4 Very High 536 Woodward Library High 5 High 312 MacLeod Building High 6 High 017 Old Administration Building High 7 High

    Buildings With No Mechanism But Having A Defined Lateral System With Low Capacity

    066 Biological Sciences North Wing High 8 High 447 Chemistry A Block Chem-Phys Building High 9 High 449 Food Nutrition & Health High 10 Very High 624 George Cunningham Building Addition High 11 High 864 Wesbrook Building High 12 High

    MEDIUM SEISMIC RISK BUILDINGS

    002-1 Acadia Park Highrise Medium High

    029 Campus & Community Planning 2 Medium High

    081 Bookstore / NEC / Michael Smith Labs Medium High

    515 Sedgewick Library Medium Very High

    869-2 Walter Gage Residence South Tower Medium High 869-3 Walter Gage Residence North Tower Medium High 872-1 Walter Gage Residence East Tower Medium High

  • GLOTMAN SIMPSON JM ENGINEERING Consulting Engineers Consulting Structural Engineer

    Suite 608 318 Homer Street, Vancouver, BC 604-683-0595

    Page 5

    1. INTRODUCTION JM Engineering (partnered with Glotman-Simpson Engineers) was retained by The University of British Columbia to conduct a seismic review of 49 buildings previously ranked high and very high in the Delcan Report dated Dec 1994 titled Screening Study With Respect To Behaviour Under seismic Loading of University Controlled Campus Buildings. Our mandate was to conduct a more detailed seismic review of the buildings with the goal of updating the buildings ranking solely based on structural related issues as prescribed in the current 2006 BC Building Code using the current code seismic design philosophy. We understand that one of the goals of the report was to prioritize the buildings in each category to provide UBC with updated seismic risk information to aid in future planning decisions.

    2. EXISTING DELCAN DOCUMENTATION AND EVALUATION CRITERIA We were in possession of the following Delcan reports which form the basis of the current ranking of the high and very high seismic risk buildings: Delcan Report dated December 1994 titled Screening Study With Respect To Behaviour Under Seismic Loading of University Controlled Campus Buildings o Part 1 Structural Review o Appendix 1.1 Inspection Form Data Sheets (Seismic Vulnerability: Very High Priority) o Appendix 1.2 Inspection Form Data Sheets (Seismic Vulnerability: High Priority) The Delcan reports are based on following the seismic screening survey approach outlined in the 1992 NRC Guidelines for Seismic Evaluation of Existing Buildings. Their inspection forms are a modified version of the NRC Seismic Screening Inventory Form. In summary, the NRC screening approach is best suited for providing a quick seismic risk assessment of a large inventory of buildings; ideally suited for UBC. The NRC 1992 Guidelines are still currently used to screen and rank buildings. This screening involves a quick review of the building drawings, a site visit to each building, followed by completion of a screening form appended to the NRC document. The screening does not allow nor is it intended that a comprehensive seismic analysis be conducted. The NRC screening is a very quick review that provides a ranking based on structural and building related information. It is intended to generate a general grouped ranking of buildings to provide an overview of the condition of the building inventory.

  • GLOTMAN SIMPSON JM ENGINEERING Consulting Engineers Consulting Structural Engineer

    Suite 608 318 Homer Street, Vancouver, BC 604-683-0595

    Page 6

    3. UBC REPORT EXPECTATIONS

    UBCs primary objective was to receive an updated seismic risk assessment list of high and very high buildings. This list was to be based on structural related issues unlike the Delcan study which was based on the NRC screening guidelines which included non-structural issues such as building importance, building size, building area, use, occupancy density, and duration of use. In addition, UBC requested we rank each building within the very high risk and the high risk group from highest risk to lowest risk.

    UBC was also interested in understanding whether the seismic performance of the building and its corresponding ranking was a result of an overall building structural deficiency (such as lack of ductility or lack of capacity) or an isolated deficiency (such as a soft storey or short column). This information could be beneficial in providing a more economical repair which might drastically improve the buildings safety (thereby reducing the risk) by fixing a serious structural failure mechanism without having to seismically upgrade the entire building. Approximate seismic upgrading costs were also to be estimated for each building.

    4. SEISMIC ASSESSMENT EVALUATION METHODOLOGY FOR THIS REPORT To achieve the goals outlined by UBC noted above, we generally followed the screening procedures outlined in the 1992 NRC Guidelines for Seismic Evaluation of Existing Buildings. However, we deviated from the NRC guidelines in that we did not include any building information details that might affect the structural ranking of the buildings. In addition, our review differed from the NRC guidelines when it came to reviewing the structural aspects of the building. We conducted a more thorough review of the buildings structural framing with the goal of determining the seismic deficiencies as well as the seismic failure mechanism (if applicable). The seismic design criteria outlined in the 2006 BC Building Code formed the basis of our structural review. It should be noted that the 1992 NRC Guidelines are still currently used to rank buildings however we felt it necessary to exceed the level of structural review to achieve the goals outlined by UBC for this report. In order to identify the seismic performance mechanism, we conducted the following seismic assessment review procedure for this report:

    Obtain all available structural drawings for each building from Records

    Review Delcans report for each building on the high and very high list Conduct a detailed structural review of each buildings structural drawings identifying

    the gravity framing and the lateral resisting system. For a relatively small number of buildings where drawings were insufficient or site visits were necessary to confirm framing conditions, field reviews were conducted. Field reviews were conducted for the following buildings:

  • GLOTMAN SIMPSON JM ENGINEERING Consulting Engineers Consulting Structural Engineer

    Suite 608 318 Homer Street, Vancouver, BC 604-683-0595

    Page 7

    002-1 Acadia Towers 022-43 Acadia Pre School 017 Old Administration Building 021 Landscape Architecture Annex 029 Campus & Community Planning 2 052 Fraser Parkade 091 Botanical Garden Garden Pavilion 430 Osborne Unit 1 431 Osborne Unit 2 467 Health Sciences Parkade 515 Sedgewick Library 869-2 Walter Gage South Tower 869-3 Walter Gage North Tower 872-1 Walter Gage East Tower

    The lateral resisting system was reviewed in detail to determine how the building might be expected to perform during a low, medium, and high seismic event.

    In particular we concentrated on identifying the type of deficiencies that were inherent within each individual buildings lateral resisting system. This allowed us to categorize each building into medium, high or very high risk ranking.

    In some cases, we were able to reduce the current Delcan ranking to medium risk based on the ranking criteria outlined below in section 5..

    In particular, we looked for the following items when conducting the detailed drawing review:

    Did the building exhibit a defined lateral load resisting system (LLRS) in one or both directions. An LLRS is any structural framed element designed in accordance with the seismic design provisions outlined in the current building code to safely resist the shear and overturning moments (forces) generated from a seismic event. Typical systems include reinforced concrete shear walls, moment frames consisting of specially reinforced concrete or steel columns and beams, x-bracing steel frames, reinforced concrete block walls, plywood sheathed timber shear walls.

    Was the LLRS adequate for current code design values or to what level of compliance might the LLRS be capable of resisting

    Was the LLRS continuous to foundations

    Ductility of the LLRS and critical elements which experience significant deflections

    Was the diaphragm adequate for the spans

    Was the diaphragm well tied to the LLRS

    Could all the walls be properly engaged by the diaphragm

    Placement of the LLRS on plan and resulting torsion

    Short column affect short columns are where a column element is made significantly stiffer attracting more seismic load due to partial height block wall or clay tile infill, or deep spandrel beams

    Soft storeys at discontinuous walls soft storeys are where concrete walls are supported on column elements which are susceptible to collapse if they are inadequately sized or reinforced

    Type and amount of reinforcement and embedment

    Types and sizes of footings

  • GLOTMAN SIMPSON JM ENGINEERING Consulting Engineers Consulting Structural Engineer

    Suite 608 318 Homer Street, Vancouver, BC 604-683-0595

    Page 8

    Our structural review did not include the following:

    We did not conduct any destructive demolition to determine structural framing

    No detailed seismic analysis was carried out

    We did not confirm on site whether each and every buildings LLRS was still 100% intact as per the original structural drawings renovations may have occurred over time which may have reduced capacity

    5. RANKING CRITERIA FOR MEDIUM, HIGH, AND VERY HIGH SEISMIC RISK

    BUILDINGS The following criteria were used to determine the ranking of the buildings: Very High Risk Buildings: The basic characteristic of very high risk ranked buildings is that, in our opinion , they exhibit some combination or all of the following deficiencies: o Building is likely to have full or partial collapse during a moderate seismic event or

    higher loss of life probable o Lateral load resisting system is non-existent or very low capacity (less than

    approximately 10% capacity) in one or two directions o Building components such as reinforced concrete walls and moment frames have no

    ductility leading to brittle failures o Failure mechanisms have been identified resulting in significant probability of

    building partial or full collapse if the mechanism was triggered. These include such items as soft storeys, no ductility and short columns

    o The building exhibits no redundancy in the lateral load resisting system High Risk Buildings: High risk buildings are ranked if, in our opinion, they exhibit some combination or all of the following deficiencies: o Building may experience partial localized collapse during a moderate seismic event

    or higher with loss of life probable. Damage to the building is likely localized o Lateral resisting system is defined but is typically insufficient and only exhibits low

    capacity (less than approximately 30% capacity) in both directions o Building components such as reinforced concrete walls and moment frames have

    limited ductility but are capable of supporting low level seismic events o There are no apparent catastrophic failure mechanisms that can lead to a pre-

    mature brittle or catastrophic collapse of the entire building o The building exhibits some redundancy in the lateral load resisting system such that

    load sharing is possible if lateral resisting load elements became damaged.

