Upload
pthakur234
View
222
Download
0
Embed Size (px)
Citation preview
8/12/2019 137341447 Challenges in Connecting Renewable Energy Into the South African Grid
1/13
Wayne Kitching
8/12/2019 137341447 Challenges in Connecting Renewable Energy Into the South African Grid
2/13
Introduction SAs power generation is still dominated by Eskom
Mostly coal.
DoEsIRP 2 sets targets for introduction of renewablegeneration.
8/12/2019 137341447 Challenges in Connecting Renewable Energy Into the South African Grid
3/13
Contents Technical Challenges
Unfamiliarity of local industry with RE
Ability to evacuate the required amount of power
Grid code compliance Compliance with Eskom/ Utility standards
Health and safety
Civil/Infrastructure
Commercial Challenges PPA
Bureaucracy and inefficiencies in supply authorities
Overseas developers lack of understanding of SA
8/12/2019 137341447 Challenges in Connecting Renewable Energy Into the South African Grid
4/13
Lack of understanding of SA Difficult to quantify, but:
The large amounts of copper used in the collectornetwork and earthing would be very attractive to thieves
8/12/2019 137341447 Challenges in Connecting Renewable Energy Into the South African Grid
5/13
Commercial challenges PPA may not be to the developers advantage
Rates not nearly as high as some European feed-in
tariff rates makes it more difficult to make a profit. Reliance on Eskom and munics for building
infrastructure will probably introduce delays.
8/12/2019 137341447 Challenges in Connecting Renewable Energy Into the South African Grid
6/13
Local industry not familiar with RE Supply authorities not used to RE/embedded generators in their
network. Lack of understanding may lead to misinterpretation of grid code
may lead to supply authorities constantly moving the goal posts,
Local suppliers may not have the correct cable and the ideallengths MV cables only in rolls of 300 or 500 m (Wind).
Local LV cables may not be suitable for solar applications needcables that will withstand conditions including UV radiation.
As wind and solar farms need large amounts of cable, shortagesmay occur when several projects are being constructed
Cable manufacturers may not be able to keep up with demandwhen a number of RE projects are under construction
8/12/2019 137341447 Challenges in Connecting Renewable Energy Into the South African Grid
7/13
Grid code compliance Grid code document for RE generators has not been
finalised yet although Wind Grid code has been approved
Some signed agreements may not comply with it as supply
authorities dont.
LVRT requirements in SA Wind Grid code stricter thanmost countries codes many generators/inverters willprobably not comply.
WTG manufacturers wont supply models of their product When connecting using long lines (even short lines when
using MV) Q and V requirements not met
8/12/2019 137341447 Challenges in Connecting Renewable Energy Into the South African Grid
8/13
Ability to evacuate the required
amount of power Most RE projects are in remote areas
Electrical network inadequate for evacuating the
required amount of power will need gridstrengthening.
In some cases it may mean long lines and largetransformers, even though Eskoms TDP does take into
account some RE project.
8/12/2019 137341447 Challenges in Connecting Renewable Energy Into the South African Grid
9/13
Compliance with Eskom/ Utility
standards For Eskom connections, the grid connection must
comply with Distribution Standard for the integrationof Embedded Generators
Has specific requirements about anti-islandingprotection and other requirements for the PUC
Cant therefore copy a design from another country
without modifying, Other utilities probably dont have standards. NRS
documents not finalised yet.
8/12/2019 137341447 Challenges in Connecting Renewable Energy Into the South African Grid
10/13
Health and safety During construction, the nature of the projects are
likely to be unlike projects contractors have worked onbefore.
Increases the risk of H&S incidents
Operationally, extra sources are introduced into thegrid greater risk of electrocution of maintenance
personnel if proper isolating/earthing proceduresarent in place or arent followed.
8/12/2019 137341447 Challenges in Connecting Renewable Energy Into the South African Grid
11/13
Civil/ Infrastructure/
constructability In many RE sites, the access roads will need upgrade,
especially for wind farms May not be able to take turbine blades and mast around
corners
Overseas, digging trenches and laying cable is donewith a machine. In SA, manual labour may need to beused.
8/12/2019 137341447 Challenges in Connecting Renewable Energy Into the South African Grid
12/13
Lack of understanding of SA
situationWind/solar facilities use large amounts of copper for
earthing and the collector network. Major risk of theft.
Cultural/ language differences may pose challengeswhen working with overseas developers.
8/12/2019 137341447 Challenges in Connecting Renewable Energy Into the South African Grid
13/13
Minimising the risk Self-build the Eskom/Utility infrastructure