8
Project Sea Dragon  Core Breeding Centre and Broodstock Maturation Centre, Bynoe Harbour Draft Environmental Impact Statement  PART B ‐ ENVIRONMENTAL ASSESSMENT 13256 13 AIR QUALITY AND NOISE 13.1 TERMS OF REFERENCE ADDRESSED IN CHAPTER This chapter provides a description of potential air and noise impact from incineration and power facilities associated with the Project as required under Section 4.1 and 4.3.3 of the ToR. Two options for disposal of prawn mortalities are being considered by Seafarms i.e. disposal by incineration or transport and disposal offsite to landfill. In the event incineration is selected as the preferred option, the assessment air quality emissions from the incinerator applies to the proposed action.  Potential air and noise emissions from the power facility on site has been assessed to address Section 4.1 of the ToR.  Table 131 summarises the requirements of the ToR and references where they have been addressed in this EIS.  TABLE 131  TERMS OF REFERENCE Terms of Reference Sections 4 Risk Assessment   4.1 The EIS should be undertaken with specific emphasis on the identification, analysis and mitigation of potential impacts through a wholeofproject risk assessment. Chapter 6 and 13 4.3.3 Mitigation and monitoring   If incineration is proposed, the EIS should refer to the NT EPA Guideline Disposal of Waste by Incineration at https://ntepa.nt.gov.au/wastepollution/guidelines/guidelines, for information that should be considered. Chapter 13 Appendix 19 13.2 OVERVIEW Based on the risk assessment undertaken in Chapter 6, incineration and power station facilities have been identified as potentially impacting sensitive receptors within close proximity to the facilities. This chapter provides a summary of the assessment criteria, assessment method and predicted impacts at the nearest sensitive receiver when the Project is at full scale operation, and outlines management measures.  The nearest sensitive receptor to the incineration and power generation facilities is the accommodation facility located approximately 60 m to the southwest. The power station and accommodation locations are shown in Figure 14 and Figure 131. The incinerator will be located in close proximity to the power facility fuel storage, currently within the common facilities area, and be housed in a shed.    

13 QUALITY AND NOISE - NTEPA

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: 13 QUALITY AND NOISE - NTEPA

Project Sea Dragon  

Core Breeding Centre and Broodstock Maturation Centre, Bynoe Harbour 

Draft Environmental Impact Statement  

PART B ‐ ENVIRONMENTAL ASSESSMENT  13‐256 

13 AIR QUALITY AND NOISE 

13.1 TERMS OF REFERENCE ADDRESSED IN CHAPTER 

This chapter provides a description of potential air and noise impact from incineration and power facilities 

associated with the Project as required under Section 4.1 and 4.3.3 of the ToR. 

Two options for disposal of prawn mortalities are being considered by Seafarms i.e. disposal by incineration or 

transport and disposal offsite to landfill. In the event incineration is selected as the preferred option, the 

assessment air quality emissions from the incinerator applies to the proposed action.  

Potential air and noise emissions from the power facility on site has been assessed to address Section 4.1 of the 

ToR.  

Table 13‐1 summarises the requirements of the ToR and references where they have been addressed in this 

EIS.  

TABLE 13‐1   TERMS OF REFERENCE 

Terms of Reference  Sections 

4  Risk Assessment    

4.1  The EIS should be undertaken with specific emphasis on the 

identification, analysis and mitigation of potential impacts through a 

whole‐of‐project risk assessment. 

Chapter 6 and 13 

4.3.3  Mitigation and monitoring   

  If incineration is proposed, the EIS should refer to the NT EPA 

Guideline Disposal of Waste by Incineration at 

https://ntepa.nt.gov.au/waste‐pollution/guidelines/guidelines, for 

information that should be considered. 

Chapter 13 

Appendix 19 

13.2 OVERVIEW 

Based on the risk assessment undertaken in Chapter 6, incineration and power station facilities have been 

identified as potentially impacting sensitive receptors within close proximity to the facilities. This chapter 

provides a summary of the assessment criteria, assessment method and predicted impacts at the nearest 

sensitive receiver when the Project is at full scale operation, and outlines management measures.  