  • GLOTMAN SIMPSON JM ENGINEERING Consulting Engineers Consulting Structural Engineer

    Suite 608 318 Homer Street, Vancouver, BC 604-683-0595

    Page 9

    Medium Risk Buildings: Buildings were ranked medium risk if the following was found in a building: o The buildings have a well defined lateral load resisting system in place in both

    directions. o The lateral load resisting system is capable of resisting at least approximately 30%

    of current code capacity in both directions. o The buildings lateral system has redundancy. o There are no apparent failure mechanisms. o The building is expected to survive a large seismic event with no anticipated loss of

    life but extensive damage is expected in the structural framing system.

    6. REDUCED RANKING OF SEVEN BUILDINGS FROM HIGH/VERY HIGH TO MEDIUM During our review we found that seven of the 49 buildings previously ranked high or very high risk were able to be re-ranked as medium risk. These buildings and a brief explanation are outlined below: 002-1 Acadia Park Highrise: Delcans report categorically ranked all highrise structures

    as high risk. Our reviewed showed a well developed lateral load resisting system in place. Based on the framing, we are of the opinion this building is a medium risk.

    029 Campus & Comm Planning These two buildings have sufficient framing in place and

    the seismic demand on the lateral system would be, in our opinion, sufficiently low to reduce the risk to medium.

    081 Bookstore The bookstore, NEC, and Micheal Smith Labs complex are

    structurally one building. The bookstore was seismically upgraded when the Micheal Smith Lab bldg was built.

    515 Sedgewick Library The building is essentially located underground. This pre-

    cast building was thought to be high risk due to the lack of connection between pre-cast elements. The bearing of the pre-cast slabs is such that, in our opinion, the building would have to undergo such extreme building movements which was not practical.

    869-2 Walter Gage South Delcans report categorically ranked all highrise structures

    as high risk. Our reviewed showed a well developed lateral load resisting system in place. Based on the framing, we are of the opinion this building is a medium risk.

    869-3 Walter Gage North Delcans report categorically ranked all highrise structures

    as high risk. Our reviewed showed a well developed lateral load resisting system in place. Based on the framing, we are of the opinion this building is a medium risk.

  • GLOTMAN SIMPSON JM ENGINEERING Consulting Engineers Consulting Structural Engineer

    Suite 608 318 Homer Street, Vancouver, BC 604-683-0595

    Page 10

    872-1 Walter Gage East Delcans report categorically ranked all highrise structures

    as high risk. Our reviewed showed a well developed lateral load resisting system in place. Based on the framing, we are of the opinion this building is a medium risk.

    7. POSSIBLE RE-RANKING OF BUILDINGS BASED ON FULL SEISMIC ANALYSIS We found that, in our opinion, a total of four buildings may benefit from conducting a full seismic analysis which includes modeling the building and conducting a non-linear dynamic analysis. These buildings are all currently ranked high. They have a defined lateral resisting system however it is estimated they are capable of only resisting lower level seismic forces. We did not observe any obvious seismic failure mechanism. There is sufficient framing and redundancy in place which, in our opinion, justifies the need for a full seismic analysis. The goal of this analysis would be to reduce the ranking from high to medium. These buildings include: 449 Food Nutrition & Health 467 Health Sciences Parkade 624 George Cunningham Building Addition 864 Wesbrook Building

    8. POSSIBLE RE-RANKING OF BUILDINGS BASED ON FULL SEISMIC ANALYSIS

    AND FIXING THE FAILURE MECHANISM There were another four buildings with similar potential benefits from conducting a full seismic analysis as outlined in section 7 above, but with a seismic mechanism that must also be fixed. The fix of the seismic mechanism is a localized element which would have limited intrusion in the building and be relatively economical to remediate. The fix would not bring the building into compliance with current seismic design levels, although the fix would be designed to the current code. The goal with the analysis and fix is to be able to downgrade the buildings from high or very high to medium. These buildings include: 017 Old Administration Building 023 Henry Angus Office Tower 052 Fraser River Parkade 536 Woodward Library

    9. POSSIBLE RE-RANKING OF BUILDINGS BASED ON FIXING THE FAILURE

    MECHANISM ONLY (QUICK FIX) Similar to item 8 above, we identified three buildings where, in our opinion, it would be possible to employ a quick localized fix of the seismic mechanism which would enable the building to be downgraded from high or very high to medium.

  • GLOTMAN SIMPSON JM ENGINEERING Consulting Engineers Consulting Structural Engineer

    Suite 608 318 Homer Street, Vancouver, BC 604-683-0595

    Page 11

    The fix would not bring the building into compliance with current seismic design levels, although the fix would be designed to the current code. These buildings include: 091 Botanical Garden Garden Pavilion 148 Chemistry B Block South Wing 312 MacLeod Building

    10. COMMENTS ON COSTING OF SEISMIC UPGRADES We have provided estimates of the anticipated seismic upgrade costs for each building based on previous experience with seismic upgrades of other buildings. These are our best approximation based on this level of review. A full seismic analysis would enable these costs to be firmed up. The costs should be based on the $/sq ft x the building area noted in our building forms. These may differ from the areas of the buildings UBC have on file. Our area is based on framed area which often differs from the building area. At this time we have allowed an equal per sq ft cost allocated towards architectural, mechanical, and electrical upgrades/repairs. Where the buildings are obviously light on finishes, such as parkades or gymnasia, we have lowered the Arch/Mech/Elec costs. The total cost for the seismic upgrade is the cumulative costs of the structural component and the arch/mech/elec component. The costs are based on a seismic upgrade to 100% of current code design criteria (unless noted specifically as less on the individual building sheet). There is precedent in the City of Vancouver for reducing the level of upgrade to 75% of current code if the costs to upgrade or the difficulty to go to 100% are prohibitive. These costs do not include soft costs.

    11. SPECIAL CONDITION BUILDING 724 POWER HOUSE The Power House building would be considered a post disaster building by current codes. This carries a seismic factor of 1.5 over normal buildings. UBC should confirm this building warrants this classification. The building is currently ranked very high in the Delcan report. A review of the drawings and a quick site visit was not adequate to properly assess this building due to the complexity of the framing, the multiple phases that have been built over the years (1924, 1946, 1961, 1969). The building is constructed of concrete, steel, block, and tile. The roof and floor diaphragm connections to the main vertical elements, the brittle nature of the tile and block, the lack of ductility in the walls, and the importance that this building plays in a post disaster role has led us to recommend that a separate full seismic analysis be conducted on this building (which may include some destructive demolition) to properly rank this building. Until that time, we recommend the very high ranking remain.

