Execution Plan: Fuel Duct Installation Project Sr.No. Execution Plan Responsibility Hours Day 1 Day 2 Day 3 Day 4 Day 5 Day 6 1 Getting the work permit from Client every day ETW 1 2 Area Barrication. ETW 2 3 Providing the Scaffolding material and scaffolder AAC / Client 4 Removing the instruments connections AAC / Client 5 Removal of Insulation ETW 6 6 De-torduing of lower flange and upper flange ETW 3 7 Wood arrangement for lifting the duct assembly on the ground. AAC / Client 8 Holding duct assembly using crane for proper de-bolting of flanges. ETW 6 9 Lifting of fuel duct assembly and placement on the wood on ground. ETW 6 10 Removal of central flange. ETW 6 11 Cleaning of all flanges for inspection. ETW 6 12 Inspection of all the flanges with gaskets and bolts & Overall inspection. AAC / Client 13 ETW 6 14 ETW 8 15 Allignment inspection for fuel duct. AAC / Client & ETW 5 16 Torquing of flange's nut bolts. ETW 5 17 Inspection of bolt torquing. AAC / Client 2 18 Fuel duct re-insulation. ETW 10 19 Weather shield installation. ETW 6 20 Box up and house keeping. ETW 6 crane. simultaneously.
Sheet1Execution Plan: Fuel Duct Installation
ProjectSr.No.Execution PlanResponsibilityHoursDay 1Day 2Day 3Day
4Day 5Day 6Remarks1Getting the work permit from Client every
dayETW12Area Barrication.ETW23Providing the Scaffolding material
and scaffolderAAC / ClientRequired ready on Day 14Removing the
instruments connectionsAAC / ClientRequired ready on Day 15Removal
of InsulationETW66De-torduing of lower flange and upper
flangeETW37Wood arrangement for lifting the duct assembly on the
ground.AAC / ClientRequired ready on Day 18Holding duct assembly
using crane for proper de-bolting of flanges.ETW69Lifting of fuel
duct assembly and placement on the wood on ground.ETW610Removal of
central flange.ETW611Cleaning of all flanges for
inspection.ETW612Inspection of all the flanges with gaskets and
bolts & Overall inspection.AAC / Client13After inspection
clearance, installtion of new feul duct lower spool using
crane.ETW614Fuel duct assembly erection, installation and
re-fitting both flanges simultaneously.ETW815Allignment inspection
for fuel duct.AAC / Client & ETW5Simultaneous
operation.16Torquing of flange's nut bolts.ETW517Inspection of bolt
torquing.AAC / Client218Fuel duct re-insulation.ETW1019Weather
shield installation.ETW620Box up and house keeping.ETW6