The nearest sensitive receptor to the incineration and power generation facilities is the accommodation facility 

located approximately 60 m to the southwest. The power station and accommodation locations are shown in 

Figure 1‐4 and Figure 13‐1. The incinerator will be located in close proximity to the power facility fuel storage, 

currently within the common facilities area, and be housed in a shed. 

 

   

Page 2: 13 QUALITY AND NOISE - NTEPA

Project Sea Dragon  

Core Breeding Centre and Broodstock Maturation Centre, Bynoe Harbour 

Draft Environmental Impact Statement  

PART B ‐ ENVIRONMENTAL ASSESSMENT  13‐257 

FIGURE 13‐1   LOCATION OF PROPOSED POWER FACILITY AND ACCOMMODATION FACILITY 

The National Environment Protection Council (NEPC) set uniform standards for Australian ambient air in 

February 2016. These are known as the National Environment Protection (Ambient Air Quality) Measure (Air 

NEPM), which sets non‐binding standards and ten‐year goals.  In the absence of specific Northern Territory 

regulated standards, appropriate criteria have been adopted from other jurisdictions and the most stringent 

NEPM goals and standards have been used as a benchmark. It should be noted that the NEPM is for ambient 

monitoring and not for the regulation of specific point sources.  

There is no specific guidance in the Northern Territory for the assessment and management of air quality 

impacts however guidelines exist for disposal of waste by incineration (Guideline for disposal of waste by 

incineration, NT EPA 2013). 

A conservative screening level assessment has been undertaken to determine the potential air quality impacts 

to sensitive receptors within the area as a result of incineration and power generation facilities proposed 

during operation of the project. Occupational air quality impacts on workers at these facilities has not been 

assessed. 

13.2.1 Air emissions from power facility  

The proposed power facility at the site will generate 6 MW of power A worst case scenario was assessed 

including nine CAT32 diesel generators, packaged in containers. One of the generators would remain in 

standby, and the assessment assumes that eight would be operating at any one time. The exact generator 

model and layout is subject to detailed design and commercial arrangements. 

Page 3: 13 QUALITY AND NOISE - NTEPA

Project Sea Dragon  

Core Breeding Centre and Broodstock Maturation Centre, Bynoe Harbour 

Draft Environmental Impact Statement  

PART B ‐ ENVIRONMENTAL ASSESSMENT  13‐258 

Emissions from the diesel generators have been obtained from the product specification and are summarised 

in Table 13‐2. The most significant air pollutant generated by this facility, based on the ratio of its emission rate 

to impact assessment criterion, will be nitrogen dioxide (NO2) released as oxides of nitrogen (NOx) from onsite 

diesel generation units. NOx from combustion consists largely of nitric oxide (NO) and partly NO2, and after 

emission from the stack NO is transformed to NO2 through oxidation with atmospheric ozone. This process is 

accelerated in warmer temperatures and sunlight.  

In accordance with the US EPA Guideline of Air Quality Models (2005), the US EPA emission database specifies 

a 5.7 % exhaust exit ratio of NO2 to NOx for Caterpillar reciprocating diesel generators. For a screening 

assessment, a conservative ratio of 10% has been assumed – this allows for some oxidation to occur in the 

near‐field immediately after release from an exhaust.   

Even though the immediate exhaust exit NO2 to NOx ratio is likely to be below 10%, the high heat and 

ultraviolet light levels can lead to rapid oxidation in a tropical climate and a ratio of 30% is a conservative 

assumption. A scenario has also been assessed assuming a ratio of 30%. 

TABLE 13‐2  DIESEL GENERATION NOX EMISSIONS 

Pollutant  Emissions  

(g/hp‐hr)* 

Emissions g/s 

 (1 generator) 

Emissions from 8 generators 

(g/s) 

NOx  5.8  1.73  13.84 

NO2 –  10% conversion 0.173  1.384 

NO2 –  30% conversion 0.519  4.152 

*grams per horsepower‐hour

As the air quality criteria is the 100th percentile, worst case conditions would generally occur in every direction 

from the power facility for at least one hour per year. A review of wind rose data from Dum In Mirrie (BoM site 

014277) shows that winds are predominantly from the west (wet season), and east (dry season) with very little 

wind from the south during the year.   