  • GLOTMAN SIMPSON JM ENGINEERING Consulting Engineers Consulting Structural Engineer

    Suite 608 318 Homer Street, Vancouver, BC 604-683-0595

    Page 12

    12. PERFORMANCE BASED SEISMIC DESIGN BENEFITS FOR UBC There is an opportunity of using Performance Based Design to retrofit the buildings at UBC ranked high and very high risk which may help reduce the seismic upgrade costs from the current conventional seismic design approach used in the 2006 BC Building Code. If UBC Regulatory would accept this approach to seismic upgrade, we estimate that seismic upgrade cost savings might be in the order of approximately 20% for each building. There is precedent for using Performance Based Design in BC. Currently the Seismic Retrofit Guidelines for BC Low Rise School Buildings September 30, 2011 is based on a Performance Based Design approach. The intent of using this design approach is to achieve life safety by reducing the probability of structural collapse to acceptable risk levels instead of concentrating on damage prevention. Performance Based Design involves using higher order structural analysis and design techniques to evaluate a buildings reaction to seismic loading. A three dimensional finite element computer model is developed that accurately predicts the structural behaviour of each element of the structure and how the elements are connected together. The modeling includes how the elements react to loads that exceed their resistance and how the loads will re-distribute through the adjacent elements as a result. This computer model is then subjected to cyclic seismic loading records developed from historical earthquake recordings where the load intensity and direction vary with time. The resulting non-linear time history analysis can be used to evaluate how a structure will behave under earthquakes of different types and magnitudes and further to evaluate how changes to those structures will affect their response. The ability to accurately evaluate how a structure will behave under earthquakes of different types and magnitudes allows for a much more thorough assessment of a buildings risk under seismic loading. Assessments can be made as to what type and magnitude of earthquake will lead to different levels of damage or, ultimately, to collapse. Based on the probability of these different types and magnitudes of earthquakes an accurate numerical assessment of risk can be made for individual buildings, such as the return period of earthquake that will likely lead to collapse. These numerical assessments can be used to rank buildings for seismic risk. The seismic risk rankings can be combined with impact rankings, such as number of occupant days per year, to develop a very detailed evaluation of the relative benefit gained from upgrading each building. The ability to accurately evaluate how changes to a buildings structure will affect their response to seismic loading allows for a much more targeted approach to upgrading. Different upgrading approaches can be evaluated to achieve minimalist approaches to reducing risk to acceptable levels, such as moving a building from a high risk category to a medium risk based on the return period seismic event that would lead to collapse. Alternatively, specific collapse mechanisms can be addressed without having to upgrade the entire structure. Finally, it is likely that non-linear time history analysis can be used to show that some of the buildings that have been reviewed may behave much better than anticipated under seismic loading with the goal to downgrade these buildings from the very high or high risk category to medium risk.

  • GLOTMAN SIMPSON JM ENGINEERING Consulting Engineers Consulting Structural Engineer

    Suite 608 318 Homer Street, Vancouver, BC 604-683-0595

    Page 14

    APPENDIX

    INDIVIDUAL BUILDING DATA SHEETS

    The following Appendix presents the individual data sheets for each of the buildings reviewed. The following provides guidance in reviewing the data sheets: - the buildings are presented in numerical order based on UBC Building Number - the year built was based on information obtained from the drawings - the design code is based either on information on the drawings or if not stated based on the

    assumed applicable code at that time - the rank is the applicable rank based on the corresponding risk level - the areas noted in the cost portion are based on approximate structural framed areas and

    may not correspond to the areas that UBC uses our costing estimate has assumed these areas. The areas should not be adjusted without adjusting the corresponding cost per sq ft.

    - the approximate costs outlined on the project data sheets do not include soft costs - the total cost of the seismic upgrade is the cumulative costs of the structural component and

    the arch/mech/elec component - where (Partial Upgrade Only) is noted, these are the estimated costs to upgrade the building

    sufficiently to reduce the risk level to medium - no ranking or costing has been provided for medium ranked buildings

  • GLOTMAN SIMPSON JM ENGINEERING Consulting Engineers Consulting Structural Engineer

    UBC Building Seismic Risk Assessment Review May 2012

    UBC Building No.

    002-1

    UBC Building Name

    ACADIA PARK

    HIGHRISE

    Year Built

    1967

    Design Code

    Assumed 1965 National Building Code Of Canada

    Seismic Risk Level

    MEDIUM

    Rank

    Not applicable

    Gravity Framing

    Description

    - 15 storey tower - reinforced concrete slabs, columns and walls - conventional strip & spread footings

    Lateral Resistance Framing System

    - nominal ductile concrete shear walls - redundancy with several walls in each direction - torsional capacity available

    Description Of

    Seismic Deficiencies

    - the concrete shear walls have nominal ductility which are

    capable of resisting medium level seismic events but would be deficient for higher level seismic events

    Description Of Seismic Failure

    Mechanism

    - not applicable due to medium ranking

    Description Of Proposed Seismic Analysis Or Upgrade

    Recommend Seismic Analysis Simple Seismic Complex Seismic For Possible Re-Ranking Upgrade Upgrade

    Description Of

    Possible Seismic Upgrade Or Analysis

    Not Applicable

    Order Of Magnitude of Cost For Seismic

    Upgrade

    Structural

    Arch/Mech/Elec Work

  • GLOTMAN SIMPSON JM ENGINEERING Consulting Engineers Consulting Structural Engineer

    UBC Building Seismic Risk Assessment Review May 2012

    UBC Building No.

    002-43

    UBC Building Name

    ACADIA PARK PRE

    SCHOOL

    Year Built

    1967

    Design Code

    Assumed 1965 National Building Code Of Canada

    Seismic Risk Level

    VERY HIGH

    Rank

    4

    Gravity Framing

    Description

    - one storey building - timber stud walls around perimeter with timber posts supporting

    vaulted roof trusses - clerestory windows all around perimeter - brick veneer up to clerestory likely not tied to stud walls

    Lateral Resistance Framing System

    - none apparent

    Description Of

    Seismic Deficiencies

    - roof diaphragm is discontinuous - no defined shear walls and posts/beams not tied - brick veneer likely not restrained

    Description Of Seismic Failure

    Mechanism

    - anticipated catastrophic failure as roof diaphragm shears off the

    top of the clerestory posts - possible falling of brick veneer walls all around perimeter

    Description Of Proposed Seismic Analysis Or Upgrade

    Recommend Seismic Analysis Simple Seismic Complex Seismic For Possible Re-Ranking Upgrade Upgrade

    Description Of

    Possible Seismic Upgrade Or Analysis

    Recommend replacement of the building as upgrade costs will

    likely equal a new building

    Order Of Magnitude of Cost For Seismic

    Upgrade

    Structural

    Arch/Mech/Elec Work

    X

  • GLOTMAN SIMPSON JM ENGINEERING Consulting Engineers Consulting Structural Engineer

    UBC Building Seismic Risk Assessment Review May 2012

    UBC Building No.

    017

    UBC Building Name

    OLD

    ADMINISTRATION

    BUILDING

    Year Built

    1959

    Design Code

    Assumed 1953 National Building Code Of Canada

    Seismic Risk Level

    HIGH

    Rank

    7

    Gravity Framing

    Description

    - two storey building with one partial basement - assumed timber framed stud walls and timber floors/roof

    Lateral Resistance Framing System

    - assumed drywall sheathed interior walls and strapped perimeter

    walls with stucco

    Description Of

    Seismic Deficiencies

    - no defined shear walls - clerestory in basement level walls along west side plus returns

    creates a soft storey

    Description Of Seismic Failure

    Mechanism

    - collapse of west wall due to soft storey in basement

    Description Of Proposed Seismic Analysis Or Upgrade

    Recommend Seismic Analysis Simple Seismic Complex Seismic For Possible Re-Ranking Upgrade Upgrade

    Description Of

    Possible Seismic Upgrade Or Analysis

    It may be possible to reduce the building to a medium level of risk

    by completing a full seismic assessment using the NRC Seismic

    Screening Guidelines AND fixing the soft storey condition

    Order Of Magnitude of Cost For Seismic

    Upgrade

    Structural

    $5/sq ft

    22,000 sq ft

    (Partial Upgrade Only)

    Arch/Mech/Elec Work

    $5/sq ft

    22,000 sq ft

    (Partial Upgrade Only)

    X

  • GLOTMAN SIMPSON JM ENGINEERING Consulting Engineers Consulting Structural Engineer

    UBC Building Seismic Risk Assessment Review May 2012

    UBC Building No.

    018

    UBC Building Name

    GENERAL

    SERVICES

    ADMINISTRATION

    BUILDING

    Year Built

    1969

    Design Code

    Assumed 1965 National Building Code Of Canada

    Seismic Risk Level

    VERY HIGH

    Rank

    24

    Gravity Framing

    Description

    - 3 storeys plus basement - reinforced concrete slabs, columns & walls

    Lateral Resistance Framing System

    - a few concrete shear walls east west, some discontinuous - no concrete shear walls north south

    Description Of

    Seismic Deficiencies

    - lack of shear walls in both directions - no ductility in the few walls that do exist - discontinuous walls bearing a beams or columns below

    Description Of Seismic Failure

    Mechanism

    - brittle failure in low seismic events - collapse of soft storey supporting columns

    Description Of Proposed Seismic Analysis Or Upgrade

    Recommend Seismic Analysis Simple Seismic Complex Seismic For Possible Re-Ranking Upgrade Upgrade

    Description Of

    Possible Seismic Upgrade Or Analysis

    Extensive and complex fix to address the discontinuous walls.