A screening level air quality assessment was undertaken using AUSPLUME assuming worst‐case meteorological 

conditions. Each generator is assumed to have a 7 m high, 0.2 m diameter stack, with an exit velocity of 

21.9 m/s. The exit velocity is based on exhaust flow rates given in the CATC32 specification. Eight out of the 

nine generators are assumed to be operating concurrently.  

13.2.2 Air emissions from incineration 

The proposed incinerator is a small dual chamber system. Waste is burnt in the primary chamber and hot gases 

and emissions are burnt in the secondary chamber. The incinerator will be located in close proximity to the 

power facility fuel storage and be housed in a shed.  

An incinerator with a burn rate of 50 kg/hr is proposed in order to dispose of prawn carcasses/mortalities.  At 

full scale operation of the BMC and CBC the potential incineration task is approximately 200 kg of prawn 

carcasses each week. Given the capacity of the proposed unit, this equates to the incineration of 50 kg of 

prawn mortalities for one hour four times per week. However initially, the task is much less. The incinerator is 

proposed to be located adjacent the power facility, approximately 90 m away from the accommodation facility.  

Page 4: 13 QUALITY AND NOISE - NTEPA

Project Sea Dragon  

Core Breeding Centre and Broodstock Maturation Centre, Bynoe Harbour 

Draft Environmental Impact Statement  

PART B ‐ ENVIRONMENTAL ASSESSMENT  13‐259 

The NT Guideline for Disposal of Waste by Incineration (2013) sets out emission limits for incinerators as well 

as other requirements listed below: 

Two chambers 

A minimum temperature of 850 ºC in the primary chamber 

Air supply to achieve efficient combustion of all wastes 

A minimum retention time of two seconds 

No impingement of exhaust gases onto building or sensitive sites. 

The guideline also recommends a radial buffer distance of 500 m between the incinerator and any sensitive 

land uses such as the accommodation facilities. The incinerator may achieve the air quality goals under normal 

operation, however should equipment fail, accidents occur or following other causes, then a buffer is a means 

to let these residual emissions dissipate without adversely impacting on sensitive land uses or amenity. The 

guideline does not consider the volume of waste being incinerated, nor the frequency of operation. 

Waste is burnt in the primary chamber and hot gases and emissions are burnt in the secondary chamber. The 

incinerator will be located in close proximity to the power facility fuel storage and be housed in a shed. 

The proposed incinerator with a two second retention, secondary chamber meets requirements of the NT EPA 

guideline listed above, however the proposed buffer distance of 500 m has not been achieved (refer to Figure 

13‐2). 

13.2.3 Noise from power facility 

Noise levels for each generator (CAT32, 800 eKW) were modelled assuming a sound pressure level of 85 dB(A) 

at one metre, as required in the design specification. The generators are enclosed within containers and the 

noise level is assumed to be outside of the container.  

NT EPA offers guidance for noise levels from construction sites (Noise guidelines for development sites in the 

Northern Territory (NT EPA 2014) however has no guidelines for operational noise impacts. Intrusive noise 

impacts are often assessed as acceptable where the industrial noise source does not exceed the background 

noise level by more than 5 dB(A). An example of this is the NSW Industrial Noise Policy 2000 which classifies 

intrusive noise as being ‘noise that intrudes above the background level by more than 5 decibels’. 

13.3 POTENTIAL IMPACTS 

13.3.1 Air emissions from power facility 

The worst case predicted hourly NO2 levels at a distance of 60 m from the power facility is an hourly average 

peak of 123 µg/m³, which is 50% of the impact assessment criterion. The distance of 60 m represents the 

approximate distance of the accommodation facility in the proposed concept layout (Figure 1‐4).  

Assuming the conservative 30% conversion of NOX to NO2, an additional model scenario was run. The predicted 

peak hourly NO2 at the accommodation facility is 370 µg/m³, which exceeds the criterion. A buffer of 300 m 

from the power facility is needed in order to reduce the maximum predicted impact to the criteria level of 246 

µg/m³. 

The screening air quality assessment shows that operation of the power facility has the potential to exceed the 

maximum hourly average NO2 level at the accommodation facility. 

Page 5: 13 QUALITY AND NOISE - NTEPA

Project Sea Dragon  

Core Breeding Centre and Broodstock Maturation Centre, Bynoe Harbour 

Draft Environmental Impact Statement  

PART B ‐ ENVIRONMENTAL ASSESSMENT  13‐260 

13.3.2 Air emissions from incineration  

The UK government considers that “The use of an onsite incinerator with afterburner can be considered to 

represent BAT for animal remains disposal” (BAT = Best Available Technology) (DEFRA, 2002, p.viii).  Further, 

the UK consider "shells from shellfish with soft tissue" as Category 2 ABP (Animal by Product) and allow for 

small onsite incineration (with similar operational controls to that of the NT EPA Guideline) and this is classed 

as low risk. 

Relevant allowable emission limits from incinerators in the Northern Territory are presented below in Table 

13‐3. Arsenic and mercury are included as they are possible in an industry related to marine organisms. Also 

note that the United Kingdom Department for Environment, Food & Rural Affairs (DEFRA) (2002) found that 

dioxin and furans can be generated by small carcass incinerators with afterburners – poultry farms, general 

farms and hunt kennels generating levels above recognised best practice standards (a pig farm incinerator 

operating on diesel was right on the 0.1 ng/m³ limit). 

TABLE 13‐3  SUMMARY OF RELEVANT ALLOWABLE INCINERATOR EXHAUST EMISSIONS 

Substance  Emission limit  Source 

Particles (as TSP)  50 mg/m³  NTEPA Waste Incinerator Guidelines adopting the 

Biohazard Waste Industry (BWI) of Australia and 

New Zealand Industry Code of Practice for the 

Management of Clinical and Related Wastes 

NOx (as NO2)  350 mg/ m³ 

SO2  150 mg/m³ 

HCl  100 mg/m³ 

Arsenic  0.5 mg/m³ 

Mercury  0.05 mg/m³ 

Dioxins / furans  0.1 ng/m³ 

The proposed incinerator is a small facility and will operate for a limited number of hours during the day, a few 

days a week.  With such a low mass throughput, a risk assessment approach has identified very low residual 

impact upon the environment. Residual risk associated with potential impact can be managed through the 

adoption of standard operating procedures that require the facility to be operated when favourable winds limit 

exposure to accommodation facilities. Choosing to operate the facilities when accommodation is vacant may 

also be possible. 

13.3.3 Noise emissions from power facility 

Existing background noise levels at the site would be very low, as there are no existing industrial noise sources. 

As the power facility will operate during both the day and night time, it is expected that background noise 

levels would be below 30 dB(A). In areas where the background noise level may drop below 30 dB(A), a level of 

30 dB(A) is adopted. The criteria for this site would therefore be the background plus 5 dB(A), which is 35 

dB(A). The day time noise level and criteria would potentially be higher than the night time however as the 

power facility operates with a relatively constant noise level the night time would be the most stringent criteria 

that needs to be assessed against.  

A preliminary noise model has been prepared to gain an understanding of predicted noise levels at the 

accommodation village and also how far the power facility should be from the accommodation to minimise 

potential noise impacts. The following assumptions in Table 13‐4 were made in the preliminary noise model. 

Page 6: 13 QUALITY AND NOISE - NTEPA

Project Sea Dragon  

Core Breeding Centre and Broodstock Maturation Centre, Bynoe Harbour 

Draft Environmental Impact Statement  

PART B ‐ ENVIRONMENTAL ASSESSMENT  13‐261 

TABLE 13‐4  NOISE MODEL ASSUMPTIONS 

Input/assumption  Data used in the model 

Prediction algorithm   ISO 9613‐2 ‘Acoustics – Attenuation of sound during propagation 

outdoors’ 

Modelling software  Cadna A 4.6 

Ground absorption coefficient  1 for soft ground 

Generator height  4 m 

Number of generators operating  8 (worst case scenario) 

Sound pressure level at 1 m  85 dB(A) 

Meteorological conditions  Atmospheric propagation conditions were modelled with noise 

enhancing wind conditions for noise propagation (downwind 

conditions) or equivalently a well‐developed moderate ground 

based temperature inversions 

Preliminary model results show that the predicted noise level at the accommodation facility would be 56 dBA, 

which exceeds the adopted noise criteria by more than 20 dBA.  