    Need many new concrete shear walls both directions. Also

    possible to augment the seismic system using steel x-bracing

    around the perimeter columns.

    Order Of Magnitude of Cost For Seismic

    Upgrade

    Structural

    $25/sq ft

    80,000 sq ft

    (Full Upgrade)

    Arch/Mech/Elec Work

    $25/sq ft

    80,000 sq ft

    (Full Upgrade)

    X

  • GLOTMAN SIMPSON JM ENGINEERING Consulting Engineers Consulting Structural Engineer

    UBC Building Seismic Risk Assessment Review May 2012

    UBC Building No.

    021

    UBC Building Name

    LANDSCAPE

    ARCHITECTURE

    ANNEX

    Year Built

    1921

    Design Code

    Assumed No Building

    Code

    Seismic Risk Level

    HIGH

    Rank

    3

    Gravity Framing

    Description

    - 2-1/2 storey timber framed building consisting of stud walls and

    columns with joists/beams

    Lateral Resistance Framing System

    - assumed timber stud walls with drywall - exterior stud walls with board strapping and unreinforced clay

    tile infill

    Description Of

    Seismic Deficiencies

    - lack of defined plywood sheathed shear walls - brittle clay tile infill

    Description Of Seismic Failure

    Mechanism

    - shear failure due to lack of shear walls and hold downs

    Description Of Proposed Seismic Analysis Or Upgrade

    Recommend Seismic Analysis Simple Seismic Complex Seismic For Possible Re-Ranking Upgrade Upgrade

    Description Of

    Possible Seismic Upgrade Or Analysis

    Add new shear walls and hold downs in both directions, tie floor

    diaphragms to new walls, and remove clay tile infill walls

    Order Of Magnitude of Cost For Seismic

    Upgrade

    Structural

    $ 20./sq ft

    5,000 sq ft

    (Full Upgrade)

    Arch/Mech/Elec Work

    $20./sq ft

    5,000 sq ft

    (Full Upgrade)

    X

  • GLOTMAN SIMPSON JM ENGINEERING Consulting Engineers Consulting Structural Engineer

    UBC Building Seismic Risk Assessment Review May 2012

    UBC Building No.

    023

    UBC Building Name

    HENRY ANGUS

    OFFICE TOWER

    Year Built

    1965

    Design Code

    Assumed 1960 National Building Code Of Canada

    Seismic Risk Level

    VERY HIGH

    Rank

    22

    Gravity Framing

    Description

    - 9 storey building with reinforced concrete slabs supported on

    columns/walls and perimeter loadbearing pre-cast mullions

    Lateral Resistance Framing System

    - discontinuous end reinforced concrete shear walls with

    continuous stair and elevator cores shafts

    Description Of

    Seismic Deficiencies

    - soft storey at discontinuous shear walls on small columns - no ductility in existing concrete walls - lack of tie at perimeter pre-cast mullions - lack of seismic joint with classroom block

    Description Of Seismic Failure

    Mechanism

    - brittle shear collapse with failure of soft storey columns and failure of pre-cast perimeter mullions

    Description Of Proposed Seismic Analysis Or Upgrade

    Recommend Seismic Analysis Simple Seismic Complex Seismic For Possible Re-Ranking Upgrade Upgrade

    Description Of

    Possible Seismic Upgrade Or Analysis

    Add new concrete shear walls and remove soft storey mechanism

    by continuing walls down to the foundations. Carbon fibre

    existing walls. May be possible to reduce to medium with full

    analysis and addressing soft storey and carbon fibre. Full

    upgrade will require new walls.

    Order Of Magnitude of Cost For Seismic

    Upgrade

    Structural

    $40/sq ft

    48,000 sq ft

    (Full Upgrade)

    Arch/Mech/Elec Work

    $40/sq ft

    48,000 sq ft

    (Full Upgrade)

    X X

  • GLOTMAN SIMPSON JM ENGINEERING Consulting Engineers Consulting Structural Engineer

    UBC Building Seismic Risk Assessment Review May 2012

    UBC Building No.

    028

    UBC Building Name

    FRED LASSERRE

    BUILDING

    Year Built

    1962

    Design Code

    Assumed 1953 National Building Code Of Canada

    Seismic Risk Level

    VERY HIGH

    Rank

    23

    Gravity Framing

    Description

    - 3 storey with basement and penthouse consisting of reinforced

    concrete slabs with supporting concrete columns & walls - penthouse roof supported on pre-cast columns

    Lateral Resistance Framing System

    - reinforced concrete shear walls with discontinuous walls at each

    of the stairs and interior locations

    Description Of

    Seismic Deficiencies

    - existing concrete walls have very low ductility - soft storeys due to discontinuous walls - lack of shear walls - unreinforced block between columns

    Description Of Seismic Failure

    Mechanism

    - failure of supporting columns due to block infill and soft storeys - failure of pre-cast penthouse columns

    Description Of Proposed Seismic Analysis Or Upgrade

    Recommend Seismic Analysis Simple Seismic Complex Seismic For Possible Re-Ranking Upgrade Upgrade

    Description Of

    Possible Seismic Upgrade Or Analysis

    Remove unreinforced perimeter block walls, address soft storeys

    at the discontinuous concrete shear walls, add new bracing or

    shear walls to foundations

    Order Of Magnitude of Cost For Seismic

    Upgrade

    Structural

    $30./sq ft

    55,000 sq ft

    (Full Upgrade)

    Arch/Mech/Elec Work

    $30./sq ft

    55,000 sq ft

    (Full Upgrade)

    X

  • GLOTMAN SIMPSON JM ENGINEERING Consulting Engineers Consulting Structural Engineer

    UBC Building Seismic Risk Assessment Review May 2012

    UBC Building No.

    029

    UBC Building Name

    CAMPUS &

    COMMUNITY

    PLANNING 2

    Year Built

    1953

    Design Code

    Assumed 1941 National Building Code Of Canada

    Seismic Risk Level

    MEDIUM

    Rank

    Not applicable

    Gravity Framing

    Description

    - 2 buildings connected by breezeway - one storey timber framed building with crawl space - two storey timber framed with perimeter block unreinforced

    walls

    Lateral Resistance Framing System

    - one storey likely strapped stud walls with drywall - two storey unreinforced block walls around perimeter

    Description Of

    Seismic Deficiencies

    - one storey (medium) not applicable - two storey (high) unreinforced block walls

    Description Of Seismic Failure

    Mechanism

    - not applicable due to medium ranking

    Description Of Proposed Seismic Analysis Or Upgrade

    Recommend Seismic Analysis Simple Seismic Complex Seismic For Possible Re-Ranking Upgrade Upgrade

    Description Of

    Possible Seismic Upgrade Or Analysis

    Not Applicable

    Order Of Magnitude of Cost For Seismic

    Upgrade

    Structural

    Arch/Mech/Elec Work

  • GLOTMAN SIMPSON JM ENGINEERING Consulting Engineers Consulting Structural Engineer

    UBC Building Seismic Risk Assessment Review May 2012

    UBC Building No.

    052

    UBC Building Name

    FRASER RIVER

    PARKADE

    Year Built

    1982

    Design Code

    1980 National Building Code Of

    Canada

    Seismic Risk Level

    VERY HIGH

    Rank

    17

    Gravity Framing

    Description

    - 3 storey parkade - pre-cast double tees, beams and concrete shear walls - jointed topping on top of double tees acting as diaphragm

    Lateral Resistance Framing System

    - six short pre-cast concrete walls in e/w direction, two longer pre-

    cast walls adjacent to the ramps n/s

    Description Of

    Seismic Deficiencies

    - no visible tying of pre-cast double tees or beams to columns

    and no visible ties between floor diaphragm to pre-cast walls - concrete topping acting as diaphragm slab in significantly

    jointed

    Description Of Seismic Failure

    Mechanism

    - possible collapse of framing due to pre-cast double tees and/or

    beams falling off supporting corbels

    Description Of Proposed Seismic Analysis Or Upgrade

    Recommend Seismic Analysis Simple Seismic Complex Seismic For Possible Re-Ranking Upgrade Upgrade

    Description Of

    Possible Seismic Upgrade Or Analysis

    Introduce ductile ties between pre-cast horizontal and vertical

    elements will reduce to a high. Recommend full seismic analysis to determine if tying is sufficient

    to reduce to a medium or if additional shear walls are required.

    Order Of Magnitude of Cost For Seismic

    Upgrade

    Structural

    $5./sq ft ties $ 12./sq ft new walls + ties

    135,000 sq ft

    Arch/Mech/Elec Work

    Not applicable

    X X

  • GLOTMAN SIMPSON JM ENGINEERING Consulting Engineers Consulting Structural Engineer

    UBC Building Seismic Risk Assessment Review May 2012

    UBC Building No.