Refer to Figure 13‐2 for an indication of predicted noise contours generated from eight operating generators. 

13.4 MITIGATION AND MONITORING 

Preliminary air and noise assessments of the proposed power facility and incinerator have been undertaken to 

determine potential impacts on the nearest sensitive receiver. The nearest sensitive receivers to the power 

facility are personnel at the accommodation facility approximately 60 m away.  

The outcomes of the assessment recommended that the accommodation facility be moved to a location that is 

approximately 520 m from the power facility in order to achieve both noise and air quality outcomes. 

Therefore, as part of detailed design, the location of the power facility will be moved approximately 520 m 

south along the access road. In the event incinerator is the preferred method for disposing of prawn 

mortalities, the incinerator will also be moved 520 m south along the proposed access road. In the event the 

incinerator is not the preferred method for disposing of prawn mortalities, and noise attenuation to achieve 

noise criteria was applied to the power facility, the separation distance of 520 m would still be required to 

achieve air quality outcomes related to the power facility. 

Page 7: 13 QUALITY AND NOISE - NTEPA

Project Sea Dragon  

Core Breeding Centre and Broodstock Maturation Centre, Bynoe Harbour 

Draft Environmental Impact Statement  

PART B ‐ ENVIRONMENTAL ASSESSMENT  13‐262 

FIGURE 13‐2  AIR AND NOISE MODELLING RESULTS  

Page 8: 13 QUALITY AND NOISE - NTEPA

Project Sea Dragon  

Core Breeding Centre and Broodstock Maturation Centre, Bynoe Harbour 

Draft Environmental Impact Statement  

PART B ‐ ENVIRONMENTAL ASSESSMENT  13‐263 

13.4.1 Air emissions from power facility  

The screening air quality assessment shows that operation of the power facility has the potential to exceed the 

maximum hourly average NO2 level at the accommodation facility. The noise assessment for the diesel 

generator in dictates a 520 m separation distance would reduce ambient noise at the accommodation facilities 

to meet the proposed threshold.  A further screening modelling run was performed with this distance.  In this 

instance, the 1‐hour assessment criterion of 246 µg/m³ can be achieved with an NO2 to NOx ratio of 43%.  This 

ratio is well within the expected worst‐case scenario due to the tropical conditions. 

Even with an oxidation rate producing a 43% NO2 to NOx ratio, the 1‐hr NO2 criterion will not be exceeded at 

the accommodation facility 520 m away. 

By increasing the separation distance between the power facility and accommodation facility to 520 m, the 

potential impact on air quality from power facility air emissions would be a residual risk of Very Low. 

13.4.2 Air emissions from incinerator 

The following mitigation and design requirements are recommended: 

Exhaust should be three metres higher than the top of any building within 100 m of the incinerator 

Exhaust efflux velocity should be 10 m/s or more during all operational hours of waste incineration 

Once operational, a stack test be undertaken to confirm emission limits comply with requirements of the 

NT EPA Guideline for Disposal of Waste by Incineration 

Conduct a risk assessment accounting for the small number of hours operating and calculate a mass 

balance to assess the potential amount of arsenic and mercury that may be found in prawn carcasses in 

prawn carcasses that may be present in exhaust emissions. 

By increasing the separation distance between the incinerator and accommodation facility to 520 m, the 

potential impact on amenity from incineration air emissions would be a residual risk of Low. 

13.4.3 Noise emissions from power facility 

Results show that a distance of approximately 520 m would be needed for the sound level emitted from all 

eight generators operating at one time to be 35 dB(A) at the accommodation facility. For comparative purposes 

the approximate distance to achieve a noise level of 40 dBA would be 320 m and 45 dBA would be 200 m from 

the power facility.  

Therefore, by increasing the separation distance between the power facility and accommodation facility to 

520 m, the potential impact on amenity from power facility noise emissions would be a residual risk of Low.