    064

    UBC Building Name

    BIOLOGICAL

    SCIENCES BLDG

    (CENTER BLOCK)

    Year Built

    1948

    Design Code

    Assumed 1941 National Building Code Of Canada

    Seismic Risk Level

    VERY HIGH

    Rank

    26

    Gravity Framing

    Description

    - 3 storey building with small penthouse and basement - reinforced concrete ribbed slab with concrete columns, walls,

    and pre-cast perimeter mullions

    Lateral Resistance Framing System

    - a few short concrete walls with no ductility - conceptually moment frames may have been envisioned but

    these have essentially no ductility

    Description Of

    Seismic Deficiencies

    - lack of shear walls and no ductility in the existing walls - lack of ductility in perimeter pre-cast mullions - torsional resistance issue

    Description Of Seismic Failure

    Mechanism

    - shear failure due to lack of shear walls and torsion

    Description Of Proposed Seismic Analysis Or Upgrade

    Recommend Seismic Analysis Simple Seismic Complex Seismic For Possible Re-Ranking Upgrade Upgrade

    Description Of

    Possible Seismic Upgrade Or Analysis

    This building is irregularly shaped which makes the seismic

    upgrade very intrusive and costly. New concrete shear walls or

    bracing is required which will have significant interface issues

    with the rest of the building systems.

    Order Of Magnitude of Cost For Seismic

    Upgrade

    Structural

    $40./sq ft

    68,000 sq ft

    (Full Upgrade)

    Arch/Mech/Elec Work

    $40./sq ft

    68,000 sq ft

    (Full Upgrade)

    X

  • GLOTMAN SIMPSON JM ENGINEERING Consulting Engineers Consulting Structural Engineer

    UBC Building Seismic Risk Assessment Review May 2012

    UBC Building No.

    066

    UBC Building Name

    BIOLOGICAL

    SCIENCES NORTH

    WING

    Year Built

    1974

    Design Code

    1970 National

    Building Code of Canada

    Seismic Risk Level

    HIGH

    Rank

    8

    Gravity Framing

    Description

    - 4 storey building with basement - reinforced concrete ribbed slab with concrete columns, walls,

    and pre-cast perimeter mullions

    Lateral Resistance Framing System

    - short none ductile eccentric reinforced concrete walls

    Description Of

    Seismic Deficiencies

    - lack of shear walls - no ductility in walls

    Description Of Seismic Failure

    Mechanism

    - shear and flexural failure due to lack of walls

    Description Of Proposed Seismic Analysis Or Upgrade

    Recommend Seismic Analysis Simple Seismic Complex Seismic For Possible Re-Ranking Upgrade Upgrade

    Description Of

    Possible Seismic Upgrade Or Analysis

    Add more concrete shear walls or bracing. Consider reducing

    shear demand by removing pre-cast vertical elements.

    Order Of Magnitude of Cost For Seismic

    Upgrade

    Structural

    $25./sq ft

    63,000 sq ft

    (Full Upgrade)

    Arch/Mech/Elec Work

    $25./sq ft

    63,000 sq ft

    (Full Upgrade)

    X

  • GLOTMAN SIMPSON JM ENGINEERING Consulting Engineers Consulting Structural Engineer

    UBC Building Seismic Risk Assessment Review May 2012

    UBC Building No.

    071-1

    UBC Building Name

    BOTANY

    GREENHOUSE 1

    Year Built

    1982

    Design Code

    Unknown

    Seismic Risk Level

    VERY HIGH

    Rank

    1

    Gravity Framing

    Description

    - aluminum tube framing with glass

    Lateral Resistance Framing System

    - none

    Description Of

    Seismic Deficiencies

    - no lateral system in place

    Description Of Seismic Failure

    Mechanism

    - shattered glass

    Description Of Proposed Seismic Analysis Or Upgrade

    Recommend Seismic Analysis Simple Seismic Complex Seismic For Possible Re-Ranking Upgrade Upgrade

    Description Of

    Possible Seismic Upgrade Or Analysis

    No further comments.

    Order Of Magnitude of Cost For Seismic

    Upgrade

    Structural

    Arch/Mech/Elec Work

  • GLOTMAN SIMPSON JM ENGINEERING Consulting Engineers Consulting Structural Engineer

    UBC Building Seismic Risk Assessment Review May 2012

    UBC Building No.

    071-2

    UBC Building Name

    BOTANY

    GREENHOUSE 2

    Year Built

    1982

    Design Code

    Unknown

    Seismic Risk Level

    VERY HIGH

    Rank

    2

    Gravity Framing

    Description

    - aluminum tube framing with glass

    Lateral Resistance Framing System

    - none

    Description Of

    Seismic Deficiencies

    - no lateral system in place

    Description Of Seismic Failure

    Mechanism

    - shattered glass

    Description Of Proposed Seismic Analysis Or Upgrade

    Recommend Seismic Analysis Simple Seismic Complex Seismic For Possible Re-Ranking Upgrade Upgrade

    Description Of

    Possible Seismic Upgrade Or Analysis

    No further comments.

    Order Of Magnitude of Cost For Seismic

    Upgrade

    Structural

    Arch/Mech/Elec Work

  • GLOTMAN SIMPSON JM ENGINEERING Consulting Engineers Consulting Structural Engineer

    UBC Building Seismic Risk Assessment Review May 2012

    UBC Building No.

    081

    UBC Building Name

    BOOKSTORE/NEC/

    MICHAEL SMITH

    LABS

    Year Built

    1981/1990/2002

    Design Code

    1998 BC

    Building Code

    Seismic Risk Level

    MEDIUM

    Rank

    Not applicable

    Gravity Framing

    Description

    - original is reinforced concrete slabs, columns, walls - NEC is structural steel, x-braces, concrete shear walls - M Smith is concrete slabs, columns, walls plus an upgrade to

    the original for gravity & lateral

    Lateral Resistance Framing System

    - reinforced concrete shear walls and steel x-bracing

    Description Of

    Seismic Deficiencies

    - none noted recently upgraded in

    Description Of Seismic Failure

    Mechanism

    - not applicable

    Description Of Proposed Seismic Analysis Or Upgrade

    Recommend Seismic Analysis Simple Seismic Complex Seismic For Possible Re-Ranking Upgrade Upgrade

    Description Of

    Possible Seismic Upgrade Or Analysis

    No Further Comments

    Order Of Magnitude of Cost For Seismic

    Upgrade

    Structural

    Arch/Mech/Elec Work

  • GLOTMAN SIMPSON JM ENGINEERING Consulting Engineers Consulting Structural Engineer

    UBC Building Seismic Risk Assessment Review May 2012

    UBC Building No.

    091

    UBC Building Name

    BOTANICAL

    GARDEN

    GARDEN PAVILION

    Year Built

    1981

    Design Code

    Assumed 1975 National Building Code Of Canada

    Seismic Risk Level

    VERY HIGH

    Rank

    5

    Gravity Framing

    Description

    - post & beam timber framed one storey pavilion on top of a

    reinforced concrete basement - timber columns appear to cantilever off the concrete slab

    Lateral Resistance Framing System

    - there is some capacity of the cantilevered timber columns

    Description Of

    Seismic Deficiencies

    - the roof framing is not tied to the cantilevered columns and the

    clerestory currently in place prevents this connection

    Description Of Seismic Failure

    Mechanism

    - collapse of roof framing by shearing off columns

    Description Of Proposed Seismic Analysis Or Upgrade

    Recommend Seismic Analysis Simple Seismic Complex Seismic For Possible Re-Ranking Upgrade Upgrade

    Description Of

    Possible Seismic Upgrade Or Analysis

    Tie roof framing/diaphragm to the ring beam by removing the

    clerestory and adding framing to tie the two together. This would

    reduce the ranking to medium.

    Order Of Magnitude of Cost For Seismic

    Upgrade

    Structural

    $15./sq ft

    3600.

    (Partial Upgrade Only)

    Arch/Mech/Elec Work

    $15./sq ft

    3600.

    (Partial Upgrade Only)

    X

  • GLOTMAN SIMPSON JM ENGINEERING Consulting Engineers Consulting Structural Engineer

    UBC Building Seismic Risk Assessment Review May 2012

    UBC Building No.

    144

    UBC Building Name

    CHEMISTRY C

    BLOCK

    EAST WING

    Year Built

    1962

    Design Code

    Assumed 1953 National Building Code Of Canada

    Seismic Risk Level

    VERY HIGH

    Rank

    19

    Gravity Framing

    Description

    - 3 storey building with basement and penthouse - reinforced concrete one way slabs with beams supported on

    columns and walls

    Lateral Resistance Framing System

    - reinforced concrete walls in one direction and assumed

    concrete non ductile moment frame in the other

    Description Of

    Seismic Deficiencies

    - moment frame is non-ductile - penthouse has no lateral system - concrete walls are none-ductile

    Description Of Seismic Failure

    Mechanism

    - brittle failure from moment frame column collapse and/or

    penthouse collapse

    Description Of Proposed Seismic Analysis Or Upgrade

    Recommend Seismic Analysis Simple Seismic Complex Seismic For Possible Re-Ranking Upgrade Upgrade

    Description Of

    Possible Seismic Upgrade Or Analysis

    Add lateral system to support penthouse. Add shear walls or

    bracing in the weak direction and upgrade existing concrete walls.

    Order Of Magnitude of Cost For Seismic

    Upgrade

    Structural

    $40/sq ft

    40,000 sq ft

    (Full Upgrade)

    Arch/Mech/Elec Work

    $40./sq ft

    40,000 sq ft

    (Full Upgrade)

    X

  • GLOTMAN SIMPSON JM ENGINEERING Consulting Engineers Consulting Structural Engineer

    UBC Building Seismic Risk Assessment Review May 2012

    UBC Building No.

    148

    UBC Building Name

    CHEMISTRY B

    BLOCK

    SOUTH WING

    Year Built

    1958

    Design Code

    Assumed 1953 National Building Code Of Canada

    Seismic Risk Level

    Left Wing HIGH Right MEDIUM Link VERY HIGH

    Rank

    14

    Gravity Framing

    Description

    - left reinforced concrete one way slabs and beams supported

    on columns and walls - right reinforced concrete rib slab and beams supported on

    columns and walls - link concrete slabs & beams supported on columns

    Lateral Resistance Framing System

    - left & right reinforced concrete shear walls with nominal

    ductility - link no system in place

    Description Of

    Seismic Deficiencies

    - left - insufficient ductility in shear walls and no system in

    penthouse - right insufficient ductility in shear walls - link no system in place

    Description Of Seismic Failure

    Mechanism

    - left collapse of penthouse roof - link collapse of supporting columns

    Description Of Proposed Seismic Analysis Or Upgrade

    Recommend Seismic Analysis Simple Seismic Complex Seismic For Possible Re-Ranking Upgrade Upgrade

    Description Of

    Possible Seismic Upgrade Or Analysis

    Left introducing penthouse lateral system will reduce ranking to medium. Right is already a medium. Link tie ends to the buildings and add buttresses or similar for out of plane seismic.

    Order Of Magnitude of Cost For Seismic

    Upgrade

    Structural

    Left - $5./sq ft (50,000 sq ft)

    Link - $100./sq ft (1500 sq ft)

    (Partial Upgrade)

    Arch/Mech/Elec Work

    Left - $5./sq ft (50,000 sq ft)

    Link - $100./sq ft (1500 sq ft)

    (Partial Upgrade)

    X

  • GLOTMAN SIMPSON JM ENGINEERING Consulting Engineers Consulting Structural Engineer

    UBC Building Seismic Risk Assessment Review May 2012

    UBC Building No.

    308

    UBC Building Name

    LEONARD KLINCK

    BUILDING

    Year Built

    1947

    Design Code

    Assumed 1941 National Building Code Of Canada

    Seismic Risk Level

    VERY HIGH

    Rank

    25

    Gravity Framing

    Description

    - four storey building consisting of reinforced concrete waffle slab

    & beams supported on columns and shear walls

    Lateral Resistance Framing System

    - short reinforced concrete shear walls, many are discontinuous

    Description Of

    Seismic Deficiencies

    - lack of shear walls and non ductility in existing walls - soft storey due to discontinuous shear walls - torsional issues - diaphragm issues in cantilevered wings

    Description Of Seismic Failure

    Mechanism

    - soft storey failure of supporting columns at discontinuous walls - shear failure due to lack of walls - column failure due to torsion

    Description Of Proposed Seismic Analysis Or Upgrade

    Recommend Seismic Analysis Simple Seismic Complex Seismic For Possible Re-Ranking Upgrade Upgrade

    Description Of

    Possible Seismic Upgrade Or Analysis

    This is a complex fix that will be quite intrusive. All discontinuous

    concrete walls to be upgraded and many new concrete shear

    walls need to be added. Diaphragm could be acceptable if

    sufficient walls are added

    Order Of Magnitude of Cost For Seismic

    Upgrade

    Structural

    $30./sq ft

    128,000 sq ft

    (Full Upgrade)

    Arch/Mech/Elec Work

    $30./sq ft

    128,000 sq ft

    (Full Upgrade)

    X

  • GLOTMAN SIMPSON JM ENGINEERING Consulting Engineers Consulting Structural Engineer

    UBC Building Seismic Risk Assessment Review May 2012

    UBC Building No.

    308-1

    UBC Building Name

    LEONARD KLINK

    BUILDING ADDITION

    Year Built

    1966

    Design Code

    Assumed 1965 National Building Code Of Canada

    Seismic Risk Level

    VERY HIGH

    Rank

    25

    Gravity Framing

    Description

    - see building 308 (part of 308 this is not a separate building)

    Lateral Resistance Framing System

    - see building 308

    Description Of

    Seismic Deficiencies

    - see building 308

    Description Of Seismic Failure

    Mechanism

    - see building 308

    Description Of Proposed Seismic Analysis Or Upgrade

    Recommend Seismic Analysis Simple Seismic Complex Seismic For Possible Re-Ranking Upgrade Upgrade

    Description Of

    Possible Seismic Upgrade Or Analysis

    Order Of Magnitude of Cost For Seismic

    Upgrade

    Structural

    Arch/Mech/Elec Work

  • GLOTMAN SIMPSON JM ENGINEERING Consulting Engineers Consulting Structural Engineer

    UBC Building Seismic Risk Assessment Review May 2012

    UBC Building No.

    312

    UBC Building Name

    MACLEOD

    BUILDING

    Year Built

    1962

    Design Code

    Assumed 1960 National Building Code Of Canada

    Seismic Risk Level

    HIGH

    Rank

    6

    Gravity Framing

    Description

    - 4 storey building consisting of reinforced concrete one way

    slabs and beams supported on columns and walls

    Lateral Resistance Framing System

    - reinforced concrete shear walls with low ductility but lots of

    redundancy

    Description Of

    Seismic Deficiencies

    - there are two offset wall issue on the 3

    rd floor

    - walls have low ductility

    Description Of Seismic Failure

    Mechanism

    - the supporting columns at the offset walls could fail

    Description Of Proposed Seismic Analysis Or Upgrade

    Recommend Seismic Analysis Simple Seismic Complex Seismic For Possible Re-Ranking Upgrade Upgrade

    Description Of

    Possible Seismic Upgrade Or Analysis

    Strengthen the supporting columns at the offset walls and the

    building could be downgraded to medium.

    Order Of Magnitude of Cost For Seismic

    Upgrade

    Structural

    $5./sq ft

    71,000 sq ft

    (Partial Upgrade Only)

    Arch/Mech/Elec Work

    $5./sq ft

    71,000 sq ft

    (Partial Upgrade Only)

    X

  • GLOTMAN SIMPSON JM ENGINEERING Consulting Engineers Consulting Structural Engineer

    UBC Building Seismic Risk Assessment Review May 2012

    UBC Building No.

    344

    UBC Building Name

    UNIVERSITY

    CENTER

    Year Built

    1958

    Design Code

    Assumed 1953 National Building Code Of Canada

    Seismic Risk Level

    VERY HIGH

    Rank

    12

    Gravity Framing

    Description

    - 3 storey building constructed with pre-cast slabs bearing on

    cast-in-place concrete beams with supporting columns and walls

    Lateral Resistance Framing System

    - a couple of short concrete walls in one direction

    Description Of

    Seismic Deficiencies

    - lack of concrete shear walls in both directions with no ductility in

    existing walls - weak diaphragm - pre-cast planks not tied and could fall off supporting beams

    Description Of Seismic Failure

    Mechanism

    - shear failure of columns and collapse of pre-cast slabs

    Description Of Proposed Seismic Analysis Or Upgrade

    Recommend Seismic Analysis Simple Seismic Complex Seismic For Possible Re-Ranking Upgrade Upgrade

    Description Of

    Possible Seismic Upgrade Or Analysis

    Add new concrete shear walls or bracing in both directions, tie

    pre-cast slabs to supporting beams, upgrade diaphragm.

    Intrusive fix.

    Order Of Magnitude of Cost For Seismic

    Upgrade

    Structural

    $40./sq ft

    38,000 sq ft

    (Full Upgrade)

    Arch/Mech/Elec Work

    $40./sq ft

    38,000 sq ft

    (Full Upgrade)

    X

  • GLOTMAN SIMPSON JM ENGINEERING Consulting Engineers Consulting Structural Engineer

    UBC Building Seismic Risk Assessment Review May 2012

    UBC Building No.

    344-1

    UBC Building Name

    UNIVERSITY

    CENTER ADDITION

    Year Built

    1967

    Design Code

    Assumed 1965 National Building Code Of Canada

    Seismic Risk Level

    Very High

    Rank

    12

    Gravity Framing

    Description

    - one storey addition consisting of reinforced concrete slabs,

    walls, columns

    Lateral Resistance Framing System

    - a few short concrete walls - the system is not well defined

    Description Of

    Seismic Deficiencies

    - lack of shear walls or bracing - stepped diaphragm which needs detailed assessment - discontinuous shear walls from above bearing on columns

    Description Of Seismic Failure

    Mechanism

    - failure of supporting columns at discontinuous shear walls - failure of diaphragm - shear failure of interior columns due to deflections

    Description Of Proposed Seismic Analysis Or Upgrade

    Recommend Seismic Analysis Simple Seismic Complex Seismic For Possible Re-Ranking Upgrade Upgrade

    Description Of

    Possible Seismic Upgrade Or Analysis

    See main University Building 344 for comments. This phase

    would be upgraded at the same time as 344 due to how tied

    together they are.

    Order Of Magnitude of Cost For Seismic

    Upgrade

    Structural

    Arch/Mech/Elec Work

    X

  • GLOTMAN SIMPSON JM ENGINEERING Consulting Engineers Consulting Structural Engineer

    UBC Building Seismic Risk Assessment Review May 2012

    UBC Building No.

    386

    UBC Building Name

    MACMILLAN

    BUILDING

    Year Built

    1965

    Design Code

    Assumed 1960 National Building Code Of Canada

    Seismic Risk Level

    VERY HIGH

    Rank

    13

    Gravity Framing

    Description

    - 3 storey multi-wing building framed with reinforced concrete

    ribbed slab supported on columns and walls

    Lateral Resistance Framing System

    - reinforced 6 and 8 concrete shear walls

    Description Of

    Seismic Deficiencies

    - buildings are irregularly shaped with many expansion /seismic joints where diaphragm/slab is not supported seismically resulting in significant lack of walls (ie wings are not tied together)

    - long diaphragms with large openings - shear failure in columns due to pounding between wings - shear failure in columns due to soft storey

    Description Of Seismic Failure

    Mechanism

    - brittle failure of columns in shear or crushing - large deflections in diaphragm and failure at the expansion

    joints

    Description Of Proposed Seismic Analysis Or Upgrade

    Recommend Seismic Analysis Simple Seismic Complex Seismic For Possible Re-Ranking Upgrade Upgrade

    Description Of

    Possible Seismic Upgrade Or Analysis

    Intrusive and complex fix including many new shear walls or

    braces. Upgrading diaphragm or adding more walls in-span.

    Connections of diaphragm to the shear walls or introduction of

    new walls.

    Order Of Magnitude of Cost For Seismic

    Upgrade

    Structural

    $40./sq ft

    150,000 sq ft

    (Full Upgrade)

    Arch/Mech/Elec Work

    $40./sq ft

    150,000 sq ft

    (Full Upgrade)

    X

  • GLOTMAN SIMPSON JM ENGINEERING Consulting Engineers Consulting Structural Engineer

    UBC Building Seismic Risk Assessment Review May 2012

    UBC Building No.

    387

    UBC Building Name

    FOREST SCIENCES

    GREENHOUSE

    Year Built

    1986

    Design Code

    Unknown

    Seismic Risk Level

    VERY HIGH

    Rank

    3

    Gravity Framing

    Description

    - aluminum tube framing with glass

    Lateral Resistance Framing System

    - none

    Description Of

    Seismic Deficiencies

    - no lateral system in place

    Description Of Seismic Failure

    Mechanism

    - shattered glass

    Description Of Proposed Seismic Analysis Or Upgrade

    Recommend Seismic Analysis Simple Seismic Complex Seismic For Possible Re-Ranking Upgrade Upgrade

    Description Of

    Possible Seismic Upgrade Or Analysis

    No further comment.

    Order Of Magnitude of Cost For Seismic

    Upgrade

    Structural

    Arch/Mech/Elec Work

  • GLOTMAN SIMPSON JM ENGINEERING Consulting Engineers Consulting Structural Engineer

    UBC Building Seismic Risk Assessment Review May 2012

    UBC Building No.

    430

    UBC Building Name

    OSBORNE CENTRE

    UNIT 1

    Year Built

    1969

    Design Code

    Assumed 1965 National Building Code Of Canada

    Seismic Risk Level

    VERY HIGH

    Rank

    16

    Gravity Framing

    Description

    - 2 storey gymnasium with pre-cast tee roof slabs spanning to

    concrete walls. The central portion has reinforced ribbed slabs and beams supported on columns and walls.

    Lateral Resistance Framing System

    - reinforced concrete shear walls

    Description Of

    Seismic Deficiencies

    - pounding between gym wings and central core (not tied) - diaphragm not tied together sufficiently - no walls in one direction (n/s) and e/w walls need to be tied to

    the roof tees - out of plane issues at gable end walls

    Description Of Seismic Failure

    Mechanism

    - failure of diaphragm and separation of roof slabs from

    supporting walls plus no capacity in n/s direction collapse possible

    Description Of Proposed Seismic Analysis Or Upgrade

    Recommend Seismic Analysis Simple Seismic Complex Seismic For Possible Re-Ranking Upgrade Upgrade

    Description Of

    Possible Seismic Upgrade Or Analysis

    Add steel x-bracing to u/s of roof slabs for diaphragm, tie roof

    slab to concrete walls, add n/s walls in the central core and at

    each end of the gymnasiums

    Order Of Magnitude of Cost For Seismic

    Upgrade

    Structural

    $30./sq ft

    40,000 sq ft

    (Full Upgrade)

    Arch/Mech/Elec Work

    $20./sq ft

    40,000 sq ft

    (Full Upgrade)

    X

  • GLOTMAN SIMPSON JM ENGINEERING Consulting Engineers Consulting Structural Engineer

    UBC Building Seismic Risk Assessment Review May 2012

    UBC Building No.

    431

    UBC Building Name

    OSBORNE CENTRE

    UNIT 2

    Year Built

    1971

    Design Code

    Assumed 1970 National Building Code Of Canada

    Seismic Risk Level

    HIGH

    Rank

    4

    Gravity Framing

    Description

    - 2 storey 3 gym building with structural steel roof supported on

    concrete columns tied with tilt-up concrete wall panels

    Lateral Resistance Framing System

    - tilt-up concrete wall panels

    Description Of

    Seismic Deficiencies

    - diaphragm tie to walls deficient - transfer of diaphragm forces to tilt-up panels weak - supporting concrete columns have out-of plane issues - open court roof not restrained

    Description Of Seismic Failure

    Mechanism

    - separation of tilt-up panels from columns/roof diaphragm

    possible - column shear issues at open court roof

    Description Of Proposed Seismic Analysis Or Upgrade

    Recommend Seismic Analysis Simple Seismic Complex Seismic For Possible Re-Ranking Upgrade Upgrade

    Description Of

    Possible Seismic Upgrade Or Analysis

    Tie tilt-up wall panels to columns and roof diaphragm, add drag

    struts to transfer diaphragm loads to supporting walls, add

    bracing in the open court framing.

    Order Of Magnitude of Cost For Seismic

    Upgrade

    Structural

    $30./sq ft

    30,000 sq ft

    (Full Upgrade)

    Arch/Mech/Elec Work

    $20./sq ft

    30,000 sq ft

    (Full Upgrade)

    X

  • GLOTMAN SIMPSON JM ENGINEERING Consulting Engineers Consulting Structural Engineer

    UBC Building Seismic Risk Assessment Review May 2012

    UBC Building No.

    447

    UBC Building Name

    CHEMISTRY A

    BLOCK

    CHEM-PHYS BLDG

    Year Built

    1986

    Design Code

    1985 National Building Code Of

    Canada

    Seismic Risk Level

    HIGH

    Rank

    9

    Gravity Framing

    Description

    - 4 storey building with reinforced concrete flat slabs supported

    on columns and walls

    Lateral Resistance Framing System

    - reinforced concrete shear walls

    Description Of

    Seismic Deficiencies

    - lack of walls in the e/w direction - existing walls have limited ductility

    Description Of Seismic Failure

    Mechanism

    - no obvious failure mechanism

    Description Of Proposed Seismic Analysis Or Upgrade

    Recommend Seismic Analysis Simple Seismic Complex Seismic For Possible Re-Ranking Upgrade Upgrade

    Description Of

    Possible Seismic Upgrade Or Analysis

    Need to add more concrete shear walls, particularly in the e/w

    direction. This is an intrusive fix based on the building layout.

    Order Of Magnitude of Cost For Seismic

    Upgrade

    Structural

    $ 15./sq ft

    100,000 sq ft

    (Full Upgrade)

    Arch/Mech/Elec Work

    $15,/sq ft

    100,000 sq ft

    (Full Upgrade)

    X

  • GLOTMAN SIMPSON JM ENGINEERING Consulting Engineers Consulting Structural Engineer

    UBC Building Seismic Risk Assessment Review May 2012

    UBC Building No.

    449

    UBC Building Name

    FOOD, NUTRITION,

    & HEALTH

    BUILDING

    Year Built

    1980

    Design Code

    1977 National Building Code Of

    Canada

    Seismic Risk Level

    HIGH

    Rank

    10

    Gravity Framing

    Description

    - 3 storey building consisting of reinforced concrete flat slabs

    supported on columns and walls

    Lateral Resistance Framing System

    - reinforced concrete shear walls

    Description Of

    Seismic Deficiencies

    - lack of concrete shear walls - plan irregularity resulting in large torsional forces

    Description Of Seismic Failure

    Mechanism

    - no obvious failure mechanism

    Description Of Proposed Seismic Analysis Or Upgrade

    Recommend Seismic Analysis Simple Seismic Complex Seismic For Possible Re-Ranking Upgrade Upgrade

    Description Of

    Possible Seismic Upgrade Or Analysis

    Recommend carrying out a detailed seismic assessment to

    determine if the existing system may be capable of being

    downgraded to medium. If not, add more concrete walls or

    bracing.

    Order Of Magnitude of Cost For Seismic

    Upgrade

    Structural

    $15./sq ft

    70,000 sq ft

    (Full Upgrade)

    Arch/Mech/Elec Work

    $15./sq ft

    70,000 sq ft

    (Full Upgrade)

    X X

  • GLOTMAN SIMPSON JM ENGINEERING Consulting Engineers Consulting Structural Engineer

    UBC Building Seismic Risk Assessment Review May 2012

    UBC Building No.

    467

    UBC Building Name

    HEALTH SCIENCES

    PARKADE

    Year Built

    1980

    Design Code

    1977 National Building Code Of

    Canada

    Seismic Risk Level

    HIGH

    Rank

    2

    Gravity Framing

    Description

    - 4 storey parkade with reinforced concrete slabs & beams

    supported on columns and walls

    Lateral Resistance Framing System

    - folded plate frame and reinforced concrete shear walls

    Description Of

    Seismic Deficiencies

    - lack of walls in the e/w direction - possible deflections in folded plate frame - possible short column issues at ramp columns

    Description Of Seismic Failure

    Mechanism

    - possible collapse due to lack of walls

    Description Of Proposed Seismic Analysis Or Upgrade

    Recommend Seismic Analysis Simple Seismic Complex Seismic For Possible Re-Ranking Upgrade Upgrade

    Description Of

    Possible Seismic Upgrade Or Analysis

    Recommend detailed seismic assessment due to non-

    conventional seismic system. May be able to reduce ranking to

    medium. Otherwise add concrete walls or bracing in both

    directions.

    Order Of Magnitude of Cost For Seismic

    Upgrade

    Structural

    $ 7./sq ft

    260,000 sq ft

    (Full Upgrade)

    Arch/Mech/Elec Work

    $2./sq ft

    260,000 sq ft

    (Full Upgrade)

    X X

  • GLOTMAN SIMPSON JM ENGINEERING Consulting Engineers Consulting Structural Engineer

    UBC Building Seismic Risk Assessment Review May 2012

    UBC Building No.

    472

    UBC Building Name

    INTERNATIONAL

    HOUSE

    Year Built

    1958

    Design Code

    Assumed 1953 National Building Code Of Canada

    Seismic Risk Level

    VERY HIGH

    Rank

    9

    Gravity Framing

    Description

    - 3 storey reinforced concrete slab building supported on columns

    and walls

    Lateral Resistance Framing System

    - reinforced concrete walls in one direction

    Description Of

    Seismic Deficiencies

    - discontinuous diaphragm - soft storey in columns - no walls in e/w direction - existing walls have no ductility

    Description Of Seismic Failure

    Mechanism

    - anticipate collapse in moderate seismic event or greater

    Description Of Proposed Seismic Analysis Or Upgrade

    Recommend Seismic Analysis Simple Seismic Complex Seismic For Possible Re-Ranking Upgrade Upgrade

    Description Of

    Possible Seismic Upgrade Or Analysis

    Add concrete walls or bracing in both directions, address short

    columns issues (remove or gap block walls), upgrade diaphragm.

    Order Of Magnitude of Cost For Seismic

    Upgrade

    Structural

    $80./sq ft

    15,000 sq ft

    (Full Upgrade)

    Arch/Mech/Elec Work

    $80./sq ft

    15,000 sq ft

    (Full Upgrade)

    X

  • GLOTMAN SIMPSON JM ENGINEERING Consulting Engineers Consulting Structural Engineer

    UBC Building Seismic Risk Assessment Review May 2012

    UBC Building No.

    515

    UBC Building Name

    Sedgewick Library

    Year Built

    1970

    Design Code

    Assumed 1965 National Building Code Of Canada

    Seismic Risk Level

    MEDIUM

    Rank

    Not applicable

    Gravity Framing

    Description

    - 2 storey underground building consisting of precast double tee

    slabs, pre-cast beams, and pre-cast columns with cast-in place foundation walls

    Lateral Resistance Framing System

    - reinforced concrete foundation walls in one direction

    Description Of

    Seismic Deficiencies

    - pre-cast elements not tied but bearing seats are large - no walls n/s in upper level

    Description Of Seismic Failure

    Mechanism

    - not applicable due to medium ranking

    Description Of Proposed Seismic Analysis Or Upgrade

    Recommend Seismic Analysis Simple Seismic Complex Seismic For Possible Re-Ranking Upgrade Upgrade

    Description Of

    Possible Seismic Upgrade Or Analysis

    Not applicable

    Order Of Magnitude of Cost For Seismic

    Upgrade

    Structural

    Arch/Mech/Elec Work

  • GLOTMAN SIMPSON JM ENGINEERING Consulting Engineers Consulting Structural Engineer

    UBC Building Seismic Risk Assessment Review May 2012

    UBC Building No.

    523-1

    UBC Building Name

    D.H. COPP

    BUILDING

    Year Built

    1961

    Design Code

    Assumed 1960 National Building Code Of Canada

    Seismic Risk Level

    VERY HIGH

    Rank

    6

    Gravity Framing

    Description

    - 3 storey plus penthouse building consisting of reinforced one

    way concrete slabs & beams supported on columns and walls

    Lateral Resistance Framing System

    - a few short walls & non-ductile moment frames

    Description Of

    Seismic Deficiencies

    - moment frames are non-ductile - very few concrete walls - short columns due to deep spandrel beams - torsion issues

    Description Of Seismic Failure

    Mechanism

    - shear failure of moment frame columns

    Description Of Proposed Seismic Analysis Or Upgrade

    Recommend Seismic Analysis Simple Seismic Complex Seismic For Possible Re-Ranking Upgrade Upgrade

    Description Of

    Possible Seismic Upgrade Or Analysis

    Upgrade would be similar to the Friedman upgrade. Add concrete

    walls in both directions. Strengthen short columns.

    Order Of Magnitude of Cost For Seismic

    Upgrade

    Structural

    Similar To Friedman Upgrade

    Arch/Mech/Elec Work

    Similar To Friedman Upgrade

    X

  • GLOTMAN SIMPSON JM ENGINEERING Consulting Engineers Consulting Structural Engineer

    UBC Building Seismic Risk Assessment Review May 2012

    UBC Building No.

    523-3

    UBC Building Name

    MEDICAL SCIENCES

    BLOCK C

    Year Built

    1965

    Design Code

    Assumed 1960 National Building Code Of Canada

    Seismic Risk Level

    VERY HIGH

    Rank

    7

    Gravity Framing

    Description

    - 3 storey plus penthouse building consisting of reinfo